+ All Categories
Home > Documents > ADDENDUM #3 MAY 31, 2018

ADDENDUM #3 MAY 31, 2018

Date post: 30-Jan-2022
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
24
Addendum #3 - Page 1 City of North Bend Simpson Park Improvements, Project #15.32.1 May 2018 ADDENDUM #3 - MAY 31, 2018 RE: CITY OF NORTH BEND North Bend Simpson Park Improvements Project #15.32.1 FROM: HGE INC., Architects, Engineers & Planners 333 South 4 th Street Coos Bay, Oregon 97420 541-269-1166 TO: Prospective Bidders This Addendum forms a part of the Contract Documents and modifies the original Documents dated May 2018, as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject Bidder to disqualification. This Addendum consists of THREE (3) pages together with the following attachments: Section 03-1000 - Concrete Forming and Accessories, Addendum #3 Section 03-3000 - Cast-in-Place Concrete, Addendum #3 Drawing Sheet G0.1 - Cover Sheet, Add #3 Drawing Sheet C2.00 - Overall Site Plan, Add #3 Drawing Sheet C3.00 - Civil Utility, Add #3 Drawing Sheet C3.10 - Civil Utility, Add #3 Drawing Sheet C3.20 - Signage, Add #3 Drawing Sheet VA5.2 - Details Drawing Sheet VA5.4 - Details Drawing Sheet PA2.1 - Floor Plan, Add #3 Drawing Sheet PA2.2, Add #3 Drawing Sheet PA5.1, Add #3 Drawing Sheet PA5.2 - Details CHANGES TO PROJECT MANUAL 1. Section 03-1000 - Concrete Forming and Accessories: REPLACE with attached Specification Section 03-1000 - Concrete Forming and Accessories, Revised, Addendum #3. 2. Section 03-3000 - Cast-in-Place Concrete: REPLACE with attached Specification Section 03-3000 - Cast-in-Place Concrete, Revised, Addendum #3. CHANGES TO DRAWINGS 1. Sheet G0.1, Cover Sheet: Replace with attached Sheet G0.1 Cover Sheet, ADD #3; updated Index.
Transcript

Addendum #3 - Page 1

City of North Bend Simpson Park Improvements, Project #15.32.1 May 2018

ADDENDUM #3 - MAY 31, 2018 RE: CITY OF NORTH BEND North Bend Simpson Park Improvements Project #15.32.1 FROM: HGE INC., Architects, Engineers & Planners

333 South 4th Street Coos Bay, Oregon 97420 541-269-1166

TO: Prospective Bidders This Addendum forms a part of the Contract Documents and modifies the original Documents dated May 2018, as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject Bidder to disqualification. This Addendum consists of THREE (3) pages together with the following attachments:

• Section 03-1000 - Concrete Forming and Accessories, Addendum #3 • Section 03-3000 - Cast-in-Place Concrete, Addendum #3 • Drawing Sheet G0.1 - Cover Sheet, Add #3 • Drawing Sheet C2.00 - Overall Site Plan, Add #3 • Drawing Sheet C3.00 - Civil Utility, Add #3 • Drawing Sheet C3.10 - Civil Utility, Add #3 • Drawing Sheet C3.20 - Signage, Add #3 • Drawing Sheet VA5.2 - Details • Drawing Sheet VA5.4 - Details • Drawing Sheet PA2.1 - Floor Plan, Add #3 • Drawing Sheet PA2.2, Add #3 • Drawing Sheet PA5.1, Add #3 • Drawing Sheet PA5.2 - Details

CHANGES TO PROJECT MANUAL

1. Section 03-1000 - Concrete Forming and Accessories: REPLACE with attached Specification Section 03-1000 - Concrete Forming and Accessories, Revised, Addendum #3.

2. Section 03-3000 - Cast-in-Place Concrete: REPLACE with attached Specification Section 03-3000 - Cast-in-Place Concrete, Revised, Addendum #3.

CHANGES TO DRAWINGS

1. Sheet G0.1, Cover Sheet: Replace with attached Sheet G0.1 Cover Sheet, ADD #3; updated Index.

Addendum #3 - Page 2

City of North Bend Simpson Park Improvements, Project #15.32.1 May 2018

2. Sheet C2.00, Overall Site Plan: Replace with attached revised Sheet C2.00, Add #3, Overall Site Plan, for changes at drive area east of Visitor Information Center building, to accommodate two-way traffic, AND, changes to all Accessible Crossings, per recent changes in ODOT requirements (lengthening ramp landing areas).

3. Sheet C3.00, Civil Utility: Replace with attached revised Sheet C3.00, Add #3: Sewer lateral modification; sewer demolition.

4. Sheet C3.10, Civil Utility: Replace with attached revised Sheet C3.10, Add #3: Swale Note.

5. Sheet C3.20, Signage: Replace with attached revised Sheet C3.20, Add #3: Striping change.

6. Sheet VA4.1 and Sheet VS2.3, East and West Elevations: Roofline at Grid 5 to extend 8 inches past Grid 5 as shown on Sheet VA2.1 - Floor Plan.

7. Sheet VA5.2, Details: Add attached Sheet VA5.2. 8. Sheet VA5.4, Details: Add attached Sheet VA5.4. 9. Sheet VS1.2, Structural, General Notes, Cross-Laminated Timber: ADD the

following paragraph: “Project specific installation requirements and screw attachment procedure for roof CLT panels are as follows:

Install Main roof CLT panels starting at the lowest elevation panel and work towards the higher end. At the first panel, attach screws from CLT to ridge per 1/VS6.2 then push down the elevated corner, warping the panel and install screws per 11/VS6.1 to the exterior sill plate. The force required to warp the panel will be at least 300 lbs. Install the next panel adjacent to the first panel, attach to ridge beam in similar fashion, then connect the first and second CLT panels together per 9/VS6.2, only the diagonal screws from the first panel to the second panel. Next, attach the second CLT panel to the exterior wall per 11/VS6.1. Finally, connect the diagonal screws from the second panel to the first panel per 9/VS6.2.”

10. Sheet VS2.3, Structural Roof Framing Plan: Change overhang at Grid 7 to match Sheet VA2.1 - Floor Plan (1’-4”).

11. Sheet PA2.1, Floor Plan, and Sheet PA2.2: Replace with attached Sheets PA2.1-Add #3 and PA2.2-Add #3: Window sizes and type clarified.

12. Sheet PA5.1: Replace with attached Sheet PA5.1-Add #3: Additional stem wall detail. 13. Sheet PA5.2, Details: Add attached Sheet PA5.2.

Addendum #3 - Page 3

City of North Bend Simpson Park Improvements, Project #15.32.1 May 2018

APPROVALS:

ITEM SPECIFIED SECTION

APPROVAL

Acoustical Panels 09-5100 - Acoustical Ceilings, paragraph 2.01

Rockfon Sonar, Item #16201, Size 2x4, Narrow Tegular, Color - White, NRC - .95, Class A fire rating; Rockfon LLC, Telephone: 503-387-5773 / 800-323-7164.

