+ All Categories
Home > Documents > A Practile Training Report (2)

A Practile Training Report (2)

Date post: 07-Apr-2018
Category:
Upload: edition123
View: 224 times
Download: 0 times
Share this document with a friend

of 61

Transcript
  • 8/4/2019 A Practile Training Report (2)

    1/61

  • 8/4/2019 A Practile Training Report (2)

    2/61

    A PRACTICAL TRANING REPORT

    ON

    NTPC POWER STATION, BADARPUR

    (III YEAR)

    SUBMITTED IN PRACTICAL FULFILLMENT OF THE REQUIREMENT

    BACHELORS OF TECHNOLOGY. FOR THE AWARD OF

    IN

    MECHANICAL ENGINEERING

    PROJECT BY

    NISHU GUPTA (09-ME-1238)

    DEPARTMENT OF MECHANICAL

    Echelon Institute of TechnologyKabulpur,

    Jasana-Manjawali Road,

    12 k.m. from badkal chowk,

    Faridabad - 121101

    Haryana

    JULY 2011

  • 8/4/2019 A Practile Training Report (2)

    3/61

    ACKNOWLEDGEMENT

    With profound respect and gratitude, I take the opportunity to convey my thanks to

    complete the training here.

    I do extend my heartfelt thanks to Ms. Rachna singh Bahel for providing me this

    opportunity to be a part of this esteemed organization.

    I am extremely grateful to all the technical staff of BTPS / NTPC for their co-operation and

    guidance that has helped me a lot during the course of training. I have learnt a lot working under

    them and I will always be indebted of them for this value addition in me.

    I would also like to thank the training incharge of Echelon Institute of Technology,

    Faridabad and all the faculty members of Mechanical Engineering Department for their effort of

    constant co- operation, which have been a significant factor in the accomplishment of my

    industrial training.

    NISHU GUPTA

    EIT, FARIDABAD

  • 8/4/2019 A Practile Training Report (2)

    4/61

    CERTIFICATE

    This is to certify that student of Batch Mechanical Branch IIird Year; EchelonInstitute of Technology Faridabad has successfully completed his industrial training at Badarpur

    Thermal power station New Delhi for 27days from 4th July to 30th July 2011.

    He has completed the whole training as per the training report submitted by him.

    Training Incharge

    BTPS/NTPC

    NEW DELHI

  • 8/4/2019 A Practile Training Report (2)

    5/61

    Training at BTPS

    I was appointed to do eight-week training at this esteemed organization from 18th June

    to 11th august 2007. In these eight weeks I was assigned to visit various division of the

    plant which were

    1. Boiler Maintenance Department(BMD I/II/III)2. Plant Auxiliary Maintenance(PAM)3. Turbine Maintenance Department(TMD)

    This 27 days training was a very educational adventure for me. It was really amazing to

    see the plant by your self and learn how electricity, which is one of our daily

    requirements of life, is produced.

    This report has been made by self-experience at BTPS. The material in this report has

    been gathered from my textbooks, senior student report, and trainer manual provided

    by training department. The specification & principles are at learned by me from the

    employee of each division of BTPS.

    NISHU GUPTA

  • 8/4/2019 A Practile Training Report (2)

    6/61

    INDEX

    1. Introduction NTPC

    Badarpur Thermal Power Station

    2. Basic steps of Electricity generation COAL TO STEAM

    STEAM TO MECHANICAL POWER

    COAL CYCLE

    ELECTRICITY FROM COAL

    3. RANKINE CYCLE PROCESS OF RANKINE CYCLE

    RANKINE CYCLE WITH REHEAT

    4. Boiler Maintenance Department

    BMD I

    BMD II

    BMD III

    5. Plant Auxiliary Maintenance

    6. Turbine Maintenance Department

  • 8/4/2019 A Practile Training Report (2)

    7/61

    ABOUT NTPC

    NTPC Limited is the largest thermal power generating company of India. A public sector company,it was incorporated in the year 1975 to accelerate power development in the country as a wholly

    owned company of the Government of India. At present, Government of India holds 89.5% of the

    total equity shares of the company and FIIs, Domestic Banks, Public and others hold the balance

    10.5%. Within a span of 31 years, NTPC has emerged as a truly national power company, with

    power generating facilities in all the major regions of the country.

    The total installed capacity of the company is 31134 MW (including JVs) with 15 coal based and 7

    gas based stations, located across the country. In addition under JVs, 3 stations are coal based &

    another station uses naphtha/LNG as fuel. By 2017, the power generation portfolio is expected to

    have a diversified fuel mix with coal based capacity of around 53000 MW, 10000MW through gas,9000 MW through Hydro generation, about 2000 MW from nuclear sources and around 1000 MW

    from Renewable Energy Sources (RES). NTPC has adopted a multi-pronged growth strategy which

    includes capacity addition through green field projects, expansion of existing stations, joint

    ventures, subsidiaries and takeover of stations.

    NTPC has set new benchmarks for the power industry both in the area of power plant construction

    andoperations. Its providing power at the cheapest average tariff in the country..

    NTPC is committed to theenvironment, generating power at minimal environmental cost and

    preserving the ecology in the vicinity of the plants. NTPC has undertaken massive a forestation in

    the vicinity of its plants. Plantations have increased forest area and reduced barren land. Themassive a forestation by NTPC in and around its Ramagundam Power station (2600 MW) have

    contributed reducing the temperature in the areas by about 3c. NTPC has also taken proactive

    steps forash utilization. In 1991, it set up Ash Utilization Division

    A "Centre for Power Efficiency and Environment Protection(CENPEEP)"has been established in

    NTPC with the assistance of United States Agency for International Development. (USAID).

    Cenpeep is efficiency oriented, eco-friendly and eco-nurturing initiative - a symbol of NTPC's

    concern towards environmental protection and continued commitment to sustainable power

    development in India.

    As a responsible corporate citizen, NTPC is making constant efforts to improve the socio-economic

    status of the people affected by its projects. Through itsRehabilitation and Resettlement

    programmes, the company endeavours to improve the overall socio economic status Project

    Affected Persons.

    NTPC was among the first Public Sector Enterprises to enter into a Memorandum of

    Understanding (MOU) with the Government in 1987-88. NTPC has been placed under the

    'Excellent category' (the best category) every year since the MOU system became operative.

    http://www.ntpc.co.in/operations/operations.shtmlhttp://www.ntpc.co.in/operations/operations.shtmlhttp://www.ntpc.co.in/operations/operations.shtmlhttp://www.ntpc.co.in/infocus/environment.shtmlhttp://www.ntpc.co.in/infocus/environment.shtmlhttp://www.ntpc.co.in/infocus/environment.shtmlhttp://www.ntpc.co.in/infocus/ashutilisation.shtmlhttp://www.ntpc.co.in/infocus/ashutilisation.shtmlhttp://www.ntpc.co.in/infocus/ashutilisation.shtmlhttp://www.ntpc.co.in/otherlinks/cenpeep.shtmlhttp://www.ntpc.co.in/otherlinks/cenpeep.shtmlhttp://www.ntpc.co.in/otherlinks/cenpeep.shtmlhttp://www.ntpc.co.in/infocus/socialcomm.shtmlhttp://www.ntpc.co.in/infocus/socialcomm.shtmlhttp://www.ntpc.co.in/infocus/socialcomm.shtmlhttp://www.ntpc.co.in/infocus/socialcomm.shtmlhttp://www.ntpc.co.in/otherlinks/cenpeep.shtmlhttp://www.ntpc.co.in/infocus/ashutilisation.shtmlhttp://www.ntpc.co.in/infocus/environment.shtmlhttp://www.ntpc.co.in/operations/operations.shtml
  • 8/4/2019 A Practile Training Report (2)

    8/61

    Harmony between man and environment is the essence of healthy life and growth. Therefore,

    maintenance of ecological balance and a pristine environment has been of utmost importance to

    NTPC. It has been taking various measures discussed below for mitigation of environment

    pollution due to power generation.

    Environment Policy & Environment Management SystemDriven by its commitment for sustainable growth of power, NTPC has evolved a well defined

    environment management policy and sound environment practices for minimizing environmental

    impact arising out of setting up of power plants and preserving the natural ecology.

    National Environment Policy:

    At the national level, the Ministry of Environment and Forests had prepared a draft Environment

    Policy (NEP) and the Ministry of Power along with NTPC actively participated in the deliberations

    of the draft NEP. The NEP 2006 has since been approved by the Union Cabinet in May 2006.

    NTPC Environment Policy:

    As early as in November 1995, NTPC brought out a comprehensive document entitled "NTPC

    Environment Policy and Environment Management System". Amongst the guiding principles

    adopted in the document are company's proactive approach to environment, optimum utilization

    of equipment, adoption of latest technologies and continual environment improvement. The

    policy also envisages efficient utilization of resources, thereby minimizing waste, maximizing ash

    utilization and providing green belt all around the plant for maintaining ecological balance.

    Environment Management, Occupational Health and Safety Systems:

    NTPC has actively gone for adoption of best international practices on environment, occupational

    health and safety areas. The organization has pursued the Environmental Management System(EMS) ISO 14001 and the Occupational Health and Safety Assessment System OHSAS 18001 at its

  • 8/4/2019 A Practile Training Report (2)

    9/61

    different establishments. As a result of pursuing these practices, all NTPC power stations have

    been certified for ISO 14001 & OHSAS 18001 by reputed national and international Certifying

    Agencies.

    Pollution Control systems:

    While deciding the appropriate technology for its projects, NTPC integrates many environmental

    provisions into the plant design. In order to ensure that NTPC comply with all the stipulated

    environment norms, various state-of-the-art pollution control systems / devices as discussed

    below have been installed to control air and water pollution.

    JOURNEY OF NTPC

    NTPC was set up in 1975 with 100% ownership by the Government of India. In the last 30

    years, NTPC has grown into the largest power utility in India

    .

    In 1997, Government of India granted NTPC status of Navratnabeing one of the nine

    Jewels of India, enhancing the powers to the Board of Directors

    NTPC became a listed company with majority government ownership of 89.5%.

