AECL-6416
ATOMIC ENERGY ffjj^ L'ENERGIE ATOSVIIQUEOF CANADA LIMITED V f i j DU CANADA
A DISPOSAL CENTRE FOR IMMOBILIZED NUCLEAR WASTE:
CONCEPTUAL DESIGN STUDY
UN CENTRE DE STOCKAGE POUR LES DECHETS NUCLEAIRES FIXES:
ETUDE DE CONCEPTION
Acres Consulting Services Limitedin association with/en association avec
RE/SPEC Inc.Dilworth, Secord, Meagher and Associates
and/et
Design and Project Engineering Branchin association with/en association avecW. L. Wardrop and Associates Limited
Whiteshell Nuclear Etablissement de RecherchesResearch Establishment Nucleaires de Whiteshell
Pinawa, Manitoba ROE 1L0
February 1980 fevrier
ATOMIC ENERGY OF CANADA LIMITED
A DISPOSAL CENTRE FOR IMMOBILIZED NUCLEAR WASTE:CONCEPTUAL DESIGN STUDY
by
Acres Consulting Services Limitedin association with
RE/SPEC Inc.Dilworth, Secord, Meagher and Associates
and
Design and Project Engineering Branchin association with
W.L. Wardrop and Associates Limited
Whiteshell Nuclear Research EstablishmentPinawa, Manitoba ROE 1L0
1980 February
AECL-6416
UN CENTRE DE STOCKAGE POUR LES DECHETS NUCLEAIRES FIXES:ETUDE DE CONCEPTION
par
Acres Consulting Services Limiteden association avec
RE/SPEC Inc.Dilworth, Secord, Meagher and Associates
et
Le Service d'Ingénierie de Conceptions et Projetsen association avec
W.L. Wardrop and Associates Limited
RESUME
Ce rapport décrit une étude conceptuelle d'un centre de stock-age pour les déchets nucléaires fixés. Les installations en surfacecomprennent des usines de prépara.ion des cylindres en acier contenantles déchets nucléaires fixés dans le verre, des bâtiments à chevaletd'extraction de puits et toutes les installations de soutien nécessai-res. L'enceinte de stockage souterraine est située à un seul niveau àune profondeur de 1000 m. Les cylindres de déchets sont mis er; placedans des trous de sondage des planchers de galeries. Toutes les instal-lations en surface et souterraines sont décrites, les opérations et lesprogrammes sont résumés et les prévisions de coûts et les besoins enmain d'oeuvre sont indiqués.
L'Energie Atomique du Canada LimitéeEtablissement de Recherches Nucléaires de Whiteshell
Pinawa, Manitoba ROE 1L01980 février
AECL-6416
A DISPOSAL CENTRE FOR IMMOBILIZED NUCLEAR WASTE:CONCEPTUAL DESIGN STUDY
by
Acres Consulting Services Limitedin association with
RE/SPEC Inc.Dilworth, Secord, Meagber and Associates
and
Design and Project Engineering Branchin association with
W.L. Wardrop and Associates Limited
ABSTRACT
This report describes a conceptual design of a disposal centrefor immobilized nuclear waste. The surface facilities consist of plantsfor the preparation of steel cylinders containing nuclear waste immobil-ized in glass, shaft headframe buildings and all necessary supportfacilities. The underground disposal vault is located on one level at adepth of 1000 m. The waste cylinders are einplaced into boreholes in thetunnel floors. All surface and subsurface facilities are described,operations and schedules are summarized, and cost estimates and manpowerrequirements are given.
Atomic Energy of Canada LimitedWhiteshell Nuclear Research Establishment
Pinawa, Manitoba ROE 1L01980 February
AECL-6416
CONTENTS
Page
1. INTRODUCTION 1
2. THE CONCEPT 3
2.1 FUEL CYCLE AND WASTE DISPOSAL SCENARIO 32.2 IMMOBILIZED WASTE QUANTITIES, CHARACTERISTICS
AND CONTAINER DESIGN 5
2.2.1 Quantities 52.2.2 Characteristics 52.2.3 Container 6
2.3 DISPOSAL CENTRE FACILITIES AND OPERATIONS 7
2.3.1 Surface Facilities 72.3.2 Vault 8
TABLE 10FIGURES 11
3. SURFACE FACILITIES 15
3.1 SITE LAYOUT 15
3.1.1 Description 15
3.1.2 Materials Movement 16
3.2 DESCRIPTION OF FACILITIES 17
3.2.1 Waste Immobilization Plants 17
3.2.1.1 Process Description 173.2.1.2 Reference Plant Description 19
3.2.2 Wacte Shaft Headframe 203.2.3 Service Shaft Headframo. 213.2.4 Backfill Preparation Plant 213.2.5 Low-Level Liquid Waste (LLW) Treatment 223.2.6 Solid Waste Management 223.2.7 Services 233.2.8 Environmental Laboratory 24
FIGURES 25
.../cont.
CONTENTS, continued
Page
4. VAULT 35
4.1 STUDY METHODOLOGY, SPECIFICATIONS ANDDESIGN CRITERIA 35
4.4.1 General Specifications and Constraints 354.1.1.1 Setting 35U.I.1.2 Operations 36
4.2 THERMAL-ROCK MECHANICS ANALYSIS 364.3 LAYOUT 39
4.3.1 Shafts and Major Drifts 404.3.2 Panels 414.3.3 Rooms 42
4.4 VAULT DEVELOPMENT AND OPERATION 42
4.4.1 Master Schedule 424.4.2 Access and Demonstration, Phase I 444.4.3 Primary Development, Phase II 444.4.4 Panel Development and Emplacement,
Phase III 454.4.5 Maintenance and Decommissioning,
Phase IV 46
4.5 FACILITIES AND EQUIPMENT 46
4.5.1 Rock Excavation ind Handling 464.5.1.1 Access and Demonstration 464.5.1.2 Primary Development 474.5.1.3 Panel Development 48
4.5.2 Shafts and Hoists 50
4.5.2.1 Service Shaft and Hoist 504.5.2.2 Waste Shaft and Hoist 514.5.2.3 Ventilation Shafts 52
4.5.3 Container Handling 52
.../cont.
Services4.5.4.14.5.4.24.5.4.34.5.4.44.5.4.5
VentilationCompressed AirWaterDrainage and Pumping SystemPower System
CONTENTS, continued
Page
4.5.4 Services 545456575759
4.6 BACKFILLING AND SEALING 60
TABLE 63FIGURES 64
5.. COSTS AND MANPOWER REQUIREMENTS 77
3.1 COSTS 77
5.1.1 Basis for Cost Estimates 77
5.1.2 Surface Facilities 73
5.1.3 Vault 79
5.2 MANPOWER REQUIREMENTS 80
5.2.1 Surface Facilities 80
5.2.2 Vault 80TABLES 82FIGURE 92
6. SUMMARY, CONCLVSIOm AND RECOMMENDATIONS 93
6 1 SUMMARY AND CONCLUSIONS 93
6.1.1 General 93
6.1.2 Technical Feasibility 936.1.3 Schedules 956.1.4 Cost Estimates 956.1.5 Manpower Requirements 96
.../cont.
CONTENTS, concluded
Page
6.2 RECOMMENDATIONS 97
6.2.1 Surface Facilities 976.2.2 Vault 98
TABLE 100
7. REFERENCES 101
APPENDIX A BIBLIOGRAPHY OF SUPPORTING STUDIES 102
APPENDIX B THERMAL-ROCK MECHANICS 104
1. INTRODUCTION
A program has been initiated by Atomic Energy of Canada
Limited (AECL) to develop methods for the disposal of irradiated fuel
and/or high-level radioactive wastes . Since the reference concept is
burial deep underground in crystalline rock, a major segment of the
program involves the design of an underground vault which will safely
Isolate nuclear wastes from the biosphere. This report presents a
synthesis of the results of conceptual studies, carried out in fiscal
year 1978, on the deaign of a disposal centre for immobilized nuclear
waste. The main surface facility is an immobilization and packaging
plant for the waste. Shafts link the surface to the underground vault.
The wastes are emplaced in rooms underground, and the rooms are then(2)
backfilled. A companion report describes a similar disposal centre
for immobilizing and disposing of irradiated fuel.
Both irradiated fuel and immobilized waste disposal concepts
have been studied because the Canadian government has not yet determinedA
which route the Canadian nuclear program will follow. Irradiated CANDU
fuel contains fissionable material whose recoverable energy is at least
equivalent to that of natural uranium and is several times that of
natural uranium if it is used in conjunction with thorium. The key to
extracting this energy is fuel recycle, which includes chemical sepa-
ration of the true radioactive waste from the other material in the
fuel. However, there is considerable debate in the international
community concerning the future role of commercial reprocessing. Until
the government has made its decision, therefore, it is essential to
develop technologies that can immobilize and dispose of either type of
waste.
CANada Deuterium Uranium
- 2 -
The objectives of these studies were to develop a reference
design for the vault, and to develop designs fcr the attendant waste
handling, backfill and sealing operations, and for the surface immo-
bilization plants and surface services. Costs and manpower requirements
were also determined. Emphasis was placed on analysis of technical
feasibility and on studying one complete scenario in reasonable detail,
rather than on investigating a broad range of processing and disposal
alternatives. The vault layout and container emplacement designs were
derived from preliminary studies previously performed by Acres Con-(3)
suiting Services Limitedv .
The past year's studies were only one stage in the on-going
investigation. They have not developed the final designs or even neces-
sarily complete ones Other emplacement and vault layout options, as
well as surface fa iities, will be investigated in future studies.(2)
However, the des ,ns presented here and in the companion report are a
reference to which the other alternatives can be compared.
Surface facility design was performed by the Design and
Project Engineering Branch, Whiteshell Nuclear Research Establishment,
Atomic Energy of Canada Limited, in association with W.L. Wardrop and
Associates Limited. The study coordinator was M.M. Ohta (AECL).
The underground vault design and analyses were performed by
Acres Consulting Services Limited in association with RE/SPEC Inc. and
Dilworth, Secord, Meagher and Associates Limited. R.G. Charlwood
(Acres) was the study manager and A.S. Burgess was the study engineer.
The disposal centre study was funded by the Whiteshell Nuclear
Research Establishment (WNRE), Atomic Energy of Canada Limited, with
H.Y. Tammemagi acting as technical coordinator.
2. THE CONCEPT
2.1 FUEL CYCLE AND WASTE DISPOSAL SCENARIO
The disposal centre has been designed to immobilize and dis-
pose of all high-level waste which would be produced by reprocessing all
the irradiated fuel discharged from all once-through natural uranium
fuelled CANDU-PHW (CAMada IJeuterium Uranium - .Pressurized Heavy Vfater)
reactors in Canada up to and including the year 2016. The CANDU fuel
cycle, with reprocessing, is illustrated in Figure 2-1.
The rate of production of reprocessing waste, and hence of
waste packages, has been estimated based on the following assumptions:
1. All irradiated natural uranium fuel discharged from standard
CANDU-PHW reactors in Canada up to the year 2016 will be re-
processed. The separated plutonium and uranium are assumed to
be used in advanced fuel cycles. Only the waste from re-
processing the once-through fuel is considered in this report.
2. The fuel will have been irradiated to 588 GJ/kg U, and cooled
for a minimum of 10 years before reprocessing.
3. The arisings are based on a reactor development scenario with
a total once-through reactor generating capacity in Canada of
194 GW(e) in the >ear 2016.
4. Each waste immobilization plant will operate at design capa-
city for 30 years. The in-service dates will be:
Plant Capacity(Mg V/a)1500150030003000
In-Service Date(Jan. 1)2000200320C&2014
- 4 -
5. Each container will include the waste from reprocessing fuel
containing 1.45 Mg U.
6. Immobilization and packaging of the reprocessing waste will be
followed by emplacement of the containers in the vault.
The disposal centre development and operation timetable
specified for the studies was:
1. Selection of site completed 1984
2. Demonstration facility completed 1983
3. Start of construction of full scale vault 1994
4. Start of emplacement of waste packages 2000
5. End of large-scale emplacement 2043
6. Backfilling drifts and start of shaft sealing 2044
For the purposes of this study, it was assumed that the full
scale vault would be built as an extension of the demonstration facility.
Other scenarios would, of course, lead to other timetables.
The rate of production of reprocessing waste, its key proper-
ties in the immobilized form and the packaging concept are summarized in
Section 2.2.
The disposal centre layout (Figure 2-2) shows the surface
facilities required for immobilizing liquid reprocessing waste in glass
and its packaging in steel containers. The filled containers may be
temporarily stored at the surface before transfer to the underground
emplacement rooms for disposal. When full, the underground vault and
entries will be backfilled and sealed.
- 5 -
The major on-site facilities and operations are summarized in
Section 2.3. More complete descriptions of facilities and equipment are
given in Sections 3 and A.
2.2 IMMOBILIZED WASTE QUANTITIES, CHARACTERISTICS AND
CONTAINER DESIGN
2.2.1 Quantities
The disposal centre accepts reprocessing wastes from irra-
diated fuel arisings to the year 2016 for immobilization and emplacement
in containers in the vault by the year 2043. The key quantities involved
in this scenario are summarized in Table 2-1.
The maximum waste immobilization, packaging and emplacement
rate is 6210 containers per year. A cumulative total of 186 300 con-
tainers will be emplaced, derived from the waste from reprocessing
270 000 Hg U of irradiated fuel. This quantity of irradiated fuel would
arise from the generation of approximately 14x10 kW-h of electricity.
2.2.2 Characteristics
The high-level wastes processed at the disposal centre will be
a mixture of the following two streams from fuel reprocessing:
1. A concentrated aqueous stream which will contain virtually all
of the fission products and will contribute most of the initial
heat generation. This stream may contain small quantities of
actinides.
2. An alkaline stream which will contain most of the plutonlum
and actinides. This stream will contribute most of the long-
term toxicity.
- 6 -
Glass was trhe only waste immobilization form considered in the
study. An alkaline borosilicate glass was selected because:
1. Borosilicate glasses have better mechanical, chemical, thermal
and radiolytic stability than phosphate glasses.
2. Phosphate glasses and their components are highly corrosive,
requiring exotic construction materials for the processing
equipment and waste containers.
3. Borosilicate glasses are easier to process as they melt at
lower temperatures than phosphate glasses.
The reference waste glass contains approximately one percent
fission products by weight. Detailed composition of the optimum glass
for CANDU waste is a subject of ongoing research and development.
2.2.3 Container
The reference immobilized waste container is shown in Figure 2-3.
It is constructed of AISI-304L stainless steel because of the high
temperatures and oxidizing conditions to which it is exposed during the
immobilization process.
E;.ch container encapsulates a glass block with a volume of
0.43 m and a weight of 1075 kg. Total package weight is 1675 kg. It
contains fission products derived from reprocessing seventy-seven bundles
of CANDU fuel. For 10-year cooled waste, the surface radiation field of
a filled container is expected to be in the range of 100 Gy/h, requiring
radiation shielding as well as remote handling at the immobilization
plants ar.i in the vault.
- 7 -
2.3 DISPOSAL CENTRE FACILITIES AMD OPERATIONS
2.3.1 Surface Facilities
The surface facilities will receive liquid high-level repro-
cessing wastes for immobilization. Their operations are shown diagram-
matically in Figure 2-4.