Suspension System 09-5100 - Acoustical Ceilings, paragraph 2.02

Rockfon/Chicago Metallic Tempra 4000, Size 9/16, Heavy Duty, Color - White, Material - Steel; Rockfon LLC, Telephone: 503-387-5773 / 800-323-7164.

END OF ADDENDUM #3

03-1000 - Page 1

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

SECTION 03-1000CONCRETE FORMING AND ACCESSORIES

PART 1 GENERAL1.01 SECTION INCLUDES

A. Formwork for cast-in place concrete, with shoring, bracing and anchorage.B. Formliner - Textured Architectural Concrete.C. Openings for other work.D. Form accessories.E. Form stripping.

1.02 RELATED REQUIREMENTSA. Section 03-2000 - Concrete Reinforcing.B. Section 03-3000 - Cast-in-Place Concrete.C. Section 31-2316 - Excavation: Shoring and underpinning for excavation.

1.03 REFERENCE STANDARDSA. ACI 117 - Standard Specifications for Tolerances for Concrete Construction and Materials;

2010.B. ACI 301 - Specifications for Structural Concrete; 2010 (Errata 2012).C. ACI 318 - Building Code Requirements for Structural Concrete and Commentary; 2011.D. ACI 347R - Guide to Formwork for Concrete; 2014.

1.04 SUBMITTALSA. See Section 01-3000 - Administrative Requirements, for submittal procedures.B. Formliner Product Data: Provide data on void form materials and installation requirements.

1. Sample Panel: Submit a 24” x 24” sample of the formliner pattern for review and approval.2. Shop Drawings: Plan, elevation, and details showing overall pattern, joint locations, form

tie locations, end locations and other special conditions.3. Samples: Form ties, samples, and description, showing method of break-back when forms

are removed.PART 2 PRODUCTS2.01 FORMWORK - GENERAL

A. Provide concrete forms, accessories, shoring, and bracing as required to accomplishcast-in-place concrete work.

B. Design and construct to provide resultant concrete that conforms to design with respect toshape, lines, and dimensions.

C. Comply with applicable state and local codes with respect to design, fabrication, erection, andremoval of formwork.

D. Comply with relevant portions of ACI 347, ACI 301, and ACI 318.2.02 WOOD FORM MATERIALS

A. Form Materials: At the discretion of the Contractor.2.03 REMOVABLE PREFABRICATED FORMS

A. Manufacturers:1. Fitzgerald Formliners.2. SpecFormliner.3. Substitutions: See Section 01-6000 - Product Requirements.

B. Preformed Plastic Forms: Thermoplastic form liner, tight fitting, stiffened to support weight ofconcrete without deflection detrimental to tolerances and appearance of finished surfaces.

CONCRETE FORMING AND ACCESSORIES03-1000 - Page 2

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

C. Pattern:1. Fitzgerald Formliners, Pattern 16938 or equal. 1.5" wide plank, Randon Depth PLank.2. Peak: 1.5 inches.3. Valley: 1.5 inches.4. See photo image end of section for image example.

2.04 FORMWORK ACCESSORIESA. Form Release Agent: Capable of releasing forms from hardened concrete without staining or

discoloring concrete or forming bugholes and other surface defects, compatible with concreteand form materials, and not requiring removal for satisfactory bonding of coatings to be applied.1. Composition: Colorless reactive, mineral oil-based, soy-based, or vegetable-oil based

compound.2. Do not use materials containing diesel oil or petroleum-based compounds.

B. Filler Strips for Chamfered Corners: Rigid plastic type; 3/4 x 3/4 inch size; maximum possiblelengths.

C. Embedded Anchor Shapes, Plates, Angles and Bars: As specified in Section 05-1200.PART 3 EXECUTION3.01 EXAMINATION

A. Verify lines, levels and centers before proceeding with formwork. Ensure that dimensions agreewith drawings.

3.02 EARTH FORMSA. Hand trim sides and bottom of earth forms. Remove loose soil prior to placing concrete. Use

only for bottoms and concrete sides not exposed to view.3.03 ERECTION - FORMWORK

A. Erect formwork, shoring and bracing to achieve design requirements, in accordance withrequirements of ACI 301.

B. Provide bracing to ensure stability of formwork. Shore or strengthen formwork subject tooverstressing by construction loads.

C. Align joints and make watertight. Keep form joints to a minimum.3.04 FORMLINER INSTALLATION

A. Install in accordance with manufacturer's written instructions as applicable to each type ofsubstrate required. Install in accordance with specified pattern and mortar.

B. Tolerances: Dimensions of the finished panel, at the time of erection in the structure, shallconform to the tolerances for precast, non prestressed elements in ACI 117, unless otherwisespecified by the Architect.

C. Formliner to "return" at wall ends as shown in Drawings, typical all exposed concrete wall ends.3.05 APPLICATION - FORM RELEASE AGENT

A. Apply form release agent on formwork in accordance with manufacturer's recommendations.B. Apply prior to placement of reinforcing steel, anchoring devices, and embedded items.

3.06 INSERTS, EMBEDDED PARTS, AND OPENINGSA. Provide formed openings where required for items to be embedded in passing through concrete

work.B. Locate and set in place items that will be cast directly into concrete.C. Coordinate with work of other sections in forming and placing openings, slots, reglets, recesses,

sleeves, bolts, anchors, other inserts, and components of other work.3.07 FORM CLEANING

A. Clean forms as erection proceeds, to remove foreign matter within forms.

CONCRETE FORMING AND ACCESSORIES03-1000 - Page 3

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

B. Clean formed cavities of debris prior to placing concrete.3.08 FORMWORK TOLERANCES

A. Construct formwork to maintain tolerances required by ACI 117, unless otherwise indicated.3.09 FIELD QUALITY CONTROL

A. An independent testing agency will perform field quality control tests, as specified in Section01-4000 - Quality Requirements.

B. Inspect erected formwork, shoring, and bracing to ensure that work is in accordance withformwork design, and to verify that supports, fastenings, wedges, ties, and items are secure.

3.10 FORM REMOVALA. Do not remove forms or bracing until concrete has gained sufficient strength to carry its own

weight and imposed loads.B. Loosen forms carefully. Do not wedge pry bars, hammers, or tools against finish concrete

surfaces scheduled for exposure to view.3.11 FORMLINER IMAGE EXAMPLE

A. See below.END OF SECTION

CONCRETE FORMING AND ACCESSORIES03-1000 - Page 4

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

03-3000 - Page 1

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

SECTION 03-3000CAST-IN-PLACE CONCRETE

PART 1 GENERAL1.01 SECTION INCLUDES

A. Floors and slabs on grade.B. Concrete foundation walls and exposed exterior walls with formliner texture, exposed smooth

interior walls.C. Joint devices associated with concrete work.D. Miscellaneous concrete elements, including equipment pads, light pole bases, thrust blocks,

and manholes.1.02 RELATED REQUIREMENTS

A. Section 014000 - Quality Requirements.B. Section 03-1000 - Concrete Forming and Accessories: Forms and accessories for formwork.C. Section 03-2000 - Concrete Reinforcing.D. Section 03-3511 - Concrete Floor Finishes: Densifiers, hardeners, applied coatings, and

polishing.1.03 REFERENCE STANDARDS

A. ACI 117 - Standard Specifications for Tolerances for Concrete Construction and Materials;2010.

B. ACI 211.1 - Standard Practice for Selecting Proportions for Normal, Heavyweight, and MassConcrete; 1991 (Reapproved 2009).

