Decision 2013-369
Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation Foothills Area Transmission Development October 7, 2013
The Alberta Utilities Commission
Decision 2013-369: Alberta Electric System Operator, AltaLink Management Ltd. and
ENMAX Power Corporation
Foothills Area Transmission Development
Applications No. 1608620, No. 1608642, No. 1608637, No. 1608643, No. 1608649,
No. 1608846, No. 1608861 and No. 1608862
Proceeding ID No. 2001
October 7, 2013
Published by
The Alberta Utilities Commission
Fifth Avenue Place, Fourth Floor, 425 First Street S.W.
Calgary, Alberta
T2P 3L8
Telephone: 403-592-8845
Fax: 403-592-4406
Website: www.auc.ab.ca
Contents
1 Introduction and background .............................................................................................. 1 1.1 The Foothills Area Transmission Development applications ........................................ 4
1.1.1 Two AESO need applications ........................................................................... 4 1.1.1.1 FATD need Application No. 1608620 ................................................. 4 1.1.1.2 Amendment to the SATR NID Application No. 1608846 .................. 5
1.1.2 Four facility applications associated with the FATD NID ............................... 6 1.1.2.1 AltaLink Application No. 1608642 – Langdon to Janet ...................... 6 1.1.2.2 AltaLink Application No. 1608637 – north Foothills transmission
development ...................................................................................................... 6 1.1.2.3 AltaLink Application No. 1608643 – Foothills 138-kV transmission
development ...................................................................................................... 7
1.1.2.4 ENMAX Application No. 1608649 ..................................................... 7
1.1.3 Two facility applications associated with the SATR NID amendment ............ 7 1.1.3.1 AltaLink Application No. 1608861 – south Foothills transmission
development ...................................................................................................... 7 1.1.3.2 AltaLink Application No. 1608862 – Windy Flats 138S substation
and line reconfiguration .................................................................................... 8 1.2 Process for new transmission and legislative framework .............................................. 8
1.2.1 Need applications .............................................................................................. 9
1.2.2 Facility applications ........................................................................................ 10 1.2.3 Other requirements.......................................................................................... 13
2 The AESO’s need applications .......................................................................................... 13 2.1 Assessment of the need to expand the transmission system in southern Alberta ........ 14
2.1.1 Views of the AESO ......................................................................................... 14 2.1.1.1 Application No. 1608620 – FATD NID ............................................ 14
2.1.1.2 Amendment to the SATR NID .......................................................... 16 2.1.2 Views of the Diagonal group .......................................................................... 17 2.1.3 Views of Phyllis Robertson ............................................................................ 17
2.1.4 Views of Industrial Power Consumers Association of Alberta (IPCAA)....... 17
2.1.5 Views of Benign Energy Canada II Inc. (Benign Energy) ............................. 18 2.1.6 Views of TransAlta Corporation (TransAlta) ................................................. 18 2.1.7 Views of ENMAX Green Power Inc. (EGPI) and ENMAX Shepard Inc. (ESI)
......................................................................................................................... 19 2.1.8 Commission findings ...................................................................................... 19
2.1.8.1 Application No. 1608620 – FATD NID ............................................ 19 2.1.8.2 Amendment to the SATR NID .......................................................... 20
2.2 Reasonableness of the proposed technical solutions .................................................... 20 2.2.1 Views of the AESO ......................................................................................... 21
2.2.1.1 FATD NID ......................................................................................... 21 2.2.1.2 Amendment to the SATR NID .......................................................... 26
2.2.2 Views of AltaLink........................................................................................... 30
2.2.3 Views of the Diagonal group .......................................................................... 32 2.2.4 Views of Phyllis Robertson ............................................................................ 39 2.2.5 Views of IPCAA ............................................................................................. 40
2.2.5.1 FATD NID ......................................................................................... 40 2.2.5.2 Amendment to the SATR NID .......................................................... 41
ii • AUC Decision 2013-369 (October 7, 2013)
2.2.6 Views of TransCanada Energy Ltd. (TransCanada) ....................................... 42
2.2.7 Views of Ronald and Laurie Conner .............................................................. 43 2.2.8 Views of Powerex Corp. (Powerex) ............................................................... 43 2.2.9 Commission findings ...................................................................................... 45
3 Criteria and route siting principles ................................................................................... 57 3.1 AltaLink’s routing methodology .................................................................................. 57
3.1.1 Preliminary siting stage................................................................................... 58 3.1.1.1 Preliminary routings .......................................................................... 66
3.1.2 Detailed siting stage ........................................................................................ 69
3.1.3 Final siting stage ............................................................................................. 74
4 Consultation ......................................................................................................................... 79 4.1 Views of AltaLink ........................................................................................................ 80
4.1.1 Group and personal consultation .................................................................... 81 4.1.2 Aboriginal consultation ................................................................................... 82 4.1.3 AltaLink response to intervener consultation concerns .................................. 82
4.2 Views of the interveners............................................................................................... 83 4.2.1 Langdon to Janet application .......................................................................... 83
4.2.2 North Foothills and Foothills 138-kV applications ........................................ 84 4.2.3 South Foothills and Windy Flats 138-kV applications ................................... 85
4.3 Views of ENMAX ....................................................................................................... 85
4.4 Commission findings ................................................................................................... 85
5 Environment ........................................................................................................................ 87 5.1 Introduction .................................................................................................................. 87 5.2 Application No. 1608642 – Langdon to Janet ............................................................. 90
5.3 Application No. 1608637 – north Foothills transmission development ...................... 91 5.4 Application No. 1608643 – Foothills 138-kV transmission development ................... 94
5.5 Application No. 1608861 – south Foothills transmission development ...................... 95 5.6 Application No. 1608862 – Windy Flats 138S substation and line reconfiguration ... 96 5.7 Application No. 1608649 – ENMAX application........................................................ 97
6 Electrical considerations .................................................................................................... 97 6.1 Views of the applicant .................................................................................................. 97 6.2 Views of the interveners............................................................................................... 99 6.3 Commission findings ................................................................................................... 99
7 AltaLink Application No. 1608642 – Langdon to Janet ................................................ 101 7.1 Preferred and alternate route selection ....................................................................... 101
7.2 Views of AltaLink ...................................................................................................... 102 7.3 Views of the interveners............................................................................................. 104
7.3.1 Interveners on the preferred route ................................................................. 104 7.3.2 Interveners on the alternate route .................................................................. 108 7.3.3 Intervener objecting to preferred route variant ............................................. 110
7.4 Commission findings ................................................................................................. 111
8 AltaLink Application No. 1608637 - north Foothills transmission development ........ 112 8.1 The preferred and stakeholder-proposed Foothills substation site selection ............. 112
AUC Decision 2013-369 (October 7, 2013) • iii
8.1.1 Introduction ................................................................................................... 112
8.1.2 Views of AltaLink......................................................................................... 113 8.1.3 Views of the interveners ............................................................................... 115 8.1.4 Commission findings .................................................................................... 119
8.2 The preferred and alternate 240-kV transmission routes ........................................... 120 8.2.1 Introduction ................................................................................................... 120 8.2.2 Interveners along the north Foothills line routes .......................................... 123 8.2.3 Views of AltaLink......................................................................................... 124 8.2.4 Views of the interveners ............................................................................... 129
8.2.5 Commission findings .................................................................................... 132 8.3 Tower structure options at the Bow River crossing ................................................... 135
8.3.1 Introduction ................................................................................................... 135 8.3.2 Interveners in the Bow River crossing portion ............................................. 136
8.3.3 Views of AltaLink......................................................................................... 136 8.3.4 Views of interveners ..................................................................................... 137
8.3.5 Commission findings .................................................................................... 138
9 AltaLink Application No. 1608643 Foothills 138-kV transmission development ....... 139 9.1 The preferred and alternate routes.............................................................................. 139 9.2 Views of AltaLink ...................................................................................................... 142 9.3 Views of the interveners............................................................................................. 144
9.4 Commission findings ................................................................................................. 147
10 AltaLink Applications No. 1608861 and No. 1608862 - South Foothills and Windy Flats
138-kV transmission developments ......................................................................................... 149 10.1 Introduction ................................................................................................................ 149
10.1.1 The preferred and alternate substation sites ................................................ 149 10.1.2 The preferred and alternate transmission line routes .................................. 149
10.1.3 Other project components ........................................................................... 151 10.2 Preferred versus alternate route .................................................................................. 154
10.2.1 Views of AltaLink ....................................................................................... 154
10.2.2 Views of interveners.................................................................................... 158 10.3 Hybrid A versus Hybrid B ......................................................................................... 162
10.3.1 Views of AltaLink ....................................................................................... 162 10.3.2 Views of the interveners .............................................................................. 164
10.4 Preferred versus Hybrid B .......................................................................................... 164 10.4.1 Views of AltaLink ....................................................................................... 164
10.5 Commission findings ................................................................................................. 166 10.5.1 Preferred versus alternate route ................................................................... 166 10.5.2 Hybrid A route versus Hybrid B route ........................................................ 167 10.5.3 Preferred route versus Hybrid B route ........................................................ 167 10.5.4 Preferred route versus CERC route ............................................................. 168
10.5.5 Windy Flats 138S substation ....................................................................... 170
11 ENMAX Application No. 1608649 ................................................................................... 171 11.1 Discussion .................................................................................................................. 171
11.2 Commission findings ................................................................................................. 171
iv • AUC Decision 2013-369 (October 7, 2013)
12 Decision .............................................................................................................................. 172
Appendix A: Proceeding participants who have registered a statement of intent to
participate ........................................................................................................ 175
Appendix B: Oral hearing ........................................................................................................ 180
Appendix C: Abbreviations ..................................................................................................... 183
Appendix D: Process meeting Decision 2012-360 .................................................................. 186
List of tables
Table 1. AltaLink open houses for the north Foothills project ........................................... 81
Table 2. Proximity to residence comparison between the preferred route and the
alternate route ......................................................................................................... 103
Table 3. Siting comparison between the preferred site and alternate site ....................... 114
Table 4. Comparison between the preferred route and north alternate route ................ 125
Table 5. Comparison between the preferred route and Frank Lake alternate route ..... 128
Table 6. Comparison of the preferred and alternate routes .............................................. 142
Table 7. Project assessment metrics for the preferred and alternate routes ................... 154
Table 8. Incremental residential impacts ............................................................................ 155
Table 9. Project assessment metrics for the hybrid routes ................................................ 163
Table 10. Project assessment metrics for the south portion of the preferred and alternate
routes ........................................................................................................................ 165
AUC Decision 2013-369 (October 7, 2013) • v
List of figures
Figure 1 – Overall project map ....................................................................................................... 2 Figure 2 – Transmission system in 2014 following completion of the East Calgary NID, plus
proposed transmission developments ......................................................................... 22
Figure 3 – AESO 138-kV alternatives in the High River area ..................................................... 25 Figure 4 – Windy Flats configuration ........................................................................................... 26 Figure 5 – Grid Power Fidler to Langdon proposal ...................................................................... 35 Figure 6 – Grid Power proposal – Langdon termination .............................................................. 36 Figure 7 – Grid Power proposal – Fidler termination ................................................................... 37
Figure 8 – Grid Power 911L at 138-kV ........................................................................................ 39 Figure 9 – North Foothills project Study Area (with Preliminary Routes) ................................... 59
Figure 10 – South Foothills project study area (with preliminary routes) .................................... 61 Figure 11 – Langdon to Janet study area (with preliminary routes) ............................................. 63 Figure 12 – 138-kV study area in the High River – Okotoks area ............................................... 65 Figure 13 – Preliminary routes for the 434L/646L line ................................................................ 67
Figure 14 – Component B – proposed routing for the 646L Line ................................................ 68 Figure 15 – Substation target areas ............................................................................................... 70 Figure 16 – North Foothills project preferred and alternate routes .............................................. 75
Figure 17 – South Foothills project preferred and alternate routes .............................................. 76 Figure 18 – Langdon to Janet preferred and alternate routes ........................................................ 77
Figure 19 – Foothills 138-kV project preferred and alternate routes............................................ 78 Figure 20 – AltaLink’s staged environmental approach ............................................................... 88 Figure 21 – Langdon to Janet project area map .......................................................................... 101
Figure 22 – Preferred route/route variant for entering the Langdon and Crossings substations 102
Figure 23 – Frank Lake environmentally significant area and important bird area .................... 117 Figure 24 – North Foothills route options................................................................................... 121 Figure 25 – Alternate Foothills substation .................................................................................. 123
Figure 26 – Cross-section drawings of structure options at Bow River crossing ....................... 135 Figure 27 – Foothills 138-kV route options ................................................................................ 139
Figure 28 – Alternate route segment near Foothills substation .................................................. 140 Figure 29 – Foothills 237S substation preferred and alternate locations .................................... 141 Figure 30 – Phyllis Robertson’s property location ..................................................................... 146 Figure 31 – South Foothills project preferred and alternate routes ............................................ 150
Figure 32 – Terminate 603L into Windy Flats 138S substation ................................................. 152 Figure 33 – Terminate 608L into Windy Flats 138S substation ................................................. 153
AUC Decision 2013-369 (October 7, 2013) • 1
The Alberta Utilities Commission
Calgary, Alberta
Decision 2013-369
Alberta Electric System Operator, Applications No. 1608620, No. 1608642,
AltaLink Management Ltd. and No. 1608637, No. 16808643, No. 1608649,
ENMAX Power Corporation No. 1608846, No. 1608861 and No. 1608862
Foothills Area Transmission Development Proceeding ID No. 2001
1 Introduction and background
1. The Alberta Electric System Operator (AESO) filed an application with the
Alberta Utilities Commission (AUC or the Commission) on July 5, 2012, for approval of a needs
identification document (NID) to expand the transmission system in the vicinities of southeast
Calgary, Okotoks and High River. This NID application was registered as Application
No. 1608620 and is referred to in this decision as the Foothills Area Transmission Development
(FATD) need application, or the FATD NID.
2. AltaLink Management Ltd. (AltaLink) filed three facility applications on July 12, 2012,
requesting approval to construct and operate various transmission facilities to meet part of the
need described in the AESO’s FATD need application. The applications were registered as
Applications No. 1608642, No. 1608643 and No. 1608637. ENMAX Power Corporation
(ENMAX) also filed one facility application on July 13, 2012, requesting approval to alter and
operate some of its existing substations to meet the remainder of the need described in the
AESO’s FATD need application. The application was registered as Application No. 1608649.
3. The AESO filed a second application with the AUC on September 21, 2012, for approval
to amend the Southern Alberta Transmission Reinforcement (SATR) NID approval, which
involves the re-termination of a proposed line to a new Windy Flats 138S substation from the
existing Peigan 59S substation in the area southwest of Fort Macleod. This application was
registered as Application No. 1608846 and is referred to in this decision as the SATR NID
amendment.
4. AltaLink subsequently filed two facility applications on September 25, 2012, requesting
approval to construct and operate various transmission facilities to meet the need described in the
AESO’s SATR NID amendment. These applications were registered as Applications
No. 1608861 and No. 1608862.
5. These eight applications were considered jointly by the Commission and designated as
the Foothills Area Transmission Development Proceeding ID No. 2001. The total estimated
project cost for the above applications is approximately $827 million within +20/-10% accuracy.
The following map provides an overview of the facilities proposed in this proceeding.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
2 • AUC Decision 2013-369 (October 7, 2013)
CLARESHOLM
NANTON
VULCAN
GRANUM
STAVELY
FORT
MACLEOD
LITTLE BOW
RIVERCLEAR
LAKEWILLOW
CREEK
T.16
R.24W.4MR.26
22X22X
R.27W.4M.R.28
T.19
T.20
T.21
T.22
R.29
HIGH RIVER
BLACKIE
OKOTOKS
CALGARY
791
797
2
2
552
2
2
783
7
2A
23
23
799
BOW
547
RIVER
FRANK
LAKE
THIRD
LAKE
1201L
552
2A
1201L
HIGHWOOD RIVER
SHEEP
RIVER
CANAL T.23
560 LANGDON
SHEPARD
2
2
3
3
2
533
534
529
520
R.25
23
T.18
T.17
T.15
T.14
T.13
T.12
T.11
T.10
T.9
T.8
Figure 1 – Overall project map
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 3
6. The facilities proposed by AltaLink include approximately 200 kilometres of contiguous
transmission lines connecting southeast Calgary to the High River area and to the Fort Macleod
area, and approximately 18 kilometres of transmission line connecting southeast Calgary
eastward to the Langdon area.
7. The Commission issued notice of the applications and of a process meeting for the five
Foothills Area Transmission Development applications on August 28, 2012. The notice provided
the date of and location for the process meeting and a preliminary schedule of the process steps
for the Foothills Area Transmission Development applications. It was published in the
Calgary Herald, Calgary Sun and Okotoks Western Wheel newspapers on September 5, 2012, in
the Chestermere Anchor newspaper on September 6, 2012, and in the High River Times
newspaper on September 7, 2012. It was also mailed directly to all landowners, residents and
other interested parties residing within 800 metres of the edge of the transmission line
right-of-way and substation site boundary for the preferred and alternate routes and sites and all
route options, and delivered to all residences and addresses in the project area by way of a
general postal code drop.
8. The process meeting, scheduled for October 17, 2012, was cancelled because three
additional applications were filed by the AESO and AltaLink between September 21, and
September 25, 2012, which related to the first five Foothills Area Transmission Development
applications by virtue of the proposed Foothills 237S substation. The meeting was cancelled to
give potentially directly and adversely affected parties time to participate in the proceeding.
9. The Commission issued a revised notice of applications and process meeting for the eight
Foothills Area Transmission Development applications on October 19, 2012.1 The notice
provided the revised date and location of the process meeting, and an updated preliminary
schedule of the process steps for the Foothills Area Transmission Development applications.
10. A process meeting was held on November 26, 2012, at the Heritage Inn Hotel &
Convention Centre in High River before Commission member Anne Michaud. The goal of the
process meeting was to establish a schedule and process to fairly and effectively consider the
Foothills Area Transmission Development applications.
11. The Commission issued Decision 2012-3602 with respect to the process meeting on
December 24, 2012. In that decision, the Commission listed the issues it considered to be
relevant to the proceeding, ruled on standing, and set a schedule and process for the
Foothills Area Transmission Development applications.
1 The revised notice was published in the High River Times and Rockyview Weekly newspapers on
October 30, 2012, in the Calgary Herald, Calgary Sun, Okotoks Western Wheel, Nanton News, Vulcan
Advocate, Pincher Creek Echo, Claresholm Local Press and Fort Macleod Gazette newspapers on
October 31, 2012, and in the Chestermere Anchor newspaper on November 2, 2012. It was also mailed directly
to all landowners, residents and other interested parties residing within 800 metres of the edge of the
transmission line right-of-way and substation site boundary for the preferred and alternate routes and sites and
all route options, and delivered to all residences and addresses in the project area by way of a general postal
code drop. 2 Decision 2012-360: Alberta Electric System Operator, AltaLink Management Ltd., ENMAX Power
Corporation, Foothills Area Transmission Development – Process Meeting Decision, Applications
No. 1608620, No. 1608642, No. 1608637, No. 1608643, No. 1608649, No. 1608846, No. 1608861 and
No. 1608862, Proceeding ID No. 2001, December 24, 2012.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
4 • AUC Decision 2013-369 (October 7, 2013)
12. AltaLink filed amendments to its facility applications on December 21, 2012. The
Commission issued a notice of amendments to the facility applications for the Foothills Area
Transmission Development applications on January 4, 2013.3
13. AltaLink filed a second amendment to one of its facility applications on March 8, 2013.
14. The Commission issued a notice of hearing for the Foothills Area Transmission
Development applications on March 15, 2013, which noted the March 8, 2013 amendments.4
15. The Commission deemed the applications complete on April 10, 2013.
16. The Commission also held three information sessions, between September 24, 2012, and
November 13, 2012, in High River, Indus and Claresholm. Notification of the information
sessions was provided in the notice of applications and the revised notice of applications.
17. The hearing commenced on Tuesday, May 14, 2013, at the Heritage Inn Hotel &
Convention Centre in High River before Commission member and panel chair Anne Michaud,
Commission member Neil Jamieson and acting Commission member Patrick Brennan. The
hearing concluded on May 30, 2013, at the AUC’s hearing room in Calgary.
18. The Commission deemed the record for this proceeding closed on July 12, 2013.
1.1 The Foothills Area Transmission Development applications
1.1.1 Two AESO need applications
1.1.1.1 FATD need Application No. 1608620
19. The AESO stated that the need for transmission reinforcement in the vicinities of
southeast Calgary, Okotoks and High River is driven predominantly by the future load growth,
insufficient transmission capacity to allow wind generation flow from southern Alberta to the
load centres, and increasing interest in gas-fired generation in the south Calgary and High River
areas. The AESO added that the transmission system constraints could occur as early as 2014.
20. The FATD need application proposed the following major 240-kilovolt (kV)
components:
a 240/138-kV Foothills 237S substation located in the vicinity of High River, including
two 240/138-kV 400-megavolt-ampere (MVA) transformers
3 The notice of amendments was published in the Calgary Herald, Calgary Sun and Okotoks Western Wheel
newspapers on January 9, 2013, and in the High River Times and Chestermere Anchor newspapers on
January 11, 2013; it was mailed directly to all landowners, residents and other interested parties residing within
800 metres of the edge of the transmission line right-of-way and substation site boundary who may be directly
and adversely affected by the amendments. In addition, the notice was delivered to all residences and addresses
in the project area by way of a general postal code drop. 4 The notice of hearing was published in the High River Times and Rockyview Weekly newspapers on
March 26, 2013, in the Calgary Herald, Calgary Sun, Okotoks Western Wheel, Nanton News, Vulcan Advocate,
Pincher Creek Echo, Claresholm Local Press and Fort Macleod Gazette newspapers on March 27, 2013, and in
the Chestermere Anchor on March 28, 2013; it was mailed directly to all landowners, residents and other
interested parties residing within 800 metres of the edge of the transmission line right-of-way and substation site
boundary for the preferred and alternate routes and sites and all route and site options, and was also delivered to
all residences and addresses in the project area by way of a general postal code drop.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 5
a double-circuit 240-kV transmission line between Janet 74S and Langdon 102S
substations, with an approximate summer rating of 800 MVA per circuit
a double-circuit 240-kV transmission line between ENMAX No. 65 and Foothills 237S
substations, with an approximate summer rating of 600 MVA per circuit
a 240-kV transmission line 1109L between ENMAX No. 25 and No. 65 substations by
reusing portions of transmission line 850L, with an approximate summer rating of 490 MVA.
a double-circuit 240-kV transmission line between East Calgary 5S and Langdon 102S
substations by connecting transmission lines 936L and 937L to transmission lines 1077L
and 917L, with an approximate summer rating of 490 MVA per circuit
termination of the 985L line at Janet 74S substation
21. The FATD need application proposed the following major 138-kV components:
a 138-kV transmission line between Foothills 237S and High River 65S substations, with
an approximate summer rating of 260 MVA
a 138-kV transmission line between Foothills 237S and Okotoks 678S substations, with
an approximate summer rating of 260 MVA
reconfiguration of the 850L line between Okotoks 678S and Carseland 525S substations
by using portions of some existing transmission lines and new line segments
discontinued operation of some portions of existing transmission lines which would not
be reused
1.1.1.2 Amendment to the SATR NID Application No. 1608846
22. The SATR NID Approval No. U2011-115,5 issued by the Commission on June 7, 2011,
includes a new double-circuit 240-kV transmission line from Peigan 59S substation to a future
Foothills substation to be located in south Calgary and a static var compensation addition at the
Peigan 59S substation. The AESO’s amendment to this approval sought to re-terminate the new
double-circuit transmission line to a new Windy Flats 138S substation from the existing Peigan 59S
substation and other associated transmission facilities. The AESO stated that the amendment is
driven by a risk to the in-service date for the original approval which arises from work on federal
lands and project cost reduction associated with the Windy Flats option, identified by AltaLink.
23. The amendment proposed to replace the developments associated with Peigan 59S
substation in the approval with the following Windy Flats configurations:
a Windy Flats 138S substation east of Peigan 59S substation, including one 240/138-kV
400 MVA transformer and two shunt reactors
a double-circuit 240-kV transmission line with a maximum 50 per cent series
compensation from Windy Flats 138S substation to Foothills 237S substation
a double-circuit 240-kV transmission line connecting Windy Flats 138S substation to the
967L/968L line via an in and out scheme
5 Approval U2011-115, Alberta Electric System Operator, Southern Alberta Transmission Reinforcement,
Application Nos. 1606564 and 16056526, proceeding ID No. 748, June 7, 2011.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
6 • AUC Decision 2013-369 (October 7, 2013)
a new single-circuit 138-kV transmission line connecting Windy Flats 138S substation
with the 603L line
a new single-circuit 138-kV transmission line connecting Windy Flats 138S substation
with the 608L line
1.1.2 Four facility applications associated with the FATD NID
1.1.2.1 AltaLink Application No. 1608642 – Langdon to Janet
24. The Langdon to Janet project application is comprised of five major components:
construction of approximately 18 kilometres of double-circuit 240-kV transmission line
1064L/1065L from Langdon 102S substation to Janet 74S substation
modification of transmission line 1080L/850L between the ENMAX No. 25 substation
and Janet 74S substation
re-termination of transmission line 936L/937L between the Crossings 511S substation,
and East Calgary 5S substation
expansion of the Janet 74S substation site to install new 240-kV circuit breakers, and
rearrange terminations for several 240-kV transmission lines
expansion of the Crossings 511S substation to add four new 240-kV circuit breakers
25. AltaLink amended this application on March 8, 2013, to relocate four turning structures
of the1064/1065L line, located in the southeast quarter of Section 18, Township 23, Range 28,
west of the Fourth Meridian.
1.1.2.2 AltaLink Application No. 1608637 – north Foothills transmission development
26. The north Foothills transmission development application is comprised of four major
components:
construction of new 240-kV Foothills 237S substation, located in the northwest quarter of
Section 35, Township 18, Range 28, west of the Fourth Meridian
construction of approximately 51 kilometres of double-circuit 240-kV 1106L/1107L line
from Foothills 237S substation to ENMAX No. 65 substation
relocation of the 911L/850L line south of ENMAX No. 65 substation
relocation of a segment of the 850L line onto triple-circuit structures of the 106L/1107L
line
27. AltaLink amended this application on December 21, 2012, to include an alternate
Foothills 237S substation site located in the northwest quarter of Section 8, Township 19,
Range 27, west of the Fourth Meridian. Consequently, the associated 1106L/1107L line route
would be shifted from the preferred Foothills substation site to the alternate Foothills substation
site.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 7
1.1.2.3 AltaLink Application No. 1608643 – Foothills 138-kV transmission development
28. The Foothills 138-kV transmission development application is comprised of five major
components:
addition of a new 138-kV switchyard with two new 240/138-kV transformers in the
Foothills 237S substation
construction of a new 138-kV 646L line from the Foothills 237S substation to
Okotoks 678S substation
construction of a new 138-kV 434L line from Foothills 237S substation
to High River 65S substation; the 434L line would be constructed on double-circuit
towers with the 646L line
alterations to High River 65S substation, the Okotoks 678S substation, the 727L line, the
911L line and the 850L line to facilitate the construction of the 646L line
salvage of the portion of the 727L line between Janet 74S substation and Okotoks 678S
substation
29. AltaLink amended this application on December 21, 2012, to include an additional
138-kV route associated with the alternate Foothills 237S substation site.
30. AltaLink amended this application again on March 8, 2013, to add an additional structure
near the confluence of the 727L and 727AL lines in the southeast quarter of Section 2,
Township 20, Range 29, west of the Fourth Meridian.
1.1.2.4 ENMAX Application No. 1608649
31. The ENMAX application is comprised of four major components:
addition of two 240-kV circuit breakers at ENMAX No. 65 substation
termination of the 1106L line, 1107L line and 1109L line at ENMAX No. 65 substation
termination of the 1109L line and 985L line at ENMAX No. 25 substation
disconnection of the 911L line at ENMAX No. 65 substation
1.1.3 Two facility applications associated with the SATR NID amendment
1.1.3.1 AltaLink Application No. 1608861 – south Foothills transmission development
32. The south Foothills transmission development application is comprised of seven major
components:
construction of a new 240-kV Windy Flats 138S substation located southwest of
Fort McLeod including circuit breakers, reactors and associated equipment
modifications to the existing double-circuit 240-kV 967L/968L line to terminate the
967L/968L line at Windy Flats 138S substation
installation of two additional 240-kV circuit breakers at the Foothills 237S substation
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
8 • AUC Decision 2013-369 (October 7, 2013)
construction of approximately 120 kilometres of double-circuit 240-kV 1037L/1038L
line from the Windy Flats 138S substation to the Foothills 237S substation
construction of a new series capacitor station SC1 266S to provide series compensation
for the proposed double-circuit 240-kV 1037L/1038L line
modification to the portion of 138-kV transmission line 197L just outside of
Stavely 349S substation to provide safe clearance to accommodate the cross-over of the
proposed double-circuit 1037L/1038L line to the preferred site location of capacitor
station SC1 266S
relocation of four sections of the 240-kV 911L line slightly away from the right-of-way
so that the double-circuit 240-kV 1037L/1038L line could be constructed on those
sections of the existing alignment of the 911L line
33. AltaLink amended this application on December 21, 2012, to include additional routes
for the new 1037L/1038L line, due to the inclusion of an alternate Foothills 237S substation site.
These additional routes shift the start point from the preferred Foothills substation site to the
alternate Foothills substation site.
1.1.3.2 AltaLink Application No. 1608862 – Windy Flats 138S substation and line
reconfiguration
34. The Windy Flats 138S substation and line reconfiguration application is comprised of
four major components:
construction of new 138-kV substation equipment at the Windy Flats 138S substation to
include one 138/240-kV 400-MVA transformer, circuit breakers and associated
equipment
connection of the existing 138-kV 603L line to the Windy Flats 138S substation by using
a portion of the existing 603AL line in series with a new 138-kV transmission line
connection of the existing 138-kV 608L line to the Windy Flats 138S substation by using
a portion of existing transmission line 608L in series with a new 138-kV transmission
line
installation of airbreaks on the 608L and 608AL lines for isolation and reliability
purposes
1.2 Process for new transmission and legislative framework
35. Two approvals from the Commission are required to build new transmission in Alberta,
other than critical transmission infrastructure. The first is an approval of the need for expansion
or enhancement to the system pursuant to Section 34 of the Electric Utilities Act. The second is a
permit to construct and a licence to operate a transmission line pursuant to sections 14 and 15 of
the Hydro and Electric Energy Act.
36. Under the Electric Utilities Act, the Alberta Electric System Operator (AESO), in its
capacity as the Independent System Operator (ISO), is responsible for preparing a document
called a needs identification document. The needs identification document describes the need for
new transmission and proposes a transmission solution to meet that need (this is also referred to
as a need application). The AESO files the need application with the Commission for approval,
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 9
pursuant to Section 34 of the Electric Utilities Act. When making a decision on a contested need
application, in accordance with subsection 34(3) of the Electric Utilities Act, the Commission
may approve the needs identification document, refer the needs identification document back to
the AESO with directions or suggestions for changes or additions, or refuse to approve the needs
identification document.
37. Facility applications are prepared by a transmission facility owner assigned by the AESO.
When considering an application for a transmission facility, the Commission must consider
whether the proposed transmission line is in the public interest having regard to the social and
economic effects of the transmission line and the effect of the transmission line on the
environment, pursuant to Section 17 of the Alberta Utilities Commission Act.
1.2.1 Need applications
38. Section 33 of the Electric Utilities Act states in part:
33(1) The Independent System Operator must forecast the needs of Alberta and develop
plans for the transmission system to provide efficient, reliable and non-discriminatory
system access service and the timely implementation of required transmission system
expansions and enhancements.
39. Section 34 of the Electric Utilities Act states in part:
34(1) When the Independent System Operator determines that an expansion or
enhancement of the capability of the transmission system is or may be required to meet
the needs of Alberta and is in the public interest, the Independent System Operator must
prepare and submit to the Commission for approval a needs identification document that
(a) describes the constraint or condition affecting the operation or performance of
the transmission system and indicates the means by which or the manner in
which the constraint or condition could be alleviated,
(b) describes a need for improved efficiency of the transmission system, including
means to reduce losses on the interconnected electric system, or
(c) describes a need to respond to requests for system access service.
(2) On its own initiative or in response to views expressed by the Commission, the
Independent System Operator may amend a needs identification document submitted to
the Commission for approval.
40. Section 11 of the Transmission Regulation, which describes the information that the
AESO must include in a need application, specifies that it must include an assessment of current
transmission capacity; load and generation forecasts; studies and analysis that identify the timing
and nature of the need for new transmission; and a technical and economic comparison of the
technical solutions considered by the AESO to address the need identified. Section 11 also
requires a need application to state which technical solution the AESO preferred.
41. Section 38 of the Transmission Regulation describes what principles and matters the
Commission must have regard for when deciding upon a need application. Subsection 38(e)
requires the Commission to consider the AESO's assessment of the need to be correct unless an
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
10 • AUC Decision 2013-369 (October 7, 2013)
interested person satisfies the Commission that the assessment is technically deficient, or that
approval of the need application would not be in the public interest. Subsection 38(e) states:
38 When considering whether to approve a needs identification document under
section 34(3) of the Act the Commission must:
…
(e) consider the ISO’s assessment of the need to be correct unless an interested
person satisfies the Commission that
(i) the ISO’s assessment of the need is technically deficient, or
(ii) to approve the needs identification document would not be in the public
interest.
42. The first need application considered by the Commission's predecessor, the Alberta
Energy and Utilities Board (EUB or the Board), was for 240-kilovolt transmission upgrades
between Pincher Creek and Lethbridge. The Board described the needs assessment process as
follows:
It is the Board's view that section 34 contemplates a two-stage consideration of a NID. In
the first stage, the Board must determine whether an expansion or enhancement of the
capability of the transmission system is necessary to alleviate constraint, improve
efficiency, or respond to a request for system access.
If it is determined that expansion or enhancement of the system is required to address
constraint, inefficiency, system access requests, or any combination thereof, the Board
must then assess, in the second stage, whether enhancement or expansion measures
proposed by AESO are reasonable and in the public interest.6
43. The Commission has consistently followed this approach when deciding upon need
applications.7
1.2.2 Facility applications
44. Under Section 35 of the Electric Utilities Act, the AESO may direct, at the time of
preparing a needs identification document, after filing a needs identification document, or after
receiving an approval of a needs application, a transmission facility owner to submit a
transmission facility proposal to meet the need identified. In this case, the AESO directed
AltaLink and ENMAX, respectively, to prepare the above-mentioned facility applications. The
applications were filed under sections 14 and 15 of the Hydro and Electric Energy Act, which
state:
14(1) No person shall construct a transmission line or any part of a transmission line
unless the person is the holder of a permit issued by the Commission.
6 EUB Decision 2004-087, Southwest Alberta 240-kV Transmission System Development Addendum to
Decision 2004-075, Application No. 1340849, October 14, 2004, pages 13-14. 7 EUB Decision 2005-049: Alberta Electric System Operator Needs Identification Document Application
Southwest Alberta 240-kV Transmission System Development Pincher Creek – Lethbridge Area, page 5; AUC
Decision 2009-126: Alberta Electric System Operator, Needs Identification Document Application Southern
Alberta Transmission System Reinforcement, Application No. 1600862, Proceeding ID No. 171, September 8,
2009, page 1; Decision 2010-188: Alberta Electric System Operator, Needs Identification Document
Application Hanna Region Transmission System Development, Application No. 1605359, Proceeding ID
No. 278, April 29, 2010, page 3.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 11
(2) No person shall make a significant extension or alteration of a transmission line
unless the Commission has amended the person’s permit or issued a new permit to cover
the extension or alteration.
(3) Repealed 2007 cA-37.2 s82(14).
(4) This section does not preclude a person proposing to apply for a permit or the
person’s agents from
(a) entering on any Crown or other land lying in the intended route of the
transmission line to make surveys or examinations, or
(b) negotiating for the acquisition of interests in land that may be required for the
transmission line.
15 No person shall operate a transmission line unless the person is the holder of a
subsisting licence to operate the transmission line, issued by the Commission.
45. Section 15.1 of the Hydro and Electric Energy Act states that the Commission, in
considering a facility application, shall take into account a certification by the AESO. It states:
15.1 When the Commission is considering an application for an approval, permit or
licence under this Part in respect of a transmission line or part of a transmission line that
has the potential to meet a need identified in a needs identification document that has
been approved by the Commission under section 34(1) of the Electric Utilities Act, the
Commission shall take into account a certification by the Independent System Operator
that the technical aspects of the application meet the requirements set out in the needs
identification document.
46. The Commission may combine a need application and a facility application which
pertains to the need application pursuant to Section 15.4 of the Hydro and Electric Energy Act.
47. In making its decision on a facility application, the Commission must consider whether
the project is in the public interest. Section 17 of the Alberta Utilities Commission Act reads in
part:
17(1) Where the Commission conducts a hearing or other proceeding on an application to
construct or operate a …transmission line under the Hydro and Electric Energy Act… it
shall, in addition to any other matters it may or must consider in conducting the hearing
or other proceeding, give consideration to whether construction or operation of the
proposed… transmission line is in the public interest, having regard to the social and
economic effects of the …line …and the effects of the…… line …on the environment.
48. Regarding the interpretation of “public interest”, the Commission is mindful of
Decision 2009-028,8 which states:
…The Commission recognizes that there is no universal definition of what comprises the
“public interest” and that its meaning cannot be derived from strictly objective measures.
The Commission acknowledges that the ultimate determination of whether a particular
project is in the “public interest” will largely be dictated by the circumstances of each
transmission facility application.
8 Decision 2009-028: AltaLink Management Ltd. – Transmission Line from Pincher Creek to Lethbridge,
Application No. 1521942, Proceeding ID No. 19, March 10, 2009.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
12 • AUC Decision 2013-369 (October 7, 2013)
In the Commission's view, assessment of the public interest requires it to balance the
benefits associated with upgrades to the transmission system with the associated impacts,
having regard to the legislative framework for transmission development in Alberta. This
exercise necessarily requires the Commission to weigh impacts that will be experienced
on a provincial basis, such as improved system performance, reliability, and access with
specific routing impacts upon those individuals or families that reside or own land along
a proposed transmission route as well as other users of the land that may be affected. This
approach is consistent with the EUB's historical position that the public interest standard
will generally be met by an activity that benefits the segment of the public to which the
legislation is aimed, while at the same time minimizing, or mitigating to an acceptable
degree, the potential adverse impacts on more discrete parts of the community.
When assessing whether AltaLink's proposed route is in the public interest, the
Commission must weigh the benefits with the site specific impacts that will be
experienced by landowners and residents along the proposed route as well as others that
may be impacted. The Commission understands that these impacts are real and may be
significant. Transmission towers are large structures that may obscure scenery, impact
agricultural operations, and may have an influence on land use and development plans.
The Commission expects transmission facility owners to take all reasonable steps to
avoid such impacts but acknowledges that despite the use of sound routing and planning
practices such impacts are sometimes truly unavoidable given the nature of transmission
lines. Where such impacts are truly unavoidable, the Commission expects that the
Applicant would explore all reasonable steps to mitigate those impacts.9
49. The Commission has consistently applied this interpretation of "public interest".
50. The Commission may approve, approve with conditions, or deny a facility application.
Section 19 of the Hydro and Electric Energy Act states:
19(1) On an application for an approval, permit or licence under this Part, or for an
amendment of an approval, permit or licence, the Commission may grant the approval,
permit, licence or amendment subject to any terms and conditions that it prescribes or
may deny the application.
(1.1) Notwithstanding subsection (1), the Commission shall not refuse an approval of a
transmission line or part of a transmission line designated as critical transmission
infrastructure as defined in the Electric Utilities Act on the basis that, in its opinion, it
does not meet the needs of Alberta.
(2) Without restricting the generality of subsection (1), the Commission may do one or
more of the following:
(a) require changes in the plans and specifications of a hydro development, power
plant or transmission line;
(b) require changes in the location of a hydro development, power plant or
transmission line;
(c) prescribe a date before which the construction of, or operation of, the hydro
development, power plant or transmission line must commence;
9 Decision 2009-028, paragraphs 32, 33 and 35.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 13
(d) prescribe the location and route of the transmission line as precisely as it
considers suitable;
(e) prescribe the location of the right of way of the transmission line and the
relationship of its boundaries to the transmission line or any part of the
transmission line.
1.2.3 Other requirements
51. Applications must meet the informational and other requirements set out in AUC
Rule 007: Applications for Power Plants, Substations, Transmission Lines and Industrial System
Designations (AUC Rule 007). Applicants must provide technical and functional specifications,
environmental information including noise assessments, information on public consultation,
route selection criteria and the cost of a proposed project.
52. In addition, applicants must seek the requisite approvals under other applicable provincial
or federal legislation.
2 The AESO’s need applications
53. This section discusses the AESO’s two need applications, including the views of the
applicants and interested parties, and the Commission findings on the evidence related to the two
applications. The parties who objected to or had concerns with the need applications and
provided evidence are listed below:
the Diagonal group
Phyllis Robertson
Industrial Power Customers Association of Alberta
Benign Energy Canada II Inc.
TransAlta Corporation
ENMAX Green Power Inc.
ENMAX Shepard Inc.
TransCanada Energy Ltd.
Ronald and Laurie Conner
Powerex Corp.
54. Grid Power Development and Design Inc. (Grid Power) was hired by both the
Diagonal group and Phyllis Robertson to perform technical assessments of the AESO’s need
applications. Grid Power prepared a technical report on behalf of the Diagonal group to evaluate
some of the 240-kV components within the need applications and recommended a Fidler to
Langdon proposal. Further, Grid Power prepared a technical report on behalf of Mrs. Robertson
to evaluate the 138-kV components in the High River area proposed in the FATD NID and
recommended a 911L at 138-kV proposal.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
14 • AUC Decision 2013-369 (October 7, 2013)
2.1 Assessment of the need to expand the transmission system in southern Alberta
2.1.1 Views of the AESO
2.1.1.1 Application No. 1608620 – FATD NID
55. The AESO stated that the need for transmission reinforcement in the vicinities of
southeast Calgary, Okotoks and High River is driven by the forecasted load growth in the area,
integration of local gas-fired generation to the system and accommodation of the transfer of wind
generation from southern Alberta. The AESO forecasted that the load in the Calgary,
Strathmore/Blackie and High River planning areas will increase by approximately
450 megawatts (MW), or 25 per cent, by 2021; while the installed wind generation in Alberta is
forecasted to increase by approximately 1,600 MW, to a total of approximately 2,500 MW by
2019. The AESO further stated that the local gas-fired generation plants, with a combined
capacity exceeding 1,300 MW, had applied for system access service in or adjacent to the south
Calgary area for an in-service date as early as 2014.
56. The AESO’s system studies focused on the transmission system in south Calgary and the
High River planning area, which it collectively referred to as the study area, or south Calgary
area. The High River planning area includes the towns of Black Diamond, Turner Valley,
High River, Okotoks and the areas between these towns.
57. The AESO first identified transmission system reliability constraints in the south Calgary
area in its 2009 Long-term Transmission Plan. These reliability constraints include both thermal
overloads and voltage violations. The AESO confirmed these system constraints in its 2011
Long-term Transmission Plan.
