+ All Categories
Home > Documents > Adb Bd if 96 15 en Scannedimage.011(1)

Adb Bd if 96 15 en Scannedimage.011(1)

Date post: 07-Jul-2018
Category:
Upload: jaswinder-sohal
View: 213 times
Download: 0 times
Share this document with a friend

of 49

Transcript
  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    1/49

    91

    AFRICAN DEVELOPM ENT BANK

    REPUBLIC OF CONGO

    PROJECT COM PLETION REPORT

    REHABILITATION OF DRINKING W ATER SUPPLY

    INSTALLATIONS IN BM ZZAVILLE

    DEPARTM ENT OF INFM STRUCTURE AND INDUSTRY

    SOUTH REGION M ARCH 1995

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    2/49

    *

    TABLE OF CONTENTS

    BASIC INFORM ATION

    1.

    Pages

    i-v

    1

    1

    1

    1

    2

    INTRODUCTION

    1.1 Geographic Setting

    1.2 Bank Group's Commitment in the Sector

    1.3 Project Background

    1.4 Sources of Infonnation

    SECTOM L OBJECTIVE AND PROJECT AlM

    PROJECT DESIGN

    3. 1 Origin of Project

    3.2 Preparation, Evaluation, Negotiation and Approval

    PROJECT IM PLEM ENTATION

    4. 1 Entry into Force of the Loan and Start-up

    of Project

    4.2 M odifications

    4.3 Implementation Schedule

    4.4 Procurem ent of Goods and Services

    4.5 Costs and Disbursements

    OPERATIONAL PERFORM ANCE

    5. 1 The Contract

    5. 1 Role of the Project

    5.3 Other Factors

    INSTITUTIONAL PERFORM ANCE

    6. 1 Legal and lnstitutional Framework

    6.2 Organization and M anagement

    6.3 Personnel and Training

    6.4 Accounting and Auditing

    6.5 Tariffs

    6.6 Billing and Collection

    6.7 Perfonnance of Consultants, Entrepreneurs

    and Suppliers

    6.

    6

    6

    7

    7

    8

    12

    13

    13

    14

    14

    14

    15

    16

    16

    17

    18

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    3/49

    FINANCIAL PERFORM ANCE

    7. 1 Operational Analysis

    7.2 Analysis of Financial Structure

    7.3 Financial Rate of Return

    7.4 Financial Conditions and Clauses

    19

    19

    20

    20

    21

    22

    22

    22

    23

    24

    8. ECON9MIC AND SOCIAL PERFORMANCES

    8.1 Econom ic Perform ances

    8.2 Social Incidences

    9. SUSTAINABILITY

    10. PERFORM ANCE OF THE BANK AND TI'1E BORROW ER

    10. 1 General and Specific Performance

    10.2 W orking Relations

    CONCLUSIONS AND LESSONS

    24

    25

    26

    26

    26

    11.1 Conclusions

    11.2 Lessons Learned from the Project

    MAPIS)

    ANNEXES

    This report has beén written by Messrs HOUSSEIN Y.A (Hydraulics Engineer) and Keba 'BA

    (Consultant. Financial Analyst) following their mission to CONGO in February 1995. Al1

    enquiries should be addressed to Mr. S.C DESAI, S1SI.2 Ext.4120

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    4/49

    r

    EOUIVALENTS. ACRONYM S AND ABBREVIATIONS

    CURRENCIES

    (1st Quarter 1995)

    Currrncy unit

    UA 1

    UA 1

    UA 1

    CFA.Franc

    '

    CFA .F 780.436

    US$ 1.45985

    FF 7.80436

    On evaluation

    (3rd Quarter 1982)

    UA 1

    UA 1

    UA 1

    W EIGHTS AND M EASURES

    ha

    km

    I/d/inh

    lm

    m/h

    m 3/h

    m 3/d

    m3/s

    m m

    hectare

    kilometre

    litres per day per inhabitant

    linear metre

    metre prr hour

    cubic metre per hour

    cubic metre per day

    cubic metre per second

    m illimetre

    CFA.F 372.945

    US$ 1.00601

    'FF 7.4589

    ABBREVIATIONS

    Aid and Cooperation Fund

    African Developm ent Bank

    Competitive Bidding

    Caisse Française de Développement

    Drinking W ater Supply

    Drinking Water Sgpjly and Sanitation

    European Development Fund

    German Technical Cobperation Agency

    International Fund for Agricul'ural Development

    ACF

    ADB

    CB

    CFD

    DW S

    DW SS

    EDF

    GTZ

    IFAD

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    5/49

    k

    IRRI

    JIC)V

    fD

    j

    PC:

    TD 1

    ENPN

    N EF

    i

    i

    = Internal Rate of Rettlrn

    Japanese lnternational Cooperation Agency

    =

    M edium Voltage

    Not Determined

    =

    Project Completion Report

    Tender Document

    =

    Société. Nationale de Distribution d'Eatt

    = Uàited. Nations Children's Fuhb

    ' Fiscal Year

    1st January - 31 December

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    6/49

    LB T 0F ANNEXES

    NO Description N O of pages

    Map of Congo / project qrea

    lmplementation Schedule

    Comparative table of costs

    Loan granting conditions

    Comparative status of SNDE'S income statement

    Surnm ary of SNDE'S balance sheets

    3

    4

    5

    6

    Assumptions of financial projections

    Calculation table of IFRR

    Calculation table of IERR

    8

    9 1

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    7/49

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    8/49

    =>

    BASIC PROJECT INFORM ATION

    1.

    2.

    COUNTRY

    PROJECT

    Republiq of Congo

    Rehabilitation of drinking water supply installations

    in Brazzaville

    CS/CN/SP/83/010

    Govermnent of Congo

    3.

    4.

    5.

    LOAN NO

    BORROW ER

    EXECUTING AGENCY Société Nationale de Distribution d'Fmu (SNDE)

    A. LOAN

    Amount (in UA million)

    Interest rate

    Period of reimbursement

    Grace period

    Date negotiated

    Date approved

    Date signed

    Entry into force

    B. PROJECT INFORMATION

    1.

    2.

    3.

    4.

    5.

    6.

    7.

    8.

    EVALUATION

    26.59

    CURRENT

    23.84

    9.50%

    20 years

    3 years

    18/11/82

    21/12/82

    07/01/83

    M ay 1983

    EVALUATION

    39.52

    CURRENT

    31.010.

    2.

    Total cost (in UA million)

    Financing plan (in UA million)

    ADB

    Govt.

    Total

    F.E L.C Total

    26.59 - 26.59 '

    12.93 12.93

    26.59 12.93 39.52

    F .E

    23.84

    23.84

    L.C Total

    -

    23.84

    7. 17 7. 17

    7 . 17 31.01

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    9/49

    3.

    4

    5.

    6.

    j

    2.

    3.

    4.

    5.

    6.

    7.

    8.

    9.

    ii

    EVALUATION CURRENT

    Effective date of 1st disb. 13/04/83

    Effectkve date of last disb. 31/12/94

    1tart

    up of project

    implelj ntation activities April 1983 7/07/83

    Completion of project

    impleml entation activi

    ties April 1985 07/90

    C. PERFORM ANCE INDICATORS

    EVALUATION CURRENT

    Bâlànce % 10%

    Dèlay lin relation to schedule

    -

    Dela' in rel. to entry into force 3 month:

    -

    Delaly in rel. ttj completion date 60 months

    -

    Delal in rel. to last disbursement 34 months

    Numbpr of extensions of deadline

    at lajt disbursement two (2)

    Status o'f project execution Compléted

    List of verifiable indicators

    nd stlges of completion

    (% of envisaged stages): Evaluation Current

    Production (m3/d) 90,000 61,000

    -

    Subscribers 17,038 50,000

    lnstitutional perfbrmance Inadequate

    Petfôxance of firms satisfactory

    Ierforrizance of Consultants Inadequate

    EVALUATION CURRENT

    IFRR (%) 20.48 7.54

    lERR (%) nd 18

    48

    D . M ISSIONS

    I DATE Noof pers. > G

    -

    Iden 'ification nd nb nd

    l d ndreparation nd n

    1 ion 09/1982 2 Eng

    .

    + Fin. an. 4valyat

    - M onitoring nd nd nd

    supelvision 04/1984 Eng. 2

    12/1986 Eng. + Fin. an. 4

    04/1987 ' Eng. + Fin. an. 4

    02/1995 Eng. + Fin. an. 4

    < N 'U

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    10/49

    ' ' - 1ll -

    . DISBURSEM ENT

    (in UA million)

    -

    Total disbursed

    -

    Balance

    -

    Amount reallocated

    -

    Amount cancelled

    -

    Annual disbursement

    (in UA million)

    23.836

    2.754

    2.693 (PARESO)

    0.061

    1983 1984 1985 1986 1987 1988 1989 1990 1994 Total

    4.46 8.71 6.76 3.03 0.38 0.31 0.09 0.04 0.06 23.84

    2.45 2.77 - 0.69 - 0.64 0.62 - 7. 17

    6.91 11.48 6.76 3.72 0.38 0.95 0.71 0.04 0.06 31.01

    ADB

    Gvt.

    Tot.

    % 22.2 37 22 12 1.2 3 2.3 0.1 0.2 100

    F. ENTREPRENEURS / SUPPLIERS

    Civil encineerinc (lot 1) and enuipment (lot 2)

    Name

    Responsibility

    Contract signing date

    Contract expiry date

    Am ount of basic contract

    Amount of contract amendmtstz)

    Total amount of contract

    Supply and Iaying of supply nipes and

    primary distrtibution network tbatch 3)

    Name

    Responsibility

    Contract signing date

    Contract expiry date

    Am ount of basic contract

    Amount of ctract amendtst4)

    Total amount of contract

    Société Générale d'Entreprise-congo (SGE)

    -

    France

    lot 1; lot 2 hydraulic and electro-ptimp

    equipment subcontraeted to DEGREM ONT

    8/03/83

    8/09/84 (lot 1); 8/03/85 (lot 2)

    CFA .F 4, 130,989,900

    CFA .F 1,731,437,944

    CFA .F 5,862,427,844

    SPIE-CAPAG - France

    lot 3

    24/03/83

    24/03/85

    CFA.F 3,333,517,500

    CFA.F 1,632,921,175

    CFA.F 4,966,438,675

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    11/49

    Secondary distribution network + connections (batch 4)

    Name SAVCONGO - France

    Responsibility lot 4-1 PVC Pipes and accessories

    Iontrad signing date 23/06/85

    1

    ontract expiry date -

    Duratibn of contract 1 year

    Amoun/ of basic contract CFA.F 125,171,339

    Amount of ctract amendts CFA

    .F .177, 143,600

    Total aiount of contract CFA.F 502,314,939

    Name PONT A M OUSSON - France

    Responsibility lot 4-3 connection equipment; lot 4-2, water

    l metres

    Contrac' signing date 30/06/85

    Iontract expiry date

    1 of contract CFA

    .