C. ACI 301 - Specifications for Structural Concrete; 2010 (Errata 2012).D. ACI 302.1R - Guide for Concrete Floor and Slab Construction; 2004 (Errata 2007).E. ACI 304R - Guide for Measuring, Mixing, Transporting, and Placing Concrete; 2000.F. ACI 306R - Cold Weather Concreting; 2010.G. ACI 318 - Building Code Requirements for Structural Concrete and Commentary; 2014.H. ACI 347R - Guide to Formwork for Concrete; 2014.I. ASTM C33/C33M - Standard Specification for Concrete Aggregates; 2013.J. ASTM C39/C39M - Standard Test Method for Compressive Strength of Cylindrical Concrete

Specimens; 2015a.K. ASTM C94/C94M - Standard Specification for Ready-Mixed Concrete; 2015.L. ASTM C109/C109M - Standard Test Method for Compressive Strength of Hydraulic Cement

Mortars (Using 2-in. or (50-mm) Cube Specimens); 2013.M. ASTM C150/C150M - Standard Specification for Portland Cement; 2015.N. ASTM C171 - Standard Specification for Sheet Materials for Curing Concrete; 2007.O. ASTM C173/C173M - Standard Test Method for Air Content of Freshly Mixed Concrete by the

Volumetric Method; 2014.P. ASTM C260/C260M - Standard Specification for Air-Entraining Admixtures for Concrete; 2010a.Q. ASTM C494/C494M - Standard Specification for Chemical Admixtures for Concrete; 2013.R. ASTM C618 - Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan

for Use in Concrete; 2015.S. ASTM C1059/C1059M - Standard Specification for Latex Agents for Bonding Fresh to

Hardened Concrete; 2013.T. ASTM C1107/C1107M - Standard Specification for Packaged Dry, Hydraulic-Cement Grout

(Nonshrink); 2014.

CAST-IN-PLACE CONCRETE03-3000 - Page 2

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

U. ASTM C1240 - Standard Specification for Silica Fume Used in Cementitious Mixtures; 2014.1.04 SUBMITTALS

A. See Section 01-3000 - Administrative Requirements, for submittal procedures.B. Product Data: Submit manufacturers' data on manufactured products showing compliance with

specified requirements and installation instructions.C. Mix Design: Submit proposed concrete mix design.

1. Indicate proposed mix design complies with requirements of ACI 301, Section 4 - ConcreteMixtures.

2. Indicate proposed mix design complies with requirements of ACI 318, Chapter 5 -Concrete Quality, Mixing and Placing.

D. Sustainable Design Submittal: If any fly ash, ground granulated blast furnace slag, silica fume,rice hull ash, or other waste material is used in mix designs to replace Portland cement, submitthe total volume of concrete cast in place, mix design(s) used showing the quantity of portlandcement replaced, reports showing successful cylinder testing, and temperature on day of pour ifcold weather mix is used.

E. Project Record Documents: Accurately record actual locations of embedded utilities andcomponents that will be concealed from view upon completion of concrete work.

F. Warranty: Submit manufacturer warranty and ensure forms have been completed in Owner'sname and registered with manufacturer.

1.05 QUALITY ASSURANCEA. Perform work of this section in accordance with ACI 301 and ACI 318.B. Follow recommendations of ACI 306R when concreting during cold weather.

1.06 WARRANTYA. See Section 01-7800 - Closeout Submittals, for additional warranty requirements.B. Slabs with Moisture Vapor Reducing Admixture (MVRA): Provide warranty to cover the cost of

flooring failures due to moisture migration from slabs for ten years.1. Include cost of repair or removal of failed flooring, placement of topical moisture

remediation system, and replacement of flooring with comparable flooring system.PART 2 PRODUCTS2.01 FORMWORK

A. Comply with requirements of Section 03-1000.B. Formwork Design and Construction: Comply with guidelines of ACI 347R to provide formwork

that will produce concrete complying with tolerances of ACI 117.2.02 REINFORCEMENT

A. Comply with requirements of Section 03-2000.2.03 CONCRETE MATERIALS

A. Cement: ASTM C150/C150M, Type I - Normal Portland type.1. Acquire all cement for entire project from same source.

B. Fine and Coarse Aggregates: ASTM C 33.1. Acquire all aggregates for entire project from same source.

C. Fly Ash: ASTM C618, Class C or F.D. Calcined Pozzolan: ASTM C618, Class N.E. Silica Fume: ASTM C1240, proportioned in accordance with ACI 211.1.F. Water: Clean and not detrimental to concrete.

CAST-IN-PLACE CONCRETE03-3000 - Page 3

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

2.04 ADMIXTURESA. Do not use chemicals that will result in soluble chloride ions in excess of 0.1 percent by weight

of cement.B. Air Entrainment Admixture: ASTM C260/C260M.

2.05 ACCESSORY MATERIALSA. Underslab Vapor Retarder: Multi-layer, fabric-, cord-, grid-, or aluminum-reinforced

polyethylene or equivalent, complying with ASTM E1745, Class A; stated by manufacturer assuitable for installation in contact with soil or granular fill under concrete slabs. The use ofsingle ply polyethylene is prohibited.1. Installation: Comply with ASTM E1643.2. Accessory Products: Vapor retarder manufacturer's recommended tape, adhesive,

mastic, prefabricated boots, etc., for sealing seams and penetrations.3. Manufacturers:

a. Stego Industries, LLC: www.stegoindustries.com.b. Substitutions: See Section 01-6000 - Product Requirements.

B. Non-Shrink Cementitious Grout: Premixed compound consisting of non-metallic aggregate,cement, water reducing and plasticizing agents.1. Grout: Comply with ASTM C1107/C1107M.2. Minimum Compressive Strength at 28 Days, ASTM C109/C109M: 7,000 pounds per

square inch.C. Epoxy Adhesive: Moisture-insensitive, two-part; consisting of epoxy resin, non-metallic

aggregate, and activator.1. Manufacturers:

a. Hilti RE-500 V3.b. Simpson SET-XP or 3.c. Or equivalent.

2.06 BONDING AND JOINTING PRODUCTSA. Latex Bonding Agent: Non-redispersable acrylic latex, complying with ASTM C1059/C1059M,

Type II.1. Manufacturers:

a. SpecChem, LLC; Strong Bond Acrylic Bonder: www.specchemllc.com/sle.b. W.R. Meadows, Inc.; ACRY-LOK-: www.wrmeadows.com/sle.c. Substitutions: See Section 01-6000 - Product Requirements.

B. Slab Isolation Joint Filler: 1/2 inch thick, height equal to slab thickness, with removable topsection that will form 1/2 inch deep sealant pocket after removal.1. Material: ASTM D1751, cellulose fiber.