The following major operations will be performed in the surface
facilities:
1. Evaporate, calcine, and vitrify the waste arisings.
2. Fill and seal the container.
3. Provide temporary storage of the container at the surface.
The highly-radioactive waste liquid will be spray-calcined and
fed into a melter, where it will be mixed with glass frit to form molten
borosilicate glass. The glass will then be poured into the container.
When it has cooled, the container will be sealed, inspected and decon-
taminated.
It has been assumed that the immobilization plants will be
located within ICO m of the headframe so transportation will be through
a shielded conveying system, and the need for on-site transport flasks
will be avoided.
Temporary storage will be provided in the headframe building
for approximately 1500 containers, thereby insulating the process oper-
ations from potential delays in the vault. The reference storage system
is a dry hot-cell.
- 8 -
The handling system will be designed for reliable operation
and will be operated to minimize the radiation exposure to the opera-
tors. As with all equipment designed for operation in a radioactive
environment, it will be simple, with few components to maintain. Those
requiring maintenance will be strategically located and easily accessed.
2.3.2 Vault
The vault is designed for construction on a modular basis.
When complete, it will consist of 16 panels each containing 24 rooms.
Each room will accommodate 500 containers emplaced in a grid of drill
holes in the floor.
Initially, the two exhaust shafts would be sunk, one to be
used for intake ana one for exhaust during the demonstration phase; the
demonstration rooms would then be excavated.
The development and emplacement operations are planned on a
retreating basis from the exhaust shafts toward the main waste-lowering
shaft and intake ventilation shaft. The perimeter drifts will be used
for waste haulage, while the central drift will be used for construction
traffic, thus providing separation between waste emplacement and exca-
vation operations.
The vault receives immobilized waste containers from the
surface for disposal. Underground operations are shown in Figure 2-4.
Operations directly related to the active material are:
1. Transfer from the surface buffer storage to cage,
2. Transport by unshielded cage to vault level.
3. Transfer to underground buffer storage.
- 9 -
4. Transport in shielded flask to emplacement room.
5. Emplacement in drill holes in room floor.
6. Backfilling holes and rooms.
There is a significant mining operation in progress under-
ground at the same time.
Each room will be backfilled on completion of the waste em-
placement. Once all the rooms in the vault have been filled, the drifts
will be backfilled and the shafts will be sealed, thus completing the
disposal operation.
- 10 -
TABLE 2-1
IRRADIATED FUEL ARISINGS, REPROCESSING AND WASTE
IMMOBILIZATION QUANTITIES
Year
2000200120022003200420052006200720082009201020112012201320142015201620172018201920202021202220232024
1 2025202620272028202920302031203220332034203520362037203820392040204120422043
Irradiated FuelArisings
Annual(Mg U/a)
9 10010 30011 40012 30013 30014 40012 90012 90012 80012 70012 50012 40012 40012 20012 10011 900
11 800
Cumulative(Mg U)
64 40073 500S3 80095 200
107 500120 400133 400146 300159 200172 000184 700197 200209 600222 000234 200246 300258 200
270 000
Reprocessing Operations
ReprocessingRate
(Mg U/a)
1 5001 5001 5003 0003 0003 0006 0006 0006 0006 0006 0006 0006 0006 0009 0009 0009 0009 0009 0009 0009 0009 0009 0009 0009 0009 0009 0009 0009 0009 0007 5007 5007 5006 0006 0006 0003 0003 0003 0003 0003 0003 0)03 0)03 000
Cumulative(Mg U)
Reprocessed
1 5003 0004 5007 500
10 50013 500
' 19 50025 50031 50037 50043 50049 50055 50061 50070 50079 50088 50097 500106 500115 500124 500133 500142 500151 500160 500169 500178 500187 500196 500205 500213 000220 500223 000234 000240 000240 000249 000252 000255 000258 000261 000264 000267 000270 000
Reprocessing WasteImmobilization and Packaging
Waste ContainerProduction Rate(Container/a)
1 0351 0351 0352 0702 0702 0704 1404 1404 1404 1404 1404 1404 1404 1406 2106 2106 2106 2106 2106 2106 2106 2106 2106 2106 2106 2106 2106 2106 2106 2105 1755 1755 1754 1404 1404 1402 0702 0702 0702 0702 0702 0702 0702 070
CumulativeNumber ofContainers
1 0352 0703 1055 1757 2459 31513 45517 59521 73525 87530 01534 15538 29542 43548 64554 85561 06667 27573 48579 69585 90592 115S8 325
104 535110 745116 955123 165129 375135 585141 795146 970152 145157 320161 460165 600169 740171 810173 880175 950178 020180 090182 160184 230186 300
- 1 1 -
FUEL FABRICATION
tORE MILLING a PROCESSING
t
CANDU REACTOR 0 D n t l D
LUJL-MIU
EXPLORATION MINING
URANIUM ORE
r
i•i
i
FUEL REPROCESSING
ITO ADVANCEDFUE:L CYCLE
VAULT SURFACEFACILITIES
DISPOSAL' VAULT
DISPOSAL BY EMPLACEMENT
vFIGURE 2 - 1 . CANDU FUEL CYCLE WITH REPROCESSING
REPROCESSED WASTECONTAINER EMPLACEMENT
WASTE PECEIVINd, PACKAGINGvAMD HANDLING
•^FACILITIES
WASTE SHAFT
*NOTEBLDGS. NOTTO SCALE
ERVICE SHAFT
EMPLACEMENT ROOM
WASTE HAULAGE DRIFT
BACKFILL RAIL HAULAGE DRIFT
MAIN DEVELOPMENT DhlFT
ROCK RAIL HAULAGE DRIFT
WASTE HAULAGE DRIFT
DOWJJCASTVENTILATIONSHAFT
FIGURE 2-2. DIAGRAMMATIC LAYOUT OF DISPOSAL CENTRE
- 13 -
TOTAL CONTAINER WEIGHT
1675 kg.
DIMENSIONS IN mm
3275•»>*N>>*'
\\\\\S \\S\ VO^N. W
FIGURE 2-3. CONTAINER FOR IMMCDILIZED WASTE
-c-I
FIGURE 2-4. SURFACE FACILITIES AND VAULT OPERATIONS
- 15 -
3. SURFACE FACILITIES
3.1 SITE LAYOUT
3.1.1 Description
The major surface facilities at the disposal centre will be
the waste immobili2ation plants, waste shaft headframe building (includ-
ing the waste storage cell), service headframe and support services.
They will be located on a 38-ha site as shown in Figure 3-1. For this
scenario, an exclusion zone excending 1 km from the mine ventilation
intake and exhaust stacks has been assumed. Figure 3-2 shows the
relative sizes cf the centre, the surface facilities and the vault, and
also shows the proposed exclusion zone.
The buildings at the centre have been arranged around the
waste shaft headframe building. Waste containers are transferred from
the immobilization plants through underground tunnels. Situating the
immobilization plants along an arc close to the waste shaft minimizes
the tunnel lengths.
The administrative buildings, stores, warehouse, inactive
maintenance workshop, mined rock handling and backfill preparation
facilities are arranged close to the vault service shaft for ease of
materials and personnel movement. A cafeteria has been provided in the
inactive area. Power and heating plant are centrally located to reduce
utility piping and power line costs, whereas water supply and inactive
liquid waste treatment systems are located near the water source.
- 16 -
3.1.2 Materials Movement
The maximum rates at which materials will be received at the
centre are as follows:
1. Vault backfill material (900-1000 m 3/d).
2. Glass frit (200 Mg/week).
3. Coal for Heating Plant (90 Mg/d).
4. Empty waste containers (217/week).
5. Miscellaneous materials including equipment, chemicals and
supplies.
Because of the large quantities of materials, rail and road
access is desirable. Economics of the specific mode will depend on the
source location. Storage areas and bins have been provided close to the
point of use, e.g., coal is stored outside in pits close to the heating
plant. Waste containers are received and stored in designated areas at
each plant. Two-week storage bins have been provided for glass frit,
and each bin serves two immobilization plants.
Most other materials are expected to be delivered to the site
by truck. A warehouse and material storage yard are available for
equipment, materials of construction and other bulk materials storage.
Chemicals will be received and stored at the points of consumption.
Small equipment, components, tools and other supplies will be received
at the stores building.
Movement of active materials within the site is generally
limited to the active zone. Inactive wastes and materials can leave the
active zone through one of the control points after monitoring. The
major inactive material which will require disposal is the mine rock.
- 17 -
A 17-hectare disposal area is provided at the site, and the rock will be
piled by scraper trucks in a pile 10 m high.
Transfer of immobilized waste containers from the plants to
the temporary storage facility will be through four independent tunnels.
Each tunnel will be approximately 4 m wide to permit maintenance.
3.2 DESCRIPTION OF FACILITIES
3.2.1 Waste Immobilization Plants
To achieve the desirable immobiliEation rates, a total of four
waste vitrification plants are provided. Since the plants are identical
in concept, only the reference plant of 1035 waste containers per annum
capacity is described below.
3.2.1.1 Process Description
The immobilization process includes the following four major
components:
1. Calcination.
2. Vitrification.
3. Off-gas treatment.
4. Secondary waste processing.
\ock diagrams of the first and second steps are presented in
Figure 3-3. High-level wastes are received and analyzed for actinide
and fission product content and fed to a spray calciner. The calciner
is an externally-heated vertical cylinder. Waste is introduced at the
top in the form of a fine spray. Drying and decomposition of nitrate
salts take place through progressive heating to 700°C as the waste falls
to the bottom of the container. The calcine flows by gravity to the
- 18 -
bottom of the calciner hopper, from where it is pneumatically trans-
ported to a melter. Off-gases generated during calcination pass through
a reinforced sintered powder metal filter, which retains 99.9 percent of
the calcine. Solids deposited on the filter are blown back and fall to
the bottom of the calciner hopper,
The calcine is mixed with the glass-making constituents, and
the mixture is vitrified in a ceramic melter. Melting is achieved by
passage of current through the glass melt, using Inconel 690 electrodes
placed at opposite ends, of the melter ceramic cavity. Product glass
overflows into the waste container, and is annealed to prevent devitri-
fication. A lid is welded on to seal the container, and the weld is
ultrasonical.'.y inspected. The container curface is decontaminated by
steam and pressurized water sprays, and inspected before the container
is transferred to the active head frame building.
A flow diagram of the off-gas treatment is shown in Figure 3-4.
Off-gases leaving the calciner filter consist mainly of atomizing air,
water and oxides of nitrogen, and carry up to 2 wt.% ruthenium and
0.5 wt.% of the nonvolatile fission product content of the calciner
feed. Treatment imst be provided to retain these constituents within
the system, and to limit the discharges from all sources at the site to
< 1% of the Derived Release Limit. The treatment system consists of
quench cooling, scrubbing in a venturi scrubber, condensation of excess
moisture, and mist elimination. The bulk of the volatilized ruthenium
is then removed in a ferric oxide filter. This is followed by a cata-
lytic decomposer for the oxides of nitrogen, a roughing filter, an
iodine adsorber and a final high efficiency filter. The remaining off-
gases are mixed with the plant ventilation flow and discharged through
the plant stack.
The secondary waste processing flow diagram is illustrated in
Figure 3-5. During off-gas treatment, all volatile radionuclldes,
- 19 -
particulates and most of the water and oxides of nitrogen are retained
in a liquid stream. This secondary waste stream is concentrated and the
concentrate recycled to the calciner. Overheads from the concentrator
consist of water and nitric acid which are treated further in ion-
exchange columns. Column effluents are transferred to the low-level
liquid waste treatment facility for further decontamination or monitor-
ing before discharge to the environment.
3.2.1.2 Reference Plant Description
The reference waste immobilization plant is located in a
building 70 m long, 45 m wide and 18 m high. The main floor, and sec-
tions through the building are shown in Figures 3-6 and 3-7, respec-
tively. The building can be divided into the following four zones:
1. Process Area.
2. Decontamination and Maintenance Zone.
3. Analytical Wing.
4. Administration Area.
Process cells a e located at the heart of the facility, and
are arranged in order of increasing activity. Entrance to the plant is
through the administration area where change rooms, offices and control
room are also located. The analytical area and decontamination area are
accessible through change rooms. The laboratory is connected to the
process area by a flight of stairs.
Filled waste containers are dispatched to the active head-
frame building through a tunnel from the end of the process area. Solid
low-level wastes are dispatched through a truck bay in the decontamina-
tion area. Transfer of equipment and material between the process area
and the decontamination area is by an overhead crane and air-lock
arrangement. Smaller tools and equipment can also be transferred
between the two zones through a mechanical gallery and airlocks.
- 20 -
A combination of remote- and direct-contact maintenance is
employed. Remote replacement is used for highly active equipment which
may require occasional replacement. Direct maintenance, after decon-
tamination to reduce radiation fields to acceptable levels, is used for
the remaining equipment. Cells are designed and handling equipment is
provided throughout the plant to meet these maintenance objectives.
Contamination control is provided by the cell walls and venti-
lation air flow. The plant is divided into four ventilation zones,
depending on personnel movement requirements and potential contamination
risks. Ventilation flows take place from areas of no or low-level
activity potential to areas where high activity levels may be present.
Air is finally extracted by the exhaust blowers, filtered, monitored and
discharged through the plant stack. A total 15 m /s of air will be
discharged from each waste immobilization plant during active operation.
3.2.2 Haste Shaft Headframe
The waste shaft headframe building will receive containers of
immobilized waste. The building contains the hoist headframe structure,
temporary storage cell, associated operating galleries and all required
services and facilities (Figures 3-3 and 3-9).
The temporary storage facility is a hot cell with a total
available area of 640 m . Storage capacity is provided for up to 1500
containers to prevent shut-down of the immobilization plant during vault
maintenance downtime. Waste containers will be received through four
tunnels from the immobilization plants on railmounted trolleys. Con-
tainers will be transferred one by one, using a 2-Mg remotely-operated
overhead crane, to storage or directly to the cage loading area. In the
storage area, containers will be stored in racks for retrieval when
required for vault emplacement.
- 21 -
Containers will be moved within the storage area by remotely-
operated overhead cranes. Transfer into the cage utilizes an indexing
table and a hydraulically-operated boon crane.
3.2.3 Service Shaft Headframe
The service shaft headframe will consist of a reinforced
concrete structure on a base incorporating the shaft collar (Figure
3-10). The headframe will accommodate the rock skip, service cage and
emergency man-riding cage hoists and all associated control equipment.
The base of the headframe will provide approximately 1200 t of rock-
storage capacity, acting as a surge facility between the underground and
surface operations.
For the installation of hoist machinery in the headframe and
their subsequent servicing and maintenance, a heavy-duty jib crane will
be installed on the skip hoist floor. The crane will be capable of
hoisting the heaviest pieces of equipment from ground level to the upper
floor of the frame and pcsitioning them, in a single operation. Supple-
mentary lifting equipment will be provided from the various levels for
equipment that is not directly accessible to the jib crane.
Rail access will be provided to the service cage for transfer
of large pieces of equipment between surface and underground.
