+ All Categories
Home > Documents > Acid Cleaning in Commissioning

Acid Cleaning in Commissioning

Date post: 03-Jun-2018
Category:
Upload: mhdbas
View: 226 times
Download: 4 times
Share this document with a friend

of 85

Transcript
  • 8/12/2019 Acid Cleaning in Commissioning

    1/85

    3.3 ................................................................................................... 4

    3. ......................................................................................................... 43. ............................................................................ 4

    - ........................................................................................................................... 5.4 ................................................................................................. 5

    .4.4 ................................................................................................... 5.4. ..................................................................................................... 5

    .4.3 ....................................................................................................... 5.4. .............................................................................................................. 5

    .4. ................................................................................................. 5.4. ................................................................................................... 5

    .4.5 ........................................................................................... 5.4.6 ........................................................................................ 5

    . .......................................................................... 6..4 ........................................................................................... 7

  • 8/12/2019 Acid Cleaning in Commissioning

    2/85

    .. ...................................................................................... 10. ................................................................................................................ 10

    ..4 ................................................................................................... 10.. ............................................................................................................ 10

    ..3 .............................................................................. 10.. ............................................................................................................ 10

    .. ...................................................................................... 10 .......................................................................................................... 11 .......................................................................................................... 11

    4.Process ............................................................................................................................ 134.1 Pre-flushing of the boiler system ................................................................................ 13

    4.1.1 Objectives of the flush ......................................................................................... 134.1.2 Flow rates ........................................................................................................... 134.1.3 Water management ............................................................................................. 134.1.4 Water temperature .............................................................................................. 134.1.5 chemical monitoring ............................................................................................ 134.1.6 Performance of the flush ..................................................................................... 144 1 7 Demin Water consumption 14

  • 8/12/2019 Acid Cleaning in Commissioning

    3/85

    4.4.2 Water temperature .............................................................................................. 204.4.3 Chemical monitoring ........................................................................................... 204.4.4 water consumption .............................................................................................. 20

    4.5 Passivation treatment ................................................................................................ 204.5.1 Flow rate ............................................................................................................. 204.5.2 Water temperature .............................................................................................. 214.5.3 Chemical monitoring ........................................................................................... 214.5.4 Water consumption ............................................................................................. 214.5.5 Brief outline of the process .................................................................................. 21

    5.Draining and inspection .................................................................................................... 216. Effluent treatment ............................................................................................................ 22Check Lists ......................................................................................................................... 23Reference drawing No. CKW H004 263 c ......................................................................... 23Chemical Cleaning diagram .............................................................................................. 23Check List No.1 ................................................................................................................... 28Initial valves status for filling of system ................................................................................ 28Check List No.2 ................................................................................................................... 34Pre-flushing of the boiler system ......................................................................................... 34

  • 8/12/2019 Acid Cleaning in Commissioning

    4/85

    7 3.3

    -(HP): RL42

    .- (MP) :RR09

    RR06. 3.

    .

    . 4.4

    RR01 RR01

    4.

    RR02RR03RR04 RR01

  • 8/12/2019 Acid Cleaning in Commissioning

    5/85

    -.4

    .4.4 .

    .4.100600 m3/h.

    .4.3 3 .

    .

    (80 m3/h) ) ( . 600 m3/h 2 .

    . .4.

    50 -7 0C (.)

    4

  • 8/12/2019 Acid Cleaning in Commissioning

    6/85

    600 t/h .

    ) 200 t/h

    CC06 RR06.

    600 t/h . (side-streaming) .

    600 t/hRR07 CC07

    . .

    CC08CC16CC17CC20 .

    .

    .

  • 8/12/2019 Acid Cleaning in Commissioning

    7/85

  • 8/12/2019 Acid Cleaning in Commissioning

    8/85

    300 t/h .

    { . }

    .3 .3.4

    60C. 4.

    .

    60C . 300 t/h.

    .3.3.4

    .

  • 8/12/2019 Acid Cleaning in Commissioning

    9/85

    HFRL40J1 .

    4. % NC90 .

    ) CC05) CC05 8 barCC05. CC03CC04.

    CC31 CC05 1000

    ppm HF4. %

    . . RR06.

    CC068 bar. HF CC32

    .

  • 8/12/2019 Acid Cleaning in Commissioning

    10/85

    300 t/h50 - 60C.

    . ..4

    600 m3/h

    ..5060C

    ..3 10 S/cm- 2.4-

    pH= 6 - 7

    .. 3-:500700 m3..

    50 - 60C 1 - 3 .

    .

  • 8/12/2019 Acid Cleaning in Commissioning

    11/85

    . J2

    . pH

    3.

    ... .

    4.

    .

    .

    .52 % .

  • 8/12/2019 Acid Cleaning in Commissioning

    12/85

    temp drain line RR15 from the steam condensate lines RA 10 Z 021, RA 10 Z 023, RB 15

    Z 023 and RC 10 Z 021.

    Temp. drain line RR16 from the steam condensate line RB 20 Z 0213.3 Acid injection points

    - HP-System

    The injection point for the acid at the feed water line RL42 shall be at the intersection

    f th d i li RL 40 Z 012

  • 8/12/2019 Acid Cleaning in Commissioning

    13/85

    Stage 3:

    Feed water lineseconomizerdrumsuper heaterlive steam linetemp. connectingline RR09cold reheat linere heaterhot reheat linefinal discharge line RR 07main

    drain collector RR01effluent basin.

    3.5 pressure testing of temporarily installed piping

    Prior to the commencement of the chemical cleaning process, the boiler system will be filled

    at low flow (100 t/h).

    As soon as the system is full, and the pressure increases at the pressure gage upstream of

    the final discharge valve CC07, regulate the valve in order to maintain a pressure of 28 bars.

    Then check all temporarily piping thoroughly.

    After checking the chemical cleaning process starts with the initial water flushing.

    4.Process

    4.1 Pre-flushing of the boiler system

    4.1.1 Objectives of the flush

    The objective of the cleaning operation is to remove small quantities of loosely adherent

    sand dust, Welding flux, wood splinters and construction debris.

  • 8/12/2019 Acid Cleaning in Commissioning

    14/85

    Turbidity less than 0.1 units above the incoming water (measured on absorbiometer 425 nm,

    50 mm cuvette).

    Conductivity of less than 10 S/cm above the incoming water.

    4.1.6 Performance of the flush

    Status of valves and flow rates according to Framaborgs check-list

    4.1.7 Demin. Water consumption

    Approx. 3-4 times filling volume = 7501000 m3.

    4.1.8 Brief outline of the process

    After completion of pressure the system is full of water. With boiler feed pump in operation at

    a flow rate of 100 t/h, the entirely system shall be re vented. When venting being performed

    and the system pressure increased, regulate valve CC07 at the end of the system to

    maintain a pressure of 8 bars.

    Then divert flow via drain line RR02 to stage 1.1 outlet with valve CC05.

  • 8/12/2019 Acid Cleaning in Commissioning

    15/85

    When turbidity and conductivity are stable at low level, flush re heater elements at max.

    available of 600 t/h. via outlet drain line RR07 and valve CC07.

    Flush through re heater spray water lines successively.

    When water quality is satisfied flush through all auxiliaries, i.e. CC08, CC16, CC17, and

    CC20, then flush all permanent drains shortly.

    Then shut down boiler feed pumps and refill water storage facilities.

    Then drain evaporator, economizer and drain lines outside of the turbine house.

    4.2 degreasing of boiler system and re-flushing

    Note:

    The HP-Heaters and the feed-water pipe work up to the isolating valve RL 49 S 002 shall be

    degreased separately.

    Th t ill b i l t d b f th t il i t ll d id d i d

  • 8/12/2019 Acid Cleaning in Commissioning

    16/85

    After completion of the soak, the detergent will be displaced with max flow rates of the feed

    water pumps. (600 t/h).

    Then the evaporator will be drained.

    4.2.1 Flowrates

    - The HP heaters will be circulated with a flow of approx. 30 t/h

    - The flow during open circuit treatment will be 300 t/h.

    4.2.3 Detergent injection point

    For the completely filling of the boiler system only the injection point J1 at the feed water line

    RL40 will be used.

    4.2.4 Chemical monitoring

    The degreasing will be considered to have been successfully completed when the effluent

    water on the completion of detergent displacement meets the following criteria:

    Turbidity less than 0.1 units above the incoming water

  • 8/12/2019 Acid Cleaning in Commissioning

    17/85

    During the soaking period the HP feed heaters and the feed water lines will be degreased.

    Before starting the circulating pumps the flow direction will be set up as follows:

    Close valve RL 40 S 002, CC01, open valves CC21/22 in the acid injection line RR21, and

    valve CC26 in temporary line RR24 from feed water line RL20 to the mixing tank.

    Feed water lines and HP Heaters receive a reverse flow.

    The degreasing agentstrisodium phosphate and detergentwill be dosed and circulated

    for a duration of approx. 3 hours. Then the system will be shut down and the degreasing

    agents allowed to soak for 6 hours.