58. The AESO reported that it conducted detailed system performance analyses and
developed a transmission system expansion plan, referred to as the 2011 Foothills Area
Transmission Development plan, in its 2011 engineering report. The 2011 FATD engineering
report assessed the existing transmission system in the study area based on the AESO’s 2009
Corporate Load Forecast (referred to as FC2009) and two generation scenarios (scenario A1 -
high northern generation development and scenario B5 - high southern generation development)
from its 2009 Long-term Transmission Plan. The 2011 FATD engineering report concluded that
the study area will experience several thermal overloads under normal and single-contingency
operating conditions in 2014, due to steady load growth, insufficient transmission capacity to
allow power flow from southern Alberta to the load centres, and insufficient transmission
capacity to integrate new local generation. It also concluded that there is a risk of voltage
collapse in the High River planning area following a single-contingency event during the
summer peak load condition due to the forecasted load growth in the area, and an inadequate
transmission supply connecting this area to the grid. The AESO noted that both thermal
overloads and voltage violations increase significantly by 2019.
59. The AESO updated its generation forecast in its 2011 Long-term Transmission Plan.
Subsequently, the AESO conducted sensitivity studies applying the updated generation forecast
in its 2011 FATD engineering report. The study results indicated to the AESO that the proposed
FATD plan is required in the second quarter of 2014.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 15
60. The AESO performed one set of sensitivity studies in 2012 to determine whether the
69-kV transmission upgrades in south Calgary would affect the conclusions and
recommendations in the 2011 FATD engineering report. Originally, the AESO applied to
upgrade the 69-kV transmission system in south Calgary in its need Application No.1604960
(Proceeding ID No. 234). These proposed 69-kV transmission system upgrades were modelled in
the 2011 FATD engineering report; however, the AESO amended the need application in
April 2012. The need application was subsequently approved in Decision 2012-194.10 The
sensitivity studies performed by the AESO for Proceeding ID No. 234 replaced the originally-
proposed 69-kV transmission upgrades in south Calgary with the existing transmission system in
south Calgary. The AESO compared the results of the sensitivity studies with the results of the
2011 FATD engineering report and found that the conclusions of the assessment of the need in
the 2011 FATD engineering report would not be materially impacted if the 69-kV transmission
upgrades in south Calgary are not built.
61. Based on the AESO’s 2012 long-term outlook load and generation forecast, referred to as
the 2012LTO, the AESO performed a second set of sensitivity studies in 2012 (2012LTO and
high-voltage direct-current (HVDC) dispatch supplementary report) to determine whether the
2012LTO and the 2012LTO combined with various dispatch assumptions of the Western Alberta
Transmission Line (WATL) and the Eastern Alberta Transmission Line (EATL), referred to as
2012LTO+HVDC, will affect the conclusions and recommendations made in the 2011
engineering report. The summer peak load in Calgary, Strathmore/Blackie and High River area
was forecasted by the AESO to be 2,123 MW in 2019 in the 2012LTO, in comparison with
2,338 MW in the FC2009. The installed wind generation in Alberta by 2019 was forecasted to be
2,544 MW for the environmental scenario in the 2012LTO, in comparison with 4,488 MW for
scenario B5 - high southern generation in the AESO’s 2009 Long-term Transmission Plan.
According to the AESO, the results of these sensitivity studies confirmed the need assessment in
the 2011 FATD engineering report. The AESO indicated that the 2012LTO+HVDC scenario
showed an increase in the trend for the identified overloads as compared to those of the
2012LTO scenario.
62. Based on the above studies, the AESO stated that prior to the proposed transmission
development in the FATD NID, the transmission system throughout the south Calgary area
would be subject to line overloading, voltage violations and curtailment of generation output.
The AESO noted that such reliability criteria violations are not permitted under Alberta
Reliability Standards and would compromise the ability of the transmission system to reliably
serve load in the area. It further noted that such violations would constrain generation production
even under normal operating conditions, which would limit the AESO’s ability to provide system
access service in a manner that gives market participants a reasonable opportunity to exchange
electricity and ancillary services.
63. The AESO stated that its participant involvement program for the FATD need application
was conducted between November 2010 and June 2012. The AESO directed the transmission
facility owners, ENMAX and AltaLink, to assist in the conduct of the participant involvement
program. ENMAX, AltaLink and the AESO utilized various methods to notify occupants,
residents and landowners of the need for the project and held open houses between February and
November 2011. The AESO also consulted with the representatives of municipalities to discuss
10
AUC Decision 2012-194, Alberta Electric System Opreator, AltaLink Management Ltd., ENMAX Power
Corporaion, South Calgary 69-kV Transmission System Upgrade, Proceeding ID No. August 8, 2012.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
16 • AUC Decision 2013-369 (October 7, 2013)
and address any concerns. It consulted with the Town of High River, the Town of Okotoks, the
City of Calgary, the Municipal District (M.D.) of Foothills and the M.D. of Rocky View County,
as well as government agencies, organizations, industry companies, First Nations and Métis
Nations.
64. The AESO also publicized its intention to file the FATD need application in newspapers
within the project area.
2.1.1.2 Amendment to the SATR NID
65. The AESO stated that the proposed amendment does not change the need for the
enhancement of the capability of the transmission system described in the SATR NID. Instead, it
seeks to amend the approved technical solution to address that need, that is, the south termination
of the 240-kV 1037L/1038L line (911L line rebuild) at the new Windy Flats 138S substation,
instead of the existing Peigan 59S substation. Therefore, the AESO explained that no need
assessment on the existing transmission system was performed.
66. The AESO stated that the approved SATR milestone11 for the 911L line rebuild has been
met since 2010, and confirmed that the milestone continues to be met by the latest wind
generation forecasts.12 The AESO stated that there would be constraints on the existing 911L line
under normal operating conditions and added that it has a statutory obligation to ensure the
timely implementation of transmission system developments to alleviate the constraints so
market participants will not be adversely affected by the absence of reliable transmission system
access.
67. In February 2013, the AESO published the 2012 Long-term Outlook Update
(2012LTOU). In the 2012LTOU, there is approximately 1,560 MW of total wind generation in
Alberta by 2017. The AESO explained that the revised wind generation forecast in the
2012LTOU was only the base case scenario and that the environmentally-driven scenario
remains valid.
68. The AESO stated that there are 14 wind projects currently in the AESO’s interconnection
queue, most of them with proposed in-service dates between 2014 and 2016,13 and that the reason
that some of the wind project developers are not proceeding is the lack of transmission capacity.
The AESO stated that it would be unreasonable to expect wind developers to complete their
investments and then sit and wait for transmission access, and that it’s inappropriate for the
AESO to require that these investments be made before filing a NID for transmission system
development. It submitted that it has a statutory obligation to anticipate the timing and location
of future generation additions, and to ensure that transmission is available to meet these future
needs.
69. The AESO conducted a participant involvement program in respect of its SATR NID
amendment from November 2010 to September 2012. It notified and consulted, as necessary,
with all occupants, residents and landowners within 800 metres of the proposed development, as
well as government agencies, industry companies, First Nations, and Métis Nations.
11
NID Approval No. U2010-264, Alberta Electric System Operator, Southern Alberta Transmission System
Reinforcement with Finalized Milestones, July 19, 2010. 12
Exhibit 889.01, AESO reply argument, paragraph 11. 13
Exhibit 755.01, AESO project list.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 17
2.1.2 Views of the Diagonal group
70. The Diagonal group stated that there is no urgency for the 911L line rebuild due to
changes in market conditions and the approval of major transmission facilities. The group added
that it respected the Commission’s direction in Decision 2012-360 that the application to amend
the SATR NID did not re-open the issue of the underlying need that the solution was designed to
address. The Diagonal group submitted that the report prepared by Grid Power, recommending
the move of the north and south termination points of the 911L line rebuild to Langdon and
Fidler substations respectively, did not question the underlying need for this line.14
2.1.3 Views of Phyllis Robertson
71. Despite having concerns with the proposed Foothills 138-kV development,
Phyllis Robertson acknowledged that the power system needs an upgrade.15 Grid Power was
retained by Mrs. Robertson. Grid Power acknowledged in its report that the AESO had justified
the need for additional load supply in the High River area on the basis of the AESO’s 2009 load
forecast and an assumed operating condition where all local generation is simultaneously
out-of-service. The report stated that system re-enforcements would be required in the five-plus
years time horizon for the High River regional system; although there is no immediate urgent
need, additional load supply capability would likely be required by 2017, and on this basis, it
recommended the acceptance of the AESO’s position that system improvements in the
High River area are required.
2.1.4 Views of Industrial Power Consumers Association of Alberta (IPCAA)
72. IPCAA questioned the need for the 911L line rebuild on the basis that the fundamental
conditions that justify the original SATR need have changed significantly since it was approved
in 2009.
73. IPCAA submitted that there is a 50 per cent reduction to the wind development forecast
in the AESO’s latest generation forecast. The original wind generation forecast in the SATR
ranged from 2,200 MW to 3,900 MW by 2017, which was driven by the anticipated economic
conditions of high natural gas prices and the ability to sell renewable energy credits to California.
However, IPCAA observed that the oversupply of natural gas in the North American market has
driven down the price leading to combined cycle plants having more economic merit than wind
generation. Further, IPCAA noted that California has altered its legislation on carbon dioxide
(CO2) offsets to encourage local green generation development, which contributed to a dramatic
drop in the wind development forecast. IPCAA noted that the AESO was now predicting only
1,352 MW of wind generation in southern Alberta by 2017, and 2,019 MW by 2022.16 Based on
the intended capacity of the planned stages of the SATR NID approval, IPCAA submitted that
Stage I is sufficient until 2017, and no decision should be made to initiate any construction of
Stage II until at least 2020.
74. IPCAA submitted that the SATR need was developed prior to the approval of the
two north to south high-voltage direct-current lines. With the addition of the two high-voltage
direct-current lines, it argued that the underlying bulk system configuration on which the original
14
Exhibit 896.01, Diagonal group reply argument, page 4, paragraph 15. 15
Exhibit 788.01, Revised opening statements from Phyllis Robertson, page 3, paragraph 15. 16
Exhibit 450.01, IPCAA Statement of intent to participate, page 2.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
18 • AUC Decision 2013-369 (October 7, 2013)
SATR need was based, has been radically altered. IPCAA anticipated that much of the southern
Alberta wind production could be transported through these high-voltage direct-current lines.
75. IPCAA argued that due to the dramatic changes of the wind generation forecast and bulk
system configuration, the in-service date for the 911L line rebuild is questionable. It contended
that it is a project built for generation congestion, not load supply reliability. IPCAA added that
the sense of urgency is artificial because there are methods of managing constraints that should
be considered, such as using dynamic thermal line ratings, proposed by the AESO in this
proceeding as the solution to address the issues raised by Powerex, or remedial action schemes,
as an interim measure to address congestion issues. IPCAA submitted that the Commission
should send back both need applications to the AESO and direct the AESO to re-examine its
in-service date.
76. IPCAA also submitted that the estimated cost for Stage I of the SATR has doubled since
the SATR NID was approved. Without the proper fixed cost contracts in place to ensure project
development accountability, there is no guarantee that the cost would not continue to rise as the
lines are built. It argued that the estimated $1.8 billion in capital cost to implement the SATR
need would represent significant savings for Alberta consumers, if the project is in fact no longer
needed.
2.1.5 Views of Benign Energy Canada II Inc. (Benign Energy)
77. Benign Energy supported the FATD project because the transmission system in southern
Alberta had been underbuilt for years. It explained that it is the holder of an AUC permit for the
construction and a licence to operate the Heritage wind farm, and submitted that the AESO
advised that only 100 MW of an approved total of 297 MW could be tied into the transmission
system. It noted that, along with other similar wind projects, the Heritage wind farm project
remained subject to significant transmission constraint in southern Alberta. It was also advised
by the AESO that the facility applications in the FATD project are required for its Heritage
project to transmit its electricity to the market.
78. Benign Energy submitted that construction of transmission lines and related substations
in the north and south Foothills applications are necessary to relieve a bottleneck of electricity
constraining generation in southern Alberta. In particular, it is anticipated that the Heritage
project will tie into the Fidler substation, which will eventually link to the Windy Flats 138S
substation for transmission to the proposed Foothills 237S substation and Janet 74S substation.
Benign Energy submitted that failure to approve the FATD applications would render it unable
to fully build the Heritage wind farm or would result in delays and modifications that will have
significant and adverse economic consequences.
2.1.6 Views of TransAlta Corporation (TransAlta)
79. TransAlta supported the AESO’s SATR NID amendment and associated facility
applications, and submitted that there are existing transmission constraints that are frequently
imposed on its wind generating facilities in the Pincher Creek area, even under normal operating
conditions. For example, it is currently experiencing constraints at its Ardenville, Blue Trail and
Soderglen wind generating facilities.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 19
80. TransAlta explained that early in 2013, the AESO had notified it of the proposed
connection of a new wind aggregated generating facility, adding that the connection of this
project may introduce additional constraints which may occur under normal and abnormal
operating conditions. TransAlta stated that it was advised by the AESO that the proposed
double-circuit line from the Windy Flats substation to the Foothills substation planned for 2015
will remove the identified system constraints. TransAlta stated that the facilities in the south
Foothills project are urgently required and supports the earliest possible in-service date in order
to alleviate known constraints, which are directly and adversely impacting its generating
facilities.
2.1.7 Views of ENMAX Green Power Inc. (EGPI) and ENMAX Shepard Inc. (ESI)
81. Both EGPI and ESI are in support of the FATD NID application. EGPI is the parent
company of ESI, which owns the Shepard Energy Centre. They submitted that the Shepard
Energy Centre, the expected in-service date of which is January 1, 2015, needs the facilities
proposed in the FATD in order to deliver its full capacity to the grid in a timely manner.
2.1.8 Commission findings
2.1.8.1 Application No. 1608620 – FATD NID
82. As noted in paragraph 39, Section 34 of the Electric Utilities Act contemplates a
two-stage assessement of need applications. First, the Commisison considers whether an
expansion or enhancement of the existing transmission system is necessary to alleviate
constraint, improve efficiency or respond to a request for system access. Second, the
Commission considers if the AESO’s preferred alternative to address that need is reasonable and
in the public interest.
83. With respect to the first stage assessment of the FATD NID, the Commission observes
that no party disputed the AESO’s conclusion that there is a need to expand and enhance the
transmission systems in the vicinities of southeast Calgary, Okotoks and High River. To the
contrary, all of the parties recognized that some measures were required to address this need. The
real dispute amongst the parties relates to the means proposed by the AESO to address the
identified need, a topic that the Commission addresses in Section 2.2 below.
84. The Commission has reviewed the load and generation forecasts prepared by the AESO
in support of the NID and considers that those forecasts reflect recent changes in market
conditions and up-to-date information regarding future generation. Although the AESO’s future
wind generation forecast has dropped compared to earlier forecasts, it continues to forecast
2,544 MW of total installed wind generation by 2019 in its 2012LTO environmentally-driven
scenario. Likewise, the AESO continues to forecast load growth for the area, although at a more
modest pace than it previously predicted. The Commission is satisfied that the assumptions made
by the AESO in its load and generation forecasts are sound, and that the forecasts themselves are
reasonable.
85. The Commission is similarly satisfied that the power system planning studies, undertaken
by the AESO under various scenarios, support the AESO’s conclusion that there is a need to
expand or enhance the transmission system in the study area to avoid reliability constraints in the
southeast Calgary, Okotoks and High River areas.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
20 • AUC Decision 2013-369 (October 7, 2013)
86. The Commission also finds that sensitivity studies undertaken by the AESO confirm the
need to expand or enhance the transmission system in the study area. The Commission notes, in
that respect, that those studies appropriately took into account recent changes in system
configurations such as the WATL and EATL, and verified the need for upgrading the
transmission system in the study area. The Commission accepts the results of the sensitivity
study that while certain planned facilities such as the Foothills to Sarcee line could be delayed,
the system upgrades are required in the study area by 2014.
87. The Commission concludes that the AESO’s load and generation forecasts for the study
area are reasonable and concludes that there is a need to expand and enhance the transmission
system in the vicinities of southeast Calgary, Okotoks and High River. The Commission accepts
that the need for system reinforcement in the area is primarily driven by the need for facilitating
the transfer of wind generation from southern Alberta, interconnection of local gas-fired
generation and forecasted load growth.
2.1.8.2 Amendment to the SATR NID
88. While IPCAA questioned the ongoing validity of the SATR NID approval given changes
to market conditions since it was issued, the Commission finds that it is not an issue that it
should properly consider in this proceeding.
89. The AESO’s application to amend the SATR NID approval did not relate to the need to
expand or enhance the transmission system in southern Alberta. Rather, its amendment request
was specific to one element of the SATR NID approval, its preferred technical solution to
address the need for the 911L line rebuild. Because the AESO is not seeking to amend that
aspect of the SATR NID approval, and because the ongoing validity of that determination was
not raised in a subsequent application to review and vary the SATR NID approval, the
Commission finds that the concerns raised by IPCAA in this respect are not properly before it.
Notwithstanding the Commission’s conclusion that this element of the SATR NID approval is
not properly before it in this proceeding, the Commission is of the view that the need for the
911L line rebuild is consistent with the AESO’s finalized SATR milestones for staged
implementation approved by the Commission. Specifically, the Stage I construction milestone
for the 911L line rebuild approved by the Comission was 500 MW of generation forecast in
Pincher Creek and the Peigan region. In this proceeding, the AESO reiterated that this milestone
has been met since 2010, and continues to be met by the latest wind generation forecast.
90. Because it is the Commission’s view that its previous approval of the need to expand or
enhance the transmission system in southern Alberta continues to be in force, it is of the view
that the only issue raised by the SATR NID amendment is whether the technical solution (Windy
Flats configuration) proposed is the appropriate technical solution to meet that need. That issue is
discussed below.
2.2 Reasonableness of the proposed technical solutions
91. Because Grid Power’s Fidler to Langdon and 911L at 138-kV proposals in relation to the
technical solutions are intrinsically linked with the facility applications, the Commission is
addressing the Grid Power proposals in conjunction with the need applications.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 21
2.2.1 Views of the AESO
2.2.1.1 FATD NID
240-kV system development
92. The AESO stated that reconfiguring, upgrading or rebuilding existing transmission lines
was preferred over transmission development options that required distinctly separate new
corridors to minimize land impacts and maximize the efficient use of existing rights-of-way. The
AESO added that a voltage conversion from 138-kV to 240-kV was also considered where
possible. Further, it stated that it employed an incremental approach to isolate, and subsequently
alleviate constraints and reliability violations caused by existing transmission lines to satisfy the
requirements of the Alberta Reliability Standards in the long-term. Except for the proposed
FATD plan, the AESO did not develop any other alternatives to the 240-kV transmission system
expansion plan.
93. The AESO explained that its 2011 FATD plan was derived from the its 2011 FATD
engineering report and was comprised of four development steps. Step one included
reinforcement of the 240-kV transmission path from the Langdon 102S substation to Janet 74S
substation to East Calgary 5S substation, which was applied for in the East Calgary transmission
system upgrades and the Shepard Energy Centre connection project, and approved in
Decision 2012-283.17 Steps two and three included all the transmission facilities applied for in
the FATD NID. Step four included possible future transmission upgrades. The major component
of the step four development was a new 240-kV double-circuit transmission line from Sarcee
42S substation to Foothills 237S substation.
94. The AESO explained that its 2012LTO and HVDC dispatch supplementary report
assumed the following system configurations:
FATD East configuration: includes steps one to three of the 2011 FATD plan
FATD East plus third-circuit configuration: includes steps one to three of the 2011 FATD
plan, as well as the new 138-kV circuits connecting the ENMAX No. 65 to No. 54 to
No. 41 substations
FATD full configuration: includes steps one to four of the 2011 FATD plan
95. The following figure, found in the FATD NID, illustrates the proposed 240-kV
transmission facilities in the AESO’s FATD NID:
17
Decision 2012-283, Alberta Electric System Operator, AltaLink Management Ltd., ENMAX Power
Corporation, East Calgary Transmission Project and Shepard Energy Centre Interconnection, Proceeding
No. 1229, November 1, 2012.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
22 • AUC Decision 2013-369 (October 7, 2013)
T
72
7L
72
7L
85
0L
911L
De-e
nerg
ized
1
03
7L
9
85
L
1109L (
old
8
50L @
24
0kV
)
10
03
L
10
38
L
1080L (
se
ctio
ns o
f 9
11
L)
Transmission System in 2014 following completion of the East Calgary
NID, plus Proposed Transmission Developments
Sarcee
East Calgary
5S
936L 937L
E
x Janet
x 42S 916L
SS-2 2.80L
SS-23
23.80L
74S
D
1064L
1065L
Note:
This diagram contains a
simplified representation of
the system configuration.
Technical detail has been
simplified for illustration
purposes. It does not
indicate geographical
locations of facilities. Some
existing substations and
circuits are not shown.
J
SS-25
I
F
Langdon
102S
C
Legend
Existing 138 kV
New 138 kV
Existing 240 kV SS-65
1106L
1107L
x
XXXX
New 240 kV
Join existing lines
Energized with FATD-East
New substation included in
FATD East NID
x 850L
H
G
B
Carseland
525S
De-energize 138 kV
De-energize 240 kV
Okotoks
678S
727AL
646L
L
FATD-East NID
o Magcan
142S K
A Foothills
237S
A Summary List Reference 434L
High River 65S
Figure 2 – Transmission system in 2014 following completion of the East Calgary NID, plus proposed transmission
developments
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 23
96. The AESO disagreed with Grid Power that the Fidler to Langdon proposal would offer
more system capability than the AESO’s FATD plan. The AESO pointed out that Grid Power
included the high-voltage direct-current lines in its analysis of its Fidler to Langdon proposal but
excluded them when evaluating the AESO’s proposal. The AESO explained that Grid Power
used WATL and EATL to alleviate overloads in the post-contingency period. Wind generation
was then increased in the post-contingency period by redispatching WATL and EATL, until one
or both of them reached their respective limits. The AESO concluded that such an approach
yields a higher total transfer capability (TTC) than is practically feasible for the operation of the
high-voltage direct-current lines. The AESO stated that its TTC analysis demonstrates that its
FATD plan provides significantly more TTC than the Fidler to Langdon proposal under all
options.18
97. According to the AESO, a TTC analysis is recognized as a test of transfer capability and
is not, in any event, a substitute for a full reliability assessment. It explained that the TTC
analysis may not accurately model future loads and generation because it simply assumes load
and generation are added at specific locations to stress specific transmission paths.
98. The AESO argued that it did not create the overload of the 936L/937L line for the Fidler
to Langdon proposal by dispatching WATL at zero MW. It noted that it is required to make
assumptions to support transmission system planning and it previously established a high-voltage
direct-current dispatch methodology for planning purposes. The AESO stated that it consistently
applied this methodology to model both the performance of the ENMAX No. 65 substation
termination proposed in the FATD plan and the Langdon termination proposed by Grid Power.
The AESO submitted that, from a long-term planning perspective, the ENMAX No. 65
substation termination is more robust than a Langdon termination because it satisfies the Alberta
Reliability Standards under a wider range of operating conditions and, therefore, avoids or delays
the need for future transmission system development.
99. The AESO stated that the Langdon termination would result in dependence upon the
Langdon substation and increase the number of major transmission lines terminating there from
eight to ten. It added that its FATD plan avoids this dependence by directing the power to
ENMAX No. 65 and Janet 74S substations, both of which directly serve the Calgary area load.
Rather than increasing the impact of a significant power supply disruption at either the Langdon
substation or in the corridors leading to the substation, the AESO explained that its proposal
ensures that the ENMAX No. 65 and Janet 74S substations would remain separately supplied in
the event of such a disruption.
100. The AESO testified that it had considered the option of having a new line from Fidler to
the load centre in the Calgary area during the initial stage of the development of the SATR need
application. However, the AESO stated that it discarded this option in the initial phase of the
SATR because of constructability and environmental issues. The AESO reiterated that it had not
changed its views since then.
101. Although the power from various generation sources flows on the single corridor between
Shepard Energy Centre and Janet 74S substation, the AESO submitted that terminating at
ENMAX No. 65 substation diversifies the system. Currently, most of the power supplying the
city of Calgary is transferred from the Langdon 102S to Janet 74S substations. ENMAX No. 65
18
Exhibit 721.0, AESO Reply Evidence, Appendix C, Attachment B, pages 8-9.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
24 • AUC Decision 2013-369 (October 7, 2013)
substation is close to the load centre in south Calgary. The AESO explained that terminating the
line at this substation helps to unload Janet 74S substation and spread the flows out more evenly
around Calgary. It further noted that terminating at ENMAX No. 65 substation assists with
operational flexibility because it is currently difficult for operators to plan maintenance around
these highly loaded lines.
102. The AESO further stated that creating diversity on the system is very important for the
long-term. It observed that as the city of Calgary continues to grow, its ENMAX No. 65
termination will provide strong supply sources to its surrounding area. The AESO explained that
it is also looking at a 240-kV loop around the west of the city in its long-term plan, which
requires diversity on the system.
103. The AESO stated that the Goose Lake to Chapel Rock project (the Chapel Rock project)
is not part of this proceeding.19 In response to the Grid Power submission that the proposed
Fidler termination would eliminate the need for the Chapel Rock project, the AESO stated that
the Grid Power proposal would not eliminate the need for the Chapel Rock project because its
cancellation would restrict wind development in southern Alberta due to limited capability of the
Milo to Langdon transmission line. The AESO added that additional transmission facilities
would be needed by 2022, if the Chapel Rock project was cancelled. The AESO added that the
cancellation would also prevent it from restoring the Alberta-British Columbia intertie path
rating because additional transmission facilities are required to do so. The AESO concluded that
the Fidler to Langdon proposal would not result in indirect cost savings of $342 million by going
south to Fidler because the Chapel Rock project is nonetheless required.
138-kV system development
104. The AESO identified three alternatives in developing the 138-kV transmission system
expansion plan to reinforce the existing local transmission system in the vicinity of High River
and Okotoks:
two single-circuit 138-kV transmission lines: one from Foothills 237S to Okotoks 678S
substation and one from Foothills 237S to High River 65S substation
a double-circuit 138-kV transmission line from Foothills 237S to High River 65S
substation and a new single-circuit 138-kV transmission line from Okotoks 678S to
High River 65S substation
a double-circuit 138-kV transmission line from Foothills 237S to Okotoks 678S
substation and a new single-circuit 138-kV transmission line from Okotoks 678S to
High River 65S substation
105. The AESO stated that all three alternatives meet the short-term and long-term need for
transmission system expansion between Foothills 237S, High River 65S and Okotoks 678S
substations and satisfy all reliability requirements in the long-term. It explained that based on the
information provided by AltaLink, alternative 1 was selected for the proposed 138-kV
development plan because, in comparison, alternatives 2 and 3 are higher in cost and land
impacts. The following figure illustrates the schematic configurations of the three alternatives:
19
The Goose Lake to Chapel Rock project is comprised of a new Chapel Rock 500/240-kV substation and
associated 240-kV transmission line. An application for this project was filed and registered as
Proceeding ID No. 2349.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 25
727L
727L
727L
Alternative 1 (Preferred)
Alternative 2
Alternative 3
Okotoks
Magcan
Foothills
High River
Okotoks
Magcan
Foothills
High River
Okotoks
Magcan
Foothills
High River
Legend Note:
New 138 kV These diagrams contains a simplified representation of the system configuration. Technical detail has been simplified for illustration purposes. They do not
Existing 138 kV indicate geographical locations of facilities.
Figure 3 – AESO 138-kV alternatives in the High River area
106. The AESO stated that using the Foothills substation to supply the High River and
Okotoks areas would provide geographic separation from south Calgary. It explained that this
would provide long-term supply security for the High River area by enabling future expansion of
the 138-kV transmission system and operational flexibility for both the Calgary and High River
areas. The AESO stated that the Grid Power proposal of 911L at 138-kV would not result in
these benefits. The AESO also explained that its Foothills 138-kV plan would allow for the
salvage and removal of some existing transmission facilities that would no longer be needed after
the new facilities are in place.
107. The AESO stated that there is no evidentiary basis for the assertions made by Grid Power
that its 911L at 138-kV proposal would not require a third circuit out of ENMAX No. 65
substation. It argued that the Grid Power proposal would not result in cost savings of between
$115 and $130 million due to the avoidance of the third circuit because the third circuit is
required in both the AESO’s proposed 138-kV plan and in Grid Power’s proposal.
108. The AESO stated that the 911L at 138-kV proposal would cost more than the $2.5 million
claimed by Grid Power because additional transmission facilities would be required to enable the
Grid Power proposal to comply with reliability criteria and meet the needs of the High River area.
The AESO estimated that based on an association for the advancement of cost engineering class
level estimates between Class 5 (screening) and Class 4 (concept/feasibility), the total cost of
Grid Power’s proposal would be $60 million with an uncertainty range of -40% to +80%.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
26 • AUC Decision 2013-369 (October 7, 2013)
109. The AESO added that the 911L at 138-kV proposal would require the termination of
three 138-kV lines at ENMAX No. 65 substation and that this would fully utilize the three
remaining 138-kV bays designed to serve the south Calgary load. In addition, connecting the
350 MW Saddlebrook power plant to the 138-kV transmission system in High River would result
in reliability violations and is not a viable alternative.
2.2.1.2 Amendment to the SATR NID
110. The AESO amended one of the technical solutions in the SATR NID approval, namely
the 911L line rebuild. Instead of terminating the new double-circuit 240-kV 1037L/1038L line at
the existing Peigan 59S substation as approved previously (Peigan configuration), the AESO
proposed to move the south termination point to a new Windy Flats 138S substation (Windy
Flats configuration). The following figure in the AESO’s need amendment application illustrates
the proposed Windy Flats configuration.
Figure 4 – Windy Flats configuration
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 27
111. The AESO stated that while preparing detailed engineering and scheduling for the
proposed south Foothills application, AltaLink identified an in-service date risk arising from
work on federal lands required to upgrade the existing Peigan 59S substation, which had an
in-service date of 2014. Consequently, AltaLink proposed the development of a new 240/138-kV
substation east of Peigan 59S substation to serve as the southern termination point for the
proposed 1037L/1038L line and also provided to the AESO an order of magnitude cost
comparison between the two configurations.
112. The AESO performed steady state analyses to assess transmission system performance
for both the Peigan and Windy Flats configurations, assuming both summer peak load and light
load conditions in 2016. The study results concluded that both configurations would serve the
same functionality and meet the transmission system requirements.
113. Having considered the potential effects of delaying the new line if it were terminated at
the Peigan 59S substation, the reduced cost of terminating the line at the new Windy Flats
substation, and that the same technical functionality existed for both configurations, the
AESO proposed to amend the original need approval to request the construction of a new
Windy Flats 138S substation east of Peigan 59S substation and terminating the new
1037L/1038L line at this substation. The AESO indicated that the primary reason for the
amendment is that the Peigan 59S termination would not meet the in-service date. It clarified that
it had included AltaLink’s two cost estimates in the SATR NID amendment for the purposes of
describing the cost implications of the amendment and not for conducting a comparative
analysis.20
114. As discussed in Section 2.1.8.1, the AESO acknowledged that the wind generation
forecast has significantly changed since the SATR NID was approved and that it had conducted
sensitivity studies utilizing the updated generation and load forecasts. The AESO stated that the
approved SATR construction milestone for the 911L line rebuild has been met since 2010 and
confirmed that the milestone continues to be met by the latest wind generation forecasts.
115. The AESO testified that the timing for the 911L line rebuild is now critical. It is currently
experiencing constraints on the existing 911L line from an operational perspective.21 Starting
next year, there will be N-0 constraints under normal system operation. The AESO explained
that remedial action schemes, as suggested by IPCAA, is not an appropriate planning response to
address N-0 constraints, adding that such constraints would become increasingly severe as new
wind generation is connected to the transmission system in southern Alberta. Due to the earliest
achievable in-service date of Q3 2015 for the 911L line rebuild, it would not be in the public
interest to continue to delay the 911L line rebuild and constrain market participants in southern
Alberta.
116. The intertie between British Columbia and Alberta (referred to as path 1), is rated as
1,200 MW for imports from British Columbia to Alberta, and 1,000 MW for exports from
Alberta to British Columbia. Based on the AESO’s current operating policies and procedures
(OPP) 304 Alberta-BC interconnection transfer limits,22 the maximum British Columbia to
Alberta import and export capabilities are 780 MW and 800 MW, respectively. The AESO stated
20
Exhibit 550.01, AESO responses to IPCAA information requests, page 7. 21
Transcript, Volume 2, page 185, line 8. 22
AESO OPP 304 Alberta-BC Interconnection Transfer Limits, http://www.aeso.ca/downloads/OPP_304.pdf.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
28 • AUC Decision 2013-369 (October 7, 2013)
that for the FATD planning studies, the existing Alberta-British Columbia intertie operational
limits as described in the AESO’s OPP 304 were assumed and tested to determine whether the
limits could be maintained over the range of generation and system conditions evaluated. It
concluded that the proposed FATD does not negatively impact the current operational limits of
the Alberta-British Columbia intertie.
117. The AESO concurred with Powerex that the main issue limiting the simultaneous wind
and imports is the overload on the proposed 240-kV line between the Goose Lake and proposed
Windy Flats substations after the outage of the Chapel Rock to Langdon 500-kV line, and
proposed two mitigation measures to address this issue:
Dynamic thermal line rating: to be placed on the 240-kV lines between Goose Lake and
Windy Flats substations.
Remedial action scheme: to trip the Alberta-British Columbia intertie for the outage of
the Chapel Rock to Langdon 500-kV line. This remedial action scheme will be armed
only at combination of high wind generation and high import conditions.
118. The AESO testified that it would ensure that it takes all necessary mitigation measures in
advance of the need. Based on the results of the market simulation tool, it concluded that with
the planned transmission system, no adverse impact on intertie capability is expected in 2017,
and that anticipated wind generation and in-merit imports in 2022 can be accommodated without
constraints in all but a few hours under normal system conditions. The AESO stated that the
timeline to install the dynamic thermal line rating is between 2017 and 2022; while the timeline
to install the remedial action scheme is 2022. If the need were to arise before 2017, it would be
prepared to move forward with the implementation of these measures. The dynamic thermal line
rating does not require acquisition of rights-of-way and it is a piece of equipment that must be
mounted on towers. With respect to a remedial action scheme, the AESO stated that it would
take a year at most to implement.
119. The AESO stated that the dispatch of WATL and EATL in a south to north direction
could alleviate potential path 1 curtailments caused by the 936L line (East Calgary 5S to
Langdon 102S substations) contingency under high wind and high import conditions.
120. The AESO concluded that the FATD will be a step towards restoring the Alberta-British
Columbia intertie capability and confirmed that the mitigation measures and the timing thereof
would be addressed as part of the intertie restoration program.
121. The AESO spoke of the many legislated duties it has as the transmission system planner,
including Section 15.1(2) of the Transmission Regulation, reproduced below:
…when considering the location of new transmission facilities or of enhancements or
upgrades to existing transmission facilities, the ISO must consider
(a) wire solutions that reduce or mitigate the right of way, corridor or other route
required, and
(b) maximize that efficient use of rights of way, corridors or other routes that already
contain or provide for utility or energy infrastructure.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 29
122. The AESO provided the following examples of the legislative duties it must fulfill in
planning the transmission system.
plan the capability of the transmission system to meet the current and future needs of
market participants23
develop plans for the transmission system to provide efficient, reliable and
non-discriminatory system access service and the timely implementation of required
transmission system expansions and enhancements24
plan a transmission system that satisfies reliability standards25
take into consideration geographic separation for the purpose of ensuring reliability of the
transmission system26
plan a transmission system that is sufficiently robust so that 100 per cent of the time,
transmission of all anticipated in-merit electric energy can occur when all transmission
facilities are in-service27
make arrangements for the expansion or enhancement of the transmission system so that,
under normal operating conditions, all anticipated in-merit electricity can be dispatched
without constraint28
123. The AESO argued that it considered the use of existing infrastructure and right-of-way in
its planning process for the SATR need application and, consequently, proposed the 911L line
rebuild to terminate at the existing Peigan 59S substation. However, it became apparent during
the subsequent development process that the Peigan substation rebuild would not be available in
a timely manner to meet the needs of market participants. In order to meet this urgent need, the
AESO proposed the Windy Flats alternative.
124. The AESO recognized that the Peigan configuration might better serve the private
interest of the Conners, but that it must also have regard for the greater public interest, ensure the
timely implementation of transmission system enhancements to satisfy reliability standards, and
allow all in-merit electricity to be dispatched without constraint under normal operating
conditions. According to the AESO, there is no basis for the argument that the SATR NID
amendment has the effect of discriminating against the Conners or the Piikani First Nation. It
explained that the process for acquiring access to federal lands is different than the process for
acquiring access to lands that are subject to provincial jurisdiction. The potential for delay
associated with the Peigan substation upgrades on federal lands poses scheduling implications
and risks that are unacceptable to the AESO.
23
Electric Utilities Act, Section 17(i). 24
Electric Utilities Act, Section 33(1). 25
Transmission Regulation, Section 15(1)(a). 26
Transmission Regulation, Section 15.1(1). 27
Transmission Regulation, Section 15(1)(e)(i). 28
Transmission Regulation, Section 15(1)(f).
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
30 • AUC Decision 2013-369 (October 7, 2013)
2.2.2 Views of AltaLink
125. With respect to Grid Power’s conceptual Fidler to Langdon route, AltaLink submitted
that the opinions of Mr. Trevor Cline, who authored the Grid Power report and testified at the
hearing on siting, costing and the social, economic and environmental effects of transmission
lines, must be given the same weight as those of a lay witness. AltaLink stated that Mr. Cline is
not an expert with respect to assessing land-use impacts or transmission line routing, adding that
the only projects in which Mr. Cline has had a role in siting as a project manager were in the
early 1990s and were minor in scale. AltaLink also stated that Mr. Cline did not have substantial
experience in transmission line costing, design, construction, or project management and had
never been involved in the construction of a project with terrain comparable to the land along the
conceptual Fidler to Langdon route. According to AltaLink, Mr. Cline had less relevant
experience with respect to transmission line design, construction methods, costing, and siting
than project managers working for transmission facility owners in Alberta today.
126. Although the Langdon termination is shorter, AltaLink submitted that the preferred route
to ENMAX No. 65 substation requires 66 fewer acres of right-of-way. It argued that Mr. Cline
did not consider the agricultural benefits associated with the triple-circuit monopoles and ignored
that the Langdon termination would mean the addition, rather than the replacement, of a line.
127. With respect to residential impacts, AltaLink submitted that only two residences within
150 metres would be closer to a transmission line than they are today along its preferred route, as
opposed to three such residences on the conceptual Fidler to Langdon route. Regarding
residences within 800 metres, AltaLink stated that there will be 28 on the preferred route, as
opposed to 22 along the conceptual Fidler to Langdon route.
128. AltaLink contended that Mr. Cline’s cost estimate for the Langdon termination was
simply based on average costs of the north Foothills line and did not account for angle or
dead-end structures, despite having a sharp turn and a termination at the Langdon 102S
substation’s west side. In its view, Mr. Cline has also double-counted a blended line cost.
129. AltaLink submitted that the Langdon termination would result in the congregation of
important substations in one geographical area, which does not align with the AESO’s preference
for geographical diversity by locating substations in different areas where opportune to do so.
AltaLink agreed with the AESO that the ENMAX No. 65 termination provides operational
flexibility because it will be easier for AltaLink to take line outages, or if such outages are not
possible, will mean that maintenance crews are working in less congested areas when
undertaking live line work.
130. AltaLink disagreed with Mr. Cline’s conclusion that his Fidler termination would
significantly reduce land-use impacts for both local residences and the environment, arguing that
he did not undertake any field studies or engage any experts when he drew a straight line on a
map and called it a “representative” or “conceptual” route. Further, Mr. Cline used the alternate
Fidler substation site, which was not approved in the recent Commission Decision 2013-177,29
for the Fidler project, and is approximately four kilometres from the preferred Fidler substation
site, approved by the Commission. Terminating at the approved Fidler substation site would
increase the distance assumed by Mr. Cline.
29
Decision 2013-177, Alberta Electric System Operator, AltaLink Management Ltd., Fidler 312S Substation
Transmission Project, Proceeding ID No. 2284, May 10, 2013.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 31
131. AltaLink submitted that in contrast to Mr. Cline, it has direct experience with the social,
economic and host of other challenges that arise in exploring routing through the Porcupine
Hills. Both the Southwest 240-kV project and the initial work for the proposed Fidler to
Chapel Rock project included potential routes in the area. When such routes were suggested
within or close to the Porcupine Hills, AltaLink received an immediate and significant level of
stakeholder and general public opposition. AltaLink learned that routing in the Porcupine Hills
raises social and environmental concerns. People in and around that area are informed because
they place great value on the Porcupine Hills, not only from an environmental perspective, but
also from a recreational perspective, as well as for the preservation of the beauty of the hills.
132. According to AltaLink, Mr. Cline’s cost estimate for the Fidler termination is neither
realistic nor credible, contending that Mr. Cline did not know where the conceptual route would
exactly go, how long it would be, how it would be built, what structures would be used and
where, what construction techniques would be used, and so on. It argued that Mr. Cline made no
investigation into the constructability of the route and did no research or analysis on the potential
costs. Like the Langdon termination, Mr. Cline’s cost estimate for the Fidler termination is based
on a simplistic application of a per-kilometre average line cost of the south Foothills line (across
flat prairie on lattice towers) to the steep terrain and winding hills and valleys of the
Porcupine Hills, without any certainty with respect to the structures that would be used or the
challenges that would be encountered.
133. AltaLink submitted that the conceptual Fidler to Langdon route would encounter
construction challenges in the Porcupine Hills because it would zigzag all over the place. The
conceptual Fidler to Langdon route would require more than twice the heavy angles and
dead-end structures than the south Foothills line. In addition, most of the structures would have
to be modified because 38 per cent of the Fidler route crossing the Porcupine Hills would have
elevation changes greater than ten percent. Unlike building a line on the flat prairie as the south
Foothills line, graded roads would be required for access, construction and maintenance.
134. With respect to environmental impacts, AltaLink submitted that although an additional
Oldman River crossing can be avoided in the conceptual Fidler to Langdon route, this route
would involve approximately 44 transmission line crossings of the tributaries of the
Oldman River, most of which share similar environmental sensitivities as the Oldman River. In
addition, given the expected terrain constraints, a large number of access trails and watercourse
crossings would be required to gain access to the right-of-way for construction. AltaLink
considers the crossing of dozens of tributaries to have a higher, overall potential for impacts than
one crossing of a larger river. Although its preferred route for the south Foothills line passes
close to Mud Lake, there are two towers 173 metres and 146 metres away from the edge of
Mud Lake respectively. Further, although Mud Lake is within Environmentally Significant Area
291, it is not recognized as a significant breeding or staging area for water birds.
135. Stantec Consulting Ltd. (Stantec), AltaLink’s environmental expert, submitted that the
conceptual Fidler to Langdon route would have a much higher environmental effect. This route
encounters a much greater number of environmental resources than the south Foothills line.
