+ All Categories
Home > Documents > 94654511-PRINCE2-2009-Glossary

94654511-PRINCE2-2009-Glossary

Date post: 05-Apr-2018
Category:
Upload: dejannikolovski
View: 216 times
Download: 0 times
Share this document with a friend

of 38

Transcript
  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    1/38

    PRINCE2: Glossary of Terms

    Term Definition

    accept

    (risk response)

    A risk response to a threat where a conscious and

    deliberate decision is taken to retain the threat,having discerned that that it is more economical to doso than to attempt a risk response action. The threat

    should continue to be monitored to ensure that itremains tolerable.

    acceptance The formal act of acknowledging that the project hasmet agreed Acceptance Criteria and thereby met the

    requirements of its stakeholders.

    acceptance criteria A prioritised list of criteria that the Project Productmust meet before the customer will accept it i.e.measurable definitions of the attributes that must

    apply to the set of products to be acceptable to keystakeholders.

    activity An activity is a process, function or task that occursover time, has recognizable results and is managed.

    They are usually defined as part of processes orplans

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    2/38

    PRINCE2: Glossary of Terms

    Term Definition

    agile methods Agile methods are (mostly) software developmentmethods that apply a project approach of using short

    time-boxed iterations where products areincrementally developed. PRINCE2 is compatiblewith agile principles.

    approval The formal confirmation that a product is completeand meets its requirements (less any concessions)

    as defined in its Product Description.

    approver The person or group (e.g. a Project Board) who isidentified as qualified and authorised to approve a

    (management or specialist) product as being

    complete and fit for purpose.

    assumption A statement that is taken as being true for thepurposes of planning, but which could change later.

    An assumption is made where some facts are not yetknown or decided and is usually reserved for mattersof such significance that if they change or turn out notto be true then there will need to be considerable re

    planning.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    3/38

    PRINCE2: Glossary of Terms

    Term Definition

    assurance All the systematic actions necessary to provideconfidence that the target (system, process,

    organisation, programme, project, outcome, benefit,capability, product output, deliverable) is appropriate.Appropriateness might be defined subjectively or

    objectively in different circumstances. The implicationis that assurance will have a level of independence

    from that which is being assured.

    See also Project Assurance and quality assurance.

    authorisation The point at which an authority is granted.

    authority The right to allocate resources and make decisions(applies to project, stage and team levels).

    avoid(risk response)

    A risk response to a threat where the threat eithercan no longer have an impact or can no longer

    happen.

    baseline Reference levels against which an entity is monitoredand controlled.

    baseline managementproduct

    A type of management product that defines aspectsof the project and once approved is subject to

    change control.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    4/38

    PRINCE2: Glossary of Terms

    Term Definition

    benefit The measurable improvement resulting from anoutcome perceived as an advantage by one or more

    stakeholders.Benefits Review Plan Defines how and when a measurement of the

    achievement of the projects benefits can be made. Ifthe project is being managed within a programme

    this information may be created and maintained atthe programme level.

    benefits tolerance The permissible deviation in the each expectedbenefit is allowed before the deviation needs to be

    escalated to the next level of management. Benefitstolerance is documented in the Business Case. See

    tolerance.

    Business Case The justification for an organisational activity [project]

    which typically contains costs, benefits, risks andtimescales and against which continuing viability istested.

    centre of excellence A corporate co-ordinating function for portfolio,programmes and projects providing standards,

    consistency of methods and processes, knowledgemanagement, assurance and training

    Change Authority A person or group to which the Project Board maydelegate responsibility for the consideration ofrequests for change or off-specifications. The

    Change Authority may be given a change budget andcan approve changes within that budget.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    5/38

    PRINCE2: Glossary of Terms

    Term Definition

    change budget The money allocated to the Change Authorityavailable to be spent on authorised requests for

    change.

    change control Change control is the procedure that ensures that allchanges that may affect the projects agreedobjectives are identified, assessed, and either

    approved, rejected or deferred.

    checkpoint A team-level, time-driven review of progress.