    After completion of the soak degreasing solutions will be displaced from feed water and

    boiler system by means of the feed water pumps with a flow of 300 t/h.after removal a

    high velocity flushing takes place until the turbidity & conductivity is stable at lowest level.

    Then drain evaporator completely.

  • 8/12/2019 Acid Cleaning in Commissioning

    18/85

    This process should also provide an ideal surface in service generation of a passive

    magnetite film.

    4.3.2 Flow rate

    For the cleaning of the boiler (Eco, evaporator and super-heater) a flow of 100/300 t/h if

    required, for the re-heater a flow of 350 t/h is necessary.

    4.3.3 Temperature

    The temperature of the demin. water will be between 50 and 60C.

    4.3.4 Chemical monitoring

    During the acid cleaning, the following chemical monitoring takes place:

    Measurement of the acid concentration by conductivity, iron content by a photometer.

    HF concentration and dissolved Iron will be measured in a two minute interval.

    4.3.4 Water consumption

    Approx. 3 x volume = 750 m3 demin. water (incl. displacement)

  • 8/12/2019 Acid Cleaning in Commissioning

    19/85

    Monitoring of acid concentration and dissolved iron will be dissolved iron will be carried out

    at the sampling point CC31 upstream of the valve CC05, and continue until iron

    concentration drops down to approx. 1000 ppm and HF concentration reaches approx. 1%.

    Then the flow will be diverted through the second and after that through the third water wall.

    Monitoring will be in the same way as for the first water wall.

    After completion, the flow will be directed through super heater and dumped via intermediate

    discharge line RR06.

    A backpressure of 8 bars will be required and maintained with valve CC06.

    Iron and HF will be monitored at the sampling point CC32, and continued until the above

    mentioned criteria will be reached.

    When the effluent meets the criteria, shut down boiler system and allow acid to soak for 1

    2 hours.

  • 8/12/2019 Acid Cleaning in Commissioning

    20/85

    Then the HP & LP relief station and the spray water line RL20 to the HP station, will be

    opened and filled up with fresh acid.

    After completion the feed pump and acid injection pump will be shut down for a soak of

    approx. 2 hours.

    After completion of the soak the bulk of acid will be displaced at a flow of 300 t/h at 50 -

    60C temperature.

    4.4 Conductivity flush

    4.4.1 Flow rate

    600 m3/h

    4.4.2 Water temperature

    50 - 60C

    4.4.3 Chemical monitoring

    Conductivity less than 10S/cm above incoming water.

  • 8/12/2019 Acid Cleaning in Commissioning

    21/85

    4.5.2 Water temperature

    Approx. 40C

    4.5.3 Chemical monitoring

    pH monitoring at the inlet and at the final discharge line

    redox potential measurement at the inlet and at the final discharge line

    Required values:

    pH 10.2

    redox potential: +20 100 mV.

    4.5.4 Water consumption

    Approx. 1.25 x volume: 300 m3

    4.5.5 Brief outline of the process

    At a flow rate of 350 m3/h ammonia solution and hydrogen peroxide will be dosed via the

    injection point J1 at the feed water line RL40.

  • 8/12/2019 Acid Cleaning in Commissioning

    22/85

    Tube samples will cut from the boiler and the residual of oxides will be measured together

    with the client.

    6. Effluent treatmentAll effluent shall be collected in the effluent basin.

    The acid will be neutralized with lime. About 70% of the necessary amount of lime will be

    dosed in to the basin prior to the acid clean. To avoid a settling of lime compressed air shall

    be injected via the air injection equipment.

    The rest of the lime shall be dosed during the acid displacement.

    For proper mixing of the lime and acid, the lime will be directly dosed in to the discharge line

    prior to entry to the effluent basin. The pH of neutralized effluent will be in a range of a pH

    from 79 units. The basin will be emptied by neutral evaporation.

  • 8/12/2019 Acid Cleaning in Commissioning

    23/85

    23

    Check Lists

    Reference drawing No. CKW H004 263 c

    Chemical Cleaning diagram

  • 8/12/2019 Acid Cleaning in Commissioning

    24/85

    24

    Water management table Page 1

    DayNo. Action Time(min) Flowm3/h Storagem3 Consumptionm3 Make upm3 Availablem31 Pre-flushing of the boiler system

    - Filling and venting of boiler system 180 100 1600 300 90 1390- Flushing of stage 1/1 15 400 1390 100 7 1297

    - Flushing of stage 1/2 30 600 1297 300 15 1012

    - Flushing of stage 2 15 600 1012 150 7 869

    - Flushing of stage 3 30 600 869 300 15 584

    - Flushing of all permanent drains 30 100 584 50 15 548

    15 hours to refill water storages up to at least 1000 m3and heated to 60 - 70C for the heating approx. 30 tones of steam (16 bar) are required.

  • 8/12/2019 Acid Cleaning in Commissioning

    25/85

    25

    Water management table Page 2

    DayNo. Action Time(min) Flowm3/h Storagem3 Consumptionm3 Make upm3 Availablem32 Degreasing of boiler system and re-flushing

    - Fill economizer and evaporator with hot wettingagent

    75 100 1000 125 37 912

    - Detergent injection for super-heater & re-heater 30 300 912 150 15 777

    - Soaking phase 480 - 777 - 240 1017

    - Displacement of detergent 45 300 1017 225 22 814

    - Re-flushing to turbidity 45 600 814 450 22 386

    3 & 4 Re-filling and heating of four RFWST

    40 hours to refill water storages up to at least 1600 m3 and heated to 60-70C for the heating approx. 130 tones of steam (16 bar) are required.

  • 8/12/2019 Acid Cleaning in Commissioning

    26/85

    26

    Water management table Page 4

    DayNo. Action Time(min) Flowm3/h Storagem3 Consumptionm3 Make upm3 Availablem35 Acid phase

    - Filling and venting 75 100 1600 125 37 1512- Re-circulating and heating 180 300 1512 - 90 1602

    - Drain Econ. & Evap. 120 - 1602 - 60 1662

    - Fill Econ. & Evap. with hot acid 75 100 1662 125 37 1574

    - Once through treatment of Evap. 30 300 1574 150 15 1439- Once through treatment of super-heater 30 300 1439 150 15 1304

    - Soaking period of HP-boiler part 60 - 1304 - 30 1334- Once through treatment of re-heater 30 350 1334 175 15 1174- Soaking period of re-heater 120 - 1174 - 60 1234

    - Acid displacement 60 300 1234 300 30 964

    - Conductivity flushing 60 600 964 600 30 394

    - Passivation 60 300 394 300 30 124

  • 8/12/2019 Acid Cleaning in Commissioning

    27/85

    27

    Water management table Page 5

    DayNo. Action Time(min) Flowm3/h Storagem3 Consumptionm3 Make upm3 Availablem36 - Soaking period of 3 hours for the passivation

    solution- Draining of the system

    7 InspectionCut tube specimen

    Day 618 hour

  • 8/12/2019 Acid Cleaning in Commissioning

    28/85

    Check List No.1

    Initial valves status for filling of system

    AbbreviationsUCR: Unit Control Room (to operate from UCR)

    RFST: Reserve Feed Water Storage Tank

    FWT: Feed Water Tank, RL 01 B 010

    BFP: Boiler Feed Pump

    W/W: Boiler Water Wall

    BEDT: Boiler Empty Drain Tank, RT 10 B 010

    BDT: Boiler Blow Down Tank, NC 20 B 001

  • 8/12/2019 Acid Cleaning in Commissioning

    29/85

    Procedure: Initial valve status for filling of system Page:

    Pre-condition Valve No. LocationFLR/Level

    Valveposition Purpose

    Temporary drain manifold

    CC 01 Stage 1.1 drain Ground Close Isolation

    CC 30 Close SamplingCC 02 Stage 1.2 Drain Close LHS w/w Head

    CC 03 Close Rear w/w Head

    CC 04 Close RHS w/w head isolation

    CC 05 Close Control

    CC 31 Close Sampling

    CC 50 Open P.I.

    CC 06 Stage 2 Drain Close Control

    CC 32 Close Sampling

    CC 51 Open P.I.

    CC 07 Stage 3 drain Close Control

    CC 33 Close Sampling

    CC 52 Open P.I.

    CC 08 LP By-pass drain Close Control

    CC 34 Close Sampling

    CC 09Connecting line RR09 from HP-part to re-heater

    Open Isolation

    CC 38 Close SamplingCC 10 System warming line Close Control

    CC 11 Close Isolation

    CC 37 Open Leak detection

    CC 53 Open P.I.