    NTPC became third largest market capitalization of listed by companies.

    The company rechristened as NTPC Limited in line with its changing business portfolio

    And transforms itself from a thermal power utility to an integrated power utility.

    National Thermal Power Corporation is the largest power generation company in India.

    Forbes Global 2000 for 2008 ranked it 411th in the world.

    National Thermal Power Corporation is the largest power generation company in India.

    Forbes Global 2000 for 2008 ranked it317th in the world.

    National Thermal Power Corporation has also set up to a plan to achieve a target of

    50,000MW generation capacity.

    1975

    1997

    2004

    2005

    2008

    2009

    2012

  • 8/4/2019 A Practile Training Report (2)

    10/61

    .

    National Thermal Power Corporation has embarked on plans to became a

    75,000MW Company by 2017.

    ABOUT BTPS

    Badarpur thermal power station started working in 1973 with a single 95 mw unit. There were 2more units (95 MW each) installed in next 2 consecutive years. Now it has total five units with

    total capacity of 720 MW. Ownership of BTPS was transferred to NTPC with effect from 01.06.2006

    through GOIs Gazette Notification.

    Given below are the details of unit with the year they are installed.

    Address: Badarpur, New Delhi -110044

    Telephone: (STD-011)-26949523

    Fax: 26949532

    Installed Capacity 720 MW

    Derated capacity 705 MW

    Location New Delhi

    Coal source Jharia coal fields

    Water source Agra canal

    Beneficary states Delhi

    Unit sizes 3x95 MW

    2X210 MWUnits Commissioned Unit I- 95 MW - July 1973

    Unit II- 95 MW August 1974

    Unit III- 95 MW March 1975

    Unit IV - 210 MW December 1978

    Unit V - 210 MW - December 1981

    Transfer of BTPS to NTPC Ownership of BTPS was transferred to

    NTPC with effect from 01.06.2006

    through GOIs Gazette Notification

    2017

  • 8/4/2019 A Practile Training Report (2)

    11/61

    BASIC STEPS OF ELECTRICITY GENERATION

    The basic steps in the generation of electricity from coal involves following steps:

    Coal to steamSteam to mechanical power

    Mechanical power to electrical power

    COAL TO ELECTRICITY: BASICS

    \

  • 8/4/2019 A Practile Training Report (2)

    12/61

    Coal to Steam

    Coal from the coal wagons is unloaded in the coal handling plant. This Coal is

    transported up to the raw coal bunkers with the help of belt conveyors. Coal is

    transported to Bowl mills by Coal Feeders. The coal is pulverized in the Bowl Mill,where it is ground to powder form. The mill consists of a round metallic table on which

    coal particles fall. This table is rotated with the help of a motor. There are three large

    steel rollers, which are spaced 120 apart.

    When there is no coal, these rollers do not rotate but when the coal is fed to the table it

    packs up between roller and the table and ths forces the rollers to rotate. Coal is

    crushed by the crushing action between the rollers and the rotating table. This crushed

    coal is taken away to the furnace through coal pipes with the help of hot and cold air

    mixture from P.A. Fan.P.A. Fan takes atmospheric air, a part of which is sent to Air-

    Preheaters for heating while a part goes directly to the mill for temperature control.

    Atmospheric air from F.D. Fan is heated in the air heaters and sent to the furnace as

    combustion air. Water from the boiler feed pump passes through economizer and

    reaches the boiler drum. Water from the drum passes through down comers and goes to

    the bottom ring header. Water from the bottom ring header is divided to all the four

    sides of the furnace. Due to heat and density difference, the water rises up in the water

    wall tubes. Water is partly converted to steam as it rises up in the furnace. This steam

    and water mixture is again taken to the boiler drum where the steam is separated from

    water.

    Water follows the same path while the steam is sent to superheaters for superheating.

    The superheaters are located inside the furnace and the steam is superheated (540C)and finally it goes to the turbine. Flue gases from the furnace are extracted by induced

    draft fan, which maintains balance draft in the furnace (-5 to10 mm of wcl) with

    forced draft fan. These flue gases emit their heat energy to various super heaters in the

    pent house and finally pass through air-preheaters and goes to electrostatic

    precipitators where the ash particles are extracted.

    Electrostatic Precipitator consists of metal plates, which are electrically charged. Ash

    particles are attracted on to these plates, so that they do not pass through the chimney

    to pollute the atmosphere. Regular mechanical hammer blows cause the accumulation

    of ash to fall to the bottom of the precipitator where they are collected in a hopper for

    disposal.

  • 8/4/2019 A Practile Training Report (2)

    13/61

    Steam to Mechanical Power

    From the boiler, a steam pipe conveys steam to the turbine through a stop valve (which

    can be used to shut-off the steam in case of emergency) and through control valves that

    automatically regulate the supply of steam to the turbine. Stop valve and control valves

    are located in a steam chest and a governor, driven from the main turbine shaft,

    operates the control valves to regulate the amount of steam used. (This depends upon

    the speed of the turbine and the amount of electricity required from the

    generator).Steam from the control valves enters the high pressure cylinder of theturbine, where it passes through a ring of stationary blades fixed to the cylinder wall.

  • 8/4/2019 A Practile Training Report (2)

    14/61

    These act as nozzles and direct the steam into a second ring of moving blades mounted

    on a disc secured to the turbine shaft. The second ring turns the shafts as a result of the

    force of steam. The stationary and moving blades together constitute a stage of turbine

    and in practice many stages are necessary, so that the cylinder contains a number of

    rings of stationary blades with rings of moving blades arranged between them.

    The steam passes through each stage in turn until it reaches the end of the high-pressure cylinder and in its passage some of its heat energy is changed into mechanical

    energy.

    The steam leaving the high pressure cylinder goes back to the boiler for reheating and

    returns by a further pipe to the intermediate pressure cylinder. Here it passes through

    another series of stationary and moving blades .Finally, the steam is taken to the low-

    pressure cylinders, each of which enters at the centre flowing outwards in opposite

    directions through the rows of turbine blades through an arrangement called the

    double flow- to the extremities of the cylinder. As the steam gives up its heat energy to

    drive the turbine, its temperature and pressure fall and it expands. Because of this

    expansion the blades are much larger and longer towards the low pressure ends of the

    turbine.

    Mechanical Power to Electrical Power

    As the blades of turbine rotate, the shaft of the generator, which is coupled to that of the

    turbine, also rotates. It results in rotation of the coil of the generator, which causes

    induced electricity to be produced.

    (COAL CYCLE)

    From Jharia mines

    Railway wagon

    BTPS wagon tripper

  • 8/4/2019 A Practile Training Report (2)

    15/61

    Magnetic separator

    Crusher house

    Coal stock yard

    RC bunker

    RC feeder

    Bowl mill Furnace

    ELECTRICITY FROM COAL

    Coal from the coal wagons is unloaded with the help of wagon tipplers in the C.H.P. this

    coal is taken to the raw coal bunkers with the help of conveyor belts. Coal is then

    transported to bowl mills by coal feeders where it is pulverized and ground in thepowered form.

  • 8/4/2019 A Practile Training Report (2)

    16/61

    This crushed coal is taken away to the furnace through coal pipes with the help of hot

    and cold mixture P.A fan. This fan takes atmospheric air, a part of which is sent to pre

    heaters while a part goes to the mill for temperature control. Atmospheric air from F.D

    fan in the air heaters and sent to the furnace as combustion air.

    Water from boiler feed pump passes through economizer and reaches the boiler drum .

    Water from the drum passes through the down comers and goes to the bottom ring

    header. Water from the bottom ring header is divided to all the four sides of the

    furnace. Due to heat density difference the water rises up in the water wall tubes. This

    steam and water mixture is again taken to the boiler drum where the steam is sent to

    super heaters for super heating. The super heaters are located inside the furnace and

    the steam is super heated (540 degree Celsius) and finally it goes to the turbine.

    Fuel gases from the furnace are extracted from the induced draft fan, which maintains

    balance draft in the furnace with F.D fan. These fuel gases heat energy to the various

    super heaters and finally through air pre heaters and goes to electrostatic precipitatorswhere the ash particles are extracted. This ash is mixed with the water to from slurry is

    pumped to ash period.

    The steam from boiler is conveyed to turbine through the steam pipes and through stop

    valve and control valve that automatically regulate the supply of steam to the turbine.

    Stop valves and controls valves are located in steam chest and governor driven from

    main turbine shaft operates the control valves the amount used.

    Steam from controlled valves enter high pressure cylinder of turbines, where it passes

    through the ring of blades fixed to the cylinder wall. These act as nozzles and direct the

    steam into a second ring of moving blades mounted on the disc secured in the turbine

    shaft. The second ring turns the shaft as a result of force of steam. The stationary and

    moving blades together.

    MAIN GENERATOR

    Maximum continuous KVA rating 24700KVA

    Maximum continuous KW 210000KW

    Rated terminal voltage 15750VRated Stator current 9050 A

    Rated Power Factor 0.85 lag

    Excitation current at MCR Condition 2600 A

    Slip-ring Voltage at MCR Condition 310 V

    Rated Speed 3000 rpm

    Rated Frequency 50 Hz

    Short circuit ratio 0.49

    Efficiency at MCR Condition 98.4%

    Direction of rotation viewed Anti Clockwise

    Phase Connection Double Star

    Number of terminals brought out 9( 6 neutral and 3 phase)

  • 8/4/2019 A Practile Training Report (2)

    17/61

    MAIN TURBINE DATA

    BASIC POWER PLANT CYCLE

    The thermal (steam) power plant uses a dual (vapour+ liquid) phase cycle. It is a closecycle to enable the working fluid (water) to be used again and again. The cycle used is Rankine

    Cycle modified to include superheating of steam, regenerative feed water heating and reheating

    of steam.

    On large turbines, it becomes economical to increase the cycle efficiency by using reheat, which

    is a way of partially overcoming temperature limitations.