2.07 CURING MATERIALSA. Evaporation Reducer: Liquid thin-film-forming compound that reduces rapid moisture loss

caused by high temperature, low humidity, and high winds; intended for application immediatelyafter concrete placement.1. Manufacturers:

a. SpecChem, LLC; SpecFilm Concentrate or SpecFilm RTU:www.specchemllc.com/#sle.

b. W. R. Meadows, Inc; Evapre or Evapre-RTU: www.wrmeadows.com/#sle.c. Substitutions: See Section 01-6000 - Product Requirements.

B. Moisture-Retaining Sheet: ASTM C171.1. Curing paper, regular.

2.08 CONCRETE MIX DESIGNA. Proportioning Normal Weight Concrete: Comply with ACI 211.1 recommendations.

CAST-IN-PLACE CONCRETE03-3000 - Page 4

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

1. Replace as much Portland cement as possible with fly ash, ground granulated blastfurnace slag, silica fume, or rice hull ash as is consistent with ACI recommendations.

B. Admixtures: Add acceptable admixtures as recommended in ACI 211.1 and at ratesrecommended or required by manufacturer.

C. Normal Weight Concrete:1. Compressive Strength, when tested in accordance with ASTM C 39/C 39M at 28 days:

4,000 psi, unless drawings indicate otherwise. Concrete should be a minimum of a 6-sackmix.

2. Fly Ash Content: Maximum 15 percent of cementitious materials by weight.3. Calcined Pozzolan Content: Maximum 10 percent of cementitious materials by weight.4. Silica Fume Content: Maximum 5 percent of cementitious materials by weight.5. Water-Cement Ratio: Maximum 40 percent by weight.6. Total Air Content: 4-1/2 percent, determined in accordance with ASTM C173/C173M, 5%

for concrete exposed to soil/weather.7. Maximum Slump: 4 inches.8. Maximum Aggregate Size: 3/4 inch.

2.09 MIXINGA. Transit Mixers: Comply with ASTM C94/C94M.

PART 3 EXECUTION3.01 EXAMINATION

A. Verify lines, levels, and dimensions before proceeding with work of this section.3.02 PREPARATION

A. Formwork: Comply with requirements of ACI 301. Design and fabricate forms to support allapplied loads until concrete is cured, and for easy removal without damage to concrete.

B. Where new concrete is to be bonded to previously placed concrete, prepare existing surface bycleaning with steel brush and applying bonding agent in accordance with manufacturer'sinstructions.1. Use latex bonding agent only for non-load-bearing applications.

3.03 REBAR DOWELING WITH EPOXY ADHESIVEA. Install in accordance with manufacturers evaluation report.

1. Coordinate inspection.2. Clean hole.3. Insure adequate mixing.4. Allow cure time.

3.04 PLACING CONCRETEA. Place concrete in accordance with ACI 304R.B. Place concrete for floor slabs in accordance with ACI 302.1R.C. Notify Architect and Owner's Independant Testing Agency not less than 24 hours prior to

commencement of placement operations.D. Ensure reinforcement, inserts, embedded parts, and formed construction joint devices will not

be disturbed during concrete placement.E. Place concrete continuously without construction (cold) joints wherever possible; where

construction joints are necessary, before next placement prepare joint surface by removinglaitance and exposing the sand and sound surface mortar, by sandblasting or high-pressurewater jetting.

F. Finish floors level and flat, unless otherwise indicated, within the tolerances specified below.3.05 SLAB JOINTING

A. Locate joints as indicated on the drawings.

CAST-IN-PLACE CONCRETE03-3000 - Page 5

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

B. Anchor joint fillers and devices to prevent movement during concrete placement.C. Isolation Joints: Use preformed joint filler with removable top section for joint sealant, total

height equal to thickness of slab, set flush with top of slab.3.06 FLOOR FLATNESS AND LEVELNESS TOLERANCES

A. Maximum Variation of Surface Flatness:1. Exposed Concrete Floors: 1/4 inch in 10 feet.

B. Correct the slab surface if tolerances are less than specified.C. Correct defects by grinding or by removal and replacement of the defective work. Areas

requiring corrective work will be identified. Re-measure corrected areas by the same process.3.07 CONCRETE FINISHING

A. Repair surface defects, including tie holes, immediately after removing formwork.B. Unexposed Form Finish: Rub down or chip off fins or other raised areas 1/4 inch or more in

height.C. Exposed Form Finish: Rub down or chip off and smooth fins or other raised areas 1/8 inch or

more in height. Provide finish as follows:1. Smooth Rubbed Finish: Wet concrete and rub with carborundum brick or other abrasive,

not more than 24 hours after form removal.D. Vertical Cast-In-Place Concrete:

1. Avoid patching.2. Fill tie holes with approved and appropriate tie-hole patching compounds only, expansive

or non-shrink, matching color of concrete. Compound to be shrinkage compensating toremain tightly in the tie hole,.

E. Concrete Slabs: Finish to requirements of ACI 302.1R, and as follows:1. Surfaces to Receive Thin Floor Coverings: "Steel trowel" as described in ACI 302.1R; thin

floor coverings include carpeting, resilient flooring, seamless flooring, resinous matrixterrazzo, thin set quarry tile, and thin set ceramic tile.

2. Decorative Exposed Surfaces: Trowel as described in ACI 302.1R; use steel-reinforcedplastic trowel blades instead of steel blades to avoid black-burnish marks; decorativeexposed surfaces include surfaces to be stained or dyed, pigmented concrete, surfaces toreceive liquid hardeners, surfaces to receive dry-shake hardeners, surfaces to be polished,and all other exposed slab surfaces.

3. Other Surfaces to Be Left Exposed: Trowel as described in ACI 302.1R, minimizingburnish marks and other appearance defects.

4. Sidewalk Paving, ramps: Light broom, texture perpendicular to direction of travel withtroweled and radiused edge 1/4 inch radius.

3.08 CURING AND PROTECTIONA. Comply with requirements of ACI 308R. Immediately after placement, protect concrete from

premature drying, excessively hot or cold temperatures, and mechanical injury.B. Maintain concrete with minimal moisture loss at relatively constant temperature for period

necessary for hydration of cement and hardening of concrete.C. Formed Surfaces: Cure by moist curing with forms in place for full curing period.D. Surfaces Not in Contact with Forms:

1. Initial Curing: Start as soon as free water has disappeared and before surface is dry.Keep continuously moist for not less than three days by water ponding, water-saturatedsand, water-fog spray, or saturated burlap.

2. Final Curing: Begin after initial curing but before surface is dry.a. Moisture-Retaining Sheet: Lap strips not less than 3 inches and seal with waterproof

tape or adhesive; secure at edges.

CAST-IN-PLACE CONCRETE03-3000 - Page 6

North Bend Simpson Park Improvements, Project # 15.32.1 May 2018 - REVISED Addendum #3

3.09 FIELD QUALITY CONTROLA. An independent testing agency will perform field quality control tests, as specified in Section

01-4000 - Quality Requirements.B. Provide free access to concrete operations at project site and cooperate with appointed firm.C. Submit proposed mix design of each class of concrete to inspection and testing firm for review

prior to commencement of concrete operations.D. Tests of concrete and concrete materials may be performed at any time to ensure conformance

with specified requirements.E. Compressive Strength Tests: ASTM C39/C39M. For each test, mold and cure three concrete

test cylinders. Obtain test samples for every 100 cubic yards or less of each class of concreteplaced.