    CC 12 Temp. filling pump discharge Ground Close Isolation

    CC 13 Close Isolation

    CC 14 Temp. filling pump suction Close Isolation

    CC 15 Main drain line to effluent basin Open Isolation

  • 8/12/2019 Acid Cleaning in Commissioning

    30/85

    Procedure: Initial valve status for filling of system Page:

    Pre-condition Valve No. LocationFLR/Level

    Valveposition Purpose

    RL 20 S 026 No.5 HP-Heater inlet Open Quick closing 3-way valve

    RL 20 S 240/241 Feed line before No.5 HP-Heater Open Drain (to BEDT)

    RL 20 S 332/356 Close P.I. (RL 20 P 006)RL 20 S 339/340 Feed line after No.5 HP-Heater Close P.I. (RL 20 P 008)

    RL 20 S 042 Close Safety valve

    RL 20 S 230/231 Close Vent (to BEDT)

    RL 20 S 027 No.5 HP-Heater outlet Open Quick Closing Check Valve

    RL 20 S 043/044 Balance line around RL 20 S 027 Open

    RL 20 F 002/3 Feed line after No.5 HP-Heater Open Do not alter Flow meter

    RL 20 S 364/365S 366/367

    S 368/369

    OpenP.I. (RL 20 P 010)

    (RL 20 P 013)

    (RL 20 P 014)RL 20 S 370 Close dp-measurement

    RL 40 S 301 Close

    RL 31 S 001 Feed water Reg. Station UCR Close Isol.

    RL 31 S 004 UCR Close Low-Load Control valve

    RL 31 S 005 Open Isol.

    RL 32 S 001 UCR Close Isol.

    RL 32 S 002 UCR Close By-pass

    RL 32 S 004 UCR Close Full load control valve

    RL 32 S 005 Close Isolator

    RL 32 S 006 Close By-pass

    RL 33 S 001 Close Isol.

    RL 33 S 002 Close By-pass

    RL 33 S 004 UCR Close Full load control valve

    RL 33 S 005 Close Isol.

    RL 33 S 006 Close By-pass

    RL 20 S 245/246 Close Vent

  • 8/12/2019 Acid Cleaning in Commissioning

    31/85

    Procedure: Initial valve status for filling of system Page:

    Pre-condition Valve No. LocationFLR/Level

    Valveposition Purpose

    NA 20 S 338/339S 340/341

    Boiler drum CloseRemote water levelindicator

    NA 20 S 342/343S 344/345

    Close

    NA 20 S 346/347S 348/349

    Close

    NA 20 S 350/351S 352/353

    Close

    NA 20 S 301/302 Close P.I.(NA 20 P 001)

    NA 20 S 303/304 Close P.I. (NA 20 P 002)

    *)

    NA 20 S 305/306

    S 307/308 Blow down line to B.F.V. Close F.I.*)NA 20 S 003 Close NA 20 S 004 Open

    NA 20 S 007 Open

    NA 20 S 363 Close

    NA 20 S 001 Drum over flow to B.D.T. Close

    NA 20 S 002 UCR Open

    NC 10 S 001/002 L.H.S. w/w Headers CloseDrain (to drainheader evap. part)

    NC 17 S 001/002 Close NC 16 S 001/002 Close

    NC 15 S 001/002 R.H.S. w/w Headers Close Drain

    NC 18 S 001/002 Close

    NC 19 S 001/002 Close

    NC 11 S 001/002 Rear w/w headers Close

    NC 12 S 001/002 Close

    NC 13 S 001/002 Close

    NC 14 S 001/002 Close

  • 8/12/2019 Acid Cleaning in Commissioning

    32/85

    Procedure: Initial valve status for filling of system Page:

    Pre-condition Valve No. LocationFLR/Level

    Valveposition Purpose

    NA 90 S 305/306 S/H 3 Outlet header Close P.I. (NA 90 P 002)

    NA 90 S 308/309 Live steam line RA2 Close Sampling (permanent)

    RA 04 S 001 Open Boiler stop valveRA 04 S 002 Open Bypass

    RA 10 S 310/314 Close F.I.

    RA 10 S 312/316 Close

    RA 10 S 311/317 Close

    RA 10 S 313/315 Close

    RA 20 S 010 UCR Close Hp-Bypass station

    RA 10 S 221S 222

    UCR

    CloseOpen

    Drain

    RA 10 S 223S 224

    UCR

    CloseOpen

    Drain

    RA 10 S 302/305 Live steam line Close P.I. (RA 10 P 001)

    RA 10 S 301/304 Close P.I. (RA 10 P 002)

    RA 15 S 332/334 Close P.I. (RA 10 P 003)

    RA 15 S 001 Warm up line Close

    RA 15 S 002 UCR Open

    RL 27 S 201/202 S/H attemperator spray water supply Close Drain

    RL 27 S 002 UCR Open Isol.

    RL 28 S 301/302S 303/304

    Spray water to attempt. 1 Close F.I.

    RL 28 S 305 Open Isol.

    RL 28 S 001 UCR Open Control

    RL 28 S 306 Close Isol.

    RL 28 S 307 Bypass Open Isol.

    RL 28 S 002 UCR Open Control

    RL 28 S 308 Close Isol

  • 8/12/2019 Acid Cleaning in Commissioning

    33/85

    Procedure: Initial valve status for filling of system Page:

    Pre-condition Valve No. LocationFLR/Level

    Valveposition Purpose

    NC 73 S 301/302 R/H 2 outlet headerClose/Open

    Vent

    NC 75 S 001S 002

    R/H 1 outlet headerUCR

    CloseOpen

    Drain

    NC 76 S 001S 002

    R/H 2 inlet headerUCR

    CloseClose

    Drain

    NE 10 S 301/302 R/H 1 inlet header Close P.I. (NE 10 P 001)

    NE 40 S 301/302 R/H 2 outlet Close P.I. (NE 40 P 001)

    NE 40 S 001 Close Safety valve (gagged)

    NE 40 S 002 Close

    RB 10 S 331/332 Hot reheat line Close P.I. (RB 10 P 001)

    RB 15 S 223S 224

    UCR

    CloseOpen

    Drain

    RB 20 S 220S 221

    UCR

    CloseOpen

    Drain

    RL 24 S 201/202 R/H Spray water Close Drain

    RL 24 S 002 UCR Open Isol.

    RL 25 S 301/302S 303/304

    Spray water to L.H.S. R/Hattemperator

    Close F.I. (RL 25 F 001)

    RL 25 S 305 Open Isol.

    RL 25 S 002 UCR Open Control

    RL 25 S 306 Close Isol.

    RL 25 S 307 Bypass Open Isol.

    RL 25 S 003 UCR Open Control

    RL 25 S 308 Close Isol.

    RL 26 S 301/302S 303/304

    Spray water to R.H.S. R/Hattemperator

    Close F.I. (RL 26 F 001)

    RL 26 S 305 Open Isol.

  • 8/12/2019 Acid Cleaning in Commissioning

    34/85

    Check List No.2

    Pre-flushing of the boiler systemNotes on pre-flushing of the boiler

    Aim:

    The aim of the pre-flushing is to remove loose debris from the system.

    This is achieved by flushing the system with water at velocities in the range of 0.3 to 1.4 m/s,

    which will require a flow rate of 600t/h (167Kg/sec).

    The loose debris being removed, increases the turbidity of the water being discharged. To

    arrive an endpoint, chemist stationed at the outlet, monitors continuously the turbidity of the

    water being discharge which decrease as the system is being flushed clean.

    Turbidity is measured in the form of absorbance using a absorbiometer.

    Absorbance can be related back to the suspended debris in the discharge water with the

    following assumption: 0.1 absorbance in a 5 cell is equivalent to 1.4 ppm suspended solids.

    Our theoretical aim is to achieve an analytical endpoint of 0.1 absorbance above the

    incoming water in a 5 cm cell. Our practical end point is to flush till absorbance reading level

    out at a low level.

    Brief outline of the procedure

  • 8/12/2019 Acid Cleaning in Commissioning

    35/85

    35

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Flushing ofstage 1/1 & 1/2

    1. System has beenpressure tested to28 bar

    2. Pressure tripswitch set at 23 bars3. Water storagefacilities full.4. Valves set as perchecklist.5. B.F.Ps temp.filling pump anddemin. watertransfer pumpsready.6. All personnel

    ready and incommunication.7. Boiler system isfull.

    1. Confirm valve CC15 isstill open.

    Valve CC15 must remain openduring all operations!

    Notify staff on valve CC07on starting B.F.P. on leakoff.

    CC07 CC07 Crack CC07 open.

    Increase flow steady to

    100t/h

    .

    Regulate CC07 to maintain

    pressure of 8 bars.

  • 8/12/2019 Acid Cleaning in Commissioning

    36/85

    36

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    NC 86S 001

    NC 86S 001

    NC 82S 001

    NC 82S 001

    NC 83S 001

    NC 83S 001

    NC 84S 001

    NC 84S 001

    NC 85S 001

    NC 85S 001

    When air is expelled

    NC 81NC 82

    NC 83NC 84NC 85S 001

    NC 81NC 82

    NC 83NC 84NC 85S 001

    Vent re-heater elements NC 71S 301

    NC 71S 301

    NC 72S 301

    NC 72S 301

    NC 73S 301

    NC 73S 301

    NC 74S 301

    NC 74S 301

    When air is expelled NC 71NC 72NC 73NC 74S 301

    NC 71NC 72NC 73NC 74S 301

  • 8/12/2019 Acid Cleaning in Commissioning

    37/85

    37

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When venting is completedstart temp. filling pump andfill up feed water tank to

    max. available level.