    By returning partially expanded steam, to a reheat, the average temperature at which the heat

    is added, is increased and, by expanding this reheated steam to the remaining stages of the

    turbine, the exhaust wetness is considerably less than it would otherwise be conversely, if the

    maximum tolerable wetness is allowed, the initial pressure of the steam can be appreciablyincreased. Bleed Steam Extraction:

    For regenerative system, nos. of non-regulated extractions is taken from HP, IP turbine.

    Regenerative heating of the boiler feed water is widely used in modern power plants; the effect

    being to increase the average temperature at which heat is added to the cycle, thus improving

    the cycle efficiency.

    Rated output of Turbine 210 MWRated speed of turbine 3000 rpm

    Rated pressure of steam before emergency 130 kg/cm^2

    Stop valve rated live steam temperature 535 degree Celsius

    Rated steam temperature after reheat at inlet to receptor valve 535 degree Celsius

    Steam flow at valve wide open condition 670 tons/hour

    Rated quantity of circulating water through condenser 27000 cm/hour

    1. For cooling water temperature (degree Celsius) 24,27,30,33

    1.Reheated steam pressure at inlet of interceptor valve in

    kg/cm^2 ABS23,99,24,21,24,49,24.82

    2.Steam flow required for 210 MW in ton/hour 68,645,652,662

    3.Rated pressure at exhaust of LP turbine in mm of Hg 19.9,55.5,65.4,67.7

  • 8/4/2019 A Practile Training Report (2)

    18/61

    FACTORS AFFECTING THERMAL CYCLE EFFICIENCY

    Thermal cycle efficiency is affected by following:

    Initial Steam Pressure.

    Initial Steam Temperature.Whether reheat is used or not, and if used reheat pressure and temperature.

    Condenser pressure.

    Regenerative feed water heating.

  • 8/4/2019 A Practile Training Report (2)

    19/61

    RANKINECYCLE

    The Rankine cycle is a thermodynamic cycle which converts heat into work. The heat is

    supplied externally to a closed loop, which usually uses water as the working fluid. This cycle

    generates about 80% of all electric power used throughout the world, including virtually allsolar thermal, biomass, coal and nuclear power plants. It is named after William John

    Macquorn Rankine, a Scottish polymath..

    The Rankine cycle is sometimes referred to as a practical Carnot cycle because, when an

    efficient turbine is used, the TS diagram begins to resemble the Carnot cycle. The main

    difference is that heat addition (in the boiler) and rejection (in the condenser) are isobaric in the

    Rankine cycle and isothermal in the theoretical Carnot cycle. A pump is used to pressurize the

    working fluid received from the condenser as a liquid instead of as a gas. All of the energy in

    pumping the working fluid through the complete cycle is lost, as is most of the energy of

    vaporization of the working fluid in the boiler. This energy is lost to the cycle because the

    condensation that can take place in the turbine is limited to about 10% in order to minimize

    blade erosion; the vaporization energy is rejected from the cycle through the condenser.

    But pumping the working fluid through the cycle as a liquid requires a very small fraction ofthe energy needed to transport it as compared to compressing the working fluid as a gas in a

    compressor (as in the Carnot cycle).

    The efficiency of a Rankine cycle is usually limited by the working fluid. Without the pressure

    reaching super critical levels for the working fluid, the temperature range the cycle can operate

    over is quite small: turbine entry temperatures are typically 565C (the creep limit of stainless

    steel) and condenser temperatures are around 30C. This gives a theoretical Carnot efficiency of

    about 63% compared with an actual efficiency of 42% for a modern coal-fired power station.

    This low turbine entry temperature (compared with a gas turbine) is why the Rankine cycle is

    often used as a bottoming cycle in combined-cycle gas turbine power stations.

    http://en.wikipedia.org/wiki/Thermodynamicshttp://en.wikipedia.org/wiki/Solar_thermalhttp://en.wikipedia.org/wiki/Biomasshttp://en.wikipedia.org/wiki/Power_planthttp://en.wikipedia.org/wiki/William_John_Macquorn_Rankinehttp://en.wikipedia.org/wiki/William_John_Macquorn_Rankinehttp://en.wikipedia.org/wiki/Polymathhttp://en.wikipedia.org/wiki/Carnot_cyclehttp://en.wikipedia.org/wiki/TS_diagramhttp://en.wikipedia.org/wiki/Isobaric_processhttp://en.wikipedia.org/wiki/Isothermal_processhttp://en.wikipedia.org/wiki/Carnot_cyclehttp://en.wikipedia.org/wiki/Critical_point_%28thermodynamics%29http://en.wikipedia.org/wiki/Creep_%28deformation%29http://en.wikipedia.org/wiki/Carnot_efficiencyhttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Combined_cyclehttp://en.wikipedia.org/wiki/Combined_cyclehttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Carnot_efficiencyhttp://en.wikipedia.org/wiki/Creep_%28deformation%29http://en.wikipedia.org/wiki/Critical_point_%28thermodynamics%29http://en.wikipedia.org/wiki/Carnot_cyclehttp://en.wikipedia.org/wiki/Isothermal_processhttp://en.wikipedia.org/wiki/Isobaric_processhttp://en.wikipedia.org/wiki/TS_diagramhttp://en.wikipedia.org/wiki/Carnot_cyclehttp://en.wikipedia.org/wiki/Polymathhttp://en.wikipedia.org/wiki/William_John_Macquorn_Rankinehttp://en.wikipedia.org/wiki/William_John_Macquorn_Rankinehttp://en.wikipedia.org/wiki/William_John_Macquorn_Rankinehttp://en.wikipedia.org/wiki/Power_planthttp://en.wikipedia.org/wiki/Biomasshttp://en.wikipedia.org/wiki/Solar_thermalhttp://en.wikipedia.org/wiki/Thermodynamics
  • 8/4/2019 A Practile Training Report (2)

    20/61

    Description

    A Rankine cycle describes a model of the operation of steam heat engines most commonly found

    in power generation plants. Common heat sources for power plants using the Rankine cycle are

    coal, natural gas, oil, and nuclear. The Rankine cycle is sometimes referred to as a practical

    Carnot cycle as, when an efficient turbine is used, the TS diagram will begin to resemble the

    Carnot cycle.

    The main difference is that a pump is used to pressurize liquid instead of gas. This requires

    about 1/100th (1%) as much energy as that compressing a gas in a compressor (as in the Carnot

    cycle).The efficiency of a Rankine cycle is usually limited by the working fluid. Without

    the pressure going super critical the temperature range the cycle can operate over is quite small,

    turbine entry temperatures are typically 565C (the creep limit of stainless steel) and condenser

    temperatures are around 30C. This gives a theoretical Carnot efficiency of around63%

    compared with an actual efficiency of 42% for a modern coal-fired power station. This low

    turbine entry temperature (compared with a gas turbine) is why the Rankine cycle is often used

    as a bottoming cycle in combined cycle gas turbine power stations.The working fluid in a Rankine cycle follows a closed loop and is re-used constantly. The

    water vapor and entrained droplets often seen billowing from power stations is generated by the

    cooling systems (not from the closed loop Rankine power cycle) and represents the waste heat

    that could not be converted to useful work. Note that cooling towers operate using the latent

    heat of vaporizationof the cooling fluid.

    The white billowing clouds that form in cooling tower operation are the result of water droplets

    which are entrained in the cooling tower airflow; it is not, as commonly thought, steam. While

    many substances could be used in the Rankine cycle, water is usually the fluid of choice due to

    its favorable properties, such as nontoxic and unreactive chemistry ,abundance, and low cost, as

    well as its thermodynamic properties. One of the principal advantages it holds over other cycles

    is that during the compressions tage relatively little work is required to drive the pump, due to

    the working fluid being in its liquid phase at this point. By condensing the fluid to liquid, thework required by the pump will only consume approximately 1% to 3% of the turbine power

    http://en.wikipedia.org/wiki/Heat_engineshttp://en.wikipedia.org/wiki/Power_planthttp://en.wikipedia.org/wiki/Coalhttp://en.wikipedia.org/wiki/Natural_gashttp://en.wikipedia.org/wiki/Oilhttp://en.wikipedia.org/wiki/Carnot_cyclehttp://%20window.location.hash%3D%27/#outer_page_16'http://en.wikipedia.org/wiki/Carnot_cyclehttp://en.wikipedia.org/wiki/Carnot_cyclehttp://en.wikipedia.org/wiki/Critical_point_%28thermodynamics%29http://en.wikipedia.org/wiki/Creep_%28deformation%29http://en.wikipedia.org/wiki/Carnot_efficiencyhttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Combined_cyclehttp://en.wikipedia.org/wiki/Vaporhttp://en.wikipedia.org/wiki/Cooling_towershttp://en.wikipedia.org/wiki/Heat_of_vaporizationhttp://en.wikipedia.org/wiki/Cooling_towerhttp://%20window.location.hash%3D%27/#outer_page_16'http://%20window.location.hash%3D%27/#outer_page_16'http://en.wikipedia.org/wiki/Cooling_towerhttp://en.wikipedia.org/wiki/Heat_of_vaporizationhttp://en.wikipedia.org/wiki/Cooling_towershttp://en.wikipedia.org/wiki/Vaporhttp://en.wikipedia.org/wiki/Combined_cyclehttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Carnot_efficiencyhttp://en.wikipedia.org/wiki/Creep_%28deformation%29http://en.wikipedia.org/wiki/Critical_point_%28thermodynamics%29http://en.wikipedia.org/wiki/Carnot_cyclehttp://en.wikipedia.org/wiki/Carnot_cyclehttp://%20window.location.hash%3D%27/#outer_page_16'http://en.wikipedia.org/wiki/Carnot_cyclehttp://en.wikipedia.org/wiki/Oilhttp://en.wikipedia.org/wiki/Natural_gashttp://en.wikipedia.org/wiki/Coalhttp://en.wikipedia.org/wiki/Power_planthttp://en.wikipedia.org/wiki/Heat_engines
  • 8/4/2019 A Practile Training Report (2)

    21/61

    and so give a much higher efficiency for a real cycle. The benefit of this is lost somewhat due to

    the lower heat addition temperature. Gas turbines, for instance, have turbine entry

    temperatures approaching 1500C. Nonetheless, the efficiencies of steam cycles and gas turbines

    are fairly well matched.