3.2.4 Backfill Preparation Plant
To prepare the material required for the final backfilling of
the vault, rock will be reclaimed from the service headframe bin by a
conveyor and transferred to the intermediate rock storage pile. Rock
which is to be disposed of will be loaded from this pile by a front-end
loader into dump trucks for transfer to the disposal area. Rock re-
quired for crushing will be Tiken by conveyor to the preparation plant
- 22 -
for screening and crushing. Following crushing, coarse aggregate will
be stored in a bin in the preparation plant.
Pit-run sand and gravel will be brought to the site by means
of dump trucks, discharged into a bin and fed by a stacker to a surge
pile. It will be reclaimed and fed by conveyor into the crusher and
screen house where it will be screened as necessary and stored in a bin.
The crushed rock, sand and gravel will be blended and the aggregate
conveyed to the headframe of the service shaft. Bentonite will be
transferred underground via the service cage and mixed with the blended
aggregates just prior to backfill placement.
3.2.5 Low-Level Liquid Waste (LLW) Treatment
Up to 250 m /day of low-level liquid wastes will be generated
by the active facilities at the centre. Generally, these wastes will
have a sufficiently low activity level to be acceptable for discharge to
the environment. However, if monitoring indicates unacceptable activity
levels, treatment will be provided at the LLW facility. It will include
flocculation and sedimentation followed by ion-exchange treatment.
Expected decontamination factors are in the order of 10 . The treated
waste will be discharged once per day, after monitoring to ensure that
the release does not exceed the site license limits.
3.2.6 Solid Waste Management
Active solid wastes generated at the centre will be pre-
treated, segregated, packaged and tagged. Additional processing will be
provided at the solid-waste processing building. This will include
sorting, compaction or incineration, and packaging. It is expected that
containers, similar to those selected for the reactor wastes for final
disposal at the low- and medium-active waste vault, will be used for
these wastes. At this stage, it is assumed that the waste will be
- 23 -
packed in 200-dm drums and stored in concrete bunkers similar to those
used at the Bruce* Waste Management Site.
Ashes from the incinerator, ion-exchange resins, sludge from
the LLW facility and other suitable waste residues will be incorporated
into bitumen. The bitumen plant will be located at the LLW building.
Packaged wastes from the LLW plant will be shipped directly to the
concrete bunkers for storage.
3.2.7 Services
The centre is provided with inactive services common to all
active facilities, the head frame buildings and the vault. These
include:
1. Heating and standby power plant which will supply the chilled
water, hot water and compressed air requirements for the site.
2. Substation for power transformation and distribution to the
various facilities.
3. Inactive workshop.
4. Store for equipment and other supplies.
5. Central administration building.
6. Vault spoil storage area.
7. Water pumping station and treatment plant.
8. Sewage treatment facility.
The site is provided with domestic sewer, storm sewer, domes-
tic and service water, and utility distribution lines.
- 24 -
3.2.8 Environmental Laboratory
A laboratory is provided for monitoring the site and the
environment for radioactivity. The laboratory will be set up before the
active facilities start up to gather background data for subsequent
monitoring of the environmental impacts of centre operation.
I
bo
FIGURE 3-1. WASTE DISPOSAL CENTRE LAYOUT
6.1km
VAULT -VENTILATION " > l
SHAFTS S |
EXCLUSION
3.6km
VAULT BOUNDARY
ZONE BOUNDARY
iI11
_Ji
SURFACEFACILITIES
FIGURE 3-2. IMMOBILIZED WASTE DISPOSAL CENTRE SITE LAYOUT(Not to scale)
ACCOUNTTA
I
ABILITYNK
RECEPTIONTflN"
MIXED WASTE
i
ATOMIZING
FEEDTANKS
f
AIR
ED WASTE:ROM FIGURE
3.5 TRANSPORT AIR
DECONTAM-INATIONGROUP
CALCINERS FILTERS
t tCALCINE
\
1
SOLIDTRANSPORT
CONTAINERFILLING AMDWELDING OF
TOP
T
— 1
CYCLONES
\ t
MtLl LH
tGLASS
-RIT
D OFF GAS TREATMFNT
•
FIGURE 3.4
i 1
OFF-GASES
FIGURE 3-3. CHEMICAL FLOW DIAGRAM OF THE CALCINATION AND VITRIFICATION STEPS
FROM FIGURE 3.3
OFF-GASES^.
TO
ATMOSPHEREVIA PLANTSTACK
COOLING
HEPA
FILTRATION*i
SCRUBBING CONDENSATIONMIS1
SEPARA'
TO SECONDARY WASTE RECYCLING
NOx
DECOMPOSITION
FIGURE 3.5
RUTHENIUM
ADSORPTION
rnow
HEATING
00
I
FIGURE 3-4. OFF-GAS TREATMENT
TO OFF-GASSYSTEM
FROM _ _ .FIGURE 3 . 4 *
RECEPTION8. FEEDING
FROM Ru FILTER
FROM FILTER LEACH __,
FROM OFF-GAS SCRUBBE?
EVAPORATOR CONDENSER
TO FIGURE 3.3
ACTIVATEDIRON BED NEUTRALIZATION
FURTHERDECON-
TAMINATION
ZEOLITEDEMINERALIZFR
HNO3
TO LOH-LEVELWASTE SYSTEM
DISCHARGE TOENVIRONMENT
FIGURE 3 - 5 . CHEMICAL FLOW DIAGRAM OF SECONDARY WASTE PROCESSING
oI
FIGURE 3 - 6 MAIN FLOOR PLAN OF THE WASTE IMMOBILIZATION PLANT
MECHANICAL GALLERY
LOADINGP I T LOADING
DOCK[RARE
SECTION A-A
TRUCKBAT
LOADINGDOCK
LOADINGPIT
OPERATINGGALLERY
DISPATCH
CHEMICALSTORAGEROOM
VENTILATI01ROW
CHEMICALPREPARATION
ROOM
LABORATORIES ACTIVE
MAINTENANCE
SHOP
TRUCK
BAY
SECTION B-B
FIGURE 3 - 7 CROSS SECTIONS OF THE K4STE IMMOBILIZATION BUILDING SHOWNIN FIGURE 3 - 6
-OVERHEAD DOOft
OPERATING GALLERY
SI I
ho
I
• * • ' ' f * * -
SCALE IN METRES
FIGURE 3-8. WASTE SHAFT HEADFRAHE BUILDING PLAN
- 33 -
SKIP HOIST
CAGE HOIST
EQUIPMENT aWORKERS CAGE
WASTEROCK
BACKFILL
FIGURE 3 -10 . SERVICE SHAFT HEADFRAME
- 35 -
4. VAULT
4.1 STUDY METHODOLOGY, SPECIFICATIONS AND DESIGN CRITERIA
The vault design study methodology is shown in Figure 4-1 and
consists of the following general sequence of tasks:
1. Determination of preliminary design criteria.
2. Determination of preliminary design concepts.
3. Thermal-rock mechanics analysis.
4. Design of vault layout, services and operation.
5. Estimates of cost and manpower requirements.
6. Design Concept Report.
4.1.1 General Specifications and Constraints
AECL specifications for this design study were based upon pre-(3)vious conceptual studies , available data, and constraints used by
other study groups. Those which have not been described in Section 2.2
are summarized below.
4.1.1.1 Setting
The vault is located on a single level at a depth of 1000 m in
a crystalline rock whose properties are either those of granite or
gabbro. It consists of rooms for waste emplacement, connected by
drifts. Containers are emplaced in drill holes in the floor of the
rooms.
- 36 -
4.1.1.2 Operations
All construction and development operations for the vault use
standard and accepted mining industry techniques.
Emplacement procedures and handling equipment for containers
are designed to ensure that radiation doses received by personnel will
be consistent with current design target levels for nuclear workers.
Conventional worker safety standards will also be met.
Vault development and waste emplacement operations are kept
separate. Ventilation of the vault is designed to provide air flows for
worker protection and comfort during both construction and waste emplace-
ment phases. Provision is also to be made for temporary ventilation in
those areas which may require short-term worker access. The ventilation
system either draws air through the construction area and then through
the waste emplacement ar^a, or provides separate systems.
All air flowing from the "active" part of the vault flows
through a radioactive particulate monitoring system. In the event of
airborne radioactive contamination, the airflow is directed through a
filter system before discharge into the environment.
The containers are emplaced in drill holas in the room floor
with one container per drill hole. Backfill is placed above the con-
tainer in the drill hole. Each room is completely backfilled after
waste containers have been emplaced in all drill holes in that room.
4.2 THERMAL-ROCK MECHANICS ANALYSIS
A thermal-rock mechanics analysis of the reference concept was
undertaken to establish the criteria for use in the layout and design
studies for the vault. Specifically, this required establishing the
- 37 -
thermal loadings which would be acceptable within the limitations of the
specifications and design options. Details of the thermal-rock mechanics
analysis are contained in Appendix B.
For the purpose of this study, the vault area has been divided
into three regions.
1. The container (near-field) region, which includes the back-
filled cavity and the volume of rc<c along the room and
pillar extending from the room floor to a few metres below the
container.
2. The room-and-pillar region, which includes the rock mass in
the room-and-pillar unit and extends to several room diameters
both above and below the room.
3. The far-field region, which extends vertically from the surface
to two or more times the vault depth below the level of the
vault and horizontally to at least a vault's length beyond the
edges of the vault.
The thermomechanical constraints which were agreed for these
regions with AECL at the initiation of the study are summarized in
Table 4.1. The waste heat generation as a function of time relative to
the heat generation at the time of emplacement is illustrated in
Figure 4-2.
During the far-field analyses, the potential for the devel-
opment of a perturbed fissure zone (defined as the zone of rock where
existing fissures may be opened due to the action of tensile stresses)
was recognized. For the purposes of this study, the acceptable depth of
the zone was limited to 100 m.
- 38 -
The design was such that modifications to the thermal loadings
could be achieved within this concept by:
1. Varying the spacing of the rooms (extraction ratio).
2. Varying the spacing of the containers along the room (pitch).
Revisions to capacity requirements may be met by the extension
of panels or addition of further panels. The transverse spacing and the
number of containers across the room was fixed for these studies.
Two specific rock types, granite and gabbro, were considered.
No distinction was made between the rock types with regard to their
mechanical properties. The thermal conductivity and coefficient of
thermal expansion were considered to provide the distinction between the
two rock types.
A matrix of the important variables (extraction ratio, pitch
and panel thermal loading (PTL) for near-field and room-and-pillar
analyses, or gross thermal loading (GTL) for far-field analyses) was
used to deiine the required thermal analyses. The extraction ratio,
pitch and PTL satisfying the thermal constraints for all three regions
of the vault were chosen for the subsequent rock mechanics analyses.
For the two-dimensional plane-strain rock mechanics analyses,
a linear Mohr-Coulomb failure criterion was used for both the intact
rock and joints. In addition, a 'no tension' criterion was employed in
all the analyses.
For both granite and gabbro, the preferred PTL-pitch-extrac-
tion ratio combinations are controlled by the minimum drill-hole spacing
and the backfill temperature constraints. However, the container skin
temperature constraint could become significant if the acceptable back-
fill temperature were increased (backfill constraint) or the acceptable
- 39 -
container skin temperature were reduced ^container skin temperature con-
straint). This would apply particularly to a vault in gabbro. Varia-
tion in effects of far-field constraints were not examined parametrically,
but are not anticipated to be significant at the thermal loadings
required by the other constraints. Room stability and pillar strength
ratio criteria do not appear to be critical for any of the thermal
loadings considered.
Based on tb<=" analyses described, the thermal and thermomecha-
nical constraints and restrictions, and the common extraction ratio of
25Z, the following configuration was selected for the vault design
criteria.-
Granite and Gabbro - extraction ratio - 25%2
- PTL <_ 24 W/m
- GTL <_ 23.6 W/
- pitch _> 1.5 m
For gabbro, the selected configuration is controlled by the
allowable container spacing and backfill temperature constraints at an
extraction ratio of 25%. The selected configuration for the granite
vault is defined by the minimum container spacing constraint and the
common extraction ratio value of 25% established by the gabbro case.
4.3 LAYOUT
The detailed vault layout was developed using the design
criteria developed from the thermal-rock mechanics analyses.
In addition, the following factors were considered:
1. The number of penetrations of the pluton should be minimized
consistent with economic development of the vault.
- 40 -
2. The layout should be flexible so that it could be readily
modified to suit changes in waste management practices or
geological conditions, by extending a panel or by construction
of additional panels.
3. Development and emplacement operations should retreat toward
the main shafts to avoid working in active and heat-generating
areas.
4. Separation of development and emplacement operations would be
achieved by physical barriers and/or operating procedures.
5. The conceptual design should be workable, although not necess-
arily optimal.
The layout for the vault is shown in Figure 4-3. Design
considerations which led to this layout are discussed below.
4.3.1 Shafts and Major Drifts
The shafts are indicated on Figure 4-3. The service shaft,
waste shaft and downcast ventilation shaft will be at one end of the
vault. At the opposite end, two upcast shafts will provide ventilation
air exhaust. All shafts are located outside the vault area with a
minimum distance to the nearest panel of 200 m. This was determined
from thermal analyses to restrict the temperature rise at the shafts to
less than 5°C with the maximum rise occurring 50 years after emplacement.
Rock handling and container handling facilities will be sep-
arated vertically in the shaft area, with common maintenance facilities
on the main vault level.
The development and operation of the vault will require drifts
for access and materials transport. These will be:
- 41 -
1. Main drift for access during primary development and panel
development.
2. Waste transport drifts to permit transport of containers
separate from development operations.
3. Rock rail haulage and backfill rail haulage drifts located
30 m below and above the main drift, respectively, with
raises driven to the vault level for transfer of materials.
4. Panel drifts to provide access for room development, waste
emplacement and backfilling.
All drifts will be driven on a 0.5% upgrade from the main
shaft group to facilitate drainage. Cross sections are based on single-
lane operation, widened for passing areas at suitable locations. Turning
points will be provided at approximately 200-m intervals in panel drifts
to assist in traffic operations during waste emplacement. Intersections
will be offset to reduce roof spans and, in the case of panel drift/main
drift intersections, to permit installation of security grills for
operations separation.
4.3.2 Panels
The vault will contain 14 full panels with 2 half panels at
each end as shown in Figure 4-3. Each full panel contains 24 rooms, 12
on either side of the panel drift, and provides space for the emplace-
ment of 12 000 containers. Room/panel drift intersections are offset to
reduce roof spans.
The room spacing was determined from the results of thermal-
rock mechanics analyses which defined an extraction ratio of 25%. The
panel dimensions (430 m by 450 m) were determined from consideration of
- 42 -
rock excavation and haulage methods. Rock will be loaded into trucks in
the room using front-end loaders, and will be hauled to the rock raise
for dumping to the rock rail haulage level.
Development and emplacement activities will not take place
concurrently in the same panel. Development of each panel will begin
with excavation of the panel drift from the main drift to the waste
transport drift. Rooms will be developed beginning at the main drift.
4.3.3 Rooms
The rooms are designed to permit location of four containers
at 1.5 m centre-to-centre spacing across the room, as shown in Figure 4-3.