    CC12 CC12

    Divert flow via stage 1/1drain

    CC01CC05

    CC01CC05 Crack CC05 open.

    CC07 CC07 Regulate CC05 to maintain apressure of 8 bars.

    RL 40S 002

    RL 40S 002

    Increase flow steady to400t/h

    Regulate CC05 to maintain 8 bars.

    Monitor F.W.T.level Note: during flushing with flow rates

    up to 600t/h the temp. filling pumpmust run with max. avail flow rate.When F.W.T. is empty notify staffon the stages drains and run B.F.P.in leak off operation till FWT is filledagain then continue flushing again.

    Chemist to be monitoringwater quality at stage 1/1outlet sampling point CC31.

    When water quality issatisfactory, flush via HPheaters bypass line

    RL 20S 008RL 20

    S 026

    RL 20S 008RL 20

    S 026After 2 mins. flushing viabypass lines

    RL 20S 008RL 20S 026

    RL 20S 008RL 20S 026

  • 8/12/2019 Acid Cleaning in Commissioning

    38/85

    38

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When water quality issatisfactory, divert flow viaeconomizer and water walls

    to stage 1/2 drain.

    CC02

    CC03CC04

    CC02

    CC03CC04

    CC01 CC01

    Increase flow steady to600t/h

    Regulate CC05 to maintainpressure of 8 bars.

    When pressure is stableflush through water wallsseparately

    CC03CC04

    CC03CC04

    Chemist to be monitoringwater quality at outletsampling CC31

    When water quality issatisfactory, flush via 2ndwater wall

    CC03CC02

    CC03CC02

    Divert flow through 3rdwater wall

    CC04CC03

    CC04CC03

    When water quality issatisfactory, decrease flowrate to 150t/h

    CC05 CC05 Close CC05 in

    Flushing of

    stage 2

    Divert flow via super-heater

    elements and stage 2 drain CC06 CC06 Crack CC06 openCC05CC04

    CC05CC04 Regulate CC06 to maintain

    pressure at 8 bars.

    When pressure is stable,flush through super-heaterspray-water lines

    RL 28S 306RL 28S 308

    RL 28S 306RL 28S 308

  • 8/12/2019 Acid Cleaning in Commissioning

    39/85

    39

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    After 5 mins. RL 29S 306RL 29

    S 308

    RL 29S 306RL 29

    S 308RL 28S 306RL 28S 308

    RL 28S 306RL 28S 308

    After 3 mins. RL 29S 306RL 29S 308

    RL 29S 306RL 29S 308

    When flushing of super-heater spray-water lines iscompleted, increase flowsteady to 600t/h

    Regulate CC06 to maintainpressure of 8 bars.

    Monitor FWT level

    Chemist to be monitoringwater quality at stage 2outlet sampling point CC32

    When water quality at outletand/or water storage

    facilities are depleted, notifystaff at CC06 valve ofintention to decrease flowsteady to 150 t/h

    CC06 CC06 Close CC06 in

  • 8/12/2019 Acid Cleaning in Commissioning

    40/85

    40

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Flushing ofStage 3

    When 150 t/h is achieved CC07 CC07

    CC06 CC06 Regulate CC07 to maintainbackpressure of 8 bars.

    When backpressure isstable, increase flow steadyto 400 t/h

    Regulate CC07 to maintainpressure of 8 bars.

    Flush re-heater spray-waterlines RL 25

    S 306RL 25S 308

    RL 25S 306RL 25S 308

    After 5 mins. RL 26

    S 306RL 26S 308

    RL 26

    S 306RL 26S 308

    RL 25S 306RL 25S 308

    RL 25S 306RL 25S 308

    After 3 mins. RL 26S 306RL 26S 308

    RL 26S 306RL 26S 308

    When flushing of re-heaterspray-water lines iscompleted, increase flowsteady to 600 t/h.

    Regulate CC07 to maintainpressure of 8 bars.

    Monitor FWT level

  • 8/12/2019 Acid Cleaning in Commissioning

    41/85

    41

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Chemist to be monitoringwater quality at the stage 3outlet sampling point CC33.

    When water quality isapproaching our endpoint,flush through HP-Bypassstation and back-flush HP-bypass station spray-waterlines

    RA 20S 010

    RL 20S 302

    RL 20

    S 304

    CC20

    RA 20S 010

    RL 20S 302

    RL 20

    S 304

    CC20

    Check water quality atsampling point CC36

    When quality is satisfactoryCC 20

    RL 20S 302

    RL 20S 304

    RA 20A 010

    CC 20

    RL 20S 302

    RL 20S 304

    RA 20A 010

    Flush through LP-bypassstation CC08 CC08 Regulate CC07 to maintain

    pressure of 8 bars.

  • 8/12/2019 Acid Cleaning in Commissioning

    42/85

    42

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When water quality atsampling point CC34upstream of CC08 is

    satisfactory CC08 CC08When water quality at stage3 sampling point CC33 issatisfactory, decrease flowto 100 t/h CC07 CC07 Close CC07 in

    Temp. emptying pump onboiler blow down tankready for use.

    Confirm temp. water walldrain valves CC02, CC03,CC04, closed CC05

    CC25CC05CC25

    Emptying pump discharge

    Monitor water level at blowdown tank, and startemptying tank if necessary.

    During flushing of system drains,listen for steady flow then close.

    Drains in the feed line RL 20S 222/S 223

    RL 20S 222/S 223

    RL 20S 240/S 241

    RL 20S 240/S 241

    RL 24S 201/S 202

    RL 24S 201/S 202

    In re-heater spray-water supply

    RL 27S 201/S 202

    RL 27S 201/S 202

    In super-heater spray-water supply

  • 8/12/2019 Acid Cleaning in Commissioning

    43/85

    43

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Economizer NC 09S 001/S002

    NC 09S 001/S 002

    Drain header for evaporation part

    Lower water wall headers,permanent drains NC 15

    NC 18NC !9S 001/S 002

    NC 15NC 18NC !9S 001/S 002

    RHS w/w headers

    NC 11NC 12NC 13NC 14S 001/

    S 002

    NC 11NC 12NC 13NC 14S 001/

    S 002

    Rear w/w headers

    NC 10NC 16NC 17S 001/S 002

    NC 10NC 16NC 17S 001/S 002

    LHS w/w headers

    Super-heater NC 61NC 62NC 63NC 64NC 65

    S 001/S 002

    NC 61NC 62NC 63NC 64NC 65

    S 001/S 002

    Super-heater drains on drainheader HP part

    Re-heater NC 75NC 76S 001/S 002

    NC 75NC 76S 001/S 002

    Drain header for re-heater part

  • 8/12/2019 Acid Cleaning in Commissioning

    44/85

    44

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Live steam, cold & hot re-heat lines CC16 CC16 Temp. drain manifold

    RA 10

    S 221

    RA 10

    S 221

    RA 10S 223

    RA 10S 223

    RC 10S 229

    RC 10S 229

    RB 15S 223

    RB 15S 223

    CC16 CC16

    Hot re-heat line drain CC17 CC17 Temp. drain manifold

    RB 20S 220 RB 20S 220

    When steady flow RB 20S 220

    RB 20S 220

    CC17 CC17

    Notify staff on CC07 ofintention to shut down,decrease flow steady CC07 Close CC07 in

    Shut down B.F.P. andtemp. filling pump CC07 CC07

    Empty blow down tankcompletely.

    Refill water storagefacilities.

    Heat one feed waterreserve storage tank up60C

  • 8/12/2019 Acid Cleaning in Commissioning

    45/85

    45

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Open drum venting valve,then drain economizer andevaporator completely.

    NC 81S 001/002

    CC02CC03CC04CC05NC 09-88?S001-002

    NC 81S 001/002

    CC02CC03CC04CC05NC09-88?S 001-002

    CC15 CC15 Drain external lines.

  • 8/12/2019 Acid Cleaning in Commissioning

    46/85

    Check list No. 3

    Degreasing and re-flushing of the boiler systemNotes on degreasing and re-flushing of boiler system

    Aim:

    Degreasing by means of 0.050.1% nonionic detergent at 60 - 70C for the boiler system, with

    subsequent period of approx. 8 hours.

    Degreasing by means of 2 -3 % trisodium phosphate and 0.05% ionic detergent for HP-feed water

    lines and HP-heaters 4 & 5 tube-nest, at a temperature of 60 - 70C.

    Brief outline of procedure

    Prior to the commencement of detergent injection economizer and evaporator will be drained.

    At a flow of 100 t/h the boiler will be filled subsequently with hot detergent solution. Overflowing the

    boiler drum , the super-heater and re-heater elements will be flushed with an increased flow rate of 300

    t/h till the boiler system is full of detergent solution. Then the feed water pumps will be shut down for a

    soaking period.

