+ All Categories
Home > Documents > ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and...

ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and...

Date post: 04-Jun-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
38
ADVANCEMENT OF TRANSMISSION SYSTEM INTERCONNECTION: CASE Second Meeting of Taskforce 2 on April 16 and 17, 2014 INTERCONNECTION: CASE OF NEPAL Surendra Rajbhandari Director, Nepal Electricity Authority
Transcript
Page 1: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

ADVANCEMENT OFTRANSMISSION SYSTEM

INTERCONNECTION: CASEOF NEPAL

Second Meeting of Taskforce 2 on

April 16 and 17, 2014

ADVANCEMENT OFTRANSMISSION SYSTEM

INTERCONNECTION: CASEOF NEPAL

Surendra RajbhandariDirector, Nepal Electricity Authority

Page 2: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Overview of Nepal PowerSystem

Total installed capacity: 770 MW

Under Construction: 1200 MW

Transmission Lines: 2640 cct km

Grid Substations capacity: 1900 MVA

Average annual growth rate of peak: 10%

Average annual growth rate of energy: 8.5%

Access to grid electricity: 63%

Peak Load in FY 2013/14= 1200 MW

Capacity shortage in FY 2013/14= 600 MW

Total installed capacity: 770 MW

Under Construction: 1200 MW

Transmission Lines: 2640 cct km

Grid Substations capacity: 1900 MVA

Average annual growth rate of peak: 10%

Average annual growth rate of energy: 8.5%

Access to grid electricity: 63%

Peak Load in FY 2013/14= 1200 MW

Capacity shortage in FY 2013/14= 600 MW

Page 3: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Installed Capacity: 770.9 MW

In Grid 766.4MW Off Grid 4.5 MW

Hydro 712.99 MW Thermal 53.41 MWHydro 712.99 MW Thermal 53.41 MW

ROR 620.99 MW Storage 92 MW

IPP 240.5 MW NEA 380.99 MW

Page 4: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

NEA Transmission System DiagramI

Lamosangu

Trishuli

AnarmaniM/ nagar

KGA

Modi

MMRS

Dubi

Jhim

Butwal BhrtprHtd

Parwanipur India

Chapur Dhalke LahanLamai

Birgunj

Tanakpur

Page 5: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Existing Power ExchangeArrangement

Nepal and India has been exchanging power formany years. Power is being exchanged and tradedmainly through 8 points along the Indo-Nepal border. Present level of exchange: 50 MW, trading: 150

MW. Power exchanges mainly through 33kV and 132kV

links. To facilitate power exchange, two committees exist:

Power Exchange Committee constituted in 1992 andJoint Commission on Water Resources (2000).

Nepal and India has been exchanging power formany years. Power is being exchanged and tradedmainly through 8 points along the Indo-Nepal border. Present level of exchange: 50 MW, trading: 150

MW. Power exchanges mainly through 33kV and 132kV

links. To facilitate power exchange, two committees exist:

Power Exchange Committee constituted in 1992 andJoint Commission on Water Resources (2000).

Page 6: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Existing Interconnectionswith India

Transmission Link EvacuationCap. (MW)

Traded,MW

VoltageLevel, kV

Kusaha--Kataiya 130 80 132Gandak -Rampur 50 25 132Gandak -Rampur 50 25 132Mahendranagar-Tanakpur

50 30 132

Kataiya- Rajbiraqj 10 8 33Raxual- Birgunj 10 10 33Sitamadhi-Jaleswor 10 8 33Nepalgunj-Nanpara 10 8 33Jayanagar-Siraha 8 8 33

Page 7: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Under Construction andPlanned Interconnections

with IndiaTransmission Link Transfer

Cap.(MW)

VoltageLevel, kV

Status

Dhalkebar- Muzzafarpur 1200 400 Undercons.

Dhalkebar- Muzzafarpur 1200 400 Undercons.

Bardaghat- Gorakhpur 1800 400 PlannedDuhabi- Jogbani 1800 400 Identified

& ProposedOther Links To be

identified

Page 8: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Existing Power ExchangeArrangement

Electricity Act and Hydropower policyprovides provision for electricity trade. PTC, India is the nodal body for trade. Power trade and exchange exist between

India & Bhutan and India & Bangladesh. While Bhutan is the sole power exporter,

Nepal and Bangladesh are importers Nepal is facing critical power shortage and is

becoming net importer. Power imports willincrease until 2016/17.