    Processes of the Rankine cycle

    Ts diagram of a typical Rankine cycle operating between pressures of 0.06bar and 50bar.There

    are four processes in the Rankine cycle, each changing the state of the working fluid. These

    states are identified by number in the diagram to the right

    i.Process 1-2 : The working fluid is pumped from low to high pressure, as the fluid is a liquid at

    this stage the pump requires little input energy.

    ii.Process 2-3 : The high pressure liquid enters a boiler where it is heated at constant pressure

    by an external heat source to become a dry saturated vapour.iii.Process 3-4 : The dry saturated vapour expands through a turbine, generating power.This

    decreases the temperature and pressure of the vapour, and some condensation may occur.

    iv.Process 4-1 : The wet vapor then enters a condenser where it is condensed at a constant

    pressure and temperature to become a saturated liquid. The pressure and temperature of the

    condenser is fixed by the temperature of the cooling coils as the fluid is undergoing a phase-

    change. In an ideal Rankine cycle the pump and turbine would be isentropic ,i.e., the pump and

    turbine would generate no entropy and hence maximize the net work output. Processes 1-2and

    3-4 would be represented by vertical lines on the Ts diagram and more closely resemble that of

    the Carnot cycle. The Rankine cycle shown here prevents the vapour ending up in the superheat

    region after the expansion in the turbine, which reduces the energy removed by the condensers.

    http://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Turbinehttp://en.wikipedia.org/wiki/Surface_condenserhttp://en.wikipedia.org/wiki/Boiling_pointhttp://en.wikipedia.org/wiki/Phase_Transitionhttp://en.wikipedia.org/wiki/Phase_Transitionhttp://en.wikipedia.org/wiki/Isentropichttp://en.wikipedia.org/wiki/Isentropichttp://en.wikipedia.org/wiki/Phase_Transitionhttp://en.wikipedia.org/wiki/Phase_Transitionhttp://en.wikipedia.org/wiki/Boiling_pointhttp://en.wikipedia.org/wiki/Surface_condenserhttp://en.wikipedia.org/wiki/Turbinehttp://en.wikipedia.org/wiki/Gas_turbine
  • 8/4/2019 A Practile Training Report (2)

    22/61

    Real Rankine cycle (non-ideal) : Rankine cycle with superheat

    In a real Rankine cycle, the compression by the pump and the expansion in the turbine are not

    isentropic. In other words, these processes are non-reversible and entropy is increased during

    the two processes. This somewhat increases the power required by the pump and decreases the

    power generated by the turbine. In particular the efficiency of the steam turbine will be limited

    by water droplet formation. As the water condenses, water droplets hit the turbine blades at

    high speed causing pitting and erosion, gradually decreasing the life of turbine blades and

    efficiency of the turbine. The easiest way to overcome this problem is by superheating the steam.

    On the Ts diagram above, state 3 is above a two phase region of steam and water so after

    expansion the steam will be very wet. By superheating, state 3 will move to the right of the

    diagram and hence produce a dryer steam after expansion.

    http://en.wikipedia.org/wiki/Pumphttp://en.wikipedia.org/wiki/Turbinehttp://en.wikipedia.org/wiki/Entropyhttp://en.wikipedia.org/wiki/Power_%28physics%29http://en.wikipedia.org/wiki/Power_%28physics%29http://en.wikipedia.org/wiki/Entropyhttp://en.wikipedia.org/wiki/Turbinehttp://en.wikipedia.org/wiki/Pump
  • 8/4/2019 A Practile Training Report (2)

    23/61

    Rankine cycle with reheat

    In this variation, two turbines work in series. The first accepts vapour from the boiler at high

    pressure. After the vapour has passed through the first turbine, it re-enters the boiler and is

    reheated before passing through a second, lower pressure turbine. Among other advantages,this prevents the vapour from condensing during its expansion which can seriously damage the

    turbine blades, and improves the efficiency of the cycle.

    Regenerative Rankine cycle

    The regenerative Rankine cycle is so named because after emerging from the

    condenser (possibly as a sub cooled liquid) the working fluid is heated by steam tapped from

    the hot portion of the cycle. On the diagram shown, the fluid at 2 is mixed with the fluid at 4

    (both at the same pressure) to end up with the saturated liquid at 7. The Regenerative Rankine

    cycle(with minor variants) is commonly used in real power stations. Another variation is where

    'bleed steam' from between turbine stages is sent to feed water heaters to preheat the water on

    its way from the condenser to the boiler.

    http://en.wikipedia.org/wiki/Turbinehttp://en.wikipedia.org/wiki/Vaporizationhttp://en.wikipedia.org/wiki/Boilerhttp://en.wikipedia.org/wiki/Condensationhttp://en.wikipedia.org/wiki/Subcooled_liquidhttp://en.wikipedia.org/wiki/Steamhttp://en.wikipedia.org/wiki/Feedwater_heaterhttp://en.wikipedia.org/wiki/Feedwater_heaterhttp://en.wikipedia.org/wiki/Feedwater_heaterhttp://en.wikipedia.org/wiki/Steamhttp://en.wikipedia.org/wiki/Subcooled_liquidhttp://en.wikipedia.org/wiki/Condensationhttp://en.wikipedia.org/wiki/Boilerhttp://en.wikipedia.org/wiki/Vaporizationhttp://en.wikipedia.org/wiki/Turbine
  • 8/4/2019 A Practile Training Report (2)

    24/61

    BOILER MAINTENANCE DEPARTMENT

    Boiler and its description

    A boiler is a closed vessel in which water or other fluid is heated. The heated or vaporized

    fluid exits the boiler for use in various processes or heating applications Construction of

    boilers is mainly ofsteel, stainless steel, and wrought iron. In live steam models,

    copper or brass is often used. Historically copper was often used for fireboxes(particularly

    for steam locomotives), because of its better thermal conductivity. The price of copper

    now makes this impractical.

    Cast iron is used for domestic water heaters. Although these are usually termed "boilers",

    their purpose is to produce hot water, not steam, and so they run at low pressure and try

    to avoid actual boiling. The brittleness of cast iron makes it impractical for steam pressure

    vessels. The boiler is a rectangular furnace about 50 ft (15 m) on a side and 130 ft (40 m)tall. Its walls are made of a web of high pressure steel tubes about 2.3 inches (60 mm) in

    diameter. Pulverized coal is air-blown into the furnace from fuel nozzles at the four

    corners and it rapidly burns, forming a large fireball at the centre. The thermal radiation of

    the fireball heats the water that circulates through the boiler tubes near the boiler

    perimeter.

    The water circulation rate in the boiler is three to four times the throughput and is

    typically driven by pumps. As the water in the boiler circulates it absorbs heat and

    changes into steam at 700 F (370 C) and 3,200 psi (22.1MPa). It is separated from the

    water inside a drum at the top of the furnace.

    The saturated steam is introduced into superheat pendant tubes that hang in the hottestpart of the combustion gases as they exit the furnace. Here the steam is superheated to

    1,000 F (540C) to prepare it for the turbine. The steam generating boiler has to produce

    steam at the high purity, pressure and temperature required for the steam turbine that

    drives the electrical generator. The generator includes the economizer, the steam drum,

    the chemical dosing equipment, and the furnace with its steam generating tubes and the

    superheated coils. Necessary safety valves are located at suitable points to avoid

    excessive boiler pressure. The air and flue gas path equipment include: forced draft (FD)

    fan, air preheated (APH), boiler furnace, induced draft (ID) fan, fly ash collectors

    (electrostatic precipitator or bag house) and the flue gas stack.

    For units over about 210 MW capacity, redundancy of key components is provided byinstalling duplicates of the FD fan, APH, fly ash collectors and ID fan with isolating

    dampers .On some units of about 60 MW, two boilers per unit may instead be provided.

    http://en.wikipedia.org/wiki/Pressure_vesselhttp://en.wikipedia.org/wiki/Waterhttp://en.wikipedia.org/wiki/Mild_steelhttp://en.wikipedia.org/wiki/Stainless_steelhttp://en.wikipedia.org/wiki/Wrought_ironhttp://en.wikipedia.org/wiki/Live_steamhttp://en.wikipedia.org/wiki/Copperhttp://en.wikipedia.org/wiki/Brasshttp://en.wikipedia.org/wiki/Fireboxhttp://en.wikipedia.org/wiki/Steam_locomotivehttp://en.wikipedia.org/wiki/Cast_ironhttp://en.wikipedia.org/wiki/Cast_ironhttp://en.wikipedia.org/wiki/Steam_locomotivehttp://en.wikipedia.org/wiki/Fireboxhttp://en.wikipedia.org/wiki/Brasshttp://en.wikipedia.org/wiki/Copperhttp://en.wikipedia.org/wiki/Live_steamhttp://en.wikipedia.org/wiki/Wrought_ironhttp://en.wikipedia.org/wiki/Stainless_steelhttp://en.wikipedia.org/wiki/Mild_steelhttp://en.wikipedia.org/wiki/Waterhttp://en.wikipedia.org/wiki/Pressure_vessel
  • 8/4/2019 A Practile Training Report (2)

    25/61

    The steam generating boiler has to produce steam at the high purity, pressure and

    temperature required for the steam turbine that drives the electrical generator. The boiler

    includes the economizer, the steam drum, the chemical dosing equipment, and

    The furnace with its steam generating tubes and the super heater coils. Necessary safety

    valves are located at suitable points to avoid excessive boiler pressure. The air and flue

    path equipment include: forced draft (FD)fan, air preheater (APH), boiler furnace, induced

    draft (ID) fan, fly ash collectors(electrostatic precipitator or baghouse) and the flue gas

    stack .

    http://en.wikipedia.org/wiki/Furnacehttp://en.wikipedia.org/wiki/Centrifugal_fanhttp://en.wikipedia.org/wiki/Air_preheaterhttp://en.wikipedia.org/wiki/Electrostatic_precipitatorhttp://en.wikipedia.org/wiki/Dust_collector#Fabric_filtershttp://en.wikipedia.org/wiki/Flue_gas_stackhttp://en.wikipedia.org/wiki/Flue_gas_stackhttp://en.wikipedia.org/wiki/Flue_gas_stackhttp://en.wikipedia.org/wiki/Flue_gas_stackhttp://en.wikipedia.org/wiki/Dust_collector#Fabric_filtershttp://en.wikipedia.org/wiki/Electrostatic_precipitatorhttp://en.wikipedia.org/wiki/Air_preheaterhttp://en.wikipedia.org/wiki/Centrifugal_fanhttp://en.wikipedia.org/wiki/Furnace
  • 8/4/2019 A Practile Training Report (2)

    26/61

    Schematic diagram of typical coal-fired power plant steam generator highlighting the air

    preheater (APH) location

    SPECIFICATION:.