While avoidance of some features may be possible during route refinement, other features (e.g.,
intact native grassland, steep slopes, headwater drainages) are widespread and cannot be avoided
completely. Many of these resources are highly sensitive to anthropogenic disturbances. Stantec
added that the environmental impacts which would result from the Fidler route, and on any
refined route near this route through the eastern Porcupine Hills, are expected to be much higher
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
32 • AUC Decision 2013-369 (October 7, 2013)
than the south Foothills line and present much greater challenges for mitigation. Dr. Power of
Stantec gave an example of the Foothills’ rough fescue. Currently, there is no evidence that the
rough fescue grassland community can be restored and subsequently reclaimed.
136. AltaLink submitted that Mr. Cline had not established that the AESO’s technical solution
to terminate the south Foothills line at Windy Flats 138S substation is not in the public interest.
Due to the reverse onus with respect to need applications, interested parties must establish that
the AESO’s assessment of the need is technically deficient or that to approve the need
applications is not in the public interest. AltaLink submitted that in contrast, diverting the
proposed south Foothills transmission line to Fidler 312S substation would have greater
environmental effects, be challenging from a constructability perspective, have a greater cost and
would be highly contentious.
137. AltaLink stated that Grid Power’s 911L at 138-kV proposal is not devoid of impacts. The
911L line would nonetheless have to be re-terminated into the ENMAX No. 65 substation, which
would involve some construction activity adjacent to residential areas in Calgary. The proposal
would create issues with future terminations at the ENMAX No. 65 substation. AltaLink
explained that after the third 138-kV line is constructed into the substation, which the AESO is
proposing in 2014, the 138-kV portion of the substation will be full. Given the proximity to the
freeway and ring road, there is little or no room to expand the ENMAX No. 65 substation.
138. AltaLink stated that the only section of 727L line that could be delayed under
Grid Power’s proposal is the smaller seven-kilometre portion of the line south of the Magcan
142S substation. There is no dispute between it and Mr. Cline that the 21 kilometres of the 727L
line between Magcan 142S and ENMAX No. 65 substation would have to be rebuilt for the
interconnection of the Saddlebrook power plant to the 138-kV system. The rebuild would also
require a Bow River crossing, which AltaLink is proposing to remove, and would traverse higher
density residential development. According to AltaLink, Grid Power failed to take into account
the impacts of rebuilding the transmission line in residential areas and the environmental impacts
for its 911L at 138-kV proposal.
2.2.3 Views of the Diagonal group
139. The Diagonal group stated that some of the key assumptions underlying the AESO’s
southern Alberta wind generation forecasts were wrong. The factors that have the greatest impact
on relative generation costs are greenhouse gas costs and the natural gas prices. The Diagonal
group submitted that the AESO forecasted greenhouse gas offset prices of between $25 and
$65 per tonne of CO2 between 2010 and 2020, in the 2009 Long-term Transmission Plan, but
that the effective price of CO2 in Alberta today is $1.80 per tonne. The Diagonal group added
that the AESO forecasted a natural gas price of $8 to $10 per gigajoule between 2008 and 2018
in its 2009 Long-term Transmission Plan, but the AESO has acknowledged at the hearing that
the natural gas prices are a lot lower today.
140. The Diagonal group submitted that the southern Alberta wind generation development
has fallen far short of the amount the AESO forecasted. At the time the SATR NID was
developed in 2008, there was only approximately 500 MW of wind generation in southern
Alberta. The system developments approved in the SATR NID were based on 2,700 MW of new
wind generation being developed in southern Alberta between 2007 and 2017. In other words, in
the SATR NID, the AESO was forecasting 3,200 MW of wind generation in southern Alberta by
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 33
2017; but that as of today, only approximately 815 MW of wind generation is installed in
southern Alberta. It stated that only 315 MW of southern Alberta wind generation has been
installed half way through the ten-year planning period (2007 to 2017).
141. According to the Diagonal group, current market conditions are not supportive of wind
project development. It pointed out that the AESO’s recently released 2012LTOU has a lower
wind forecast than its 2012LTO. The Diagonal group quoted from the 2012LTOU that the
reduction is a result of both consultation with stakeholders, who indicated current short-term
market conditions are not supportive of wind project development, and a reduction of wind
projects from the AESO connection queue.30 It added that the majority of southern Alberta wind
generation projects on the AESO’s project list today date from October 2007, or earlier. Since
that time, only two new southern Alberta wind generation projects have been proposed and
remain on the AESO’s project list.
142. The Diagonal group argued that the environmental-driven scenario in the AESO’s
2012LTOU is not likely to occur. The environmentally-driven case for wind generation
development in southern Alberta is a worst-case scenario, intended to represent the absolute
maximum amount of wind generation that might be developed. The base case scenario in the
2012LTOU forecasted only 1,560 MW of wind generation in all of Alberta by 2017, and only
approximately 1,240 MW in southern Alberta by 2017.
143. The Diagonal group stated that the 911L line rebuild is not urgent because the forecasted
southern Alberta wind generation development has not materialized. With regard to the AESO
statement that the wind generation in southern Alberta must be limited to approximately
1,150 MW in 2014 to meet the reliability criteria, the Diagonal group argued that there are
basically no new wind projects being proposed and there are only 815 MW of wind generation in
southern Alberta as of June 2013.
144. The Diagonal group submitted that the AESO failed to account for the significant system
development since the SATR NID was developed, i.e. EATL. EATL, a 1,000 MW direct-current
line (expandable to 2,000 MW) that has a southern terminus at Brooks in southeastern Alberta,
and provides another means of egress for wind generation from southeastern Alberta.
145. The Diagonal group concluded that the AESO should take a second look at its plans for
transmission development in southern Alberta due to less wind generation than forecasted and
more transmission capacity than was anticipated at the time of SATR NID approval. It pointed to
Decision 2013-135,31 in which the Commission recently directed the AESO to change an ISO
rule based on a material change between what the AESO forecasted and what has actually
occurred. According to the Diagonal group, this is another example where there has been a
material change between the AESO forecast and what has actually occurred.
146. The Grid Power report prepared for the Diagonal group stated that the AESO’s proposal
in the FATD NID will result in an almost immediate risk of dispatch conflicts between wind
output from the Pincher Creek area, imports over the British Columbia intertie and generation
from southern Alberta’s combined cycle plants. Grid Power recommended a modification of the
30
Exhibit 752.01, AESO 2012 Long-Term Outlook Update, page 10. 31
Decision 2013-135, ATCO Power Ltd. and ENMAX Energy Corporation, Complaints regarding ISO Rule
Section 302.1: Real Time Transmission Constraint Management, April 5, 2013.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
34 • AUC Decision 2013-369 (October 7, 2013)
two need applications in this proceeding by building a 240-kV connection from the
Langdon 102S substation in the north to the proposed Fidler substation in the south. More
specifically, Grid Power proposed to:
modify the north termination point of the double-circuit 240-kV 1106L/1107L line
between Foothills 237S and ENMAX No. 65 substations proposed in the FATD NID to
Langdon 102S substation instead of ENMAX No. 65 substation
modify the south termination of the double-circuit 240-kV 1037L/1038L line between
Foothills 237S and Windy Flats 138S substations proposed in the SATR NID amendment
to Fidler 312S substation west of the existing Peigan 59S substation; and cancel the
Windy Flats 138S substation
cancel or defer the Goose Lake to Crowsnest (Chapel Rock) transmission development
approved in the SATR NID approval
147. The following map in the Grid Power report illustrates the Fidler to Langdon proposal.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 35
Figure 3 Recommended Configuration
Modifications to the North Foothills
and South Foothills double circuit 240
kV transmission line (SATR Rebuild
911L Calgary South to Peigan)
Figure 5 – Grid Power Fidler to Langdon proposal
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
36 • AUC Decision 2013-369 (October 7, 2013)
148. Specifically in the north end, Grid Power’s conceptual Fidler to Langdon route follows
the preferred north Foothills line route from Foothills 237S substation up to route marker B240
and continues north to parallel the existing 1201L line until it reaches Langdon 102S substation.
The route modification provided by Grid Power is reproduced below and shown in purple.
Figure 6 – Grid Power proposal – Langdon termination
149. In the south end, Grid Power did not propose a defined route. Grid Power recommended
a modification to the preferred south Foothills line route in or near where it leaves the 911L line
route and deviates southeast to run southwest and south until it reaches Fidler 312S substation.
This conceptual Fidler to Langdon route is reproduced below and is shown in purple.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 37
Figure 7 – Grid Power proposal – Fidler termination
150. Grid Power stated that its Fidler to Langdon proposal would offer more system transfer
capability, as opposed to the FATD proposal to build a 240-kV line from ENMAX No. 65
substation to Foothills 237S substation and further south to Windy Flats 138S substation.
Grid Power contended that its Fidler to Langdon proposal would provide sufficient transfer
capability for at least the next ten-year wind generation forecast in the Pincher Creek region,
without risk of any dispatch conflicts between wind output from the Pincher Creek region and
imports from British Columbia and the combined-cycle power plants in southern Alberta.
151. With respect to the north termination at Langdon, the Diagonal group submitted that the
Fidler to Langdon proposal would provide reliability benefits by separating southern Alberta
wind and gas generation south of Calgary (including Saddlebrook generation) to Langdon 102S
substation in one corridor from the substantial output from the Shepard Energy Centre to
ENMAX No. 65 substation in another corridor. With regard to the AESO’s criticism that the
Fidler to Langdon proposal creates an over-reliance on the Langdon substation, where three
different substations are adjacent to each other, the Diagonal group responded that the AESO’s
FATD combines wind generation from southern Alberta, power transmitted on WATL and
power from the Shepard Energy Centre in the Shepard to Janet corridor, arguing the risk
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
38 • AUC Decision 2013-369 (October 7, 2013)
associated with the AESO’s proposal to combine all the different generation sources in a single
transmission corridor is greater than the risk associated with the alleged over-reliance on
Langdon 102S substation in Grid Power’s proposal.
152. Grid Power estimated that compared with the AESO’s proposal, its Fidler to Langdon
proposal will result in cost savings of $389 million, including both direct and indirect savings on
capital costs. The direct savings are contributed from reduced line length, avoidance of
additional costs of monopole structures and reduced number of heavy angle structures. The
indirect savings of $342 million are the avoided costs of the Chapel Rock project. With respect
to potential cost savings from the Fidler to Langdon proposal, the Diagonal group emphasized
that the magnitude of the benefits associated with eliminating the Goose Lake to Chapel Rock
project was huge. Even if the conceptual route to Fidler were to cost more than Mr. Cline’s
estimate because of the challenging terrain, that cost would be more than offset by the avoided
cost of the eliminated Chapel Rock project.
153. With respect to Mr. Cline’s qualification, the Diagonal group argued that siting
transmission lines is inherently not a technical or scientific exercise. It does not depend on
technical or scientific qualification or training. Siting transmission lines is something that is
learned on the job and is ultimately a subjective exercise. It explained that the exercise of siting
transmission lines involves relatively basic skills like looking at maps, counting residences,
identifying existing linear disturbances for the purpose of identifying paralleling opportunities
and looking at public databases for environmental information such as the location and size of
environmentally significant areas. The Diagonal group admitted that Mr. Foley from AltaLink
certainly has more experience than Mr. Cline in siting transmission lines, but does not have
greater expertise.
154. Further, the Diagonal group stated that the Langdon termination would have reduced
residential impacts because the conceptual Fidler to Langdon route is 4.5 kilometres shorter and
has significantly fewer residences than the preferred route. For example, there would only be
three residences within 150 metres on the Langdon route, as opposed to seven residences on the
preferred route. Also, at route marker B240, the conceptual Fidler to Langdon route continues
north, paralleling the existing 1201L line, which would reduce land-use impacts.
155. The Diagonal group argued that the Langdon termination would have a smaller
incremental impact compared to replacing the small wood pole line between route markers
B240 and A260 with a line which uses extremely tall triple-circuit monopoles and would also
result in cost savings of approximately $35 million.
156. The Diagonal group stated that Stantec downplays the environmental effects of locating
the preferred route so close to Mud Lake and crossing the Oldman River. Both routes have
environmental challenges. The preferred route for the south Foothills line passes very close to a
major wetland area (i.e. Mud Lake) and crosses the nationally significant Oldman River. The
Diagonal group’s conceptual Fidler to Langdon route would avoid 18 kilometres of new 240-kV
line through the nationally recognized Environmentally Significant Area 291 and crossing of the
Oldman River valley. It admitted that the conceptual Fidler to Langdon route would cross the
southeastern edge of the Porcupine Hills which was not ideal. The Diagonal group also admitted
that Mr. Cline’s conceptual Fidler to Langdon route would need to be subjected to the greater
scrutiny of a proper route selection process.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 39
2.2.4 Views of Phyllis Robertson
157. Phyllis Robertson specifically opposed the technical solution associated with the 138-kV
transmission system in High River area proposed in the FATD NID. Grid Power stated in its
report that the AESO’s proposed Foothills 237S substation and the associated 138-kV
transmission lines from the Foothills substation to High River and Okotoks are not the best
solution to meet the load supply requirements of the High River regional system.
158. Grid Power argued that the AESO’s proposal would have a negative impact on the
region’s system reliability and would place the region at higher risk of islanding, with possible
damage to loads and generators as a consequence. Grid Power explained that the major
disadvantage of the AESO’s proposal for the High River regional system is that the entire region
is supplied from the proposed Foothills 237S via one new high capacity double-circuit 138-kV
line and leaves the 765L line, the 138-kV line from the Janet 74S to Strathmore 151S
substations, as the only other connection to the grid. If a transmission structure fails or is
knocked over on this new line, the regional system will, under the typical dispatch pattern of the
local generation, separate from the system. Grid Power added that a high intensity lightning
strike could also cause the region to be out-of-step.
159. Grid Power recommended converting a short section of the existing 240-kV 911L line (to
be decommissioned as part of the FATD project) to 138-kV operation and connect it to the
existing 727L line at the MagCan site to create a fourth 138-kV supply line into the region. This
proposal is referred to 911L at 138-kV by Grid Power. The following figure in the Grid Power
report illustrates the proposed configuration for the High River regional system.
Figure 8 – Grid Power 911L at 138-kV
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
40 • AUC Decision 2013-369 (October 7, 2013)
160. Grid Power stated that its 911L at 138-kV proposal would provide 305 MW and 327 MW
of capability for summer and winter loading respectively and concluded that based on the most
recent AESO load forecast, its proposal would provide sufficient load supply capability in the
High River region for the next 20 years.
161. Grid Power also stated that 911L at 138-kV would open up the opportunity to connect the
proposed Saddlebrook power plant to the regional system instead of to the 240-kV system.
System reliability would be improved by connecting this plant to a regional system which would
then be completely independent of the wind production coming north on the 911L line rebuild
and the Shepard Energy Centre on the east side of Calgary. Grid Power admitted that
interconnecting the Saddlebrook power plant to the 138-kV system could result in higher initial
system losses and potentially a higher loss factor cost for the owner of the plant. Mr. Cline also
testified that the Saddlebrook power plant interconnection would require that the 727L line from
Magcan 142S substation to ENMAX No. 65 substation be rebuilt immediately with a large
conductor.32
162. Grid Power stated that its 911L at 138-kV would not have any new impacts while the
AESO’s Foothills 138-kV project involves a new line with its associated land-use impacts.
Grid Power concluded that cancelling the Foothills 138-kV project and utilizing the 911L at
138-kV proposal would address the load supply need in the High River region with no additional
land-use impacts. Compared with the AESO’s proposal, it estimated that the total cost saving
from its 911L at 138-kV proposal would be $98 million.
163. Grid Power agreed with the AESO that both the FATD 138-kV configuration and the
911L at 138-kV configuration would have the same issue of high loading on the transformer at
ENMAX No. 65 substation by 2019, stating that the high loading would be the result of an
incomplete 138-kV system in Calgary. It added that the third circuit out of ENMAX No. 65
substation is not required for its 911L at 138-kV proposal.
164. With respect to siting constraints at ENMAX No. 65 substation, Grid Power argued that
ENMAX No. 65 substation is of comparable size to Janet 74S substation. However,
ENMAX No. 65 substation currently has only four line terminations compared to 14 at Janet 74S
substation.
2.2.5 Views of IPCAA
2.2.5.1 FATD NID
165. IPCAA submitted that it has identified concerns and deficiencies with regards to the
AESO’s FATD need application that, if approved, could have significant negative cost impacts
on ratepayers and would be contrary to the public interest. IPCAA recommended that the
Commission deny this need application on the grounds that it is technically deficient and that it is
in non-compliance with Section 11(3)(f) of the Transmission Regulation and Section 6.1 of AUC
Rule 007 to examine and compare transmission development alternatives for both the 240-kV
and 138-kV components of the application.
32
Transcript, Volume 9, pages 1715-1716.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 41
166. IPCAA submitted that the AESO failed to develop any other 240-kV alternatives to its
240-kV components, and simply relied upon the presumption that to “minimize land impacts and
maximize the efficient use of existing rights-of-way”33 would automatically result in the
preferred alternative. The AESO did not explain why other existing corridors (for example, along
the 1201L line corridor to Langdon) could not have been considered for the 240-kV
development. Further, the AESO did not contemplate any development alternatives that would
require expansion beyond the existing corridors.
167. IPCAA submitted that the AESO’s incremental approach is in fact a piecemeal planning
approach, and that in the absence of a holistic Calgary area plan, it is disconcerting that the
FATD plan may pose limitations on the future flexibility of the large Calgary area development,
ultimately resulting in a sub-optimal plan.
168. IPCAA noted that a 138-kV single-circuit from Okotoks 678S to Carseland 525S
substations is a common element among the three alternatives for the AESO’s 138-kV
components. This circuit would be created by reusing sections of the existing 138-kV lines 727L
or 911L and 850L, as appropriate, to form a new 138-kV connection between the Okotoks 678S
and Carseland 525S substations. IPCAA submitted that the AESO failed to explain the reason or
the economics of salvaging conductors and structures for a significant portion of the existing
727L and 850L lines to form the new 850L line between the Carseland 525S and Okotoks 678S
substations. Further, the AESO did not consider other ways to connect these two substations.
IPCAA concluded that as a result, although the AESO examined three alternatives in its
application, it was nonetheless deficient because all of its designs share a common element that
represents a significant portion of the scope, for which no development alternatives were
considered.
2.2.5.2 Amendment to the SATR NID
169. IPCAA submitted that the AESO expressed disregard for the cost implications of the
amendment by stating that the primary reason for the amendment was to meet its in-service date.
The AESO did not use the cost information provided by AltaLink to conduct a comparative
analysis and had little or no knowledge of the details that constitute the estimates. IPCAA is
concerned that the AESO has not satisfied its obligation to act in the best interest of ratepayers
by properly considering the cost implications associated with the amendment.
170. IPCAA was concerned about the cost comparison between the Windy Flats configuration
and the original Peigan configuration. It questioned how constructing a brand new Windy Flats
substation would cost only $1.36 million more than upgrading the existing Peigan substation
and, with respect to transmission line cost, how the Peigan option would cost $21.9 million more
than the Windy Flats option. IPCAA was also concerned that the “soft cost” estimated by
AltaLink, which included owner costs, distributed costs and other costs, accounts for close to
$33.7 million of the cost differential between the two configurations. IPCAA submitted that
there is little accessibility to information regarding the soft cost component of transmission
project costs, which makes it difficult for ratepayers to examine soft costs in any general tariff
applications or deferral account proceedings.
33
Exhibit 9.00, AESO Needs Identification Document, pdf page 15, Section 3.2.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
42 • AUC Decision 2013-369 (October 7, 2013)
171. IPCAA submitted that the Grid Power report made reasonable arguments to support the
Fidler to Langdon proposal and concurred with Grid Power that ratepayers are spending over
$3 billion to install high-voltage direct-current infrastructure into Alberta’s bulk transmission
system which should be put to good use. It argued that the AESO did not appear to be using the
full control capability of these lines to maximize transfer capability.
172. In conclusion, IPCAA recommended that the Commission direct the AESO to conduct a
due diligence of the NID cost estimates provided by AltaLink to gain a clear understanding of
the reasons for the cost reduction in the Windy Flats configuration. Due to the potential cost
savings of $487 million and sufficient time available, IPCAA recommended that the Grid Power
proposal be evaluated by the AESO outside of a regulatory proceeding.
2.2.6 Views of TransCanada Energy Ltd. (TransCanada)
173. TransCanada stated that assuming the AESO will not alter the reliability criteria at an
operational level to address N-2 contingencies, it is generally not opposed to the need
applications. It noted that substantial amount of generation sources need to flow their energy into
the Janet 74S, East Calgary 5S and ENMAX No. 65 substations over a limited number of
transmission lines, most of which are double-circuit. TransCanada examined a N-2 contingency
of the double-circuit 240-kV 985L/1003L line between the Janet and ENMAX No. 25
substations and identified some substantial constraints on the 138-kV transmission system. For
example, the overloads on 138-kV circuits could be as high as 98 per cent. It found that neither
tripping the entire Shepard plant at 850 MW nor shedding load in the southern parts of the
ENMAX system is effective in reducing the 138-kV overloads; it therefore expected the AESO
to address the technical deficiency involving this N-2 event, and to provide a mitigating plan
involving load or generation during the time period between completion of the FATD facilities
until other NID applications are approved and the facilities are completed relative to north
Calgary and the Strathmore/Blackie planning area.
174. TransCanada compared the four mitigation options in the event of a double-circuit outage
between the Janet 74S and ENMAX No. 25 substations proposed by the AESO, and concluded
that among the four options, a circuit swap of the 985L and 1065L lines appears to be the only
option that did not create additional issues with load or generation shedding nor low voltage in
load areas. Mitigation measures such as tripping lines and transformers may not be viable
alternatives because Calgary load continues to grow and southern Alberta generation increases to
meet that demand. Although the Foothills to Sarcee line would eliminate the N-2 contingency by
creating a second path to Calgary and onto points northward, the constructability of the Foothills
to Sarcee line is dependent upon the outcome of the province’s southwest ring-road negotiations,
which are both longstanding and controversial at best. TransCanada reiterated that the circuit
swap represents a similar, effective and viable solution to eliminate the N-2 risk.
175. TransCanada submitted that its Saddlebrook power plant should not be connected to a
lower-voltage transmission system without significant investigation. The studies attached to the
Grid Power report did not offer enough detail for TransCanada to determine whether the
proposed 138-kV system would have sufficient capacity for Saddlebrook output. These studies
were only intended to support Grid Power’s evaluation of options, not a clear recommendation
that the plant be connected to the 138-kV system.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 43
176. TransCanada acknowledged that the primary focus of the FATD was to relieve southern
Alberta transmission constraints, but believed that there was lack of clarity on how the north
Calgary issues would be mitigated until relieved by future transmission development.
TransCanada is supportive of the commitment made by the AESO to include a comprehensive
Calgary area transmission development plan in the long-term plan it has scheduled to be
completed by the end of 2013.
177. TransCanada requested the Commission place the following conditions on the approval
of the FATD NID. The potential for a double-circuit outage between the Janet 74S and
ENMAX No. 25 substations must not result in operational procedures that would require
constraints being imposed on the Saddlebrook power plant. In addition, the potential outage of
these circuits must be resolved by way of a circuit swap or, in the alternative, the AESO must
investigate and implement a solution to the double-circuit outage risk prior to construction of the
FATD facilities.
2.2.7 Views of Ronald and Laurie Conner
178. Ronald and Laurie Conner (the Conners) own lands near the proposed Windy Flats 138S
substation and along the proposed transmission line routes. The Conners submitted that it is not
reasonable nor in the public interest to dispossess them of part of the affected lands and part of
their livelihood by constructing and operating the line and a new Windy Flats 138S substation on
their lands when an upgraded Peigan 59S substation, or the proposed Fidler 312S substation,
would meet the public need in Alberta. They argued that upgrading an existing substation does
not interfere with the private rights of other people to anything like the degree that the
Windy Flats 138S substation would interfere with their private rights.
179. The Conners submitted that the AESO failed to consider technical solutions that follow
existing linear disturbances, as directed by Section 15.1(2) of the Transmission Regulation. They
noted that the AESO is proposing a new, greenfield route for the line including its southern
termination at the Windy Flats 138S substation, which is contrary to the generally-agreed best
practice of following or mirroring the route of existing linear disturbances in the sense of
following the route of the existing 911L line.
180. The Conners submitted that the AESO’s SATR NID amendment is in breach of
Section 15 of the Canadian Charter of Rights and Freedoms because it discriminates between
land and not particular landowners. The indirect effect of the AESO’s recommendation is to
deny benefits and protections to both the Conners and the Piikani First Nation due to their race.
They contend that they would lose the benefits and protection which would result from the
detailed environmental assessment prescribed by the Canadian Environmental Assessment Act
and become subject to a less favourable framework for compensation for lands taken for public
purposes than those which apply under the Indian Act. The Piikani First Nation lose the
opportunity to allow the further use of the reserve lands, already encumbered with electrical
transmission facilities, in return for payments under the Indian Act.
2.2.8 Views of Powerex Corp. (Powerex)
181. Powerex neither supports nor opposes the need application, however it is concerned that
the Alberta-British Columbia intertie capability would be negatively impacted by the proposed
transmission development arising from the SATR NID amendment and the Goose Lake to
Chapel Rock development. It is also concerned that the AESO has proposed transmission plans
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
44 • AUC Decision 2013-369 (October 7, 2013)
without having studied and documented their impact on the Alberta-British Columbia intertie
transfer capability.
182. Powerex submitted that the impact of the SATR NID amendment on the Alberta-British
Columbia intertie was a relevant consideration and should be addressed in the FATD proceeding.
Pursuant to Section 16(1) of the Transmission Regulation, the AESO was directed by the Alberta
government in 2004, to restore the interconnection to its path ratings of 1,200 MW west to east
and 1,000 MW east to west.
183. Powerex stated that any impact the proposed facilities have on the transfer capabilities of
the Alberta-British Columbia interconnection may have direct operational, economic and
efficiency impacts on both the Alberta Interconnected Electric System and the British Columbia
transmission system. Pursuant to Section 38 of the Transmission Regulation, Powerex submitted
that the Commission must have regard for the principle that it is in the public interest to foster a
transmission system that is flexible, reliable and efficient, and preserves options for future
growth, improving transmission system reliability and efficiency.
184. Powertech Labs Inc. (Powertech), on behalf of Powerex, produced nomograms showing
that the British Columbia to Alberta power transfer capability would be increasingly constrained
with the increasing levels of wind generations in the Pincher Creek area. If all of the 349 MW of
wind generation currently installed in the Pincher Creek area operates at maximum output,
Powerex submitted that the British Columbia to Alberta transfers would be restricted to
approximately 925 MW or less as a result of the SATR NID amendment and Chapel Rock
project. Based on the regulatory approvals, Powerex estimated that an additional 466 MW could
be installed by 2015, bringing the total Pincher Creek (Goose Lake) peak wind capacity to
815 MW.34Assuming that all these wind power plants were built by their planned in-service dates
and operated at maximum output, Powerex stated that the British Columbia to Alberta transfers
would be restricted to 600 MW or less.
185. Powertech concluded that British Columbia to Alberta imports are restricted by the 936L
line contingency to 890 MW for the FATD east configuration and 1,015 MW for the FATD east
plus the third-circuit configuration respectively. Powertech added that there may be other more
restrictive contingencies than the 936L line contingency. However, it stated that this spot-check
approach demonstrated at least one contingency that could impact the British Columbia to
Alberta transfers.
186. Powerex agreed with the AESO that the constraints on the transfer capability of the
Alberta-British Columbia intertie can be alleviated by mitigation measures, such as remedial
action schemes and dynamic thermal line ratings. However, Powerex is concerned that if the
implementation measures are not done on a timely basis, there is a risk that the measures will not
be operational in sufficient time to address the identified constraints. In conclusion, Powerex
requested the Commission to place a condition in the approval of the AESO’s SATR NID
amendment, that the AESO implement the necessary mitigation measures no later than the
Chapel Rock project in-service date, to ensure that there is no negative impact to the
British Columbia to Alberta import transfer capability. Alternatively, Powerex requested the
Commission to establish an expedited process to return the application back to the AESO with
the direction that it amend the application to include the implementation of the necessary
34
Exhibit 616.02, Powerex Evidence, page 8, A19.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 45
mitigation measures no later than the Chapel Rock project in-service date, or direct the AESO to
ensure there are no negative impacts to the Alberta-British Columbia intertie capability for all
future NID applications.
2.2.9 Commission findings
187. In Section 2.1.8.1, the Commission found that there is a need to expand or enhance the
transmission system in the southeast Calgary, Okotoks and High River areas. In Section 2.1.8.2,
the Commission confirmed that there continues to be a need to expand or enhance the
transmission system in southern Alberta. In this section, the Commission must evaluate the
AESO’s preferred technical solutions to meet these two identified needs. When evaluating those
applications, Section 38(e) of the Transmission Regulation requires the Commission to decide if
any interested party has demonstrated that the AESO’s assessment of need was technically
deficient or if approval of the FATD NID application and/or the SATR NID amendment would
not be in the public interest.
188. As the Commission understands it, it is IPCAA’s position that the FATD NID application
is technically deficient because it did not include meaningful alternatives to its preferred
technical solutions. Regarding the SATR NID amendment, IPCAA appears to take the position
that its approval is not in the public interest given the cost implications associated with the use of
the Windy Flats configuration versus the Peigan configuration.
189. The Commission understands that it is the position of Phyllis Robertson and the Diagonal
group that it is not in the public interest to approve the FATD NID and the SATR NID
amendment because there are better alternatives available, the Fidler to Langdon and 911L at
138-kV alternatives proposed by Grid Power.
190. Mr. and Mrs. Conner take the position that approval of the SATR NID amendment is not
in the public interest because it is not the best alternative to meet the identified need and because
its approval would breach Section 15 of the Canadian Charter of Rights and Freedoms.
191. Neither TransCanada nor Powerex opposed the approval of the two need applications, but
both asked the Commission to place certain conditions on the approvals it may issue.
192. Given the nature of the issues expressed by interveners with respect to the two need
applications, the Commission’s findings on those applications have been structured as follows.
First, the Commission addresses the issue of whether the FATD NID is technically deficient for
failing to examine and compare alternative technical solutions to meet the need identified.
Second, the Commission assesses the Fidler to Langdon and the 911L at 138-kV alternatives
proposed by Grid Power on behalf of the Diagonal group and Phyllis Robertson. In this
assessment the Commission compares the Grid Power and the AESO alternatives to determine
whether the Grid Power alternatives are superior to those developed by the AESO. Third, the
Commission makes findings specifically with respect to the concerns raised regarding the
Windy Flats substation by Mr. and Mrs. Conner and IPCAA. Finally, the Commission addresses
Powerex and TransCanada’s requests that certain conditions be attached to any NID approvals
issued by the Commission.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
46 • AUC Decision 2013-369 (October 7, 2013)
Is the FATD NID technically deficient for want of alternatives?
193. Section 11(3) of the Transmission Regulation sets out the information that the AESO is to
include in a needs identification document. Subsection 11(3)(f) states:
(3) In addition to the requirements set out in section 34(1) of the Act, the needs
identification document must describe the timing and nature of the need, constraint or
condition affecting or that will affect the operation, efficiency and reliability of the transmission system, including the following:
(f) the options considered for alleviating the constraint or condition;
194. Section 6.1 of AUC Rule 007 provides further information requirements for NID
applications and includes requirements specific to the comparison of transmission alternatives
considered by the AESO to address an identified need. The introduction to Section 6.1 states that
“the information requirements set out below may not be applicable in all cases; they will vary
with the complexity and size of the project”.
195. IPCAA argued that the FATD NID is technically deficient because it does not comply
with Section 11(3)(f) of the Transmission Regulation and Section 6.1 of AUC Rule 007.
Specifically, IPCAA asserted that the AESO failed to examine and compare transmission
development alternatives for the 240-kV components of that project. It also contended that the
three 138-kV alternatives considered by the AESO shared a single significant common element
and no alternatives to that common element were examined or compared.
196. The AESO explained its approach to developing its preferred alternative for 240-kV
transmission development in the FATD NID application. The AESO stated:
In order to minimize land impacts and maximize the efficient use of existing rights-of-
way that would be required to accommodate such 240-kV developments, reconfiguring,
upgrading and/or rebuilding existing transmission lines was preferred over transmission
development options that required distinctly separate new corridors. Furthermore, voltage
conversion from 138-kV to 240-kV was also considered where possible
197. The AESO stated that, having adopted this approach, it did not identify transmission
alternatives for the study that would similarly maximize the opportunities for the transmission
facility owners to use existing infrastructure and rights-of-way.
198. The Commission notes that when considering the location of new transmission facilities
or enhancements or upgrades to existing facilities Section 15.1 of the Transmission Regulation
requires the AESO to consider:
…
(a) wires solutions that reduce or mitigate the right of way, corridor or other route
required, and
(b) maximizing the efficient use of rights of way, corridors or other routes that already
contain or provide for utility or energy infrastructure.35
35
Transmission Regulation, Section 15.1(2).
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 47
199. The Commission finds that the information requirements of Section 11 of the
Transmission Regulation must be read in concert with the directions to the AESO regarding
transmission planning found elsewhere in that regulation, including those in Section 15.1. When
so interpreted, the Commission finds that it is open to the AESO to include only a single
transmission alternative in a NID if it is of the view that there is only one reasonable alternative
that is consistent with the ISO’s transmission planning obligations. Put another way, the
Commission does not believe that Section 11(3) obligates the AESO to develop and compare
transmission alternatives that it does not consider to be reasonable or viable. The Commission
considers that this interpretation is consistent with the flexibility provided in the introduction to
Section 6.1 of AUC Rule 007.
200. In the Commission’s view, the AESO’s decision to not include a discussion of 240-kV
transmission options that required the development of new corridors in the FATD NID was
reasonable, given the presence of existing rights-of-way and transmission infrastructure that was
capable of voltage conversion, and having regard for the population and development density in
the study area. While the Commission considers that it is generally helpful to it and interested
parties to review more than one technical solution to address an identified need, it accepts that in
limited circumstances only a single reasonable alternative will be available.
201. Regarding, the 138-kV upgrades proposed by the AESO, the Commission observes that it
is not uncommon for the AESO to include in a NID several transmission alternatives that share a
common element. If the AESO is of the view that the common element is required regardless of
the various other elements of the technical solutions proposed, then the AESO is obligated, as the
transmission system planner, to include that common element in the technical solutions it
develops and compares. In the Commission’s view, the fact that the three alternatives considered
by the AESO for the 138-kV system, all included a common element does not, on its own, lead
to the conclusion that the FATD NID is technically deficient.
202. Having regard to the foregoing, the Commission is not satisfied that the FATD NID was
technically deficient, as alleged by IPCAA, for non-compliance with Section 11(3) of the
Transmission Regulation.
Is approval of the FATD NID and SATR NID amendments not in the public interest
because the Fidler to Langdon alternative is superior?
Can the Commission consider the Fidler to Langdon alternative?
203. The 240-kV technical solution proposed by Grid Power (i.e. the Fidler to Langdon
alternative) addressed the proposed Windy Flats substation described in the SATR NID
amendment as well as the AESO’s preferred 240-kV technical solution for the FATD NID. The
Fidler to Langdon alternative, which is shown in Figure 5, eliminates the Windy Flats substation
and instead terminates the proposed south Foothills line (i.e. 1037L/1038L line) at Fidler 312S
substation instead of the Windy Flats 138S substation and the proposed north Foothills line (i.e.
1106L/1107L line) at the Langdon 102S substation instead of the ENMAX No. 65 substation.
204. The first issue the Commission must consider when assessing the viability of the Fidler to
Langdon alternative is whether it is consistent with existing NID approvals, including the SATR
NID approval.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
48 • AUC Decision 2013-369 (October 7, 2013)
205. The Commission finds that the proposed Fidler to Langdon alternative is inconsistent
with the SATR NID approval because it proposes to change or eliminate some of the technical
solutions described in that approval. Although the Diagonal group states that it is not attempting
to re-open the SATR NID approval, many of its arguments and the Grid Power report contend
that the need application approved in relation to SATR should be changed. Significantly,
Grid Power proposed to cancel or delay the Goose Lake to Crowsnest (Chapel Rock)
transmission development that was approved in the SATR NID.
206. In Decision 2012-360, the decision on the process meeting for this proceeding, the
Commission advised interested parties that the continued viability of the SATR NID approval
was not an issue it could or should address in this proceeding. The Commission noted at that
time that it had not received an application to review and vary that approval. No party
subsequently sought a review of the SATR NID and the Commission continues to be of the
position that it would be improper to review any elements of the SATR NID approval that is not
specifically subject to the AESO’s application to amend that approval.
207. The Commission finds that recognizing the Fidler to Langdon technical solution
proposed by Grid Power as viable would be tantamount to granting a de facto review of elements
of the SATR NID approval that are not subject to the AESO’s application to amend that
approval. Accordingly, the Commission is of the view that the Fidler to Langdon alternative is
not a technical solution that it should properly consider in this proceeding. However, even if the
Commission were satisfied that it could properly consider the Fidler to Langdon alternative, it is
of the view that the Fidler to Langdon alternative is not demonstrably superior to the AESO’s
technical solution from a technical and costs perspective and is inferior to the AESO’s solution
from an environmental and land-use perspective. The Commission’s reasons for these
conclusions follow.
Comparison of the AESO’s FATD with the Fidler to Langdon alternative
208. One issue that arose at the hearing was the qualification of Mr. Trevor Cline, the author
of the Grid Power evidence and Grid Power’s witness. Before considering the Fidler to Langdon
alternative prepared by Grid Power, the Commission finds it necessary to address the issue of
Mr. Cline’s qualification as an expert witness.
209. The AESO and AltaLink questioned whether Mr. Cline had the necessary knowledge,
experience and expertise to provide expert evidence on matters related to transmission line
costing and routing, including the associated land-use and environmental impacts. The
Diagonal group challenged this assertion and argued that transmission routing and siting is a
subjective exercise that does not require technical or scientific qualification or training.
210. Mr. Cline has previously testified before the Commission. In Decision 2012-303,36 the
Commission recently ruled on Mr. Cline’s qualifications as a routing expert and the weight to
which his evidence on various subjects would be accorded.
With respect to Mr. Cline, the Commission recognizes that while there may be
deficiencies in Mr. Cline’s qualifications with respect to the siting of transmission lines,
those deficiencies go to the weight to be accorded to his expert opinions.
36
Decision 2012-303, ATCO Electric Ltd., Eastern Alberta Transmission Line Project, Proceeding ID No. 1069,
Application No. 1607153 and 1607736, November 15, 2012.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 49
The Commission notes that much of the evidence given by Mr. Cline, which will be more
fully discussed in the relevant sections below, went to issues that he had no qualifications
upon which to rely in giving opinion evidence. Issues such as the impacts of transmission
lines on agricultural operations, the impact of transmission lines on property values, and,
as discussed above, the environmental impacts of transmission lines and the relevance of
environmentally sensitive areas in the siting process are all areas where Mr. Cline strayed
in giving opinion evidence. The Commission finds, as a general statement, the evidence
provided by Mr. Cline in areas where he was clearly not qualified to opine, will be given
the weight of a lay witness rather than the weight of a properly qualified expert in these
areas. Where that evidence diverges from the evidence of a properly qualified expert
witness, the evidence of the qualified expert witness will be preferred.37
211. The evidence before the Commission in this proceeding was that Mr. Cline has not
acquired any further expertise or qualifications in the above-mentioned areas.
212. Having regard to the foregoing, the Commission accepts that Mr. Cline has expertise in
transmission planning. The Commission notes that Mr. Cline was not qualified as a routing or
siting expert, nor was he qualified to give opinion evidence on the impacts of transmission lines
on residences, agriculture or the environment. Accordingly, in this hearing the Commission has
accorded Mr. Cline’s evidence on topics outside of his area of expertise with the same weight
that it would accord to a lay witness.
213. The Commission’s technical comparison of the Fidler to Langdon alternative to the
AESO’s technical solution focused on total transfer capability, reliability and system diversity to
meet future system needs/growth.
214. Regarding total transfer capability, the Commission finds that neither alternative is
demonstrably superior. The Commission’s conclusion on this issue is driven largely by the fact
that the AESO and Grid Power modelled the dispatches of the WATL and EATL high-voltage
direct-current lines differently for post-contingency conditions. The AESO’s model redispatched
the remaining high-voltage direct-current line only if one of the two high-voltage direct-current
lines is out-of-service; whereas Grid Power’s model appeared to adjust the high-voltage
direct-current line flow for other critical outages as well.
215. While Grid Power concluded that employment of the Fidler to Langdon alternative would
result in greater total transfer capability compared to the AESO’s solution, the Commission is
not convinced of its superiority given that the two parties employed a different dispatch
methodology in their modelling. Further, based on the evidence before it, including the fact that
the AESO has not finalized its operational study on high-voltage direct-current line dispatches,
the Commission is not able to conclude that the methodology employed by the AESO was more
or less reasonable than that employed by Grid Power. Accordingly, the Commission is not
convinced that the Fidler to Langdon proposal will provide more transfer capability than the
AESO’s FATD.
216. Having regard to system diversity and reliability, the Commission finds that the Fidler to
Langdon alternative and the AESO’s alternative are substantially the same. For example, in both
the AESO’s alternative and in the Fidler to Langdon alternative there is a six-kilometre stretch
37
Decision 2012-303, pages 26-27, paragraphs 127 and 128.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
50 • AUC Decision 2013-369 (October 7, 2013)
between route marker B280 and Janet 74S substation that will have three double-circuit 240-kV
lines on the same path. Electrical power from WATL, the Alberta-British Columbia intertie,
local gas generation and southern wind generation would flow in this transmission corridor for
both the AESO’s FATD and the Fidler to Langdon alternative. Accordingly, the Commission
does not consider that either alternative is superior from the perspective of reliability.
217. Having regard to its technical comparison of the two alternatives, the Commission finds
that neither alternative is clearly superior from a technical perspective.
218. The Diagonal group emphasized that one of the significant benefits associated with the
Fidler to Langdon alternative was its substantial associated cost savings ($389 million) when
compared to the AESO alternative. The Commission notes that approximately 88 per cent, or
$342 million, of these cost savings are directly attributable to the cancellation of the
Chapel Rock (Crowsnest) project approved in the SATR NID. For the reasons provided above,
the Commission is of the view that a decision by it to eliminate the need for the Chapel Rock
project would be a de facto variance of the SATR NID approval. Accordingly, the Commission
does not consider it reasonable or appropriate to take into account the avoided costs of the
Chapel Rock project, when assessing the economic impacts associated with the Fidler to
Langdon alternative.
219. The remaining cost savings associated with the Fidler to Langdon alternative relate to
Grid Power’s estimated project costs. In the Commission’s view, the project costs estimated by
Grid Power are less reliable than those provided by the AESO, for two reasons.