    Checkpoint Report A progress report of the information gathered at acheckpoint, which is given by a team to the ProjectManager and provides reporting data as defined in

    the Work Package.

    closure notification Advice from the Project Board to inform allstakeholders and the host locations that the projectresources can be disbanded and support services,

    such as space, equipment and access, demobilised.It should indicate a closure date for costs to be

    charged to the project.

    closure recommendation A recommendation prepared by the Project Managerfor the Project Board to send as a project closure

    notification when the board is satisfied that theproject can be closed.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    6/38

    PRINCE2: Glossary of Terms

    Term Definition

    CommunicationManagement Strategy

    A description of the means and frequency ofcommunication between the project and the projects

    stakeholders.concession An off-specification that is accepted by the Project

    Board without corrective action.

    configuration Item An entity that is subject to configurationmanagement. The entity may be a component of aproduct, a product or a set of products in a release

    Configuration ItemRecord

    A record that describes the status, version andvariant of each configuration item and any details ofimportant relationships between configuration items.

    configurationmanagement Technical and administrative activities concernedwith the creation, maintenance and controlled changeof configuration throughout the life of a product.

    ConfigurationManagement Strategy

    A description of how and by whom the projectsproducts will be controlled and protected.

    ConfigurationManagement System

    The set of processes, tools and databases that areused to manage configuration data. Typically, aproject will use the configuration management

    system of either the customer or supplierorganisation.

    constraints Restrictions or limitations that the project is bounded

    by. For example, a finite amount of time, money orresource.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    7/38

    PRINCE2: Glossary of Terms

    Term Definition

    contingency Something held in reserve typically to handle timeand cost variances or risks. PRINCE2 does not

    advocate the use of contingency as: estimating variances are managed by setting

    tolerances

    risks are managed through appropriate riskresponses (including the Fall Back response

    which is contingent on the risk occurring).

    corporate or programmestandards

    These are over-arching standards that the projectmust adhere to. They will influence the four projectstrategies (Communication Management Strategy,

    Configuration Management Strategy, QualityManagement Strategy and Risk Management

    Strategy) and the project controls.

    corrective action A set of actions to resolve a threat to a planstolerances or a defect in a product.

    cost tolerance The permissible deviation in a plans cost that isallowed before the deviation needs to be escalated to

    the next level of management. Cost tolerance isdocumented in the respective plan. See tolerance.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    8/38

    PRINCE2: Glossary of Terms

    Term Definition

    customer The person or group who commissioned the workand will benefit from the end results.

    customers qualityexpectations

    A statement about the quality expected from theproject product, captured in the Project Product

    Description.

    Daily Log Used to record problems/concerns that can behandled by the Project Manger informally.

    deliverable See output

    dependencies (plan) The relationship between products or activities. Forexample, product C cannot start to be developed until

    products A and B have been completed.

    Dependencies can be internal or external.

    Internal dependencies are those under the control ofthe project manager. External dependencies are

    those outside the control of the project manager. Forexample, the delivery of a product required by this

    project from another project.

    dis-benefit Outcomes perceived as negative by one or morestakeholders. Dis-benefits are actual consequencesof an activity whereas, by definition, a risk has some

    uncertainty about whether it will materialise

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    9/38

    PRINCE2: Glossary of Terms

    Term Definition

    DSDM Atern An agile project delivery framework developed andowned by the DSDM consortium. Atern uses a time-

    boxed and iterative approach to product developmentand is compatible with PRINCE2.

    embedding (PRINCE2) Embedding defines what the organisation needs todo to adopt PRINCE2 as its corporate project

    management method. It is different to tailoring whichdefines what a project needs to do to apply the

    method to a specific project environment.

    End Project Report A report given by the Project Manager to the ProjectBoard, that confirms the hand-over of all productsand provides an updated Business Case and an

    assessment of how well the project has done againstthe original Project Initiation Documentation.