Electricity Act and Hydropower policyprovides provision for electricity trade. PTC, India is the nodal body for trade. Power trade and exchange exist between

India & Bhutan and India & Bangladesh. While Bhutan is the sole power exporter,

Nepal and Bangladesh are importers Nepal is facing critical power shortage and is

becoming net importer. Power imports willincrease until 2016/17.

Page 9: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

NEA Transmission SystemExpansion Plan

To alleviate congestion and improve systemreliability. To increase the ability to distribute available

power to meet existing and future demands To meet NEA’s contractual obligation for

transmission with various power producers To increase NEA’s ability to import/export power To replace older transmission lines that are in

poor condition and no longer reliable.

To prevent equipment overloads and low voltages.

To alleviate congestion and improve systemreliability. To increase the ability to distribute available

power to meet existing and future demands To meet NEA’s contractual obligation for

transmission with various power producers To increase NEA’s ability to import/export power To replace older transmission lines that are in

poor condition and no longer reliable.

To prevent equipment overloads and low voltages.

Page 10: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

NEA Transmission SystemExpansion Plan

• NEA annually reviews its transmissionexpansion plan. Of late, NEA has stoppedupdating TSMP. It simply carries out gridimpact study for IPP projects.

• For the past few years, the country is goingthrough the biggest energy crisis ever.

• Nepal already has “10,000 MW in 10 yearsand 25,000 MW in 20 years” plans unveiledto ease out crisis. This has lead to an ad hocrevised transmission plan.

• NEA annually reviews its transmissionexpansion plan. Of late, NEA has stoppedupdating TSMP. It simply carries out gridimpact study for IPP projects.

• For the past few years, the country is goingthrough the biggest energy crisis ever.

• Nepal already has “10,000 MW in 10 yearsand 25,000 MW in 20 years” plans unveiledto ease out crisis. This has lead to an ad hocrevised transmission plan.

Page 11: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

NEA Transmission SystemExpansion Plan

The revised plan is basically designed to easeevacuation of power to be generated by IPPs.

DoED has already issued survey license formore than 9,000 MW.

To address the power evacuation problemsforeseen, the Government and NEA havedecided to develop many transmission links inphase wise manner. Plan is silent on how these will be

implemented.

The revised plan is basically designed to easeevacuation of power to be generated by IPPs.

DoED has already issued survey license formore than 9,000 MW.

To address the power evacuation problemsforeseen, the Government and NEA havedecided to develop many transmission links inphase wise manner. Plan is silent on how these will be

implemented.

Page 12: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Potential for PowerTrade from Nepal

• Total theoretical potential: >83,000 MW

• Economically feasible: 43,000 MW

• Storage capacity plants: 21,400 MW

• Existing capacity: 770 MW

• Projects under construction:

NEA and subsidiary companies = 1002 MW

IPPs = 297 MW

• Total theoretical potential: >83,000 MW

• Economically feasible: 43,000 MW

• Storage capacity plants: 21,400 MW

• Existing capacity: 770 MW

• Projects under construction:

NEA and subsidiary companies = 1002 MW

IPPs = 297 MW

Page 13: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Hydropower Potential of Nepal

Hydropower Potential of Nepal, MW

River Basin Gross Economical

Sapta Koshi Basin 22,350 10,860Sapta Koshi Basin 22,350 10,860

Sapta Gandaki Basin 20,650 5,270

Karnali and MahakaliBasin 36,180 25,125

Southern River Basin 4,110 878

Total 83,290 42,133

Page 14: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Load Forecast

-

1,000

2,000

3,000

4,000

5,000

6,000

-

5,000

10,000

15,000

20,000

25,000

30,000

Pea

k L

oa

d (

MW

)

En

erg

y (

GW

h)

Fiscal Year

Energy

Peakload

-

1,000

2,000

3,000

4,000

5,000

6,000

-

5,000

10,000

15,000

20,000

25,000

30,000

Pea

k L

oa

d (

MW

)

En

erg

y (

GW

h)

Fiscal Year

Energy

Peakload

Page 15: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Load ForecastFiscal Year Energy, GWh Peak Load, MW

2014/15 6,510 1,4262015/16 7,054 1,5432016/17 7,576 1,6542017/18 8,433 1,8372017/18 8,433 1,8372018/19 9,284 2,0192019/20 10,177 2,2092020/21 10,899 2,3612021/22 11,669 2,5232022/23 12,491 2,695