    MAIN BOILER AT 100% LOAD

    Evaporation 700t/hr

    Feed water temperature 247C

    Feed water leaving economizer 276C

    STEAM TEMPERATURE:

    :

    Drum 341C

    Super heater outlet 540C

    Reheat inlet 332C

    Reheat outlet 540C

  • 8/4/2019 A Practile Training Report (2)

    27/61

    STEAM PRESSURE:

    Drum design 158.20 kg/cm2

    Drum operating 149.70 kg/cm2

    Super heater outlet 137.00 kg/cm2

    Reheat inlet 26.35 kg/cm2

    Reheat outlet 24.50 kg/cm2

    FUEL SPECIFICATION

    :COAL DESIGN WORST

    Fixed carbon 38% 25%

    Volatile matter 26% 25%

    Moisture 8% 9%

    Grind ability 50% hard grove 45% hard grove

    OIL:

    Calorific value of fuel oil 10,000 kcal/kg

    Sulphur content 4.5% W/W

    Moisture content 1.1% W/WFlash point 66C

    HEAT BALANCE

    Dry gas loss 4.63%

    Carbon loss 2%

    Radiation loss 0.26%

    Unaccounted loss 1.5%

    Hydrogen in air and water in fuel 4.9%Total loss 13.3%

    Efficiency 86.7%

    AUXILIARIES OF BOILER

    1. FURNACEFurnace is primary part of boiler where the chemical energy of fuel is converted

    to thermal energy by combustion. Furnace is designed for efficient and completecombustion. Major factors that assist for efficient combustion area mount of fuel

  • 8/4/2019 A Practile Training Report (2)

    28/61

    inside the furnace and turbulence, which causes rapid mixing between fuel and air.

    In modern boilers, water-cooled furnaces are used.

    2. BOILER DRUMDrum is of fusion-welded design with welded hemi-spherical dished ends. It is provided

    with stubs for welding all the connecting tubes i.e. downcomers, risers, pipes, saturated

    steam outlet. The function of steam drum internals is to separate the water from the

    steam generated in the furnace walls and to reduce the dissolved solid contents of the

    steam below the prescribed limit of 1 ppm and also take care of the sudden change of

    steam demand for boiler.

    The secondary stage of two opposed banks of closely spaced thin corrugated sheets,

    which direct the steam and force the remaining entertained water against the corrugated

    plates. Since the velocity is relatively low this water does not get picked up again but runsdown the plates and off the second stage of the two steam outlets. From the secondary

    separators the steam flows upwards to the series of screen dryers, extending in layers

    across the length of the drum. These screens perform the final stage of separation.

    3. Classifier

    It is an equipment which serves separation of fine pulverized coal particles medium from

    coarse medium. The pulverized coal along with the carrying medium strikes the impactplate through the lower part. Large particles are then transferred to the ball mill.

  • 8/4/2019 A Practile Training Report (2)

    29/61

    4. Worm Conveyor

    It is equipment used to distribute the pulverized coal from bunker of one system to

    bunker of other system. It can be operated in both directions.

    5. WATER WALLS:

    Water flows to the water walls from the boiler drum by natural circulation. The front and

    the two side water walls constitute the main evaporation surface absorbing the bulk

    of radiant heat of the fuel burnt in the chamber. The front and rear walls are bent at the

    lower ends to form a water-cooled slag hopper. The upper part of the chamber is

    narrowed to achieve perfect mixing of combustion gases. The water walls tubes are

    connected to headers at the top and bottom. The rear water walls tubes at the top are

    grounded in four rows at a wider pitch forming the grid tubes.

    6. REHEATER

    Reheater is used to raise the temperature of steam from which a part of energy has been

    extracted in high- pressure turbine. This is another method of increasing the cycle

    efficiency. Reheating requires additional equipment I.e. Heating surface connecting boiler

    and turbine pipe safety equipment like safety valve, non-return valve, isolating valves,

    high pressure feed pump, etc. Reheater is composed to two sections namely front and

    rear pendant section which is located above the furnace arch between water-cooled

    screen wall tubes and rear wall hanger tubes.

  • 8/4/2019 A Practile Training Report (2)

    30/61

    7. Super heaters

    Whatever type of boiler is used, steam will leave the water at its surface and pass into

    the steam space. Steam formed above the water surface in a shell boiler is always

    saturated and become superheated in the boiler shell, as it is constantly. If superheated

    steam is required, the saturated steam must pass through a superheater. This is simply a

    heat exchanger where additional heat is added to the steam.

    In water-tube boilers, the superheater may be an additional pendant suspended in the

    furnace area where the hot gases will provide the degree of superheat required. In other

    cases, for example in CHP schemes where the gas turbine exhaust gases are relatively

    cool, a separately fired superheater may be needed to provide the additional heat.

    Fig. A water tube boiler with a super heater

    If accurate control of the degree of superheat is required, as would be the case if the

    steam is to be used to drive turbines, then an attemperator (desuperheater) is fitted. This

    is a device installed after the superheater, which injects water into the superheated steam

    to reduce its temperature.

  • 8/4/2019 A Practile Training Report (2)

    31/61

    8. ECONOMISER

    The function of an economizer in a steam-generating unit is to absorb heat from the flue

    gases and add as a sensible heat to the feed water before the water enters the

    evaporation circuit of the boiler.

    Earlier economizer were introduced mainly to recover the heat available in the flue gases

    that leaves the boiler and provision of this addition heating surface increases the

    efficiency of steam generators. In the modern boilers used for power generation feed

    water heaters were used to increase the efficiency of turbine unit and feed

    water temperature.

    Use ofeconomizer or air heater or both is decided by the total economy that will result

    in flexibility in operation, maintenance and selection of firing system and other related

    equipment. Modern medium and high capacity boilers are used both as economizers andair heaters. In low capacity, air heaters may alone be selected.

    . An economizer

    Stop valves and non-return valves may be incorporated to keep circulation in economizer

    into steam drum when there is fire in the furnace but not feed flow. Tube elements

    composing the unit are built up into banks and these are connected to inlet and outlet

    headers.

  • 8/4/2019 A Practile Training Report (2)

    32/61

    9. AIR PREHEATER

    Air preheater absorbs waste heat from the flue gases and transfers this heat to incoming

    cold air, by means of continuously rotating heat transfer element of specially formed

    metal plates. Thousands of these high efficiency elements are spaced and compactly

    arranged within 12 sections. Sloped compartments of a radially divided cylindrical shell

    called the rotor. The housing surrounding the rotor is provided with duct connecting both

    the ends and is adequately scaled by radial and circumferential scaling.

    Special sealing arrangements are provided in the provided in the air preheater to prevent

    the leakage between the air and gas sides. Adjustable plates are also used to help the

    sealing arrangements and prevent the leakage as expansion occurs. The air preheater

    heating surface elements are provided with two types of cleaning devices, soot blowers to

    clean normal devices and washing devices to clean the element when soot blowing alone

    cannot keep the element clean.

    An air preheater

    10. PULVERIZER

    A pulverizer is a mechanical device for the grinding of many types of materials.

    For example, they are used to pulverize coal for combustion in the steam-generating

    furnaces of the fossil fuel power plants.

  • 8/4/2019 A Practile Training Report (2)

    33/61

    A Pulverize

    Types of Pulverize.

    i. Ball and Tube millsA ball mill is a pulverizer that consists of a horizontal cylinder, up to three diameter sin

    length, containing a charge of tumbling or cascading steel balls, pebbles or steel rods. A

    tube mill is a revolving cylinder of up to five diameters in length used for

    finer pulverization of ore, rock and other such materials; the materials mixed with water

    is fed into the chamber from one end, and passes out the other end as slime.

    ii. Bowl millIt uses tires to crush coal. It is of two types; a deep bowl mill and the shallow bowl mill.

    Bowl Mill: - One of the most advanced designs of coal pulverizes presently manufactured.

    Motor specificationsquirrel cage induction motor

    Rating-340 KW

    Voltage-6600KV

    Curreen-41.7A

    Speed-980 rpm

    Frequency-50 HzNo-load current-15-16 A

  • 8/4/2019 A Practile Training Report (2)

    34/61

    An external view of a Coal Pulverizer

    Advantages of Pulverized Coal

    Pulverized coal is used for large capacity plants.

    It is easier to adapt to fluctuating load as there are no limitations on the combustion

    capacity.Coal with higher ash percentage cannot be used without pulverizing because of

    the problem of large amount ash deposition after combustion.

    Increased thermal efficiency is obtained through pulverization.

    The use of secondary air in the combustion chamber along with the powered coal helps

    in creating turbulence and therefore uniform mixing of the coal and the air during

    combustion.

    Greater surface area of coal per unit mass of coal allows faster combustion as more coal

    is exposed to heat and combustion.

    The combustion process is almost free from clinker and slag formation.

    The boiler can be easily started from cold condition in case of emergency.Practically no ash handling problem.

    The furnace volume required is less as the turbulence caused aids in complete

    combustion of the coal with minimum travel of the particles.