220. First, the AESO’s cost estimate for the FATD was derived from information provided by
AltaLink, the transmission facility owner, which has considerable experience in siting and
costing transmission lines in the project area. By way of contrast, Mr. Cline was not qualified as
a routing expert in the proceeding and the Commission is not convinced, based on his evidence,
that he had the necessary skills, knowledge and experience to offer a credible opinion on the
high-level costs of the Fidler to Langdon alternative. For example, Mr. Cline speculated in his
evidence that it would be cheaper to build through the Porcupine Hills than across the southern
prairies based on a study that AltaLink completed for a project in northern Alberta. AltaLink
responded to Mr. Cline’s claims and pointed out that not only had Mr. Cline significantly
underestimated the cost of the structures, he failed to take into account the fact that conditions
considered in the AltaLink study were considerably different from the conditions in the
Porcupine Hills. Specifically, AltaLink observed that because of increased wind and ice loading
in the southern Foothills area, it would be necessary to use almost twice as many structures than
would be required in the study area in northern Alberta.38
221. The second and related concern for the Commission is that Grid Power did not
reasonably account for the challenges associated with routing a transmission line across the
terrain proposed in its alternative or the additional costs associated with addressing such
challenges. The Commission notes in this respect Grid Power’s application of the per kilometre
average line cost of the south Foothills project to the Fidler termination on the Fidler to Langdon
alternative. As noted by AltaLink, the terrain associated with the south Foothills project is flat
prairie whereas the proposed Fidler to Langdon alternative would traverse the more complex
terrain of the Porcupine Hills.
38
Transcript, Volume 12, pages 2549-2550.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 51
222. The Commission is of the view that, given the shortcomings identified above, it is
difficult, if not impossible, to reasonably quantify the costs associated with Grid Power’s Fidler
to Langdon alternative. The Commission concludes that given these uncertainties, neither
alternative is superior from a cost perspective.
223. The Commission finds that the AESO’s preferred FATD alternative is clearly superior to
the Fidler to Langdon alternative from the perspective of environmental impacts. In this respect,
the Commission considered evidence on environmental impacts from Mr. Cline, and from
Dr. Gahbauer and Dr. Power, two expert witnesses that are employed by Stantec and were hired
by AltaLink to provide expert evidence with respect to environmental impacts.
224. The Commission gives the evidence on environmental impacts from the Stantec expert
witnesses considerably more weight than that provided by Mr. Cline. The Commission found
their evidence with respect to the environmental effects to be credible, well-informed and
premised on their considerable experience in the area. As noted previously, Mr. Cline was not
qualified to give expert evidence relating to environmental impacts.
225. The Commission finds that routing through the eastern Porcupine Hills presents more
environmental challenges than the south Foothills line route on flat prairie and is convinced by
the expert opinion of Dr. Gahbauer and Dr. Power that the combination of the gradient, climate
and concentration of rough fescue grassland along the Fidler to Langdon alternative would lead
to a high level of environmental disturbance.
226. The Commission observes that the Diagonal group did not present any detailed
information on the environmental impacts of the proposed routing for the preferred south
Foothills line in the vicinity of Mud Lake or the crossing of the Oldman River. The Commission
also accepts AltaLink's submissions that the crossing of dozens of tributaries of the Oldman
River has a higher overall potential for impacts than one crossing of a larger river and that
Mud Lake is not recognized as a significant breeding or staging area for water birds.
227. The Commission also observes that, in the past, there has been substantial opposition to
energy development, including the routing of transmission lines in the Porcupine Hills area. In
previous proceedings on new transmission facilities in that area, the Commission heard from area
landowners and the general public regarding their opposition to the construction of transmission
lines in the Porcupine Hills. While previous opposition to energy development in the Porcupine
Hills does not preclude future development, the Commission does accept that there are a number
of Albertans who have previously expressed a strong desire to preserve this area because of its
unique natural characteristics.
228. The Commission observes that, with respect to the Langdon termination, the residential
impacts are similar between the Fidler to Langdon route and the AESO’s alternative, in terms of
the residences that are newly exposed to transmission lines. While the conceptual Fidler to
Langdon route is shorter, the preferred route requires fewer acres of right-of-way.
229. In the above section, the Commission considered whether an interested party had
demonstrated that approval of the FATD NID and the SATR NID amendments were not in the
public interest because the Fidler to Langdon alternative proposed by the Diagonal group and
supported by IPCAA was a better technical solution than that proposed by the AESO. Having
considered the evidence before it, the Commission has concluded that no interested party met
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
52 • AUC Decision 2013-369 (October 7, 2013)
this test. Specifically, the Commission finds that the Fidler to Langdon alternative is
incompatable with the existing SATR NID approval because it incorporates the elimination of
one of the transmission upgrades described in that approval. Further, the Commission is satisfied,
after comparing the two alternatives from the perspectives of technical capability, costs and
environmental and land-use impacts, that the AESO’s FATD alternative is superior to the Fidler
to Langdon alternative.
Comparison of the 138-kV alternatives
230. The AESO’s proposal for the proposed Foothills 237S substation and associated 138-kV
system development in the High River and Okotoks area is based on its long-term transmission
development strategy for both the local system in High River and Okotoks and the bulk system
in southern Alberta. The AESO intends to serve the load in High River and Okotoks area via a
new 240/138-kV source substation instead of from south Calgary, and to interconnect the
Saddlebrook power plant to the grid via this substation. Grid Power’s 911L at 138-kV proposal,
on the other hand, intends to supply the load in the High River and Okotoks areas via three 138-
kV lines from ENMAX No. 65 substation in south Calgary and one 138-kV line from Janet 74S
substation. Grid Power’s alternative eliminates the need for the Foothills substation.
231. In the following sections the Commission compares the two alternatives from the
perspectives of technical capability, costs and land-use impacts.
232. The Commission is of the view that construction of the proposed Foothills substation in
the area would provide greater future operational flexibility between High River and south
Calgary’s regional systems as compared to the Grid Power proposal. The Commission also
agrees with the AESO that construction of the Foothills substation would also open a potential
connection for the future western component of the full FATD from Foothills to Sarcee
substations. The Commission considers this to be an important consideration due to the physical
constraints that prevent the future expansion of the ENMAX No. 65 substation.
233. The load in the High River planning area was 86 MW at the time of the planning area
summer peak in 2011.39 Based on the AESO’s 2012LTO, the load in the High River planning
area is forecasted to be 114 MW in 2021 at the time of the planning area summer peak. The
average annual load growth rate for the High River area is 2.8 per cent.40 The Commission is of
the view that the High River area is not a load centre large enough to accommodate 350 MW of
local generation to its regional 138-kV system without further investigation and is not convinced
that Grid Power’s 911L at 138-kV proposal would provide a better interconnection option for the
Saddlebrook power plant by connecting it to the low voltage system in the High River area.
234. The AESO’s evidence showed that connecting the Saddlebrook power plant to the
138-kV system, as proposed by Grid Power, would result in reliability criteria violations. The
Grid Power report stated that its suggested 138-kV Saddlebrook interconnection is better than the
240-kV interconnection because it leverages the existence of local generation to improve the
reliability for the local load supply; however, Grid Power provided no technical evidence to
support this contention. The Commission finds that connecting the Saddlebrook power plant to
the local 138-kV system in High River as suggested by Grid Power, would likely result in higher
39
Exhibit 10.00, Appendix F AESO 2012 Supplement to Load and Generation Forecast, pdf page 1005,
Table 1: 2012 LTO Summer Load at Planning Area Peak. 40
Exhibit 10.00, Appendix F, AESO 2012 supplement to load and generation forecast, pdf page 1005.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 53
system losses and the need to immediately rebuild approximately 21 kilometres of the existing
727L line.
235. Grid Power stated that its 911L at 138-kV proposal would only cost $2.5 million and
result in a total saving of $98.3 million, including both the savings from the future Big Rock
project and the cancellation of the AESO Foothills 138-kV proposal. As noted previously in this
report, it is the Commission’s view that it would be improper for it to take into account cost
savings that are premised upon foregoing other AESO projects.
236. The AESO estimated that Grid Power’s 911L at 138-kV proposal would cost $60 million
with -40/+80% accuracy, as opposed to $82 million for its Foothills 138-kV proposal based on a
-10%/+20% accuracy. The AESO’s present value analysis indicated that the cost of its proposal
would be in the range of $13 million to $45 million more than Grid Power’s proposal based on
the uncertainty ranges associated with each of the cost estimates.
237. The Commission prefers the AESO’s cost evidence over that provided by Grid Power. As
noted earlier, the Commission is not satisfied that Mr. Cline possesses the necessary skills,
knowledge or experience to provide expert opinion evidence on the costs associated with
transmission upgrades. Regardless of the Commission’s concerns about the Grid Power
estimates, it appears to the Commission that Grid Power’s 911L at 138-kV proposal would have
a lower cost than the AESO’s 138-kV alternative. However, due to the wide range of uncertainty
of these cost estimates (-40/+80%), the magnitude of potential cost benefits associated with
Grid Power’s proposal is not certain.
238. The Commission is of the view that neither alternative is superior to the other from the
perspective of land-use impacts and observes, in this respect, that the AESO’s proposal would
require approximately 14 kilometres of new double-circuit line and seven kilometres of the 727L
line between High River 65S and Magcan 142S substations to be rebuilt while removing
approximately 21 kilometres of the existing 727L line between the Janet 74S and Okotoks 678S
substations. By way of contrast, the Grid Power’s 911L at 138-kV proposal would require
approximately 21 kilometres of the existing 727L line to be rebuilt in order to interconnect the
Saddlebrook power plant. Further, the Grid Power proposal would limit the opportunity to
expand the 138-kV development at the ENMAX No. 65 substation in the future due to its
proximity to the highway and the ring road.
239. The Commission finds that the AESO’s Foothills 138-kV development plan would
provide better operational flexibility and long-term supply security for the High River area than
Grid Power’s 911L at 138-kV proposal, and that building the new Foothills substation would
allow for the bulk system development in southern Alberta and local generation interconnection.
In the Commission’s view, these technical considerations outweigh the cost and land-use
implications in developing the Foothills 138-kV plan.
240. Having regard to the foregoing, the Commission finds that the AESO's Foothills 138-kV
development plan is superior to the Grid Power 911L at 138-kV proposal. Accordingly, the
Commission concludes that no interested party has demonstrated that the AESO’s 138-kV
preferred technical solution was technically deficient or that its approval is not in the public
interest.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
54 • AUC Decision 2013-369 (October 7, 2013)
The SATR NID amendment and the Windy Flats substation
241. Two interveners argued that approval of the SATR NID amendment was technically
deficient and not in the public interest: Ronald and Laurie Conner, and IPCAA.
242. The Conners take the position that the SATR NID amendment is technically deficient
because the AESO failed to propose a technical solution that follows existing linear disturbances.
As noted earlier, the ISO has numerous statutory obligations associated with its function as the
transmission system planner. While the AESO must consider maximizing the use of efficient
rights-of-way, corridors, or other routes that already contain or provide for utility infrastructure,
this obligation must be read in concert with its other planning obligations as set out in the
Electric Utilities Act and the Transmission Regulation. Specifically, the AESO must plan a
system that satisfies reliability requirements and is sufficiently robust so that 100 per cent of the
time, transmission of all anticipated in-merit electric energy can occur when all transmission
facilities are in-service and, under normal operating conditions, can be dispatched without
constraint.
243. The Commission accepts the AESO’s evidence that the driver for the SATR NID
amendment (i.e. the Windy Flats configuration) is existing constraints on the 911L line and the
prospect of increasing critical constraints on that line starting in 2014, which will increasingly
constrain market participants in southern Alberta if not addressed in the near term. As noted in
Section 2.1.8 above, the Commission is of the view that the AESO has verified and confirmed
the FATD need by performing power system analyses that shows the existing transmission
system will create a “bottleneck” for the transmission of increasing wind generation to Calgary
by 2014. The Commission also finds that the urgency of the need is further supported by the
current constraints on the southern Alberta transmission system: constraints on the existing 911L
line and those experienced by TransAlta at its Ardenville, Blue Trail and Soderglen wind power
plants.
244. The Commission agrees with the AESO that the construction milestone for the 911L line
rebuild in the SATR NID approval has been met. The Commission is also persuaded that without
the FATD, the current and future wind generation will not be able to fully produce power at their
rated MW capacity and it accepts that pursuing the original Peigan configuration would result in
an 18- to 30- month delay and would not meet the in-service date of the 911L line rebuild. The
Commission finds that mitigation measures, such as remedial action schemes, to alleviate the
existing transmission system constraints under normal system operations are not viable
transmission planning solutions, and that it is not in the public interest to delay the 911L line
rebuild and hinder the market participants’ timely access to the transmission system.
245. Given the constraints identified by the AESO and the relative urgency to address these
constraints, the Commission considers that the AESO’s decision to pursue an alternative that
does not follow an existing disturbance or right-of-way for a small portion of the 120-kilometre
long line was reasonable in the circumstances and does not represent a technical deficiency.
246. The Conners also argue that it is not in the public interest because it breaches Section 15
of the Canadian Charter of Rights and Freedoms. A person who alleges a breach of Section 15
must show discrimination "in the sense that it denies human dignity or treats people as less
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 55
worthy".41 The Conners submitted no evidence of such discrimination and, in the Commission’s
view, it would not be reasonable to draw such a conclusion from any other evidence filed in this
proceeding.
247. Further, the Commission finds that there is no basis for the argument that the SATR NID
amendment has the effect of discriminating against the Conners or the Piikani First Nation due to
their race. The Commission is satisfied that the reason for the change in the substation location is
due to the potential for delay associated with the Peigan substation upgrades on federal lands
which poses scheduling implications and risks that are unacceptable to the AESO as the
transmission system planner. In the Commission’s view, the fact that the process for acquiring
access to federal lands is different than the process for acquiring access to lands that are subject
to provincial jurisdiction has nothing to do with the race of either the Conners or the Piikani First
Nation. Rather, the Commission considers that the existence of different regulatory approval
regimes for federal and provincial lands simply reflects the division of powers set out in sections
91 and 92 of the Canadian Constitution.42
248. Accordingly, the Commission finds that the Conners have not shown that a breach of
Section 15 of the Canadian Charter of Rights and Freedoms exists or that approval of the SATR
NID amendment is not in the public interest.
249. IPCAA argued that approval of the SATR NID application is not in the public interest
because the AESO failed to take into account the cost implications associated with the upgrade.
250. The Commission finds this argument to be without merit. In the Commission’s view the
AESO took reasonable steps to estimate the costs associated with the proposed SATR NID
amendment. As noted above, the Commission is satisfied that the AESO fulfilled its statutory
planning obligations when it proposed the amendment to address impending constraints on the
southern Alberta system.
251. Neither Powerex nor TransCanada took a position on whether the Commission should
approve the FATD NID and SATR NID amendment. However, both companies asked the
Commission to place conditions on any approval that the Commission might issue.
252. Powerex requested the Commission to condition its approval of the SATR NID
amendment by requiring the AESO to implement mitigation measures to address constraints on
the transfer capability of the Alberta-British Columbia intertie.
253. The Commission asked Powerex to produce a new nomogram in order to determine the
transfer capability of the 815 MW wind generation in the Pincher Creek area assuming the
Chapel Rock project is not yet in-service. The new nomogram submitted by Powerex eliminates
the nomogram interaction between British Columbia to Alberta transfers and Pincher Creek wind
generation output assuming the implementation of mitigations measures. Powerex submitted
that, as a result, the British Columbia to Alberta transfer capability would be limited to the
Western Electricity Ccoordinating Council path rating of 1,200 MW west to east flow for
815 MW of wind generation in the Pincher Creek area. Powerex is not objecting to the two need
applications nor did it argue that the need applications are technically deficient.
41
Gosselin v. Quebec (Attorney General) [2002] 4 S.C.R. 429, paragraph 17,. See also Canadian Foundation for
Children, Youth and the Law v. Canada [2004] 1 SCR 76 at paragraph 53. 42
P. Hogg , Constitutional Law of Canada, paragraphs 55-57.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
56 • AUC Decision 2013-369 (October 7, 2013)
254. The AESO has confirmed that it will address mitigation measures and the timing for
implementing these measures as part of the intertie restoration program. In the Commission’s
view, the conditions requested by Powerex are of an operational nature and do not arise from the
need application. Consequently, the Commission denies Powerex’s request for conditions to the
approval for the Windy Flats SATR NID amendment.
255. TransCanada requested the Commission to condition its approval of the FATD NID
application by including measures to avoid constraints being imposed upon its Saddlebrook
power plant under certain contingency conditions.
256. The Commission observes that the AESO investigated different mitigation measures to
resolve the N-2 contingency described by TransCanada. Further, the AESO committed to
develop mitigation measures to address all category C5 events that may exist in a timely manner.
Given this commitment, the Commission is of the view that no conditions are required to be
attached to the FATD NID approval.
257. In conclusion, Section 38 of the Transmission Regulation instructs the Commission on
the factors that it must consider when considering a need application filed by the AESO.
258. The Commission is satisfied that the public interest criteria set out in subsection 38(a) of
the Transmission Regulation are met. Reliable electrical transmission facility infrastructure is a
prerequisite to having an efficient and competitive generation market. The AESO has identified
the constraints of the existing transmission system and studied the performance of the proposed
alternative under forecasted load and generation scenarios and different system conditions.
259. The Commission is satisfied that the AESO’s proposed FATD will provide a reliable and
efficient transmission system which also has the flexibility for the future load growth and
transmission expansion. The proposed FATD facilities use land efficiently because the
development aims to maximize the use of existing rights-of-way, upgrading and rebuilding the
existing transmission lines.
260. The Commission is satisfied that the criteria set out in subsection 38(b) the
Transmission Regulation are met. The AESO’s proposed FATD will enhance system reliability,
efficiency and operational flexibility, which will consequently promote a robust competitive
electric market. In this application, concerns about reliability, system efficiency and operational
flexibility are met by means of new 240-kV substations, new transmission lines, new reactive
power compensation devices, the voltage conversion of the existing transmission lines and
discontinuing operation of some existing transmission facilities. The Commission is satisfied that
the proposed FATD will provide system capacity to meet the forecasted load and generation until
2019, and that the proposed transmission enforcement also preserves options for the long-term
plan of the transmission system in the project area beyond 2019.
261. The Commission has reviewed the need applications together with references in the
AESO’s 2012 Long-term Transmission Plan and is satisfied that the need applications and the
long-term plan are consistent. It also finds that this application is reflective of the AESO’s
responsibilities; in particular, its responsibility to plan the capability of the transmission system
to meet the current and future needs of market participants and plan a transmission system that
satisfies reliability standards. The criteria set out in subsections 38(c) and (d) of the
Transmission Regulation are also met.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 57
262. With regard to subsection 38(e) of the Transmission Regulation, none of the interested
parties has satisfied the Commission that the AESO’s assessment of the need to expand the
transmission system in the southeast Calgary, Okotoks, High River, Nanton, Stavely,
Claresholm, Granum and Fort Macleod areas to meet load growth, address congestion, improve
system reliability and allow for the interconnection of future generation in the region is
technically deficient or not in the public interest.
263. Interveners did not take issue with the AESO’s participant involvement program. The
Commission finds that the AESO’s participant involvement program met the requirements of
AUC Rule 007. Further, the AESO applications met the technical requirements set out in
AUC Rule 007.
264. Having regard to all of the foregoing, the need applications and the preferred alternatives
are approved as filed by the AESO. In coming to this decision, the Commission had specific
regard for the evidence and argument of the parties, and the clear direction provided in
subsections 38(a) through (e) of the Transmission Regulation.
265. Finally, the Commission is compelled to comment on the uncivil and accusatory
submissions in Benign Energy's argument and reply. The Commission considers that such
submissions are unacceptable and unwarranted in this, or in any proceeding. Each party is
entitled to make its case before the Commission; no party should be the subject of personal
attack and invective. The Commission took no note of such submissions.
3 Criteria and route siting principles
3.1 AltaLink’s routing methodology
266. AltaLink stated that its objective during the route determination of the facility
applications was to identify one or more routes with lowest overall impact, having regard for
potential agricultural, residential, and environmental impacts, project costs, electrical
considerations, potential visual impacts and special constraints.43 In determining these routes,
AltaLink reviewed environmental and land-use data, considered feedback garnered from a broad
range of stakeholders over the course of its participant involvement program, and relied on its
siting experience and judgement.
267. AltaLink described its routing methodology as a “funnelling process” which
progressively refined the potential routes while more detailed information was gathered and
analyzed. Through this process, less desirable routing alternatives were eliminated until the
routes with the least overall impacts were identified. First, at the conceptual stage, AltaLink
identified potential land related impacts to assist the AESO in determining the best technical
solution for the project. Second, in the preliminary siting stage, AltaLink defined an appropriate
study area, identified major siting constraints within that study area, and then identified workable
preliminary routes. Third, in the detailed siting stage, based on feedback from the first round of
consultation, it further refined the routes, defined them in more detail, and decided upon a
preferred and an alternate route. Fourth, in the final siting stage, detailed routes were presented to
stakeholders on those routes for their input in the second round of AltaLink’s participant
involvement program. Based on the input from stakeholders, these routes were refined further
43
Exhibit 348.00, page 45, paragraph 208.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
58 • AUC Decision 2013-369 (October 7, 2013)
into the final proposed preferred and alternate route segments, applied for in the applications.
The specifics of AltaLink’s applications in this proceeding are set out below.
3.1.1 Preliminary siting stage
268. The study areas for the project developed to assist the AESO in determining the best
technical solution were further developed in the preliminary siting stage.
269. The study area for the north Foothills project consisted of Township Road 184 to the
south, the quarterline adjacent to Range Road 270 to the east, the quarter section line north of
Highway 22X to the north and Range Road 10 to the west. AltaLink stated that the areas beyond
these boundaries would not provide route options with lower impacts or cost.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 59
Figure 9 – North Foothills project Study Area (with Preliminary Routes)44
44
Exhibit 13.00, page 58. Figure 4-2 Study Area (with Preliminary Routes).
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
60 • AUC Decision 2013-369 (October 7, 2013)
270. AltaLink explained that paralleling existing transmission lines was considered in
developing preliminary routes for the north Foothills project. Within the study area, paralleling
existing transmission lines 1201L, 850L, and 911L was viewed as having potential for lower
overall impacts. Transmission line 1201L runs predominately north-south from the Frank Lake
area to Langdon and is sited through agricultural lands. As the line has been in place since 1985,
agricultural practices have evolved around the transmission line. AltaLink stated that while the
850L line runs diagonal through quarter sections, the line has been in place since 1953 and land
use has developed with the transmission line in place. Where the 850L line switches to a north-
south alignment, it joins up with 911L line, providing another potential site to parallel.
271. For the south Foothills project, the study area was modified to ensure it supported the
AESO NID and a review of the land use and residential densities in the area was conducted. The
study area boundaries for the south Foothills project are Township 7, parallel to 967L/968L line
to the south, the section lines at Range 24 of the Fourth Meridian to the east, the Bow River
valley to the north and the lower slopes of the eastern side of the Porcupine Hills to the west.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 61
Figure 10 – South Foothills project study area (with preliminary routes)45
45
Exhibit 348.00, page 49. Figure 4-2 Study Area (with preliminary routes).
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
62 • AUC Decision 2013-369 (October 7, 2013)
272. The AESO NID identified the proposed 1037L/1038L line as a replacement of the
existing 911L line. The existing 911L line right-of-way could not be repurposed for the new
transmission line because the 911L line cannot be de-energized prior to the new lines being in-
service. As a result, a new right-of-way is required. While the existing right-of-way could not be
used, AltaLink stated a route that parallels the 911L line was identified as an option that would
have a low overall impact. AltaLink stated that after the project is constructed and the 911L line
is removed, there would be a 40-metre shift in the routing, where the line parallels the 911L line.
273. The study area boundaries for the Langdon to Janet project are Township Road 230 to the
south, the section lines at Range 24 west of the Fourth Meridian to the east, Township Road 260
to the north, and the transportation and utility corridor in Calgary to the west.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 63
Figure 11 – Langdon to Janet study area (with preliminary routes)46
46
Exhibit 90.00, page 55. Figure 4-2 Study Area (with Preliminary Routes).
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
64 • AUC Decision 2013-369 (October 7, 2013)
274. AltaLink stated that paralleling of existing transmission lines, use of existing AltaLink-
owned rights-of-way and lands previously used for a railway were considered in developing
preliminary routes.
275. For the 138-kV project, AltaLink identified areas and transmission lines that could be
reused, rebuilt, relocated or salvaged, adding that the re-use of existing lines or rights-of-way is
generally considered to be of lower impact than greenfield routes. Subsequent to the construction
of the proposed transmission lines in the various applications, the 911L line would be available
for reuse or salvage. The AESO functional specification identified the reuse of a segment of the
existing 911L line from the Okotoks 678S substation as an option to complete the 850L circuit to
the Carseland 525S substation. The AESO functional specification also identified a segment of
the 911L line from the Okotoks 678S substation south to the Foothills 237S substation as an
option to reuse at 138-kV between the Foothills 237S substation and Okotoks 678S substation.
AltaLink identified 727L and 727AL lines as transmission lines that could be reused or the
right-of-way re-purposed. The AESO has identified that a segment of the existing 727L line
could be utilized for the connection of the 850L line from Carseland 525S substation to the
Okotoks 678S substation. AltaLink stated that lines 727L and 727AL could be used as double-
circuit lines to reduce impacts.
276. AltaLink also investigated rebuilding the 753L line as a double-circuit line and
converting a portion of the 850L line from 138-kV to 240-kV as options in reducing impacts.
277. The study area for the Foothills 138-kV project was confined due to the use of existing
transmission lines. For areas where greenfield development may occur, AltaLink considered a
study area with the northern boundary following a quarterline south of 338th Avenue, the eastern
boundary located approximately 1.6 kilometres east of the 1201L line, the southern boundary at
562nd Avenue, and the western boundary east of 40th Street and 48th Street in Okotoks.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 65
Figure 12 – 138-kV study area in the High River – Okotoks area47
47
Exhibit 213.00, page 64. Figure 4-3 Study Area for Components A and B.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
66 • AUC Decision 2013-369 (October 7, 2013)
278. The study area for development between Okotoks and Calgary followed existing
transmission lines 727L, 911L and 850L.
279. To determine potential routes, AltaLink conducted a quarterline analysis. It viewed siting
transmission line on quarterlines of cultivated fields as a low-impact option. Once the
quarterlines in the study area were established, AltaLink reviewed no-go areas. Examples of
no-go areas are urban areas and high-density country residential areas, airport constraint areas,
public road allowances, parks and protected areas, major water bodies and provincial historic
sites. AltaLink’s quarterline analysis then removed quarter sections with residences within
150 metres from the quarterline; gas and oil wells within 50 metres of the quarterline; quarter
sections with residences within 800 metres of the quarterline; and quarterlines that cross lands
identified by the province as environmentally significant areas. After the removal of the no-go
areas in AltaLink’s quarterline analysis, AltaLink explained that there were no continuous
quarterline segments that connected the north study area to the south. As a result, AltaLink began
re-introducing quarterline segments previously removed due to the proximity of oil and gas
wells, residences within 150 metres and 800 metres, and environmentally significant areas.
3.1.1.1 Preliminary routings
280. Based on its quarterline analysis, AltaLink created preliminary routes for consultation.
For the north Foothills project, AltaLink developed preliminary routes north and south of the
Bow River. South of the Bow River, it developed two routes, one which paralleled the 1201L
line and one primarily greenfield route along quarterlines west of line1201L. AltaLink stated a
crossover route was identified, allowing for a combination of these two routes. To the north of
the Bow River, a number of preliminary routes were identified following quarterlines and
paralleling or replacing transmission lines. It also identified three target areas for the Foothills
237S substation.
281. For the south Foothills project, AltaLink explored the paralleling of existing and planned
future linear disturbances such as highways, irrigation canals and rail lines. The potential to
parallel a planned highway bypass east of the town of Claresholm provided AltaLink with an
opportunity to avoid the town.
282. AltaLink created three preliminary routes for consultation with stakeholders. The west
route primarily paralleled the 911L line, included an option to follow the highway bypass to the
east of the town of Claresholm and included an option to utilize a connector to cross over to the
quarterline south of Frank Lake. A central option was developed which originated southwest of
Fort Mcleod crossing the Oldman River and included an option to utilize a connector to cross
over to the 911L line parallel route northwards on quarterlines. An east route was developed
running east of Fort Mcleod crossing the Oldman River and continuing north to the edge of
Vulcan county.
283. For the Langdon to Janet project, AltaLink stated that the typical quarterline greenfield
routing was limited due to the relatively dense development in the area. AltaLink developed two
preliminary routes, one that paralleled the existing 936L/937L line and utilized AltaLink’s
existing right-of-way and a greenfield option that would parallel the Western Alberta
Transmission Line, Highway 560 and a potential irrigation canal.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 67
284. For the new build portion of the Foothill 138-kV project, from the Foothills 237S
substation to the High River 65S substation and Okotoks 678S substation, AltaLink determined
that a double-circuit transmission line out of the Foothills 237S substation would be the best
option, to minimize impacts and land fragmentation. AltaLink developed preliminary routes that
paralleled existing transmission lines, highways as well as routes sited on quarterlines.
Figure 13 – Preliminary routes for the 434L/646L line48
285. For the remainder of the route to the Okotoks 678S substation, AltaLink proposed a
combination of a rebuild of the 727L line, reusing a portion of the 911L line and a short segment
of new transmission line.
48
Exhibit 213.00, page 73. Figure 4-9 Component A – Preliminary Routes for the 434L/646L Line.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
68 • AUC Decision 2013-369 (October 7, 2013)
Figure 14 – Component B – proposed routing for the 646L Line49
49
Exhibit 213.00, page 74. Figure 4-10 Component B – Proposed routing for the 646L Line.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 69
286. For the components of the Foothills 138-kV project from the Okotoks 678S substation to
the Carseland 525S substation, AltaLink assessed reusing the 727L or 911L lines, but selected
the 911L line because it had fewer residences within 150 metres, had newer and more suitable
structures, and required no additional right-of way. The reuse of 911L line would require that the
voltage be reduced to 138 kV.
287. For the remaining components, AltaLink proposed that a portion of the 850L line be
increased from 138-kV to 240-kV, from ENMAX No. 65 substation to ENMAX No. 25
substation and the salvage of the 727L line between Janet 74S substation and Okotoks 678S
substation. AltaLink stated that there would be minimal visual change to the portion of the 850L
line that is being energized at a higher voltage and no new right-of-way required. Portions of the
salvaged 727L line would still contain FortisAlberta’s single-phase distribution lines underbuilt
on to the poles.
3.1.2 Detailed siting stage
288. During the detailed siting stage, AltaLink utilized feedback from the first round of
consultation and additional data to continue to refine the preliminary routes and identify a
preferred and alternate route. Examples of typical siting-related stakeholder feedback included:
identification of current agricultural practices, including aerial spray programs
identification of relevant area structure plans and development plans
identification of current and future land uses
identification of newly expanded road allowances
constraints around the river crossing locations
preferences for structure locations
identification of other potential route segment alternatives (e.g., along road allowances)
289. In addition to the stakeholder feedback, AltaLink considered the following additional
data:
from preliminary engineering and indicative tower spotting
on historical resources
from field collected environmental data sets (e.g., rare plants, raptor nests)
from updates to existing data sets (e.g., oil and gas wells)
290. For the north Foothills project south of the Bow River, refinements were made around
Frank Lake. AltaLink heard two competing views, one to have the route away from the highway
as south as possible to minimize development impacts, and one to have the route as north as
possible to have a greater distance from Frank Lake. AltaLink developed a mid-quarter route to
balance these views. AltaLink also made refinements on the west preliminary route, removing a
Bow River crossing location from consideration because several towers would be located within
a flood plain and hogback. AltaLink eventually removed the west route from consideration after
consulting with the landowners because additional turns and jogs were required, resulting in
higher agricultural impact and cost. It developed a new route between the west route and the
route paralleling the 1201L line.
291. To the north of the Bow River, the route parallel to the 850L line was refined to match
tower structure placement and to avoid residences. The greenfield preliminary option was shifted
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
70 • AUC Decision 2013-369 (October 7, 2013)
further from Highway 22X to allow for future highway expansion. AltaLink stated that the
preliminary route paralleling the 950L/911L line required an additional eight metres of
permanent right-of-way and 50 metres of temporary right-of-way to accommodate the line.
292. AltaLink stated it considered parcel suitability and impacts of the substation footprint,
interconnection of proposed and future 500 kV and 240 kV transmission lines, 138-kV
connections to High River and Okotoks and 240-kV interconnection of local generation to
determine the site for the Foothills 237S substation. It assessed sites for potential impact on
agriculture, residences, and the environment; electrical reliability; cost; and space for future
expansion of the substation. Preference was given to sites adjacent to the 1201L line, to reduce
cost and impacts to connect the 1201L line to the substation. AltaLink also required a site that
could provide 138-kV interconnections to High River and Okotoks. Lastly, sites close to the
911L line were considered. AltaLink stated that at the commencement of the FATD project, the
911L line would be decommissioned and a portion of the line could potentially be re-purposed to
interconnect local generation, such as TransCanada’s Saddlebrook power plant. It identified
three sites, designated as D8, D12 and C215, as potential substation locations.
Figure 15 – Substation target areas50
50
Exhibit 13.00, page 92. Figure 4-27 Preferred and Alternate Routes with Substation Target Areas.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 71
293. The D8 site was selected because it provided the best opportunity to reuse existing
infrastructure to connect local generation in the future, provided low local impacts and had few
impediments to the connection of future 240 kV and 500 kV lines. The D12 site was eliminated
because it would result in higher impacts for future interconnections for local generation. The
D12 site required a longer 240-kV line to connect the 911L line, which AltaLink envisioned
could be reused for future local generation interconnection. The D12 site was also less centrally
located in the southern study area and would provide less flexibility for future routing options.
294. AltaLink also rejected the C215 site as it would result in the greatest impacts for future
connections. Like the D12 site, the C215 site is less centrally located in the southern study area,
and development to the west near High River, Aldersyde and Okotoks would limit the potential
for future transmission lines. This site would also require a longer length of 240-kV lines to
connect with the 911L line. AltaLink also stated that the 138-kV connections to High River and
Okotoks would have the highest potential for residential impacts and would require a less
favourable river crossing.
295. For the north Foothills project, AltaLink selected the parallel 1201L line option as the
preferred route, with three optional routing segments around Frank Lake, the central diagonal
portion, and Highway 22X. Around Frank Lake, the preferred routing is situated west and north
of the lake. AltaLink also created a preferred variant route that parallels the 1201L line across the
lake. An alternate route was also developed which completely bypasses Frank Lake and its
associated environmentally significant area. The alternate route is sited on quarterlines before
realigning with the preferred route, parallel to the 1201L line.
296. AltaLink created a central alternate route sited on quarterlines as opposed to being
parallel to the 850L line. AltaLink stated the alternate route is long and has a greater number of
residences within 800 metres, but would not be sited diagonally across fields.
297. AltaLink created the Highway 22X alternate route as an option from paralleling the 850L
line in a diagonal configuration. This alternate route would travel north on the quarterline to
Highway 22X and then travel west into the city of Calgary to terminate at the ENMAX No. 65
substation. AltaLink stated this alternate route is longer, has more residences within 800 metres,
has the potential to impact future development, and does not have the opportunity to reuse
existing rights-of-way.
298. AltaLink rejected the remaining preliminary routes when selecting the preferred and
alternate routes.
299. For the south Foothills project, approximately 40 local refinements were made during the
detailed siting stage. For the west route, after considering feedback from landowners and the
town planner, AltaLink added that it refined the routing to follow the highway bypass and the
town of Claresholm to the east, instead of parallel to the 911L line to the west of the town. As
well, the route was adjusted to follow a secondary highway being developed north of High River
at the suggestion of the Town of High River, M.D. of Foothills and other stakeholders. The
adjustment reduced residential and land-use impacts. AltaLink also shifted the routing at the
northern end west of the Highway 2 crossing to reduce residential impacts and one tower on the
911L line was removed from the centre of a field to facilitate the spanning of the field by the
new line.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
72 • AUC Decision 2013-369 (October 7, 2013)
300. Refinements to the central route were made to take into account a landowner’s cultivation
practices, to reduce residential impacts, and to take into account wetland data. Near the
Windy Flats 138S substation location, the line was shifted five kilometres to the west, resulting
in a 2.5-kilometre reduction in length, a reduction in cost and fewer agricultural impacts. Other
adjustments and jogs were incorporated to reduce impacts on gravel extraction, agriculture and
irrigation, and to avoid surface water.
301. On the east route, adjustments were made to take into account cultivation practices,
preferences to reduce residential impacts, and to take into account wetland data. At the south
end, the line was shifted west of the quarterline to align with a steep side slope. North of
Highway 3, the route was shifted to a diagonal routing at the landowner’s request to reduce
residential impacts, cost and length. Shifts were also created to avoid irrigation, align with
cultivation and agricultural practices, and avoid surface water.
302. AltaLink identified the west route as the preferred route, the central route as the alternate
route and rejected the east route. AltaLink stated that the preferred route presented the lowest
overall impact compared to the other routes. A driving factor for developing the preferred route
was paralleling the 911L line. It added that the 911L line has been in-service since 1964 and
local land use has evolved around the presence of the line. The SATR NID approval also directs
the salvage and removal of the 911L line which would result in a lower incremental impact. The
preferred route would parallel the 911L line for 70 kilometres (59 per cent of its length). While
the preferred route has more residences within 800 metres, it has the fewest residences within
800 metres where it is not in parallel with the existing 911L line. The preferred route also crosses
the fewest kilometres of cultivated lands, has the least potential impact on environmental features
and interactions, parallels the most existing and planned future developments, is the shortest
route and has the lowest cost.
303. AltaLink selected the central route as the alternate route. The alternate route is primarily
a greenfield route situated primarily on quarterlines to reduce potential impacts. When compared
to the east route, the alternate route has a lower potential impact on cultivated land, avoids
potential impacts on parcels bordered on two sides by transmission lines, has a lower number of
raptor nests and observations of species of concern within 800 metres of the right-of-way,
follows more quarterlines that are not in close proximity to existing transmission lines, is shorter,
and is less costly.
304. The east route was rejected because it has greater potential agricultural impacts, higher
numbers of species of concern and raptor nests within 800 metres of the right-of-way, has more
potential for agricultural and residential impacts, crosses the Little Bow River at a crossing
identified as a higher risk with respect to historical resources, and is longer. AltaLink stated that
the new line and existing 138-kV transmission line would be half a mile apart for 39 kilometres,
which has the potential to impact agricultural practices and residences.
305. AltaLink also rejected three route segments in creating the preferred and alternate routes.
A route segment from the High River area to the Aldersyde area was rejected because it had
more potential residential and agricultural impacts, additional river crossings, and was a longer
length. The route segment to the west of Claresholm paralleling the 911L line was also rejected.
It stated that while the option to the east, parallel to the future highway bypass, is more
expensive, it has a lower overall impact, adding that this routing aligns with the town’s
municipal development plan and Alberta Transportation’s future plans. AltaLink also stated that
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 73
the move to the east side of town also has a lower potential for residential and agricultural
impacts; there are no residences within 150 metres and 26 first-row residences within 800 metres
of the alignment to the east side of town. To the west of town, there are two residences within
150 metres and 65 residences within 800 metres. AltaLink also removed the route segment into
the Peigan 59S substation because of the proposed SATR NID amendment, removing the Peigan
substation as a potential termination point for the project.
306. AltaLink created four new route segments, connecting the preferred and alternate routes
to create additional route option combinations.
307. For the Langdon to Janet project, the route paralleling the 936L/937L line was
determined to be the preferred route. AltaLink stated that while this route has more residences
within 150 and 800 metres, the overall land-use impacts were lower because it follows existing
linear developments, minimizing fragmentation. The preferred route was further refined from the
preliminary route. The deflection point to cross a double-circuit 240-kV transmission line was
moved to the east to accommodate existing and planned development. The route was further
refined as it approached Langdon 102S substation to utilize the same alignment currently being
utilized by the 936L/937L line. The existing 936L/937L line would then be re-located to the
north side of the new 1064L/1065L line. This refinement moved the existing and new
transmission lines from crossing a parcel diagonally near a residence. AltaLink also created a
variant route option, where the transmission line would continue to run along the old CP Rail
right-of-way to Range Road 274, just north of the Langdon 102S substation. This variant option
has the potential to reduce land-use impacts but would place the transmission line closer to
residences. Another refinement was an offset to the south boundary of the CP Rail parcel after
CP Rail raised concerns regarding potential electrical effects on future rail lines.
308. AltaLink selected the greenfield preliminary route as the alternate route, which primarily
follows quarterlines and has fewer residences within 150 and 800 metres. It applied refinements
to the preliminary route, attempting to align the transmission line with a future stormwater
conveyance system in the area and an existing railway.
309. AltaLink implemented refinements to various components of the Foothills 138-kV
program. The 434L/646L line was relocated from the north side of Highway 23 to the south side
to increase distance from a residence and the route was altered near Highway 2 and
498th Avenue to accommodate an interchange. AltaLink also proposed to terminate both lines
727L and 464L at the High River 65S substation, but determined there was not enough room to
accommodate both lines in that configuration. As a result, it proposed to terminate the 753L line
into a new bay, to free up its existing bay for the new circuit. A number of small refinements
were also implemented to improve clearance and avoid pipelines.
310. AltaLink selected the preliminary route by Highway 543 as the preferred route and the
route parallel to lines 911L, 753L and 727L as the alternate route for transmission line
434L/646L. AltaLink stated that the preferred route is located almost entirely in or adjacent to
municipal road allowances or highway rights-of-way. The alternate route is parallel to existing
transmission infrastructure but traverses more private lands. There are two points in the routing
option that allow for a combination between the preferred and alternate routes.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
74 • AUC Decision 2013-369 (October 7, 2013)
3.1.3 Final siting stage
311. In the final siting stage, AltaLink presented the preferred and alternate routes to
stakeholders during the second round of consultation to confirm the selection of these routes and
consult with landowners regarding tower placement. Where possible, tower placements were
adjusted to minimize potential residential and land-use impacts. To finalize the preferred and
alternate routes, AltaLink also consulted with Alberta Environment and Sustainable Resource
Development, Alberta Transportation, counties and municipalities. AltaLink also conducted
engineering and design work, additional environmental work, obtained historical resource
information, and updated their environmental, oil and gas, and other data.
312. For the north Foothills project, a triple-circuit structure was proposed for the portion
parallel to the 850L line, after landowners raised issues with agricultural impacts from a new
line. The proposed use of triple-circuit structures resulted in a shift in the proposed centreline to
maintain the line as close to the location of the existing 850L line as possible. This shift resulted
in the centreline moving approximately 20 metres north, placing the new centreline
approximately 14 metres south of the existing 850L line.
313. For the Bow River crossing, landowners requested the use of a pair of single-circuit
transmission lines rather than double-circuit towers after expressing concerns with the height of
the taller, double-circuit structure. AltaLink stated that both options were viable.
314. The use of monopole structures is also proposed within the city of Calgary, to mitigate
concerns with future development. During detailed engineering design work, AltaLink
discovered that the termination of the north Foothills project at the north side of the ENMAX
No. 65 substation would not be feasible and refined the routing to terminate at the south end of
the substation. This places the transmission line within the city of Calgary transportation and
utility corridor. AltaLink stated that it would seek ministerial consent for the portion of the
transmission line within the transportation and utility corridor boundary prior to construction.51
51
Exhibit 13.00, page 150.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 75
Figure 16 – North Foothills project preferred and alternate routes52
315. After continued consultation with stakeholders, AltaLink amended its application to
include the D12 substation site as an alternate site for the substation. AltaLink stated that the
D12 site was a viable option for the Commission to consider.