F. Take one additional test cylinder during cold weather concreting, cured on job site under sameconditions as concrete it represents.

3.10 DEFECTIVE CONCRETEA. Test Results: The testing agency shall report test results in writing to Architect and Contractor

within 24 hours of test.B. Defective Concrete: Concrete not conforming to required lines, details, dimensions, tolerances

or specified requirements.C. Repair or replacement of defective concrete will be determined by the Architect. The cost of

additional testing shall be borne by Contractor when defective concrete is identified.D. Do not patch, fill, touch-up, repair, or replace exposed concrete except upon express direction

of Architect for each individual area.3.11 PROTECTION

A. Do not permit traffic over unprotected concrete floor surface until fully cured.B. Protect slabs scheduled for exposed finish, polished or trowel finish, from damage, staining, or

discoloration during entire course of construction.END OF SECTION

138

I-5

101

4297

20

38

101

395

20

84

30

395

30

I-5

84

OWNERCITY OF NORTH BENDHIGHWAY 101NORTH BEND, OR 97459CONTACT:TERRENCE O'CONNORCITY MANAGER

ARCHITECTHGE, Inc.ARCHITECTS, ENGINEERS& PLANNERS333 S. 4TH STREETCOOS BAY, OREGON 97420PHONE: 541.269.1166 FAX: 541.269.1833CONTACT - JOSEPH A. SLACK, AIAPROJECT ARCHITECT -OFFICE: 541-269-1166 EXT 273

STRUCTURAL ENGINEERDCI ENGINEERS921 SW WASHINGTON STREETSUITE 560PORTLAND, OR 97205PHONE: 503.242.2448CONTACT: KYLE KRAXBERGER, PE

A.B.A.F.F.ARCH.B&BB.C.B.M.BLDG.B.S.B.V.C.

B.W.CAL.C.B.C.I.CIR.CLC.O.CONC.CONT.CONT'RCOR.C/SC.F.C.Y.DD.M.H.D.F.DIM.DIA.DBL.DEMOEA.EL.

ALUMINUMABOVE FINISHED FLOORARCHITECTBALLED AND BURLAPPEDBOTTOM OF CURBBENCHMARKBUILDINGBOTTOM OF SLOPEBEGINNING OF VERTICALCURVEBOTH WAYSCALIPERCATCH BASINCAST IRONCIRCULARCENTERLINECLEANOUTCONCRETECONTINUOUSCONTRACTORCORNERCROSS SLOPECUBIC FEETCUBIC YARDDEGREE OF CURVATUREDROP MANHOLEDRINKING FOUNTAINDIMENSIONDIAMETERDOUBLEDEMOLISH / DEMOLITIONEACHELEVATION

E.V.C.ENGR.EX.(E)EXT.E.W.E.S.F.F.E.F.G.FIN.FL.F.H.FTG.FT.GA.GAL.G.C.G.R.GD.GPMG.V.HBHWH.P.HT.HOR.HWY.I.D.IN.INL.INT.INV.J.B.

END OF VERTICAL CURVEENGINEEREXISTINGEXISTINGEXTERIOREND WALLEND SECTIONFINISH FLOOR ELEVATIONFINISHED GRADEFINISHFLOORFIRE HYDRANTFOOTINGFOOT OR FEETGAUGEGALVANIZEDGENERAL CONTRACTORGUARD RAILGRADEGALLONS PER MINUTEGAS VALVEHOSE BIBHEAD WALLHIGH POINTHEIGHTHORIZONTALHIGHWAYINSIDE DIAMETERINCHINLETINTERIORINVERTJUNCTION BOX

GENERALG0.1 COVER SHEET, SHEET INDEX

LLATL.P.LT.LIN.L.F.L.C.L.A.MMAX.M.H.MFG.MIN.MISC.MON.N.I.C.N.T.S.NO.NOM.O.C.O.D.O.F.C.I.

O.F.O.I.

P.A.P.V.C.PC.P.C.C.

PLPTPLYWD.

LENGTH OF CURVELATITUDELOW POINTLEFTLINEARLINEAR FEETLANDSCAPE CONTRACTORLANDSCAPE ARCHITECTMETERMAXIMUMMANHOLEMANUFACTURERMINIMUMMISCELLANEOUSMONUMENTNOT IN CONTRACTNOT TO SCALENUMBERNOMINAL DIMENSIONON CENTEROUTSIDE DIAMETEROWNER FURNISHED,CONTRACTOR INSTALLEDOWNER FURNISHED,OWNER INSTALLEDPLANTING AREAPOLYVINYL CHLORIDE PIPEPOINT OF CURVATUREPOINT OF COMPOUNDCURVATUREPROPERTY LINEPOINT OF TANGENTPLYWOOD

PNL.PSIP.T.RR.O.W.RT.REQ'DREV.REINF.SAN.SECT.S.V.SIM.SDS.I.SSSPEC.SQ.S.F.S.Y.STA.S/STT.C.T.E.T&GT.W.T.S.TWP.TYP.UNOU.S.G.S.V.C.

PANELPOUNDS PER SQUARE INCHPRESSURE TREATEDRADIUSRIGHT OF WAYRIGHTREQUIREDREVISIONREINFORCINGSANITARYSECTIONSHEET VINYLSIMILARSTORM DRAINSTORM INLETSANITARY SEWERSPECIFICATIONS OR SPECIFIEDSQUARESQUARE FOOTSQUARE YARDSTATIONSTAINLESS STEELTANGENTTOP OF CURBTAPERED ENDTONGUE & GROOVETOP OF WALLTOP OF SLOPETOWNSHIPTYPICALUNLESS NOTED OTHERWISEU.S. GEOLOGICAL SURVEYVERTICAL CURVE

VAR.VERT.W/W/OW.W.M.W.V.