    End Stage Assessment The review by the Project Board and ProjectManager of the End Stage Report to decide whether

    to approve the next Stage Plan . According to thesize and criticality of the project, the review may beformal or informal. The authority to proceed should

    be documented as a formal record.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    10/38

    PRINCE2: Glossary of Terms

    Term Definition

    End Stage Report A report given by the Project Manager to the ProjectBoard at the end of each management stage of the

    project. This provides information about the projectperformance during the stage and the project statusat stage end.

    enhance(risk response)

    A risk response to an opportunity where proactiveactions are taken to:

    Enhance the probability of the event occurring

    Enhance the impact of the event should it occur

    event-driven control This is a control that takes a place when a specificevent occurs. This could be, for example, the end of

    a stage, the completion of the Project Initiation

    Documentation or the creation of an ExceptionReport. It could also include organisational eventsthat may affect the project, such as the end of the

    financial year.

    exception A situation where it can be forecast that there will bea deviation beyond the tolerance levels agreedbetween Project Manager and Project Board (or

    between Project Board and corporate or programmemanagement).

    exception assessment This is a review by the Project Board to approve (orreject) an Exception Plan.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    11/38

    PRINCE2: Glossary of Terms

    Term Definition

    Exception Plan This is a plan that often follows an Exception Report.For a Stage Plan exception, it covers the period from

    the present to the end of the current stage. If theexception were at a project level, the Project Planwould be replaced.

    Exception Report A description of the exception situation, its impact,options, recommendation and impact of the

    recommendation. This report is prepared by theProject Manager for the Project Board.

    Executive The single individual with overall responsibility forensuring that a project meets its objectives and

    delivers the projected benefits. This individual should

    ensure that the project maintains its business focus,that it has clear authority and that the work, includingrisks, is actively managed. The Executive is the

    chairperson of the Project Board, representing thecustomer and is responsible for the Business Case.

    exploit(risk response)

    A risk response to an opportunity by seizing theopportunity to ensure that the opportunity will happen

    and that the impact will be realised.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    12/38

    PRINCE2: Glossary of Terms

    Term Definition

    fallback(risk response)

    A risk response to a threat by putting in place afallback plan for the actions that will be taken to

    reduce the impact of the threat should the risk occur

    follow-on actionrecommendations

    Recommended actions related to unfinished work,on-going issues and risks and any other activities

    needed to take a product to the next phase of its life.These are summarised and included in the EndStage Report (for phased hand-over) and End

    Project Report.

    governance

    (corporate)

    The ongoing activity of maintaining a sound system

    of internal control by which the directors and officersof an organisation ensure that effective managementsystems, including financial monitoring and controlsystems, have been put in place to protect assets,

    earning capacity and the reputation of theorganisation.

    governance(project)

    Those areas of corporate governance that arespecifically related to project activities. Effective

    governance of project management ensures that anorganisations project portfolio is aligned to the

    organisations objectives, is delivered efficiently andis sustainable.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    13/38

    PRINCE2: Glossary of Terms

    Term Definition

    handover The transfer of ownership of a set of products to therespective User(s). The set of products is known as

    a Release. There may be more than one hand-overin the life of a project (phased delivery). The finalhand-over takes place in the Closing a Project

    processes.

    Highlight Report A time-driven report from the Project Manager to theProject Board on stage progress.

    impact (of risk) The result of a particular threat or opportunity actuallyoccurring, or the anticipation of such a result.

    inherent risk The exposure arising from a specific risk before anyaction has been taken to manage it.

    initiation stage The period from when the Project Board authorisesinitiation to when they authorise the project (or decide

    not to go ahead with the project). The detailedplanning and establishment of the project

    management infrastructure is covered by theInitiating a Projectprocess

    issue Anything happening during the project which unlessresolved will result in a change to a baselined

    product, plan or objective (time, cost, quality, scope,risk and benefits).

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    14/38

    PRINCE2: Glossary of Terms

    Term Definition

    Issue Register Used to capture and maintain information on all ofthe issues that are being managed formally. The

    Issue Register should be monitored by the ProjectManager on a regular basis.

    Issue Report A report containing the description, impactassessment and recommendations for a request forchange, off-specification or a problem/concern. It is

    only created for those issues that need to be handledformally.

    Lessons Log An informal repository for lessons that apply to thisproject or future projects.