    F 679,227,346mount

    Name S.C.K .N France

    Responjibility Iot 4-4, rolling stock

    Contract signing date 30/05/85

    lontract expiry date

    lur

    ation Of contract 1 year

    Amountlof contract CFA.F 154,741,000

    Name I.M .C. - France

    Responjibility lOt 4-5, tools

    Contract signing date 24/06/85

    lontract expiry date

    Iuration of contract 1 yenr

    Amountl of contract CFA.F 57,871,115

    èöxst

    tvax,r.

    Name SAUR-AFRIQUE - France

    Responjibility Supervision and inspection of works

    Contract signing date 16/11/82

    lontract expiry date

    -

    Iuration of contract 2 years

    Amoun? of basic contract CFA.F 465,369,200

    l of ctract amendmt CFA.F 47,750,000mount

    ' bunt of contract c#A

    .F 513,119,200otal am

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    12/49

    Nnm e

    Responsibility

    Contract signing date

    Contract expiry date

    Duration of contract

    Amount of contract

    SGI - Switzerland

    Tariffs study

    08/1988

    08/1989

    8 months

    CFA.F 49,200,000

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    13/49

    N M

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    14/49

    ' INTRODUCTION

    Geographic Setting

    Situated astride the Equator, the Republic of Congo covers an area of 342,000 square

    kilometres. It is bordered on the north by the Central African Republic and the Republic of

    Cameroon, on the south by Zaire and the Atlantic Ocean over a distance of some 200 km , and

    on the east by the Obangui and Congo rivers which separate it from Zaire, and lastly on the west

    by Gabon. The population of Congo was estimated at 1.9 million inhabitants in 1987 with an

    annual growth rate of 2.7% . The towns of Brazzaville, political and adm inistrative capital and,

    Pointe Noire, economic centre and port town, alone have 40% of the total population.

    Bank Group's Comm itment in the Sector

    The Brazzaville drinking water supply reinforcement project whose loan amounts to UA

    26.59 m illion is the Bank Group's second comm itment in the sector. The ADB had previously

    financed, in 1972, to the tune of UA 1.2 million the extension works of the Brazzaville DW S

    system from the Djoué plant built in 1954. Two other projects financed by ADB (rehabilitation

    of Brazzaville DW S installations am ounting to UA 16.76 m illion and Brazzaville rain water

    sewage the loan of which amounts to UA 32.97 million were not ilpplemented and were

    reallocated in 1994 as part of a plan to pay Congo's arrears. The total am ount of the Bank's

    operations in the sector in Congo is UA 27.79 million, representing 15% of the country's

    portfolio. Apart from ADB, the other m ain external support organs are the German Technical

    Cooperation Agency (GTZ). Japanese International Cooperation Agency (JICA), International

    Fund for Agricultural Development (IFAD), European Development Fund (EDF) and UNICEF.

    These organs mainly take part in DW SS programmes in the rural areas.

    Proiect Background

    1.3. 1 At the time of evaluating the present project, the Brazzaville DW S system had a

    production capacity of 36,000 m3/d following the extension Of the former installations of the

    Djoué water treatment plant financed by the ''Fonds d'Action et de Coopération (FACI'' and

    ADB. However, this increase was still inadequate in the face of the town's water requirem ents

    estimated at 63,048 m3/d, i.e. a shortfall of 27,048 m3/d and a water coverage of 40% . Major

    quarters of the town (M'fi1ou, Talangai, Mpissa and ''Cité des 17'') with a population of nearly

    81,000 inhabitants were totally cut off from the corporation's DW S system .

    water.3.2 Following the proclam ation by the United Nations Of the international and

    sanitation decade in 1981, the Congolese Governm ent drew up a development programm e for

    this sector. This programme was included in the first five-year development plan (1982-1986)

    whose investments envisaged for the sector aimed, as a m atter of priority, at improving DW S

    in the urban centres and Brazzaville in particular. In 1981 the Congolese government financed

    a study of the Brazzaville DW S master plan up to the year 2000 including detailed technical

    studies of a first phase aimed at meeting water needs by 1990. The Plan was finalized in

    October 1981 and its results enabled the Government to submit a request to ADB for financing

    this project.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    15/49

    2

    1.3.3 The project was evaluated in 1982 and implemented between 1983 and 1986 under the

    respondibility of its executing agency, the ''Société Nationale de Distribution d'Eau (SNDEIi'.

    1.4 Sources of Information

    This Project Completion Report (PCR) was based on information obtained from the 

    . .

    project evuluation report, archives of ADB q.npytthe executing agency as well as the outcome of

    dilcusslons held during project site visits with variouis officials of SNDE departments.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    16/49

    ; 3

    ECTOM L OBJECTIVX AND PROJECT AIM

    2. 1 W ithin the context of the international water and sanitation decade, the Congolese

    Government set itself the following sectoral objectives;

    i) Drirlkinc Water Supply

    In urban areas, raise the drinking water supply rate of 40% in 1982 to 90% in

    1986 to reach 100% in 1990;

    ln rural areas, raise the drinking water supply rate of 6% in 1982 to 50% in

    1990.

    ii) Sanitation

    The objectives aimed at a substantial improvement in the level of sanitation

    services in urban centres and providing them in rural areas.

    2.2 ln response to the above-mentioned sectoral objectives, the Brazzaville DW S

    reinforcement project aimed at enhancing the water supp.ly capacity of the town by building new

    roduction, transportation, storage and distribution facilities from the Djirl river. The

    lmplementation of the project was partly to help satisfy water needs up to the year 1990 and

    cover at least 99% of the estimated needs as soon as it became operational in 1985.

    Furthermore, the project aimed at erlhancing SNDE'S capacity in operating and maintaining the

    DW S installations with the procurement of operating vèhicles and training of persormel to run

    the treatment plant. taastly, the conduct of a tariffs study within the context of the project wöuld

    help to detennine tariff levels that would ensure the viability of the project and that of SNDE.

    2.3 In the early 1980's, the development of the DWSS sector formed jart of the first five-

    year development plan (1982-1986) whose operations were designed under a master plgn of the

    Brazzaville DWS over a twenty (20) year period (1980-2000). At the beginning of the planning

    period, the situation of the sector was as follows:

    Urban

    Rural

    DW S

    40%

    6%

    Sanitation

    2.4 Under the five-year plan, the aim was to attain in 1990 a drinking water supply coverage

    of 100% in urban areas and 50% in rural areas, and provide adequate sanitation for the

    populations.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    17/49

    4

    2.5 Based qn the estimates of an average growth consumption per inhabitant from 83 l/d/inh.

    in 1980 to 106 l/d/inh. by the year 2000, the water production and distribution plan adopted

    consisted in the construction of a new intake structure on the Djiri river with a rate of flow of

    about 40 m3/s at all times. The plan was based on the construction in two stages of the Djiri

    water treatm e t plant.

    2.6 Wxith rggard to sanitation and drainage of rain waters in particular, a master plan and

    feasibility study was conducted in 1986 and hetpçd to define a programme of works in three

    phases over a jls-year period. The first phase which takes into account the most urgent works

    (sâtlitation in 'ost densely populated quarters, protection of major heavy infrastructures, halting

    of the most se ious erosion phenomena in the urbanized sectors) was the subject of an ADB loan

    in 1989. This could not be started as a result of the slow attitude of the authorities to make the

    loafl enter into force, to launch the various tender documents and also of the fact that the countly

    was under sanction following payment arrears. In 1994, this loan was reallocated as part of a 

    ,lan to pay Cmngo s arrears.

    l

    .

    7 The myin components of the Brazzaville DWS strengthening project, as defined and

    evàluated by ADB, are the following:

    A . Construction of a water intake

     

    structure of 4,500 m 3/h ;

    B. Building of a treatment plant with a capacity of 2,250 m 3/h during the first phase;

    Construction of a 10,000 m3 treated water storage tank and reequipm ent of two

    previous ones;

    D. Building of 14 houses for the personnel;

    E. lm plementation of road works comprising a bitumized section Qf 2.3 km and a

    track of 6 .36 km ;

    F. Laying of supply and primary distribution pipes of a total length of 41.8 km ;

    G. Building of a secondary distribution network of 200 km and 25,000 individual

    connections;

    H . Supply and installation of hydraulic equipment and electro-pumps;

    1. Supply and installation of electrical equipment;

    J. Supply of operating vehicles

    K. Training of personnel;

    L. Engineering-consultancy services for works supervision and inspection'

    M . Conduct of a tariffs study.

    .. r1 .'.ik a..'.'@r; ., b :kkk

    ...

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    18/49

    5

    PROJECT DESIGN

    3. 1 Oricin of Proiect

    The Brazzaville DWS reinforcement project was identified within the context of a master

    plan sm dy on the Brazzaville DW S system conducted in 1982. The Plan included a feasibility

    smdy which helped to select the most appropriate site for harnessing the water and construction

    of a water treatment plant. The detailed feasibility study on the first phase of the Plan helped

    in the preparation of tender documents Of structures to be built. On the basis of the results of

    the Plan's study, the Congolese Government subm itted an application for financing works for

    the first phase of the Plan.

    Preparation. Evaluation, Negotiation and Approval

    3.2.1 The project preparation consisted in the implementation of the master plan and detailed

    prelim inary studies as well as the drafting of tender documents by a consultancy finn recruited

    by the government. The project was evaluated in September 1982 and approved by the Board

    of Directors in December 1982. The ADB loan agreement for an amount of UA 26.59 million

    was signed in January 1983.