    11. CYCLONE SEPARATOR

    Cyclonic separation is a method of removing particulates from an air, gas or liquid stream,

    without the use offilters, through vortex separation. Rotational effects and gravity are

    fine droplets of liquid from a gaseous stream.

    http://en.wikipedia.org/wiki/Particulatehttp://en.wikipedia.org/wiki/Filter_%28air%29http://en.wikipedia.org/wiki/Vortexhttp://en.wikipedia.org/wiki/Rotationhttp://en.wikipedia.org/wiki/Gravityhttp://en.wikipedia.org/wiki/Gravityhttp://en.wikipedia.org/wiki/Rotationhttp://en.wikipedia.org/wiki/Vortexhttp://en.wikipedia.org/wiki/Filter_%28air%29http://en.wikipedia.org/wiki/Particulate
  • 8/4/2019 A Practile Training Report (2)

    35/61

    A high speed rotating (air)flow is established within a cylindrical or conical container

    called a cyclone. Air flows in a spiral pattern, beginning at the top (wide end) of the

    cyclone and ending at the bottom (narrow) end before exiting the cyclone in a straight

    stream through the center of the cyclone and out the top. Larger (denser) particles in the

    rotating stream have too much inertia to follow the tight curve of the stream, and strike

    the outside wall, then falling to the bottom of the cyclone where they can be removed. In

    a conical system, as the rotating flow moves towards the narrow end of the cyclone, the

    rotational radius of the stream is reduced, thus separating smaller and smaller particles.

    The cyclone geometry, together with flow rate, defines the cut point of the cyclone. This is

    the size of particle that will be removed from the stream with a 50% efficiency. Particles

    larger than the cut point will be removed with a greater efficiency, and smaller particles

    with a lower efficiency.

    http://en.wikipedia.org/wiki/Flow_ratehttp://en.wikipedia.org/wiki/Flow_rate
  • 8/4/2019 A Practile Training Report (2)

    36/61

    PLANT AUXILIARY MAINTENANCE

    1. WATER CIRCULATION SYSTEM

    Theory of Circulation

    Water must flow through the heat absorption surface of the boiler in order that it be

    evaporated into steam. In drum type units (natural and controlled circulation), the

    water is circulated from the drum through the generating circuits and then back to the

    drum where the steam is separated and directed to the super heater. The water leaves

    the drum through the down corners at a temperature slightly below the saturation

    temperature. The flow through the furnace wall is at saturation temperature. Heat

    absorbed in water wall is latent heat of vaporization creating a mixture of steam and

    water. The ratio of the weight of the water to the weight of the steam in the mixture

    leaving the heat absorption surface is called circulation ratio.

    Types of Boiler Circulating System

    i.Natural circulation system

    ii.Controlled circulation system

    iii.Combined circulation system

    i. Natural circulation SystemWater delivered to steam generator from feed water is at a temperature well below the

    saturation value corresponding to that pressure. Entering first the economizer, it is

    heated to about 30-40C below saturation temperature. From economizer the water

    enters the drum and thus joins the circulation system. Water entering the drum flows

    through the down corner and enters ring heater at the bottom. In the water walls, a part

    of the water is converted to steam and the mixture flows back to the drum. In the drum,

    the steam is separated, and sent to super heater for superheating and then sent to the

    high-pressure turbine. Remaining water mixes with the incoming water from the

    economizer and the cycle is repeated. As the pressure increases, the difference in densitybetween water and steam reduces. Thus the hydrostatic head available will not be able

    to overcome the frictional resistance for a flow corresponding to the minimum

    requirement of cooling of water wall tubes. Therefore natural circulation is limited to

    the boiler with drum operating pressure around 175 kg/ cm.

    ii. Controlled circulation SystemBeyond 80 kg/ cm of pressure, circulation is to be assisted with mechanical pumps to

    overcome the frictional losses. To regulate the flow through various tubes, orifices plates

    are used. This system is applicable in the high sub-critical regions (200 kg/ cm).

  • 8/4/2019 A Practile Training Report (2)

    37/61

    1. ASH HANDLING PLANTThe widely used ash handling systems are:

    i. Mechanical Handling System

    ii. Hydraulic System.

    iii. Pneumatic System.

    iv. Steam jet System.

    Ash Handling System at Badarpur Thermal Power Station, New Delhi

    The Hydraulic Ash handling system is used at the Badarpur Thermal Power Station.

    Hydraulic Ash Handling System

    The hydraulic system carried the ash with the flow of water with high velocity througha channel and finally dumps into a sump. The hydraulic system is divided into a low

    velocity and high velocity system. In the low velocity system the ash from the boilers

    falls into a stream of water flowing into the sump. The ash is carried along with the

    water and they are separated at the sump. In the high velocity system a jet of water is

    sprayed to quench the hot ash. Two other jets force the ash into a trough in which they

    are washed away by the water into the sump, where they are separated. The molten slag

    formed in the pulverized fuel system can also be quenched and washed by using the

    high velocity system. The advantages of this system are that its clean, large ash handling

    capacity, considerable distance can be traversed, absence of working parts in contact

    with ash.

  • 8/4/2019 A Practile Training Report (2)

    38/61

    Fly Ash Collection

    Fly ash is captured and removed from the flue gas by electrostatic precipitators or

    fabric bag filters (or sometimes both) located at the outlet of the furnace and before the

    induced draft fan. The fly ash is periodically removed from the collection hoppers belowthe precipitators or bag filters. Generally, the fly ash is pneumatically transported to

    storage silos for subsequent transport by trucks or railroad cars.

    Bottom Ash Collection and Disposal

    At the bottom of every boiler, a hopper has been provided for collection of the bottom

    ash from the bottom of the furnace. This hopper is always filled with water to quench

    the ash and clinkers falling down from the furnace. Some arrangement is included to

    crush the clinker sand for conveying the crushed clinkers and bottom ash to a storagesite.

    1. WATER TREATMENT PLANTAs the types of boiler are not alike their working pressure and operating conditions

    vary and so do the types and methods of water treatment. Water treatment plants used

    in thermal power plants used in thermal power plants are designed to process the raw

    water to water with a very low content of dissolved solids known as demineralised

    water. No doubt, this plant has to be engineered very carefully keeping in view the typeof raw water to the thermal plant, its treatment costs and overall economics.

  • 8/4/2019 A Practile Training Report (2)

    39/61

    A water treatment plant

    The type of demineralization process chosen for a power station depends on three main

    factors.i. The quality of raw material.ii. The degree of de-ionization i.e. treated water quality.iii. Selectivity of resins.

    Water treatment process is generally made up of two sections:

    Pre-treatment section.

    Demineralization section

    Pre-treatment Section

    Pre-treatment plant removes the suspended solids such as clay, silt, organic and

    inorganic matter, plants and other microscopic organism. The turbidity may be taken

    as two types of suspended solid in water; firstly, the separable solids and secondly the

    non-separable solids (colloids). The coarse components, such as sand, silt, etc: can be

    removed from the water by simple sedimentation. Finer particles, however, will not

    settle in any reasonable time and must be flocculated to produce the large particles,

    which are settling able. Long term ability to remain suspended in water is basically afunction of both size and specific gravity.

    Demineralization

    This filter water is now used for demineralising purpose and is fed to cation exchanger

    bed, but enroute being first dechlorinated, which is either done by passing through

    activated carbon filter or injecting along the flow of water, an equivalent amount of

    sodium sulphite through some stroke pumps. The residual chlorine, which is maintained

    in clarification plant to remove organic matter from raw water, is now detrimental toaction resin and must be eliminated before its entry to this bed.

  • 8/4/2019 A Practile Training Report (2)

    40/61

    A demineralization tank

    A DM plant generally consists of cation, anion and mixed bed exchangers. The final

    water from this process consists essentially of hydrogen ions and hydroxide ions whichis the chemical composition of pure water. The DM water, being very pure, becomes

    highly corrosive once it absorbs oxygen from the atmosphere because of its very high

    affinity for oxygen absorption. The capacity of the DM plant is dictated by the type and

    quantity of salt sin the raw water input. However, some storage is essential as the DM

    plant may be down for maintenance. For this purpose, a storage tank is installed from

    which DM water is continuously withdrawn for boiler make-up. The storage tank for

    DM water is made from materials not affected by corrosive water, such as PVC. The

    piping and valves are generally of stainless steel. Sometimes, a steam blanketing

    arrangement or stainless steel doughnut float is provided on top of the water in the tank

    to avoid contact with atmospheric air. DM water make-up is generally added at the

    steam space of the surface condenser (i.e., theVacuum side). This arrangement not only sprays the water but also DM water gets

    deaerated, with the dissolved gases being removed by the ejector of the condenser itself.

  • 8/4/2019 A Practile Training Report (2)

    41/61

    WTP-II Flash mixture (Cl2 +Pac (Poly aluminium chorine) )

    Clarifier tank Storage tank Clarifier pump(A or B)

    +Cation anion Active carbon filter Pressure filter (A, B, C, D)

    Degasser tank (Co2 removed)

    Degasser pump -Anion (NaoH used)

    Strong base anion Mixed bed(6.57 ph)

    DM Storage tank

    Systematic arrangement of water treatment II

    1.DRAUGHT SYSTEM

    There are four types of draught system:

    i.Natural Draught

    ii.Induced Draught

    iii.Forced Draught

    iv.Balanced Draught

    Natural Draught System

    In natural draft units the pressure differentials are obtained have constructing tail

    chimneys so that vacuum is created in the furnace. Due to small pressure difference, airis admitted into the furnace

  • 8/4/2019 A Practile Training Report (2)

    42/61

    A natural draught system

    Induced Draft System

    In this system, the air is admitted to natural pressure difference and the flue gases are

    taken out by means of Induced Draught (I.D.) fans and the furnace is maintained under

    vacuum.

    Forced Draught System

    A set of forced draught (F.D.) fans is made use of for supplying air to the furnace and so

    the furnace is pressurized. The flue gases are taken out due to the pressure difference

    between the furnace and the atmosphere.