    During the soaking period of boiler system feed water lines and HP-heaters tube-nests shall be

    degreased.

    On completion of the soaking period the degreasing solution will be displaced from feed water line via

  • 8/12/2019 Acid Cleaning in Commissioning

    47/85

    47

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Degreasing andre-flushing ofthe boilersystem

    1.Initial waterflushing completed

    - confirm CC09, CC15,CC05, CC02, CC03, CC04is open.

    2. water storagefacilities full i.e. allRFSTs full at 60-70C

    -confirm CC01 is closed

    -confirm pressure tripswitch is still activated.

    3. FWT full at 60C

    4.BFP, S-F-injectionpumps and temp.filling pump ready.

    Notify staff at drain valveCC05 on starting BFP onleak off.

    5. Detergent ready

    Increase flow steady to 100t/h6. All personnelready and incommunication Commence detergent

    injection7. Economizer andevaporator empty,super-heaters andre-heaters full ofclean demin. water

    Chemist to be monitoringdetergent at stage 1 outletsampling point.

    When detergent is detectedat sampling CC31 CC 05 CC05

    Vent boiler NC 81S 001

    NC 81S 001

    Drum vent

    NC 86S 001

    NC 86S 001

  • 8/12/2019 Acid Cleaning in Commissioning

    48/85

    48

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When economizer andevaporator is full i.e. openstage 1 drain CC05 CC05 Regulate CC05 to maintain

    pressure of 8 bars.

    When detergent is detectedat the boiler vents NC 81

    S 001NC 81S 001

    Increase flow steady to300t/h

    Keep pressure with CC05

    Divert flow through 1stwater wall

    CC 03CC 04

    CC 03CC 04

    When the bulk of debris isdisplaced, divert flow via2ndwater wall. CC 03

    CC02CC03

    CC02When the bulk of debris isdisplaced, divert flow via 3rdwater wall.

    CC 04CC 03

    CC 04CC 03

    When the bulk of debris isdisplaced, divert flow viasuper-heaters and re-heaters to stage 3 drain. CC 07

    CC 05CC04

    CC 07CC 05CC 04

    Regulate CC07 to maintainpressure of 8 bars.

    Vent super-heaters and re-heaters

    NC 82NC 83NC 84NC 85S 001

    NC 82NC 83NC 84NC 85S 001

    Close vent when detergent isdetected.

  • 8/12/2019 Acid Cleaning in Commissioning

    49/85

    49

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    5 mins after flow has beendiverted to super-heaters,open stage 2 drain line. CC 06

    CC07CC 06

    CC 07Regulate CC 06 to maintainpressure of 8 bars.

    Chemist to be monitoringdetergent at stage 2 outletsampling CC 32.

    When the bulk of debris isdisplaced, divert flow to re-heater elements. CC 07

    CC 06CC 07

    CC 06Regulate CC 07 to maintainpressure of 8 bars.

    Chemist to be monitoringdetergent at stage 3 outletsampling point CC 32.

    5 mins after the flow has

    been diverted to re-heaterelements, flush throughHP-Bypass station andback-flush HP-Bypassstation on spray water lines

    RA 20S 010

    RA 20A 010

    RL 20S 302

    RL 20S 302

    RL 20S 304

    RL 20S 304

    CC 20 CC 20When detergent is detectedat sampling point CC 33upstream of the valveCC20

    CC 20 CC 20

  • 8/12/2019 Acid Cleaning in Commissioning

    50/85

    50

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    RL 20S302

    RL 20S302

    RL 20

    S 304

    RL 20

    S 304RA 20S 010

    RA 20S 010

    When detergent is detectedat stage 3 outlet samplingpoint CC 33, flush line toLP-Bypass station CC 08 CC 08

    When detergent is detectedat sampling point CC 34,upstream of the drain valveCC 08 CC 08 CC08

    When the bulk of debris isremoved from re-heaterelements, notify staff onCC07 of intention to shutdown.

    Shut down BFP CC 07 CC 07

    Shut down detergentinjection pump CC 21

    CC 22CC 15

    CC 21CC 22CC 15

    Allow detergent solution tosoak for at least 8 hours orovernight.

  • 8/12/2019 Acid Cleaning in Commissioning

    51/85

    51

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Degreasing ofHP-Heaterstube-nests andfeed-water line.

    Prior to thecommence of thedegreasing, thefeed-water line up to

    valve RL 40 S 002and HP-Heatertube-nests must bedrained.

    The following valvestatus is required: RL 40

    S 002RL 40S 002

    (draining is onlynecessary, if thetemperature in thefeed-water piping is

    less 60C !)

    RL 31S 001

    RL 31

    S 004

    RL 31S 001

    RL 31

    S 004RL 31S 005

    RL 31S 005

    RL 32S 001

    RL 32S 001

    RL 32S 004

    RL 32S 004

    RL 32S 005

    RL 32S 005

    RL 33S 001 RL 33S 001

    RL 33S 004

    RL 33S 004

    RL 33S 005

    RL 33S 005

  • 8/12/2019 Acid Cleaning in Commissioning

    52/85

    52

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Check status of BFPsdischarge valves

    RL 11S 009

    RL 12

    S 009RL 13S 009

    Confirm setting of HP-Heaters in- and outletvalves

    RL 20S 008

    RL 20S 025

    RL 20S 026

    RL 20

    S 027Spray-water line to super-heater RL 27

    S 001RL 27S 001

    Spray-water line to re-heater RL 24

    S 001RL 24S 001

    Open vents RL 20S 214/S 215

    RL 20S 214/S 215

    RL 20S 212/S 213

    RL 20S 212/S 213

    RL 20S 230/S 231

    RL 20S 230/S 231

  • 8/12/2019 Acid Cleaning in Commissioning

    53/85

    53

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    RL 20S 245/S 246

    RL 20S 245/S 246

    Start draining feed-watersystem

    RL 20S 222/S 223

    RL 20S 222/S 223

    RL 20S 240/S 241

    RL 20S 240/S 241

    CC 21CC 22CC 40CC 41

    CC 21CC 22CC 40CC 41

    When system is drainedcompletely RL 20S 222/S 223

    RL 20S 222/S 223

    RL 20S 240/S 241

    RL 20S 240/S 241

    CC 40CC 41

    CC 40CC 41

    Fill system with hot water(60 - 70C) from FWT bygravity.

    RL 11S 009

    RL 11S 009

    When air is expelled andhot water detected at vents

    RL 20S 241/S 215

    RL 20S 241/S 215

    RL 20S 212/S 213

    RL 20S 212/S 213

  • 8/12/2019 Acid Cleaning in Commissioning

    54/85

    54

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    RL 20S 230/S 231

    RL 20S 230/S 231

    RL 20S 245/S 246

    RL 20S 245/S 246

    When system is full RL 11S 009

    RL 11S 009

    Start S-F-pumps andcommence circulation CC 26

    CC26ACC 26CC26A

    Regulate CC26 and CC26A tomaintain a backpressure of 2 bars.

    When backpressure isstable, dose trisodiumphosphate and detergent.

    Chemist to be monitoringP2O5- content in thedegreasing solution.

    When P2O5is stable, stoppump circulation and allowdetergent to soak forapprox. 6 hours.On completion of the soak. CC 21

    CC 22CC 21CC 22

    Drain feed water linepartially by means of thecirculating pump. Thenprepare system (disconnectsuction piping from feedwater line) for re-flushingwith the boiler feed-waterpumps.

  • 8/12/2019 Acid Cleaning in Commissioning

    55/85

    55

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Re-flushing ofthe boilersystem

    1. Water storagefacilities full.

    Prior to re-flushing confirmCC 09 is still open. CC 09

    2. BFPs and temp

    filling pump ready

    Furthermore open CC 15

    and CC 01

    CC 15

    CC 01

    CC 15

    CC 01Confirm pressure tripswitch is still activated.

    Notify personnel on CC 05on starting BFP on leak off.

    CC 05 CC 05 Crack CC05 open

    Monitor FWT level

    Chemist to be monitoringpH and turbidity at stage 1sampling point CC 31

    Increase flow steady to100t/h

    Regulate CC05 to maintainpressure of 8 bars.

    Vent feed water system RL 20S 214/S 215

    RL 20S 214/S 215

    RL 20S 212/S 213

    RL 20S 212/S 213

    RL 20S 230/S 231

    RL 20S 230/S 231

    When air has beenexpelled, divert flow via

    HP-heaters bypass forapprox. 3 mins.

    RL 20

    S 008

    RL 20S 025

    RL 20

    S 008

    RL 20S 025

    RL 20S 026

    RL 20S 026

  • 8/12/2019 Acid Cleaning in Commissioning

    56/85

    56

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    RL 20S 027

    RL 20S 027

    Divert flow via HP-heatertube-nests RL 20

    S 008

    RL 20

    S 008

    RL 20S 025

    RL 20S 025

    RL 20S 026

    RL 20S 026

    RL 20S 027

    RL 20S 027

    When the bulk ofdegreasing solution isdisplaced, increase flow to300t/h

    When the pH value atsampling point CC31 isapproaching 6, divert flowto economizer and waterwalls to stage 1/2 drain.