    Lessons Report A report that documents any lessons that can beusefully applied to other projects. The purpose of the

    report is to provoke action so that the positivelessons become embedded in the organisation(s)

    way of working and that the organisation(s) are ableto avoid the negative lessons on future projects.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    15/38

    PRINCE2: Glossary of Terms

    Term Definition

    logs Logs are informal repositories managed by theProject Manager that do not require any agreement

    by the Project Board on their format and composition.PRINCE2 has two logs: the Daily Log and theLessons Log.

    management product Those products that will be required as part ofmanaging the project, and establishing and

    maintaining quality (for example, Highlight Reports,End Stage Reports, etc.). The management

    products stay constant, whatever the type of project,and can be used as described, or with any relevantmodifications, for all projects. There are three types

    of management product: baselines, records andreports.

    management stage A management stage is the section of the project thatthe Project Manager is managing on behalf of theProject Board at any one time, at the end of which

    the Project Board wishes to review progress to date,the state of the Project Plan, Business Case and

    risks, and the next Stage Plan in order to decidewhether to continue with the project.

    milestone A significant event in the plans schedule such ascompletion of key Work Packages, technical stage,

    or a management stage.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    16/38

    PRINCE2: Glossary of Terms

    Term Definition

    off-specification Something that should be provided by the project, butcurrently is not (or is forecast not to be) provided and

    that the Project Manager is unable to resolve withinagreed tolerances. This might be a missing productor a product not meeting its specifications. It is one

    type of issue.

    operational andmaintenance acceptance

    A specific type of Acceptance by the person or groupwho will support the product once it is handed-over

    into the operational environment.

    outcome The result of change, normally affecting real-worldbehaviour and/or circumstances. Outcomes are

    desired when a change is conceived. Outcomes areachieved as a result of the activities undertaken to

    effect the change.

    output A specialist product that is handed over to a user(s).Note that management products are not outputs but

    created solely for the purpose of managing theproject.

    performance targets A plans goals for time, cost, quality, scope, benefitsand risk.

    plan A detailed proposal for doing or achieving somethingdetailing the what, when, how and by whom. In

    PRINCE2 there are only the following types of plan:Project Plan, Stage Plan, Team Plan, Exception Plan

    and Benefits Review Plan.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    17/38

    PRINCE2: Glossary of Terms

    Term Definition

    planned closure The PRINCE2 activity to close a project.

    planning horizon The period of time for which it is possible toaccurately plan.

    portfolio All the programmes and stand-alone projects beingundertaken by an organisation, a group of

    organisations or an organisational unit.

    premature closure The PRINCE2 activity to close a project before itsplanned closure. The Project Manager must ensurethat work in progress is not simply abandoned, butthat the project salvages any value created to dateand checks that any gaps left by the cancellation of

    the project are raised to corporate/programmemanagement.

    prerequisites (plan) Any fundamental aspects that must be in place andremain in place for the plan to succeed.

    PRINCE2 A method that supports some selected aspects ofproject management. The acronym stands for

    Projects IN a Controlled Environment.

    PRINCE2 principle The guiding obligations for good project managementpractice that are the basis of a project being

    managed using PRINCE2.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    18/38

    PRINCE2: Glossary of Terms

    Term Definition

    PRINCE2 project A project that applies the PRINCE2 principles.

    probability This is the evaluated likelihood of a particular threator opportunity actually happening, including a

    consideration of the frequency with which this mayarise.

    problem/concern A type of issue (other than a request for change oroff-specification ) that the Project Manager needs to

    resolve or escalate

    procedure A specified series of actions for a particular aspect ofproject management established specifically for theproject, for example a risk management procedure.

    process A structured set of activities designed to accomplisha specific objective. A process takes one or moredefined inputs and turns them into defined outputs.

    producer The person or group responsible for developing aproduct.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    19/38

    PRINCE2: Glossary of Terms

    Term Definition

    product An input or output, whether tangible or intangible,that can be described in advance, created and

    tested. PRINCE2 has two types of productsmanagement products and specialist products.

    product breakdownstructure

    A hierarchy of all the products to be produced duringa plan.

    product checklist A list of the major products of a plan, plus key datesin their delivery.