    3.2.2 In view of the critical situation of Brazzaville's DW S system , the various phases of the

    smdy, i.e. the Plan, feasibility study and detailed preliminary plan of the first phase and drafting

    of the relevant tender documents were undertaken within a very short period (less than 7 months)

    to enable works to be started quickly. This situation did not make it possible to carry out,

    among others, a detailed study of the main physico-chemical aspects of the Djiri river in an

    adequate hydrologic cycle (at least one year). The Bank did not participate in the preparation

    process. AIl these factors explain the m odifications and contract amendments which occurred

    during the project works (para. 4.2). However, during evaluation, the Bank recommended a

    tariffs study to ensure SNDE a sound management and thus supplement the study of the master

    Plan which dwelt mainly on the technical aspects.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    19/49

    -

    J

    ; ,j

    A . ' '

    QJ .:

    .

    ,

    . g

    k

    .

    .

    .

    ,' ''i 4. PROJECT IM PLEM ENTATION, OPERATION AND COSTS .?

    .

    ' t .

    .

    I

    .

    '

    il'

    ,. 4. 1 Entry into force of the loan and start-up of pro

    -

    iect ';

     

    .

    .

    t .k j j).). . 

    .

    j

    .

    yr 7 1  4. 1. 1 The lo 'p agreement was signed on 7 January 1 983 and enteied into force in May 1983, ) 

    .'

    .

    i.e. less than 5 months after it had been signed. Th shbrt period. between tke signi ng of the . '

    .

    .

    l -

    .

    loân and its entry into force is mainly due to the fact thàt, ahart from the general condkitions, the ',

    '

    '

    '' dent condlitions only included the Bortower'd comtjj itntent letters as well as the prbsegtation

    r

    ( #. PIXCCt

    ;' .: 1 . .

    v

    '

    ë

    ,

    of SNDE'S debt recovery plan. The conditiohs of entry into force are provided as anlex 4. No =.

    .

    I

    .

    .

    .

    v

    $. delay waj therefore attributed to the fulfilment of condittioùs of entry into force. :

    .)

    ' I '

    ;: 4 1 2 W ork started in July 1983 i

    .

    e. a slight delay of three months in relation to the schedule. '.1j, 

    '

    :

    . ,,

    j :j, .

    k : y. j j , , ,; ,  This slight delaly can be attributed to the fact that at the time of prolect evaluatibn in S'eptember

    j:l ' ' I

    .

    :

    ; ' 1982, the seleotion process of firms for works and the engineering consultant had already been à-

    1 M '' '1t3.: finâlized. The quick start-up of works is explained b#'the critical situation of the Btazzaville /,

    j ' '

    ,

    :

    DW S system . (

    ;

    ,

    '

    .

    ':

    )('.. ' 7'7

    ;.:, (( ,,kjj.

    tq 4.2 M odifications .

    -

    .

    '

      . .

    -'

    .

    Jj . . ;g.j;. qq

    j ., 4.2. 1 During prolect implementation, the most significant modifications concerned the ;

    jy(  e twy

    .

    following aspeets: .i.,

    ..c ç j . . ..'ç'ay ' .,

    , :ç

    i) the 15 km long 20 kv MV line envisaged for the electrification of the installations t

    : .r 1

    .

    . i ' ; . l

    ; k

    ,

    Was modified. Indeed, the vottaje Waj tàised to 30 kV' ih. view of the elee.ri-clty ;':

    ; r . supplv fèr installations of the 5#atei' treàtment plant à' well ad. thi Mi , .

    '

    -

    '

    - ,

     '

    .

    .

    -

    I a'' a''--' ; z'' ' h '

     

    '

    .

    Academy situated about 1.5 km from the glte of thé 'plànt. The cojt of wotk on ';.

    ,,

    .

    :, ,,

    jhe Brazzaville-Military Academy section was fully born: by the Conjolege pady .:.'

    :.

    .

    ; ,

    which also carried out the adjudication process. The extension of the 30 kv line '

    J j

    ,v : to the treatment plant was financed by ADB; 'ï

    .

    : .

    4

    j . .; -'

    r .'.' l '

    ..

    ii) 'dditional works and equipment due to poor preparation of the tender documents ?

    '

    ?? ' . l :''

    . ', and those imposed by actual site conditions and difficulties in implementing the

    .

    .

    kg . j -tk:

    .

    ) ' terms of the various contracts. The additional works and equipment represented

     

    .

    l .4.t

    k. 1 1 . 5 % Of the total cost of the project. ;'.,n

    y .. j , t. .tk ,

    4 2 2 W ità regard to the implementation schedule, these modifications caused an extension by o-:

    , * * .;.

    15 months of ihe initial programme envisaged for civil engineering works with the induced '':'

    I ktj) tjw .ffects on works inspection and supervision

    .

    In any case, these modifications coupled w

    ..

    l @

    7 attendant slow administrative procedures (signipg of contract ame dments) explain the extension '

    l f ks supervision

    .

    J

    @

    ,

    x by 39 months of the serivices of the bureau in charge o wor ,

    g j . k-,.,' ); t.: - .

    '

    4 2 3 M oreover, the change made in the financing and implementation of electritication works '''?

    ( . .

    .' had a siguifican't impact on the operation of the treatmen't plant

     

    The frequent power cuts at the .4'

    l :j ).

    Brazzaville eleetric plant, the simation at the subscriber s end and the fact that the national

    .

    . '

    .

    '

    ' ,i

     

    1

    l

    .

    ?

    o. q

     

    ,

    kh 1f . t,

    jj:

    .

    ,

    .

    '

    .

    é

    :iLî . ...-

    '

     

    ;

    $t?:' .. k

    : .'' :

    ,

    t ''J J)

    2''à . '.:

     

    . t;. 

    '

    $ .

    % '

    j1.: '' ''T

    ,:q

    .

    *V' '

    ,

    .

    .

    '

    ..

    k

    . ' *,

    .

    ;t

    sà,f. :k4

    -i''

     

    , . - .ï'i

    ' . 'J: .'.

    . - . , . . .

    . ..wrï.......... ...- u...k1ls....... .. .. -c.) .-.1k2...

    ....... . . .

    .

    .,..

    '

    . . . . . . .., ..l'''

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    20/49

    ..%

    @

    N

    electricity corporation (SNE) was not involved in the inspection of these works are the cause of

    current difficulties observed in the plant's power supply. Hence, the poor connection of

    lightning arresters disrupts, in case of storm, electricity supply to the plant (rather many blow-

    outs of transformers at a rate of 4 to 5 a year always during stormy weather).

    4.3 lm plementation Schedule

    4.3.1 W ork actually started on 7 July 1983 and there was provisional acceptance of civil

    enqineering works, hydraulic equipment and electro-pumps on 6/09/85 and that of works on the

    Iaylng of pipes of the prim ary network on 11/05/85. The acceptance of a section of the pipe

    laying works of the secondary network took place in August 1988. To date, connection works

    have not been com pleted as a result of the cancellation of the relevant contract for non payment

    by the government of bills issued by the corporation. Besides, part of the connection equipment

    had disappeared for lack of adequate storage. Lastly, the final report on the tariffs study ending

    the project activities was only sublnitted in July 1990.

    4.3.2 Compared with estim ates of the appraisal report, therefore, there was a delay of nearly

    60 months due particularly to the completion of the tariffs study. The delay is 44 months if one

    considers the completion of works on the laying of pipes of the secondary network.

    4.3.3 According to SNDE officials, quarterly reports were prepared during the project

    implementation period. However, neither the m ission could be provided with a copy nor could

    one be found in the Bank's archives. The same goes for the final report on completion of

    works. M oreover, this problem was not pointed out in the reports of the Bank's supervision

    m issions. On the other hand, reports of site meetings were made available to the mission and

    served as sources of information in the preparation of the present PCR.

    4.4 Procurement of Goodsand Services

    4.4. 1 The project was implemented on several contracts. The various components as described

    in the appraisal repol't, with the exception of the training (K), inspectiolz/supervision works (L)

    and tariff study (M) components, were regrouped in lots as follows:

    lu7t 1: Civil engineering works include components A, B, C, D, E, 1.

    Lot 2: Supply and laying of hydraulic and electro-pump equipment, com ponent H .

    Lot 3: Supply and laying of main supply pipes and primary distribution network, component H .

    Lot 4: Supply of equipment for secondary distribution network, components G,J. This lot,

    subdivided into 5 sub-lots, was the subject of the following separate and individual

    contracts: i) sub-lot 4-1, pvc mains; ii) sub-lot 4-2, connection materials; iii) sub-lot 4-3,

    metres' iv) sub-lot 4-4, operating vehicles' v) sub-lot 4-5, tools. Pipe laying works of

    the secondary network, the subject of component G, were to be carried out by SNDE on

    force account according to estimates of the appraisal report. However, in view of

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    21/49

    8

    technical and financial diffiçulties, SNDE wao ungble to im plement them and they

    ' h ubject of a mutually agreed contract with a French finn with the approvalecamq t e s

    of the Bank.

    l

    .

    4.2 The procurement of goods and services for civil engineering works and major equipmetlt 

    .

    was done throuch international competitive biddinc (ICB). At this stace. in view of the 

    - - - - - -'-' '

    , .

    .

    emergency situation mentioned by the Congolese authorities (para 3.2.2), the Bank à evalbation

    done on tlhe basis of results of firm's tenders

     

    The evaluatibn mission tim ited itself toas

    lonformity of tender launching operations and award of contracts in accordancehecking the c

    l

    with Bank guidelines.

    4.4.3 Lots 1, 2 and 3 were awarded on the basis of advance procurement procedures. Lot 1

    and 2 were allocated to a French firm which sub-contracted 1ot 2 to another French firm while

    1 d French firm

    .

    ot 3 went to a thir

    l

    .

    4.4 Engineerin/ consultancy services on works supervision and insp. ection (component L)  *-' '''

    '

    financed by th ' Government formed the subject of a contract awarded under a mutual agreement 

    .

    had previously conducted the master plan, feasibility and detailedo a French fi 1u. The Iatte

    l dies and prepared the tender documeats. The contract on petsonnel trainingreliminary sty

    (component K) was allocated to a firm which sub-contracted lot 2. Lastly, a Swiss firm was

    warded the clntract on tariffs study.

    l

    .