VARIESVERTICALWITHWITHOUTWOVEN WIRE MESHWATER VALVE

MECHANICAL ENGINEERMFIA INC. CONSULTING ENGINEERS2007 S.E. ASH ST.PORTLAND, OR 97214PHONE:503-234-0548CONTACT: JOHN VAN BLADEREN

ELECTRICAL ENGINEERDOUBLE "E" ENGINEERING315 ASH ST.MYRTLE POINT, OR 97458PHONE: 541.294.0587CONTACT: GREG PRIDE

SITE

SITE IMPROVEMENTSC0.10 EXISTING CONDITIONS MAPC0.20 EROSION CONTROL PLANC0.21 EROSION CONTROL DETAILSC1.00 SITE DEMO PLAN

C2.10 SITE LAYOUT PLANC3.00 CIVIL UTILITY PLANC3.10 SIGNING & STRIPING PLANC3.20 SIGN STRIPING PLANC4.00 GRADING PLANC5.00 LANDSCAPE PLANC6.00 TRAFFIC CONTROL PLANC9.00 CIVIL DETAILSC9.10 CIVIL DETAILSC9.11 CIVIL DETAILSC9.12 CIVIL DETAILSC9.13 CIVIL DETAILSC9.14 CIVIL DETAILSC9.15 CIVIL DETAILSC9.16 CIVIL DETAILSC9.20 SITE DETAILSC9.21 SITE DETAILSC9.22 SITE DETAILSE100 ELECTRICAL SITE PLANE101 ELECTRICAL SITE PLANE102 DETAILS

VISITOR INFORMATION CENTER BUILDING (V)V A2.1 FLOOR PLANV A2.3 ROOF PLAN / REFLECTED CEILING PLANV A3.1 BUILDING SECTIONSV A3.2 BUILDING SECTIONSV A4.1 BUILDING ELEVATIONSV A4.2 BUILDING ELEVATIONSV A5.1 DETAILSV A5.2 DETAILSV A5.3 DETAILSV A5.4 DETAILSV A5.5 DETAILSV A6.1 INTERIOR ELEVATIONSV A6.2 DETAILSV S1.0 STRUCTURAL NOTESV S1.1 STRUCTURAL NOTES, SPECSV S1.2 STRUCTURAL NOTES, SPECSV S2.1 FOUNDATION PLANV S2.3 ROOF FRAMING PLANV S4.1 DETAILSV S4.2 DETAILSV S5.1 DETAILS

V S6.1 DETAILSV S6.2 DETAILS

V P2.1 PLUMBINGV P6.1 PLUMBING SHCEDULESV M2.1 MECHANICALV M6.1 MECHANICAL SCHEDULESV E1.1 SCHEDULEV E2.1 LIGHTING PLANV E3.1 POWER / SIGNAL PLAN

PARK DEPARTMENT BUILDING (P)P A2.1 FLOOR PLANP A2.2 ROOF PLANP A3.1 BUILDING SECTIONS P A4.1 BUILDING ELEVATIONS P A5.1 DETAILS

P S1.0 STRUCTURAL NOTESP S1.1 STRUCTURAL NOTES, SPECSP S2.2 ROOF FRAMING PLANP S2.4 ROOF FRAMING PLANP S4.1 DETAILSP S5.1 DETAILSP S5.2 DETAILS

P MP2.1 HVAC & PLUMBINGP E1.1 SCHEDULEP E2.1 LIGHTING PLANP E3.1 POWER / SIGNAL PLAN

LANDSCAPEHGE, Inc.ARCHITECTS, ENGINNERS& PLANNERS333 S. 4TH STREETCOOS BAY, OREGON 97420PHONE: 541.269.1166 FAX: 541.269.1833CONTACT: STEPHANIE MARTELL

CIVIL ENGINEERHGE, Inc.ARCHITECTS, ENGINNERS& PLANNERS333 S. 4TH STREETCOOS BAY, OREGON 97420PHONE: 541.269.1166 FAX: 541.269.1833CONTACT: BARBARA NEGHERBON

CITY OF NORTH BENDSIMPSON PARK IMPROVEMENTS

TEAM

SHEET INDEX

ABBREVIATIONS

REDMOND

FLORENCE

REEDSPORT

GRANTS PASS

BANDONRIDDLE

MEDFORD

ROSEBURG

OAKLAND

KLAMATH FALLS

LAPINE

EUGENE

NEWPORT

ALBANY

SALEM

SISTERS

BEND

BAKER CITY

PRINEVILLE

BURNS

JOHN DAY

THE DALLES

ASTORIA

LA GRANDE

PENDLETON

PORTLAND

COQUILLE

NORTH BEND

GOLD BEACH

Copyright © 2017, HGE, Inc.

PROJECTNO.:

DATE:

REVISIONS:BYDATE

SHEETNO.DRAWNBY:

333

S. 4

TH S

TREE

TC

OO

S B

AY

, OR

EGO

N97

420

P: 5

41.2

69.1

166

F: 5

41.2

69.1

833

ww

w. h

ge1.

com

AR

CH

ITEC

TSEN

GIN

EER

SP

LA

NN

ER

S

2840

G

COOS BAY, OREGON

JOSEPH A. SLACK

OF

NO

O

GERET

ATS

TCET

IH

CRA

SI TE

ER

RED

MAY 2018

15.32.1

G0.1

CONSTRUCTION

CIT

Y O

F N

OR

TH B

END

SIM

PSO

N P

ARK

IMPR

OVE

MEN

TSH

IGH

WAY

101

, NO

RTH

BEN

D, O

REG

ON

1 VISITOR INFORMATION CENTER VIEW FROM SOUTHEAST

2 PARKS DEPARTMENT BUILDING VIEW FROM SOUTH EAST

5/30/2018

P A5.2 DETAILS

C2.00 SITE LAYOUT PLAN

5/18/20181 ADD#1

ADD#3

sceniza
Polygon
sceniza
Line
sceniza
Line
sceniza
Line
sceniza
Typewritten Text
3
sceniza
Typewritten Text
JD
sceniza
Polygon
james
Line
james
Line
james
Line
james
Typewritten Text
3
sceniza
Polygon
james
Line
james
Line
james
Line
james
Typewritten Text
3
james
Line
james
Line
james
Line
james
Typewritten Text
1
sceniza
Polygon
james
Line
james
Line
james
Line

2

A

WRAP IN 5/8" GYP.BD.

2-1/2 " X 7-1/2" STOREFRONT, WITH INSULATED GLAZING

2 X 6 TRIM

FROM 2 X 4WOOD SIDING, WEATHER BARRIER

STRUCTURAL STEEL COLUMN IN 2 X 6 WALL

B

8 X 8 STRUCTURAL STEEL TUBE COLUMN, SEE STRUCTURAL,PAINTED

CLOSURE TRIM METAL, SAME MATERIAL/FINISH AS STOREFRONT,FILL W/ RIGID INSUL.

0' - 2 5/16"

LARGE FRAME CURTAIN WALL SYSTEM

1' - 9"

MAX

.

0' -

1 7/

8"

0' - 6"

WRAP FORMLINER AROUND END OF WALL, TYP.

TYP. 6 INCH CONC. WALL

33"W. X 2-1/2" DEEP DOWNSPOUT,24 GA. PREFINISHED METAL

CLOSURE METAL, SAME MATERIALAS STOREFRONT

2 X 6 NAILER, POWER FASTENEDTO STEEL COLUMN

SEALANT7-1/2" STOREFRONT SYSTEM, WITH SILL PAN FLASHING BELOW

CLOSURE METAL TRIM,SAME MATERIAL ASSTOREFRONT

4

C

BREAK METAL CLOSURE TRIM FROM STOREFRONT MATERIAL

2' X 4-1/2" STOREFRONT SECTION,INSULATED GLASS (NOT SHOWN)

TRIM FROM 1 X

1 X 4, TYPICAL

2-1/2" X 7-1/2" STOREFRONT, INSULATED GLASS

2 X 6 SECURED TO STRUCTURAL COLUMN W/ SIMPSON TB SCREWS, @ 24" O.C. MAX.

C

1

0' - 6" 0' - 0 19/32" 0' - 5 1/2" 0' - 0 5/8"

GAP FRAMING TO CONC.