Page 16: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Load Forecast

Fiscal Year Energy, GWh Peak Load, MW2023/24 13,409 2,8882024/25 14,462 3,1092025/26 15,591 3,3462026/27 16,798 3,5982025/26 15,591 3,3462026/27 16,798 3,5982027/28 18,086 3,8662028/29 19,538 4,1692029/30 21,097 4,4932030/31 22,774 4,8412031/32 24,584 5,2162032/33 26,544 5,622

Page 17: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Planned Generation

S. No Year ProjectsInstalled Capacity (MW)

ROR Storage

1 2014/2015Chamelia 30Kulekhani III 14PPA concluded 72

Total in 2014/2015 102 14Total in 2014/2015 102 14

2 2015/16Upper Trisuli 3 A 60Upper Sanjen 14.8PPA Concluded 166

Total in 2015/2016 240.8 03

2016/17Upper Tamakosi 456Sanjen 42.5PPA Concluded 492

Total in 2016/2017 992 0

Page 18: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Planned and Proposed Generation

S. N. Year ProjectsInstalled Capacity

(MW)ROR Storage

42017/2018

Upper Modi A 42

Rahughat 324

2017/2018 Rahughat 32

PPA Concluded 217

Total in 2017/20178 291

5 2018/2019

Middle Bhotekosi 102

Rasuwagadhi 111

Trisuli 3 B 40

PPA concluded 246

Total in 2018/2019 499

Page 19: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Planned and Proposed Generation

S. No. Year Projects Installed Capacity,MW

ROR StorageTanahu 140

6 2019/2020

Tanahu 140Tamakosi V 87PPA Concluded 9.6

Total in 2019/2020 96.6 140

7 2020/2021Upper Arun 335PPA applied 200

Total in 2020/2021 535

Page 20: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Planned and Proposed Generation

S. No. Year Projects Installed Capacity,MW

ROR StorageROR Storage

8 2022/23 Dudhkosi Storage 300

9 2024/25 Tamor Storage 530

10 2025/26 Nalsing Gad Storage 400

Total upto 2025/26 2756.8 1314

Page 21: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Planned and ProposedGeneration

• Planned and proposed generation does notinclude: Export projects: Arun 3 (900 MW), Upper

Karnali (900 MW), Upper Marsyangdi (600MW), Likhu IV ( 120 MW)

Generation projects under study by NEA: AndhiKhola (180 MW), Uttar Ganga (300 MW),Kaligandaki 2 (660 MW)

Budhi Gandaki (600 MW), West Seti (750 MW)

Private sector projects not included after 2020/21

• Planned and proposed generation does notinclude: Export projects: Arun 3 (900 MW), Upper

Karnali (900 MW), Upper Marsyangdi (600MW), Likhu IV ( 120 MW)

Generation projects under study by NEA: AndhiKhola (180 MW), Uttar Ganga (300 MW),Kaligandaki 2 (660 MW)

Budhi Gandaki (600 MW), West Seti (750 MW)

Private sector projects not included after 2020/21

Page 22: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Transmission Projects UnderConstruction

Project Km Year Cost,M$

Source

Kusum-Hapure 132 kV TL 20 2013/14 6.30 GN, NE

Singati-Lamasangu 132 kV TL 45 2013/14 19.50 GN, NE

Hetauda- Siuchatar 132kVSecond Circuit

40 2013/14 2.80 GN, NE

Dumre-Damauli-Marsyangdii132 kV TL

56 2014/15 18.62 ADB, NG,NE

Butwal- Kohalpur 132 kVSecond Circuit

208 2013/14 17.30 ADB, NG,NE

Khimti-Dhalkebar 220 kV 75 2013/14 28.00 WB, NG, NE

Hetauda- Bharatpur 220 kV 72 2014/15 28.50 WB, NG, NE

Page 23: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Transmission Projects UnderConstruction

Project Km Year Cost, M$ Source

Bharatpur-Bardghat 220kV TL

73 2014/15 30.00 WB, NG, NE

Kabeli 132 kV TC 70 2015/16 41.00 WB, NG, NE

TCB 132 kV TL 28 2015/16 23.00 GN, NE

Kohalpur-Mahendranagar132 kV 2nd Circuit

198 2015/16 20.00 ADB, NG,NE

Dhalke-Bhitta 400kV TL 40 2014/15 30.00 IN, NG, NE

Hetauda- Dhalkebar-Duhabi 400kV TL

285 2015/16 139.00 WB, NG, NE

Trishuli 3 B Hub-Matatirtha 220 kV TL

46 2015/16 22.70 CH, NG, NE

Total 1256 426.72

Page 24: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Transmission Projects: Planned