    5 Costs and Disbursements

    lroiect costs .

    I

    .

    5. 1 The acqual project costs were quoted in UA worked Out from amounts quoted in CFA for

    purposes of co'parison. The final total project cpst was calculated on .the basis of the exchange

    rates in force i(n September 1986. At that time, the dollar was equivalent to CFA.F 380.62327

    and the rate of UA in terms of the doll@r Fas 1.0846% Cplpparçll with the êF, the UA was

    ivalent to 7.60465 i.e. 412.824 in relation to the .CFA. 'fhe tabie below shows thequ

    comparison of cost estimates, contract and actual costs or the project at the end of works.

    -

    1. ua-rll..zn 4::.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    22/49

    ' #

    K.q

    .

    9

    Table 3. 1

    Comparative Table of Costs

    (in UA million)

    Eval. Contract

    10.23 10.46

    Contract

    Amendm ent

    3.71

    Actual

    Civil eng. Hyd equip/elect.

    (components A,B,C,D,E,I,H)

    Primary supply pipes (F)

    Secondary distrib. network (G)

    Operating vehicles (J)

    Training of personnel (K)

    14.17

    9.07

    8.39

    0.34

    8.06

    2.57

    0.37

    0.12

    1. 12

    0.12

    0. 16

    Works superv. and inspection (L) 0.32

    Tariffs study (M)

    3.94

    0.42 2.99

    0.37

    0. 12

    1.24

    0.12

    0. 12

    0. 19

    10.82

    39.52

    Contingencies

    Total 22.80 8.19 31.01

    NB. Contract costs as well as actual costs include risks and contingencies.

    4.5.2 A study of the table shows that the actual project costs are On the whole lower than those

    estimated on evaluation. This difference is mainly due to an Overestimation of costs of works

    and supplies as a result of poor preparation of the project. Furthermore, it is noted that the

    actual costs are much higher than the costs of contracts. This is due to the Iarge number of

    contract amendm ents negotiated for additional works and supplies.

    B. Disbursements

    ADB and Government contributions to the financing of the project are shown in table 3.2 .5 .3

    below:

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    23/49

    10

    Tabls 3.2

    Financing Plan

    (in U'A million) .

    Sources On Evaluation At the end of W orks

    F.E. L.C. Total F.E. L.C. Total

    ADB 26.59 - 26.59 23.84 - .23.84

    Gokt. 12.93 12.93 7.17 7. 17

    lbtal 26.59 12.93 39.52 23.84 7.17 31.01

    t 1 4 An analysis of the above table shows that, coppared to the final cost of the project,

    '

    '

    -

    è timates made on evuluation. Indeed,bB s participation was higher in relative value to tk es

    although lowel in absolute value than the loan amounf, ADB'S contribution reptesçnted 76.'87 %

    of the projecl cost as against 67.28% envisaged on evaluation. At the same time, the

    Goverrlment's contribution declined by nearly 9.6% cömpared with the estimates made tm

    evaluation. Jhese differences in the case of ADB are due to the poor quality of the tender

    ocuments w 'ich brought about a Iarge number of amendment to contracts, for a total amouht

    1

    of UA 8.7 million representing nearly 28% of the overall cost of the contracts.

    Table 3.3

    Estimated Schedule of Expenditures per Source of Financing

    (in UA million)

    Source 1983 1984 1985 Total

    ADB 14.96 10.51 1. 12 26.59

    Govt. 3.63 7.67 1.63 12.93

    Total 18.59 18.18 2.75 39.52

    Table 3.4

     

    L

    Actual Schedule of Exnendtttlrts pef Source of Financing

    .

    '

    (in UA million)

    1983 1984 1985 1986 1987 1988 1989 1990 1994 Total

    ADB 4.46 8.71 6.76 3.03 0.38 0.31 0.09 0.04 0.06 23.84

    Gvt. 2.45 2.77 0.69 0.64 0.62 7. 17

    Tot. 6.91 11.48 6.76 3.72 0.38 0.95 0.71 0.04 0.06 31.01

    % 22.2 37 22 12 1.2 3 2.3 .0.1 0.2 100

    *

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    24/49

    4.5.5 Tables 3.3 and 3.4 above show the estimated and actual schedule of expenditures per

    source of financing.

    4.5.6 The analysis of these tables shows that the Bank's disbursements initially planned over

    a three-year period did spread over 9 years (excluding the 3 years when the country was under

    sanction). However, over the first four years during which physical works had practically been

    completed, disbursements already represented 93% of the project costs. The indicated

    expendimres from 1987 to 1990 represent especially payment for additional works already

    carried out between 1983 and 1986 and for which amendm ents to contract had been signed.

    1994 expendimres represent outstanding payments as a result of sanctions against the country

    between 1990 and 1994.

    4.5.7 Disbursements made by the Bank represented 89.6% of estimates made at the time of

    evaluation (UA 23.84 million against UA 26.59 million) while those of the Government were

    only 55% of the estimates. In the case of the Bank, this gap is explained by the fact that the

    costs on evaluation were overestimated given the poor project preparation with the result that,

    in spite of the numerous contract amendments, the loan yielded a balance. The low level of

    government disbursements is especially due to fiancial difficulties which did not enable it to

    honour its commitments (a shortfall of 10,000 connections).

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    25/49

    12

    5. OPERATIONAL PERFORM ANCE

    5. 1 The Contract

    ljor objective of the Brazzaville Dws strengthening yroject was to improve the.1. 1 ne m

    water supply ckpacity through the establishment of new water productlon, trailsportation, storage

    d distributionl facilities from the Djiri river. The proj çct therefore made it possible, amongn

    her things, to build a water intake structure of 4

    ,

    500 m 3/hour, a tteatment plant of 2,250t

    m3/hour and a storage tank of 10,000 m 3.

    5.1.2 On evaluation, it was envisaged that the plant would attaln its full capaçity as soon as it

    became oyeratibnal, i.e. 54,000 m3/day. With the already existing plant, the d'aily production

    of water In Brazzaville was around 90,000 m 3, i.e. 32,400,000 m3/year. Howeyer, annual

    I

    production was lower than that envisaged on evaluation as shown in the table below:

    Table 4. 1

    Comparative Status of Actual and Estimated Ammal

    W ater Productioh in B'razzaville

    (in '000 m3)

    Estimated Produced D iff.

    1286 32,400 17,530 -46%

    1987 32,400 21,370 -34%

    1988 32,400 21,000 -35%

    1989 32,400 25,550 -35%

    1990 32,400 22,020 -21%

    1991 32.400 22,000 -32%

    1992 32,400 24,811 -23%

    1993 32,400 25,362 -21%

    5.1.3 This poor jerfonnance can be explained by two factors. First of all, the assumptions that

    the Djoue and Dliri plants would attain their fMll capacity were rather optimistic under the

    technical condqtions of operation. Then, the structures built under this project have major

    defects which 're both due to the design, implementation and operation of the installations.

    Indeed, the Djjl i plapt had major operatlng difficulties caused by: i) sand deposit at the water

    intake point; ii) deficiencies of the electric jower supply system; iii) lack of sewerage for rain

    ters around lhe 10,000 m3 reservoir and lv) inadequate stock of spare parts for maintenancea

    of the facilities). AIl these defects mentioned by the monitoring and audit missions carried out

    n 1992 stem from the short period within which the project was evaluated and financed. 

    iorated very fast for Iack of m aintenanee.oreover

    , the vehicles procured under the project deter

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    26/49

    13

    5.2 Role of the Proiect

    5.2. 1 The Brazzaville DWS reinforcement project is the first component of the emergency

    phase, the outcome of the study of the M aster Plan ''horizon 2000'' financed by the Congolese

    government. lts implementation was to help reduce the water production shortfall estim ated at

    83, 160 m3/day in 1990. The daily production of the new plant (54,000 m3/day) was therefore

    to bring the shortfall down to 29, 160 m3/day.

    5.2.2 Alongside the increase in water production, the project enabled the comlection of a large

    part of the population to the network. The number of subscribers in Brazzaville therefore rose

    from 26,700 in 1986 to 50,000 in 1994, i.e. an increase of 87% (there have been 15,000

    connections under the present project).

    5.2.3 Lastly, this project is the first phase of a DWS development strategy in Brazzaville. The

    implementation of the secönd phase and rehabilitation of the former network will enable the

    people to have easy access to drinking water.

    5.3 Other Factors

    5.3.1 The project's contribution in tenns of training of SNDE personnel was appreciable.

    Indeed, two engineers and three senior technicians have had a two-m onth training with the firm

    that supplied hydraulic equipment. Besides, 13 pump operators have had a nine-month training

    locally. The mission observed, however, that none of the executives sent on training currently

    works at the Djiri plant. W hat is more, the staff do not seem to be quite satisfied with their

    training course, apparently due to the fact that it was rather simple and not quite adapted to the

    operating conditions at the Djiri plant. In any case, this situation poses the problem of judicious

    choice, on the one hand of the training courses provided the Staff of the project implementation

    organs and, on the other the workers who benefit from them .

    5.3.2 The management of such a project by SNDE'S technical units has been quite a valuable

    experience for future operations of the donors in this sector. lt is, however, regrettable that w ith

    the numerous changes in which the firm 's staff have been involved, none of the officials who

    participated in the project is currently at post in the Technical Division.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    27/49

    14

    6. INSTITUTIONAL PERFORM ANCE

    Legal and Institutional Framework

    6.1.1 SNDE'S legal framework has undergone grofounà changes since the project's evaluation

    in 1982. lndeed, by decree 83/668 of 30/08/1983, SN DE was made a Pilot State Entreprise

    1 o

    managed under terms and conditions defined by legislation N 54/83 of 6 July 1983.

    l

    .

    t .2 Under this legislation, a qerformance contract was concluded between the State and the

    pilot Entrèprisg, among other thlngs, on the injtiul 'material infrastrucmre to be placed at the

    disposal of SN E, definition of an investmeht programme necessary for the entreprise, its price

    policy and al1 other specific clauses on the activity of the entreprise. This legislation clearly

    outlines the prerogatives of the supervising M inistry wh ich should exercise a permanent power

    of policy and 'nspection over the entreprise. M oreover, this legislation provides for the setting

    up of a Board of Directors as well as its composition and powers.