    CC 02CC 03CC 04

    CC 02CC 03CC 04

    RL 40S 002

    RL 40S 002

    CC 01 CC 01 Regulate CC05 to maintainpressure of 8 bars.

    Vent evaporator NC 81S 001

    NC 81S 001

    NC 86S 001

    NC 86S 001

  • 8/12/2019 Acid Cleaning in Commissioning

    57/85

    57

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When air is expelled NC 81S 001

    NC 81S 001

    NC 86S 001

    NC 86S 001

    Increase flow steady to600t/h

    Regulate CC05 to maintainpressure of 8 bars.

    When the bulk of detergentis displaced fromevaporator water walls,divert flow through eachwater wall separately.

    CC 03CC 04

    CC 03CC04

    When turbidity issatisfactory, divert flow to

    2nd

    , water wall.CC 03

    CC 02CC 03

    CC 02When turbidity issatisfactory, divert flow to3rdwater wall.

    CC 04CC 03

    CC 04CC03

    When turbidity issatisfactory, open waterwalls together.

    CC 02

    CC 03

    CC 02

    CC 03

  • 8/12/2019 Acid Cleaning in Commissioning

    58/85

    58

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Decrease flow steady to100t/hDivert flow via super-heaterand re-heater to stage 3

    outlet drainCC 07

    CC 05CC 07

    CC 05Regulate CC07 to maintainpressure of 8 bars.

    Vent super-heater and re-heater elements

    NC 82NC 83NC 84NC 85S 001

    NC 82NC 83NC 84NC 85S 001

    Close vents when air is

    expelled

    NC 71

    NC 72NC 73

    NC 71

    NC 72NC 73

    Increase flow steady to300t/h

    NC 74S 001

    NC 74S 001 Regulate CC07 to maintain

    pressure of 8 bars.Chemist to be monitoringturbidity at stage 3sampling point CC33

    When the bulk of detergentis displaced from super-heater and re-heaterelements, flush super-heater and re-heater spray-water lines.

    RL 28S 306

    RL 28S 306

    RL 28S 306

    RL 28S 306

    ?

  • 8/12/2019 Acid Cleaning in Commissioning

    59/85

    59

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    After 3 mins. RL 29S 306

    RL 29S 306

    RL 29S 308

    RL 29S 308

    RL 28S 306

    RL 28S 306

    RL 28S 308

    RL 28S 308

    After 2 mins. RL 29S 306

    RL 29S 306

    RL 29S 308

    RL 29S 308

    RL 25S 306

    RL 25S 306

    RL 25S 308

    RL 25S 308

    After 3 min. RL 26S 306

    RL 26S 306

    RL 26S 308

    RL 26S 308

    RL 25S 306

    RL 25S 306

    RL 25S 308

    RL 25S 308

    After 2 mins. RL 26

    S 306

    RL 26

    S 306RL 26S 308

    RL 26S 308

    When flushing of re-heaterspray-water lines iscompleted, increase flowsteady to 600t/h

    Regulate CC07 to maintainpressure of 8 bars.

  • 8/12/2019 Acid Cleaning in Commissioning

    60/85

    60

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When turbidity at stage 3outlet is nearing ourendpoint flush HP-Bypassstation and back-flush HP-

    Bypass station spray-waterlines.

    RA 20S 010

    RA 20S 010

    RL 20S 302

    RL 20S 302

    RL 20S 304

    RL 20S 304

    CC 20 CC 20When water quality atsampling point CC36 is

    satisfactoryCC 20 CC 20

    RL 20S 302

    RL 20S 302

    RL 20S 304

    RL 20S 304

    RA 20S 010

    RA 20S 010

    Flush LP-Bypass station CC 08 CC 08

    When water quality atsampling point CC34 is

    satisfactory CC 08 CC 08Flush stage 2 drain line CC 06 CC 06 Crack CC06 open

    Regulate CC07 to maintainpressure at 8 bars.

  • 8/12/2019 Acid Cleaning in Commissioning

    61/85

    61

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When water at stage 3outlet drain meets theircriteria, decrease flowsteady shut system down.

    CC 07CC 15CC 02CC 03CC 04

    CC 07CC 15CC 02CC 03CC 04

    Drain evaporator !

  • 8/12/2019 Acid Cleaning in Commissioning

    62/85

    Check list No.4

    Heating up boiler systemNotes: on heating up boiler system

    Aim:

    Heating of the iron masses of the boiler system by means of circulating hot water across the system till

    a metal temperature of approx. 60C is achieved.

    Brief outline of the procedure

    With the feed water tank full of hot water, the system will be circulated by means of a boiler feed pump

    at a flow rate of 300t/h. the flow will be directed as follows:

    BPF - feed water lineeconomizer or evaporator water wallsdrumsuper-heaterlive steam line

    temp. piping RR09cold re-heat linere-heaterhot re-heat linetemp. piping RR07 and RR10

    main condensate piping RM 20feed water tank.

    During circulation, auxiliary steam from unit 1/2 or from auxiliary boiler will be injected into feed water

    tank continuously.

    As soon as the desired temperature is achieved, the steam injection will be stopped and the pump shut

    down.

    Prior to the subsequent acid treatment the economizer and evaporator shall be drained completely.

  • 8/12/2019 Acid Cleaning in Commissioning

    63/85

    63

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Circulation andheating of boilersystem 1. Boiler is filled with

    clean water- Confirm CC 09 is stillopen.

    2.FWT is full at60C

    - Confirm pressure tripswitch is still activated

    3. RFST are full at60C

    Prior of staring the BFP setvalves as follows: CC 15 CC 15

    4. Auxiliary steamready

    5. BFPs ready

    6. All personnelready and in

    communicationNotify staff on valve CC07of intention to start BFP onleak off CC 07 CC 07 Crack CC07 open

    Increase flow steady to100t/h

    Regulate CC07 to maintain apressure of 8 bars.

    Vent boiler system NC 81NC 86S 001

    NC 81NC 86S 001

    NC 82NC 83NC 84NC 85S 001

    NC 82NC 83NC 84NC 85S 001

    Super-heater vents

  • 8/12/2019 Acid Cleaning in Commissioning

    64/85

    64

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    NC 71NC 72NC 73NC 74

    S 001

    NC 71NC 72NC 73NC 74

    S 001

    Re-heater vents

    When air is expelled closethe vents.

    Change flow from oncethrough to re-circulationmethod CC 11

    CC 10CC 11CC 10 Crack CC01 open

    CC 07 CC 07 Regulate CC10 to maintain apressure of 8 bars.

    When system pressure is

    stable, increase flow steadyto 300t/h

    After 1 hour of circulatingvia economizer, drum,super-heaters and re-heater divert flow via lowerevaporator water wallheaders

    CC 01RL 42S 002

    CC 01RL 42S 002

    Check wall temperature offeed water line, live steamline, cold & hot re-heat line.

    When wall temperatureapproaching 60C, divertflow via economizer again

    RL 40S 002

    CC 01

    RL 40S 002

    CC 01

  • 8/12/2019 Acid Cleaning in Commissioning

    65/85

    65

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When wall temperature ofapprox. 60C, is achieved,shut down circulation.

    CC 37

    CC10CC 11

    CC 37

    CC10CC 11 Leak detection between CC10 and

    CC 11

    Drain economizer andevaporator.Open boiler vent NC 81

    NC 86S 001

    NC 81NC 86S 001

    CC 01CC 05

    CC 01CC 05 Crack CC05 open

    When draining hasstopped, open allpermanent evaporator w/wdrains.

    NC 10NC 11

    NC 10NC 11

    Monitor water level on blowdown tank and start drainpump if necessary

    NC 12NC 13NC 14NC 15NC 16NC 17NC 18NC 19S 001/

    S 002

    NC 12NC 13NC 14NC 15NC 16NC 17NC 18NC 19S 001/

    S 002

    NA 20S 003

    NA 20S 003

    Boiler drum blow down lineisolation.

  • 8/12/2019 Acid Cleaning in Commissioning

    66/85

    66

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When evaporator is drainedcompletely

    NC 10NC 19

    S 001

    NC 10NC 19

    S 001

    NA 20S 003

    NA 20S 003

    CC 05CC 01

    CC 05CC 01

  • 8/12/2019 Acid Cleaning in Commissioning

    67/85

    Check No.5

    Acid cleaning phase

    Notes on HF acid phase

    Aim:

    To provide chemically cleaned surfaces free of any loose or adherent mill scale or material.

    Briefly outline of the procedure

    Economizer and evaporator empty, super-heater, re-heater and steam lines full of clean demin. water.

    At a flow rate of 100t/h at 60C, inhibited acid will be dosed via injection point J1 in the feed water line

    RL 40 till the economizer and evaporator is filled with acid at a strength of approx. 1%.