316. For the south Foothills project, on the preferred route, a new alignment was developed to
align the route along an irrigation canal next to Mud Lake. Adjustments to the preferred route
were also made to avoid a feedlot, accommodate a setback from a sensitive species habitat and
allow for the expansion of an existing irrigation pivot. On the alternate route, adjustments were
made to accommodate agricultural practices, create greater separation from residences and
accommodate a setback from a storage facility. AltaLink also selected the location for a route
segment, designated as the Claresholm Connector, to allow for a combination of the preferred
and alternate routes.
52
Exhibit 13.00, page 105. Figure 4-34 Preferred and Alternate Segments with Designation Points (Final Siting
Stage).
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
76 • AUC Decision 2013-369 (October 7, 2013)
Figure 17 – South Foothills project preferred and alternate routes53
53
Exhibit 348.00, page 16. Figure 3-1 Preferred and Alternate Routes.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 77
317. For the Langdon to Janet project, no further refinements were made at the final siting
stage.
Figure 18 – Langdon to Janet preferred and alternate routes54
54
Exhibit 90.00, page 53. Figure 4-1 Final Routes.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
78 • AUC Decision 2013-369 (October 7, 2013)
318. Several changes were made during the final siting stage of the 138-kV project. A segment
of the alternate route was adjusted 10 metres to the west to avoid taking an easement and the
double-circuit transmission line was split into two separate single-circuit transmission lines to
cross under line 911L. A corner structure was also moved to avoid crossing over the corner of a
field.
Figure 19 – Foothills 138-kV project preferred and alternate routes55
55
Exhibit 213.00, page 106. Figure 4-37 Final Routing for the Foothills 138-kV Project.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 79
4 Consultation
319. The Commission requires applicants for transmission lines to include a description of
their participant involvement program in their application. Appendix A, Participant Involvement
Program requirements, of AUC Rule 007 specifies that a participant involvement program must
be conducted before an application is filed, and should include the distribution of a
project-specific information package, responses to questions and concerns raised by potentially
affected persons and a discussion of options, alternatives and mitigation measures. The applicant
is expected to ensure that information is conveyed to the public in an understandable manner.
320. The applicant must also make all reasonable attempts to contact potentially directly and
adversely affected persons to discuss the project, and must respond to any questions or concerns
they may have. Additionally, the applicant is required to notify all persons initially consulted to
close the participant involvement loop, if the scope of the project changes or a portion of a
project, such as a preliminary route segment, is no longer being pursued. The applicant must
document the participant involvement program. It must retain communication logs, registered
mail or courier tracking, and personal consultation and notification documents. It must also track
concerns and objections received prior to filing the application and potential mitigations.
321. The applicant must also hold at least one information session or open house meeting in
each community that would be affected by the proposed development.
322. For transmission line developments, the applicant must provide public notification to all
occupants, residents and landowners within 800 metres of the edge of the proposed right-of-way
of the proposed transmission line.
323. The applicant must personally consult with all occupants, residents and landowners on or
adjacent to the right-of-way of the proposed transmission line. Personal consultation must
include a face-to-face visit or telephone conversation. In an urban setting, the applicant must
provide notification to, and personally consult with, all occupants, residents and landowners
within the first row of houses facing the proposed transmission line.
324. Project-specific information packages must be distributed to all occupants, residents and
landowners and should provide detailed information about the proposed development. The
information packages must include applicant contact information, the location of the proposed
project, including a site-specific map, a discussion of any potential restrictions regarding the
development of lands adjacent to the project, a description of the proposed on-site equipment, the
anticipated project schedule and an AUC brochure regarding participation in the Commission
process.
325. The Commission and its predecessor, the Alberta Energy and Utilities Board, have
previously expressed the importance of conducting an effective notification and consultation
program before an application is filed. In Decision 2008-006,56 the Board stated that
“the program should include responding to questions and concerns, discussing options, providing
alternatives and potential mitigation measures, and seeking confirmation that potentially affected
parties do not object.” The Board went on to state that it “expects applicants to be sensitive to
56
EUB Decision 2008-006: Montana Alberta Tie Ltd. 230-kV International Merchant Power Line Lethbridge
Alberta to Great Falls Montana, Applications No. 1475724, No. 1458443 and No. 1492150, January 31, 2008,
page 36.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
80 • AUC Decision 2013-369 (October 7, 2013)
timing constraints the public may have especially when dealing with landowners engaged in
agricultural endeavours.” The Board also stated that “the consultation process is a two-way street
and it also expects the public to participate in meaningful discussions with a proponent of a
project.”
4.1 Views of AltaLink
326. AltaLink stated that the goal of its consultation process was to inform those who might be
directly and adversely affected by the project, provide an opportunity for stakeholders to ask
questions, express their concerns, discuss alternatives and mitigation measures, and, to obtain
more information about the proposed routes. AltaLink stated it has taken stakeholder input into
consideration in all stages of the project.
327. The participant involvement programs for the Foothills area transmission developments
were quite extensive and were conducted over a period of three and a half years. AltaLink
notified approximately 8,100 stakeholders; conducted consultation with almost 1,400
stakeholders; held a total of 45 open houses and information sessions with more than 860
attendees and conducted consultation with 65 government agencies, 20 municipalities, 98
companies and 35 community groups and other organizations.
328. AltaLink stated that it conducted a two-phase participant involvement program with the
landowners, residents, and occupants in the vicinity of the proposed transmission lines and
substations, as well as local businesses; local, regional, provincial and federal government
representatives and departments; companies with operations in the vicinity of the project,
aboriginal groups, including First Nations and Métis, and special interest groups and
associations.
329. A two-phase consultation process was conducted. The first round of consultation began
with individual landowners in the vicinity of the proposed routes. A project-specific information
package was mailed to each landowner which included:
a project newsletter
the location of proposed facilities, including site-specific maps
a brochure describing AltaLink’s projects in southern Alberta
a brochure discussing electric and magnetic fields
a brochure which provided answers to frequently answered questions on the role and cost
of transmission service
an AUC brochure of the facility application process
a two-page overview of the FATD project supplied by the AESO
330. All individuals identified were provided with strip maps of the area of their land and
residences to allow them to identify their location in proximity to the potential routes.
331. Open houses followed the mail out of project-specific information packages and were
held in communities along the preliminary routes. For example, for Application No. 1608637 -
north Foothills project, the following open houses were conducted during the first phase of
consultation.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 81
Table 1. AltaLink open houses for the north Foothills project
Date
Community
Location
Address
Hours of
operation
April 18, 2011 High River Highwood Memorial
Centre
128 – 5 Avenue West
High River, AB
4 – 8 p.m.
April 19, 2011 Okotoks Foothills Centennial
Centre
4, 204 Community Way
Okotoks, AB T1S 2N3
4 – 8 p.m.
April 20, 2011 Indus Indus Recreation
Centre
225155A Range Road 281A
Indus, AB T1X 0H7
4 – 8 p.m.
April 27, 2011 De Winton Heritage Pointe Golf
Course
1 Heritage Pointe Drive, De
Winton, AB T0L 0X0
4 – 8 p.m.
332. Open houses for all applications were advertised by way of project newsletters,
newspaper advertisements, posters and bold signs in high traffic areas, AltaLink’s website,
information centres, a toll-free telephone line and written correspondence. Information centres
for the public were also set up and staffed by AltaLink representatives.
333. AltaLink engaged third-party community consultation agents to carry out personal
consultation with landowners and residents within 150 metres of preliminary routes, as well as
those known to have unique farming practices or lands with environmental constraints likely to
affect the ultimate choice of routing. Consultation agents also consulted with persons in the
vicinity of a proposed route who requested consultation.
334. Once more detailed preferred and alternate routes were developed, AltaLink conducted a
second round of consultation. The second phase involved the notification of stakeholders still
potentially impacted by routes under consideration and stakeholders along routes that were no
longer under consideration by AltaLink.
335. An information package consisting of a project newsletter, updated maps, information on
structure types and work space requirements, information on the selection of the preferred and
alternate routes, and AESO newsletters for the need for transmission development was also
distributed. As part of the second phase, AltaLink set up an information centre and open houses.
For example, for the south Foothills project, open houses were held on February 28, 2011, in
High River; March 1, 2011, in Nanton; March 2, 2011, in Vulcan; and March 3, 2011, in
Claresholm. The open houses were advertised in the information package, local newspapers,
posters, street signs, and on AltaLink’s website.
336. AltaLink representatives continued to conduct personal consultations and distribute
project-specific information packages as AltaLink further refined and finalized the preferred and
alternate routes.
4.1.1 Group and personal consultation
337. AltaLink stated that personal consultation in phases one and two of its program included
door-to-door visits, telephone calls, one-on-one meetings and direct discussions with landowners
and residents; personal discussions at open houses and information centres; group presentations,
meetings and discussions; and correspondence. The consultation agents conducted face-to-face
visits and telephone conversations with all occupants, residents and landowners on or adjacent to
the proposed right-of-way for proposed routes.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
82 • AUC Decision 2013-369 (October 7, 2013)
338. AltaLink met with environmental groups and municipal representatives during its
participant involvement program as well as notified all county planning departments and federal,
provincial and municipal departments, and agencies about the proposed transmission lines and
substations. AltaLink also notified companies that own or operate pipelines, well sites or other
infrastructure in the vicinity of the proposed routes. AltaLink sent phase one and phase two
project overview and project information packages, and met with representatives to respond to
questions and discuss issues. AltaLink stated that consultation is ongoing and that no concerns
were identified that could not be resolved through further consultation, implementation of
mitigation measures or additional studies.
4.1.2 Aboriginal consultation
339. AltaLink conducted consultation with First Nation groups based on all components of the
AESO’s FATD NID and SATR NID amendment. It followed the Province of Alberta’s
requirements for First Nations consultation. For these applications, Alberta Sustainable Resource
Development (now known as Alberta Environment and Sustainable Resource Development)
confirmed the need to consult with the following First Nations:
Blood Tribe/Kainai First Nation
Piikani First Nation
Siksika First Nation
Tsuu T’ina First Nation
Stoney Nakoda First Nation (Chiniki, Bearspaw and Wesley First Nation)
340. AltaLink discussed its plans to conduct project-specific traditional land-use assessments
with these First Nations and provided the First Nations with project information packages. It also
provided support for the First Nations to conduct the traditional land-use assessments, and stated
that it continues to maintain communications with First Nations representatives, identify
potential project interactions with traditionally used sites and resources, and to develop
appropriate mitigation strategies. AltaLink also conducted information sessions with numerous
First Nations.
341. AltaLink also engaged Métis groups in consultation, distributed project information to the
Métis Nations of Alberta and held open houses.
4.1.3 AltaLink response to intervener consultation concerns
342. AltaLink stated in its argument that only a very small portion, six of approximately
8,100 stakeholders, took issue with the consultation that was completed on the project. The six
stakeholders were Mr. Nauta, Mr. Maldeghem, Mr. Friesz, Ms. Klatzel-Mudry, Mr. Bretin and
Ms. Carlson.
343. AltaLink submitted that it was clear that these parties were properly consulted and
described its consultation with each of the interveners. AltaLink demonstrated that Mr. Nauta
had been involved in several discussions with AltaLink and in argument, submitted that his
concerns were ultimately with the preferred route for the Foothills 138-kV line, and not with the
consultation program.
344. Mr. Maldeghem stated that he was not properly consulted on the triple-circuit monopole
option. AltaLink put forth that Mr. Maldeghem’s counsel cancelled a meeting due to the fact that
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 83
AltaLink does not compensate people for consultation. AltaLink then later provided a sketch of
the monopole option to Mr. Maldeghem’s counsel, but Mr. Maldeghem could not recall if he had
reviewed it.
345. AltaLink questioned Mr. Friesz about a consultation meeting AltaLink had with him.
Mr. Friesz ultimately conceded that he had been consulted on at least six occasions.
346. AltaLink disagreed with Ms. Klatzel-Mudry, who expressed concerns about the tower
design for the Bow River crossing. It contended that the single-circuit option was clearly
explained in the consultation. AltaLink stated that cross-section diagrams of the tower sizes,
which illustrated the differences between the tower options, were taken to all meetings.
347. AltaLink also argued that Mr. Bretin was consulted on a number of occasions and
submitted in undertaking 15 at the hearing that it informed Mr. Bretin of the preferred route on
March 14, 2012, and that the final routing was submitted on July 12, 2012.
348. AltaLink stated that many attempts were made to invite Ms. Carlson to consult.
Ms. Carlson indicated that she did not wish to further consult on the project in May 2011. In
October 2011 she was sent a project-specific information package which showed the revised
alternate route. On March 13, 2012, Ms. Carlson again indicated that she did not wish to consult
when advised by an AltaLink representative that the alternate route would go through her field
and would remain a viable route option. AltaLink maintained that it provided Ms. Carlson with
all the information that she would require to inform herself of the proposed changes to the
alternate route and provided several opportunities to discuss it.
349. AltaLink put forth that, for a project of this magnitude, the limited number of concerns
raised by stakeholders about the consultation conducted speaks to the program’s success, that it
was remarkably effective, and that it exceeded AUC Rule 007.
4.2 Views of the interveners
4.2.1 Langdon to Janet application
350. Members of the Mattson group took issue with AltaLink’s consultation. Mr. Vern Bretin
wrote to the Commission that he now believed that any further involvement by himself in
regards to the activities of SNC/AltaLink could have an impact on the siting upon his land and
that he felt threatened. Ms. Shelia Buckley stated that AltaLink did not respond to a request from
her to have her property bought at a reasonable price.
351. The Mattson group submitted in its argument that it believed that, while the consultation
process may help landowners understand the ‘how’ and ‘why’ of transmission line siting and
give the applicant the possibility to lessen the site-specific burden on landowners, a right-of-way
over a person’s land should be avoided whenever possible.
352. Mr. Daniel Meier stated that he was extremely disappointed by AltaLink’s lack of
communication, adding that his family had not heard anything for over a year and had to
approach AltaLink to receive an update on the project.
353. Ms. Sharon Carlson testified that AltaLink’s consultation was disappointing and grossly
unsatisfactory. She stated that AltaLink failed to disclose or provide reasons why it was
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
84 • AUC Decision 2013-369 (October 7, 2013)
necessary to have a transmission lines across the McLaren/Carlson land and that no notification
of the change between the initial proposed alternate route and the current proposed alternate
route was provided.
354. Mr. and Mrs. McLaren, and Ms. Carlson stated that on May 3, 2011, they attended an
open house in Chestermere and submitted their concerns about the preferred and alternate routes
to Mr. Jay Wildman, an AltaLink land agent, and requested that AltaLink contact them once the
routing of the transmission lines was complete.
355. Except for being contacted by AltaLink on March 2011, and May 13, 2011, when the
original alternate route was discussed, Ms. Carlson stated that they did not receive any further
communication until July 20, 2012, when the alternate route was submitted to the AUC. This
applied-for line was significantly different than what was discussed with them when they were
first approached by AltaLink.
4.2.2 North Foothills and Foothills 138-kV applications
356. Mr. Randle stated at the hearing that he appreciated AltaLink listening to his concerns
and, in fact, that it amended its application to include an alternate substation location. He
mentioned that he got along really well with AltaLink employees. Mr. Randle attended many
open houses, met with AltaLink on his land on many occasions and even met with its
representatives at the AltaLink office.
357. Mr. Maldeghem stated at the hearing that although he did eventually become aware, he
was not initially consulted about the proposal of the monopole option.
358. Mr. Nauta questioned the AltaLink panel on their interpretation of public consultation.
Mr. Nauta stated that he did not receive any real consultation on the project.
359. Although the members of the Diagonal group wrote in their statements of intent to
participate that they had issues with the public consultation program conducted by AltaLink,
their statements did not provide further details about their concerns.
360. The members of the Diagonal group testified that throughout the consultation with
AltaLink, none of the members had been given a cross-section depicting the relative heights of
the new triple-circuit monopole structures versus the existing wood pole structures that were to
scale.
361. Mr. Friesz of the Diagonal group also testified that he thought AltaLink was playing with
his words in the consultation record regarding his preference for a triple-circuit monopole. He
emphasized that AltaLink was trying to convince the members of the Diagonal group that
placing all three of the circuits on a monopole structure was a vast improvement, while he was
saying that the diagonal routing of the line was the major problem. In his view, triple-circuiting
the line was a minor improvement. Mr. Friesz also submitted that he was not shown a picture of
the triple-circuited structure drawn to scale prior to the hearing and he was shocked when he saw
it.
362. Ms. Klatzel-Muldry stated that she was confused by the depiction of a single-circuit and
of a double-circuit version of the Bow River crossing that she received during consultation. She
stated that without a full understanding of the single-tower or two-tower options, it is very
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 85
difficult to make a decision on the matter. She submitted that she had no recollection of being
informed that the transmission line would go from one larger tower to two towers, and had never
signed-off or been consulted on the matter.
363. Ms. Klatzel-Muldry added that she had not expected that the consultation forms
completed during the consultation would be used a year and half later at the hearing; and that she
had thrown away her own notes a few months after the consultation because she had not heard
from anyone or thought that they would be useful. Recollecting what she had discussed during
the 2011 consultations was not an easy task.
364. Mr. Brunen of Western Sky-Land Trust stated that they had made contact with AltaLink
to discuss their interest with the Thomson property and their wishes for a single-tower alignment
crossing the Bow River. Western Sky-Land Trust did not receive any follow-up or consultation
from AltaLink other than the telephone call Mr. Brunen initiated.
4.2.3 South Foothills and Windy Flats 138-kV applications
365. Members of the Committee for East Route Conservation (CERC) group wrote in their
statements of intent to participate that they had issues with the public consultation program
conducted by AltaLink, but no further details were provided about their concerns.
366. The Conners stated that during their consultation with AltaLink in 2010, the preferred
route would severely disrupt their ranching and gravel operations. They discussed this concern
with AltaLink on many occasions and AltaLink gave them suggestions on how to navigate
around obstacles. In the end, AltaLink did not pursue any of these suggestions. They stated that
AltaLink would present ideas, only to later inform them that they could not be implemented.
AltaLink presented the amendment location, which was next to the Conners’ residence, after an
agreement on the preferred route was not reached with them.
4.3 Views of ENMAX
367. ENMAX conducted a public consultation process in accordance with the requirements of
AUC Rule 007 for both ENMAX No. 25 substation and ENMAX No. 65 substation. It conducted
public notification of landowners, residents and occupants within 800 metres of the proposed
substations, and personal consultation with all potentially directly and adversely affected
landowners and residents. It also notified local and provincial government officials and other
identified organizations, and held four open houses.
368. ENMAX stated that, throughout the consultation process for the project, no concerns
were raised with respect to the substations’ modifications.
369. ENMAX and AltaLink agreed that AltaLink would perform all consultation on behalf of
ENMAX for the 1064L/1065L line.
4.4 Commission findings
370. The participant involvement program was initiated early in the planning process by
AltaLink and ENMAX, respectively. The Commission considers that AltaLink and ENMAX
made a reasonable effort to ensure that all potentially affected parties were informed of the
application and had an opportunity to consider the potential impacts of the project. The design,
nature and extent of the participant involvement program provided parties with an opportunity to
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
86 • AUC Decision 2013-369 (October 7, 2013)
provide input. AUC Rule 007 does not require compensation for consultation and in previous
decisions, the Commission found that AltaLink acted reasonably in denying payment of fees for
consultation.57 Interveners did not take issue with the AESO’s or ENMAX’s participant
involvement program.
371. Although the Commission acknowledges the importance of the concerns expressed by
interveners regarding AltaLink's consultation, the Commission must assess the participant
involvement program as a whole, in light of the nature and scope of the project at hand.
AltaLink’s participant involvement program notified approximately 8,100 households in the area
of the preliminary routes and personal consultation occurred with approximately
1,400 individuals. Taking into consideration the scale and scope of the program, it is not
surprising that there were some oversights. Although regrettable, the Commission is satisfied that
when these oversights were identified, AltaLink attempted to rectify them.
372. Some landowners expressed concerns that the single-circuit versus double-circuit
configuration or the one versus two tower terminology for the Bow River crossing was confusing
for stakeholders to understand. The Commission agrees that AltaLink could have better
explained the number of towers that were being proposed for each option to cross the Bow River
and the corresponding heights of these towers, but also recognizes that AltaLink made efforts to
take into account the concerns expressed by landowners and residents through its various stages
of routing. For example, in light of the changes to the landowners’ preferences, AltaLink
proposed an alternate tower configuration option for the Bow River crossing portion of the route;
an alternate site location for the Foothills substation was also proposed by AltaLink to reflect its
consultation with Mr. Randle.
373. The Commission will consider a participant involvement program to be effective if it
meets AUC Rule 007 requirements and has allowed stakeholders an opportunity to understand
the project and its potential impacts, express their concerns about the project and to provide
site-specific input to improve the project; however, an effective participant involvement program
may not resolve all stakeholder concerns.
374. The evidence demonstrates that AltaLink undertook a comprehensive participant
involvement program; that it utilized effective communication tools, including direct
consultation, mail notifications, open houses and information sessions. AltaLink also established
information centres and provided a dedicated phone number and an email address. It conducted a
phased approach to consultation to inform persons who might be potentially and adversely affect
by the proposed transmission lines and substations.
375. The Commission finds that potentially affected parties were provided with sufficient
information from AltaLink to understand the project and opportunities to express their concerns
during the participant involvement program. Also, if the persons who were notified and
consulted had unresolved concerns, these persons were informed about the Commission hearing
process, and had an opportunity to participate in the hearing and bring forward their concerns.
57
Decision 2009-049: ATCO Electric Ltd. Construct Updike Substation 886S and 144-kV Transmission Line
7L34, Application No. 1589611, Proceeding ID No. 114, April 28, 2009, paragraph 43; Decision 2011-445:
AltaLink Management Ltd. New 240/138-kV Nilrem 574S Substation, double-circuit 240-kV Transmission
Lines 953L/1047L and double-circuit 138-kV Transmission Lines 679L/680L, Application No. 1606753,
Proceeding ID No. 938, November 10, 2011.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 87
376. Similarly, the evidence shows that ENMAX conducted a comprehensive participant
involvement program consisting of public notification, direct consultation and open houses.
ENMAX did not receive any objections to or concerns about the substations’ modifications
during its participant involvement program.
377. Based on the above, the Commission finds that the participant involvement programs of
AltaLink and ENMAX were conducted in accordance with AUC Rule 007.
5 Environment
5.1 Introduction
378. AltaLink stated that it used a staged approach to integrate environmental considerations
into project development, design and construction and described the following major
components of its environmental approach:
the review of environmental data both from electronic sources and field studies at the
route development stage so that the sensitive environmental features could be identified
and avoided where possible
the avoidance of environmental impacts through the elimination of unsuitable routes
adherence to environmental legislation and guidelines, including Land Use Guidelines for
Protection of Selected Wildlife Species and Habitat within Grassland and Parkland
Natural Regions of Alberta, Guide for Transmission Lines and Conservation and
Reclamation Information Letter Environmental Protection Guidelines for Electric
Transmission Lines (C&R/IL/95-2) and Environmental Protection Guidelines for
Transmission Lines (AE R&R/11-03)
review and consideration of available environmental information and stakeholder
knowledge of the local area during project planning and construction
Identification and evaluation of local environmental features (terrain and soils,
vegetation, wildlife, aquatics resources) and environmentally significant areas with
site-specific field investigations as needed
the implementation of environmental monitoring and reporting during construction
379. AltaLink presented the overview of its staged environmental approach in the following
flow chart.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
88 • AUC Decision 2013-369 (October 7, 2013)
Figure 20 – AltaLink’s staged environmental approach58
58
Exhibit 13.00, page 149. Figure 10-1 Environmental Approach Overview.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 89
380. AltaLink stated that it retained Stantec to carry out an environmental evaluation of the
FATD project along the proposed preferred and alternate route segments in accordance with the
requirements of AUC Rule 007 and Alberta Environment and Sustainable Resource
Development guidelines for transmission lines. Stantec concluded that with the implementation
of appropriate mitigation measures, both the preferred and alternate route segments are viable
from an environmental perspective.
381. AltaLink stated that it developed the environmental specifications and requirements
(ESR)59 which defined construction-related environmental commitments and expectations for the
FATD project. AltaLink compiled the environmental mitigation measures in the ESR. Prior to
the commencement of the construction, AltaLink committed to require its contractors to prepare
and submit a construction and environmental management plan that meets the ESR for
AltaLink’s approval.
382. AltaLink described mitigation measures to be applied during construction to reduce
potential effects to biophysical resources. Project-wide mitigation measures were to include
scheduling construction, as well as construction and operations mitigations incorporating
provincial transmission line guidelines and industry best practices and standards. AltaLink
further committed to incorporate resource feature mitigations and additional site-specific
mitigations, if required, based upon the results of a pre-disturbance assessment program.
383. AltaLink noted that it had implemented, and would further introduce a number of design
features, to assist in reducing the potential environmental effects of the project. Towers were to
be located in a manner to avoid water bodies, water wells and disturbance to springs. Where
possible, AltaLink proposed towers to be set back from rivers or creeks and no towers were sited
within permanent, open water wetlands. Larger setbacks were applied for towers near outer
erosive river banks and, where possible, AltaLink stated it would avoid building structures
within any stream areas that were inherently unstable. It further committed to locate towers,
access trails and all-weather access roads at least 30 metres from the ordinary high water mark of
water bodies. In addition, Water Act approval will be applied for any water bodies that cannot be
avoided when siting.
384. AltaLink proposed that towers be set back from the edges of steep or unstable slopes and
that existing roads and previously-disturbed areas be used, where feasible, to access the
right-of-way and tower sites. Where possible, access approaches were proposed to be constructed
perpendicular to the watercourse to reduce disturbance to riparian vegetation. AltaLink proposed
to locate towers, access trails and temporary workspaces to avoid or reduce disturbance to rare or
sensitive native vegetation species and communities.
385. AltaLink also committed to develop, prior to construction, a reclamation plan utilizing
current best management practices and to ensure compliance with Alberta Environment and
Sustainable Resource Development’s Environmental Protection Guidelines for Transmission
Lines. Re-vegetation of disturbance was proposed using seed mixes and application rates,
59
Exhibit 23.00, Appendix J AltaLink Environmental Specifications and Requirements for north Foothills
Transmission Project; Exhibit 80.00, Appendix I AltaLink Environmental Specifications and Requirements for
Langdon to Janet Project; Exhibit 204.00, Appendix I AltaLink Environmental Specifications and Requirements
for Foothills 138kV Transmission Project; Exhibit 364.00, Appendix L AltaLink Environmental Specifications
and Requirements for Windy Flats 138kV Project; Exhibit 343.00, Appendix J AltaLink Environmental
Specifications and Requirements for south Foothills Transmission Project.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
90 • AUC Decision 2013-369 (October 7, 2013)
determined through consultation with landowners. Stantec prepared an environmental evaluation
report for each of the facility applications, which are detailed below.
5.2 Application No. 1608642 – Langdon to Janet
386. AltaLink described the preferred route as running parallel to existing transmission lines
for over 94 per cent of its length and traversing predominately agricultural or previously
disturbed land. The area is described as flat to very gently undulating topography underlain by
glacial deposits. The few relatively steep slopes in the area are associated with man-made
features such as road embankments and irrigation canals.
387. The project area is part of the Western Irrigation District, and characterized by wetlands,
local drainages, irrigation canals and Chestermere Lake, which was identified as the largest lake
in the area, although numerous small ephemeral lakes and wetlands were noted. Several large
wetlands, two large alkali ponds and a poorly drained wetland complex southeast of Langdon
were also noted.
388. Watercourses in the area were classified to be Class D based on the Alberta Environment
and Sustainable Resource Development Code of Practice,60 with a low sensitivity to disturbance.
The Bow River–Chestermere Lake diversion canal supported populations of sport fish but fish
habitat in irrigation canals was considered to be of low sensitivity, not classified under the
Code of Practice and the development would not require authorization under the Fisheries Act.
AltaLink stated that no threatened or endangered fish species occurred within the area.
389. The preferred route would avoid Chestermere Lake, the wetland complex in the eastern
part of the area and most of the larger ephemeral water bodies between the towns of Shepard and
Chestermere.
390. Most of the land is described as agricultural cropland or tame pasture; larger areas of the
remaining native prairie were found north of Chestermere Lake and surrounding Langdon.
Scattered smaller patches of native prairie occur around wetlands and watercourses south of
Chestermere Lake. Native vegetation, consisting of fragments of upland native prairie and
wetlands, were of low abundance on the right-of-way.
391. One plant species at risk and two rare plants were found to potentially occur within the
area, but AltaLink noted that the known occurrences were well outside of the proposed routing.
392. The project area is said to support high biodiversity, including 62 federally- or
provincially-listed wildlife species, some of which cannot be found anywhere else in Alberta.
AltaLink noted that three of those species are listed as endangered species and seven are
considered threatened.
393. Much of the wildlife habitat in the area is said to be highly fragmented with reduced
capacity because of extensive agricultural and urban development. There are few patches of
undisturbed native prairie found in the area, with most of the remaining grassland consisting of
tame pasture with introduced grasses. Remnant wetland, riparian features, areas of tame pasture
and native prairie remain important areas for wildlife.
60
Code of Practice for Watercourse Crossings, adopted under the Water Act and the Water (Ministerial)
Regulation, consolidated to include amendments in force as of June 24, 2013 (AENV 2007).
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 91
394. The area was described as situated in prairie pothole habitat with numerous wetlands and
adjacent upland habitat that provided excellent habitat for waterbirds and breeding areas for
amphibians and other species. AltaLink specifically noted that the North American Waterfowl
Management Plan identified prairie pothole habitat as a priority area.
395. A large number of waterfowl were recorded in a large Ducks Unlimited wetland complex
and potholes south of Chestermere Lake. Federally or provincially protected shorebirds were
said to be supported in alkaline wetlands further to the south. Wetlands northeast of Chestermere
Lake also provide important staging habitat within the siting study area; however, it has a highly
developed shoreline with limited wildlife habitat suitability.
396. Both the preferred and alternate routes were routed to avoid Weed Lake and the large
alkaline wetlands south of Chestermere Lake; however they intersect several pothole wetlands
south of Chestermere Lake.
397. AltaLink indicated that a moderate amount of wildlife habitat, including native prairie,
tame pasture, and wetland were found close to the right-of-way and in the landscape area for the
Langdon to Janet segment.
398. AltaLink asserted that the routing process and commitment to site-specific mitigations
had reduced or avoided several potential effects on wildlife. The nature and severity of the
remaining effects on wildlife resource features varies between the routes.
399. AltaLink identified potential effects to wildlife occurring during ground disturbance of
habitat and sensory disturbance during construction. New habitat creation and changes to
predator and prey interactions are also expected to occur during operations. Salvage is expected
to result in short-term sensory disturbance. AltaLink proposed to reduce site-specific effects to
wildlife by applying the proposed mitigation measures.
400. The alternate route parallels fewer existing linear disturbances and was found to contain
more than twice as much native prairie and proportionally more wetland habitat than the
corresponding section of the preferred route which contained proportionally more modified
habitat. As a result, wildlife mortality and habitat loss, sensory disturbance, and altered predator
prey relationships for wetland and grassland wildlife species are more probable along the
alternate route.
401. Risk of avian collision is predicted to be potentially high along portions of both the
preferred and alternate routes, where large numbers of waterfowl were recorded. The risk of
avian collision may be slightly higher for the alternate route because construction of a new
right-of-way would traverse more than twice as many wetlands and more wetland areas of
importance.
5.3 Application No. 1608637 – north Foothills transmission development
402. The environmental evaluation report,61 prepared by Stantec, described the project as
including the transmission line right-of-way, towers, a substation, access trails and temporary
workspaces for construction. Stantec also indicated that there was one crossing of the Bow River
and 16 crossings of tributary streams to Frank Lake.
61
Exhibit 23.00, Appendix J Environment, north Foothills Transmission Project Environmental Evaluation.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
92 • AUC Decision 2013-369 (October 7, 2013)
403. Stantec assessed soils and terrain, wildlife, vegetation (including wetlands), and aquatic
resources (i.e. water bodies) that were potentially vulnerable to impacts. That evaluation report
was described as being based on available data sets, supplemented by targeted field surveys and
ground truthing on public land, and on private land where landowners allowed access.
404. The primary environmental effect of construction of the proposed Foothills 237S
substation identified was wildlife habitat loss in the area of the substation and access road, and
the change in habitat use, in adjacent areas, due to sensory disturbance.
405. AltaLink’s preferred D8 site for the Foothills substation was described as a cultivated hay
or crop field whereas the alternate substation site D12 was described as reverted tame pasture.
The tame pasture at D12 was said62 to resemble native prairie and was relatively rare in the area;
whereas the land at D8 was described as previously disturbed land and it was said that
comparable forage was available elsewhere.
406. AltaLink asserted that the D8 site was more suitable from a wildlife habitat perspective
despite being on the margin of Environmentally Significant Area 237. AltaLink indicated that
this preference was offset somewhat by the higher incremental risk of avian collisions at the D8
site but emphasized63 Dr. Gahbauer’s testimony that the D8 site was proposed to be more than
900 metres from Frank Lake and expected to pose a risk of avian collision that was comparable
to the D12 site.
407. The application described the preferred route as crossing predominately agricultural and
other previously-disturbed land for about three-quarters of its length. Native vegetation on the
right-of-way was said to be low and consist of upland native prairie fragments, wetlands, and a
number of riparian areas. The preferred route would parallel existing rights-of-way for most of
its length, which would minimize fragmentation, reduce impacts to existing land use, and reduce
incremental visual impacts.64
408. The preferred route was reported to avoid crossing Environmentally Significant
Area 237, Frank Lake, which was described65 as the most important wetland in south western
Alberta for breeding water birds. AltaLink stated that Frank Lake is an important bird area,
which provides staging and moulting habitat during spring and fall for significant numbers of
waterfowl and shorebirds, including several species of concern. It is also the site of major
Ducks Unlimited avian habitat enhancement projects. Because it is a possible breeding water
body for trumpeter swans, in order to reduce avian mortality concerns, AltaLink set the preferred
route back a minimum of 500 metres from the current high water mark. The preferred route
variant is closer to Frank Lake while the Frank Lake alternate route is further away from Frank
Lake.
409. Stantec also identified Blizzard Lake and other smaller key wetlands that form a matrix
of upland pasture and wetland habitat, particularly immediately east of Calgary as well as north
of Gladys and north of Frank Lake.
62
Exhibit 720.04, AML Reply Evidence, Appendix C1 – Environmental Considerations. pdf page 12. 63
Exhibit 854.01, AML Written Argument. page 82-83, paragraph 205. 64
Exhibit 13.00, page 6, paragraph 20. 65
Exhibit 23.00, Appendix J Environment, north Foothills Transmission Project Environmental Evaluation,
page 2-11, Section 2.6, Wildlife.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 93
410. The area where the proposed line would cross the Bow River was characterized as a
riparian area having steep river banks in an area of incised valleys or coulees but concerns about
the terrain were said to be addressed by spanning the valley. Some taller trees would be cleared
or trimmed to allow for safe operation.
411. Four wildlife species of concern were observed in the vicinity of the preferred route near
the Bow River, including two prairie falcon nests within the Alberta Environment and
Sustainable Resource Development-specified 1,000 metres setback distance. Populations of
breeding and staging waterfowl were said to be low.
412. AltaLink identified the 1201L parallel river crossing as the superior location to traverse
the Bow River valley. The alternate west route river crossing was rejected as it was said to
require an additional crossing of the Highwood River and would be closer to residents.
413. AltaLink’s preferred single-circuit design was said to have been selected in consultation
with Fish and Wildlife Management branch of Alberta Environment and Sustainable Resource
Development, and to address stakeholder concern regarding expected impacts to visual
aesthetics.
414. Stantec also stated that the preferred route was better from an environmental perspective
because it spanned valley walls, flood plain and riparian vegetation at the proposed Bow River
crossing. The Bow River crossing would also span McKinnon Flats, a managed site that provides
access to the Bow River. While both options were said to be viable, Stantec expressed a
preference for the double-circuit, indicating that in comparison, the clearing of two rights-of-way
for the single-circuit design would cause greater disturbance and that the additional wires of
single-circuit design would potentially increase the risk of avian collisions during operation.
415. The Frank Lake area alternate route was found66 to be more biophysically suitable and
pose a lower avian mortality risk than the corresponding section of the preferred route. The
Frank Lake alternate route was said to traverse much less native vegetation and less wildlife
habitat, avoid large wetlands, and be further away from Frank Lake. Although said to minimize
environmental impacts and effects to wildlife, compared to the preferred route, the Frank Lake
alternate route was characterized67 as being longer, costing more, fragmenting more agricultural
land and closer to more residences.
416. The preferred route variant, a second alternate route, was described68 as requiring up to
three structures across Frank Lake, adjacent to the existing 1201L line. Also, this route was less
biophysically suitable than the corresponding section of the preferred route because it crossed
open water sections of Frank Lake, which could pose greater erosion concerns crossing more
wetlands and the risk of bird mortality was predicted to be high even with the use of deflectors. 69
417. Stantec reported that the north alternate route and the corresponding section of the
preferred route were biophysically comparable and incrementally add to the risk of waterfowl
66
Exhibit 23.00, Appendix J Environment, north Foothills Transmission Project Environmental Evaluation,
Section 9.3.1 South Options. 67
Exhibit 13.00, north Foothills Transmission Project Application, page 6, paragraph 20. 68
Exhibit 13.00, north Foothills Transmission Project Application,page 6, paragraph 21. 69
Exhibit 23.00, Appendix J Environment, north Foothills Transmission Project Environmental Evaluation, pdf
pages 69, 104, 105 and 109.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
94 • AUC Decision 2013-369 (October 7, 2013)
mortality from avian collisions. The majority of each section was described as predominantly
flat, with low risk for wind and water erosion, and traversing primarily modified habitat. The
corresponding section of the preferred route contained more wildlife habitat on the right-of-way
than the north alternate route, which had slightly more wildlife habitat in the landscape area.
418. AltaLink submitted a project-specific north Foothills transmission project ESR70 that
described mitigation measures to be applied during project construction and operations to reduce
or avoid potential adverse effects on biophysical resources. Those measures were said to be
typical of transmission construction projects and effective, irrespective of which route was
approved.
419. Stantec indicated that, after avoidance of adverse environmental effects, the most
important mitigation measure was the timing of construction. Completing construction of the
transmission line and substation in these habitats, outside of spring and early summer and after
seed set was said to reduce the potential for adverse effects. Another key mitigation measure
proposed was the use of bird flight diverters or wire markers to reduce the risk of bird collisions
with the line.
420. As noted above, to further avoid adverse environmental effects, and mitigate effects that
cannot be avoided, AltaLink committed to conducting pre-disturbance assessments of vegetation,
wildlife and habitats, wetlands and water resources.
421. Stantec concluded71 that, with the implementation of appropriate mitigation measures, the
preferred route, Frank Lake alternate route, preferred route variant and north alternate route were
all environmentally viable. The potential environmental effects that were not avoided during
routing could be effectively reduced or avoided, by implementing the measures outlined in
AltaLink’s ESR. The Frank Lake area alternate route was said to be more suitable than the
corresponding section of the preferred route while the preferred route variant was much less
suitable than the other two south options proposed. The north alternate route was said to be
generally comparable to the corresponding section of the preferred route.
422. AltaLink retained Arrow Archaeology Limited (Arrow) to assess historical resources and
submit a Statement of Justification for the Project to Alberta Culture. Alberta Culture outlined
the requirements for historical resources impact assessments for archaeology and paleontology.
423. AltaLink committed to complete an historical resources impact assessment and not
commence construction until clearance under the Historical Resources Act has been granted. It
further committed to implement, in consultation with Alberta Culture staff, mitigation measures
for any historical resources potentially impacted by the project.
5.4 Application No. 1608643 – Foothills 138-kV transmission development
424. AltaLink asserted that potential environmental effects that were not avoided through
routing would generally be reduced or avoided by implementing the mitigation measures
proposed. The preferred route, alternate route, common segment and alternate segment are all
considered to be viable from a biophysical perspective.
70
Exhibit 23.00, Appendix J Environment, north Foothills Transmission Project Environmental Evaluation,
Environmental Specifications and Requirements, north Foothills Transmission Project, pdf page 1 to 16. 71
Exhibit 13.00, page 9, Section 1.9 Environment, paragraph 47.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 95
425. The preferred and alternate routes are comparable in terms of expected effects to soils,
terrain and vegetation; however, the alternate route is more suitable from a wildlife perspective.
426. The common segment is said to have a moderate number of environmental features, but
AltaLink expects the biophysical effects to be limited because most activities are related to
vegetation removal. The risk of avian mortality from collisions during operations is expected to
decrease because of that removal.
427. The preferred route of the 138-kV line crosses predominantly disturbed land in flat to
gently undulating terrain with very few steep slopes and small areas of soils at high risk for wind
erosion, water erosion or compaction. One crossing of the Highwood River is said to be needed
for the preferred route.
428. AltaLink found relatively low abundance of native vegetation, upland native prairie
fragments, wetlands and riparian areas on the preferred route right-of-way, which is located
within one kilometre from a colony of great blue heron, a protected bird species.
429. The alternate route crosses predominantly disturbed land in flat to gently undulating
terrain, with very few steep slopes and small areas of soils at high risk for wind erosion, water
erosion or compaction. Two river crossings, the Highwood River and Tongue Creek, are required
for the alternate route.
430. A relatively low abundance of native vegetation and a small area of wetland and riparian
habitat were found by AltaLink on the right-of-way of the alternate route. AltaLink stated that
the preferred and alternate routes are comparable in regard to expected effects to soils, terrain
and vegetation; however, the alternate route is said to be more suitable in terms of effects to
wildlife, with only slight differences in wildlife habitat quantity and quality. The alternate route
was found to have slightly more grassland habitat in the landscape area and more wildlife habitat
in the right-of-way. The preferred route contains slightly more wetland habitat, slightly higher
waterfowl counts and is closer to a Highwood River heron colony.
431. The common segment is described as crossing the Bow River and Tongue Creek. A
moderate abundance of native vegetation was noted in the right-of-way of the common segments
but because vegetation removal and rebuild are proposed on an existing right-of-way, AltaLink
predicts few effects to vegetation.
432. A moderate amount of wetland, riparian and grassland wildlife habitat is found in the
landscape area of the common segment. These areas occur mainly along the 727L line which
AltaLink is proposing to remove. As a result, effects on wildlife, particularly from an avian
collision perspective, are expected by AltaLink72 to be limited following removal of the 727L
line and, in the long-term, have a positive effect on wildlife species most susceptible to avian
collision (e.g. waterfowl).
5.5 Application No. 1608861 – south Foothills transmission development
433. AltaLink stated that while both the preferred and alternate routes of the south Foothills
project are viable, the preferred route is more suitable from a biophysical perspective. Based on
available information, potential environmental effects that are not avoided through routing would
72
Exhibit 204.00, Appendix I Foothills 138-kV Environmental Evaluation, exhibit, 204, pdf page 165.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
96 • AUC Decision 2013-369 (October 7, 2013)
be effectively reduced or avoided with the implementation of the mitigation measures it
proposed.
434. The preferred route parallels a greater length of existing transmission lines and, therefore,
would disturb less native vegetation and contribute to less overall fragmentation of wildlife
habitat than the alternate route. The preferred route is said to traverse less area of moderate or
high quality wetland and riparian habitats; which are expected to result in a lower risk of avian
collisions than the alternate route.