    6. 1.3 Also, by decree 84/401 of 23/04/84 voted by the Council of Ministers, SNDE'S Articles

    of Incorporation were armroved. difinine its orzanization and functioning. Although the

    '

    * * ' ''''' '-'''

    .

    objective of thq company has remained unchanged, the new Articles of Incorporation henceforth

    provide SNDE with an authorized capital fully held by the State and define the financial and

    Iccounting provisions applicable to the entreprise

    .

    .2 Organization and M anagement

    6.2.1 In lieu and place of the Steering Committee which existed at the time of proj ect

    evaluation, SN E is henceforth administered by a lz-member Board of D irectors appointed for

    a three-year tenh of office by decision of the supérvising M iniistry. Presided over by the

    Ianaging Director of SNDE

    ,

    this Board is inkèsted wirth the most extensive powers to act on

    behalf of and jfor the account of the firm withtn the framework of the legislation in force.

    oreover? in view of the new socio-politicâl context, b'f the three organs of 'the dderm inaht

    tèllogy which existed in 1982, only the jromoiion' atld social lectlrity committee ls xtill

    bjèràtilmél.

    6.2.2 The S PE Head Office is run by a Managing Director appointed by decree voted by the

    Council of M ihisters on the proposal of the supervising M inistry. This D irector is ass:isted in

    Iis duties by cqntral Directors appointed by decree voted by the Cabinet Council on the proposal

    of the supervising M inistry after consultation with the Managing Director. Departmental Head's

    l

    '

    i Director's proposal. There appointed by decision of the supervising M ini#tl'y o.n the M anag ng

    .

    M inistry therefore hps great intluence in the establishment of management organs.

    l

    .

    2.3 SNDE'S organization has improved substantially since the project's evaluation. Apart  '

    from the general management office, the organization chart comprises six (6) central divisions

    (instead of foyr (4) in 1982) and four regional directorates (instead of two at the time of

    evaluation). Two new units (Data Processing and Supplies) have been set up and directly

    .

    .z.. ,=.ex % ,.:x- . g

    .z.- :.œ. ...=x. -.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    28/49

    'D

    attached to the general m anagement office.

    annex 6.

    6.2.4 lnitially, the restructuring of the organization chart was to help reduce structural and

    personnel expenses while at the same time providing the M anaging Director with the necessary

    support structures to carry out his tasks. It should, however, be noted that the present

    organization is ineffective in that the prerogatives and duties of the various units are not always

    clearly defined. For example, the Cornmercial Department is, in reality, only responsible for

    commercial studies. It is neither involved in billing nor debt collection operations entrusted to

    regional offices. This situation poses a problem of competence between this departm ent and that

    of research and planning. M oreover, several departm ents do not have the human and m aterial

    resources to enable them fully play their role in the entreprise.

    15

    SNDE'S current organization chart is provided as

    6.3 Persolmel and Traininc

    6.3.1 As of 31 January 1995, SNDE'S staff numbered 669 employees as against 678 at the tim e

    of project evaluation, i.e. a decline of only 1% . However, it should be stated that the staff

    strength evolved in a saw-toothed manner. In fact, up to 1993 the number of pennanent

    employees declined steadily from 678 perm anent employees to 571 as of 31/12/93, i.e. a

    decrease of 26% . During this same period, SNDE resorted to temporary staff paradoxically

    assigned to pennanent duties. In 1994, therefore, the regional labour inspectorate insisted that

    the 127 workers then engaged temporarily be rçcruited.

    6.3.2 The table below gives a comparative status of staff distribution per category at the tim e

    of evaluation and drafting of the completion report.

    Evaluation

    59

    192

    427

    678

    Executives

    Foremen

    W orkers

    Total

    87

    249

    333

    669

    The current staff structure of the firm shows overstaffing of the executives and foremen

    category. Indeed, SNDE has 1 executive to 2.8 foremen, 1 executive to 3.8 workers and 1

    foreman to 1.3 workers. This trend is especially related to a recruitment policy not in line with

    any objective criterion, reclassitication of certain employees after non vocational training courses

    (ideological and trade union affiliated) and an automatic promotion system which does not in any

    way encourage the spirit of competition.

    6.3.3 After the project evaluation, SNDE established a training centre built through financing

    from the Germ an cooperation. Up till 1992, this centre had trained nearly 450 SNDE employeej

    in the production units and secondary centres. The trainng courses were provided by a Gennan

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    29/49

    16

    company. However, with the suspension of external assistance, this centre no longer receives

    financing and has therefore suspended its activities. To date, the entreprisé has no training

    policy reflected by the drawing up of a training scheme in response to its needs. Oj.e of the

    reasons for thls shortcom ing is that it has no executive staff capable of drawing up a training

    program me.

    6.4 Accounting and Auditing

    6.4. 1 There is a teal bottleneck in the management of SNDE'S accounts. In organizational

    lcture of the accounts department seems to be ojerational with the accounts unitserms, the stru

    I

    of the regional offices and a centralization at the head Ofhce. However, this function is

    l

    . ,haracterized by: i) inadequate control and monitoring. of operations within the accounts units

    of the regional offices; ii) inadequate internal control Of procedures; iii) a manual accounting- -

    .ystem that requires several manipulations and reveals a poor application of Iaid down

    1 dures

    .

    Moreover, the data processing system currently being designed has noccouhting proje

    lirlk between the headquarters and regional offices.

    '

    1

    6.4.2 The an'lytical accounting system mentioned in the appraisal report does not currently

    exist at SNDEI It started with the financing of the ADB 11 project, but was interrupted with the

    departure of t 'e technical assistant recruited for that purpose because of the sanctions againgt

    Congo.

    6.4.3 The accounts are still certified by the State audit service in accordance with the firm's

    ' lt of anomalies detected a

    '

    t several accounting posts, the atlditor hasylaws. Howeyer, as a resu

    never been able to certify the regularity and sincerity of SNDE'S financial statements. The

    I h Board of Directors forinancial docu ents of the fil'm have not even been subm itted to t e

    approval since 1991 .

    6.5 Tariffs

    l

    .

    5.1 The water tariff structure has remained similar to the one that prevailed at the time of

    l (j to prices whichvaluation

    ,

    characterized by the existence of three tranches that correspon

    i There was

    ,

    however, an improvement in 1984 with thencrease with tpe level of consumption.

    scrapping of t 'e 20% rebate until then applied to a water volume over 300 m3. SNDE'S tariff

    system is therefore very simple and facilitates billing.

    l

    .

    5.2 There have been four increases in water tariffs since 1982 of which, the last, 20%

    lble in the second quarter of 1994 after the devaluation of the CFA Franc

    .

    Theecame applica

    ' from CFA

    .

    F 81 in 1982 to CFA.F 131 in 199 5, i.e. anverage tariff qf m3 of water went up

    increase of 63 '. Until 1987, the tariff increase was only 34.3% whereas, according to the loan

    l

    conditions. it should have been 50% minimum. ln terms Of US dollars, the average rate of m3

    .

    .- l

    of water rose from 23 cents in 1982 to 26 cents in 1995, i.e. an increase of 13% over the

    pefiod.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    30/49

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    31/49

    18

    6.7 Perform ance of Consultants. Entrepreneurs and Suppliers

    Consultant

    6.7.1 In all respects, the services of the engineering consultancy firm were very poor. The

    Iirm

    ,

    a branch of a water supply company, is not recognized in the study and design of DW S

    ivities. Therefore, the lack of reliàble data on the Djiri river did not enable theroject act

    1

    consultant to design an adequate raw water catchment structure. The sand deposit at the intake

    I

    structure as rell as a1l other structures (decanters, filters) noted right from the first operation

    ' ld be solved, among other solutions, by stabilizing the steep banks of the riverf the plant, cou

    and constructing a primary decantation channel with an evacuation system of the deposited sand.

    Ihe consultant could not find any solutions to the specitk technical difficulties that cropped up

    during works implementation (electrical and secondary network). It is the same with problems

    regarding the procurement of goods and services where the consultant's contribution was nil.

    Entrepreneurs and Suppliers

    I

    6.7.2 The firm awarded the contracts for civil engineering works, supply of hydraulic

    I

    equipment and electro-mechanical pumps was noted for average quality work in view of the poor

    l ion problem s at the factory

    ,

    the poorngineering consusltancy services. Rain water evacuat

    quality of the access track to the 10,000 m3 reservoir, and Ieakages noted at the reservoir built

    under the project which never went into operation were not solved by this firm.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    32/49

    19

    FINANCIAL PERFORM ANCE

    7. 1 Operational Analvsis

    7. 1. 1 This analysis was made I'rom the table provided as annex 5 which gives a comparative

    status of estimated operating accounts prepared at the time of

     

    qyaluation and those on SNDE'S

    financial status for the period 1986-1993. However, we hakç. reservations on the financial

    documents as of 31/12/92 and 31/12/93 which are only provisional.

    7. 1.2 SNDE'S operational earnings were quite below the estimates m ade at the time of

    evaluation and based on the optimum production of the plant built under the project (32.4 million

    m3 per year) and annual sales of 27.54 million m3. Over the period under review, SNDE'S

    mrnover grew by 32% from CFA.F 2,958 million in 1986 to CFA.F 3,907 million in 1993 for

    an estimated annual amount of CF A.F 4,817 million. The rise in the turnover is m ainly due to

    the tariff increases between 1986 and 1993 (34%). Indeed, in terms of quantities of water,

    SNDE'S annual sales were practically sim ilar over the entire period whereas its production rose

    from 17.5 million m3 in 1986 to 25.3 million n43 in 1993, i.e. an increase of 44% . Thus,

    neither the production levels nor those of sales envisaged on evaluation were achieved as a result

    of technical and institutional shortcomings. Technically, problems connected with the design,

    implementation and operation of the project's structures caused several breakdowns at the plant

    which had several interrtlptions in its functioning with tlle result that the optim um capacity was

    never attained . Besides, in view of the state of the network, technical losses keep On rising.

    Institutionally, the absence o17 any com mercial strategy has Ied, on the one hand to an almost

    systematic lump sum billing which does not reflect actual consumption and, on the other, a rise

    in fraudulent connections. Consequently, the increase in the number of subscribers (80,000 in

    1993 as against 45,240 in 1986) was not reflected by an increase in water sales.