Project Km Year Cost, M$ Source

Modi-Lekhnath 132 kV TL 45 2016/17 12.15 IN, NG, NE

Samundratar-Trishuli 3B 132kV TL

18 2015/16 7.00 ADB*, NG, NE

Baneshwor-Bhakt 132 kV 12 2016/17 25.36 NG, NEBaneshwor-Bhakt 132 kV 12 2016/17 25.36 NG, NE

Chilime-Trishuli 220kV TL 40 2015/16 35.00 EIB*, NG, NE

Koshi 220 kV Trans Corridor 110 2016/17 90.00 IN, NG, NE

Kali Gandaki 220 kV TC 150 2017/18 130.00 ADB*, NG, NE

Marsyangdi 220 kV TC 115 2018/19 92.00 ADB*, NG, NE

Marsyangdi-Kath 220 kV TL 85 2017/18 38.00 ADB*, NG, NE

Tamakoshi -Kath 220 kV TL 100 2016/17 75.00 AD, NG,NE

Solu 132 kV Trans Corridor 90 2016/17 15.75 IN, NG, NE

Total 765 520.26

Page 25: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Transmission Projects: Planned& Proposed

Project Km Year Cost, M$ Source

Ramechhap-Garjang-Khimti132kV TL

50 2015/16 13.50 NG, NE

Hapure-Tulsipur 132kV TL 20 2015/16 4.50 NG, NEHapure-Tulsipur 132kV TL 20 2015/16 4.50 NG, NE

Dordi 132 kV Corridor 20 2016/17 4.50 NG, NE

Gulmi-Lumbini 132 kV TL 30 2018/19 9.45 NG, NE

Dhalkebar-Loharpatti 132 kV TL 20 2018/19 9.72 NG, NE

Lekhnath-Damauli 220 kV TL 45 2015/16 16.88 AD, NG, NE

Damauli-Bharatpur 220 kV TL 45 2016/17 22.50 AD, NG, NE

Karnali132 kV Corridor 60 2015/16 20.00 NG, NE

Budhiganga-Pahalpr 132 kV TL 75 2017/18 20.00 NG, NE

Total 365 121.05

Page 26: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Transmission Projects: Proposed

Project Km Year Cost, M$ SourceKohalpur-Surkhet 132 kV TL 55 2016/17 20.00 NG, NEGulmi - Chanauta 132kV TL 60 2016/17 24.00 NG, NEBajhang -Attariya 132 kV TL 110 2016/17 40.00 TBDSurkhet-Dail-Jumla 132kV TL 110 2016/17 40.00 TBDSurkhet-Dail-Jumla 132kV TL 110 2016/17 40.00 TBDKaligandaki-Jhimruk 132kV TL 90 2016/17 36.00 NG, NEHetauda- Butwal 400 kV TL 190 2017/18 152.63 TBDLamki-Mahendra 400 kV TL 105 2021/22 84 TBDButwal- Lamki 400 kV TL 220 2021/22 176.00 TBDBardaghat-Gorakhpur 400kV 40 2019/20 32 NG, NE

Duhabi-Jogbani 400kV TL 20 2019/20 16.00 NG, NEDudhkosi 400 kV Corridor 100 2022/23 80.00 TBD

Total 1060 700.13

Page 27: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Planned and ProposedTransmission

S. N. Year Transmission Line, cct km132 kV 220 kV 400 kV

1 2014/15 354 440 802 2015/16 414 172 5702 2015/16 414 172 5703 2016/17 500 400 2004 2017/18 710 370 4705 2018/19 100 2306 2019/20 807 2020/21 6508 2022/23 180

Total 2078 1612 2230

Page 28: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Planned and ProposedTransmission

• The total cost of planned and proposedtransmission line projects is estimated atUS$1.8 billion excluding the cost of RoW.

• TL development is difficult in Nepal. The costof RoW is higher than the project cost.

• NEA plans to complete about 2400 cct km oftransmission lines over the next 5 years. Thiswill enhance the transfer capacity substantially.

• NEA is reviewing its long term TSEP.

• The total cost of planned and proposedtransmission line projects is estimated atUS$1.8 billion excluding the cost of RoW.

• TL development is difficult in Nepal. The costof RoW is higher than the project cost.