5/8" GYP. BD.

R-21 BATT INSUL.

0' - 0 13/32"

0' - 1 29/32"

VARING DEPTH OF FORMLINER

CONC. BASE WALL LINE

CAST IN PLACE EXTERIOR CONC. WALL WITH FORMLINER AT EXPOSED FACES, EDGES

OUTERMOST FACE OF FORMLINER

INNERMOST FACE OF FORMLINER

LARGE SECTION CURTAINWALL/ STOREFRONT

SEALANT

1 X TRIM, 1 X 4 TRIM SURROUND, TYPICAL

SEALANT

BASE WALL WIDTH

0' - 6"FORMLINER WALL TEXTURE

CHAMFER FORMLINER AT WALL END

C

LARGE SECTION CURTAINWALL/ STOREFRONT

SEALANT

SEALANT

FORMLINER WALL TEXTURE, RETURN TO TRIM

1 X 4 TRIM

2 X 6 TRIM

3" X 2-1/2" 24 GA. DOWNSPOUT, TYPICAL

5/8" STRUCT. SHEATHING, WEATHER BARRIER

5

CAST IN PLACE EXTERIOR CONC. WALL WITH FORMLINER AT EXPOSED FACES, EDGES

6 INCH CONCRETE WALL PLUS FORM LINER TEXTURE ON EXTERIOR, SMOOTH WALL INTERIOR

2 x 4 TRIM

0' -

6"

R-21 BATT INSUL.

5/8" GYP. BD.

GAP FRAMING TO CONCRETE

VARING DEPTH OF FORMLINER

2 X 4

CONC. MASONRY UNIT.

5/8" STRUCT. SHEATHING

1 1/2" RIGID INSULATION

WOOD SIDING

Copyright © 2017, HGE, Inc.

PROJECT NO.:

DATE:

REVISIONS:BYDATE

SHEET NO.DRAWN BY:

333

S. 4

TH S

TREE

TC

OO

S B

AY

, OR

EGO

N97

420

P: 5

41.2

69.1

166

F: 5

41.2

69.1

833

ww

w. h

ge1.

com

AR

CH

ITEC

TSEN

GIN

EER

SP

LA

NN

ER

S

2840

G

COOS BAY, OREGON

JOSEPH A. SLACK

OF

NO

O

GERET

ATS

TCET

IH

CRA

SI TE

ER

RED

MAY 2018

15.32.1

V A5.2

CONSTRUCTION

CIT

Y O

F N

OR

TH B

END

SIM

PSO

N P

ARK

IMPR

OVE

MEN

TSH

IGH

WAY

101

, NO

RTH

BEN

D, O

REG

ON

3" = 1'-0"3 PLAN - STOREFRONT @ COL.

3" = 1'-0"6 PLAN - STOREFRONT @ SOUTH WALL

3" = 1'-0"1 PLAN - CONC. WALL

3" = 1'-0"9 PLAN - CORNER @ SITTING

3" = 1'-0"12 PLAN - STOREFRT, COL, WALL

3" = 1'-0"2 PLAN - OUTSIDE CORNER3" = 1'-0"4 PLAN - STOREFRONT @ WALL

3" = 1'-0"5 PLAN - CONC/WD/STOREFRONT

3" = 1'-0"7 CONCRETE WALL @ CMU ABOVE LOWER ROOF

5/30/2018 ADD#3

james
Polygon

FLR SLAB0' - 0"

A

6 INCH CONCRETE WALL PLUS FORM LINER TEXTURE ON EXTERIOR, SMOOTH WALL INTERIOR

4-1/2" CONCRETE SLAB ON GRADE, VAPOR BARRIER

FORM LINER TEXTURED CONCRETE AT EXPOSED EXTERIOR FACES

TOP OF SLAB

FINISH GRADE

0' - 6 1/16"

FLR SLAB0' - 0"

6

8" CMU WALLS W/ ELASTOMERIC COATING ON EXTERIOR

EPOXY PAINT ON INTERIOR WALLS

CONC. SLAB ON GRADE, OVER VAPOR BARRIER

EXTERIOR 4" SLAB, POSITIVE SLOPE AWAY

CONT. FOOTING, SEE STRUCT.

TOP

OF

DO

OR

FR

AME

= 7'

-2"

1' -

0"

FLR SLAB0' - 0"

C

0' - 6"FACE OF SHEATHING TO GRID (@ STUD WALL ONLY)

CLEAR CEDAR SIDING, WEATHER BARRIER, 5/8" PLYWD SHEATHING

2 X 6 STUDS @ 16" O.C.

R-21 BATT INSUL.

5/8" GYP. BD., TYP. RBR BASE

SLAB ON GRADE, VAPOR BARRIER

GRID LINE = FACE OF CONC. BEYOND

CONT. FOOTING, SEE STRUCTURAL

S.S.

FLA

SHIN

G0'

- 11

"

0' -

6"

MIN., PROVIDE S.S. FLASHING, IF LESS

FLR SLAB0' - 0"

A

0' - 5 15/16"

0' - 5 15/16"

STOREFRONT, SEE SPECS.,SET IN SILL FLASHING

SLAB ON GRADE, OVER VAPOR BARRIER

EXTERIOR SLAB, SLOPE AWAY

0' -

0 3/

4"

SLOPE UP TO FLOORLINE @ DOORWAY

1/2" TURNED DOWN HEMMED EDGE

FLR SLAB0' - 0"

A

6 INCH CONCRETE WALL PLUS FORM LINER TEXTURE ON EXTERIOR, SMOOTH WALL INTERIOR

4-1/2" CONCRETE SLAB ON GRADE, VAPOR BARRIER

FORM LINER TEXTURED CONCRETE AT EXPOSED EXTERIOR FACES

TOP OF SLAB

FINISH GRADE

0' - 6 1/16"

FLR SLAB0' - 0"

A

0' - 5 15/16"

0' - 5 15/16"

STOREFRONT, SEE SPECS.,SET IN SILL FLASHING

SLAB ON GRADE, OVER VAPOR BARRIER

EXTERIOR SLAB, SLOPE AWAY

0' -

0 3/

4"

SLOPE UP TO FLOORLINE @ DOORWAY

1/2" TURNED DOWN HEMMED EDGE

CONC. FORMLINER, RETURN TO STOREFRONT

Copyright © 2017, HGE, Inc.