    7. 1.3 At the same time, operating expenses increased by 78% from CFA.F 4,302 million in

    1986 to CFA.F 7,648 million in 1993 and are quite above the estimates made on evaluation

    (+98% in 1993). This rise is mainly attributed to personnel expenses the level of which. quite

    above forecasts, account fbr nearly 60% of the turnover. M oreover, depreciation and stocks

    rose by 98% between 1986 and l 993 given that account was taken of fixed assets of the

    secondary centres in 1989 and trend of bad debts.

    7. 1.4 In any case, contrary to estilnates made on evaluation, SNDE'S results show a structural

    deficit and cumulative Iosses reached CI7A.F 17,976 million in 1993, i.e. 143% of the

    authorized capital. The operating ratio is higher than 1 over the entire period. Apart from

    technical problems, SNDE operation has suffered from: i) a low Ievel tariff unable to ensure the

    comoration's viability' ii) an incoherent recnlitment policy especially guided by political

    considerations; and iii) total lack c)f control Over financial and commercial aspçcts.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    33/49

    20

    7.2 Analvsis of Financial Structure

    l

    .

    2.1 The appraisal report contains no estimated analysis of SNDE'S financial structure. The

    a

    .nâlysis beloj was made from the table in annex 6 presenting a summary of balance sheets for

    the period 1986-1993. 

    ,.2.2 The fi s net situation sharply d

    eteriplvted as a result of the cumulated lossçs. It

    declined from CFA.F 8,236 million in 1986 to CFA.F -5,392 million in 1993 with the result

    that SNDE is currently totally insolvent. Therefore, the debt ratio eventually reached 25 in

    1991, the last year the firm had a net positive situation.

    7.2.3 Howeyr, the sharp rise in medium and long term debts (MLTD) helped to ensure a

    balanced structure over the entire period except the year 1991. Field investigations did not help

    tb explain the rise in M LTD between 1992 and 1993.

    7.2.4 ln any case, SNDE is currently in a critical financial situation which jeopardizes water

    supply in Congo. Rehabilitating the firm callsxat thr same time for the injection of financial

    re:burèej and redefinition of a new institutipnail, and statutol'y i-ramework. This is why the State

    à-ij Itllilâtéd â privatization process of SNDE which will help to ensttr: the viability of the new

    éhtlty tb be sjt up through: i) the redefinition of an .pp p ropriate framework; ii) the restofation

    of thè fhéjor financial balances' and iii) the application.,of real market prices. To thig end, a  - - -

    ,onsultant will be recruited in December 1995 to pave tthe way fQr the finn s privatization and

    j .

    '

    ensure the transitional management of the sector until the resumption of activities by the private

    6 ltant

    ,

    to be financed by the W orld Ban:,, witll work in close collaboration withector. The yonsu

    the privatizajion committee set up to implement the programme of state withdrawal and

    restructuring bf the public entreprises sector.

    t.3 Financial Rate of Return

    7.3. 1 The assumptions for calculating IFRR on conlpletion of the projecy are provided as annex 

    ditional production of water in Brazzavitle without. Aseribing to the project the entire ad

    taking accoult of the current operating conditions of SNDE gives the project an IRR of 7.54% .

    lonsidering the actual operating conditions of this seotor

    ,

    characterized by a level of overall

    ' ' IRR is 0

    .

    47% . The table for calculating IFRR is providedosses of at least 50% , the project s

    as armex 8.

    7.3.2 These rates are quite below the estimates made on evaluation, where according to the

    assumptions, the IFRR would be 9.21 %, 13.80% or 20.48%. The rate of 0.47% perfectly

    reflect the Yality and is explained by the project's poor technical and.financial performances.

    In view of the average weighted cost of capital of abput 7.2 % , the project is not financially

    viable.

    ;.

    . ,: . .a . .k, x.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    34/49

    2 1

    7.4 Financial Conditions and Clauses

    7.4.1 On evaluation, the financial conditions of the loan provided on the one hand, for tariff

    increases of at least 50% over a five-year period as well as the application of the conclusions

    of the tariffs study in default of a State subsidy and, on the other, the submission of a plan to

    recover SNDE'S debts from its subscribers including the State and its departm ents.

    7.4.2 These conditions were perfectly appropriate and their strict application would have saved

    SNDE from finding itself in a cessation of payment situation. They were, however, not applied

    by the Borrower. The first reason stems from the fact that in their formulation, the conditions

    did not have any binding nature. In fact, since the conditions of entry into force of the loan

    were limited to the subm ission Of commitment plans and letters, it would have been necessary

    to provide in the other conditions for deadlines before the end of works to put pressure on the

    Government. M oreover, the delay in the start-up of the tariffs study rendered its conclusions

    for the socio-political reasons inapplicable.

    7.4.3 Furthermore, by insisting on the drawing up of a plan to recover SNDE'S debts, the

    evaluation mission tried to find a solution to one of the company's major problems. lt would

    have therefore been necessary to set up a debt recovery unit capable of implementing this plan.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    35/49

     

    22

     . ECONOM IC AND SOCIAL PERFORM ANCES

    I

    8. 1 Economic Performances

    8.1.1 The teo nical conditions of drawing up, implementation and operation of the project's 

    ,tructures as well as SNDE s socio-econom ic environmpnt have strongly lim ited thq results

    expected from the project. Indeed, although access to water has been facilitated for a larger

    proportion of the population of Brazzaville, the DW S situation is still preoccupying and

    characterized by quite long untimely interruptions in water supply. Several quarters receive

    1 1 Jr 2 hours per day, generally late at nigàt.ater on y

    8. 1.2 Moreover, the industries targeted at the time of evaluation (breweries, soft driA s...l

    resort to wells for their drinking water supply and therefore fully escape SNDE. The project's

    impact on the development of economic activity is therefore very little.

    8. 1.3 Given jhat most of the project's indirect benefits were not quantifiable, the evalùation

    ' ' ic rate of return (ERR). However, under SNDE'Sission did nqt calculate the project s econom

    current operating conditions, and considering the 1143 of water as an economic tariff, the m ission

    1 ' ERR at 18

    .

    48% . The table for calculating IERR is provided as annex 9.ssessed the project s

    8.2 Social lncidences

    8.2. 1 In health terms, SNDE'S totally insolvent situation renders very difficult the supply of

    1

    chem ical products for treating water. The water consum ed by the population of Brazzaville is

    therefore not jfully guaranteed, since it is not adequately treated. Consequently, the project's

    mpact on reducing water-borne diseases is very low.

    l ' i

    plementation has helped to provide training tbr ab

    .

    out twenty:2.2 However, the project s 

    hNDE employees and contributed to improve the living conditions of SNDE staff through t e

    construction lf twelve houses at the site of the plant.

    *

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    36/49

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    37/49

    .0....

    24

    10. PERFORMANCE OF THE BANK AND THE BORROW ER

    General and Specific Performance

    The Bank

    10. 1. 1 Generally, the Bank's contributitm was just average both in the project design and

    implementatio .

    10.1.2 As regards the project design, the Bank did not escape the rush on the part of the

    Congolekè party. If it is admitted that the sittlation of tlje DW S sub-sector in 1982 called for

    a fépid interv'ntion, the Bank could have taken time é1,l the same to detect the inadequaciews of

    ï by following laid down proceduies in p roj eet financing

    .

    Therefore, a prè-prejecthe basiç study

     

    J tion mission would have perhaps avttided some of the problems currentlyvaluation pr para

    facing the Djilri plant

    10.1.3 Moreover, still for the sake of paéidity, th conditions stipulated for granting the

    loan had no jinding nature, being limited to 'fôittï . aj e àl Mitments and presentâtion of recovery

    ' i è eases eiwisaged were not fully carriednb reimbursrment plans. Consequently, the tarjff ili r

    otlt and the SNDE debt recovery plan was not implzmented.

    10. 1.4 On project imjlementation, no mcommendation was made by the evaluation

    mission for adenuate t'inancial manacement of the proiect throuch the keeoing of separate 

    * -'' '*' - *'-' ;ccounts whose audit would have been financed under the project

      SNDE s poor financial 

    time of evaluation called for greater caution. Lastly, the Bank neither dem andedituation at t e

    :or received quarterly reports from the executing agency and the consùltant responsible for

    supervigion a;s indicated in the Ioan agreement. The fact that the Bank did not finance works

    inùpection a 'd supervision caused it preiudice and it did not even receive the final project  *'

    .

    èdmpletloh report.

    r

    k '

    .

    id i à The two technical supervision missions cartied out in 1984 and 1986 turned out *

    to be inadeuuate. lndeed. in view of the narttcvlar condtilticms of implementation, it would have 

    '

    *' 1 ' *' ,een necessary to monitor the project's activiiies ort à mûre regular basis

      Furthennore, given

    1he Government's contribution to this ftoject (32.7%), there should have beenhe volume of t

    fipancial supervision missions.

    10.1.6 However, within the context of this project, the Bank carried out in November

    1992 an audit m ission which helped to identify all the problem s related to the implementation

     t

    of this projec

    10.1.7 In the absence of a completion report written by the Borrower, the above views

    were obtained on the spot by the mission. For the Congolese parçy, the project suffered, on the 

    he Bank's procedures regarding the s'igning of the contract amendments and, onne hand fr m t

    ' ions did npt take account of the status of implementationhe other, from the fact that the sanct

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    38/49

    25

    of certain com ponents. Adm itting that there were delays in payments for additional works done

    by firms, the mission observed that in any case these works should have been the subject of

    contract amendments approved beforehand by the Bank. M oreover, the Borrower raised the fact

    that because of the sanctions, the balance of the loan could not be used to carry out the plant's

    technical audit, to repair the electricity supply system and carry out drainage works on the

    platform of the water storage tank.

    Borrower

    10.1.8 The Borrower's performance is hardly any better. Apart from the general

    conditions of entry into force of the loans, the Borrower did not honour any of the com mitments

    made regarding the payment of its debts and those of its departments to SNDE, and particularly

    regarding the increase in water tariffs.

    10. 1.9 Furthenmore, in view of its financial difficulties, the Borrower was unable to fully

    pay up its share of the project's financing. W ork on the laying of the secondary network was

    therefore suspended and its relations with the consultant in charge of supervision and inspection

    of works were strained in the final year of project implemehtation. Besides, in spite of the

    urgent nature of the works, the Borrower could have spared itself many inconveniences by

    avoiding to have the works carried out without the prior agreement of the Bank.