    Product Description A description of a products purpose, composition,derivation and quality criteria. It is produced at

    planning time, as soon as possible after the need for

    the product is identified.

    product flow diagram A diagram showing the sequence of production andinterdependencies of the products listed in a Product

    Breakdown Structure.

    product status account A report on the status of products. The requiredproducts can be specified by identifier or the part of

    the project in which they were developed.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    20/38

    PRINCE2: Glossary of Terms

    Term Definition

    product-based planning A technique leading to a comprehensive plan basedon creation and delivery of required outputs. The

    technique considers prerequisite, products, qualityrequirements and the dependencies betweenproducts.

    programme A temporary flexible organisation structure created toco-ordinate, direct and oversee the implementation of

    a set of related projects and activities in order todeliver outcomes and benefits related to the

    organisations strategic objectives. A programme islikely to have a life that spans several years.

    project A temporary organisation that is created for thepurpose of delivering one or more business products

    according to an agreed Business Case.

    project approach A description of the way in which the work of theproject is to be approached. For example: Are we

    building a product from scratch or buying in a productthat already exists?

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    21/38

    PRINCE2: Glossary of Terms

    Term Definition

    Project Assurance The Project Boards responsibilities to assure itselfthat the project is being conducted correctly. The

    Project Board members each have a specific area offocus for Project Assurance, namely BusinessAssurance for the Executive, User Assurance for theSenior User(s) and Supplier Assurance for the Senior

    Supplier(s).

    project authorisationnotification

    Advice from the Project Board to inform allstakeholders and the host locations that the projecthas been authorised and to request any necessary

    logistical support (e.g. communication facilities,equipment and any project support) sufficient for the

    duration of the project.

    Project Brief Statement that describes the purpose, cost, time andperformance requirements and constraints for a

    project. It is created pre-project during the StartingUp a Project process and is used during the Initiating

    a Project process to create the Project InitiationDocumentation and its components. It is supersededby the Project Initiation Documentation and not

    maintained.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    22/38

    PRINCE2: Glossary of Terms

    Term Definition

    Project InitiationDocumentation

    A logical set of documents which brings together thekey information needed to start the project on a

    sound basis and to convey that information to allconcerned with the project.

    project initiationnotification

    Advice from the Project Board to inform allstakeholders and the host locations that the project isbeing initiated and to request any necessary logisticalsupport (e.g. communication facilities, equipment andany project support) sufficient for the initiation stage.

    project lifecycle The period from the start-up of a project to theacceptance of the Project Product.

    project management The planning, delegating, monitoring and control ofall aspects of the project, and the motivation of thoseinvolved, to achieve the project objectives within theexpected performance targets for time, cost, quality,

    scope, benefits and risks..

    project managementteam

    Covers the entire management structure of ProjectBoard, Project Manager, plus any Team Manager,

    Project Assurance and Project Support roles.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    23/38

    PRINCE2: Glossary of Terms

    Term Definition

    project managementteam structure

    An organisation chart showing the people assignedto the project management team roles to be used

    and their delegation and reporting relationship.

    Project Manager The person given the authority and responsibility tomanage the project on a day-to-day basis to deliverthe required products within the constraints agreed

    with the Project Board.

    project mandate An external product generated by the authoritycommissioning the project that forms the trigger for

    Starting up a Project.

    project office A temporary office set up to support the delivery of aspecific change initiative being delivered as a project.If used, the Project Office undertakes theresponsibility of the Project Support role.

    Project Plan A high-level plan showing the major products of theproject, when they will be delivered and at what cost.

    An initial Project Plan is presented as part of theProject Initiation Documentation. This is revised as

    information on actual progress appears. It is a majorcontrol document for the Project Board to measure

    actual progress against expectations.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    24/38

    PRINCE2: Glossary of Terms

    Term Definition

    project product What the project must deliver in order to gainacceptance.

    Project ProductDescription

    A special type of Product Description used to gainagreement from the user on the projects scope and

    requirements, to define the customers qualityexpectation, and to define the acceptance criteria for

    the project.

    project atart-up totification Advice to the host locations that the project is aboutto start and requesting any required Project Support

    services.