435. The landscape area of both the preferred and alternate routes is characterized as having a
high proportion of cultivated or pasture lands with upland native prairie, wetlands, and riparian
communities composing less than one quarter of the area. Some localized dunes and sandy soil
areas were noted.
436. Both routes crossed the Oldman River, as well as several meandering rivers and creeks. A
wide variety of birds, mammals, amphibians and reptiles were said to occur in the area, including
wildlife species that are protected provincially and federally.
437. After avoidance, construction timing was identified by AltaLink as the second-most
important mitigation measure to minimize adverse environmental effects of the project. It stated
that it would “make efforts to not schedule construction in areas of native vegetation and tame
pasture between approximately April 15 and July 31.”73 Doing so would avoid the migratory bird
breeding period, avoid sensitive periods for other wildlife species, and reduce the potential for
effects on soils and vegetation. AltaLink clarified in its commitments74 that:
Nest surveys will be conducted should construction activity be proposed during the
breeding bird season (April 15 – July 31). Construction will only take place during the
bird breeding season at specific locations using site specific mitigation based on the
results of nest surveys.
438. The Claresholm Connector was described by AltaLink as a viable segment located
predominantly within cultivated land with some areas of wildlife habitat. The Windy Flats
substation variant route was determined to be viable, but less suitable from a biophysical
perspective, than a comparable section of the preferred route because the variant intersects a
much larger amount of native prairie and wetland habitat, and is expected to have higher
potential for avian collisions.
5.6 Application No. 1608862 – Windy Flats 138S substation and line reconfiguration
439. Stantec stated that the majority of the landscape area consists of native prairie with areas
of agricultural (cultivated and pasture) land and small to medium wetlands and drainages. The
project landscape area does not occur in a designated park, protected area or environmental
significant area. Stantec considers that the potential effects of the project on soil quantity and
quality through erosion are low. A very small area of the project right-of-way contains steep
slopes that would be spanned by the project. Stantec concluded that the overall potential effects
of the project on soil compaction would be low.
73
Exhibit 343.00, Appendix J south Foothills Transmission Project, Environmental Evaluation, pdf page 230,
Section 9.2 Preferred and Alternate Routes. 74
Exhibit 807.01, AltaLink undertaking 006.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 97
440. Stantec indicated that there were few drainages and wetlands within the project
right-of-way; that the disturbance to native vegetation from the salvage and rebuild of the lines
was expected to be limited; and that the risk of introducing weed species was expected to be low.
441. Stantec stated that the landscape area has important features for wildlife, including native
prairie, a coulee and a staging wetland. Following effective mitigation measures outlined in
AltaLink’s ESR,75 Stantec concluded that potential effects on wildlife, including mortality and
change in habitat availability and suitability, are expected to be low.
442. Stantec stated that the new monopoles installed during the rebuild would not provide any
additional habitat or perching opportunities for raptors over what already occurred with the
existing line. It concluded that there would be no net change in availability of nesting or perching
opportunities for raptors and that no change in predation pressure on prey species was expected.
5.7 Application No. 1608649 – ENMAX application
443. ENMAX’s application involves modifications to its No. 25 and No. 65 substations. It did
not perform any environmental studies for this application, however, it conducted environmental
assessments in the ENMAX No. 65 substation application (Proceeding No. 1007) and in the East
Calgary transmission system upgrades and Shepard Energy Centre connection application
(Proceeding ID No. 1229), respectively. Both applications were approved by the Commission.
6 Electrical considerations
6.1 Views of the applicant
444. AltaLink stated that stakeholders raised concerns with the electric and magnetic field
(EMF) levels and the effects on human and animal health. AltaLink used a computer model
called Corona and Field Effects to model the expected EMF levels for the proposed 138-kV and
240-kV transmission lines and asserts that the results of the models are well below the
International Commission on Non-Ionizing Radiation Protection (ICNIRP) guidelines. The
profiles generated by the model show that the EMF levels are strongest when close to the lines
and diminish quickly as the distance increases from the lines. Objects such as wood or metal
would cause the electric field to diminish at an even faster rate or to be completely shielded.
AltaLink stated that at 150 metres from centreline, there are no material changes in the calculated
electric or magnetic fields levels when compared to existing levels for all proposed transmission
lines. The electric field 150 metres from centreline is expected to be zero kilovolts per metre
(kV/m) for all lines except for 1064L/1065L, where the reading is 0.1 kV/m. The magnetic field
150 metres from centreline would be between 0.1 to 3.7 milligauss (mG) for the 240-kV lines,
and 0.3 mG for the 138-kV lines. The ICNIRP guideline for electric fields exposure to the public
is 4.2 kV/m and 2,000 mG for magnetic fields.
445. AltaLink stated it treated health concerns seriously and hired Exponent Inc. to prepare a
report on research developments since the 2007 World Health Organization’s review on
extremely low frequency electric and magnetic fields and health. The report concluded that,
based on the research, EMF is not a cause of any long-term adverse effects to humans, plants or
animal health. AltaLink also noted that Health Canada and the World Health Organization,
75
Exhibit 364.00, Appendix L AltaLink Environmental Specifications and Requirements Windy Flats Project.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
98 • AUC Decision 2013-369 (October 7, 2013)
among other agencies, have reviewed EMF research and that none of these agencies concluded
that exposure to EMF from transmission lines is a cause of any long-term adverse health effects.
446. At the hearing, AltaLink’s EMF expert from Exponent Inc., Dr. L. Erdreich, explained
that the evidence that there are no health effects from EMF has been firmly established for some
time. Dr. Erdreich stated: “This [EMF] is not recognized as a health risk by any of the
international or national health authorities”76 and that the “idea that there’s no adverse health
effects from these kind of exposures that you can get in the ordinary environment has been pretty
solid, since, I would say, maybe 1998 and certainly after the 2007 WHO report.”77
447. AltaLink stated that transmission line magnetic fields are generally too weak to affect
pacemakers and that there are no cases of EMF from transmission lines interfering with
pacemakers recorded in the EMF literature. AltaLink stated that it would continue to assist
stakeholders who express concern with pacemaker interference by providing information on the
expected EMF levels so that the stakeholders could discuss the use of appropriate pacemakers
with their doctors.
448. The corona phenomena occurs when the surface of a transmission line conductor builds
enough electric charge to cause the surrounding air to ionize, potentially resulting in audible
noise and radio and television interference. AltaLink stated that the maximum audible noise from
the transmission lines is 22 decibels A-weighted (dBA) (Leq) for the north Foothills project,
eight dBA (Leq) for the south Foothills project, nine dBA (Leq) for the Langdon to Janet project,
and 10 dBA (Leq) for the Foothills 138-kV project at the edge of the right-of-way. These levels
of audible sound are well below the permissible sound level of 40 dBA (Leq) in rural areas under
fair weather conditions, as required by AUC Rule 012: Noise Control (AUC Rule 012).
449. AltaLink calculated radio interference levels to be below the applicable regulatory
standard for fair weather limits from 138-kV, 240-kV and 500-kV transmission lines and that it
would conduct radio interference measurements following construction to confirm regulatory
compliance.
450. According to AltaLink, it is unlikely that transmission lines would interfere with global
positioning system (GPS) signal reception under normal operation of the transmission line. It
will work with stakeholders to investigate potential GPS related concerns and mitigate any GPS
interference caused by its facilities.
451. AltaLink is confident that the transmission line will not affect cable television, wireless
internet or satellite television reception, but is committed to identifying sources of interference
and mitigate interference caused by its facilities.
452. AltaLink will also work with stakeholders in close proximity to the proposed 138-kV and
240-kV developments to assess potential induction on metallic objects, such as fences, irrigation
pivots and equipment, and install mitigation measures as necessary.
453. A report was prepared on behalf of AltaLink and Astral Media Radio G.P. (Astral) to
assess the impact of the proposed transmission line on CKMX’s AM transmitting facilities. The
76
Transcript, Volume 4, page 660, lines 16-18. 77
Transcript, Volume 4, page 662, lines 5-8.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 99
report concluded that the preferred route will result in lower radiation levels than the existing
line and have no adverse impact on the station. AltaLink developed several mitigation options
with Astral to resolve the reradiation issues posed by the north alternate route. It is aware of the
potential safety risk and has safety work processes during construction and maintenance
activities that mitigate any potential safety concerns to AltaLink personnel.
6.2 Views of the interveners
454. Members of the Diagonal group and Mattson group raised concerns about EMF and its
potential to be a carcinogen, and submitted potential impacts of EMF on animal and plant health,
sleep cycles, stress, and cancer. Mrs. McMurray testified that there is much unknown about EMF
and its potential impact on human and animal health.78 Mr. Nauta also expressed concerns about
EMF. He stated that his family should not have to put up with being exposed to the detrimental
health effects of the transmission line.79
455. However, no expert evidence was filed by the interveners and Dr. Erdreich was not cross-
examined by the interveners on potential health effects of EMF.
456. Astral is opposed to the north alternate route, 800 metres north of the centre of radiation
from its CKMX transmitter site. Astral expressed concerns related to the north alternate route
including potential for reradiation of the CKMX radio signal, and safety risk for the AltaLink
installation and maintenance staff. The north alternate route is 800 metres directly north of the
centre of radiation from the CKMX transmitter site. This route will result in double reradiation of
the existing line and may require expensive treatment or, in a worst case, relocation of the
CKMX transmitter site to avoid compromising the station’s coverage area and Industry Canada-
regulated protection patterns. Astral submitted that the strong radio frequency fields from the
CKMX transmitter site could cause interference to construction equipment, control and telemetry
systems, and introduce potential hazards to workers.
6.3 Commission findings
457. The Commission acknowledges the interveners’ concerns about potential impacts of
EMF from transmission lines on human health. However, the evidence submitted by AltaLink
regarding electric and magnetic fields of the proposed lines and their potential impacts is
uncontroverted.
458. Further, the results of AltaLink’s computer modelling of the EMF associated with the
proposed 138-kV and 240-kV transmission lines are credible. The profiles generated by the
model show that the electric fields and magnetic fields are strongest when close to the lines and
diminish quickly as the distance increases from the lines. The electric field levels at the edge of
the right-of-way are expected to be between zero and 3.5 kV/m for the various proposed
transmission lines, which is lower than the ICNIRP guideline of 4.2 kV/m. The magnetic field
levels at the edge of the right-of-way are expected to be between two and 96.1 mG for the
various proposed transmission lines, which is also lower than the ICNIRP guideline of
2,000 mG.
78
Transcript, Volume 7, page 1385, lines 6-16. 79
Transcript, Volume 8, page 1648, lines 22-24.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
100 • AUC Decision 2013-369 (October 7, 2013)
459. The Commission took note that on the proposed preferred route for the Langdon to Janet
application, the proposed transmission line would be within 50 metres of Mr. Mattson’s
residence. AltaLink modelled this area under profile A and found that the electric and magnetic
field at 50 metres in this area is 0.1 kV/m and 3.4 mG,80 which is significantly lower than the
ICNIRP guideline of 4.2 kV/m and 2,000 mG.
460. The Commission also considers persuasive the following statement in the Exponent, Inc.
report which reviewed current EMF health research, that:
The numerous national and international scientific agencies that have reviewed this
research have not concluded that exposure to ELF EMF is a cause of any long-term
adverse health effect.81
461. Furthermore, at the hearing, it was reiterated that the health studies have not established a
link between EMF and adverse health effects from electric and magnetic fields.
462. The conclusion of Health Canada that exposure to EMF from transmission lines is not a
demonstrated cause of any long-term adverse effect to human or animal health is considered
important to note. In addition, Health Canada states that:
At present, there are no Canadian government guidelines for exposure to EMFs at ELF.
Health Canada does not consider guidelines for the Canadian public necessary because
the scientific evidence is not strong enough to conclude that exposures cause health
problems for the public (Health Canada, 2010).82
463. Astral has not expressed particular concerns of potential reradiation from its CKMX
transmission site and safety risk in relation to the preferred route of the proposed transmission
line. The Commission accepts the conclusion from the study report that the preferred route will
result in lower radiation levels than the existing line and will have no adverse impact on the
station.
464. Lastly, based on the evidence submitted by AltaLink with respect to noise impacts from
the corona effects, the proposed transmission line and substations meet the requirements of AUC
Rule 012.
465. Accordingly, the Commission finds that there is no evidence in the proceeding that
suggests that there would be adverse impacts from electrical considerations related to the
proposed transmission lines and no evidence that the effects would differ between the preferred
and alternate routes.
80
Exhibit 85.00, EMF Material, page 18, Tables 1-12 and 1-13. 81
Exhibit 85.00, Exponent Inc, Research Developments Since the 2007 WHO Review of Extremely Low
Frequency Electric and Magnetic Fields & Health, page xii. 82
Exhibit 85.00, Exponent Inc, Research Developments Since the 2007 WHO Review of Extremely Low
Frequency Electric and Magnetic Fields & Health, pages 19.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 101
7 AltaLink Application No. 1608642 – Langdon to Janet
7.1 Preferred and alternate route selection
466. The Langdon to Janet project is located in the southeast part of Calgary and the Langdon
area. Seven kilometres of the proposed preferred Langdon to Janet route will be within the
ENMAX service area and will be owned by ENMAX; the remaining portion to the east of the
city limits of Calgary will be owned by AltaLink.
467. AltaLink proposed both a preferred and an alternate route for the Langdon to Janet
transmission line application. The proposed preferred route parallels an existing transmission line
(936L/937L) for almost all of its length, while the proposed alternate route is mainly a greenfield
route. These routes are depicted in Figure 21 below.
Figure 21 – Langdon to Janet project area map83
83
Exhibit 90.00, page 53. Figure 4-1 Final Routes.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
102 • AUC Decision 2013-369 (October 7, 2013)
468. The preferred route follows the existing 936L/937L line alignment from the Langdon
substation to the Janet substation. The existing 936L/937L line has slight realignment from its
original route as it approaches the Langdon 102S substation. AltaLink is also proposing a route
variant for the final 1.5 kilometres that enters the Langdon substation. The route variant would
continue straight on an abandoned CP railway line and turn south to the Crossings and Langdon
substations. The preferred route in the vicinity of the Langdon 102S substation and the route
variant are depicted in Figure 22 below.
Figure 22 – Preferred route/route variant for entering the Langdon and Crossings substations
84
7.2 Views of AltaLink
469. AltaLink stated that the preferred route is the lower impact route because it parallels an
existing transmission line for almost its entire length (94 per cent). Land fragmentation is
minimized on this route due to paralleling the proposed transmission line with the 936L/937
line.85 Also, paralleling would reduce both the required right-of-way and the amount of private
land required for the right-of-way. South of the Janet 74S substation, AltaLink owns
approximately 5.75 kilometres of an existing 90-metre wide right-of-way. This existing
right-of-way would be used for nearly one third of the total length of the proposed line. AltaLink
also stated that paralleling the line would create less potential for impacts on the environment
because the line would run adjacent to existing disturbances. Further, the preferred route for the
84
Exhibit 90.00, page 76. Figure 4-17 Detailed routes near the Langdon 102S substation. 85
Exhibit 90.00, AltaLink application, Langdon to Janet project, paragraph 14.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 103
Langdon to Janet area has less of an impact on agriculture, traversing only four kilometres of
cultivated land, compared to nine kilometres on the alternate route.86
470. AltaLink provided information about the proximity of existing residences to the proposed
and alternate Langdon to Janet routes.87 This information is reproduced in the table below:
Table 2. Proximity to residence comparison between the preferred route and the alternate route
Preferred route Alternate route
Residences within 150 metres of centreline 8 2
Residences within 800 metres from right-of-way edge
49 38
Residences within 150 metres of centreline now closer to transmission line
4 0
Residences within 800 metres of right-of-way edge now closer to transmission line
14 1
471. AltaLink acknowledged that there are more residences along the preferred route,
however, it submitted that the incremental impact of a route paralleling the existing 936L/937L
line was lower than the impact of a new greenfield alignment.88 AltaLink explained that when
planning the transmission line routing, it took into account that residents and landowners who
participated in the consultation were concerned with the viewscape to the west towards the
Rocky Mountains. AltaLink made available simulated photos of tower renderings, cross-
sectional views and visual simulations of the towers in the consultation documents and at the
open houses. It determined in the route determination process that the option to parallel the
existing 240-kV 936L/937L line would reduce the visual impact of the line and added that in
order to mitigate visual impacts, mainly tangent towers were proposed, which reduces the size of
the towers. It also proposed to match the existing tower locations of the 936L/937L transmission
line to reduce the impact of the towers.
472. Witnesses for AltaLink testified that from a visual impact perspective, the preferred route
would have an incremental impact while the alternate route would have a greater impact since it
is primarily a greenfield route.89
473. AltaLink emphasized that by paralleling the existing transmission lines, the preferred
route requires the acquisition of less private land for the right-of-way.
474. AltaLink submitted the following total project costs, within plus 20% or minus 10% of
the costs estimates:
Langdon to Janet transmission line preferred route: $99,184,000 including $22 million in
the ENMAX service area
Langdon to Janet transmission line alternate route: $113,357,000 including $5 million in
the ENMAX service area
86
Exhibit 90.00, AltaLink application, Langdon to Janet project, Table 4-1, page 82. Also see paragraph 274,
pages 82-83. 87
Exhibit 90.00, AltaLink Langdon to Janet Project application, page 82. 88
Exhibit 90.00, AltaLink Langdon to Janet Project application, page 74, paragraph 252. 89
Transcript, Volume 11, page 2319, lines 17-25.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
104 • AUC Decision 2013-369 (October 7, 2013)
475. AltaLink stated that if the alternate route were approved, there would be a schedule delay
which would result in increased project costs, such as incremental escalation and project carrying
costs. A normalized estimate of the alternate route would be $109 million, with the project costs
presented on a common basis by assuming the work starts at the same time and proceeds on the
same schedule.
476. AltaLink argued that the Mattson group submissions focused on residential impacts,
ignoring other factors that must be collectively considered in assessing overall impacts of
proposed transmission routes. It argued that the preferred route parallels existing linear
disturbances (including an existing transmission line and former railbed), utilizes an existing
92-metre right-of-way, and that all land, with the exception of the Schemenauers, were
purchased by members of the Mattson group after the existing transmission line was present.90
477. AltaLink has stated that Mr. Mattson qualifies for a buyout, which AltaLink has
expressed as its preferred course of action. It has also proposed a monopole option for
Mr. Mattson’s land that it argues would eliminate the need for additional right-of-way on his
land and allow him to continue conducting his existing operations.91
478. Ms. Buckley and Mr. Beck raised concerns over future developments on their property,
including the construction of a residence. AltaLink argued that the only location on their
property where Ms. Buckley and Mr. Beck would not be able to construct a residence would be
within the expanded right-of-way that extends 10 metres onto their property, and that as such,
nearly all of their property would be available for development.92
479. The McLaren/Carlson group raised concerns over the fragmentation of their land by the
alternate route. AltaLink argued that the McLaren/Carlson group would have one tower located
on their parcel along with the associated right-of-way. AltaLink proposed to place the tower near
the low-lying depression that is currently not being cultivated on the property and also addressed
the group’s desire to have the line placed on the southern quarterline. It stated that there were
environmental concerns with moving the proposed transmission line and that the neighbour to
the south indicated that the towers would create obstacles to farm around.
480. AltaLink acknowledged that the right-of-way of the alternate route would have an impact
on the Louson/Gleneagles properties but sited the proposed transmission line to minimize these
impacts as the line would be placed along the CN rail line.
7.3 Views of the interveners
7.3.1 Interveners on the preferred route
481. The Mattson group consists of Vern and Patricia Bretin, Tim Mattson, John Beck and
Shelia Buckley, Patricia and Kenneth Schemenauer, Ravinder Bath and Rejean Leveque. The
group submitted that the construction of the preferred route is not the lowest impact route and
that the application should be denied or alternatively, the alternate route be chosen. The Mattson
group stated that the preferred route has greater residential and agricultural impacts and fails to
provide adequate geographic separation of transmission lines. It also submitted that AltaLink
90
Exhibit 854.01, AltaLink Argument, paragraphs 298-299. 91
Exhibit 854.01, AltaLink Argument, paragraph 302. 92
Exhibit 854.01, AltaLink Argument, paragraph 308.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 105
overstated the alleged impacts along the alternative route and that such impacts could be
mitigated.
482. The Mattson group argued that AltaLink has given paralleling the transmission line with
existing transmission lines more importance than that of avoiding impacts on residences. There
are more residences along the preferred route within 150 metres and 800 metres of the
transmission line. According to the Mattson group, this is a more crucial metric to consider when
siting transmission lines.
483. The Mattson group indicated that on the preferred route, eight houses were within
150 metres of the proposed line and four of those were closer than 70 metres, with two being
within 35 metres of the centreline. The alternate route on the other hand had only two houses
within the 150 metre mark, the closest being 125 metres away. The Mattson group further
submitted that the route with a greater number of residences within 150 metres should be
considered as the higher impact route. The preferred route would also affect 11 more residences
at 800 metres than the alternate route. The Mattson group argued that these residential metrics
support its position that the alternate route is superior.
484. The Mattson group also took issue with AltaLink’s belief that because there is already a
transmission line in the area, the impact of adding another line would be incremental. The
residents do not welcome a new larger transmission line simply because there is an existing one
in the area.
485. The Mattson group disputed AltaLink’s narrow definition of paralleling existing linear
disturbances and stated that any actual physical disruption of land is considered a disturbance
which can include quarterlines and section lines. The alternate route would consequently not
fragment more land. The group contended that it demonstrated that the alternate route parallels
linear developments for 88 per cent of its length. With this assessment of the transmission line,
the alternate route compares favourably to the 94 per cent paralleling of the preferred route; and
that under this definition of paralleling linear disturbances, the alternate route is a superior route
to the preferred.
486. The Mattson group submitted that AltaLink has placed an over-reliance on paralleling
without regard to the impact created by imposing larger rights-of-way on landowners, which in
many cases, result in increased agricultural impacts. Paralleling existing transmission lines
requires increasing the required right-of-way to 92 metres on the preferred route, while the
right-of-way on the alternate route would only require 60 metres. This increase in the width of
the right-of-way on the preferred route would increase the impact for approximately
seven kilometres on cultivated lands along the preferred route. The Mattson group stated that the
placement of the second set of parallel towers would not only increase the additional time
required to maneuver around the extra towers, but also result in additional lost acreage due to
inefficiencies created in field-till patterns. With each additional tower placed on a farmer's lands,
cultivated land is lost to the transmission tower footprint.
487. The Mattson group also added that the presence of a diagonal route had a higher impact
for farming operations. While both routes have diagonal portions, the alternate route travels
approximately half of its length on quarterlines while the preferred route is completely diagonal.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
106 • AUC Decision 2013-369 (October 7, 2013)
488. The Mattson group stated that the double-parallel diagonal route would intensify the
effects on the agricultural impacts because the lines traverse the middle of the fields, creating
further obstacles for farmers to avoid. It further stated that diagonal routing is superior when it
presents an opportunity to avoid residences or other obstacles that may be close to quarterlines,
which is not the case in the alignment of the preferred route.
489. Furthermore, the group stated that the triple wide parallel circuits running to the north
from route marker B280 where the line turns north to the Janet 74S substation would carry a
significant amount of energy as these circuits are the main suppliers to the city of Calgary. The
ENMAX Energy Centre would also be located between route marker B280 and the Janet 74S
substation. It concluded that there is a reliability concern in this section which could be reduced
if the alternate route were chosen.
490. The Mattson group stated that the Transmission Regulation specifically states that it is in
the public interest to choose a higher cost route if that route provides geographic separation.
491. The Mattson group argued that the increased cost of the alternate route is justified by the
lower residential impact of the alternate route. It emphasized that the Commission has previously
recognized that it need not approve the lowest cost alternative and that the $9 million dollar
higher alternate route was a justified cost to avoid significantly higher residential impacts.
492. Ms. Buckley and Mr. Beck of the Mattson group testified that they purchased a 28-acre
lot and subdivided it into two residential, four-acre lots, with the intention that Mr. Beck would
use the remaining 20-acre lot for his residence. The two four-acre lots were sold with one being
developed and one remaining undeveloped. AltaLink purchased both of the four-acre lots.
Ms. Buckley and Mr. Beck requested that AltaLink also purchase their land, but AltaLink
refused because there was no residence on the property.
493. Ms. Buckley and Mr. Beck further explained that they do not wish to build a residence
within 150 metres of the line and that AltaLink normally buys out a property with a residence
within 150 metres of a transmission line of this size. They asserted that only a very small portion
of the land could be used for a residence.
494. Ms. Buckley stated that she owned land on the alternate route and did not object to the
alternate route because it would be located on the quarterline and would not interfere with her
hayfield or future development of the land.
495. Ms. Buckley also indicated that the trees help cover the view of the existing transmission
line to the north of their property. If the preferred route is chosen, many of these trees would
have to be removed, increasing the impact of the new line.
496. Mr. Bretin of the Mattson group testified that he purchased his property in 1986 and used
the land for a residence and agricultural purposes, including a flower and medicinal plants
business. The Bretins were also developing an equestrian facility on the land, comprised of a
show-jumping ring, a stable, a biogas facility and paddocks for up to 40 horses with all the
permits currently in place for the development.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 107
497. Mr. Bretin stated that they moved the location of their proposed equestrian facility to a
less desirable location on their land when they received the initial information about the
proposed route because the proposed transmission line would interfere with the planned
equestrian facility. As the public consultation progressed, a new proposal showed the lines
passing directly above the planned equestrian facility. Mr. Bretin testified that he was forced to
move the equestrian facility to a third, even less desirable location.
498. Mr. Bretin added that he already has a huge visual impact on his land from the existing
transmission line and the addition of a second line would increase this impact. In his opinion, the
attempted mitigation of moving the line from the centre of his property to the north side would
not relieve the visual impact. The line would also affect his new wheel-move irrigation system as
well as locations of some of the buildings planned to accompany the equestrian facility.
Mr. Bretin also testified that he has found many dead birds under the transmission lines on his
land.
499. Mr. Mattson of the Mattson group testified that he purchased his land because it was near
one of the truckers’ hubs in east Calgary, making this location ideal for his business as a
mechanic. Mr. Mattson constructed a 5,500 square foot shop which can hold two semi-trucks and
their attached trailers at the same time. He stated that if he had known that AltaLink was
proposing such a transmission line, he would never have gone through the effort and expense of
constructing his shop.
500. Mr. Mattson’s main concern was that the proposed transmission line was too close to his
residence and if a tower were to ever fall down there could be a potential loss of life. He was also
concerned about the potential health effects from the transmission lines and the potential
drainage along the right-of-way onto the remainder of his property. Mr. Mattson stated that
Township Road 233 is often flooded during spring melt or with heavy rainfall, and that once the
transmission line is in place, his property would be flooded by excess water and improper
drainage. Mr. Mattson testified that he had incurred significant expense to create a stormwater
management pond so he could develop his shop and was concerned that the construction of the
transmission line would have a negative effect on his pond.
501. Mr. Mattson also indicated that if the preferred route were constructed with lattice
towers, he would lose the parking area, and this would have an adverse effect on his business
because it would cause difficulties for customers having their vehicles towed in and dropped
off.93
502. The proposed transmission line would impact his property value because any interested
buyer in his land would lose interest when they would hear about the proximity of the proposed
transmission line. Certain banks that he spoke to also informed him that the value of his land
would be depreciated.
503. Mr. Mattson pointed out that AltaLink had proposed a monopole option which would
require no additional right-of-way on his land; he was still contemplating this option at the time
of the hearing.
93
Transcript, Volume 12, page 2465, lines 7-13.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
108 • AUC Decision 2013-369 (October 7, 2013)
504. Mr. Schemenauer of the Mattson group testified that he has resided along the preferred
route since 1979. The Schemenauers rent out their land and have spent considerable sums on
new outbuildings and landscaping of the property. Mr. Schemenauer stated that it was always his
plan to subdivide his 45 acres into 10 four-acre lots and sell those off to fund his retirement, but
is concerned about his plan if the proposed preferred route is approved. He also has health
concerns with living in close proximity to a transmission line and stated that his wife is afraid of
transmission lines.
505. Mr. Levesque of the Mattson group testified that he chose his property on the preferred
route in 2005 because it was the only property from which he had a good view of both downtown
Calgary and of the mountains. Mr. Levesque resides on his property, but also carries his stucco
business, and recently constructed a large shop on his property. He is concerned about the
decrease in value of his property and the impact on his view. He believes that there would need
to be some tree clearing in order to place the transmission line on the preferred route,
approximately 550 feet, from his property. Once the trees were cleared, he would be able to see
the proposed transmission line very well from that distance, and his property value would
decrease accordingly.
506. Camrock Capital Partners GP (40) Ltd. was not present at the hearing, but stated in its
objection to the preferred route that future liquidity and property value of its property located at
36 Industrial Way in southeast Calgary could be affected if the preferred route were approved
and that the line should be relocated one kilometre to the east.
507. Baldev Joneja was not present at the hearing, but stated in a written submission that his
property, located in the northwest and southwest quarters of Section 15, Township 23, Range 28,
west of the Fourth Meridian, would be impacted by the psychological and physical effects of
EMF along the property line and that the Commission should approve the alternate route.
7.3.2 Interveners on the alternate route
508. Louson Investments Ltd. and Gleneagles Investments Ltd. (Louson and Gleneagles)
objected to both the Foothills Area Transmission Development need and to the Langdon to Janet
application. Louson and Gleneagles stated that the FATD NID is not in the public interest and in
the alternative, if the NID is approved, that the preferred route is a superior route.
509. Louson and Gleneagles submitted that their land, located at NE 32-23-28-W4M and
NW 33-23-28-W4M in Rocky View County, has potential for future industrial or business
development as part of the Highway 560/Glenmore Trail joint industrial corridor. The proposed
alternate route would negatively impact the industrial development potential of their land. The
alternate route could influence such development and would provide a visual barrier to the north
portion of the Louson and Gleneagles property.
510. Louson and Gleneagles argued that by contrast to the alternate route, the preferred route
would have a lesser impact because it parallels an existing transmission line and although there
are a greater number of residences in proximity to the proposed preferred route, these residences
are already exposed to an existing transmission line on the preferred route, meaning that there
would be no brand new exposures on the preferred route.94
94
Exhibit 0860.02, Final Argument of Louson Inverstments and Gleneagles Investments, paragraph 9.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 109
511. Also, the alternate route, which is a greenfield route, would have greater negative impacts
on previously undisturbed land. The alternate route only parallels a railway for less than
one kilometre, and a future stormwater conveyance plan, which is depicted to follow natural
drainage features including sensitive wetlands, currently does not exist and may never exist.
Louson and Gleneagles acknowledged that the preferred route also passes through the same key
area for industrial development, but that area already has an existing development constraint.
512. The McLaren/Carlson group stated that the alternate route would sever and fragment its
land, identified as industrial according to the intermunicipal development plan between the City
of Calgary and Rocky View County.95 Ms. Carlson clarified that although they do not yet have
the property rezoned for industrial development, they are looking to have it rezoned and sold as
industrial land at some point in the future.96
513. An expert report was submitted on the group’s behalf by McNally Land Services Ltd.,
which evaluated the routing aspects of both the preferred and alternate routes. This report
concluded that the preferred route has a lesser impact than the alternate route in terms of all
factors, except the number of residences within proximity of the transmission line. The report
added that if the proposed alternate route were changed to the original alternate route proposal,
which followed quarterline boundaries, it would mitigate the severance and fragmentation of
land of the proposed alternate route currently before the Commission.
514. The McLaren/Carlson group proposed that siting 94 per cent of the route adjacent to
existing linear disturbances was a well-accepted practice. The group cited the Western Alberta
Transmission Line Decision 2012-327, in which the Commission determined that paralleling
existing transmission lines results in lower impacts, including less fragmentation of the
environment, fewer new access trails, reduced overall operation costs and less visual impacts
than placing the transmission line on a greenfield route.
515. The McLaren/Carlson group submitted that the only negative factor associated with the
proposed preferred route was that there would be more residences exposed to the transmission
line than on the alternate route. However, the McLaren/Carlson group further submitted that the
impact assessment should not be narrowed to the point where residential impact is the ultimate
deciding factor and that when all impacts are examined among the preferred and alternate
Langdon to Janet routes, the impacts along the alternate route would be greater as it is a
greenfield route.
516. Daniel, Julie, Deborah and Michael Meier (the Meiers) objected to the Langdon to Janet
alternate route. The Meiers stated that they have serious concerns with the potential negative
health effects of transmission lines. They also objected to the construction of the alternate route
on the west side of their property as it would obstruct their view of the city of Calgary, the
Rocky Mountains, and would affect their day-to-day enjoyment of the property.
517. The Meiers also submitted that the northeast quarter of Section 26, Township 23,
Range 28, west of the Fourth Meridian was purchased as an investment property because of its
potential for a subdivision as it is adjacent to the town limits of Chestermere Lake. The Meier
95
Exhibit 600.17, Review of the Preferred and Alternate Routes of the Foothils Area Development East Region
Langdon to Janet Project, March 21, 2013, page 3. 96
Transcript, Volume 12, pages 2527-2528, lines 22-25, 1-6.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
110 • AUC Decision 2013-369 (October 7, 2013)
land would have five towers; they are concerned that these towers would reduce their ability to
develop the land and reduce the value of the property due to the obstructed view. Also, the
Meiers stated that the transmission towers may affect their ability to check the fences used to
keep in their livestock.
518. The Meiers submitted that the proposed preferred route has an incremental impact
because it would parallel an existing transmission line and is therefore more favourable than the
alternate route. They argued that paralleling linear disturbances have historically been found to
result in less overall impact than greenfield routing and cited the Western Alberta Transmission
Line in support of its argument. The Meiers stated that regard must be given to the fact that
AltaLink is committed to mitigating the visual impacts by matching the tower placements of the
existing transmission line.
519. In reply argument, the Meiers added that the impact of the greenfield alternate route
would be greater because of the number of corners that are required for the alternate route. At
least seven 90 degree turns were required on the proposed alternate route and each of those turns
would require a dead-end structure. The same section of transmission line on the preferred route
would require only one dead-end structure. The structures placed on the greenfield route would
add to the impact because of the varying structure heights. The preferred route would be the less
costly of the two routes.
520. The Forster Family Trust owns land on the alternate route from Langdon to Janet in the
north half of Section 35, Township 23, Range 28, west of the Fourth Meridian. The trust stated
that it was intervening to oppose the alternate route. In its argument, the trust supported the
Meiers, the McLaren/Carlson group, Louson Investments Ltd. and Gleneagles Investments Ltd.,
and their arguments against the alternate route.
7.3.3 Intervener objecting to preferred route variant
521. 1297833 Alberta Ltd., the owner of the southeast, northeast and northwest quarters of
Section 21, Township 23, Range 27, west of the Fourth Meridian, objected to the variant option
to the preferred route. 1297833 Alberta Ltd. stated that the future visual impact of the line would
have a negative effect on future residential development on its land.
522. 1297833 Alberta Ltd. argued that paralleling linear disturbances has historically been
found to result in less overall impact than greenfield routing. It also cited the Western Alberta
Transmission Line decision in which the Commission stated:
In the past, the Commission and its predecessors have stated that, generally,
transmission lines should be placed parallel to existing linear disturbances. Paralleling
is also supported in provincial documents and legislation including the Alberta Land
Use Framework, the Transmission Regulation, and the Environmental Protection
Guidelines for Electric Transmission Lines.97
97
Decision 2012-327, Western Alberta Transmission Line Project, December 2012, paragraph 951.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 111
7.4 Commission findings
523. The Commission examined the proposed Langdon to Janet transmission line siting on the
basis of residential impacts, visual impacts, agricultural impacts, electrical considerations,
environmental impacts and of cost.
524. The number of residences within 150 metres and 800 metres of the transmission line
favours the alternate route. However, many of the residences on the preferred route are on the
other side of the existing transmission line and would be no closer to a transmission line if the
preferred route were chosen. Furthermore, because the preferred route parallels the 936L/937L
line, the potential impacts on the residences that are within 150 metres would be incremental, as
opposed to those residences within 150 metres on the alternate route.
525. The Commission finds that paralleling the existing transmission line corridor south from
the Janet substation to the Shepard corner and then paralleling the 936L/937L line east of the
Langdon substation favours the preferred route because the proposed right-of-way only requires
an addition to the existing right-of-way rather than a new right-of-way. As a result, the potential
impacts are reduced from an environmental perspective because the land has been previously
disturbed. The preferred route has less potential for environmental impacts than the alternate
route because the alternate route attempts to follow the future Shepard Regional Drainage Plan,
which is designed to follow low-lying areas and wetlands. The preferred route parallels an
existing transmission line for almost the entirety of the route.
526. The Commission acknowledges that tree clearing around the existing transmission line
would increase the view of the transmission line, as stated by members of the Mattson group, and
also recognizes that the alternate route for the Langdon to Janet transmission line would have a
significant number of dead-end towers with varying heights and widths.
527. There is generally less incremental visual impact of the additional transmission line
paralleling the existing 936L/937L line to the east of route marker B280, and the transmission
line corridor to the north of route marker B280 than that of the mainly greenfield option of the
alternate route.
528. In addition, the preferred route parallels existing transmission lines of comparable size
throughout the transmission line length, which results in an incremental impact. AltaLink is
committed to staggering the towers to match the existing 936L/937L line to mitigate some of the
potential impacts throughout the length of the line.
529. The preferred route has less of an agricultural impact because it crosses less cultivated
land and results in less fragmentation of land as it requires an addition to the width of the
existing right-of-way, instead of new right-of-way.
530. The Commission also finds that the preferred route is superior to the route variant option.
The route variant option would require the removal and relocation of a 1.5-kilometre section of
the 936L/937L line as it enters the Crossings substation. The removal and relocation of the
936L/937L line would place it in close proximity to three residences to the north of the current
routing.
531. The preferred route costs approximately $14 million less than that of the alternate route if
schedule delays are factored in, but will cost $9 million less without the inclusion of any delays.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
112 • AUC Decision 2013-369 (October 7, 2013)
532. The Mattson group argument, that the proposed paralleling of the preferred route results
in a reliability issue, was not persuasive because no evidence was tendered in this regard and the
AESO has ascertained that the proposed routes meet the Alberta Reliability Standards.
533. Based on the above, the Commission concludes that the preferred route for the proposed
Langdon to Janet transmission line has less of an overall impact than the alternate route and is
therefore in the public interest.
534. The Commission chooses the monopole option past the property of Mr. Mattson. This
option would span monopole structures from route marker B260 to route marker B265 across the
northwest quarter of Section 13, Township 23, Range 28, west of the Fourth Meridian. This
option was put forth to reduce the impacts on Mr. Mattson, his family and his business. The
monopole option will not require a right-of-way on Mr. Mattson’s property and has the potential
to reduce the tower heights. The monopoles range in height from 41 metres to 44 metres while
the lattice structures are between 46 metres and 58 metres.98 Should Mr. Mattson agree to a
buyout of his property before measures are taken to implement the monopole option, the
Commission directs AltaLink to use lattice towers for this section of the transmission line.
8 AltaLink Application No. 1608637 - north Foothills transmission development
8.1 The preferred and stakeholder-proposed Foothills substation site selection
8.1.1 Introduction
535. AltaLink’s preferred site, identified as the D8 site, for the new Foothills 237S substation
is located at NW 35-18-28-W4M, southeast of High River. AltaLink has acquired the entire
quarter section of land on which the substation site would be located to provide room for
expansion. This site was chosen based on the parcel's suitability in relation to the substation
footprint, the interconnection of proposed and future 500-kV and 240-kV transmission lines, the
138-kV connection to High River and Okotoks, and the 240-kV interconnection of local
generation.
536. AltaLink amended its application to include a stakeholder-proposed Foothills 237S
substation site, identified as the D12 site, as an alternate site for the substation, which is located
in the NW 8-19-27-W4M. This site was within one of the substation target areas originally
identified during AltaLink’s preliminary and detailed routing stages, but was dropped from
consideration because the preferred D8 site would provide a better opportunity to reuse existing
infrastructure to connect to local generation with the least amount of new 240-kV line, and
would result in a better environmental route option to connect to the High River 65S and
Okotoks 678S substation. While this evaluation still applies, AltaLink believed that the
stakeholder-proposed D12 site represents a viable alternative and, therefore, added it for the
Commission’s consideration.
98
Transcript, Volume 11, pages 2184-2185, lines 15-25, 1-3.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 113
537. The following interveners expressed views regarding the selection of the Foothills 237S
substation site:
The Randle group was opposed to the preferred D8 site. The group consists of
Fred Randle, the estate of his late wife, Patricia Randle, and two family corporations,
F. R. Farms Ltd. and Randle Farms Ltd. The group’s 17.5 quarter sections of land are
located at the intersection of the north Foothills transmission project, the Foothills
138-kV project and the south Foothills transmission project. The D8 site is on cultivated
land and is adjacent to three quarter sections of the Randle group’s lands.
Randy and Gerry Nauta, who own lands both on the preferred and alternate
Foothills 138-kV transmission line routes, expressed a preference for the D12 site at the
hearing due to their concerns with aerial spraying. Unlike the D8 site, the stakeholder-
suggested 138-kV route, originating from the D12 site, will not cause two sides of their
parcel to be bordered by the proposed transmission line.
Albert Weeks, Craig and Carla Woolridge are opposed to the alternate D12 site and the
stakeholder-suggested 138-kV route originating from the D12 site. The Woolridges are
also opposed to the alternate route in the south portion of the proposed 1106L/1107L line.
Their general concerns include property value, visual impact, electric and magnetic
fields, and increase in traffic and noise. These individuals did not attend the hearing or
make any further written submissions.
8.1.2 Views of AltaLink
538. AltaLink stated that the D8 and D12 sites are fairly comparable and both sites meet the
functional specifications stipulated by the AESO. However, AltaLink is of the view that the D8
site is preferable from an overall impact perspective.
539. AltaLink provided a table99 comparing a number of metrics for the preferred D8 site and
the alternate D12 site in its amendments submitted on December 21, 2012. The $0.9 million cost
difference indicated in this table represented the transmission line costs only and did not include
the costs of the D12 site. AltaLink subsequently indicated in its responses to the information
requests from the Randle group, and confirmed in its reply evidence, that the total cost associated
with the Foothills 138-kV project for the D12 site is approximately $0.5 million100 more than the
D8 site.
99
Exhibit 492.00, AltaLink facility application amendments, page 2, Table 1. 100
Exhibit 720.01, AltaLink reply evidence, page 15, paragraph 62.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
114 • AUC Decision 2013-369 (October 7, 2013)
Table 3. Siting comparison between the preferred site and alternate site
Potential site: D8 D12
Preferred site Stakeholder-proposed site
1. Impacts at substation footprint
Closest residence 557 m 471 m
Land use Agricultural - Cultivated Agricultural – Grazing
Environmental Preferred Less Suitable
Access Existing (400 m from Highway) Existing (2,200 m from
Highway)
Highway) 2. Interconnection of future transmission
Future to 500 kV Beside Beside
Future 240 kV Open Open
3. Connection to Okotoks and High River
Km of 138-kV line (from B20) 6.0 km 5.5 km
Potential parallel of existing
transmission line
0 0
Potential parallel of existing
road
6.0 km 5.5 km
Residences within 150 m 2 3
Residences within 800 m 6 7
Number of heavy angle structures 6 3
Incremental cost (approx.