Each room will contain 500 containers. The room height is determined
primarily from hole drilling and container handling considerations. The
room entry is "dog-legged" to reduce the possibility of direct radiation
in the panel drift during emplacement and hole backfilling operations.
Rooms will be driven on a 2% upgrade from the panel drift to facilitate
drainage. All rooms will be single entry to minimize possible hydro-
geological interconnection through the vault. At the room entrance the
rock surface will be cleaned and the surrounding rock grouted as neces-
sary to form the foundation for a backfill "plug" to minimize intercon-
nection between rooms and drifts.
4.4 VAULT DEVELOPMENT AMD OPERATIOM
4.4.1 Master Schedule
The master schedule for development and operation of the vault
during the period 1984 to 2050 was developed to meet the project mile-
stones defined in Section 2.1. The schedule is composed of the follow-
ing phases:
- 43 -
Phase I Access and Demonstration 1984 - 1993.*
Phase II Primary Development 1994 - 1999.
Phase III Panel Development and Emplacement 2000 - 2043.
Phase IV Decommissioning 2044 - 2050.
Milestones and activities for Phases I and II are given in
Figure 4-4. The start of construction has been taken as early 1984 in
order to have the demonstration vault available for operation in 1988.
Bidding and selection of contractors will have to be complete in advance
of this date.
Development of the demonstration vault was not within the
scope of work of this study and, therefore, only an outline schedule has
been prepared. This indicates that 6 years of demonstration is avail-
able before commencing full-scale vault construction, if full-scale
waste emplacement is to start in year 2000.
The primary development start date has been established as
1994 in order to allow time for an orderly construction program. The
waste emplacement schedule has been established to suit the delivery
rates of containers from the immobilization facility at the surface.
Backfilling of each room follows immediately after emplacement of the
containers in that room is complete. The decommissioning phase follows
completion of waste emplacement.
It has been assumed that contractors would be appointed for
carrying out the Phase I and Phase II construction activities. The
Phase III and Phase IV activities have been planned on the basis that
the owner would operate the facility.
* See disclaimer on inside of front cover.
- 44 -
4.4.2 Access and Demonstration, Phase I
The start date for this phase is early 1984. The contractor
will have to have been selected and all detailed engineering required
for shaft sinking will need to be done in advance of this date.
The initial construction activity will commence in 1984 with
the sinking of a small construction shaft at the opposite end of the
vault from the service shafts area. From this shaft, an 850-m long
drift will be driven to the location of a second small shaft which,
subsequently, will be excavated to the surface by raising techniques.
These two shafts will later serve as permanent exhaust ventilation
shafts. In the area between these two shafts the demonstration and
testing facilities can be developed. From the interconnecting drift
between the shafts, an exploration drift will be driven along the centre
axis of the future vault to the location of the future service shaft at
the opposite end. This will permit exploration of the rock mass during
the early stages of activity on the site.
4.4.3 Primary Development, Phase II
Around 1992, a decision must be made as to whether to proceed
with the construction and development of the vault on the selected
provisional site. This is necessary to allow the detailed design of all
service facilities, shafts and vault to be carried out and to prepare
tender specifications for construction activities to begin in 1994.
A critical path diagram for these activities is shown in
Figure 4-4. The construction of the large service shaft will start in
1994. This shaft construction will be carried out by raising a pilot
raise from vault level to surface. At the same time, the concrete
headframe will be erected and the necessary shaft-sinking equipment
installed, allowing the shaft to be slashed to full size once the pilot
- 45 -
raise is completed. The excavated rock will be dropped to the vault
level where it will be brought by rail cars to the temporary construc-
tion shaft for hoisting to surface. Once the various shaft levels have
been cut, the backfill and rock bins excavated and all necessary shaft
and hoist equipment installed, the two adjacent shafts, the waste shaft
and the downcast ventilation shaft, will be raised to the surface.
The underground vault development will start as soon as the
rock hoisting facilities are ready in the service shaft. This devel-
opment activity consists of driving the five major drifts to the oppo-
site end of the vault. In addition, excavation and installation of the
necessary service and waste handling facilities around the shaft will be
carried out.
Inspection of the critical path shows that the service shaft
construction controls the date for the start of the primary underground
vault development in 1997. Construction of the service and downcast
shafts will require ventilation air from the pilot main drift which is
planned for prior construction during the demonstration phase. Thi;
remainder of the critical path lies on the main drift development,
leading, on completion, to the initial panel development.
4.4.4 Panel Development and Emplacement, Phase III
The detailed schedule and sequence of activities in this phase
are shown in Figure 4-5 for the period 2000 to 2043.
Four principal activity streams are planned for the panel
development and emplacement phase. These are:
1. Room excavation.
2. Room preparation and emplacement hole drilling.
3. Container emplacement.
4. Room backfilling.
- 46 -
It has been assumed that these operations will be handled by
the owner's staff, The equipment requirements and rates of operation
have been set to isuit the container delivery rates. It appears that the
resulting schedule is quite flexible and should be capable of adjustment
to suit the active materials handling requirements, monitoring, etc.
4.4.5 Maintenance and Decommissioning, Phase IV
The final backfilling of drifts and shafts, sealing and de-
commissioning of the vault is scheduled for the period 2044 - 2050.
Project completion after decommissioning is scheduled for
2050.
4.5 FACILITIES AMD EQUIPMENT
4.5.1 Rock Excavation and Handling
4.5.1.1 Access and Demonstration
This will involve excavation of the two upcast shafts, a
demonstration vault, and driving a pilot drift along the line of the
main drift for access and exploration purposes. Drill and blast methods
will be used for excavation with trackless and/or rail haulage as appro-
priate. Upcast shaft 1 will be furnished with a temporary headframe for
skip hoisting. Rock excavation quantities are summarized below.
Depth/Length Quantity(m) (m3)
Upcast Shafts (2) 1000 22 000Drifts 4450 40 050
- 47 -
4.5.1.2 Primary Development
Rock excavation for primary development will comprise:
1. Sinking of service, downcast and waste shafts.
2. Enlarging main drift to final cross section.
3. Driving waste transport drifts.
4. Driving rock and backfill rail haulage drifcs.
5. Excavation of shaft levels for rock and waste handling facil-
ities, and installation and commissioning of equipment.
Details of the shaft excavation are given in Section 4.5.2.
The excavation of service facilities around the shaft group
and of the major drifts will be carried out as soon as the service shaft
is completed and ready for double-skip hoisting.
Excavation rates have been based upon conventional drill-and
blast-methods using currently available trackless electric-hydraulic
drill jumbos. Mucking and haulage to the service shaft will be by Load-
Haul-Dump (LHD) units and diesel-powered trucks or rail equipment as
appropriate.
Excavation quantities are summarized below:
SHAFTS
Description
Service
Wasty
Downcast
Depth(m)
1 075
1 000
1 030
Diameter(m)
7.3
3.6
4.6
Volume
~WT45 000
10 000
17 000
- 48 -
HAULAGEWAYS ANDSHAFT PILLARDEVELOPMENT
Main drift
Rock rail haulage drift
Backfill rail haulage drift
Waste transport drifts (2)
Shaft levels
TotalLength
(m)
3 900
4 000
4 000
8 900
Volume
(m3)
108 000
86 000
86 000
247 000
27 000
4.5.1.3 Panel Development
Rock excavation for panel development will comprise:
1. Excavation of panel drifts.
2. Excavation of emplacement rooms.
3. Drilling of emplacement holes.
Excavation of the first panel will begin in mid-1998 in order
to be prepared for container emplacement at the beginning of 2000.
Individual panel development will begin with driving the panel drift
from the main drift to the waste transport drift. A number of rooms
will be excavated simultaneously for efficJ°ncy id scl.eule require-
ments. The excavation cycle comprises:
1. Drilling.
2. Hole loading.
3. Blasting.
4. Mucking and hauling.
5. Ground support.
These activities are shown in Figure 4-6.
- 49 -
Excavation rates and cost estimates are based upon conven-
tional drill-and-blast methods using cjrrently available trackless
electric-hydraulic drill jumbos. LHD units will load the blasted rock
into trucks for haulage to the rock passes located at the main drift.
Two independent train sets with 25-t trolley-battery electric locomo-
tives will haul muck cars from the rock passes to the service shaft.
Rock will be dumped into a large rock bin for automatic hoisting to the
surface by a double skip friction hoist.
Equipment for drilling the 0.61 m diameter, 4.75 m deep,
emplacement holes has been based on available small diameter raise
boring rigs. The drill rig will be an electrically powered, reverse
circulation, water-flush unit mounted on a crawler chassis which will
also contain rod stem storage and handling equipment. The height will
be less than 4 m when fully extended. For stability while drilling,
the drill rig will be equipped with hydraulic roof and floor jacks.
Panel development excavation quantities are summ?rized below,
and annual rates are shown on Figure 4-7.
Volume
(m3)
165 000
2 956 000
258 000
Panel
Rooms
Drill
TOTAL
drifts
holes
VOLUME
Total length
(m)
5 960
84 210
884 920
Averagecross sectional
area (m2)
27.7
35.1
0.292
3 379 000
Preparation of the room for container emplacement will require:
1. Geological mapping of the room.
2. Placing screeded concrete pad at hole locations for flask
seating.
- 50 -
3. Drilling emplacement holes.
4. Testing drill hoJes and significant fractures, and remedial
grouting if required.
5. Removing loose rock and muck from the room.
6. Placing guidance markers for waste transporter.
7. Placing of bedding backfill in emplacement drill holes.
4.5.2 Shafts and Hoists
Five shafts will be required between the surface and vault
level:
At the main shaft group - service shaft
- waste shaft
- downcast ventilation shaft
At the exhaust end of the vault - two upcast ventilation
shafts
4.5.2.1 Service Shaft and Hoist
The service shaft is required to provide for:
1. Efficient hoisting of excavated rock.
2. Conveyance of large units of mechanized equipment and under-
ground supply material with maximum weights of 10 t.
3. Expedient conveyance of underground personnel at start and end
of working shifts. The number of people to be handled at one
time is estimated at 50.
- 51 -
4. Auxiliary man-riding cage for supervisors and emergency
situations during the shifts.
5. Regulatory ladder escape way to surface.
6. All the necessary service pipes and cables from surface to the
underground vault.
The shaft will be 7.3 in diameter, concrete lined and divided
into three sections as shown in Figure 4-8. These will contain:
1. Two 13-t balanced skips for rock hoisting.
2. Service cage.
3. Ladder escape way, service pipes and cables and emergency
cage.
The rock hoisting system will be designed for a capacity of
410 t/h.
For the purpose of this study, it is assumed that the shaft
will be excavated by Alimak raising from vault level followed by slash-
ing to full diameter and lining. A typical shaft sinking operation
sequence is shown in Figure 4-9.
The service shaft headframe is described in Section 3.2.3.
4.5.2.2 Waste Shaft and Hoist
The waste shaft will be dedicated for handling containers
between the surface and the vault. The maximum container production
rate will be 6210 containers per annum from 2014 through 2029.
- 52 -
The shaft will be 3.6 m diameter, concrete-lined. The cage
will be a single-deck unit of steel construction with ar enclosed deck,
safety doors and container restraining equipment. Roof structural
members will be thickened for shielding in the event that work is
necessary near a loaded cage. Safety devices will be provided to arrest
the cage upon cable failure. The cage will have a weight of approxi-
mately 9 t and a load capacity of 10 t.
The waste shaft headframe is described in Section 3.2.2. It
has been assumed that the shaft will be excavated by full-face raising
from vault level, using an Alimak or similar system.
4.5.2.3 Ventilation Shafts
Ventilation shafts will be required to handle 283 m /s. A
single 4.6-m concrete-lined downcast and two 3.65-m concrete-lined
upcast shafts will be required.
The present schedule allows for the development of a demon-
stration vault at the exhaust end of the vault. The first upcast shaft
will, therefore, be sunk by conventional methods. It has been assumed
that the second upcast shaft and the downcast shaft will be excavated by
full-face raising from the vault level, using an Alimak or similar
system.
4.5.3 Container Handling
The containers will be sealed and decontaminated at the waste
immobilization plant, so surface contamination will not be an opera-
tional problem in the vault. Neutron fluxes are sufficiently low that
the gamma-ray shielding will be adequate for neutron-flux shielding.
Shielding requirements will be determined primarily by the gamma radi-
ation levels. The surface dose rate will be about 100 Gy/h. At 4 m
from the container surface, the dose rate is estimated to be 3.75 Gy/h.
- 53 -
The waste immobilization plant will produce containers at a
maximum rate of 6210 containers per year. On the basis of two shifts
per day, approximately 14 containers will be emplaced per shift.
Containers will be moved from storage into the waste shaft
cage by means of a remotely-operated overhead crane, indexing table and
hydraulically-operated boom crane for loading the container into the
cage.
Each container will be mechanically secured in the cage and
transported, one at a time, unshielded, from the head-frame storage to
vault level down the waste shaft. It will be unloaded from the cage
onto an indexing table with a capacity for 8 containers, using a hydrau-
lically-operated boom crane. Details of the underground transfer station
are shown in Figure 4-10. The container will be removed from the
indexing table using the transporter hoist and grapple, and will th^n be
transported in a flask by a manned diesel-powered transporter through
the waste haulage drifts and panel drifts.
The transporter design is based upon existing 4-wheeled arti-
culated diesel mine vehicles. Containers will be loaded one at a time
with the flask located over the transfer room port. The flask will be
closed by a sliding door at the base. For transport, the flask will be
rotated to the horizontal position.
The transporter will be reversed into the room to the emplace-
ment hole location. With the transporter stationary the flask will be
raised to the upright position and final alignment will be performed.
After lowering the shielding sleeve and opening the flask, the container
will be lowered into the emplacement hole and the grapple released.
After emplacing the container, a temporary shielded plug will be placed
in the drill hole. Backfilling of the drill hole is described in
Section 4.6. The transporter will return to the underground transfer
station and the cycle will be repeated.
- 54 -
To meet emplacement schedules and maintenance conaider.itions
four transporters will be required.
4.5.4 Services
4.5.4.1 Ventilation
The underground ventilation system will serve the following
purposes:
1. To maintain dust concentrations below acceptable levels.
2. To provide the required air volumes for the operation of
diesel-powered equipment so that concentrations of harmful
gases and particles are kept within regulatory limits.
3. To provide a good underground working environment for all
personnel within the limits and standards set for working
temperature, humidity, and dust and gas concentrations.
4. To ensure that any airborne radioactive contamination arising
in an extreme accident is removed in a controlled manner with
minimum risk of exposure to workers.
The use of ventilation for control of thermal effects in the
rock has not been considered in this study.
In general, raining experience has shown that the ventilation
requirements for the operation of diesel equipment will also satisfy
personnel criteria for temperature, humidity, and airborne particulates.
The design of the ventilation system has therefore been hased on the
requirements for diesel equipment operation underground.
- 55 -
The total ventilation supply of 283 m /s is tabulated below by
functional requirement and distribution.