    Balanced Draught SystemHere a set of Induced and Forced Draft Fans are utilized in maintaining a vacuum in

    the furnace. Normally all the power stations utilize this draft system.

    1. INDUSTRIAL FANSID Fan

    The induced Draft Fans are generally of Axial-Impulse Type. Impeller nominal

    diameter is of the order of 2500 mm. The fan consists of the following sub-assemblies:

    Suction Chamber

  • 8/4/2019 A Practile Training Report (2)

    43/61

    Inlet Vane Control

    Impeller

    Outlet Guide Vane Assembly

    ID Fans: - Located between electrostatic precipitator and chimney.

    Type-radical

    Speed-1490 rpm

    Rating-300 KW

    Voltage-6.6 KV

    Lubrication-by oil

    An ID fan

    FD FanThe fan, normally of the same type as ID Fan, consists of the following components:

    Silencer

    Inlet Bend

    Fan Housing

    Impeller with blades and setting mechanism

    FD Fans: - Designed to handle secondary air for boiler. 2 in number and provide

    ignition of coal.

    Type-axial

    Speed-990 rpm

    Rating-440 KW

    Voltage-6.6 KV

  • 8/4/2019 A Practile Training Report (2)

    44/61

    An FD fan

    The centrifugal and setting forces of the blades are taken up by the blade bearings. The

    blade shafts are placed in combined radial and axial anti-friction bearings, which are

    sealed off to the outside. The angle of incidence of the blades may be adjusted duringoperation. The characteristic pressure volume curves of the fan may be changed in a

    large range without essentially modifying the efficiency. The fan can then be easily

    adapted to changing operating conditions.

    The rotor is accommodated in cylindrical roller bearings and an inclined ball bearing at

    the drive side absorbs the axial thrust.

    Lubrication and cooling these bearings is assured by a combined oil level and

    circulating lubrication system.

    Primary Air Fan

    PA Fan if flange-mounted design, single stage suction, NDFV type, backward curved

    bladed radial fan operating on the principle of energy transformation due to centrifugal

    forces. Some amount of the velocity energy is converted to pressure energy in the spiral

    casing. The fan is driven at a constant speed and varying the angle of the inlet vane

    control controls the flow. The special feature of the fan is that is provided with inlet

    guide vane control with a positive and precise link mechanism.

    It is robust in construction for higher peripheral speed so as to have unit sizes. Fan can

    develop high pressures at low and medium volumes and can handle hot-air laden with

    dust particles.

    Primary Air Fans: - Designed for handling the atmospheric air up to 50 degrees Celsius,

    2 in number

    And they transfer the powered coal to burners to firing.

    Type-Double suction radial

    Rating-300 KW

    Voltage-6.6 KV

    Lubrication-by oil

    Type of operation-continuous

  • 8/4/2019 A Practile Training Report (2)

    45/61

    Primary air fan

    1. COMPRESSOR HOUSEInstrument air is required for operating various dampers, burner tilting, devices,diaphragm valves, etc: in the 210 MW units. Station air meets the general requirement

    of the power station such as light oil atomizing air, for cleaning filters and for various

    maintenance works. The control air compressors and station air compressors have been

    housed separately with separate receivers and supply headers and their tapping.

    A compressor house

    Instrument Air System

    Control air compressors have been installed for supplying moisture free dry air

    required for instrument used. The output from the compressors is fed to air receivers

    via return valves. From the receiver air passed through the dryers to the main

    instrument airline, which runs along with the boiler house and turbine house of 210

    MW units. Adequate numbers of tapping have been provided all over the area.

    Air-Drying Unit

    Air contains moisture which tends to condense, and causes trouble in operation of

    various devices by compressed air. Therefore drying of air is accepted widely in case of

    instrument air. Air drying unit consists of dual absorption towers with embedded

  • 8/4/2019 A Practile Training Report (2)

    46/61

    heaters for reactivation. The absorption towers are adequately filled with specially

    selected silica gel and activated alumina while one tower is drying the air.

    Service Air Compressor

    The station air compressor is generally a slow speed horizontal double acting double

    stage type and is arranged for belt drive. The cylinder heads and barrel are enclosed in

    a jacket, while extends around the valve also. The intercooler is provided between the

    low and high pressure cylinder which cools the air between tag and collects the moisture

    that condenses Air from L.P. cylinder enters at one end of the intercooler and goes to

    the opposite end where from it is discharged to the high-pressure cylinder; cooling

    water flows through the nest of the tubes and cools the air. A safety valve is set at rated

    pressure. Two selectors switch one with positions auto load/unload and another with

    positions auto start/stop, non-stop have been provided on the control panel of the

    compressor. In auto start-stop position, the compressor will start.

  • 8/4/2019 A Practile Training Report (2)

    47/61

    TURBINE MAINTENANCE DEPARTMENT

    TURBINE CLASSIFICATION:

    1. Impulse turbine:

    In impulse turbine steam expands in fixed nozzles. The high velocity steam from nozzles

    does work on moving blades, which causes the shaft to rotate. The essential features of

    impulse turbine are that all pressure drops occur at nozzles and not on blades.

    2. Reaction turbine:

    In this type of turbine pressure is reduced at both fixed and moving blades. Both fixed and

    moving blades act like nozzles. Work done by the impulse effect of steam due to reverse

    the direction of high velocity steam. The expansion of steam takes place on moving

    blades.

    A 95 MW Generator at BTPS, New Delhi

    COMPOUNDING:

    Several problems occur if energy of steam is converted in single step and so compoundingis done. Following are the type of compounded turbine:

  • 8/4/2019 A Practile Training Report (2)

    48/61

    i. Velocity compounded Turbine :Like simple turbine it has only one set of nozzles and entire steam pressure drop takes

    place there. The kinetic energy of steam fully on the nozzles is utilized in moving blades.

    The role of fixed blades is to change the direction of steam jet and too guide it.

    ii. Pressure Compound Turbine :This is basically a number of single impulse turbines in series or on the same

    shaft. The exhaust of first turbine enters the nozzles of next turbine. The total pressure

    drop of steam does not take on first nozzle ring but divided equally on all of them.

    iii. Pressure Velocity Compounded Turbine:

    It is just the combination of the two compounding and has the advantages of allowing

    bigger pressure drops in each stage and so fewer stages are necessary. Here for givenpressure drop the turbine will be shorter length but diameter will be increased.

    MAIN TURBINE

    The 210MW turbine is a cylinder tandem compounded type machine comprising of H.P.

    and I.P and L.P cylinders. The H.P. turbine comprises of 12 stages the I.P turbine has 11

    stages and the L.P has four stages of double flow. The H.P and I.P. turbine rotor are rigidly

    compounded and the I.P. and L.P rotor by lens type semi flexible coupling. All the 3 rotor

    are aligned on five bearings of which the bearing number is combined with thrust bearing.The main superheated steam branches off into two streams from the boiler and passes

    through the emergency stop valve and control valve before entering the governing wheel

    chamber of the H.P. Turbine.

    After expanding in the 12 stages in the H.P. turbine then steam is returned in the boiler

    for reheating. The reheated steam from boiler enters I.P. turbine via the interceptor

    valves and control valves and after expanding enters the L.P stage via 2 numbers of cross

    over pipes. In the L.P. stage the steam expands in axially opposed direction to counteract

    the thrust and enters the condenser placed directly below the L.P. turbine. The cooling

    water flowing through the condenser tubes condenses the steam and the condensate the

    collected in the hot well of the condenser.The condensate collected the pumped by means of 3x50% duty condensate pumps

    through L.P heaters to deaerator from where the boiler feed pump delivers the water to

    the boiler through H.P. heaters thus forming a closed cycle.

    STEAM TURBINE

    A steam turbine is a mechanical device that extracts thermal energy from pressurized

    steam and converts it into useful mechanical work. From a mechanical point of view, the

    turbine is ideal, because the propelling force is applied directly to the rotating element ofthe machine and has not as in the reciprocating engine to be transmitted through a

  • 8/4/2019 A Practile Training Report (2)

    49/61

    system of connecting links, which are necessary to transform are reciprocating motion

    into rotary motion. Hence since the steam turbine possesses for its moving parts rotating

    elements only if the manufacture is good and the machine is correctly designed, it ought

    to be free from out of balance forces. If the load on a turbine is kept constant the torque

    developed at the coupling is also constant. A generator at a steady load offers a constant

    torque.

    Therefore, a turbine is suitable for driving a generator, particularly as they are both high-

    speed machines. A further advantage of the turbine is the absence of internal lubrication.

    This means that the exhaust steam is not contaminated with oil vapour and can be

    condensed and fed back to the boilers without passing through the filters. It also means

    that turbine is considerable saving in lubricating oil when compared with a reciprocating

    steam engine of equal power. A final advantage of the steam turbine and a very important

    one is the fact that a turbine can develop many time the power compared to a

    reciprocating engine whether steam or oil.

    OPERATING PRINCIPLES

    A steam turbines two main parts are the cylinder and the rotor. The cylinder (stator) is a

    steel or cast iron housing usually divided at the horizontal centre line. Its halves are bolted

    together for easy access. The cylinder contains fixed blades, vanes and nozzles that direct

    steam into the moving blades carried by the rotor. Each fixed blade set is mounted in

    diaphragms located in front of each disc on the rotor, or directly in the casing. A disc and

    diaphragm pair a turbine stage. Steam turbines can have many stages. A rotor is a rotating

    shaft that carries the moving blades on the outer edges of either discs or drums. The

    blades rotate as the rotor revolves. The rotor of a large steam turbine consists of large,

    intermediate and low-pressure sections. In a multiple-stage turbine, steam at a high

    pressure and high temperature enters the first row of fixed blades or nozzles through an

    inlet valve/valves. As the steam passes through the fixed blades or nozzles, it expands and

    its velocity increases. The high velocity jet of stream strikes the first set of moving blades.