    10.2 W orkinc Relations

    W orking relations between the Barlk, the Borrower and the executing agency were

    very poor. None of the partners fully played its role. There was no regular exchange of

    information, observations or suggestions on the various aspects of the project implementation

    with the result that certain problems did not come to Iight nor could solutions be found to them

    (government counterpart, technical defects of structures.. .). In any case, the specific conditions

    under which the project was implemented should have called for much closer working relations

    in the interest of the project.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    39/49

    26

    11. CON USIONS AND LESSONS

    11.1 Conclusions

    11. 1. 1 The Brazzaville DWS strengthening projejt was designed and implemented under

    technical and fiancial conditiöns which seriously compromised its success. Indeed, for 'the sake

    1f rapidity

    ,

    lt was implemented with many shortcomings in the feasibility and detailed

    I

    preliminqry studies, and preparation Of the tender documents. The initial contractj therefore had

    .

    .

    lp

    t,

    ie àiflended for supplefnentary works. Technically, the stmctures bu'llt have sekeral

    i'Zll-V'iilèt ànd cannot achieve their operational tatgets set on evaluation

     

    Finariclallyi the

    kdertiifl  ent did not attain the envisaged level of its financing with the result thàt the laying Uf

    1he secondary network could not be carried out

    .

    M oreover, in spite of the many contract

    amendments mainly financed by the Bank, the ADB loan had a balance representing over 10%

    of the loan am ount.

    11.1.2 ln terms of financial results, the projeçt's objectives have not been achieved.

    Apart fmm technical oroblems, this is due, on the one hand to the fact that the financial

    .

    k

    '

    '

    ''

    ,onditiohs lald down were not fulfilled by the Borrôwer, and on the other, to SNDE s

    1 l this firm is totatly banknlpt and

    ,

    therefore, incapable ofnstitutional environment. Current y,

    maintaining the structures placed at its disposal. Consequently, the privatization process initiated

    by the Gover lnent is absolutely necessary for the rehabilitation of the firm and its production

    facilities.

    11.2 Lessons Learned from the Proiect

    The Borrower

    11.2. 1 The Borrower's financial situation has seriou@ly affected the project. Indeed, it

    would be necessary to ensure that comm itments m ade for the financing of local counterpart are

    I

    actually budgeted for or if possible made available before the start of project works. Moreover,

    it is importknt that adequate allocations are made in annual budgets to ùöver not only the

    maintenance of vehicles but also spare parts for the facilities built.

    The Bank

    11.2.2 The project implementation has mainly suffered from inadequate preparation. In

    our view, it is important to stress that a strict compliance with project financing procedures

    would have helped to avoid many problems in its im plementation. In the future, the Bank

    should avoid financing projects without conducting its own preparatory studies.

    11.2.3 The Bank's poor supervision has also affected this project. In fact, regular

    supervision missions (1 to 2 per year) would have made it possible not only to ensure

    compliance rith the financial conditions but also to detect timely certain technical anomalies.

    The Bank s 'ould therefore monitor ongoing projects regularly.

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    40/49

    . 27

    11.2.4 The mitigated results of the training course abroad financed under the project are,

    to a large extent, due to the fact that the course beneficiaries did not have adequate basic

    training. On its part, the Bank did nOt carefully examine the curriculum vitae submitted by the

    executing agency. Consequently, the Bank should in the future see to it that there is a perfect

    correlation between courses proposed and the basic training of prospective beneficiaries.

    Furthennore, the Bank should take measures so that as much as possible, beneficiaries of

    training courses are maintained at their post for a number of years. This 'would help to ensure

    s/00th implementation of projects and training of other staff.

    11.2.5 It is important to ensure compliance with Bank procedures on loan administration.

    There were serious shortcomings in both the monitoring of com pliance with other loan

    agreement conditions and financial implementation of the project as well as in the technical

    supervision of this project. In this regard, the implementation Of recommendations made by the

    internal audit service especially in the preparation of a log book for the dispatch and receipt of

    various documents, registers and technical or financial reports would help bring about a better

    adim inistration of loans granted by the Bank.

    11.2.6 Another lesson Iearned from this project concerns measures to be taken by the

    Bank to get the Borrower pay up its share of the financing of projects. Furthermore, provisions

    could be included in loan agreements to demand from the Borrower a commitment to cover the

    maintenance costs of equipment procured under projects as well as spare parts needed for built

    structures.

    11.2.7 Lastly, the public utilities sector in Africa is still managed by operating companies

    with many institutional, accounting and financial shortcomings. Therefore, in view of the

    importance of its interventions, the Bank should take the necessary measures to draw up a policy

    on the privatization of such companies. In the case of the present project, the study initiated by

    the W orld Bank will propose a form of privatization as well as a management structure of the

    water sector. ln its position as major donor in the sector, the Bank should take an active part

    in aIl phases of this study.

    b:congo.pcr

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    41/49

    '

    ;J

    :

    BANGUI a

    >

    v %

    : e'

    : A '

    ..

     

    .

    . ..

    v* ; 4 '

    -. 1 , *

    ' r .. 8 ' *

    ye j .. e xk

    .. .

    a.+.a w, * ** - * .  *

    .

    * .

    .

    T ; I . * -- --

    -

    ..

    .. 

    .

    J z . . N o I () .

    > T w .... '

    ...

    ..

    k J : .

    . .

    ' a .. z , .

     . f . z : .- -

     

    .

    x

    @ .

    . - . : . ( *i 1

    .

    e -- Y e 1u T

    .

    . : .. * /

    : .. ... i. -.r..... *. ks: ,)

    . ; ee q

    .

    J e .

    .

    # ., .... * .:

    j;.' 4:

    CONGO .: r. ' c A h: R o 0 N * ' 

    . : luk .

    A . - . e > - y : o t .

    ( ..S3 qi

    .% . ...

    2h.:--/ * v . .. . .>w

    .

     ' .. 2 . . .

    0 f E à N : . . - - IJ G

    '

    e

    k tp . sox nki s 4 oo

    *e

    D

    lmplon ' otzer

    +

    *

    W1

    . ucw o - Ep*no

    o1o o

    .

    J '

    &.- I ' n Qo (>

    $ . *

    *

    .

    < f

    t '1 .

    4% . 'v  *o omo

    .

    & y . -

    *

    tl '@

    .

    '

    vlv* c

    e e k@tl? : 'J

    * . .

    keue ' Mbone

    * d -'  wcn o .

    * T. .'1k :: :- jl

    k -

    4:51 kttsk E , f::zh rsl e o - -- -.

    C o ' K =

    -

    botlyu -

    x .

    *

    * - e

    Bounul- - rdolhakq -. <

    Y o

    r.s o an do . . .C *'

    - . .

    4 Frc o cevll'e # - , x x.

    ele h: -1 e ' N ' 

    4 o ' 

    -

    .

    l

    oo : . . y .: j r .:p . . ev orp o

    O

    .

    5 4 M v * . l ' S

    # O . = .-

    + xJz t) : - .j c

    -% . o . . .  . . R E

    + d. -

    . z + ..zq

    . # .#

    ve '.K Jomboîo .

    *

    .

    cpo6a tec

    oGïendl *z' il w

    . <

    '

    onx # . -  v h Gos

    . .

    Eornorto

    + ' oo

    - Y oma

    txzw:ea Vole d ecu nuvlW ble

    *

    H '

    .

    vfl. 1- sovjqoxx wctv- y 

    ou ed dlng .

    Souevœ ,a

    .

    dx l 1 4 - C h de fer

    a

    > ul + ' - - Roldwcy 

    .

    N Kcyt . . ' . . ,

    *

    .-.

    K u i m 'ny o * K I n I o Rou * ( ou P t + ) P r

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    42/49

    &

    W

    .. .

    : . . c .

    . . . .. .

    ?; . .' * ' '. '.. . .

    y .

    >.. ...p . .:... ...... . q. ....

    .

    .

    , . > . .

    .

    X ..i:. . :.'' . . '..

    .

    .

    .z,j,jd' ' . ....

     .' ;';

    .

    :

    .

    '

    '

    .

    '

     '.:: 1 k'....:...'..':. ' 11:1111 .

    .

    .

    :'.>: ' :

    : . :

    . . .

    . .

    .:. .- . r:. . .z

    .

    . .

    . .

    . .

     

    .

    .

    b .. . . . - w ?, -.

    .

    : . . . : o g

    . I , . . .' k '

    .

    F

    &

    .

    .

    . . ;

    '

    ( '. ' '. . ' . .:. .; . .

    . . .

    4$ .... . . . .'.'. :

    : '. :1 T ' ' I

    . ..

    * :.. 2. zk '

    '

    .

    ' j

    . 4 t.'. . . . .

    (  1

    o

    C)

    R ; (

    .

    , .

    c r

    .

    X

    I

    ' . . ..

    Q

    Ikll li :; 1.::':

    '

    :'

    ; t7' '.'::E:

    J

    .

    '

    :i j jj......y

    : ...... . . . .....:'

    :ji:

    ;:

    .

    ;:) :**:

    .

    *

    .

    :

    .

    1

    *

    '

    .

    '

    .

    :

    *

    .

    .

    '

    .

    1 ' ' 41111:5::lt:l ::

     . .:

    .

     

    .

    .

    ::

    .

    .#: .... .

    .

    :

     ..

    .

    ;j (::222),:1.::ë::..) N.7':::

    .Y....... ..:.:.+I

    .

    J;DdK''' 41::j11j '::y'

    .

    '

    .

    '

    : :'

     

    . 1 :':'

    g

    '

    .

     

    '

    .

    ; j'I

    y : .:

    ...

    ;jj .E..:.. .. :: j ;

     .

    J

    .

    .

    :

    .

    .

    .

    ,

    iy... I .<

    1./1.01 . .:. :.; ... : ::'.:::..:. .4:.:.:.:::: ;::. ..: . : g'.'. : :' : : I F .. ...

    : . . . . ...: .: . :) : j . .. . .....***1)/ 5

    .

    h..:.:...a .: : .. . u . .