Function
Panel Development
Waste Handling
Backfilling
Rail Haulage
Service Installations
TOTAL
Enginepower (kW)
1 600
1 000
530
-
_
3 130
VentilationRequirement (m3/s)
127
80
43
10
23
283
Distribution (m3/s)
Downcast Ventilation Shaft 283
Central Shaft Group - Upcast in Waste and Service Shafts 23
Upcast Ventilation Shafts 260
Main Drift 127
Waste Transport Drifts 123
Rock and Backfill Rail Haulage Drifts 10
The sequence of operations described in Section 4.4.4 permits
separation of ventilation flows between emplacement and development
activities.
The ventilation flow diagram is shown in Figure 4-11. In the
ventilation intake building over the downcast shaft, a single 1081-kW
fan will operate; during wintertime, gas burners will heat the intake
air to 2°C.
Over each upcast shaft, a surface structure will house a dam-
per arrangement, a filter section end an axial flow fan. During normal
- 56 -
operations, exhaust air will bypass the filter chambers and be exhausted
by a f an.
In an emergency condition in which radioactive material might
enter the ventilation airstream underground, bypass dampers will close
and the air will be exhausted through the filter bank. This will con-
sist of medium-efficiency filters and high-efficiency (95 percent)
filters. Each filter bank, prefliter and high-efficiency filter will be
approximately 12 m wide and 2.3 m high.
For each operating panel, it will be necessary to use auxi-
liary fan installations and ventilation ducts to provide the required
ventilation in the individual rooms. The maximum requirements for
ventilation in the individual rooms are identical for panel development,
waste handling and backfilling activities. This amounts to approxi-
mately 19 in Is, which is governed by the use of an LHD unit and a
diesel truck during mucking for panel development, and by the simultan-
eous operation in a room of the waste transport truck and emplacement
service vehicle. This ventilation is also desirable in rooms during
backfilling to remove and dilute the dust.
4.5.4.2 Compressed Air
A pipe distribution of compressed air will be required through-
out the vault. The main need for compressed air will be for rock
bolting, shotcreting and minor excavations such as the rock and backfill
passes, which might be carried out using air-operated drilling or
mucking equipment, particularly during primary development. The prin-
cipal rock excavation drilling will be undertaken using electric-hydrau-
lic jumbos and will not require a compressed air supply. The surface
compressor station will comprise three reciprocating compressors, each3 2
rated for 0.6 m /s at 860 kN/m , driven by 225-kW electric motors.
- 57 -
Distribution system from the compressor station through the
service shaft and along the major drifts will employ steel flange bolted
pipes. In the panel drifts and emplacement rooms, portable pipes with
quick couplings will be used. At the collar of each panel in operation,
a water-trap receiver will be installed.
At the central shaft group, a compressed air distribution
system will be required to the various service installations for the
operation of air tools and equipment.
4.5.4.3 Water
The requirement for water during the vault operation will be
for drilling equipment, watering-down of blasted rock before mucking
operations commence, emplacement-hole drilling and room preparation
using air-water jets for flushing the excavation faces and floor. The
total maximum water demand has been estimated at 22 L/s.
Water will be supplied from the main surface distribution
system. In the service shaft, the pipe will be equipped with a pres-
sure-sensing device and an emergency shutoff valve located at the shaft
collar to close off in the event of a break in the water pipe in the
shaft. A pressure-reducing station will be located at the bottom of the
service shaft to provide 400 kN/m at points of usage. Distribution
pipes will run along each of the five major drifts. For each panel,
portable quick-coupled sections will be used in the panel drifts and the
emplacement rooms. As the rooms are completed, these pipes will be
removed and reused in other rooms.
4.5.4.4 Drainage and Pumping Systems
The requirements for the underground drainage and pumping sys-
tems will be determined by the water inflow into excavated openings from
- 58 -
the surrounding rock formation, and by the consumption of supplied water
in various vault operations. A capacity of 63 L/s has been established
as a minimum pumping requirement to handle these flows.
To ensure that natural drainage will take place through the
entire vault area toward the central shaft group, the major drifts will
slope 0.5% upward from the central shaft group. All panel drifts will
slope 2% down toward the central main drift with the individual emplace-
ment rooms sloping 2% down toward the panel drifts.
The main collection sump or basin at the main shaft group will
be sized to provide adequate depth of submergence over the pump suction
for satisfactory hydraulic performance, and to provide an operating
volume which will limit the motor start frequency to not more than once
per hour. Two high-pressure multistage cartridge-type centrifugal
pumps, each rated to deliver 63 L/s against the system design head, will
be located in a dry-sump arrangement adjacent to the collection sump.
Normal operation will consist of one pump operating under start-stop
level control from the collection sump, with the second pump functioning
as a standby unit. However, these pumps will be capable of simultaneous
operation in the event of high inflow to the collection sump. Discharge
piping from the pump to the surface will be installed in the service
shaft.
On the surface, the pumped mine water will be discharged into
a settling pond. Routine sampling and monitoring will be undertaken for
the detection of radioactive contaminants in the drainage water. If an
unacceptable level of radioactivity is detected in the drainage water,
mine water discharge will be redirected to an emergency holding pond on
the surface. The point of inflow of the radioactive drainage water into
the collector ditch in the rock rail haulage drift will be located, and
the contaminated water redirected into a permanently-installed lOO-mm
emergency drainage pipe installed along the wall of the rock rail
- 59 -
haulage drift. The standby pump and spare discharge pipe will be used
for segregated pumping.
4.5.4.5 Power System
The main underground distribution will be through two 13.8 kV
cables, one located in the service shaft and the other in either of the
upcast shafts, and two 13.8 kV cables running the entire length of the
centre main drift. All of these cables will be rated such that the
entire underground load can be supplied through one shaft and one main
drift cable.
The drainage pumps, skip hoists, downcast fan and backfill
blower will operate at 4.16 kV. Most of the other AC loads will operate
at 600 V. Power for stationary loads will be provided from distribution
boards located near the service shaft and one of the upcast shafts on
the surface, and near the ends of the main drift. Power to the mobile
loads will be provided by portable power centers to be located in the
panel drifts. The power for the locomotives at each level will be
provided by three 500 VDC rectifiers connected to each end and center
point of the trolley cables.
In all main and panel drifts, lighting will be provided by
high-pressure sodium vapor fixtures, spaced at 50-m centres. Illumi-
nation for the emplacement rooms will be provided by portable flood-
lights.
In case of failure of the main power distribution system, a
diesel-powered generator will automatically provide temporary power to
critical surface and underground installations, such as the service
cage, waste hoist and handling system, main fans and the underground
drainage pumps.
- 60 -
4.6 BACKFILLING AND SEALING
Backfill material within the vault will serve two principal
purposes.
1. It will act as a relatively impermeable barrier to the flow of
water in both the rooms and drifts.
2. It will serve as a conductive medium for the transfer of heat
from the container to the surrounding host rock within the
emplacement rooms.
The sorption properties of the backfill will also be bene-
ficia1 in retarding nuclide transport. The drill hole concept developed
in this study, however, was specifically designed to limit the reliance
on the geochemical buffer characteristics of the backfill as a contain-
ment mechanism. The overall sealing of the vault will also be a func-
tion of the nature of the interface area between the rock and backfill.
Room preparation will therefore be necessary to ensure that the per-
meability of this area is satisfactory relative to the backfill and rock
permeability properties.
Backfill will be placed in emplacement drill holes after com-
pletion of each row of four holes. The room will be backfilled upon
completion of container emplacement.
Backfilling and sealing of shafts and drifts is scheduled to
begin in 2045, following completion of container emplacement, and be
completed by 2050.
For the purpose of the conceptual design study it has been
assumed that only natural materials will be used for backfill. In addi-
tion, the use of as much excavated rock as possible has been incorpo-
rated.
- 61 -
The proposed backfill consists of:
Crushed rock coarse aggregate 55%
Pit run sand and gravel fine aggregate 35%
Bentonite clay 10%.
The surface backfill preparation plant is described in Section
3.2.4. Blended fine and coarse aggregates will be delivered via a pipe
in the service shaft to a bin at the backfill rail haulage level. The
bentonite will not be added to the backfill until immediately before em-
placement. The aggregates will be transported in the rail haulage drift
to the backfill passes.
Backfilling of emplacement holes will take place one row at a
time, sequentially with the waste emplacement, using a specially de-
signed service vehicle. The operation for each hole will be as follows:
1. The service vehicle shield will locate over the emplacement
hole.
2. The temporary hole plug will be removed and a batched quantity
of silica sand placed in the drill hole to backfill the
annulus between the container and drill hole wall.
3. The remainder of the drill hole will be backfilled with a
sand/cl>!y mixture, with compaction by a drop ram.
4. The shield will be raised and the process repeated at the next
hole.
The emplacement and drill-hole backfilling operations will
take place concurrently in different rooms. This will minimize the
interdependency of the two operations.
- 62 -
Placement of backfill in the rooms and drifts will employ a
pneumatic method, shown in Figure 4-12. Ben';onite will be blended with
the aggregates at the mixer, but water will be added to the backfill at
the nozzle to ensure placement at a satisfactory moisture content. The
placement machine will be electric powered to eliminate the need for
refuelling in the emplacement room. The 1.5 m of backfill above the
container will be sufficient to ensure shielding during room backfilling.
Shaft sealing may require breaking out the concrete lining at
selected locations to ensure intimate contact between the backfill and
rock. Pneumatic or mechanical methods may be used for placement and
compaction.
TABLE 4-1
INITIAL THERMOMECHANICAL CONSTRAINTS
Geometric Region of V&ult
1Container near field
Room and pillar
Far field
Thermomechanical Constraint
Container skin temperature
Container cavity stability
Near-field rock mass stability
Backfill volume - average temperature
Roof and rib failure/support
Integrated average of strength-stress
i ratio in the pillar
Rock mass stability
Quantification
150°C
(135°C rise)
Open and stable hole
Not supported
100°C
(85 °C rise)
Conventional rock
bolting requirements
> 2
No irreversibledeformation
TASK 1
PreliminaryDesignCriteria
Define constructionand operationalrequirements anddesign constraints
Define thermalrock mechanicsdesign constraints
TASK 2
PreliminaryDesignConcepts
Define pre-liminarydesign conceptusing modifiedPhase I and IIbaselineconcept
TASK 3Analysis
The fieldthermal-rockmechanicsanalyses
Room andpillarthermal androckmechanic sanalyses
Containernear fieldzonethermaland thermalrockmechanicsanalyses
TASK 4Design Vault
Long-termcreep rupture-prelimianryassessment
Seismicresponsepreliminaryassessment
Synthesize andsummar izethermal rockmechanics resultsand specifiedconstraintsinto designcriteria
TOSHEET 2
FIGURE 4-1: VAULT STUDY METHODOLOGY (Sheet 1)
TASK 4 CONTINUED
RockExcavation and
Handling
Sheet 1
*
i
Room Layout
BackfillingandSealing
ContainerHandling and
SafetyAssessment
UndergroundServices
(Ventilation,Water, Drain-age, Power,
etc.)
tVatLay
i
Itout
TASK 5
Schedule andCost Estimate
TASK 6
Summary Reports
DesignConceptReport
FIGURE 4-1. VAULT STUDY METHODOLOGY (SHEET 2)
- 66 -
1.0
0.1
0.01
0.001 \10 100 1000 10,000
TIME SINCE FUEL DISCHARGED FROM REACTOR (YEARS)
FIGURE 4-2. RADIOGENIC HEAT GENERATION OF IMMOBILIZEDWASTE AS A FUNCTION OF TIME
4 UPCAST VENTILATION| SHAFT200._
" "CPANEiT
t SERVICESHAFT
3600 300
~==—J-PANELDRIFT(TYP)
HALF FULL PANELPANEL(TYP)
DRIFTHAULAGE
223
ISOnlSOa
T1
CONTAINER0.457m » ~
f DETAIL
ALL DIMENSIONS IN METRES
o l l l SPACESR 30
LEL.IOOO
<t. PANELDRIFT
FIGURE 4-3. VAULT LAYOUT AND ROOM DETAILS
COLL** SHM-T, eeecrS M C S " * " " , CUT W
INSTALL SHUT
NSTAJJ. PCEMANEWT EXHAUST =»N '
COLL AC S**APT,
LLOPMEXT
WASTE EMPLA.CEK>EJ»JT
iT CAL PATH ITNP)
FIGURE 4-4. PRIMARY DEVELOPMENT CRITICAL PATH DIAGRAM
PANEL1 No.
o Excavationb Preparation<f Emplacementd Backfilling
(DETAIL OF SHADED AREA)
2025
85 90 95 05 102000
Emplacementstarts
16 20 25 30 35 40 45
YEARS
Emplacementcomplete
FIGURE 4-5. PANEL DEVELOPMENT AND EMPLACEMENT SCHEDULE
7 /LOAD FOR BLASTING ROCK BOLTING
oi
FIGURE 4-6. PANEL DEVELOPMENT AflD ROCK EXCAVATION SYSTEM
ROCK EXCAVATION ( 1 0 6 m3)
oo
985 90
totn
8oootn
o
Ol
20 25
wo
OJ
o
rv
tn
-
-
\
V\\
—•
Plant 1(20001
Plant 2(2U03)
v Plant 3\ (2006)
\ \
\
Start
Start
Start
Plant
\
N
\
no OJ
up
up
up
4 Start up(2014) 1
\ Plant 1 \\ Shutdown (2T830)
\ Plant 2 \
a 3,379,000
\ Shutdown (2033>lY Plant 3\ Shutdown (2036)
\
V Plant 4Shutdown (2044)
tnOOOO
OO-oOO
o'ooo
J o
WASTE CONTAIHERS
SERVICEPIPES
[EMERGENCYCAGE
EQUIPMENT aWORKERS CAGE
ROCKHAULAGESKIP
ROCKHAULAGESKIP
BACKFILL DOWNCOMER
FIGURE 4-8. SERVICE SHAFT CAGE AND ROCK HAULAGE SKIPS
- 73 -
DRILLING MUCKINGGROUNDSUPPORT
FIGURE 4-9. SERVICE SHAFT EXCAVATION METHOD
WASTESHAFT,
IMMOBILIZEDWASTECONTAINER
FIGURE 4-10. UNDERGROUND TRANSFER STATION
WASTE HAULAGE DRIFT
EXHAUSTFAN
AEXHAUSTFAN
MAIN DRIFT
ROCK RAILHAULAGE DRIFTBACKFILL DRIFT
WASTE HAULAGE DRIFTHEATER
VENTILATINGDOWNCASTSHAFT
FIGURE 4-11. VENTILATION FLOW SYSTEM
- 76 -
EMPLACEMENT HOLE DRILLING
EMPLACEMENT HOLE TESTING
ROOM SURFACE PREPARATION(washing, drill ing S grouting)
© WASTE EMPLACEMENT
SPREADING a COMPACTING
(6) FINAL BACKFILLING
FIGURE 4-12. IMMOBILIZED WASTE EMPLACEMENT AND BACKFILLING IN VAULT
5. COSTS AND MANPOWER REQUIREMENTS
5.1 COSTS
5.1.1 Basis for Cost Estimates
The basis for estimating the costs of both the surface facili-
ties and tisS undeiground vault is summarized below.
1. All costs are expressed in 1979 January Canadian Jcliars.
2. The centre was assumed to be located 300 km from a major urban
centre and within daily commuting distance of a town capable
of housing all employees.