    After filling, the flow shall be increased to 300t/h and directed via each water wall to the stage 1 outlet

    drain.

    When iron levels being monitored at the outlet have past their peak and fresh acid being detected, the

    acid will be diverted via boiler drum and saturated steam off takes to the super-heaters and dumpedvia stage 2 outlet drain.

    When iron and acid meets their above mentioned criteria shut down carefully.

    Allow acid to soak for approx. 1 hour to dissolve suspended matters.

    On completion of the soak, start B.F.P. and increase flow steady to 350t/h. The flow is directed in such

    way that the fresh acid from economizer and evaporator will be pushed through re-heater elements

  • 8/12/2019 Acid Cleaning in Commissioning

    68/85

    68

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Acid cleaningphase

    1. RFST full at 60C - Confirm CC09 is still open CC092. FWT full at 60C - Confirm pressure trip

    switch is still activated MSV

    3. acid ready

    4. BFPs ready

    - prior to thecommencement of acidphase, confirm thefollowing valve attitudes:

    5. All personnelready and incommunication

    CC 01CC 02CC 03CC 04

    CC01 economizer "

    6. Lime dosingstation ready

    CC 05CC 06CC 07

    Drain stage 1.2Drain stage 2 3

    7. Economizer and

    evaporatorcompletely drained.

    CC 08

    CC 10CC 11

    HP-bypass drain

    8. Super-heater, re-heaters and steamlines full of cleandemin. water

    CC 16CC 17CC 21

    CC 37CC 15

    CC10CC11 Soak away pit

    pumpRFWT

    CC 22CC22A

    J1 CC 23

    CC 24CC 20

    CC 40CC 41

    J2 J2

    RR14 CC36

    NC 81NC 86S 001

    "

    A t l l

  • 8/12/2019 Acid Cleaning in Commissioning

    69/85

    69

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Notify staff at valve CC05of intention to start BFP inleak off CC 05

    CC 05 Crack CC05

    Increase flow steady to100t/hCommence injection of1.4t/h inhibited hydrofluoricacid.

    CC 21

    CC21

    Chemist to be monitoringHF-inlet strength atsampling point NC 09

    Eco-inlet drain on boiler basement.When acid strength isregulated to 1%, monitor

    acid at stage 1 outletsampling point CC31When strong acid isdetected

    CC 05 CC 05When pressure increase atstage 1 outlet CC 05 CC 05 Regulate CC05 to maintain a

    pressure of 8 bars.Close drum vents when airis expelled NC 81

    NC 86

    S 001

    NC 81NC 86

    S 001Commence line dosing toeffluent pit.

    Commence re-filling ofFWT with temp. fillingpump.Increase flow steady to Regulate CC05 to maintain

    A t l l

  • 8/12/2019 Acid Cleaning in Commissioning

    70/85

    70

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    300t/h pressure of 8 bars.

    When backpressure isstable, divert acid to 1stwater wall.

    CC 03CC 04

    CC 03CC 04

    Chemist to be monitoringacid and iron at stage 1outlet sampling valve CC31When iron levels havepassed their peaks, divertacid via 2ndwater wall. CC 03

    CC 02CC 03

    CC 02When iron levels havepassed their peaks, divertacid via 3rdwater wall. CC 04

    CC 03CC 04

    CC 03

    When iron levels havepassed their peaks, divertacid to super-heaterelements and stage 2 outlet CC 06

    CC 05CC 04

    CC 06CC 05CC 04

    Regulate CC06 to maintainpressure of 8 bars.

    Vent super-heaterelements

    NC 82NC 83NC 84NC 85S 301

    NC 82NC 83NC 84NC 85S 301

    When air is expelled NC 82NC 83NC 84NC 85S 301

    NC 82NC 83NC 84NC 85S 301

    A t l l

  • 8/12/2019 Acid Cleaning in Commissioning

    71/85

    71

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Chemist to be monitoringiron and acid at stage 2outlet sampling point CC 32

    When iron levels have

    passed their peak,decrease flow carefully toleak off operation CC 06 CC 06 Close CC 06 in

    Shut down BFPShut down acid injectionpumpShut down lime dosing

    Allow acid to soak for atleast 1 hour

    CC 15CC 21CC 22CC22A

    CC 15CC 21CC 22CC22A

    To avoid penetration ofacid into feed water system RL40S 002

    RL40S 002

    During soaking timefor the HP-Boilerpart confirm:1- Fill FWT withwater at 60C2- Before startingthe re-heater acidphase=1000 m3water at 60C must

    be available3- acid ready

    RL 31/32/ 33S 005

    RL 31/32/ 33S 005

    Isolation downstream feed watercontrol valves.

    Actual valve

  • 8/12/2019 Acid Cleaning in Commissioning

    72/85

    72

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Prior to the commencementof re-heater acid clean setvalves as follows:

    CC 02CC 03CC 04

    CC 24CC 15RL 33S 005

    CC 02CC 03CC 04

    CC 24CC 15RL 33S 005

    Confirm CC 09 is still open

    Confirm pressure switchtrip is still activated.

    Notify staff at valve CC 07of intention to start BFP onleak off

    RL 40S 002CC 07

    RL 40S 002CC 07

    Crack CC 07 open.

    Increase flow steady to350t/h

    Commence lime dosing toeffluent basinVent re-heater elements NC 71

    NC 72NC 73NC 74S 301

    NC 71NC 72NC 73NC 74S 301

    When air is expelled NC 71NC 72NC 73

    NC 74S 301

    NC 71NC 72NC 73

    NC 74S 301

    After 3 mins. Of steady flowof 350t/h CC 01

    RL 40S 002

    CC 01RL 40S 002

    Actual valve

  • 8/12/2019 Acid Cleaning in Commissioning

    73/85

    73

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Chemist to be monitoringacid strength at samplingpoint CC 38 before cold re-heat line

    When acid strength dropdown, start acid injectionpump and dose via J2 CC 23 CC 23

    Chemist to be monitoringacid and iron at stage 3outlet sampling point CC33When acid is detected treatHP-Bypass line and HP-Bypass spray-water linewith acid.

    RA 20S 010

    RL 20S 002

    RL 20S 004

    CC 20

    RA 20S 010

    RL 20S 002

    RL 20S 004

    CC 20When acid is detected assampling point CC 36upstream of the valveCC20

    CC 20

    RL 20S 002

    RL 20

    S 004

    RA 20S 010

    CC 20

    RL 20S 002

    RL 20

    S 004

    RA 20S 010

    Actual valve

  • 8/12/2019 Acid Cleaning in Commissioning

    74/85

    74

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When iron levels have pasttheir peak at stage 3sampling point, treat LP-Bypass line CC 08 CC 08

    When acid is detected atsampling point CC34upstream of the valveCC08 CC 08 CC 08

    Notify staff at CC 07 ofintention to shut down.

    Decrease flow steady toleak off operation CC 07 CC 07

    Shut down BFP

    Shut down acid injectionpump

    CC 23CC 24

    CC 23CC 24

    Shut down lime dosingAllow acid to soak for atleast 2 hours in the re-heater elements CC 15 CC 15

  • 8/12/2019 Acid Cleaning in Commissioning

    75/85

    Check list No.6

    Displacement of acid and flushing to conductivityNotes on displacement of acid and flushing to conductivity

    Aim:

    To displace acid from boiler system completely and to achieve a final conductivity of less than 10

    S/cm above the incoming water.

    Brief outline of the procedure

    The HP-boiler part is full of slightly acidic water: the re-heater is full of acid at a strength of 1%.

    After starting the BFPs the acid will be displaced at a flow of 300t/h. during displacement all system

    vents, drain, dead legs etc. must be rinsed thoroughly, then conductivity flushing with up to max. load

    of two feed pumps takes place.

    Actual valve

  • 8/12/2019 Acid Cleaning in Commissioning

    76/85

    76

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Displacementof acid andflushing toconductivity

    1. Two RFST arefull at ambienttemperature.

    - Confirm CC09 is still open CC09

    2. FWT full at amb.

    Temperature

    - Confirm pressure trip

    switch is still activated

    MSV 3. BFPs ready Prior to the commencement

    of the flush

    4. Temp.filling pumpready

    Confirm the following valveattitudes:

    RL 40S 002

    5. Lime dosingstation ready

    CC 01CC 02CC 03CC 04

    CC 05Notify staff at CC 07 ofintention to start BFP on

    leak off. CC 07 CC 07 Crack CC 07 openIncrease flow steady to300t/h

    Regulate CC 07 to maintainpressure of 8 bars.

    Vent boiler and super-heaters

    NC 81NC 86S 001

    NC 81NC 86S 001

    Check pH at venting through, closevent when pH= 5-6 units.