    Project Support An administrative role in the project managementteam. Project Support can be in the form of adviceand help with project management tools, guidance,

    administrative services such as filing, and thecollection of actual data.

    proximity (of risk) The time factor of risk, i.e. the occurrence of risks willbe more likely at particular times, and the severity oftheir impact will vary depending on when they occur.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    25/38

    PRINCE2: Glossary of Terms

    Term Definition

    quality The totality of features and inherent or assignedcharacteristics of a product, person, process, service

    and/or system that bear on its ability to show that itmeets expectations or satisfies stated needs,requirements or specification.

    quality assurance Independent check that products will be fit forpurpose or meet requirements.

    quality control The process of monitoring specific project results todetermine if they comply with relevant standards andidentifying ways to eliminate causes of unsatisfactory

    performance.

    quality criteria A description of the quality specification that theproduct must meet and the quality measurementsthat will be applied by those inspecting the finished

    product.

    quality inspection A systematic, structured assessment of a productcarried out by two or more carefully selected people

    (the review team), in a planned, documented andorganised fashion.

    quality management The coordinated activities to direct and control anorganisation with regard to quality.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    26/38

    PRINCE2: Glossary of Terms

    Term Definition

    Quality ManagementStrategy

    Defines the quality techniques and standards to beapplied, and the various responsibilities for achieving

    the required quality levels, during the project.

    quality managementsystem

    The complete set of quality standards, proceduresand responsibilities for a site or organisation. In theproject context, sites and organisations should be

    interpreted as the permanent or semi-permanentorganisation(s) sponsoring the project work, i.e. theyare external to the projects temporary organisation.

    A programme, for instance, can be regarded as asemi-permanent organisation that sponsors projects

    and may have a documented quality managementsystem.

    quality records Evidence kept to demonstrate that the requiredquality assurance and quality control activities have

    been carried out.

    Quality Register Contains summary details of all planned andcompleted quality activities. The Quality Register is

    used by the Project Manager and Project Assuranceas part of reviewing progress.

    quality review See quality inspection

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    27/38

    PRINCE2: Glossary of Terms

    Term Definition

    quality review technique A quality inspection technique with defined roles anda specific structure. It is designed to asses whether a

    product which takes the form of a document (orsimilar, e.g. a presentation) is complete, adheres tostandards and meets the Quality Criteria agreed for itin the relevant Product Description. The participants

    are drawn from those with the necessarycompetence to evaluate its fitness for purpose.

    quality tolerance Quality tolerances for a product should be identifiedfor each quality criteria by defining an acceptable

    range of values. Quality tolerance is documented inthe Project Product Description (for the project levelquality tolerance) and in the Product Description for

    each product to be delivered.

    records Dynamic management products that maintaininformation regarding project progress.

    reduce(risk response)

    A response to a risk where proactive actions takento:

    Reduce the probability of the event occurring, byperforming some form of control

    Reduce the impact of the event should it occur

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    28/38

    PRINCE2: Glossary of Terms

    Term Definition

    registers Formal repositories managed by the Project Managerthat require agreement by the Project Board on their

    format, composition and use.PRINCE2 has three registers: Issue Register, Risk

    Register, Quality Register

    reject(risk response)

    A response to a risk (opportunity) where a consciousand deliberate decision is taken not to exploit or

    enhance the opportunity, having discerned that that itis more economical to do so than to attempt a risk

    response action. The opportunity should continue tobe monitored.

    release The set of products in a hand-over. The contents ofa release are managed tested and deployed as a

    single entity. See Hand-over.

    reports Management products providing a snapshot of thestatus of certain aspects of the project

    request for change A proposal for a change to a baseline. It is a type ofissue.

    residual risk The risk remaining after the risk response has beenapplied.

    responsible authority The person or group commissioning the project(typically corporate or programme management) that

    has the authority to commit resources and funds onbehalf of the commissioning organisation.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    29/38

    PRINCE2: Glossary of Terms

    Term Definition

    reviewer A person or group independent of the producer whoassesses whether a product meets its requirements

    as defined in its Product Description.risk An uncertain event or set of events that, should it

    occur, will have an effect on the achievement ofobjectives. A risk is measured by a combination ofthe probability of a perceived threat or opportunity

    occurring and the magnitude of its impact onobjectives.

    risk actionee Some actions may not be within the remit of the riskowner to control explicitly; in that situation thereshould be a nominated owner of the action to

    address the risk. He or she will need to keep the riskowner apprised of the situation.

    risk appetite An organizations unique attitude towards risk takingthat in turn dictates the amount of risk that it

    considers is acceptable.

    risk estimation The estimation of probability and impact of anindividual risk, taking into account predetermined

    standards, target risk levels, interdependencies andother relevant factors

    risk evaluation The process of understanding the net effect of theidentified threats and opportunities on an activity

    when aggregated together.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    30/38

    PRINCE2: Glossary of Terms

    Term Definition

    risk management The systematic application of principles, approachand processes to the tasks of identifying and

    assessing risks, and then planning and implementingrisk responses.