3. Ic was assumed that construction of the centre would be car-
ried out by contractors and that the centre owner would erect
a construction camp to provide board and lodging for all
construction personnel.
4. There is no allowance for the operating costs of the demon-
stration vault.
5. For major cost items such as buildings, shafts, etc., detailed
estimates of labour, equipment capital, equipment operating,
supply, service and overhead costs were prepared.
6. For other items such as Hiiuor build >gs and services, the
estimate was based on unit d.st statistics and comparisons
with existing similar installations.
7. Interest charges during construction have not been included in
the budget cost estimates.
- 78 -
5.1.2 - Surface Facilities
These cose estimates are applicable only to the concept
described in this report. The costs can not be directly compared with
the vitrificatioa and packaging costs quoted by other nations because of
major differences in some of the design assumptions. Some assumption'
specific to this study are:
1. The burnup of CANDU fuel is 588 GJ/kg U.
2. The fuel is stored for 10 years prior to processing and
packaging.
3. There is no storage of high- and medium-level radioactive feed
liquid.
4. High- and medium-level radioactive liquid wastes from i:he
reprocessing plants are immobilized simultaneously.
The capital cost estimates for the centre facilities are shown
in Table 5-1. The total direct costs of constructing the facilities and
associated services would be $245 million. Indirect costs, which in-
clude construction indirect, engineering, administrative overheads,
taxes and commissioning, would amount to $184 million. This gives a
total estimated capital cost of ^ $429 million. Including a contingency
of 20%, the budget capital cost would be $515 million or $1.91/kg U.
The annual operating costs of the surface facilities are shown
in Table 5-2. The estimated lifetime operating cost would be $2940
million; so, including a contingency of 22.5%, the total budget lifetime
operating cost would be $3602 million or $13.36/kg U.
The cost to decommission the surface facilities is estimated
to be approximately $30 million, and the cost to provide surveillance
- 79 -
and security of the centre for a limited period after decommissioning
would be approximately $7 million.
The cash flow for the surface facilities is presented in
Table 5-3.
5.1.3 Vault
The capital cost estimates for the vault are given in Table 5-4.
The direct capital cost of the vault and associated structures and
services would be $175 million. Indirect costs would amount to $23
million for a total estimated capital cost of $198 million. Including a
contingency of 20%, the budget capital cost for the vault would be $238
million or $0.88/kg U.
It should be noted that costs incurred during exploration and
demonstration (Phase I, 1984 - 1993) ana during pri.nary development
(Phase II, 1994 - 1999) have been capitalized. Initial nurchase and
replacement of major equipment has been capitalized during panel devel-
opment and emplacement (Phase III, 2000 - 2043) and during decommis-
sioning (Phase IV, 2044 - 2050).
The annual operating costs of the vault are shown in Table 5-5.
The total estimated lifetime operating cost of the vault, including an
administrative overhead of 20%, would be $765 million. Including a
contingency of 22.5%, the total budget lifetime operating cost would be
$937 million or $3.48/kg U. All expenditures in Phases III and IV are
considered to be operating costs, with the exception of initial and
replacement purchases of major equipment. For the panel development,
emplacement, backfilling, maintenance and decommissioning phases, the
rates for various job classifications were set at approximately the same
as those used in the uranium mines in the Elliot Lake area. These rates
include all fringe benefits, vacation pay, shift work compensation and
bonuses where applicable.
- 80 -
The cash flow for the vault is presented in Table 5-6.
5.2 MANPOWER REQUIREMENTS
5.2.1 Surface Facilities
The construction of the surface facilities would take place in
four stages with each stage representing the addition of a plant. Based
on the capital costs and assumed construction duration, the construction
labour force *rould peak at 300 workers during the first stage, 150
during the second stage and 250 during the third and fourth stages.
The personnel required for the operation of the surface facili-
ties would peak at 940. These can be broken down as follows:
Immobilization Plants 1 and 2 360 (180/plant)
Immobilization Plants 3 and 4 490 (245/plant)
Support Svaff 90
A breakdown of the skill levels of the operating personnel is
shown in Table 5-7.
5.2.2 Vault
The vault development and operation manpower schedule, includ-
ing both owner and contractor staffs, is summarized in Table 5-8. The
manning estimates are budget estimates and include allowances for oper-
ations, administration and contingencies.
During Phase I (initial access and demonstration) and Phase II
(primary development) the manpower requirements fluctuate considerably.
The estimates shown are approximate and will be subject to smoothing
during the planning stages. It has been assumed that a contractor will
- 31 -
perform the work with some supervision of the owner's staff. Staff
requirements for the demonstration project have not been included.
The peak manning level during Phase I will be in the range 60
to 120. The peak during Phase II will be in the range 260 to 400.
During Phase III (panel development and emplacement), the
staff will increase to between 300 and 350 and then begin to decrease in
about 2029. A breakdown of the manpower skill levels is shown in
Table 5-9. The manpower skill levels distribution in Phase III is only
approximate, but is included to indicate the mix and the opportunities
for utilization of local labour, in terms of training and experience
requirements, for the main vault operation.
Phase IV (backfilling and sealing operations) (2044 - 2050) is
estimated to require about 135 personnel. These activities could be
extended in duration in order to minimize the impact on employinent at
the completion of the project.
Figure 5-1 shows the total manpower requirements for con-
tracting and operating the complete disposal centre.
- 82 -
TABLE 5.1
SURFACE FACILITIES CAPITAL COST
(1979 January Canadian Dollars)
Direct Costs
Site-related Work and Equipment
Site-related Services
Two Immobilization Plants (1500 Mg/a)
Two Immobilization Plants (3000 Mg/a)
Temporary Storage Building
Tunnels
Ventilation Exhaust Buildings
Auxiliary Buildings
Site Selection, Environmental and SafetyAssessment
First Year's Operating Supplies
TOTAL DIRECT COST (TDC)
Indirect Costs
Construction Indirect?? (22% of TDC)
Engineering (j0% of TDC)
Administrative Overhead
Taxes (5% of TDC)
Commissioning
TOTAL INDIRECT COST
TOTAL ESTIMATED CAPITAL COST
Contingency (20%)
TOTAL BUDGET CAPITAL COST (TBC)
Total($ x 1000)
8 572
32 500
61 990
94 225
7 500
8 293
2 016
21 813
6 000
2 420
245 329
53 972
73 599
1 600
12 266
42 644
184 081
429 410
85 882
515 292
TABLE 5.2
SURFACE FACILITIES ANNUAL OPERATING COSTS
•'.'.''. ' January Canadian Dollars x 1000)
Year
2000-2002
2003-2005
2006-2013
2014-2029
2030-2032
2033-2035
2036-2043
MiscellaneousRaw Materials
100
150
300
450
350
250
150
Coal andElectricity
1 371
1 947
2 840
3 733
3 153
2 577
1 681
TOTAL ESTIMATED LIFETIME OPERATING
CONTINGENCY (22. 5%)
C O S T
Maintenance
1 772
2 469
3 657
4 837
4 507
4 175
1 900
COST
TOTAL BIIDGET LIFETIME OPERATING COST
S
Manpower
9 380
14 280
20 200
26 320
21 700
16 940
10 640
ContractorManpower
2 016
3 024
3 954
5 040
4 032
3 024
2 016
$2940 million
$ 662 million
$3602 million
Taxes andInsurance
4 430
6 173
9 143
12 093
11 268
10 438
4 750
Total
25 862
41 529
67 220
93 231
78 975
64 530
34 723
- 84 -
TABLE 5.3
CASH FLOW FOR SURFACE FACILITIES
(1979 Canadian Dollars with no Financing Chargesincluding 20% conL::-','gen;.;)
•
Year
199419951996199719981999200020012002200320042005200620072008200920102011201220132014
t202820292030203120322033203420352036
1 -2043204420442045
Total
CapitalExpenditure($ million)
193142364234313334332012
212122322012
515
OperatingCost
($ million)
32.032.032.051.051.051.082.582.582.582.582.582.582.582.5
113.5
t113.5113.598.098.098.079.579.579.543.0
t43.0
3601.5
Others
5X
5X
iox
iox
o.ixx
o.ixx
30j
Decommissioning CostSurveillance and Security Cost
- 85 -
TABLE 5.4
VAULT CAPITAL COSTS
(1979 January Canadian Dollars)
Phase
DIREC
I
II
ii':
IV
I t e m
C COSTS
Initial upcast shafts and ventilation
Exploration and initial development
Service shaft
Downcast shaft
Primary and auxiliary ventilation
Waste shaft
Major drifts
Underground services
Waste handling installations
Backfill plant
Panel development
Waste handling
Backfilling
Room sealing and vault sealing
TOTAL DIRECT COST
TOTAL INDIRECT COST
TOTAL ESTIMATED CAPITAL COST
CONTINGENCY (20%)
TOTAL BUDGET CAPITAL COST
Total($ x 1000)
10 860
8 137
24 907
5 400
3 444
8 630
37 736
9 450
4 200
4 200
29 960
20 372
5 600
2 086
174 982
22 748
i97 730
39 .545
237 275
TABLE 5.5
VAULT ANNUAL OPERATING COST
(1975 January Canadian Dollars)
Phase
III
IV
Year
1999
2000-2002
2003-2005
2006-2013
2014-2028
2029
2030-2032
2033-2035
2036-2043
2044-2049
Annual Base Cost ($ x 1000)
PanelDevelopment
1045
1045
2090
3480
6265
6265
4870
3480
3965
WasteHandling
245
490
975
1460
14'60
1220
870
805
Backfilling
940
1880
3760
6160
5755
4700
3760
3760
16180
Services
5500
5500
5520
5845
5845
5500
5500
11000
5500
TOTAL ESTIMATED LIFETIME OPERATING COST $765 million
CONTINGENCY (22.5%) $172 million
TOTAL BUDGET LIFETIME OPERATING COST $937 million
- 87 -
TABLE 5.6
CASH FLOW FOR VAULT
(1979 January Canadian Dollars,
including 20% contingency)
Phase
I
Phase I
II
Phase II
III
Year
198419851986198719881989199019911992
Subtotal
1993199419951996199719981999
Subtotal
199920002001200220032004200520062007200820092010
Capital
634432
25
181324312924
132
34
31.
12
380732841842343022200200200
760
000512074706964227361
844
797746_---
797898---
340
(S x 1000)
Operating
19991212121616161616
__--__--
-
-_--_-
-
279464464464192192192796796796796796
Total
634432
25
18
1324312924
132
514991212151816161629
380732841342343022200200200
760
000512074706964227361
844
076210464464192192989694796796796136
.../cont.
- 88 -
TABLE 5 .6 , concluded
Phase Year
2011201220132014201520162017201820192020202120222023202420252026202720282029203020312032
| 2033
Phase 113
IV
Phase IV
20342035203620372038203920402041204220432044
Subtotal
20452046204720482049
Subtotal
Capital
---
4 746----
12 340----
4 746----
12 340----
7 403----
7 690----
75 343
2 828-__-
2 828
($ x 1000)
Operating
16 79616 79616 79624 17124 17124 17124 17124 17124 17124 17124 17124 17124 17124 17124 17124 17124 17124 17123 67719 95119 95119 95116 66816 66816 66811 97911 97911 97911 97911 97911 97911 97911 97911 932
804 478
26 55826 55826 55826 55826 558
132 790
Total
16 79616 79616 79624 17128 91724 17124 17124 17124 17136 51124 17124 17124 17124 17128 91724 17124 17124 17123 67732 29119 95119 95116 66816 66824 07111 97911 97911 97911 97919 66911 97911 97911 97911 932
880 321
29 38626 55826 55826 55826 b58
135 618
- 89 -
TABLE 5.7
SKILL LEVEL DISTRIBUTION OF SURFACE FACILITIES
OPERATING PERSONNEL DURING PEAK OPERATION
Professional
Skilled trades
Semiskilled trades
Labourer
Clerical
TOTAL
105
430
275
80
50
940
- 90 -
TABLE 5.8
VAULT MANPOWER LEVi^S SCHEDULE
Phase
I*
ri*
in**
IV*
Time
1984-1993
1994-1999
1999
2000-2002
2003-2005
2006-2013
2014-2028
2029
2030-2032
2033-2035
2036-2043
2044-2049
Administrationand Supervision
25
35
5
37
47
65
94
92
78
65
47
40
Operation
55
280
13
93
120
165
237
232
195
163
117
95
Total
80
315
18
130
167
230
331
324
273
228
164
135
* Estimates in Phases I, II and IV are approximately ± 30%
** Estimates in Phase III are ± 16%
- 91 -
TABLE 5.9
SKILL LEVEL DISTRIBUTION OF VAULT OPERATING
PERSONNEL DURING PHASE III OPERATIONS
Professionals
Skilled Trades2
Semiskilled Trades
Laborers
TOTALS
3t£ff
26
61
7
94
Labour
_
73
134
30
237
Total
26
134
141
30
331
1. Management, engineering, geological and other professionals
2. Mining, mechanical and waste-handling technician!-? and
supervisors with several years training and experience
3. Mining and mechanical equipment operators possibly trained
on the job
4. General laborers starting without previous training or
experience
1500
1990 2000 2010 2020(YEAR)
2030 2040 2050
FIGURE 5 - 1 . MANPOWER PROJECTIONS FOR THE IMMOBILIZEDWASTE DISPOSAL CENTRE
- 9J -
6. SUMMARY, CONCLUSIONS AND RECOMMENDATIONS
6.1 SUMMARY AMD CONCLUSIONS
6.1.1 General
This study has developed a conceptual design of a centre to
immobilize waste from reprocessing of natural uranium CANDU fuel and
dispose of it in an underground vault. The principal facilities and
equipment have been identified, construction and operation schedules
developed to meet the project milestones, and cost estimates prepared.
The quantities of waste which could be immobilized in the
proposed centre are those which would arise from what is presently
considered to be an optimistic projection of nuclear generation to the
year 2016. The design of the centre is modular in concept and can be
readily adapted to other scenarios.
It must be emphasized again, however, that the designs of
these facilities and equipment have not been optimized, but are offered
only as a possible design concept based on the stated assumptions and
constraints.
6.1.2 Technical Feasibility
The high-level wastes processed in the surface facilities will
be a mixture of the following two streams:
1. Concentrated high-level waste stream from fuel reprocesaing.
This stream will generate heat and will contain most of the
fission products.
2. An alkaline stream generated during solvent scrubbing oper-
ations in the reprocessing plant. This stream can carry up to
0.5% of the original plutonlum content of the irradiated fuel.
The feasibility of the process to immobilize this mixture has
not been demonstrated. Several countries in the world have the tech-
nology to immobilize the first stream but no one has immobilized the
second stream in large quantities. Considerable research effort is
being expended on this topic at WNRE. The remainder of the operations
at the centre are feasible with some expansion of technologies currently
available in Canada.
The shafts, hoists and underground facilities can be con-
structed using state-of-the-art mining technology. The influence of
heat generation by the waste on rock stability (granite or gabbro) has
been kept at acceptable levels through the selection of appropriate
container spacings, room-and-pillar design and vault layout.