$300,000/heavy angle)
N/A ($0.9 M)
4. Interconnection of local generation
Length of 240-kV line to connect
to 911L
3.5 km 9.5 km
540. AltaLink submitted that the D8 site provides the best opportunity to reuse existing
infrastructure, namely a portion of the existing 911L line passing the northeast corner of the town
of High River, to connect future local generation such as TransCanada’s 350-MW Saddlebrook
power plant located near Magcan 142S substation. AltaLink stated that by doing so, the least
amount of new 240-kV transmission line, 3.5 kilometres, would be required. Whereas if the
D12 site were approved, the future Saddlebrook generation interconnection would require
approximately 9.5 kilometres of new 240-kV transmission line.
541. AltaLink submitted that the D8 site is preferable from an environmental perspective
because the D12 site has higher habitat value than the D8 site. AltaLink explained that the
D12 site is part of a contiguous block of habitat and, taking into account wildlife, is considered
significant native prairie. An example of the higher habitat value is the documented presence of
the Sprague’s Pipit, a Species at Risk Act listed bird, that is seldom seen so close to Calgary.
542. AltaLink submitted that at the D8 site, the footprint would be on cultivated land and the
displaced wildlife species would have a variety of other easily accessible and similar foraging
options nearby. The footprint at the D12 site would be on the reverting tame pasture, used as part
of a larger block of permanent or breeding habitat by a number of wildlife species, and in
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 115
relatively short supply locally. Despite different environmental considerations, Stantec submitted
that both sites are viable from an environmental perspective.
543. It added that the D8 site is a more suitable site from a wildlife habitats perspective,
despite being on the margin of an environmentally significant area. However, Dr. Gahbauer of
Stantec admitted that this preference is somewhat offset by the higher incremental potential for
collision risk at the D8 site, related to the additional 138-kV transmission lines connecting to the
D8 site from the west. Given that the D8 site is approximately 900 metres away from
Frank Lake, Stantec stated that the incremental risk posed by the 138-kV transmission lines is
expected to be low and can be further mitigated through employment of bird markers. Stantec
agreed that, compared to the D12 site, the D8 site might have a higher risk of potential avian
collision due to the proximity of Frank Lake. However, Stantec reiterated the conclusion from
the recent Avian Power Line Interaction Committee’s report that there is a much reduced risk of
bird mortality once the transmission lines associated with a substation site are beyond 400 or 500
metres.
544. With respect to the proposed 138-kV 434L/646L line routing, AltaLink stated that the
stakeholder-suggested route originating from the D12 site is generally comparable to the
preferred route originating from the D8 site. However, the preferred route is superior from an
environmental perspective. The preferred route is within a previously disturbed road allowance,
while the stakeholder-suggested route abuts a greater area of native prairie and has a somewhat
higher potential for effects on wildlife.
545. With respect to the proposed 240-kV 1106L/1107L line routing in the north Foothills
project and proposed 1037L/1038L line routing in the south Foothills project, AltaLink indicated
that if the D12 site were approved, these two routes would shift slightly in that the 1037L/1038L
line would incorporate the 1106L/1107L line’s preferred route, or the preferred route variant,
between the D8 and D12 sites. Conversely, the 1106L/1107L line would commence at and travel
north from the D12 site.
546. AltaLink submitted that the D8 site offers better cost benefits than the D12 site. When the
cost impacts to the north Foothills transmission project, the Foothills 138-kV project and the
south Foothills transmission projects are considered collectively, the D8 site is estimated to cost
$3.1 million less than the D12 site.
8.1.3 Views of the interveners
The Randle group
547. With respect to the Saddlebrook power plant interconnection, the Randle group argued
that little weight should be given to the fact that the D8 site allows for a future interconnection
by reusing the 911L line because no interconnection application has been filed. Further, the lack
of a detailed siting study for the plant, and the uncertainty of its expected in-service date,
mitigate against the consideration of the interconnection as a factor in favour of the D8 site. The
Randle group referred to the testimony from the representative of the Town of High River that
the portion of the existing 911L line that could potentially be reused traverses the northeast
corner of the town’s newly annexed area, which represents a development constraint within the
area. The Town of High River urged AltaLink to consider the removal of this portion of the 911L
line. It stated that both the AESO and AltaLink acknowledged that the cost of interconnecting the
Saddlebrook power plant will be borne by TransCanada.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
116 • AUC Decision 2013-369 (October 7, 2013)
548. With respect to the interconnection of future transmission lines, the Randle group
submitted that the proposed Foothills 237S substation will be a major hub with a large number of
future interconnections of 500-kV, 240-kV and 138-kV transmission lines. As stipulated in the
AESO’s functional specification for this substation,101 the ultimate configuration at Foothills
237S substation is designed to have two 500-kV line connections, two 500/240-kV transformers,
ten 240-kV line connections, two 240/138-kV transformers and six 138-kV line connections.
Among these future transmission line interconnections, two 240-kV lines to ENMAX No. 65
substation, two 240-kV lines to Windy Flats 138S substation, two 240/138-kV transformers, one
138-kV line to High River 65S substation, and one 138-kV line to Okotoks 678S substation are
proposed in the FATD proceeding. The two 240-kV lines to Sarcee 42S substation contemplated
by the AESO are not required until 2019 and beyond, based on the AESO’s most recent planning
study. The Randle group argued that the D12 site would keep a large substation away from an
internationally recognized environmental area and that this benefit outweighs the relatively
minimal cost-saving associated with the D8 site.
549. The Randle group submitted that the D12 site is preferable from an environmental
perspective because it is 2,000 metres away from Frank Lake, in comparison to the D8 site,
which is 900 metres away. It added that Figure 23 reproduced from the Stantec’s report102
illustrates the boundaries of the Frank Lake environmentally significant area and important bird
area. The D8 site is within the Frank Lake environmentally significant area complex, which is of
international significance with seasonally important waterfowl use; while the D12 site is outside
of the environmentally significant area. The D8 site is crossed by an important bird area, while
the D12 site is approximately 1,200 metres outside of the important bird area. The D8 site is also
within a mapped aquatic environmentally significant area, while the D12 site is not.
101
Exhibit 18.00, AESO’s Foothills area transmission development east region (FATD East) functional
specification, pdf page 32. 102
Exhibit 720.04, AltaLink reply evidence Appendix C environmental considerations, pdf page 11.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 117
Figure 23 – Frank Lake environmentally significant area and important bird area
550. Mr. Cliff Wallis, the Randle group’s environmental expert, submitted that the D12 site
presents a lower collision risk to waterfowl because it is more than twice the distance from
Frank Lake than the D8 site. Mr. Randle testified that every year, trumpeter swans, tundra swans
and numerous other water birds use the lands in and around the D8 site, particularly in the spring
migration. Both Stantec and Mr. Wallis agreed that Frank Lake is an important staging site for
trumpeter swans during migration. The Randle group submitted that trumpeter swans are
classified as an endangered species under the Wildlife Regulation, Alta Reg. 143/1997. Based on
Stantec’s review of the eBird database, there are peak numbers of trumpeter swans at Frank Lake
in March and April during spring migration and a larger peak (more than 500 individuals
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
118 • AUC Decision 2013-369 (October 7, 2013)
recorded by one observer) in October and November during fall staging. Stantec observed
50 swans feeding at the D8 site in its field investigation conducted on March 27, 2013.
Approximately 20,000 northern pintails, along with many other bird species, were spotted during
Stantec’s field survey. Mr. Wallis indicated that the Ducks Unlimited normal setback guideline is
1.6 kilometres or more. The Randle group concluded that the further distance from Frank Lake
favours the D12 site in terms of avian mortality risk.
551. The Randle group pointed out that migratory waterfowl, including trumpeter swans and
tundra swans, also frequently use a series of sloughs or potholes in the general area to the west
and north of the D8 site. The group was concerned that the numerous future transmission lines in
and out of the substation will pose a significant risk for birds between the cultivated fields on and
near the D8 site, potholes and Frank Lake. Mr. Wallis also confirmed that reverting pasture has
not been widely used by waterfowl. Stantec acknowledged that the birds like to forage on
cultivated land more than on native prairie.
552. The Randle group submitted that the D12 site is preferable because it is farther away
from Frank Lake and will have fewer environmental impacts than the D8 site, particularly with
respect to migratory wild fowl. The group emphasized that the environmental advantage for the
D8 site is especially true given that the Foothills 237S substation is likely to be one of the largest
substations in Alberta with numerous future interconnections contemplated.
553. The Randle group added that the D8 site and the preferred 138-kV route would also have
a disproportionately large agricultural impact on the Randle lands as the routing places a
transmission line on two sides of five Randle quarter sections. Mr. Randle testified that aerial
spraying is particularly difficult when the transmission lines are on more than one side of a field.
The group also contended that its farmland is some of the best farmland in the area, and that the
property tax for the D8 land is assessed at nearly double that of the D12 land. It stated that
AltaLink acknowledged that cultivated land is typically more valuable than pasture land.
Randy and Gerry Nauta
554. Mr. Nauta favoured the D12 site with respect to his concerns about aerial spraying. The
preferred 138-kV line route associated with the D8 site will border his parcel at
NE 10-19-28-W4M on two sides. He testified that having the 138-kV lines on two sides of his
land would impede aerial spraying and consequently cause some crop losses.
555. Mr. Nauta submitted that the D8 site is prime agricultural land. The D12 site is better
suited for a substation site because it is saline pasture land and of poorer soil quality than the D8
site, as is the land running north of the D12 site.
TransCanada
556. TransCanada submitted that the connection between the Saddlebrook power plant and the
transmission system will be at TransCanada’s cost, therefore any change to the location of the
Foothills 237S substation will have a direct impact on the economic viability of the Saddlebrook
power plant. The D12 site will likely require six to seven additional kilometres of transmission
line to connect the Saddlebrook power plant to the transmission system, which will increase the
connections costs.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 119
557. TransCanada concurred with AltaLink that the D8 site appears to be preferable from an
environmental perspective and future construction of transmission lines terminating at the
Foothills substation. For example, the risk of bird strikes did not correlate with the distance from
transmission lines or substations. TransCanada submitted that it will be difficult to find a more
northerly route from the D12 site for a transmission line to serve load on the west side of Calgary
and communities in the west of the province, on account of significant residential development
between Okotoks and High River.
8.1.4 Commission findings
558. With respect to local generation interconnection, the AESO has not yet filed an
interconnection application for the future Saddlebrook power plant. Neither has AltaLink
performed any detailed siting study or undertaken any public consultation. The AESO testified
that the Saddlebrook power plant is currently planned to be connected to the Foothills 237S
substation by using a portion of the 911L line. However, the AESO has not yet finalized its
interconnection plan. Based on the uncertainty of the Saddlebrook power plant’s interconnection
plan, the Commission is of the view that the Saddlebrook power plant interconnection is not a
factor in choosing the substation site.
559. The Commission finds that the D12 site is superior to the D8 site from an environmental
perspective for the following reasons. Unlike the D8 site, the D12 site is situated outside of the
Frank Lake environmentally significant area, which is of international significance, and also
outside a mapped aquatic environmentally significant area. Compared with the D8 site whereby
proposed transmission lines will cross an important bird area, the D12 site is approximately
1,200 metres outside of the important bird area. Such a distance presents a lower collision risk to
waterfowl because there are a great number of migratory waterfowl, including trumpeter swans,
classified as an endangered species, flying around the D8 site more frequently than the D12 site.
The Commission agrees with the Randle group that the proposed Foothills 237S substation is
likely to be one of the largest 240/138-kV substations in the province and a major substation in
southern Alberta. Due to the ultimate size of the substation and potential multi-directional line
connections terminating at the substation, the Commission finds that it is better, from an
environmental perspective, to keep the substation site away from the internationally-significant
environmentally significant area that is Frank Lake.
560. The Ducks Unlimited normal setback guideline is 1.6 kilometres or more. In addition, the
significant number of northern pintails, swans and other bird species recently spotted at the
D8 site rather than at the D12 site convinced the Commission that the distance from Frank Lake
is a factor in relation to wildlife. The distance from Frank Lake to the D12 site is more than twice
the distance to the D8 site. Therefore, the Commission disagrees with Stantec that the distance
between the Foothills substation and Frank Lake is less relevant to bird collisions once the
distance is beyond 400 to 500 metres.
561. The D8 site is cultivated land while the D12 site is reverting tame pasture. The
Commission accepts Mr. Wallis’ view that reverting pasture has not been widely used by
waterfowl. Further, it is acknowledged by both AltaLink and the Randle group that the birds like
to forage on cultivated land more than on native prairie.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
120 • AUC Decision 2013-369 (October 7, 2013)
562. With respect to the 138-kV 434L/646L line routing, the Commission agrees that the
preferred route originating from the D8 site is comparable with the stakeholder-suggested route
originating from the D12 site. The two routes have different potential environmental impacts in
that the stakeholder-suggested route is adjacent to native prairie, while the preferred route is in
close proximity to Frank Lake.
563. The Commission finds that the location of the Foothills 237S substation will not cause
any material difference between the D8 and D12 sites where the 240-kV 1106L/1107L line and
the 1037L/1038L line routings are concerned. It will simply shift the termination points between
the two routes.
564. Both the D8 and D12 sites are next to the existing 500-kV 1201L line and open to
interconnect to the nearby 240-kV transmission lines. With respect to connecting to Okotoks and
High River, the D8 and D12 sites have very similar impacts in terms of residences, connection
distance and potential to parallel existing transmission lines and roads. Further, compared with
the D8 site, the stakeholder-suggested route originating from the D12 site would require half the
number of heavy angle structures.
565. In the Commission’s view, the D8 site, with its preferred 138-kV line route, poses a
greater agricultural impact on the lands of the Randle group and the Nauta family than the D12
site, with the stakeholder-suggested 138-kV line route. Even if the D12 site were selected, the
Randle group’s land would nonetheless be bisected.
566. With respect to cost consideration, the incremental cost associated with the D12 site is
approximately $3.1 million, which is less than 0.4 per cent of the entire FATD project cost. As
stated in previous decisions, cost is not an overriding consideration for the Commission, and in
this case, the environmental factors outweigh the cost.
567. Consequently, the Commission concludes that the D12 site is a better site because it has
lower overall impacts than the D8 site.
8.2 The preferred and alternate 240-kV transmission routes
8.2.1 Introduction
568. AltaLink proposed four routes for the new 240-kV double-circuit 1106L/1107L line
connecting the Foothills 237S substation to the ENMAX No. 65 substation in southeast Calgary,
in the north Foothills project. There is one preferred route and three alternate route segments: the
north alternate route, the Frank Lake alternate route and the preferred route variant. The north
alternate route is an alternative route to the diagonal portion of the preferred route, north of the
Bow River. The Frank Lake alternate route and the preferred route variant are two alternative
routes near Frank Lake. The Frank Lake alternative route proposes a route further away from
Frank Lake, while the preferred route variant is closer to Frank Lake. These routes are shown on
the map below.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 121
Figure 24 – North Foothills route options
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
122 • AUC Decision 2013-369 (October 7, 2013)
569. The preferred route begins at the proposed Foothills 237S substation using steel lattice
structures to the northwest side of Frank Lake before connecting with the 1201L line. From
there, the line continues north, paralleling the 1201L line until it meets the 850L line. The route
turns northwest, where it will utilize triple-circuit structures paralleling the existing alignment of
the 850L line to the junction of the 850L/911L line. This section of the existing 850L line would
be replaced by the new triple-circuit structures. Where the route turns north, it will utilize
monopole double-circuit structures for the final three kilometres to the ENMAX No. 65
substation. The existing 850L/911L line will be rebuilt along this segment to accommodate the
paralleling of the lines in the right-of-way.
570. The preferred route generally parallels the existing 1201L line to the north, the 138-kV
850L line to the northwest and the 240-kV 911L/138-kV 850L lines to the north again.
Specifically, the preferred route parallels or utilizes existing rights-of-way by:
paralleling approximately 28 kilometres of the 1201L line
paralleling approximately 13 kilometres of the 850L line
utilizing approximately three kilometres of the 911L/850L line right-of-way
571. In the north portion of the project, the preferred route parallels the existing diagonal
138-kV 850L line. Instead, the north alternate route segment predominantly follows quarterlines
on agricultural lands and parallels Highway 22X north of the Bow River.
572. In the south portion of the project, the preferred route predominantly parallels the existing
1201L line. AltaLink has two alternate route segments originating from its preferred D8 site for
the Foothills 237S substation: the Frank Lake alternate route segment and the preferred route
variant. The Frank Lake alternate route segment is farther from Frank Lake, which provides
habitat to waterfowl including several species of management concern. This route segment
proceeds north for approximately nine kilometres from the Foothills 237S substation and then
east for approximately three kilometres, where it connects to the preferred route. The preferred
route variant runs adjacent to the existing 1201L line structures and involves the placement of up
to three structures for the line to cross Frank Lake.
573. Choosing the stakeholder-suggested D12 site for the Foothills 237S substation would
leave only one route option, the preferred route, in the south portion of the project, which would
start from the D12 site, run east to connect to the preferred route and then follow the preferred
route to the north and eventually terminate at the ENMAX No. 65 substation. The following map
illustrates the alternate Foothills 237S substation site (the D12 site) proposed in AltaLink’s
facility application amendments.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 123
T.18
T.19
HIGH RIVER
BLACKIE
2
2
543
783
2A
2A
23
23
799
HIGHWOOD RIVER
FRANK
LAKE
PREFERRED FOOTHILLS237S SUBSTATION SITEIN APPLICATION
1201L
PROPOSED TRANSMISSION LINES FILED IN ORIGINAL
PROPOSED SUBSTATION SITE AND TRANSMISSION
EXISTING TRANSMISSION LINES
911L
R.27W.4M.R.28R.29
FOOTHILLS 237SSUBSTATION SITEIN AMENDMENTS
ALTERNATE
APPLICATIONS
LINE ADDITIONS PROPOSED IN THE AMENDMENTS
Figure 25 – Alternate Foothills substation
574. Choosing the D12 site for the location of the Foothills 237S substation, would mean that
the proposed transmission line from the D12 site southward in the vicinity of the D8 site would
become part of the new 240-kV 1037L/1038L line in the south Foothills project. This portion of
the 1037L/1038L line would either follow the preferred route or the preferred route variant near
Frank Lake and then continue to run to the south, and eventually terminate at the proposed
Windy Flats 138S substation.
8.2.2 Interveners along the north Foothills line routes
575. The Diagonal group, which consists of nine interveners residing within 800 metres of the
diagonal portion of the preferred route between route markers B240 and A260 in the north of the
Bow River, is opposed to the preferred route. Some members of the group own land on both the
preferred and north alternate routes.
576. Reece and Richard Pearson are opposed to the preferred route. The Pearson family owns
the entire section of 17-22-28-W4M along the diagonal portion of the preferred route. The west
boundary of the Pearson section is the Calgary city limits.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
124 • AUC Decision 2013-369 (October 7, 2013)
577. Bow Vista Farms, which owns over 50 quarter sections of land located southeast of the
city of Calgary and on both the preferred and north alternate routes, is opposed to the north
alternate route.
578. Abdul Hage and Moe Hage are opposed to the preferred route just south of the
Bow River and requested that the Commission deny the application, or in the alternative, select
an alternate route that does not traverse their property. No alternate route was proposed by
AltaLink for this portion of the line.
579. Astral Media Radio GP is opposed to the north alternate route, which would be located
800 metres directly north of the centre of radiation from its CKMX transmitter site.
580. Other individual landowners expressed concerns with the north Foothills project on either
their statements of intent to participate or in brief presentations at the process meeting, but they
did not attend the hearing or make any further submissions. Their stated concerns were with both
the preferred and alternate routes.
8.2.3 Views of AltaLink
581. AltaLink stated that the preferred route minimizes fragmentation of the land, reducing
impacts to existing land uses and avoids crossing Frank Lake. Compared with other routes, the
preferred route has the least impact on areas with potential historical importance.
582. In the north portion of the project, the preferred route parallels the existing 138-kV 850L
line. Instead, the north alternate route segment predominantly follows quarterlines on agricultural
lands and parallels Highway 22X north of the Bow River. The following table compares the
preferred route and north alternate route in detail:
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 125
Table 4. Comparison between the preferred route and north alternate route103
103
Exhibit 13.00, AltaLink North Foothills Transmission Project, page 116, Table 4-4.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
126 • AUC Decision 2013-369 (October 7, 2013)
583. Compared with the preferred route, the north alternate route segment has the following
characteristics:
fewer residences within 150 metres and 800 metres of the line
more of its length along quarterlines
more agricultural land that will be fragmented by the line
greater potential impacts to historical resources
less paralleling or use of existing rights-of-way
a longer line length
a lower estimated cost
584. AltaLink submitted that the preferred route has the lowest impact north of the Bow River.
The preferred route has a greater distance over which it utilizes the rights-of-way of existing
transmission lines. Local land uses along the 1201L and 850L lines have evolved and been
carried on in the presence of the line over the past 28 and 50 years, respectively. The incremental
potential impacts of the new 240-kV line adjacent to these lines will generally be lower than
locating the new 240-kV line along a greenfield route. AltaLink also submitted that the
agricultural impacts along the 850L line are expected to decrease because the triple-circuit
structures will be fewer in number, be easier to farm around than the existing H-frame structures
and will have higher clearances from the ground.
585. AltaLink argued that the diagonal routing with triple-circuit monopole design offers a
shorter and more direct route for the entire farming community. Compared with the north
alternate route, AltaLink submitted that the diagonal routing also offered the following
advantages to individual landowners:
The triple-circuit design reduces the amount of additional right-of-way by utilizing the
existing 850L line right-of-way.
The monopoles have a larger span length, resulting in fewer towers, a smaller footprint
and greater ground clearance compared to the existing 850L line H-frame structures,
which will make it easier to farm around. For example, the preferred route will result in
two fewer towers on the Pearson lands.
The monopoles will follow the same alignment as the existing 850L line which will
minimize agricultural impacts on existing farming patterns.
The visual impact will be from one line instead of two lines.
586. With respect to impacts on aerial spraying, AltaLink acknowledges that there is a setback
for aerial spraying around high-voltage transmission lines. While aerial spraying may be
restricted to some degree by transmission lines, it is still possible. AltaLink submitted that
ground spraying is also available as an alternative. If crop yields around the transmission line
towers are decreased, AltaLink has committed to compensate affected landowners for additional
impacts from the project that cannot otherwise be mitigated.
587. To specifically address Bow Vista Farms’ concern about aerial spraying, AltaLink
submitted that there may be some impact on aerial spraying perpendicular to the line, however,
aerial spraying in a parallel direction would generally be possible with a small safety buffer from
the line at the discretion of the individual aerial spraying operator. AltaLink added that there are
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 127
no existing irrigation pivots or other systems on the properties, and that if irrigation pivots were
to be installed, such an irrigation system could be designed to take into account the proposed
transmission line. Specifically addressing the Diagonal group’s concern with aerial spraying,
AltaLink reiterated that farming operations and spraying are possible along the diagonal line.
588. AltaLink submitted that concerns about the impacts of the proposed north alternate route
on Bow Vista Farms’ filming are largely unwarranted. Three filming locations are at least
800 metres or 1,600 metres away from the proposed line. Any filming at these locations taken in
any direction, but due north would not have a view of the line. In addition, if the filming
occurred in the river valley, the transmission lines would be obstructed from the view to the
north. AltaLink added that the two other filming locations are located immediately east of an
existing gravel pit. The viewscapes for any filming in those locations are already constrained by
the large aggregate development situated to the west. The views to the east would be of the
existing agricultural operations on the properties.
589. With respect to Bow Vista Farms’ concern about its aircraft operation along the north
alternate route, AltaLink submitted that there is no impact on the east/west runway or operations
to or from the north. While aircraft operations to and from the south of the north/south airstrip
may be impacted by the north alternate route, the aircraft being used at the airstrip has
performance characteristics that allow it to continue to operate safely from all four runway
directions.
590. With respect to the modified north alternate route suggested by the Diagonal group,
AltaLink stated that it will create new impacts. For example, a pipeline running along the east
quarterline of SW 15-22-28-W4M and NW 15-22-28-W4M would have to be relocated or the
transmission line would have to be placed midfield.
591. AltaLink argued that the Pearson family’s argument of residential impacts on future
development is too speculative for the Commission to consider. The Pearsons did not bring any
evidence on residential development plans and on how the preferred route would affect those
plans should they ever come to fruition.
592. Based on the above, AltaLink favoured the preferred diagonal route to the north alternate
route in the north of the Bow River.
593. The following table compares the preferred route and Frank Lake alternate route in the
south portion of the project in detail.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
128 • AUC Decision 2013-369 (October 7, 2013)
Table 5. Comparison between the preferred route and Frank Lake alternate route104
104
Exhibit 13.00, AltaLink North Foothills Transmission Project, page 113, Table 4-3.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 129
594. Compared with the preferred route, the Frank Lake alternate route segment has the
following characteristics:
more agricultural land that will be fragmented by the line
greater number of residences within 800 metres
a longer line length
fewer potential environmental impacts, including lower potential effects on wildlife
a higher estimated cost
595. The preferred route variant segment involves the placement of up to three structures for
the proposed transmission line across Frank Lake, adjacent to the existing 1201L line structures.
This route segment arose as a result of concerns expressed by stakeholders between potential
impacts to the environment and existing land uses. AltaLink submitted that most landowners in
proximity preferred the line to cross the lake so that potential impacts to their parcels and land
use could be minimized.
596. AltaLink pointed out the potential environmental impacts arising from placing the
preferred route variant in or near Frank Lake which has been a project water body for
Ducks Unlimited since the 1950s. Ducks Unlimited continues to control the water levels of the
lake with the goal of maintaining water quality and flood control. Frank Lake is regarded by
Ducks Unlimited and other stakeholders as the most important waterfowl staging area in
southwestern Alberta, as it provides habitat to waterfowl, including several species of
management concern. Ducks Unlimited and the Fish and Wildlife branch of Alberta
Environment and Sustainable Resource Development preferred routing further away from the
water body to minimize the potential environmental impacts.
597. AltaLink acknowledged the environmental concerns expressed by Ducks Unlimited and
the Fish and Wildlife branch of Alberta Environment and Sustainable Resource Development. If
the preferred route variant were to be constructed along the 1201L line parallel across
Frank Lake, two shield wires would be placed on top of the towers. AltaLink submitted that
shield wires present a higher risk to birds than conductors, because shield wires are smaller and
less visible. AltaLink also noted that the preferred route variant would place at least two
structures within the water body.
598. In conclusion, AltaLink favoured the preferred route over the Frank Lake alternate route
and preferred route variant, submitting that the preferred route provides a better balance between
the potential environmental impacts of the proposed 240-kV line around Frank Lake and the
other land-use impacts in the area.
8.2.4 Views of the interveners
Diagonal group
599. The Diagonal group submitted that the preferred diagonal route with triple-circuit
monopole structures will constitute a brand new impact, not an incremental impact. The height of
the proposed triple-circuit monopoles is four to five times higher than the existing wood pole
structures. The Diagonal group argued that the size of the new triple-circuit monopoles
effectively presents a new impact, not mitigated by the existence of the 850L line.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
130 • AUC Decision 2013-369 (October 7, 2013)
600. The Diagonal group submitted that the preferred route has more residential impacts than
the north alternate route as there are more residences within 150 metres and 800 metres of the
preferred route than the north alternate route. The preferred and north alternate routes have seven
and two residences within 150 metres of the centreline of the route, respectively. The preferred
and north alternate routes have 46 and 41 residences within 800 metres of the centreline of the
route, respectively.
601. The Diagonal group submitted that the preferred route qualitatively has a greater
fragmenting effect than the north alternate route. It explained that routes along quarterlines will
avoid fragmentation caused by going through the middle of the field. The preferred route has less
of its length along quarterlines because it follows a diagonal alignment. By contrast, the north
alternate route has more of its length along quarterlines.
602. The Diagonal group submitted that the preferred route has greater impacts on agricultural
operations than the north alternate route, stating that its members will not be able to do aerial
spraying if the small wood pole structures are replaced by tall steel monopoles. The group added
that if towers of over 50 metres high are going to be built, the impact on aerial spraying would be
less if they follow straight quarterlines, as opposed to running diagonally through the fields.
603. The Diagonal group stated that the preferred route is 36 per cent more expensive than the
north alternate route and that the incremental cost is caused by the high cost of the triple-circuit
monopole structures.
604. The Diagonal group suggested in its argument a modified north alternate route for the
Commission’s consideration. According to the proposed modification, the north alternate route
would continue running straight north from route marker A242 instead of angling off on a
diagonal through Sylvia Busslinger’s property. The route would continue north along the east
boundary of the Busslinger property and another half mile to the northeast corner of
NW 15-22-28-W4M. At that point, it would turn west and run for one mile to where it would
intersect with the existing north alternate route segment. The Diagonal group stated that this
modified route creates no new impacts and eliminates the impacts to Mrs. Busslinger, but did not
file any evidence in this regard.
The Pearson family
605. The Pearson family submitted that the preferred route simply perpetuates the outmoded
diagonal route. Diagonal routing is inefficient in terms of land use and is also midfield, which
will create more agricultural impacts. The Pearson family is concerned that placing the new
monopole line along the diagonal route will result in the creation of two major transportation and
utility corridors (the diagonal route and Highway 22X) within two miles of each other in the
vicinity of the Pearson lands.
606. The Pearson family submitted that the preferred route is many times more visually
imposing than the existing H-frame structure of the 850L line and will require more significant
setbacks for residential development when the city of Calgary inevitably expands into the area.
The Pearson family is concerned that the preferred route will significantly reduce the residential
development value of their lands.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 131
Bow Vista Farms
607. Bow Vista Farms submitted that the greenfield routing of the north alternate route creates
completely new impacts in addition to the existing impacts associated with the 850L line. There
are twelve contiguous quarter sections that form one undisturbed field along the north alternate
route. The preferred route follows an existing linear disturbance for its entire distance, while the
north alternate route does not follow an existing linear disturbance for half its length from the
ENMAX No. 65 substation to route marker B235 once contiguous fields are taken into account.
608. Bow Vista Farms stated that the preferred route has the least impact on residences and
does not have any newly exposed residences. It argued that the north alternate route adds two
residences within 150 metres and 26 residences within 800 metres of the proposed transmission
line. Bow Vista Farms added that if the north alternate route is built, there will be two lines in
close proximity, the existing 850L line H-frames and the new steel lattice towers. As a result,
Sylvia Busslinger’s residence at SW 15-22-28-W4M will have the H-frames on one side and the
steel lattice towers on the other side.
609. Bow Vista Farms further submitted that the preferred route has fewer agricultural impacts
by virtue of being a monopole construction than the north alternate route, which would be built
with lattice towers. It views the monopole design as an improvement over the existing H-frames
on the 850L line because of the smaller base, better clearance, fewer structures and being likely
easier to see in low light. Bow Vista Farms explained that the monopoles require a right-of-way
of 40 metres, whereas the lattice towers require a right-of-way of 60 metres. Because the 850L
line will stay if the north alternate route is built, the north alternate route will require
approximately twice the amount of acres of right-of-way, as compared with the preferred route.
It also stated that the monopole design is more advantageous from a weed control perspective
because it is difficult to get under the lattice towers to control weeds.
610. Bow Vista Farms argued that the north alternate route has significantly greater aerial
spraying impacts than the preferred route because the north alternate route has more than double
the turns, which result in an “L” shape on several fields, creating corners. It contended that
helicopter spraying is not as effective and is simply impractical from a cost perspective.
611. Bow Vista Farms also submitted that the north alternate route would significantly impact
an area important to the film industry in Alberta. The filming areas on Bow Vista Farms are one
of four very suitable areas in the entire province for western period pieces. The presence of the
large lattice towers of the north alternate route would render portions of these lands unusable for
filming. The setting is ideal for period pieces, which cannot have large lattice towers in the
backdrop.
612. Bow Vista Farms further argued that the north alternate route has the potential to impact
an airstrip on its lands because the proposed transmission line may contribute to an incorrect
decision by a pilot upon takeoff or landing. Bow Vista Farms contended that AltaLink’s
assertion that the plane can climb enough to clear the line after takeoff is based on best case
performance data and on temperature and elevation conditions more favourable than those of the
actual airstrip.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
132 • AUC Decision 2013-369 (October 7, 2013)
Abdul Hage and Moe Hage
613. The Hages stated that since 2007, they have invested significant time and money into
buying, maintaining and making business arrangements with Castillo Homes Ltd., a home
builder and developer, for its property. They stated that they have invested close to $2 million
and Castillo Homes Ltd. had agreed to purchase 11 lots of four acres each at a price of $650,000
per lot and buy the final lot with the existing house for $1.8 million after all 11 lots had been
sold. The Hages submitted that Castillo Homes Ltd. is not prepared to move forward if the
transmission line route across the property is approved and that it would be difficult to find
another developer for this property.
614. The Hages requested that the Commission deny the application or choose a different
route in order to protect the public interests of ensuring fairness to landowners and promoting
suitable development of local communities. The Hages specifically requested that the
Commission clarify, in its decision, that its determination for routing purposes that a
development may be speculative is not intended to apply to the assessment of compensation to
landowners.
Other interveners
615. Other interveners expressed concerns with aerial spraying, EMF, compensation and
property values, but provided little detail in support. These interveners neither participated in the
hearing, nor make any further written submissions.
8.2.5 Commission findings
616. In making its decision on the routing of the proposed 240 kV line, the Commission
considered the portion of preferred route that corresponds with the alternate route segments. The
Commission has divided its findings into two sections.
Routing options north of the Bow River
617. With respect to residential impacts, the Commission favours the preferred route over the
north alternate route. The north alternate route is primarily greenfield and has more newly
exposed residences within both 150 metres and 800 metres of the line than the preferred route.
The Commission considers that the incremental impacts on residences not previously located in
proximity to a transmission line are greater than the incremental impacts on residences already in
proximity to an existing transmission line. It also took note that one residence will be
sandwiched by the new line and the 850L line if the north alternate route is chosen because that
route is premised on the 850L line remaining in place. The Commission does not agree with the
Diagonal group that the impacts of the proposed monopoles are akin to a transmission line on a
greenfield route because the evidence is to the effect that the proposed monopoles will result in
fewer structures than what now exists on the 850L line route.
618. Further, the proposed triple-circuit monopole structures proposed for the preferred route
are much taller than the existing H-frames of the 850L line. However, the height of the monopole
is similar to the height of the lattice structures proposed for the alternate route. The north
alternate route is primarily greenfield, creating brand new visual impacts and the H-frames will
stay if the alternate route is chosen. The preferred route would combine the new line with the
850L line on the same monopoles along the existing right-of-way, which does not add additional
structures for the proposed new line. Considering that the north alternate route results in new
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 133
additional visual impacts rather than increasing the existing visual impacts, the Commission
considers the preferred route more favourable than the alternate route.
619. The Commission favours the preferred route over the north alternate route from an
agricultural impact perspective because the triple-circuit monopoles provide longer spans and,
therefore, require fewer structures than the north alternate route. The monopoles also provide
additional ground clearance, have a smaller footprint and result in fewer corners than the lattice
towers on the alternate route. The Commission heard that the lands along the preferred route
have been farmed for over 50 years with the H-frame structures in place, but the greenfield north
alternate route has a large continuous block of cultivated parcels which will be fragmented by the
route. Also, fewer corners on the preferred route means that the concerns with aerial spraying
lands bordered on two sides by a transmission line are addressed.
620. The preferred route requires only one right-of-way, although it will be widened by
27.5 metres, while the alternate route results in a new right-of-way for the alternate route and
leaves the existing right-of-way in place. The north alternate route is longer than the preferred
alternate route and provides no opportunity to parallel any existing transmission lines. As a
result, the Commission favours the preferred route over the north alternate route from a land-use
impact perspective.
621. The preferred route has an estimated cost of $9.5 million105 more than the alternate route
due to the incremental cost of the triple-circuit monopoles. This represents approximately a
four per cent increase of total cost for the north Foothills project. Accordingly, the Commission
finds that cost favours the alternate route.
622. With respect to the concerns expressed by interveners about future potential development
of their land, no evidence in support of specific development plans or subdivision approvals was
filed. Consistent with past decisions, the Commission considers that future developments and
residences that are in the concept stage, or that are at the idea stage, are not certain and may
change depending on the economy, change of circumstances for the potential developer,
amendments to municipal bylaws regarding development or inability to secure municipal
approval. Therefore, there is a great deal of uncertainty on whether such projects would ever
proceed and if so, the timing and the potential impacts. To consider such projects would be
speculative. Although requested by the Hages, the Commission is of the view that there is no
need to add any further clarification with respect to this finding.
623. The Commission observes that the reradiation report states that the preferred route will
result in lower reradiation levels of the CKMX radio signal than the existing line and should
have no adverse impact on the station. However, the alternate route will result in double the
radiation of the existing line and may require mitigation to avoid compromising the station’s
coverage and protections. AltaLink stated that it has safety processes in place during the
construction and maintenance of the transmission line.
624. The Commission heard that the north alternate route may have potential impacts on the
filming activities and risks related to the operation of the existing airstrips. These potential
impacts are not present on the preferred route.
105
Exhibit 501.01, AltaLink response to the AUC information requests, pdf page 46.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
134 • AUC Decision 2013-369 (October 7, 2013)
625. With respect to the modified north alternate route proposed by the Diagonal group, the
Commission could not consider the proposed route because it was not supported by the evidence
filed and was not tested during the proceeding.
626. Based on the above, the Commission finds that the preferred route has overall lower
impacts than the north alternate route. A portion of the preferred route north of the Bow River, in
the vicinity of the ENMAX No. 65 substation, is within the city of Calgary transportation and
utility corridor. The Commission cannot issue a permit and licence for the construction and
operation of the north Foothills application within the Calgary transportation and utility corridor
without the prior written consent of the Minister of Infrastructure. AltaLink stated that it would
seek ministerial consent for the portion of the transmission line within the transportation and
utility corridor boundary prior to construction.
Routing options near Frank Lake
627. Because the D12 site has been chosen for the location of the Foothills 237S substation,
the Commission considers that the new 240-kV 1106L/1107L line will follow the preferred route
from the D12 site to the north. There is no other route option in the south portion of the north
Foothills project from the D12 site. In addition, the choice of the D12 site results in the proposed
240-kV 1037L/1038L line in the south Foothills project either following the preferred route or
the preferred route variant near Frank Lake. The Frank Lake alternate route is not connected to
the D12 site.
628. The preferred route variant near Frank Lake is less favourable from an environmental
perspective. The Commission took note of the submissions of the Fish and Wildlife branch of
Alberta Environment and Sustainable Resource Development, Ducks Unlimited and other
stakeholders on the potential impacts of a transmission line in close proximity to Frank Lake. As
previously mentioned, Frank Lake is a very important waterfowl staging area in southwestern
Alberta and is both an environmentally significant area and important bird area. In keeping with
the Commission's reasons for choosing the D12 substation site, the Commission favours the
preferred route.
629. The preferred route variant is more favourable than the preferred route from a land-use
perspective because it results in fewer potential impacts on lands suitable for development and
on residences in proximity, and results in less fragmentation of land.
630. The project cost estimate for the preferred route is $232 million within +20/-10%
accuracy, while the cost estimate for the preferred route with the preferred route variant
incorporated is $237 million.106 Therefore, for the portion of the proposed transmission line near
Frank Lake, the preferred route would cost $5 million less than the preferred route variant. Based
on the above, the Commission concluded that the preferred route has the lowest overall impact
especially taking into account the impacts on the environment. It avoids the placement of up to
three tower structures for the proposed new line across Frank Lake and, consequently, results in
fewer environmental concerns.
106
Exhibit 501.01, AltaLink response to the AUC information requests, pdf page 39.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 135
8.3 Tower structure options at the Bow River crossing
8.3.1 Introduction
631. AltaLink proposed the single-circuit option in its application for the tower design at the
Bow River crossing portion of the proposed 1106L/1107L line, which would entail two
single-circuit towers on both the north and south banks of the Bow River. The tower is designed
to match the existing 500-kV 1201L line east of the proposed new 240-kV 1106L/1107L line.
AltaLink derived this two-tower option based on input from Fish and Wildlife branch of Alberta
Environment and Sustainable Resource Development and other stakeholders’ preference at the
time it filed its application.
632. Taking into account that visual impacts are subjective and changes to landowners’
preference, AltaLink proposed a double-circuit, one-tower option in its reply evidence107 for the
Bow River crossing portion of the 1106L/1107L lines. Unlike the two-tower option, the one-
tower option would place only one tower on each of the north and south banks of the Bow River.
While AltaLink believed that both options are viable and comparable from construction and cost
perspectives, its preferred option is still the two-tower option due to landowner preference.
633. Figure 26 illustrates the cross-section drawing of the two different tower design
options.108 The 1201L line tower on the south bank of the Bow River is 39.3 metres high. The
tower height for the double-circuit one-tower option is approximately 65 metres, while the tower
height for the single-circuit two-tower option is approximately 43.6 metres with 67 metres of
separation between the centrelines. AltaLink clarified that there would be some changes in the
range of the tower heights set out in the application because a project of this size goes through
additional engineering and design, though it was confident that if the one-tower option were
approved, it would be able to build the tower approximately 65 metres as illustrated in Figure 26.
Figure 26 – Cross-section drawings of structure options at Bow River crossing
107
Exhibit 720, page 17, paragraph 73. 108
Exhibit 720.01, AltaLink reply evidence, Appendix A, pdf page 117.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
136 • AUC Decision 2013-369 (October 7, 2013)
8.3.2 Interveners in the Bow River crossing portion
634. The Bow River Crossing group is opposed to the two-tower option at the river crossing.
The group consists of Louise Klatzel-Muldry, the estate of Virginia Klatzel and
Douglas McHugh, Terry Thomson, Frederick Thomson and Western Sky Land Trust. The
Thomsons’ land is located at NW 20-21-27-W4M, and is in the final stages of being donated to
Western Sky Land Trust for a conservation easement. Ms. Klatzel-Muldry and the estate of
Ms. Klatzel and Mr. McHugh own the land at SW-29-21-27-W4M. The Bow River Crossing
group’s lands are within 800 metres of the new 240-kV 1106L/1107L lines as the lines cross the
south bank of the Bow River. The towers to facilitate the crossing would be situated on the
Thomson land and would be approximately 215 metres away from Mr. Thomson’s cabin.
635. Mr. Richard Dugdale and Dugdale Investments Ltd. are opposed to the one-tower option
at the river crossing. The preferred route for the 1106L/1107L line is within 800 metres of their
land, and Mr. Dugdale’s residence is approximately 1,005 metres away from the proposed tower
location. He was also concerned that his access road, which AltaLink is proposing to use, would
possibly be damaged during construction activities.
8.3.3 Views of AltaLink
636. AltaLink stated that the area where the proposed 1106L/1107L line crosses the
Bow River is a riparian area of incised valleys or coulees with steep river banks. AltaLink
submitted that concerns about the terrain are addressed by spanning the valley and some taller
trees would be cleared or trimmed to allow for safe operation. Four wildlife species of concerns
were observed in the vicinity of the Bow River crossing, including two prairie falcon nests.
Population of breeding and staging waterfowl are low. AltaLink proposed the river crossing
route paralleling the existing 1201L line because the alternate route further west would require
an additional crossing of the Highwood River and would be closer to residents.