    Risk ManagementStrategy

    Describes the goals of applying risk management, adescription of the procedure that will be adopted, theroles and responsibilities, risk tolerances, the timing

    of risk management interventions, the tools andtechniques that will be used and the reporting

    requirements.

    risk owner A named individual who is responsible for themanagement, monitoring and control of all aspects of

    a particular risk assigned to them, including the

    implementation of the selected responses to addressthe threats or to maximise the opportunities.

    risk profile Describes the types of risk that are faced by anorganisation and its exposure to those risks.

    Risk Register A record of identified risks relating to an initiative,including their status and history.

    risk response Actions that may be taken to bring the situation to alevel where the exposure to risk is acceptable to the

    organisation. These responses fall into one of a

    number of risk response categories.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    31/38

    PRINCE2: Glossary of Terms

    Term Definition

    risk response category For threats, the individual risk response category canbe avoid, reduce, transfer, accept or share.

    For opportunities, the individual risk responsecategory can be exploit, enhance, reject or share.

    risk tolerance The threshold levels of risk exposure which, whenexceeded, will trigger an Exception Report to bringthe situation to the attention of the Project Board.Risk

    tolerances could include limits on the plansaggregated threats (e.g. aggregated risks costs to

    remain less than 10% of the plans budget) or limitson any individual threat (e.g. any threat to operational

    service)Risk Tolerance is documented in the Risk

    Management Strategy.

    risk tolerance line A line drawn on the summary risk profile. Risks thatappear above this line cannot be accepted (lived

    with) without referring them to a higher authority. Fora project, the project manager would refer these risks

    to the Project Board.

    role description Describes the set of responsibilities specific to a role.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    32/38

    PRINCE2: Glossary of Terms

    Term Definition

    schedule Graphical representation of a plan (for example in aGantt chart), typically describing a sequence of tasks,

    together with resource allocations, which collectivelydeliver the plan. In PRINCE2 project activities shouldonly be documented in the schedules associated with

    a Project Plan, Stage Plan or Team Plan. Actionsthat are allocated from day-to-day management maybe documented in the relevant project log (i.e. RiskRegister, Daily Log, Issue Register, Quality Register)

    if they do not require significant activity.

    scope The scope of a plan is the sum total of its products

    and the extent of their requirements. It is describedby the product breakdown structure for the plan and

    its associated Product Descriptions.

    scope tolerance The permissible deviation in a plans scope that isallowed before the deviation needs to be escalated to

    the next level of management. Scope tolerance isdocumented in the respective plan in the form of a

    note or reference to the Product BreakdownStructure for that plan. See tolerance.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    33/38

    PRINCE2: Glossary of Terms

    Term Definition

    Senior ResponsibleOwner (SRO)

    The Senior Responsible Owner (SRO) is a UKGovernment term for the individual responsible for

    ensuring that a project or programme of changemeets its objectives and delivers the projectedbenefits. They should be the owner of the overallbusiness change that is being supported by theproject. The SRO should ensure that the change

    maintains its business focus, has clear authority andthat the context, including risks, is actively managed.

    This individual must be senior and must takepersonal responsibility for successfully delivery of the

    project. They should be recognised as the ownerthroughout the organisation.

    The SRO appoints the projects Executive (or insome cases may elect to be the Executive).

    Senior Supplier The Project Board role that provides knowledge andexperience of the main discipline(s) involved in the

    production of the projects deliverable(s). The SeniorSupplier represents the supplier interests within the

    project and provides supplier resources.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    34/38

    PRINCE2: Glossary of Terms

    Term Definition

    Senior User The Project Board role accountable for ensuring thatuser needs are specified correctly and that the

    solution meets those needs.

    specialist product Specialist products are those products whosedevelopment is the subject of the plan. The specialist

    products are specific to an individual project (forexample, an advertising campaign, a car park

    ticketing system, foundations for a building, a newbusiness processes, etc. (also known as a

    deliverable or output)

    sponsor The main driving force behind a programme orproject. PRINCE2 does not define a role for thesponsor but the sponsor is most likely to be the

    Executive on the Project Board or the person whohas appointed the Executive.

    stage See management stage or technical stage.