Container surface and room backfill temperatures can also be
controlled never to exceed the assumed design maxima of 150°C and 100°C,
respectively. The container and backfill temperatures decay to close to
ambient geothermal levels within 1000 years.
Waste handling, emplacement and room backfilling can be
accomplished using adaptations of standard mining and material-handling
equipment. Radiation exposures during handling can be kept within
allowable limits.
The thermal-rock mechanics analyses have provided detailed
predictions of the initial state, transient thermal effects and non-
linear rock response and failure. Parametric studies of key parameters
have demonstrated the adaptability of the concept to suit actual rock
conditions and properties.
- 95 -
6.1.3 Schedules
The development cf the immobilization facilities has 1500
Mg U/a plants scheduled to start in years 2000 and 2003. 3000 Mg U/a
plants are scheduled to be in-service in 2006 and 2014. Modifications
to this schedule are possible if the waste arisings are different from
those assumed. The initial shafts and underground facilities should be
constructed in the period 1984 to 1987 to allow underground demonstra-
tions in the main vault area to commence in 1988. Adequate time must be
allowed before construction for bids, planning, detailed engineering,
mobilization and equipment procurement.
The main vault construction should commence in 1994 if em-
placement is to commence in 2000. Six years are available for demon-
strations before starting the main vault development for this particular
scenario.
The room and panel development, hole drilling, waste emplace-
ment and backfilling operations can be scheduled to suit the waste
immobilization rates. Considerable flexibility is available in oper-
ating rates.
The final drift and shaft backfilling and vault decommis-
sioning operations which, for the purposes of this study, are planned to
commence in 2045, can be scheduled at various rates to suit the avail-
able resources. Durations of 5 to 10 years appear realistic.
6.1.4 Cost Estimates
The capital and operating costs for the centre are summarized
in Table 6-1. For the surface facilities the capital cost is estimated
to be $515 million ($1.91/kg U) (1979 dollars) and the operating costs
to be $3602 million ($13.33/kg U ) , resulting in a total of $4117 -million
($15.24/kg U ) .
- 96 -
The capital cost of the vault is estimated to be $237 million
($0.88/kg U) and total operating costs at $937 million ($3.47/kg U ) ,
resulting in a total of $1174 million ($4.35/kg U ) .
The cost of decommissioning the centre and for surveillance
and security is estimated at $43 million ($O.16/kg U ) .
The total centre cost is therefore estimated to be $5335
million ($19.75/kg U). This cost is distributed over wastes arising
from 14 TW-h oi electrical generation, giving a unit cost of 0.40
mills/kW-h.
The surface facilities account for almost 70% of the capital
cost of the centre and approximately 80% of the operating cost. Of the
total cost of immobilization and disposal, $15.40 is accounted for by
the surface facilities and $4.35 by the underground activities.
Of the surface facility operating costs, the stainless steel
containers contribute $1680 million, and the immobilization plant man-
power contributes $1540 million (32% and 29% of the total centre cosf ,
respectively).
In the vault the cost of mining rooms, drilling holes, em-
placing wastes and backfilling are categorized as operating costs. The
cost of drilling the emplacement holes would be $110 million and the
total backfilling cost $318 million, of which $200 million was the cost
of bentonite supplies (6%, 3.7% and 2% of the centre total, respectively).
6.1.5 Manpower Requirements
The surface facilities construction labour force will build up
to a maxi.mim of 300. The vault construction labour force in the same
period (1994 - 2000) will peak at 300. The total construction labour
- 97 -
force in this period will therefore be approximately 600 and will be
primarily contractors' personnel.
The surface facilities operation manpower will peak at 940
during the period 2000 - 2035. The vault operation labour force in this
period will peak at 340, resulting in a total of 1280 on site. Of this
number 607 will be required at the site for the full operating period,
20(10 - 2043.
6.2 RECOMMENDATIONS
The following have been identified as study areas where
further attention could be useful. These are restricted to questions
which could have major impact on the design concept and its feasibility.
Optimization requirements have not been identified except in certain key
instances.
6.2.1 Surface Facilities
1. Separate immobilization of high-level and alkaline waste
streams. - This study would investigate the cost and tech-
nical impacts of separate waste immobilization for the same
scenario as developed for the mixed wastes.
2. Effects of reprocessing and waste immobilization systems
integration. - Following completion of the International Fuel
Cycle Evaluation (INFCE) study, this study could be updated to
consider a complete CANDU fuel cycle scenario, including
reprocessing, fuel fabrication and waste immobilization.
3. Future experimental work on waste immobilization should
include testing of alternative schemes for the solidification
of separate and mixed high-level and alkaline waste streams.
- 98 -
6.2.2 Vault
1. Further construction-scheduling studies of the primary devel-
opment phase could be undertaken to try to reduce the con-
struction time before emplacement.
2. Occupational radiation dose assessments of the reference and
other waste-handling and emplacement concepts should be made.
Analyses should also be made of accident scenarios.
3. The development of specially adapted emplacement hole drilling
equipment to suit the minimum room height and drilling rates
is important and can benefit from development work.
4. Backfilling and sealing methods for the shafts should be
developed in detail once the material, shaft liners and rock
response in the hydrogeological system have been established.
5. The drill-and-blast method for emplacement room excavation
should be assessed versus a possible tunnel-boring machine
method. This would include an investigation of the effect of
the blast-fractured zone on hydrogeology.
6. In view of the high cost, investigations should be made into
the effect of varying the bentonite content in the backfill.
Alternate backfill materials should also be investigated.
7. In-situ data should be acquired to confirm assumed conditions
and properties (in-situ stress, geothermal regime, joint
patterns, groundwater chemistry, etc.).
8. Laboratory, analytical and in-situ tests are required to
confirm the thermal-ror.k mechanics response around the con-
tainers in the medium term. The long-term potential for creep
rupture around the emplacement hole and room periphery requires
- 99 -
further assessment in terms of its impact on groundwater flow
in the vault zone.
9. Studies and tests are required to verify the maximum allowable
backfill temperatures.
10. Further definition is required of the far-field thermal-rock
mechanics criteria.
- 100 -
TABLE 6.1
COST SUMMARY WITH NO FINANCIAL CHARGES
(1979 January Canadian Dollars)
Item
iSURFACE FACILITIES*
Capital
Operating
TOTAL
VAULT
Capital
Operating
TOTAL
Total Capital
Total Operating
Decommissioning,Surveillance andSecurity
TOTAL
Total Cost
$ x 1000 $/kg U
515 292 1.91
3 601 778 13.33
4 117 070 15.24
237 275 0.88
937 268 3.47
1 174 543 4.35
752 567 2.79
4 539 046 16.80
43 200 0.16
5 334 813 19.75
* These cost estimates are applicable only to the
concept described in this report. They should
not be compared directly with the vitrification
and packaging costs quoted by other nations.
- 101 -
7. REFERENCES
1. J. Boulton (Ed.)» "Management of Radioactive Fuel Wastes: TheCanadian Disposal Program", Atomic Energy of Canada LimitedReport, AECL-6314 (1978).
2. Acres Consulting Services Limited and Associates, and WNREDesign and Project Engineering Branch and Associates, "ADisposal Centre for Irradiated Nuclear Fuel: ConceptualDesign Study", Atomic Energy of Canada Limited Report, AECL-6415 (1979).
3. Acres Consulting Services Limited and Associates, "RadioactiveWaste Repository Study, Parts I, II and III", Atomic Energy ofCanada Limited Report, AECL-6188-1, -7 and -3 (1978).
- 102 -
APPENDIX A
BIBLIOGRAPHY OF SUPPORTING STUDIES
TR-No. Title
47 Immobilized Fuel and Reprocessing Waste Vaults: Design
Specification and Scope of Work
48 Immobilized Fuel and Reprocessing Waste Vaults: Preliminary
Design Concepts
53 Reprocessing Waste Vault: Container Near-Field Thermal-Rock
Mechanics Analyses
54 Reprocessing Waste Vault: Room and Pillar Thermal-Rock
Mechanics Analyses
55 Reprocessing Waste Vault: Far-Field Thermal-Rock Mechanics
Analyses
56 Immobilized Fuel and Reprocessing Waste Vaults: Long-Term
Creep Rupture - Review and Assessment
57 Immobilized Fuel and Reprocessing Waste Vaults: Seismic
Response - Review and Assessment
58 Immobilized Fuel and Reprocessing Waste Vaults: Design
Criteria and Synthesis of Thermal-Rock Mechnics Analyses
60 Reprocessing Waste Vault: Design Concepts and Layouts
61 Immobilized Fuel and Reprocessing Waste Vaults: Rock
Excavation and Handling System
- 103 -
TR-No. Title
62 Immobilized Fuel and Reprocessing Waste Vaults: Shafts and
Hoists
64 Reprocessing Waste Vault: Container Handling System
65 Immobilized Fuel and Reprocessing Waste Vaults: Underground
Services
66 Immobilized Fuel and Reprocessing Waste Vaults: Backfilling
System
68 Reprocessing Waste Vault: Development and Operation -
Schedule and Cost Estimates
74 Conceptual Design Study of the Surface Facilities at the
Immobilized Waste Disposal Centre
- 104 -
APPENDIX B
THERMAL ROCK MECHANICS
B.I INTRODUCTION AND OBJECTIVES
The objective of the thermal rock mechanics study was to
establish the criteria for use in the conceptual design studies for the
vault. Specifically, this requires establishing the thermal loadings
that are acceptable within the limitations of the specifications and
design options .
For the purpose of this study, the vault area has been divided
into three regions :
1. The container (near-field) region which includes the container
emplacement hole and the volume of rock along the room and
pillar, extending from the room floor to a few metres below
the container.
2. The room-and-pillar region which includes the rock mass in the
room-and-pillar unit and extends to several room diameters
both above and below the room.
3. The far-field region which extends vertically from the surface
to two or more times the vault depth below the level of the
vault, and horizontally to at least a vault's length beyond
the edges of the vault.
Specified thermal and mechanical constraints for these regions
are summarized in Table B-l.
- 105 -
The design specification requires that the containers (3.03 m
in length and 0.457 m in diameter) be emplaced in he'> s drilled in the
floor of the room. Retrieval of the containers is not considered in the
design studies, and the room will be backfilled immediately after em-
placement of the waste containers.
Preliminary layouts were developed prior to undertaking the
thermal mechanical analyses. The arrangements were based primarily on
construction and operational considerations, with individual panels
400 m wide by 800 to 1400 m in length.
The design was such that modifications Co the thermal loadings
could be achieved within this concept by varying the spacing of the
rooms (extraction ratio) or by varying the spacing of the containers
along the room (pitch).
In addition, revisions to capacity requirements may be met by
the extension of panels or addition of further panels. The transverse
spacing and the number of containers across the room was fixed for these
studies.
B.2 MATERIAL PROPERTIES
The thermal and mechanical properties used in this study are
summarized in Table B-2.
Two specific rock types, granite and gabbro, were considered.
These were differentiated by differences in their thermal conductivity
and coefficient of thermal expansion. For the rootn-and-pillar analyses,
the variation of rock strength was also examined.
The vertical in-situ stress in the models was assumed to
result from gravitational load only. The horizontal stress was taken
as a function of depth, based qn Herget^ " , and equal to 1.5 times the
- 106 -
vertical stress at a depth of 1000 m. The g&othermal gradient was
assumed to be 15°C/km, with an average surface temperature of 0°C.
Detailed data on the geometry of rock jointing in plutons of
the Canadian Shield are not available. For this study, three models
have been used.
1. Unjointed Rock Material - representing the upper end of the
range of strength of rock masses
2. Ubiquitously-Jointed Model - in which two vertical sets and
one horizontal set were assumed over the entire rock mass,
representing the lower end of the range of rock mass strength
3. Blast-Fractured Zor.e/Discrete Joint Models - used in the
room-and-pillar analyses as being a reasonable approximation
for anticipated conditions.
For the 2-dimensional plane-strain rock mechanics analyses,
a linear Mohr-Coulomb failure criterion was used for both the intact
rock and joints. In addition, a "no-tension" criterion was employed
in all the analyses. "No-tension" modelling involve:- reversing any
tensile forces arising during the analyses and transferring these
forces to adjacent rock. This procedure is repeated until no tensile
stresses remain. This load transfer mechanism is described in detail
by Zienkiewicz^B"2).
In each region the ratio of available shear strength to
shear stress was computed for both intact rocks and joints, and ex-
pressed as the "strength ratio". Regions with strength ratios of
unity thus represent zones of strength failure. Areas of the models
in which the "no-tension" criterion was applied have been referred to
as a "perturbed fissure zone". These represent areas in which
existing fractures may be opened.
- 107 -
B.3 GENERAL CONSIDERATIONS
The thermal rock mechanics analyses of the three regions of
the vault were performed using two-dimensional finite-element models and
the material properties listed in Table B-2.
A matrix of the important variables, extraction raclo, pitch
and panel thermal loading (PTL) for near-fi°ld and room-and-pillar
analyses, or gross thermal loading (GTL) for far-field analyses, was
used to define the required thermal analyses. The heat-generation
characteristics of the wastes are presented ir Section 4.2. The
extraction ratio, pitch and PTL satisfying the thermal constraints for
all three regions of the vault were chosen for the subsequent rock
mechanics analyses. All analyses considered hoth granite and gabbro
as potential host rocks.
It was recognized that a complete parametric analysis of the
vault alternatives would be excessively time-consuming and expensive.
At the present conceptual stage of design, such studies could not,
therefore, be justified. Some parameters such as backfill temperature
and container skin temperature were limited by maximum values in the
initial specification. Parameters such as room dimensions, container
numbers and spacing across the room and minimum pitch were set at the
preliminary layout study stage.
A hierarchy of constraints and restrictions was therefore
established for the analyses.
The first level was represented by the geometric restrictions
which were developed during the preliminary layout study stage. Thus,
only layouts which satisfied these geometric restrictions were con-
sidered for analysis.
- 108 -
The second level was represented by thermal constraints,
typically container skin temperature and average backfill temperature.
Thermal analyses were, therefore, undertaken and combinations of pitch
and extraction ratio which satisfied the thermal constraints were
defined. These analyses were undertaken primarily with the container
near-fields and room-and-pillar models.
The third level was represented by stress and deformation
constraints and restrictions. These required nonlinear-coupled thermal-
mechanical analyses of the three vault regions. Because of the com-
plexity, it was advantageous to limit the number of analyses as much as
possible. Only combinations of pitch and extraction ratio which
satisfied the thermal constraints were, therefore, selected for the
thermal mechanical analyses.
Examination of the proposed layout indicates that to achieve
the same GTL, reduction of the extraction ratio would be less expensive
than an increase in the pitch; the former requires lengthening the
limited number of panel drifts, but the latter requires lengthening all
the rooms. The thermal loadings for the design criteria satisfied all
thermal and thermal-mechanical specified constraints, as well as the
restrictions developed in the course of the study.
B.4 ANALYSES OF THE VAULT
B.4.1 Container Near-Field
The thermal-mechanical analyses of the container used a two-
dimensional model of a horizontal section through the vault floor at the
mid-plane of the container drill hole (Figure B-l). Thermal analyses
were performed using the principle of superposition. In this method,
the container mid-plane radial temperature distribution is determined
from a finite-element model of an idealized single container in an
- 109 -
infinite medium. The temperature in a field of multiple containers is
then determined by summation of temperature rises from contributing
containers. The principal criteria addressed in this model were:
1. The maximum container skin temperature should not exceed 150°C
2. Irreversible thermal mechanical responses within the drill
hole should be minimal.