    The kinetic energy of the steam changes into mechanical energy, causing the shaft to

    rotate. The steam that enters the next set of fixed blades strikes the next row of moving

    blades. As the steam flows through the turbine, its pressure and temperature decreaseswhile its volume increases. The decrease in pressure and temperature occurs as the steam

    transmits energy to the shaft and performs work. After passing through the last turbine

    stage, the steam exhausts into the condenser or process steam system.

    The kinetic energy of the steam changes into mechanical energy through the impact

    (impulse)or reaction of the steam against the blades. An impulse turbine uses the impact

    force of the steam jet on the blades to turn the shaft. Steam expands as it passes through

    thee nozzles, where its pressure drops and its velocity increases. As the steam flows

    through the moving blades, its pressure remains the same, but its velocity decreases. The

    steam does not expand as it flows through the moving blades.

  • 8/4/2019 A Practile Training Report (2)

    50/61

  • 8/4/2019 A Practile Training Report (2)

    51/61

    STEAM CYCLE

    The thermal (steam) power plant uses a dual (vapor+liquid) phase cycle. It is a closed cycle

    to enable the working fluid (water) to be used again and again. The cycle used is Rankine

    cycle modified to include superheating of steam, regenerative feed water heating and

    reheating of steam.

    MAIN TURBINE

    The 210 MW turbine is a tandem compounded type machine comprising of H.P. and I.P.

    cylinders. The H.P. turbines comprise of 12 stages, I.P. turbine has 11 stages and the L.P.

    turbine has 4 stages of double flow. The H.P. and I.P. turbine rotors are rigidly

    compounded and the L.P. motor by the lens type semi flexible coupling. All the three

    rotors are aligned on five bearings of which the bearing no. 2 is combined with the thrustbearing. The main superheated steam branches off into two streams from the boiler and

    passes through the emergency stop valve and control valve before entering the governing

    wheel chamber of the H.P. turbine.

    After expanding in the 12 stages in the H.P. turbine the steam is returned in boiler for

    reheating. The reheated steam for the boiler enters the I.P> turbine via the interceptor

    valves and control valves and after expanding enters the L.P. turbine stage via 2 nos of

    cross-over pipes. In the L.P. stage the steam expands in axially opposite direction to

    counteract the trust and enters the condensers placed below the L.P. turbine. The cooling

    water flowing throughout the condenser tubes condenses the steam and the condensate

  • 8/4/2019 A Practile Training Report (2)

    52/61

    collected in the hot well of the condenser. The condensate collected is pumped by means

    of 3*50% duty condensate pumps through L.P. heaters to deaerator from where the boiler

    feed pump delivers the water to boiler through H.P. heaters thus forming a close cycle.

    The main Turbine

    TURBINE CYCLE

    Fresh steam from the boiler is supplied to the turbine through the emergency stop valve.From the stop valves steam is supplied to control valves situated in H.P. cylinders on the

    front bearing end. After expansion through 12 stages at the H.P. cylinder, steam flows

    back to the boiler for reheating steam and reheated steam from the boiler cover to the

    intermediate pressure turbine through two interceptor valves and four control valves

    mounted on I.P. turbine. After flowing through I.P. turbine steam enters the middle part

    of the L.P. turbine through cross-over pipes. In L.P. turbine the exhaust steam condenses

    in the surface condensers welded directly to the exhaust part of L.P. turbine.

    The selection of extraction points and cold reheat pressure has been done with a view to

    achieve a high efficiency. These are two extractors from H.P. turbine, four from I.P.

    turbine and one from L.P. turbine. Steam at 1.10 and 1.03 g/sq. cm. Abs is supplied for thegland sealing. Steam for this purpose is obtained from deaerator through a collection

  • 8/4/2019 A Practile Training Report (2)

    53/61

    where pressure of steam is regulated. From the condenser, condensate is pumped with

    the help of 3*50% capacity condensate pumps to deaerator through the low-pressure

    regenerative equipments. Feed water is pumped from deaerator to the boiler through the

    H.P. heaters by means of 3*50% capacity feed pumps connected before the H.P. heaters

    The turbine cycle

    SPECIFICATIONS OF THE TURBINE

    Type: Tandem compound 3 cylinder reheated type.

    Rated power: 210 MW.

    Number of stages: 12 in H.P., 11 in I.P. and 4*2 in L.P. cylinder.

    Rated steam pressure: 130 kg /sq. cm before entering the stop valve.

    Rated steam temperature: 535C after reheating at inlet.Steam flow: 670T / hr.

    H.P. turbine exhaust pressure: 27 kg /sq. cm., 327C

    Condenser back pressure: 0.09 kg /sq. cm.

    Type of governing: nozzle governing.

    Number of bearing; 5 excluding generator and exciter.

    Lubrication Oil: turbine oil 14 of IOC.

    Gland steam pressure: 1.03 to 1.05 kg /sq. cm (Abs)

    Critical speed: 1585, 1881, 2017.

    Ejector steam parameter: 4.5 kg /sq. cm.

    Condenser cooling water pressure: 1.0 to 1.1 kg /sq. cm.

    Condenser cooling water temperature: 27000 cu. M /hr.Number of extraction lines for regenerative heating of feed water: seven

  • 8/4/2019 A Practile Training Report (2)

    54/61

    TURBINE COMPONENTS

    Casing.

    Rotor.

    Blades.Sealing system.

    Stop & control valves.

    Couplings and bearings.

    Barring gear.

    TURBINE CASINGS

    HP Turbine Casings:

    Outer casing: a barrel-type without axial or radial flange.

    Barrel-type casing suitable for quick start-up and loading.The inner casing- cylindrically, axially split

    The inner casing is attached in the horizontal and vertical planes in the barrel casing so that it can

    freely expand radially in all the directions and axially from a fixed point (HP- inlet side).

    IP Turbine Casing:

    The casing of the IP turbine is split horizontally and is of double-shell construction.

    Both are axially split and a double flow inner casing is supported in the outer casing and carries

    the guide blades.

    Provides opposed double flow in the two blade sections and compensates axial thrust.

    Steam after reheating enters the inner casing from Top & Bottom.

    LP Turbine Casing:

    The LP turbine casing consists of a double flow unit and has a triple shell welded casing.

    The shells are axially split and of rigid welded construction.

    The inner shell taking the first rows of guide blades is attached kinematically in the middle shell.

    Independent of the outer shell, the middle shell, is supported at four points on longitudinal

    beams.

    Steam admitted to the LP turbine from the IP turbine flows into the inner casing from both sides.

    ROTORSHP Rotor:

    The HP rotor is machined from single Cr-Mo-V steel forging with integral discs.

    In all the moving wheels, balancing holes are machined to reduce the pressure difference across

    them, which results in reduction of axial thrust.

    First stage has integral shrouds while other rows have shrouding, riveted to the blades are

    periphery.

  • 8/4/2019 A Practile Training Report (2)

    55/61

    IP Rotor:

    The IP rotor has seven discs integrally forged with rotor while last four discs are shrunk fit.

    The shaft is made of high creep resisting Cr-Mo-V steel forging while the shrunk fit discs are

    machined from high strength nickel steel forgings.

    Except the last two wheels, all other wheels have shrouding riveted at the tip of the blades. To

    adjust the frequency of thee moving blades, lashing wires have been provided in some stages.

    LP Rotor:

    The LP rotor consists of shrunk fit discs in a shaft.

    The shaft is a forging of Cr-Mo-V steel while the discs are of high strength nickel steel forgings.

    Blades are secured to the respective discs by riveted fork root fastening.

    In all the stages lashing wires are provided to adjust the frequency of blades. In the last two

    rows, satellite strips are provided at the leading edges of the blades to protect them against wet-

    steam erosion.

    BLADES

    Most costly element of the turbine.

    Blades fixed in stationary part are called guide blades/ nozzles and those fitted in moving part

    are called rotating/working blades.

    Blades have three main parts:

    Aerofoil: working part.

    Root.

    Shrouds.

    Shroud is used to prevent steam leakage and guide steam to next set of moving blades.

    VACUUM SYSTEM

    This comprises of:

    Condenser: 2 for 200 MW units at the exhaust of LP turbine.

    Ejectors:

    One starting and two main ejectors connected to the condenser located near the turbine.

    C.W. Pumps: Normally two per unit of 50% capacity.

    CONDENSER

    There are two condensers entered to the two exhausters of the L.P. turbine. These are

    surface-type condensers with two pass arrangement. Cooling water pumped into each

    condenser by a vertical C.W. pump through the inlet pipe. Water enters the inlet chamber

    of the front water box, passes horizontally through brass tubes to the water tubes to the

    water box at the other end, takes a turn, passes through the upper cluster of tubes and

    reaches the outlet chamber in the front water box. From these, cooling water leaves the

    condenser through the outlet pipe and discharge into the discharge duct. Steam

    exhausted from the LP turbine washes the outside of the condenser tubes, losing its latent

    heat to the cooling water and is connected with water in the steam side of the condenser.This condensate collects in the hot well, welded to the bottom of the condensers.

  • 8/4/2019 A Practile Training Report (2)

    56/61

    Typical water cooler condenser

    EJECTORS

    There are two 100% capacity ejectors of the steam eject type. The purpose of the ejector is to

    evacuate air and other non-condensation gases from the condensers and thus maintain the

    vacuum in the condensers. The ejector has three compartments. Steam is supplied generally at a

    pressure of 4.5 to 5kg /cm the three nozzles in the three compartments. Steam expands in the

    nozzle thus giving a high-velocity eject which creates a low-pressure zone in the throat of the

    eject. Since the nozzle box of the ejector is connected to the air pipe from the condenser, the air

    and pressure zone. The working steam which has expanded in volume comes into contact with the

    cluster of tube bundles through which condensate is flowing and gets condensed thus after aiding

    the formation of vacuum. The non-condensing gases of air are further sucked with the next stage

    of the ejector by the second nozzle. The process repeats itself in the third stage also and finally the

    steam-air mixture is exhausted into the atmosphere through the outlet.

    CONDENSATE SYSTEM

    This contains the followingi. Condensate Pumps: 3 per u


Recommended