    Stage Plan A detailed plan used as the basis for projectmanagement control throughout a stage.

    stakeholder Any individual, group or organisation that can affect,be affected by, or perceive itself to be affected by, an

    initiative [programme, project, activity, risk]

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    35/38

    PRINCE2: Glossary of Terms

    Term Definition

    start up The pre-project activities undertaken by theExecutive and the Project Manager to produce the

    outline Business, Project Brief and initiation StagePlan.

    strategy An approach or line to take, designed to achieve along-term aim. Strategies can exist at different levels at the corporate, programme and project level. At

    the project level PRINCE2 defines four strategies:Communication Management Strategy, ConfigurationManagement Strategy, Quality Management Strategy

    and Risk Management Strategy.

    supplier The person, group or groups responsible for thesupply of the project's specialist products.

    Tailoring The appropriate use of PRINCE2 on any givenproject, ensuring that there is the correct amount of

    planning, control, governance and use of theprocesses and themes, whereas the adoption ofPRINCE2 across an organisation is known as

    embedding.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    36/38

    PRINCE2: Glossary of Terms

    Term Definition

    Team Manager The person responsible for the production of thoseproducts allocated by the Project Manager as defined

    in a Work Package to an appropriate quality, in atimescale and at a cost acceptable to the ProjectBoard. The Team Manager role reports to and takes

    direction from the Project Manager. If a TeamManager is not assigned then the Project Manager

    undertakes the responsibilities of the Team Managerrole.

    Team Plan An optional level of plan used as the basis for teammanagement control when executing Work

    Packages.

    technical stage A method of grouping work together by the set oftechniques used or the products created. This results

    in stages covering elements such as design, buildand implementation. Such stages are technical

    stages and are a separate concept frommanagement stages.

    theme An aspect of project management that needs to becontinually addressed, and that requires specific

    treatment for the PRINCE2 processes to be effective.

    time tolerance The permissible deviation in a plans time that isallowed before the deviation needs to be escalated to

    the next level of management. Time tolerance isdocumented in the respective plan. See tolerance.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    37/38

    PRINCE2: Glossary of Terms

    Term Definition

    time-driven tontrol Controls that are periodic to enable the next higherauthority to monitor progress, e.g. a control that takes

    place every 2 weeks. PRINCE2 offers two key Time-driven progress reports: Checkpoint Report andHighlight Report.

    tolerance The permissible deviation above and below a planstarget for time and cost without escalating the

    deviation to the next level of management. Theremay also be tolerance levels for quality, scope,

    benefit and risk. Tolerance is applied at project, stageand team levels.

    transfer(risk response)

    A response to a threat where a third party takes onresponsibility for some of the financial impact of thethreat. (For example through insurance or by means

    of appropriate clauses in a contract.)

    trigger An event or decision that triggers a PRINCE2process.

    user acceptance A specific type of acceptance by the person or groupwho will use the product once it is handed-over into

    the operational environment.

    user(s) The person or group who will use one or more of the

    projects products.

  • 7/31/2019 94654511-PRINCE2-2009-Glossary

    38/38

    PRINCE2: Glossary of Terms

    Term Definition

    variant A means of distinguishing between derivatives ofbaselined products. For example, an operations

    manual may have an English variant and a Spanishvariant.

    version A specific baseline of a product. Versions typicallyuse naming conventions that enables the sequenceor date of the baseline to be identified. For exampleProject Plan version 2 is the baseline after Project

    Plan version 1.

    waterfall methods A waterfall method describes a developmentapproach that is linear and sequential with distinct

    goals for each phase of development. Once a phase

    of development is completed, the developmentproceeds to the next phase and earlier phases arenot revisited (hence the analogy that water flowing

    down a mountain cannot go back)

    Work Package The set of information relevant to the creation of oneor more products. It will contain a description of the

    work, the Product Description(s), details of anyconstraints on production, and confirmation of theagreement between the Project Manager and theperson or Team Manager who is to implement the

    Work Package that the work can be done within theconstraints.


Recommended