A variety of extraction ratios and pitch which satisfied the
constraint skin temperature criterion for both the granite and gabbro
concepts were developed. The allowable ranges are shown in Figures B-2
and B-3 for granite and gabbro, respectively. These indicate that the
minimum container drill-hole spacing constraint is the governing cri-
terion for extraction ratios up to 25% for gabbro and up to 35% for
granite. These cori
gabbro and granite.
granite. These correspond to PTL's of 24 and 33 W/m , respectively, for
For the rock-mechanics analyses, both intact and jointed rock
were modelled. The jointed rock contained two vertical, orthogonal and
ubiquitous-joint sets, with strikes of 0°, 90°, 45° and -45° with
respect to the axis of the room. The ratios of the horizontal in-situ
stresses (normal versus parallel to the longitudinal axis of the room)
were assumed to be 1.5, 1.0 or 0.67. In all cases, one of the two
horizontal stresses was taken as 1.5 times the vertical geostatic stress.
The results showed that for either granite or gabbro the depth
of penetration of failure zones radially into the rock mass around the
drill holes was as follows:
1. Intact Rock - No intact-rock failure was predicted on excava-
tion. Strength failure occurred due to the thermal stresses
and penetrated a maximum distance of 5 cm at 10 years after
emplacement
- 110 -
2. Jointed Rock - Joint-strength failure was predicted for the
ubiquitous joints up to a penetration of 5 cm on excavations.
The joint-strength failure zone increased to a maximum depth
of 10 cm due to thermal stresses at 20 years after emplacement
(Figure B-4).
Only insignificant changes in these results were produced by
varying the joint orientations or the ratio of the horizontal stresses.
The minor extent of the strength-failure region is considered
to be acceptable from the point of view of stability or support of the
container near-field region. While no backfill is specifically required
in the annulus between the container and the drill-hole wall, the results
indicate that it would be prudent to include some to support any frac-
tured rock around the drill hole.
B.4.2 Room and Pillar
The thermal and thermal-mechanical analyses of the room-and-
pillar region were performed using the two-dimensional finite-element
model shown in Figure B-5.
The principal constraints to be satisfied were:
1. Maximum volume-averaged room backfill temperature to be 100°C-
2. Room stability to be achieved by conventional mining practices.
3. Average pillar strength ratio to be greater than 2.
These are summarized in Table B-l.
The parametric thermal analyses defined the allowable ranges
of extraction ratio, pitch and PTL which met the constraint that the
Ill -
volume-average room backfill temperature shall not exceed 100°C. These
are shown in Figures B-2 and B-3 for granite and gabbro, respectively.
The temperature-time history for the room backfill is shown in Figure
B-6. For the granite vault, the backfill temperature constraint limited2
the maximum allowable PTL to about 27 W/m . For the gabbro, the same
constraint United the maximum allowable PTL to about 24 W/m .
Based on the results of the container near-field and room-and-
pillar thermal analyses, for analytical expediency the following single
configuration was selected for thermomechanical analyses for both the
granite and gabbro vault concepts:
extraction
PTL
pitch
vatio =
>
25%
24 W/m2
1.5 m.
The nonlinear finite-element analyses of the room-and-pillar
concept were performed using the following three models:
1. Unjointed rock model.
2. Ubiquitously-jointed model.
3. Blast-fractured zone/discrete joint model.
Of these models, the blast-fractured zone/discrete joint model
is believed to best represent conditions of openings in hard-rock mining,
as evidenced by core drilling, stress determination and seismic
tests ' ' " . The analyses showed that the incremental changes in the
extent of the region of strength failure due to the thermal cycle were
small compared to the effects of the initial excavation. This is illus-
trated for the blast-fractured zone/discrete-joint model in Figures
B-7, B-8, B-9 and B-10. The average strength ratio in the pillar is
always well in excess of the required value of 2, as shown in the figures.
- 112 -
The regions of strength failure indicated by the analyses are
considered similar to those which can be expected in typical hard-rock
excavation at the proposed depth. Conventional rock-support methods
used in mining are considered adequate for the support of these regions.
B.4.3 Far-Field
The principal criterion addressed in the far-field analyses is
the requirement for no irreversible strains in the far-field rock mass.
For the far-field analyses, che thermal loading considered was
a GTL =23.6 W/m (this is equivalent to PTL = 24 W/m ) . This was
selected on the basis of the container near-field and room-and-pillar
thermal analyses. With this thermal loading, the maximum temperature at
the mid-plane of the vault was found to occur 50 years after emplacement
of the waste. Maximum temperatures were 87°C for granite and 102°C for
gabbro. The room-and-pillar and far-field analyses thus showed good
agreement in terms of maximum temperatures within the vault.
The thermal-mechanical analyses of the far-field region used
the no-tension type of analyses. No regions of perturbed fissure zones
were noted for this vault. In addition, no region of shear strength
failure was observed for either the granite or gabbro rock. The maximum
vertical displacement of the ground surface occurred for both rock types
approximately 2000 years after emplacement and was 10 cm for gabbro and
13 cm for granite.
B.5 SUMMARY OF ANALYSES
The t» rmal-mechanical constraints and allowable ranges for
pitch and extract!. •• ratio for the vault concept are summarized in
Figure B-ll.
- 113 -
For both granite and gabbro the preferred PTL-pitch-extraction
ratio combinations are controlled by the minimum drill-hole spacing and
the backfill temperature constraints. However, an increase in the
backfill temperature constraint or reduction in the container skin
temperature constraint could make this latter constraint significant,
particularly for a vault in gabbro. Variation in effects of far-field
constraints were not examined parametrically, but are not anticipated to
be significant at the thermal loadings required by the other constraints.
Room stability and pillar strength ratio criteria do not appear to be
critical for any of the thermal loadings considered.
Based on the analyses described, the thermal and thermome-
chanical constraints and restrictions and the common extraction ra io of
25%, the following configuration was selected for the vault design
criteria in both granite and gabbro:
Extraction ratio - 25%
PTL - 24 W/m2
GTL - 23.6 W/m2
Pitch - 1.5 ra
For gabbro, the selected configuration is controlled by the
allowable container spacing, container skin temperature and backfill
temperature constraints at an extraction ratio of 25%. The selected
configuration for the granite vault is defined by the minimum container
spacing constraint and the common extraction ratio value of 25/S estab-
lished by the gabbro case.
- 114 -
REFERENCES
B.I Herget, G., "Variations of Rock Stresses with Depth at aCanadian Iron Mine", Int. J. Rock Min. Sci. 10, No. 1, 37(1973).
B.2 O.C. Zienkiewicz, B.E. Valliappan «md J.P. King, "StressAnalysis of Rock as a No-Tension Material", Geotechnique 18.55 (1968).
B.3 D.F. Coates, "Rock Mechanics Principles", Mines Branch Mono-graph 847, Ottawa, 1967.
B.4 L. Obert and W.I. Duvall, "Rock Mechanics and the Design ofStructures in Rock", J. Wiley and Sons, 196 7.
B.5 Geller, L.B., "A New Look at Thermal Rock Fracturing", Trans.Institution of Mining and Metallurgy 79_, A133 (1970).
TABLE B-l
SPECIFIED THERMAL AND MECHANICAL CONSTRAINTS FOR VAULTS
Geometric Regionof Vault
Containernear-fieId
i
I
j Room andpillar
i
ii
Far-field
Thermomechanical Constraint
Container skin temperature
I
Container cavity stability
Near-field rock mass stability
Backfill volume-averagetemperature
Roof and rib failure/support
Integrated average of strength-stress ratio in pillar
Sustained long-term temperature
Rock mass stability anddeformation
Ground surface movement
Allowable Magnitude
150°C
(135°c rise)
open and stable hole
not supported
100 °C
(85°c rise)
conventional rock-bolting requirements
> 2
i not applicable
negligible irreversibledeformation and per-
J turbed fissure zoneI < 100 m deep
comparable to long-termregional movements
TABLE B-2
THERMAL AND THEEMOMECHANICAL MATERIAL PROPERTIES
Property
Thermal Conductivity
Specific Heat
Density
Young's Modulus
Poisson's Ratio
Angle of Internal Friction- Peak- Residual
Cohesion- Peak- Residual
Coefficient of ThermalExpansion
Units
W/m/K
J/kg/K
kg/m3
MPa
DegreesDegrees
MPaMPa
K"1
Intact
3
800
2800
40000
0
4535
191
8 d0" 6
Granite
Rock
ol,2
1
1
1
.21
33
2
.92
,1.*
Joints
_
-
-
-
-
4035
10.
-
33
2
32
Intact
2.
800
2800
40000
0.
4535
191
1
Gabbro
Rock
01'2
1
1
1
21
33
2
92
.,1.4
Joints
-
-
-
-
4035
10.
-
3
2
32
Acres Consulting Services Limited, "Radioactive Waste Repository Study",Parts 1, 2 and 3, for Atomic Energy of Canada Limited, Atomic Energy of CanadaLimited Report, AECL-6188/1, -2 and -3 (1978).
H. Stille, A.S. Burgess and U. Lindblom, "Groundwater Movement Around aRepository - Geological and Geotechnical Conditions", KBS Technical Report 54:01 (1977).
Acres Consulting Services Limited, "Atomic Energy of Canada Limited Radioactive WasteRepository Study", Topical Report II - Room Stability (1977).
L,B. Geller, "A New Look at Thermal Rock Fracturing", Trans. InstitutionMining Metallurgy, 79; A133-A170 (1970).
- 117 -
PIT.JAR
30m
PILLAR
O O O Oo o o oo o o oo o'o-oo o o oO o O Oo o o o
7.5 m
FIGURE B-l. COMTAINER NEAR-FIELD MODEL REGION
- 118 -
Container Surface Constraint: 150°C(135°C rise)
Backfill Constraint: 100°C(85°c rise)
10 W/m
ALLOWABLERANGE
1.5 2.5
FIGURE B-2. THE RANGES OF PITCH AND EXTRACTION RATIOTHAT MEET THE THERMAL AND DRILL-HOLESPACING CONSTRAINTS FOR A GRANITE VAULT
- 119 -
en
o
Container SurfaceConstraint: 150°C
(135°c r ise)Backf i l l Constraint:
100°C (85°c r ise)
^LE SPAC-
CONSTRAINT
0.5 1.5PITCH (m)
2.0 2.5
10 W/ni
ALLOWABLERANGE
FIGURE B-3. THE RANGES OF PITCH AND EXTRACTION RATIOTHAT MEET THE THERMAL AND DRILL-HOLESPACING CONSTRAINTS FOR A GABBRO VAULT
10cm SCALEH +
oI
Time = 0.0 a Time = 0.1 a Time = 1.0a Time = 10 a Time = 20 a Time = 100 a
FIGURE B-4. GRANITE VAULT: NEAR-FIELD STRENGTH RATIO CONTOURS AT VARIOUS TIMESAFTER EMPLACEMENT WITH EQUAL INITIAL HORIZONTAL STRESSES
- 121 -
20 n aboveroom free tomove verticallyfor stress —analyses
Room centrelineinsulated forthermal analyses
Room centrelinefixed horizon-tal ly for stressanalyses
1,000 m belowground surface
Immobilizedwaste
20 m below roomfixed verticallyfor stressanalyses
150 m abovecentre of roomfixed at 0°Cfor thermalanalyses
Pillar centrelineinsulated forthermal analyses
Pillar centrelinefixed horizontallyfor stress analyses
150 m below centreof room fixed atD°C
FIGURE B-5. FINITE-ELEMENT MESH FOR THERMAL-ROCKMECHANICS ANALYSIS OF ROOM-AND-PILLAR REGION
90
80
70
60
50
40
30
20
10
0
.
^,
/
J
ER ?5
**>
"0 k =
N\
X\
3 l / ra K
MM —m. —
TMAX = 83 K,S = 2.3m ,
PTL = 27 .2 W/ITI
TMAX = 73 KS = 1.5m ,
PTL = 2 3 . 9 W/rn
TMAX = 55KS = 2.On ,
PTL = 1 7 . 9 H/ni
6 8 10 20 40 60 80 100
TIME (YLAR?)
200 400
FIGURE B-6 . BACKFILL TEMPERATURE RISE AS A FUNCTION OF TIME FORVARIOUS VALUES OF PITCH, S, FOR A GRANITE VAULT
- 123 -
ER = 25%DEPTH = 1,000m
Blast-Fracturedwith 90° Joint,
DISCRETE VERTICAL JOINT
FIGURE B-7. ROOM-AND-PILLAR REGION CONTOURS OF STRENGTH RATIO AT EXCAVATION(TIME = 0) , WITH A BLAST-FRACTURED ZONE AROUND THE ROOM HAVINGUBIQUITOUS VERTICAL JOINTS, A DISCRETE VERTICAL JOINT AT 4 mFROM CENTRE OF ROOM, AND WEAK UNJOINTED ROCK ELSEWHERE (GRANITEOR GABBRO)
- 124 -
PITCH = 1.5 mER = 25% ,
PTL = 24 V/m
UHJOINTED ROCK
DISCRETE VERTICAL JOINT
FIGURE B-8. ROOM -AND-PILLAR REGION CONTOURS OF STRENGTH RATIO 10 YEARSAFTER EMPLACEMENT, USING MODEL OF FIGURE B-7 (GRANITE OR GABBRO)
- 125 -
WSTE
PITCH = 1.5mER = 25% ~
PTL = 24 V/mDEPTH = 1,000m
DISCRETE VERTICAL JOINT
FIGURE B-9. GRANITE VAULT: ROOM-AND-PILLAR REGION CONTOURS OFSTRENGTH RATIO 75 YEARS FROM EMPLACEMENT, US IMG MODELOF FIGURE B-7
- 126 -
PTL = 24 W/mDEPTH = 1,000m
DISCRETE VERTICAL JOINT
FIGURE B-1O. GABBRO VAULT: ROOM-AND-PILLAR REGIONCONTOURS OF STRENGTH RATIO AT 1 YEAR AND 75 YEARSFROM EMPLACEMENT, USING MODEL OF FIGURE R-7
1.5 2.0PITCH On)
FIGURE B-ll. THERMALMECHANICAL CONSTRAINTS
ISSN 0067-0367 ISSNOO67-0J67
To identify individual documents in the serieswe have assigned an AECL- number to each.
Please refer to the AECL- number when
requesting additional copies of this document
from
Scientific Document Distribution Office
Atomic Energy of Canada Limited
Chalk River, Ontario, CanadaKOJ UO
Pour identifier les rapports individuels faisant partie de cetteserre nous avons assigne'un numero AECL-"a chacun.
Veuillez faire mention du numero AECL -si vousdemandez d'autres exemplaires de ce rapport
au
Service de Distribution des Documents Officiels
L'Energie Atomique du Canada Limitee
Chalk River, Ontario, Canada
KOJ 1JO
Price: $7.00 per copy prix: $7.00 par exemplaire