    II:II:::: 111111*' ' '

    i :'

    '

    .

    .

    ''

    jr :L j;

    .:

    '

    .

    t

    ; '

    ,

    i

    :

    :

    2:' '

    .

    j . ; .: ir r , . :.' ' .:j' j I 

    ' '

    .'

    ,

    .

    .

    '

    .

    .

    .

    .

    .

    '

    . :';'?.#;' 4: .'.'.'.'.'. ; :à.. . . .'T' i. :;:1 1 :2: :C :... 1

    '

    ..

    '

    :'.':.. .' : .:.1. ' .'.'.'.'.. ''.'.:.'.'

    .

    .

    .

    .

    ::::.:.:.:11 :':'...';.k

    ,

    . . . . . . .

    : :. . . .. .. . 4 : ..'.'.'.'.'. :)':'):;. f: .':'.'.';:.' ..'.:.j). .: . 4 (. .'.'.'.,.*1 , : :':.' E  :  li ::

    j'.'. .'.'..: ..J . .:.j.i.; . fl j ; ;k ....:.:.;.j.jj j.,...;.:.::.::111::: j:::jq)j '' .

    .

    .

    .

    .y :.:.: ;

    I '

    .

     

    ::

    i:.

    ,

    .

    .

    .

    .

    ;

    1

    .::..j .j h: ( jj. , ,.

    . . : ;, : ...... 

    . . .

    : . :..,. . :.. ,:.:.;,j: . .,;j; .j . j , . : : :j l :. ....;i::::lj

    .

    .

    .

    .

    .

    .

    .

    .

    .

    .

    .

    .

    .

    .

    ;.4:.. .. .....'....

    .

    '

    .

    i1 ,. .

    .

    .

    .

    . . . . . .. ,

    . z. . . t .

     ) 7 . : : : .i. .::'.'.'.:

    .

    : : . :' :: ;.:' ti'. )' :. . :;:)f;l /' J V' . . ; :: i i 'S. ''' i 1t : 1 ' 2i ' .:;1:.

    :. . ... :: .: . g:: '. .'.'; '. ; . . ' .' : '.' : ::. ' :'.' ....* :

    :. .. i .:.: : . . : . .::::

    .

    : : , . . J .. ..: :. . . . :. :. .::.' 5

    .,,,,,,

    11 ' : : '.': ::: :: . :;:.' . '- t:t': rï:: :: i ::' r:lzt '- . '' : '' '' :';:1

    : : ':': : : 1 . $ .(

    .

    7 I

     . . .

    .

    .

    .

    .

    .

    .

    .

    .

    .

    .

    ,

    .

    .

    .: ...

     

    .

    .

    .:

    : .

    i2

    .

    :

    .

    E: :: .

    :

    ,....

    ;1 1I)f1) ::: .:.'. . i..:.... . ,. :...?#1t.: . ........... .. .... j ; .:.::'::.:

    . ..:

    < . . 

    . .jt , ...... : . :; . $: :i: :. . i f 1

     

    : '

    :'

    ;': :j .: .':: j::rrjpjj 4::,:::4 .

    .

    Ei:

    .

    :.i :.:.

    .:

    .

    :. .

    :.

    .

    .

    .

    .

    :

    .

    : .::).

     

    :

    : j ' :.: : :.::'j. ,;;E . .;..j:.:...:.::'. :.;.''.;:::' .'. . . . .: :.: .:.. . . .. .: ' . . .;. . . . . . ':

    . . ... ... ....

    :... .. . :...:....

    . . . . .. .

    : . :..:.:.:.q ........,..; .:... ........::h .

    .

    .

    .

    ,

    .

    .

    ,

    .

    .

    .

    ,

    .

    .

    .

    :. : 

    :k.:...;j .........;...E g, ..........i.). ..

    :. , . . . . . . ;. . . .; .j : , ..qq

    q

    j .u'...'.'.u p .qg':..y'k. .... p . t. k.':l...h 

    .

    ... .. )

    .

    . .

    . . y

    c

    u. =

    & 'n

    =

    O =

    - I F-

    d L)  1 =

    .1 tm  < I taa 

    > (x:  l

    - I I fr 

    D

    * <

    < y-

    = =

    >:

    kxl x

    = o 

    tm. s--

    z  y-

    - O to 

    .

    I  > k=

    -

    n.

    X =m =

    o #-4Z =

    X (a: o

    ua tm o -j ED 

    z  txa uu . 

    <

    . + = 1  (/3

    z

    .7 uu - . 

    = n. > u o =

    - >- e- v)

    .

    o

    P' k cx V o X .

    u: . >u n- cz . uu j (z)

    $ > Lu 0

    .

    :K s- >-  o

    j- o. cu  I s- uu co ,>  m

    , x x uu uo  x . F- (z) (ac

    >-4 F- ' = tr F-D txl

    < QD h- G1 O (m

    .

    d / = . >. G. 

    = , 7ou

    .

    'œ QD to  txl tm

    .

    >- , < = ' u-

    .

    @ X . 4 :. j..j . ,

    . . a  s- j

    .g , < . = Iu s-

    > X 'O >-f ' (Y:

    1 = O . p.g (.) < EY D

    1 O Lu . . CZ LM EM ' 9-)

    œ to s. :K

    y . . l x

    / xc 'œ.X u l -.,.ie1IA

    .. .

    .

    =.''*- 'f

    .. ( . ,.. .> .,Gr xa

    *

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    43/49

     

    @

    ANNEX 3

    REPU

    BLIC OF CONGO

    COMPLETION RtPORT

    REHABILITATION 0F BRAZZAVILLE

    DRINKING HATER SUPPLY PROJECT

    %

    Costs on evaluation

    (ln UA million)

    Component

    -

    C1v11 eng., Hdr. equip./elect. 6,27

    (Components A, B, C, D, E, 1, 8)

    -

    Supp14 pjqes (F) (Primary) . 6,23

    -

    Dlstrlbutlon network (G)(:ec'dan)6.62

    -

    operating vehlcles (J) 0

    .

    34

    -

    Training of personnel (K) 0

    ,

    13

    -Horks superv. & lnspection (L)' r-

    Tarlffs study (M) o 19'

    .

    Rlsks & contlngencles 6 8j

    a

    v *

    F a L .C . Total

    1 0 , 23

    9,07

    8 ,39

    0,34

    0. 16

    0.32

    0.19

    10.82

    39.52

    2.84

    1 .77

    0.03

    0 32

    4.01

    12.93otal 26.59

    Current costs of nrol'ect

    (1n UA million)

    Comnonent F k E . L r C . Totale

    -

    civip eng., Hdr. equip./elect. 12.09

    (Components A, B, C, D, E, 1, 8)

    -

    sqpplt piqes (F) (Prlmary) 0.:0

    -

    ulstrlbutlon netWork (G)(Second.)2.65

    -

    operating vehlcles (J) 0.37

    -

    Tralning of personnel (K) 0.12

    -

    Horks superv. & lnspection (L) 0.10

    -

    Tariffs study (H) 0.12

    Total 23.836

    (*) lncledlng risks + contingellcùes

    2.08

    0.68

    0.34

    1 . 1 4

    14.17

    12.00

    2-99

    0.37

    0, 1 2

    1,24

    0. 12

    31.01.174

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    44/49

    à. .x ..). L.i . '

    h .

    B.

      =.m w

    ANNEX 4

    REPUBLIC OF CONGO

    PRoJEcT

    co/pLiTIl:iN.uR,E,oRT

    REHABILITATION OF DRINKINd' WATER SUPPLY

    ju kt zkvjj

    -j.nNSTALLATION IN B

    Loan Grantiàg 

    CoAdli/ions

    ) ' '

    Conbitions Precedent to First Disbursefnent

    lrior to first disbursement

    ,

    the Borrower shall:

    1. undertake to make annual budget allocations to meet its share of the projdct costs

    :

    in accordance with the financing plan;

    2. undertake in writing to find additional fttnds in the event of the 'project's currènt

    cost overruns;

    3. uhdertake in writing not to use thç prpcyeds of the loan to pay various djutikq ànd

    '

    ired for the tmpletentation of the prbjçct;axes on goods and services reqp.

    4. undertake to on-lend the loan to SNDE on the same conditions as the ADB loàn;

     . cause SNDE to submit a recovery plan of its arrears from subsctibers and

    measures envisaged to ensure the recovçry of the sai.d arrears over a fivé.-year

    period from the date of the ajreement;

    6: submit a plan fOr the payment of its d#bts and those of its departments to SNDE

    for the said debts to be wiped off over a five-yeat period from the date of the

    agreement.

    Other Conditions

    I

    The Borrower shall also:

    authorize a m inimum increase in tariff of m3 of water by 50% over a five-year

    period from 1st January 1983 upless it prefers to grant an eqdivalent subjidy tb

    SND E.

    2. take account in any case f0r future increases in tariffg and grantg, of the

    conclusions of the tariffs study to be conducted.

    . .,1. :..u1 . . î,âd. ... .

  • 8/18/2019 Adb Bd if 96 15 en Scannedimage.011(1)

    45/49

    9

    iIiE;i'''-'''I-i,ië- M > & > ko P- c tn m kD C$ X r- rn o % X kn ND X > C0 %4 ND N = fo tn e- r- * < ko0 = fo rn C< e- G1 >  0 % V C X A X X X R

    * * X M X c r c > N r v

    >X & # X v v e & Xo m v O

    Y > C% * >. Ow ç< X * r- c tD

    D (r r = > * N N r- X tn

    *4 * P- > = C< CO kn

    (Y = rn fo C< e- ro r-

    = <

    N N o > % & X * r O * c

    m e r - & & = c > X X M

    > X & * X v M * & G

    œ O V - M X

    * kn N r- ru % ND (0 tn ch tn V

    D r< = e- m œ tn N ko rn ro %

    +> ND N Oh ko (0 ro e- > (Y m

    e- = fo rn G1 e- e- N X

    U% <

    v > o N % * X * m * * N

    ë * A - & c % o > % A >

    > * D * * - = > & c

    % m m m

    M ch ko tn rn o N % o e- (0 rn

    = o tn m r- rn >. % N * o G1

    w > to r- rn e- = * > o  e- N r- ?> u rn

    = <

    v N o > % & X œ r œ * &


Recommended