• NEA plans to complete about 2400 cct km oftransmission lines over the next 5 years. Thiswill enhance the transfer capacity substantially.

• NEA is reviewing its long term TSEP.

Page 29: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

27th April 2011 29

Page 30: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Capacity Balance

Year Dry Season, MWGen. Peak demand Shortage

2014/15 735 1384 6492015/16 1010 1496 4862015/16 1010 1496 4862016/17 1071 1604 5332017/18 1694 1782 882018/19 1807 1958 1512019/20 1922 2142 2202020/21 2016 2290 2742021/22 2016 2447 4312022/23 2015 2615 600

Page 31: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Capacity Balance

Year Wet Season, MWPeak

DemandGen. Shortage

(peak)Surplus(peak)

Surplus (offpeak)

2014/15 1315 972 343 0 692015/16 1421 1189 232 0 2612015/16 1421 1189 232 0 2612016/17 1524 1363 161 0 404

2017/18 1693 1987 0 294 11262018/19 1860 2217 0 357 12962019/20 2035 2492 0 457 15332020/21 2176 2501 0 326 14482021/22 2325 2628 0 303 15082022/23 2484 2628 0 144 1428

Page 32: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

3000

4000

5000

6000

7000En

ergy

, GW

hEnergy Availability

0

1000

2000Ener

gy, G

Wh

YearEnergy Availability, GWh Surplus Energy Availability, GWh Deficit

Page 33: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Rationale for RegionalCooperation

• Overall: Economic growth, cooperation and solidarity• Technical rationale: Optimum use of resources and

diversity in load profile facing each country.• Social rationale: Poverty alleviation; beneficial

impacts on health, education and quality of life.• Economic rationale: Regional cooperation would

result in•Improved reliability of supply•Enhanced trade•Environmental benefits from reduced level of

carbon emissions

• Overall: Economic growth, cooperation and solidarity• Technical rationale: Optimum use of resources and

diversity in load profile facing each country.• Social rationale: Poverty alleviation; beneficial

impacts on health, education and quality of life.• Economic rationale: Regional cooperation would

result in•Improved reliability of supply•Enhanced trade•Environmental benefits from reduced level of

carbon emissions

Page 34: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Issues/Challenges to RegionalTransmission Advancement

• Regional planning for optimal utilizationof energy resources

• National plan to support regional plan

• Creation of regional power market

• Promotion of private participation inpower sector including transmission

• Environmental issues

• Regional planning for optimal utilizationof energy resources

• National plan to support regional plan

• Creation of regional power market

• Promotion of private participation inpower sector including transmission

• Environmental issues

Page 35: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Issues/Challenges to RegionalTransmission Advancement

• Regulatory institution

• Performance standards:thermal, voltage, protectionsystem, stability, contingency level

• Harmonization of technicalspecifications, standards, GridCodes, reliability standards

• Cost allocation / timely recovery.

• Regulatory institution

• Performance standards:thermal, voltage, protectionsystem, stability, contingency level

• Harmonization of technicalspecifications, standards, GridCodes, reliability standards

• Cost allocation / timely recovery.

Page 36: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Barriers

• Political barriers

• Institutional barriers

• Legal framework and provision

• Pricing policies

• Financial barriers

• Political barriers

• Institutional barriers

• Legal framework and provision

• Pricing policies

• Financial barriers

Page 37: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

Way Forward

• Data sharing and joint planning of potential powerprojects including transmission networks

• Reinforcement and expansion of individualtransmission system

• Greater interaction at both technical as well aspolitical level to discuss the issues of power trade

• Creation of a regional fund

• Reforming individual country markets

• Harmonization of standards, codes and planning

• Data sharing and joint planning of potential powerprojects including transmission networks

• Reinforcement and expansion of individualtransmission system

• Greater interaction at both technical as well aspolitical level to discuss the issues of power trade

• Creation of a regional fund

• Reforming individual country markets

• Harmonization of standards, codes and planning

Page 38: ADVANCEMENT OF TRANSMISSION SYSTEM …sari-energy.org/.../Presentations/Nepal.pdfElectricity Act and Hydropower policy provides provision for electricity trade. PTC, India is the nodal

“To accomplish great things,we must not only act, but also dream;not only plan, but also believe”.

Anatole France

Thank You

“To accomplish great things,we must not only act, but also dream;not only plan, but also believe”.

Anatole France

Thank You


Recommended