PROJECT NO.:

DATE:

REVISIONS:BYDATE

SHEET NO.DRAWN BY:

333

S. 4

TH S

TREE

TC

OO

S B

AY

, OR

EGO

N97

420

P: 5

41.2

69.1

166

F: 5

41.2

69.1

833

ww

w. h

ge1.

com

AR

CH

ITEC

TSEN

GIN

EER

SP

LA

NN

ER

S

2840

G

COOS BAY, OREGON

JOSEPH A. SLACK

OF

NO

O

GERET

ATS

TCET

IH

CRA

SI TE

ER

RED

MAY 2018

15.32.1

V A5.4

CONSTRUCTION

CIT

Y O

F N

OR

TH B

END

SIM

PSO

N P

ARK

IMPR

OVE

MEN

TS

Author

Author

HIG

HW

AY 1

01, N

OR

TH B

END

, OR

EGO

N

1 1/2" = 1'-0"1 WALL BASE @ CONCRETE

1 1/2" = 1'-0"2 WALL BASE @ CMU1 1/2" = 1'-0"3 WALL BASE @ STUD WALL

1 1/2" = 1'-0"4 WALL BASE @ STOREFRONT1 1/2" = 1'-0"5 WALL BASE @ CONCRETE & STUD

1 1/2" = 1'-0"6 WALL BASE @ STOREFRONT @ CONC. WALL

1P A3.1

1P A3.1

2P A3.1

2P A3.1

3P A3.1

3P A3.1

WH

B C D

1

2

3

A

20'-0

"20

'-0"

8'-0

"

80' - 0"

18' -

10"

48' -

0"

9' -

0"20

' -2"

10' - 0"3' - 0"10' - 0"3' - 0"10' - 0"3' - 0"10' - 0"4' - 2"12' - 6"6' - 0"

3' - 0"

24' -

0"24

' -0"

32' - 6"

8' - 0"

9' - 9"

TOILET105

OFFICE102

STORAGE104

SHOP103

TRUCK GARAGE& EQUIPMENT

STORAGE106

HALL101

106E

103A

105

102

101 106A106B106C106D

103B

CCC

A

B

B

A

D

A

A

A

A A

C

10' - 0" W x 10' - 0" HTYPICAL

HIGH BAY WINDOWSFOR NATURAL LIGHTING

ROOF LINE ABOVE

COVEREDENTRY

SLO

PED

SLA

B 3"

SIDE EXITWITH AWNING

ROOFOVERHANG

ABOVE

STORAGE

UTILITY SINK

WALL MOUNTDATA RACK

STORAGESTORAGE

PAINT @ TRANSITION SLAB

STEEL SECURITY GRILLE INSERTS

E. PANEL

22X36 ATTIC ACCESS HATCH22X36 ATTIC ACCESS HATCH

0' - 4"

10' -

0"

CONCRETE SLAB ON GRADE W/ VAPOR BARRIER

8' -

6" 5' -

4 1/

8"

9' - 0" 4' - 0" 9' - 0" 4' - 0" 9' - 0" 4' - 0" 10' - 6 1/2"

15' - 0 5/8" 32' - 5 3/8"

60' - 0"

4' -

2 1/

8"5'

- 4"

5' -

4"3'

- 0

7/8"

BRACKETS ABOVE

BRACKETS ABOVE

3' -

0"3'

- 2"

3' -

4"

EQ.

EQ.

Copyright © 2017, HGE, Inc.

PROJECTNO.:

DATE:

REVISIONS:BYDATE

SHEETNO.DRAWNBY:

333

S. 4

TH S

TREE

TC

OO

S B

AY

, OR

EGO

N97

420

P: 5

41.2

69.1

166

F: 5

41.2

69.1

833

ww

w. h

ge1.

com

AR

CH

ITEC

TSEN

GIN

EER

SP

LA

NN

ER

S

2840

G

COOS BAY, OREGON

JOSEPH A. SLACK

OF

NO

O

GERET

ATS

TCET

IH

CRA

SI TE

ER

RED

MAY 2018

15.32.1

P A2.1

CONSTRUCTION

CIT

Y O

F N

OR

TH B

END

SIM

PSO

N P

ARK

IMPR

OVE

MEN

TSH

IGH

WAY

101

, NO

RTH

BEN

D, O

REG

ON

1/4" = 1'-0"1 FLOOR PLAN

NORTH

3,724 SQ.FT.

3 5/30/2018

3

sceniza
Typewritten Text
JD
Catrina
Polygon
james
Line
james
Line
james
Line
james
Polygon
james
Line
james
Line
james
Line

RIDGE

CONT. GUTTER

CONT. GUTTER

CO

NT.

GU

TTER

CO

NT.

GU

TTER

CONT. GUTTER

CO

NT.

GU

TTER

BRACKETS BELOW

HIPHIP

HIPHIP

1P A3.1

1P A3.1

2P A3.1

2P A3.1

3P A3.1

3P A3.1

B C D

1

2

3

A

BRACKETS BELOW

E. PANEL1X4 TRIM

3

P A5.2

CEILING11' - 6"

4

P A5.2

9

P A5.2

13

P A5.2

LAV.

6" COVEFLOORING

BASE

42" GRAB BAR

18" GRAB BAR

FRP2'

-10"

3'-4 "

3'-4

"

1'-6

"

1'-0"

7'-2

"

CEILING11' - 6"

6" COVEFLOORING

BASE

ADASHOWER

36" GRAB BAR

18" GRAB BAR

FRP

3'-0

"

3'-2

"

7'-2

"

CEILING11' - 6"

Copyright © 2017, HGE, Inc.

PROJECTNO.:

DATE:

REVISIONS:BYDATE

SHEETNO.DRAWNBY:

333

S. 4

TH S

TREE

TC

OO

S B

AY

, OR

EGO

N97

420

P: 5

41.2

69.1

166

F: 5

41.2

69.1

833

ww

w. h

ge1.

com

AR

CH

ITEC

TSEN

GIN

EER

SP

LA

NN

ER

S

2840

G

COOS BAY, OREGON

JOSEPH A. SLACK

OF

NO

O

GERET

ATS

TCET

IH

CRA

SI TE

ER

RED

MAY 2018

15.32.1

P A2.2

CONSTRUCTION

CIT

Y O

F N

OR

TH B

END

SIM

PSO

N P

ARK

IMPR

OVE

MEN

TS

Author

HIG

HW

AY 1

01, N

OR

TH B

END

, OR

EGO

N

1/8" = 1'-0"1 ROOF PLAN

3/8" = 1'-0"2 GARAGE SOUTH

3/8" = 1'-0"3 TOILET SOUTH3/8" = 1'-0"4 TOILET WEST

WINDOW SCHEDULE

MARK W x H DESCRIPTION STYLE COUNT REMARKS

A 36" x 48" Vinyl Windows PictureWindow

16 TEMPEREDGLAZING

B 48" x 30" Vinyl Windows PictureWindow

4 TEMPEREDGLAZING

D 36" x 48" Vinyl Windows TEMPEREDGLAZING

C 48" x 24" Vinyl Windows Picture 8 TEMPEREDGLAZING

TOTAL: 30

Picture Window

CasementWindow

7

CasementWindow

14

2

1

43 ADD#3

5/15/2018 ADD#11

sceniza
Polygon
sceniza
Typewritten Text
1
sceniza
Line
sceniza
Line
sceniza
Line
sceniza
Polygon
sceniza
Line
sceniza
Line
sceniza
Line
sceniza
Typewritten Text
3
sceniza
Polygon
james
Typewritten Text
5/30/2018
sceniza
Line
sceniza
Line
sceniza
Line
sceniza
Polygon
sceniza
Line
sceniza
Line
sceniza
Line
alocati
Joe's Stamp

Recommended