    Chemist to be monitoringiron and acid at stage 3outlet sampling point CC33

    NC 82NC 83

    NC 84NC 85NC 86S 001

    NC 82NC 83

    NC 84NC 85NC 86S 001

    Commence lime dosing toeffluent basin.Rinse permanent drains

    Actual valveA ti

  • 8/12/2019 Acid Cleaning in Commissioning

    77/85

    77

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Open drains for ca. 1 min.,check steady flow acrossthe valve then close.Monitor water level at blow

    down tank.Start tank emptying pump ifnecessary

    RL 40S 205/S 206

    RL 40S 205/S 206

    NC 09S 001/S 002

    NC 09S 001/S 002

    ECO drain

    NC 15NC 18NC 19S 001/S 002

    NC 15NC 18NC 19S 001/S 002

    NC 11NC 12NC 13NC 14S 001/S 002

    NC 11NC 12NC 13NC 14S 001/S 002

    NC 10

    NC 16NC 17S 001/S 002

    NC 10

    NC 16NC 17S 001/S 002

    Actual valveA ti

  • 8/12/2019 Acid Cleaning in Commissioning

    78/85

    78

    Phase Pre-condition Performances

    Actual valveattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    NC 61NC 62NC 63NC 64

    NC 65S 001/S 002

    NC 61NC 62NC 63NC 64

    NC 65S 001/S 002

    Flush super-heater spray-water lines RL 28

    S 306RL 28S 306

    RL 28S 308

    RL 28S 308

    RL 29S 306

    RL 29S 306

    RL 29

    S 308

    RL 29

    S 308After 3 mins. RL 28

    S 306RL 28S 306

    RL 28S 308

    RL 28S 308

    RL 29S 306

    RL 29S 306

    RL 29S 308

    RL 29S 308

    When bulk of acid is

    removed from re-heaterelements, flush re-heaterspray-water lines

    RL 25S 306

    RL 25S 306

    RL 25S 308

    RL 25S 308

    RL 26S 306

    RL 26S 306

    Actual valveAction

  • 8/12/2019 Acid Cleaning in Commissioning

    79/85

    79

    Phase Pre-condition Performancesattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    RL 26S 308

    RL 26S 308

    After 3 mins. RL 25S 306

    RL 25S 306

    RL 25S 308

    RL 25S 308

    RL 26S 306

    RL 26S 306

    RL 26S 308

    RL 26S 308

    Flush re-heater vents NC 71NC 72NC 73NC 74NC 75

    S 301

    NC 71NC 72NC 73NC 74NC 75

    S 301

    Check pH at venting trough closevent when pH= 5-6 units

    Increase flow steady to 600t/h

    Regulate CC 07 to maintainpressure of 8 bars

    After 5 mins. of steady flowof 600 t/h decrease flow to300 t/hDivert flow to lower waterwall headers CC 02

    CC 03CC 04CC 01

    CC 02CC 03CC 04CC 01

    RL 40S 002

    RL 40S 002

    When pressure is stable atCC 07, divert flow via 1st.water wall.

    CC 03CC 04

    CC 03CC 04

    Increase flow steady to 600t/h

    Regulate CC 07 to maintainpressure of 8 bars.

    Actual valveAction

  • 8/12/2019 Acid Cleaning in Commissioning

    80/85

    80

    Phase Pre-condition Performancesattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    After 3 min. at max. load,divert flow via 2ndwaterwall.

    CC 03CC 02

    CC 03CC 02

    After 3 min. at max. load,

    divert flow via 3rd. waterwall.

    CC 04CC 03

    CC 04CC 03

    Decrease flow to 300 t/h Regulate CC 07 to maintainpressure at 8 bars.

    When backpressure isstable, divert flow via stage2 outlet CC 06

    CC 07CC 06

    CC 07Regulate CC 06 to maintainpressure at 8 bars.

    Chemist to be monitoringconductivity at stage 2outlet sampling point CC 32

    Increase flow steady to 600t/h

    Regulate CC 06 to maintainpressure of 8 bars.

    When conductivity is lessthan 20 S/cm divert flowvia stage 3 outlet

    CC 07CC 06

    CC 07CC 06

    Chemist to be monitoringconductivity at stage 3outlet sampling point CC 33

    When turbidity isapproaching its endpoint,flush via HP-bypass lineand back-flush HP-Bypassspray-water lines

    RA 20S 010

    RL 20S 302

    RA 20S 010

    RL 20S 302

    RL 20S 304

    RL 20S 304

    CC 20 CC 20

    Actual valveAction

  • 8/12/2019 Acid Cleaning in Commissioning

    81/85

    81

    Phase Pre-condition Performancesattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    After 3 mins. RA 20S 010

    RA 20S 010

    RL 20S 302

    RL 20S 302

    RL 20S 304

    RL 20S 304

    CC 20 CC 20

    Open LP-Bypass line CC 08 CC 08

    After 3 mins. CC 08 CC 08

    When conductivity is lessthan 10S/cm aboveincoming water, decreaseflow steady to 150 t/h

    Regulate CC 07 to maintainpressure at 8 bars.

    Flush drains in steam lines CC 16 CC 16

    Flush drains for app. 1 min.check flow across thevalves

    RA 10S 221

    RA 10S 221

    RA 10S 223

    RA 10S 223

    RC 10S 229

    RC 10S 229

    RB 15S 223

    RB 15S 223

    CC 17 CC 17

    RB 20

    S 220

    RB 20

    S 220Notify staff on CC 07 ofintention to shut down

    Decrease flow steady shutdown BFPs

    CC 07CC 15

    CC 07CC 15

  • 8/12/2019 Acid Cleaning in Commissioning

    82/85

    Check list No.7

    Passivating treatmentNotes on passivation treatment

    Aim:

    To passivate the strongly activated metal surfaces and to form by means of Hydrogen Peroxide dosing

    an extremely thin coating of iron oxide to prevent post-rusting.

    Brief outline of the procedure

    With the boiler system full of clean demin. water, Ammonia and Hydrogen Peroxide will be dosed at a

    BFP flow rate of 300 t/h. the passivation chemicals shall be dosed via injection point J1 in the feed

    water line RL40. The water temperature must not exceed 40C.

    The whole boiler system will be filled with passivation solution at a pH of greater than 10.2 and a

    positive redox potential reading at a range of +20 +100 mV.

    As soon as the reading will be monitored at stage 3 outlet drain, the system will be shut down. A

    subsequent soaking period of at least 3 hours is necessary before draining the system. After draining

    the system will be prepared for blow-through.

    Actual valveAction

  • 8/12/2019 Acid Cleaning in Commissioning

    83/85

    83

    Phase Pre-condition Performancesattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    Passivationtreatment

    1. one RFST full at40C.

    - Confirm CC09 is still open

    2. FWT full at 40Ctemperature

    - Confirm pressure tripswitch is still activated

    3. Ammonia andperoxide ready

    4. BFP ready Confirm the following valveattitudes:

    CC 15CC 01CC 02CC 03CC 04

    CC 15CC 01CC 02CC 03CC 04

    RL 40S 002

    RL 40S 002

    Notify staff at valve CC 07

    of intention to start BFP onleak off CC 07 CC 07 Crack CC07 openIncrease flow steady to 100t/h Regulate CC07 to maintain

    pressure of 8 barsVent boiler systemcompletely

    NC 81NC 86S 001

    NC 81NC 86S 001

    NC 82NC 83NC 84NC 85NC 86S 001

    NC 82NC 83NC 84NC 85NC 86S 001

    Actual valvei d

    Action

  • 8/12/2019 Acid Cleaning in Commissioning

    84/85

    84

    Phase Pre-condition Performancesattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    NC 71NC 72NC 73NC 74

    NC 75S 301

    NC 71NC 72NC 73NC 74

    NC 75S 301

    When air is expelled. Closevents

    Increase flow steady to 300t/h

    Regulate CC 07 to maintainpressure at 8 bars.

    Commence injection ofammonia and hydrogenperoxide.

    Chemist to be monitoringpH and redox potential atinlet sampling point NC09(?)

    After 5 mins. of steady flowat 350 t/h, divert flow to thelower evap. water wallheaders, one wall afterother.

    CC 01CC 02

    CC 01CC 02

    After 5 mins. divert flow via2nd. water wall. CC 03

    CC 02CC 03

    CC 02

    After 5 mins. divert flowthrough 3rd. water wall. CC 04CC 03

    CC 04CC 03

    Chemist to be monitoringpH and redox potential atstage 3 outlet samplingpoint CC33

    Actual valvettit d

    Action

  • 8/12/2019 Acid Cleaning in Commissioning

    85/85

    Phase Pre-condition Performancesattitude

    Action

    Floor CommentsValvesclosed

    Valvesopen

    Openvalve

    Closevalve

    When ammonia andperoxide is detected at thesampling point, flush viaHP-Bypass station and

    back-flush HP-Bypassspray-water lines.

    RA 20S 010

    RL 20S 302

    RA 20S 010

    RL 20S 302

    RL 20S 304

    RL 20S 304

    CC 20 CC 20When ammonia andperoxide is detected atsampling point CC 36upstream of the valveCC20

    CC 20

    RL 20S 302

    RL 20S 302

    RL 20S 304

    RL 20S 304

    .


Recommended