637. AltaLink indicated that in its discussion with the Fish and Wildlife branch of Alberta
Environment and Sustainable Resource Development regarding the two-tower structure options
at the river crossing, the Fish and Wildlife branch of Alberta Environment and Sustainable
Resource Development expressed its preference for the two-tower option because it would result
in less impact on wildlife and a lower risk of bird mortality; the lines, including the existing
1201L line, would all be on the same horizontal plane and may be easier for birds to navigate.
The Public Lands Division of Alberta Environment and Sustainable Resource Development
preferred one set of taller double-circuit towers, i.e. the one-tower option, because this option
results in fewer towers on Crown land and a narrower right-of-way. Nevertheless, AltaLink
stated that both options are viable.
638. AltaLink stated that Stantec conducted investigations regarding the effects of the
Bow River crossing portion of the new transmission lines and towers on wildlife and particularly
on birds. Stantec expressed the opinion that the one-tower option had slightly lower
environmental impacts than the two-tower option because clearing of two rights-of-way for the
two-tower option would cause greater disturbance than clearing of one right-of-way for the one-
tower option.
639. Stantec pointed out that it is generally accepted that thin shield wires or optical wires
pose the greatest threat to birds because the shield wires are very thin and therefore too difficult
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 137
for birds to see. It concluded that the one-tower option is likely to result in fewer avian collisions
due to a fewer number of shield wires.
640. AltaLink, Stantec and Mr. Wallis, the Bow River Crossing group’s environmental expert
witness, agreed that even if the conductors were on the same horizontal plane, the sagging of
each conductor could be different. AltaLink stated that at particularly sensitive locations, it
would be able to mark the lines with bird deflectors, which are intended to reduce the risk of
avian mortality. Nevertheless, Stantec stated that both options are viable from a wildlife
perspective.
641. With respect to landowner preference, AltaLink witnesses testified that the landowners in
the area equally align with one option or the other.
642. There are five residences in the quarter sections in the Bow River crossing area. All of
these residences are in proximity to the existing 500-kV 1201L line. None of them are newly
exposed to a transmission line because they are all within 800 metres of the existing line. Except
for Mr. Dugdale, all four residences will be closer to the proposed 1106L/1107L line than the
existing 1201L line. Except for the Thomson cabin which is 215 metres away from the proposed
tower location, all other residences are more than 600 metres away from the proposed tower
location.
8.3.4 Views of interveners
643. The Bow River Crossing group’s environmental expert, Mr. Wallis, concurred with
Stantec that the one-tower option posed the least risks to the riparian and valley vegetation. He
also testified that spacing between the lines for the two-tower option would potentially create a
less favorable situation in relation to avian mortality than the one-tower option.
644. Western Sky Land Trust testified that the one-tower option would reduce the footprint
and be in line with its conservation and educational goals for the lands. It emphasized that the
lands are of international environmental significance.
645. Mr. Dugdale argued that his views of the Bow River valley towards the mountains in the
west would be impacted by the taller one-tower option and consequently would affect the actual
value on his property. He added that there is no permanent residence in the quarter section where
the proposed 1106L/1107L line crosses the Bow River. Mr. Dugdale testified that he understood
that the height of the two-tower option was going to be two and a half to three times taller than
the existing 1201L line.109 Mr. Dugdale was also concerned that the addition of another
transmission line could contribute to more health risks.
646. The Bow River Crossing group stated that the anticipated height of the tower was the
major factor in the landowners' stated preference. However, it observed that the height of the
tower for each option is not consistent throughout AltaLink’s application and consultation
materials. For example, the cross-section drawings on Appendix H-9110 of the application show
the height of the one-tower option and the two-tower option in comparison with the height of the
existing 500-kV 1201L line. However, the heights are only representative of the angle tower
design, while AltaLink confirmed at the hearing that the dead-end tower will be used at this river
109
Transcript, Volume 7, page 1440. 110
Exhibit 21.00, Appendix H Cross-section drawings, page 10.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
138 • AUC Decision 2013-369 (October 7, 2013)
crossing location. The group also pointed out that the range of the tower heights also varied
among different parts of the AltaLink documents. It further gave examples on how the height of
the tower was not clearly communicated to the landowners and referred to Mr. Dugdale’s
evidence in support of its views.
647. The Bow River Crossing group submitted that AltaLink’s preference of the two-tower
option relied heavily on what it perceived to be the majority landowner opinion in the area. It
believed that the landowners with facilities on their land, such as members of the Bow River
Crossing group, should have their views more strongly considered because they bear the direct
impact. The group stated that the one-tower option would create less impact on the landowners
most directly and adversely affected by the project. Mrs. Klatzel-Muldry testified of her concern
about a wider span of the lines, which is more significant when on the ground looking up and
through it, as opposed to the one-tower option. Mr. Berrien, the land-use expert for the Bow
River Crossing group also noted the difference between 90 metres of horizontal coverage with
the two-tower option and 35 metres with the one-tower option.
8.3.5 Commission findings
648. From an environmental impact point of view, the one-tower option would require
approximately 21 acres of new right-of-way, while the two-tower option would require 39 acres.
The height of the towers for the one-tower option is approximately 20 metres higher than the
two-tower option. The Commission is of the view that the smaller tower footprint favours the
one-tower option. However, there are also environmental and residential considerations.
649. The Commission accepts the conclusion drawn in the recent Avian Power Line
Interaction Committee’s report that overhead shield wires are a contributing factor for most bird
collisions, which was not disputed by any party at the hearing. Because there will only be one
overhead shield wire for the one-tower option in comparison with two shield wires for the two-
tower option, the Commission agrees with Mr. Wallis, Stantec and AltaLink that even if the
conductors were on the same horizontal plane, the sagging of each conductor can be different.
Mr. Wallis’ submission that the spacing between the lines on the two-tower option would likely
create a situation less favourable to birds than a one-tower option was also noted. Consequently,
the Commission finds that the one-tower option poses a lower risk of bird mortality.
650. Mr. Dugdale’s residence is more than 1,000 metres away from the tower location.
Compared with the existing 1201L line, the proposed new lines will be further away from his
residence and there will be no new facilities on his property. The Commission finds that the
visual impact potentially caused to Mr. Dugdale by the one, higher tower in the far distance is
incremental. With respect to Mr. Dugdale’s access road, AltaLink made a commitment to return
the road to the same state as it was before its use, or better.111 The Commission acknowledges
AltaLink’s commitment in this regard.
651. Lastly, the two options are comparable from a cost consideration.
652. Based on the foregoing, the Commission concludes that the one-tower option is
preferable to the two-tower option.
111
Transcript, Volume 5, pages 918 to 919.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 139
9 AltaLink Application No. 1608643 Foothills 138-kV transmission development
9.1 The preferred and alternate routes
653. AltaLink proposed one preferred route, one alternate route and one alternate route
segment for the new double-circuit 434L/646L lines between Foothills 237S and High River 65S
substations. These routes are shown on the map below.
Figure 27 – Foothills 138-kV route options
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
140 • AUC Decision 2013-369 (October 7, 2013)
654. The preferred route generally traverses within municipal district road allowances and
highway rights-of-way from the Foothills 237S substation to the High River 65S substation.
Approximately 95 per cent of the preferred route is located within, or immediately adjacent to
the road allowances of Highway 23, 144th Street, 498th Avenue, and Highway 543 which are
typically 30 metres or wider.
655. The alternate route generally parallels existing transmission lines, with one segment
traversing within the Highway 2 right-of-way and two segments that follow quarterlines.
Approximately 60 per cent of the alternate route parallels existing 500-kV, 240-kV and 138-kV
transmission lines.
656. AltaLink also proposed an alternate route segment112 between route markers A0 to A5 to
B10 west of the Foothills 237S substation, to provide a local variant route to the preferred route.
This segment could connect the eastern portion of the alternate route to the preferred route.
Figure 28 – Alternate route segment near Foothills substation
657. As discussed in Section 8.1.1, AltaLink amended its application to include a
stakeholder-suggested site shown as D12 for the Foothills 237S substation and associated
138-kV line routing. From site D12, the route travels west along 498th Avenue located one metre
within the road allowance until it intersects with the preferred route at route marker B20. The
stakeholder-suggested 138-kV route associated with the D12 site is shown below.
112
Exhibit 213.00, AltaLink facility application, page 99, Figure 4-30.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 141
T.18
T.19
HIGH RIVER
BLACKIE
2
2
543
783
2A
2A
23
23
799
HIGHWOOD RIVER
FRANK
LAKE
PREFERRED FOOTHILLS237S SUBSTATION SITEIN APPLICATION
1201L
PROPOSED TRANSMISSION LINES FILED IN ORIGINAL
PROPOSED SUBSTATION SITE AND TRANSMISSION
EXISTING TRANSMISSION LINES
911L
R.27W.4M.R.28R.29
FOOTHILLS 237SSUBSTATION SITEIN AMENDMENTS
ALTERNATE
APPLICATIONS
LINE ADDITIONS PROPOSED IN THE AMENDMENTS
Figure 29 – Foothills 237S substation preferred and alternate locations
658. The following interveners were opposed to the proposed routes as follows:
The Town of High River was opposed to the preferred route, particularly the route
section along Highway 543/498 Avenue north of the town’s boundary.
Phyllis Robertson was opposed to the preferred route, particularly the route section
between route markers A43 and A50. She owns lands to the north and south of the
preferred route, as well as to the south of the alternate route.
Randy and Gerry Nauta were opposed to the preferred route. The preferred route near
route marker B20 will border their land at NE 10-19-28-W4M on two sides, although it is
located in the M.D. road allowance.
Syd Mantler was opposed to the alternate route, particularly the portion between route
markers between A29 and A39. He represented both B.F.W. Holdings (2006) Ltd., as the
landowner and Deer-Country Equipment (1996) Ltd., as the business operator.
659. The Randle group’s major concern is the location of the Foothills 237S substation.
Because the Randle group is opposed to the D8 site, it was opposed to all 138-kV transmission
routes originating from the D8 substation site.
660. A few other individual landowners expressed concerns with the Foothills 138-kV project
in either their statements of intent to participate or a brief presentation at the process meeting.
Landowners concerns were associated with the salvaged lines and with the
stakeholder-suggested route. Albert Weeks, Craig Woolridge and Carla Woolridge, who are
stakeholders along the proposed routes, raised concerns with respect to property value,
residential impact, visual impact, health concerns and noise. However, they did not attend the
hearing and no further details or written submissions were filed.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
142 • AUC Decision 2013-369 (October 7, 2013)
9.2 Views of AltaLink
661. AltaLink provided a table comparing a number of metrics between the preferred and
alternate routes.
Table 6. Comparison of the preferred and alternate routes113
662. AltaLink submitted that the preferred route has the following attributes in comparison
with the alternate route:
fewer number of residences within 800 metres
comparable number of residences within 150 metres
lower agricultural impacts
greater length of line located within road allowance
similar environmental impacts
similar number of heavy angle structures
113
Exhibit 213.00, AltaLink Foothills 138-kV application, page 97, Table 4-1.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 143
663. AltaLink added that the alternate route segment provides an opportunity to utilize the
alternate route adjacent to the Foothills 237S substation and connect again to the preferred route.
The alternate route segment has higher overall impacts than the alternate route, but AltaLink
viewed it as a viable route. Compared to the corresponding segment of the preferred route, the
alternate route segment has the following characteristics:
it increases the distance to a residence and a homestead
it parallels the 500-kV 1201L line and is within the 152nd Street road allowance
it has higher potential impacts to agriculture and private lands
it increases the overall route length by approximately 700 metres
664. The stakeholder-suggested 138-kV route originating from the D12 site of the Foothills
237S substation remains on the north side of 498th Avenue and crosses to the south side of the
road to increase the distance of the line from residences and avoid a cluster of large trees.
Compared to the preferred route, AltaLink submitted that the stakeholder-suggested route has
very similar impacts for the 138-kV connection to the High River and Okotoks substations, but is
less suitable from an environmental perspective.
665. AltaLink indicated that approximately 95 per cent of the preferred route is located within
or immediately adjacent to the road allowances and that planning 138-kV transmission line
routes within road allowances generally provides an opportunity to develop lower impact
routing. Road allowances are publicly owned and have been established for the development of
roads, gas, power and communication infrastructure. Planning 138-kV transmission line routing
within road allowances minimizes impacts on private lands and adjacent land uses. AltaLink also
stated that routing within road allowances can also mitigate costs associated with transmission
line planning, easements, access, construction, future maintenance and land acquisition.
666. AltaLink stated that approximately 60 per cent of the alternate route parallels existing
transmission lines and that the paralleling of existing transmission lines provides opportunities
for lower impact routes, but results in some impact to private land.
667. AltaLink noted that the preferred route has more length within road allowance and fewer
residences than the alternate route. It also indicated that the preferred route has lower potential
agricultural impacts, while the alternate route, parallel to the existing 753L line, would have
greater agricultural impacts because farmers cannot utilize the space between the new poles and
the fence line where the 753L line is situated against the fence line.
668. AltaLink concluded that the preferred route has the lowest overall impact because it
minimizes social and economic effects, as well as effects on the environment. It viewed the
alternate route as a viable, next best option.
669. With respect to the Town of High River’s concerns, AltaLink responded that visual
impact is subjective and the Highway 543/498 Avenue corridor is not free of existing electrical
infrastructure. There is already a double-circuit FortisAlberta distribution line, a crossing of the
240-kV 911L line, the 138-kV 727L line, the 138-kV 753L line and the High River 65S
substation. The section of the existing 911L line crossing the northeast corner of the town is
required for future use and therefore cannot be removed.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
144 • AUC Decision 2013-369 (October 7, 2013)
670. AltaLink submitted that given these existing structures, any impact on the existing views
west of the highway would be incremental.
671. Further, AltaLink argued that there is no preliminary-approved plan associated with
twinning Highway 543. Even if the road does eventually get widened, AltaLink will not be
required to obtain additional right-of-way on private land because it will move the transmission
line along with the road right-of-way. AltaLink submitted that it is not difficult to move the
138-kV transmission line and the costs are not likely to be significant.
672. AltaLink submitted that the preferred route would not directly impact Mrs. Robertson’s
property because it would be situated adjacent to her lands within road allowances. AltaLink
explained that the transmission line would remain in the widened road allowance even if the road
were to be twinned in the future. The structures will remain on public land and not impact private
land. It added that Mrs. Robertson’s plans to undertake residential development of her land
identified as property B are purely conceptual in nature because she has not yet retained a
planning firm to undertake an area structure plan for the development.
673. AltaLink stated that it attempted to minimize the impact to Mr. and Mrs. Nauta by
locating the line on the south side of the road allowance, away from their residence. AltaLink
admitted that there will be a potential impact on aerial spraying around their corner that is
bordered by the proposed transmission line. However, because the line will not be on their
property, AltaLink does not offer compensation for potential loss of farming production.
674. AltaLink discussed, with the AESO, Mr. Nauta’s proposal to put a new double-circuit
line together with the existing 753L line one mile north of the preferred route. The AESO
determined that putting three of the four circuits that supply power to the High River area on to
one structure was not a reliable system solution.
675. AltaLink modified the preliminary alternate route to help mitigate Mr. Mantler’s
concerns on the attractiveness of his property. The final alternate route follows the quarterline on
the eastern edge of his property, behind his building and farther away from the highway.
676. AltaLink submitted that the Randle group’s stakeholder-suggested route is the least
suitable of all routes from a biophysical perspective because it abuts a large area of native prairie
and has a somewhat higher potential for effects on wildlife. The preferred route is the most
suitable because it will be developed almost entirely within previously disturbed road
allowances, abuts predominately cultivated land and has the lowest abundance of wildlife
resource features near the route. However, AltaLink concluded that the stakeholder-suggested
route is generally comparable to the preferred route.
9.3 Views of the interveners
Town of High River
677. The Town of High River’s newly annexed area abuts the south side of Highway 543. The
town has identified Highway 543/498 Avenue as a major traffic road and a scenic corridor
because of the magnificent views towards the west in its newly adopted Town of High River
Growth Management Strategy. The growth management strategy contains a policy that
encourages those views to be protected and enhanced.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 145
678. The Town of High River and the M.D. of Foothills adopted an intermunicipal
development plan relating to the land around the new boundary of the highway. The
intermunicipal development plan recommended the development of a set of guidelines to
preserve the visual character of the Highway 543/498 Avenue gateway.
679. The Town of High River submitted that Highway 543/498 Avenue is considered a major
gateway for the town and will potentially need to be twinned to accommodate future traffic
volumes. The twinning would be accommodated only along the northern portion of
Highway 543/498 Avenue because of the existing FortisAlberta distribution line on the south
portion, as the road was designed to be widened to the north only. The town is concerned that if
the preferred route were approved, the new 138-kV transmission line would have to be removed
in the future, when the needs for widening Highway 543 become a reality and further, because of
the waste of resources if the line had to be moved. The town was also concerned that the
preferred route would impede or hinder the future land use of its two properties immediately
north of Highway 543. In conclusion, the town preferred the alternate route along the existing
753L line.
680. In addition, the Town of High River submitted that the existing 911L line crossing
northeast of the town constrains the future development and reduces the town’s tax revenues.
The town urged AltaLink to remove that portion of the 911L line once it becomes redundant.
Views of Phyllis Robertson
681. Mrs. Robertson submitted that building the preferred route from route markers A39 to
A65 is short-sighted because the lines will likely have to be relocated in the future when
498 Avenue is twinned. Mrs. Robertson was concerned with the extra cost associated with
relocating the 138-kV transmission lines, as well as additional land-use impacts and nuisance.
682. Mrs. Robertson submitted that the current traffic on Highway 543 does not spoil the view
to the west. She explained that there is only one small FortisAlberta distribution line on the south
side of the highway between route markers A43 and A50. Anyone standing at the new
interchange with Highway 2 looking west has a relatively unobstructed view. In contrast, with
the short section between route markers A50 and A65 where power lines are on both sides, the
visual character of this stretch of the highway between route markers A43 and A50 is more
visually pleasing. Mrs. Robertson concluded that routing the transmission line along the
preferred route west of route marker A43 will degrade the visual character of the corridor and
will be inconsistent with the town’s planning documents and the intermunicipal development
plan.
683. Mrs. Robertson testified that she owns both properties A and B as shown in Figure 30.114
Property A is zoned as agricultural land, while property B is identified as residential mixed use
in the future land-use scenario of the intermunicipal development plan.
114
Exhibit 616.03, InterPLAN Strategies Inc. report, page 2, Figure 1.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
146 • AUC Decision 2013-369 (October 7, 2013)
Figure 30 – Phyllis Robertson’s property location
684. As a landowner who will have either the preferred route or the alternate route on her
lands, Mrs. Robertson stated that she would prefer to give up a small amount of right-of-way on
the north edge of her land identified as property A for the alternate route, as opposed to having a
new transmission line run through the middle and more valuable part of her lands immediately
adjacent to the town of High River. Mrs. Robertson indicated that the majority of the residences
within 800 metres of the alternate route are west of the alternate route, south of route marker
A39, on the other side of the Queen Elizabeth II Highway. To avoid the residential impact
associated with this, she proposed a hybrid route which combines the preferred route from the
Foothills 237S substation to route marker A39 with the alternate route from route marker A39 to
High River 65S substation. Mrs. Robertson submitted that the number of residences within 800
metres of the alternate route would be reduced to 36 from 96 if the hybrid route were approved,
while the number of residences within 800 metres of the preferred route is 45.
685. Mrs. Robertson submitted that the hybrid route will also avoid the visual impacts
associated with the preferred route west of route marker A43. The alternate route west of route
marker A43 is one mile north of the town of High River's boundary and parallels the existing
753L line, which will not affect the scenic corridor along Highway 543/498 Avenue as expressed
in the town’s growth management strategy and intermunicipal development plan with the
M.D. of Foothills.
686. Mrs. Robertson asked the Commission to either approve the alternate route in its entirety
or approve the hybrid route.
687. Mrs. Robertson’s land consultant, Mrs. Acteson of InterPLAN, concurred with the
position of the Town of High River in terms of the future development options in the area which
are discussed above.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 147
Views of Randy and Gerry Nauta
688. Mr. and Mrs. Nauta submitted that the preferred route would be detrimental to the
productivity of their land because the proposed preferred route has a 90 degree turn in the line
adjacent to their farmland, which will make it impossible to aerial spray their crops. Mr. Nauta
explained that even if he were to spray his crops, a number of passes would be required with a
plane, thus increasing the use of insecticides, herbicides and fungicides. He added that AltaLink
will not reimburse them for their crop losses because the lines are not on their land, but simply
next to it.
689. The Nautas were concerned with the health impacts of the preferred route, being metres
away from their home. They were also concerned that the proposed lines will affect their electric
fences. They expressed concerns about the safety hazard posed by the proposed placement of the
transmission line towers in the ditch of busy roads. They believed that the best and fairest
location for a line is on the property line between two adjoining sections of land so that the
adjacent landowners equally share in the compensation for the loss of crops. They added that the
preferred route will ruin their mountain view and devalue their property. Mr. Nauta indicated
they had no concerns with the alternate route. The Nautas also supported the submissions of the
Town of High River.
Views of Syd Mantler
690. Mr. Mantler owns a narrow lot that is situated east of Highway 2 and south of
498th Avenue, which is part of the NW 9-19-28-W4M. The lot has a large building placed
approximately 40 metres from the property line, used by Deer-Country Equipment (1996) Ltd.,
an agricultural and turf dealer in High River. The lot is used to display, assemble and repair
equipment. Typically there are 10 to 15 people working on the premises.
691. Mr. Mantler was concerned that the alternate route would have great visual impact and
reduce property values. He submitted that the proposed transmission line tower will be three
times as high as the building, which will reduce the visibility of the building from Highway 2
and attractiveness of the property which is not encumbered by the 911L line. He noted that
according to the intermunicipal development plan of the Town of High River and the M.D. of
Foothills, his lot is part of lands that are considered to be suitable for future highway commercial
development.
692. Mr. Mantler was also concerned that there may be negative effects on people working
close to a power line, stating that people would prefer not to work next to a large power line.
9.4 Commission findings
693. Because the Commission selected the D12 site for the Foothills 237S substation, the
stakeholder-suggested route is the starting point of the 138-kV line. The proposed transmission
line would continue from D12 to route marker B20 and continue west to follow the preferred
route to route marker A39. At route marker A39, the route can follow either the preferred route
or the alternate route and terminate at the High River 65S substation. The Commission must
decide which route, preferred or alternate, has the least overall impact between route marker A39
and the High River 65S substation based on the routing criteria and potential impacts of each of
the routes.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
148 • AUC Decision 2013-369 (October 7, 2013)
694. The proposed 138-kV hybrid route originates from the D12 site, follows the
stakeholder-suggested route to route marker B20, then follows the preferred route to route
marker A39, and finally follows the alternate route to High River 65S.
695. From a residential impact perspective, it appears that between route marker A39 and the
High River 65S substation there is a similar number of residences within 150 metres of the
two routes. However, Phyllis Robertson submitted that, compared with 45 residences within
800 metres of AltaLink’s entire preferred route, the hybrid route will result in only 36 residences
within 800 metres of the proposed transmission line. The Commission finds that the potential
residential impacts are similar on either route. Although there are fewer residences within
800 metres, the potential residential impacts at that distance are not significant and do not weigh
in favour of the alternate route.
696. The Commission acknowledges that due to the future twinning of Highway
543/498 Avenue, the new 138-kV transmission lines may have to be moved in the future, and
that there are additional cost and land impacts associated with the removal if the road is widened.
Although the timing of twinning the highway is not known, the potential impacts associated with
moving the proposed transmission line favour the alternate route.
697. The alternate route eliminates Mr. Nauta’s concern regarding aerial spraying around the
corner of his parcel surrounded on two sides by the preferred route. Despite the potential
agricultural impacts resulting from the alternate route being on private land between route
marker A39 and the High River 65S substation, Mrs. Robertson prefers having this route on her
property, to AltaLink’s preferred route. There is no evidence of farming of contiguous quarters
along the alternate route. However, the alternate route would parallel the existing 753L line and
would have greater agricultural impacts because farmers would not be able to utilize the land
between the new poles and the fence line (where the 753L line is situated against the fence line).
As a result, the Commission finds that potential agricultural impacts favour the preferred route.
698. Taking into account residential and agricultural impacts, future development and the
potential relocation of the line, the Commission finds that the alternate route is a better route than
the preferred route between route marker A39 and the High River 65S substation. Consequently,
the Commission finds that the hybrid route has the lowest overall impact and approves the hybrid
route.
699. The Commission observes that AltaLink applied to salvage a portion of the 727L line
between the Janet 74S and Okotoks 678S substations and that no issue was raised regarding the
proposed salvage. In addition, no other issues were raised respecting any other new facilities or
alterations to the existing facilities applied for by AltaLink as part of the Foothills 138-kV
project. The Commission accepts the evidence submitted by AltaLink, finds that the facilities
and alterations meet the requirements of AUC Rule 007 and AUC Rule 012, and that the
approval of the requested facilities, alterations and salvage is in the public interest.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 149
10 AltaLink Applications No. 1608861 and No. 1608862 - South Foothills and
Windy Flats 138-kV transmission developments
10.1 Introduction
10.1.1 The preferred and alternate substation sites
700. As stated above, the Commission approved the amendment to the SATR NID approval to
change the southern termination of the1037L/1038L line to a new substation instead of to the
Peigan 59S substation, previously approved in Needs Identification Document Approval
No. U2011-115. The Commission must now consider the AltaLink facility application which is
intended to meet the approved amended needs identification document.
701. The proposed Windy Flats 138S substation would be the southern termination of the
1037L/1038L line and would contain one 240/138-kV transformer, ten 240-kV circuit breakers,
two 138-kV circuit breakers and two 240-kV reactors within a 135-metre by 235-metre fenced
area. AltaLink proposed to site the substation at SW 17-8-26-W4M; however, due to objections
from the landowner, it developed an alternative location at SW 18-8-26-W4M. A third location,
east of the proposed sites, was also developed but was eliminated from consideration when the
final preferred and alternate routing of the transmission line was developed. This third option
was eliminated because it was longer, it had the potential to impact more agricultural lands, it
crossed the Oldman River at a less desirable location, and had a higher cost.
702. AltaLink also proposed the re-termination, at the Windy Flats 138S substation, of the
existing 603L and 608L lines, and to rebuild parts of the 603AL and 725BL lines to allow two
wind generators to be connected at full capacity. The 603AL and 725BL lines would be rebuilt
on the same alignment as the existing 603AL and 725BL lines, utilizing an undeveloped road
allowance, and paralleling the existing 967L/968L line. To re-terminate the 603L and 608L lines
into the Windy Flats 138S substation, two short sections, of approximately 95 metres each,
would be built on the south side of the substation. AltaLink also proposed two airbreak structures
in the 608L and 608AL lines in the SW 15-8-26-W4M and NW 10-8-26-W4M. These airbreak
structures would each require 10-metre easements. AltaLink stated that there are no new
potential impacts from these alterations to stakeholders in the area.
10.1.2 The preferred and alternate transmission line routes
703. For the south Foothills project, a new double-circuit 240-kV transmission line, designated
as 1037L/1038L is proposed. AltaLink proposed a preferred and an alternate route. The preferred
route generally parallels the existing 911L line, while the alternate route is primarily a greenfield
route. AltaLink also proposed a Claresholm Connector, connecting the routing of the preferred
and alternate routes and allowing for the combination of the two routes, which are depicted
below.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
150 • AUC Decision 2013-369 (October 7, 2013)
Figure 31 – South Foothills project preferred and alternate routes115
115
Exhibit 348.00, page 16. Figure 3-1 Preferred and Alternate Routes.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 151
704. From the Foothills 237S substation, the preferred route proceeds south, parallel to the
1201L line before veering west to create a greater separation from Frank Lake. The line then
proceeds south, parallel to the 911L line to route marker A30, where the alternate route option
begins. AltaLink created a route variant leaving Foothills 237S substation, closely paralleling
1201L line closer to Frank Lake. From route marker A30, the preferred route continues in a
southerly direction, parallel to the 911L line until route marker A45, where the preferred route
cuts to the east side of the town of Claresholm. AltaLink stated the preferred route veers east to
align two major infrastructure projects, the proposed transmission line and the proposed
Highway 2 bypass. Also, this portion of the preferred route is in keeping with the town of
Claresholm’s long-term development plan and the town's request to route around Claresholm.116
The transmission line continues to parallel 911L line, south of Claresholm until route marker
A79, where the transmission line heads in a south east direction towards the Windy Flats 138S
substation. AltaLink proposed two locations for the Windy Flats 138S substation, and created a
route variant to the alternate substation site. The route variant is located to the west of the
preferred route, requiring 1.5 kilometres of additional line and four additional heavy-angle,
dead-end structures.
705. AltaLink’s alternate route is primarily a greenfield route. The alternate route separates
from the preferred route alignment at route marker A30 and proceeds east and south, away from
the towns of Stavely, Claresholm and Granum. The alternate route passes by the southeast side
of Mud Lake before joining the preferred route alignment west of Fort Macleod.
706. The Claresholm Connector, which connects the preferred and alternate routes, allows for
a blended preferred and alternate route. The Claresholm Connector is 8.1 kilometres long and is
located north of the town of Claresholm. According to AltaLink, the connector would be located
at the lowest impact point of connection available near the midpoint of the preferred and
alternate routes; it follows quarterlines and has five residences within 800 metres.
10.1.3 Other project components
707. AltaLink also proposed the series capacitor station SC1 266S at approximately the centre
point of the 1037L/1038L line. The series capacitor station SC1 266S would consist of two
240-kV series capacitors, two 240-kV circuit breakers and the associated protection equipment
within a 101-metre by 139-metre fenced site. AltaLink created two potential locations depending
on whether the preferred or alternate route was selected for the1037L/1038L line. The preferred
location is at SW 15-14-27-W4M on the same site as the Stavely 349S substation. The alternate
location is at NE 15-15-26-W4M and would come within 150 metres of the residence at this site.
A small portion of land would also be required to accommodate the series capacitor site.
AltaLink obtained an option to purchase either of the sites.
708. AltaLink proposed to connect the existing 138-kV 603L and 608L lines to the
Windy Flats 138S substation at either the preferred or alternate site. The removal and rebuild of
parts of the 603AL and 725BL lines are required for the new connections. The existing 603AL
and 725BL lines would be rebuilt using the same alignment, which currently utilizes an
undeveloped public road allowance parallel to the existing 240-kV 967L/968L line.
116
Transcript, Volume 3, page 479, line 8-13.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
152 • AUC Decision 2013-369 (October 7, 2013)
Figure 32 – Terminate 603L into Windy Flats 138S substation117
709. To connect the 603L line to the Windy Flats 138S substation, AltaLink proposed to
construct 95 metres of new single-circuit 138-kV transmission line from the substation to the
603AL line and redesignate a portion of the 603AL line, from the new line portion to route
marker A10, as the 603L line. The existing jumper at the 603L97 line would be opened in the
direction of Peigan substation. The end result would have the 603L line connect the
Soderglen 248S substation to the Windy Flats 138S substation and the 603AL line connect the
Peigan 59S substation to the 603L97 line.
117
Exhibit 352.00, page 13, Figure 3-3 – Terminate 603L into Windy Flats 138S Substation.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 153
Figure 33 – Terminate 608L into Windy Flats 138S substation118
710. To connect the 608L line to the Windy Flats 138S substation, AltaLink proposed to
construct 95 metres of new single-circuit 138-kV transmission line from the substation to the
603AL line, upgrade the portion of the 603AL line from the substation to route marker A40 as a
single-circuit line, and rebuild a portion of the 725BL line, from route markers A40 to A50, as a
double-circuit line to carry the 608L and 725BL lines. At route marker A50, the rebuilt 608L line
would connect to the existing 608L line via a T-tap and the existing 608L line from this point to
Blue Trail 528S substation would be redesignated as 608AL. The 725BL line would continue
east on its existing routing. AltaLink also proposed to install two airbreaks on either side of the
T-tap junction for isolation and reliability purposes. Lastly, AltaLink would open the existing
jumper on line 608L71 in the direction of the Peigan 59S substation, and the portion of the 608L
line from this jumper location to the Peigan 59S substation would be re-designated as 608BL.
The end result would be the 608L line connecting the Windy Flats 138S substation to the
Ardenville 1418S substation, the 608AL line running from line 608L102 to Blue Trail 528S
substation, and the 608BL line running from the 608L71 line to the Peigan 59S substation. The
725BL line would continue on its existing routing but would be on an upgraded, double-circuit
tower between route markers A40 and A50.
118
Exhibit 352.00, page 15, Figure 3-4 – Terminate 608L into Windy Flats 138S Substation.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
154 • AUC Decision 2013-369 (October 7, 2013)
10.2 Preferred versus alternate route
10.2.1 Views of AltaLink
Table 7. Project assessment metrics for the preferred and alternate routes119
Major aspects and considerations Preferred route Alternate route
Total right-of-way length (km) 118 125
Agriculture
Cultivated Land Crossed (km) 76 84
Cultivated land crosses where there is no existing parallel transmission line (km) 26 70
Forage Land (Tame Pasture) Crossed (km) 11 2
Irrigated Parcels Crossed (km) 7 2
Residential
Residences within 150 m of centreline (#) 2 1
Residences within 800 m from right-of-way edge (#) 99 76
Environmental
Surface Water in of within 800 m of right-of-way (ha) 269 461
GVI - Total Native Prairie Crossed (km) 22 21
Protected or Provincially Designated Areas and Environmentally Sensitive Areas in or within 800 m of right-of-way (#) 2 2
Species of Management Concern and Species at Risk Act Listed Species Observations in or within 800 m of right-of-way (#) 124 81
Special considerations
LSDs with Listed Historical Values in or within 800 m of right-of-way (#) 455 364
Class 1 0 0
Class 2 0 0
Class 3 0 0
Class 4 20 40
Class 5 435 324
Airfields in or within 800 m of right-of-way edge (#) 1 1
Aggregate Areas in or within 800 m of right-of-way edge (#) 1 1
Opportunity to parallel transmission line to be salvaged (#) 70 17
Technical considerations
Number of Heavy Angles or Dead-end structures (#) 56 60
711. While AltaLink stated that both the preferred and alternate routes of the south Foothills
project are in the public interest, it stated the preferred route is the superior route because it is
shorter, has fewer potential agricultural impacts, has fewer potential environmental impacts, has
fewer heavy angle or dead-end structures, and costs less.
119
Exhibit 793.01, AML Undertaking 008.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 155
712. In terms of potential agricultural impacts, AltaLink submitted that the preferred route
would cross 76 kilometres of cultivated lands while the alternate route crosses 84 kilometres.
However, out of the 76 kilometres of cultivated lands on the preferred route, only 26 kilometres
would not parallel an existing transmission line. While the preferred route would cross more
irrigated parcels than the alternate route, the preferred route impacts fewer irrigation pivots.120
The preferred route would cross more forage lands than the alternate route.
713. AltaLink’s metrics indicated that the preferred route would cross fewer hectares (ha) of
surface water and that the number of native prairie, protected or provincially-designated areas
and environmentally sensitive areas crossed, are similar. The preferred route contains more
species of management concern, Species at Risk Act listed species observations within
800 metres of the edge of the right-of-way, and more sections of land with listed historical
resource values in or within 800 metres of the edge of the right-of-way.
714. While both routes run parallel to the existing 911L line, the preferred route runs parallel
for 53 kilometres more than the alternate route, which potentially reduces impacts. As the 911L
line will be salvaged at the end of the project, the potential impact along the paralleled portions
result in a substitution impact rather than a new or incremental impact. AltaLink stated that one
benefit of paralleling the 911L line would be that local land use has been carried out with the
presence of the 911L line for 49 years. Because of the familiarity of the transmission line, many
impacts are incremental rather than new. For example, agricultural practices, irrigation systems
and access roads have each accommodated transmission lines so there would be fewer potential
impacts of replacing the 911L line with the new 240-kV transmission line than impacts
associated with locating the line in a greenfield setting.121 Another example of an incremental
impact is the number of irrigation pivots potentially impacted by the transmission line. While
both the preferred and alternate routes will impact two irrigation pivots, on the preferred route,
one pivot is currently impacted by the 911L line. If the preferred route were selected, only one
additional pivot would be impacted, while the alternate route would impact two new irrigation
pivots.
Table 8. Incremental residential impacts122
Major aspects
and
considerations
911L Preferred route
Portion of preferred
transmission route on parallel
Preferred route
incremental
Alternate route
Portion of alternate route on parallel
Alternate route
incremental
Number of residences within 150 metres of centreline
4 2 2 0 1 0 1
Number of residences within 800 metres from the edge of the right-of-way
211 88 41 47 75 14 61
120
Exhibit 348.00, page 99, paragraph 333. 121
Exhibit 348.00, page 100, paragraph 338. 122
Exhibit 348.00, page 100, Table 4-4 Incremental Residential Impacts.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
156 • AUC Decision 2013-369 (October 7, 2013)
715. AltaLink stated that while the raw numbers for residential impact favour the alternate
route, when comparing the impacts in relation to the existing 911L line, the preferred route has
lower impacts than the alternate route. The existing 911L line impacts four residences within
150 metres of the centreline and 211 residences within 800 metres from the edge of the
right-of-way. While the preferred route has two residences within 150 metres of the centreline,
both residences are located where the transmission line will parallel the 911L line. The residence
on the alternate route within 150 metres is located where there is currently no transmission line.
Similarly, for the 800 metre metric, 41 residences are located on the preferred route where it is
parallel to the 911L line compared to 14 residences on the alternate route. This results in an
incremental impact to 47 residences within 800 metres of the edge of the right-of-way for the
preferred route versus 61 for the alternate route.
716. AltaLink elaborated that for residences within 150 metres of the preferred route, one is an
abandoned residence that is to be razed (and not included in the table above), and the other is a
recently added trailer that can be moved. On the proposed alternate route, AltaLink stated that it
will purchase the residence that is within 150 metres to facilitate the series capacitor station site.
As such, AltaLink submitted that there is no appreciable difference between the two routes when
using the metric of residences within 150 metres.123
717. AltaLink added that while the new towers are larger, which could increase visual impact,
the incremental impacts would be lower than if the transmission line were not adjacent to another
transmission line.
718. AltaLink submitted that because the preferred route parallels the 911L line for 53 more
kilometres than the alternate route, the environmental evaluation concluded that the preferred
route has fewer potential environmental impacts.124
719. AltaLink stated that opposition to the south Foothills project was primarily by
landowners located either in or near the town of Claresholm, or at the south end of the south
Foothills project near the portion of the route that is common to both the preferred and alternate
routes, on lands associated with the Windy Flats substation site. Opposing landowners in or near
the town of Claresholm combined to form the Committee for East Route Conservation (CERC)
and wanted a route to the west of the town to be considered (the CERC route).125
720. In response, AltaLink argued that it originally considered this route, but abandoned it in
favour of the preferred route. It added that while the preferred route is longer and more
expensive than the CERC route, the incremental cost of the preferred route is justified given the
lower site-specific impacts associated with the preferred route to the east of Claresholm.126
721. AltaLink stated that the main considerations in routing the preferred route to the east of
the town of Claresholm were the alignment of the proposed transmission line with the
Highway 2 bypass, pipelines, major infrastructure projects, and the request of the Town of
Claresholm and its long-term development plan.127 AltaLink rejected the preliminary route to the
123
Exhibit 348.00, page 98, paragraph 332. 124
Exhibit 348.00, page 99, paragraph 333. 125
Exhibit 854.01, page 27, paragraph 58. 126
Exhibit 883.01, page 6, paragraph 15. 127
Transcript, Volume 3, page 479, lines 8-13.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 157
west of the town of Claresholm because it believed the east route has a lower overall impact than
the route to the west of Claresholm, favoured by CERC.
722. More specifically, AltaLink argued that the preferred route would have fewer residential
impacts than the CERC route. There are 26 first-row residents within 800 metres and none within
150 metres on the preferred route, and 65 first-row and two residences within 150 metres of the
CERC route; 128 however, more residences would be newly exposed to a transmission line on the
preferred route because the CERC route is in an area that parallels the 911L line. It added that
the preferred route is better from a visual impact perspective and provided aerial photos of the
CERC members’ properties, which showed many of the residences would have obstructed views
of the transmission line to the east.129 AltaLink stated that visual impacts could be further
mitigated through tower siting and that the Highway 2 bypass would be sited between these
residences and the transmission line.130 In contrast, AltaLink stated that most of the homes on the
west side of Claresholm are oriented to the west with unobstructed views towards the west.131 It
added that the preferred route contains fewer towers on cultivated fields.132
723. AltaLink emphasized that it considered the preferred route’s alignment with the
Highway 2 realignment a benefit, and that it took into account the town’s long-term plans.
AltaLink stated that the municipal development plan is an official land use planning document
used to guide future development of the town of Claresholm, and consideration of the municipal
development plan was critical to the process of identifying the best route because transmission
lines are of long duration.133
724. AltaLink stated that from an impact perspective, the creation of a common footprint
corridor for major infrastructure would result in low impacts.134 It argued that the Highway 2
bypass plans are not speculative and that, while it has not been designated as a highway, it has
gone through consultations, studies and plans.135 In addition, AltaLink has been given assurances
by Alberta Transportation that the Highway 2 bypass would proceed.136
725. AltaLink stated that the Town of Claresholm made it clear that it opposed the
transmission line being routed to the west of town and preferred the realignment option east of
town137 and explained that municipalities with populations exceeding 3,500 are required to adopt
a municipal development plan, which includes the land uses proposed for the municipality and
the manner of future developments in the municipality.138
726. Summarizing the position of the town, AltaLink indicated that the Town of Claresholm
opposed an alignment of the new transmission line along the 911L line because this alignment
would be inconsistent with the following two objectives: encouraging residential development
128
Exhibit 854.01, page 29, paragraph 63. 129
Transcript, Volume 4, page 565, lines 15-18. 130
Exhibit 854.01, pages 47-48, paragraph 109. 131
Exhibit 720.01, page 37, paragraph 197. 132
Exhibit 588.01, CERC.AML-008. 133
Exhibit 720.01, page 9, paragraph 25. 134
Transcript, Volume 3, page 486, lines 7-19. 135
Transcript, Volume 3, page 520, lines 6-18. 136
Transcript, Volume 4, pages 556-557, lines 11-25, 1-2. 137
Transcript, Volume 3, pages 484-485, lines 12-25, 1. 138
Exhibit 720.01, page 8, paragraphs 17-18.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
158 • AUC Decision 2013-369 (October 7, 2013)
and expansion to the west, and maximizing views of the Porcupine Hills to the west.139 The town
favoured the alignment to the east of town along the Highway 2 bypass and other linear facilities
because it was more consistent with its land use planning objectives to the east of the town.140
The Town of Claresholm sent a letter to AltaLink on April 29, 2013, confirming its support of
the preferred route.141
727. AltaLink argued that the Berrien report142 was deficient due to the absence of consultation
with residents on the west side of Claresholm, town officials and town planners who would be
affected by the CERC route. Stakeholder input allows AltaLink to identify specific concerns,
gain local knowledge and discuss site-specific mitigation measures,143 and there is an inherent
bias when only one group of stakeholders is consulted.144 AltaLink consulted on preliminary
routes both on the east and west sides of Claresholm, as well as with town and government
officials, to conclude that the route to the east of Claresholm is the lower impact route.145
728. With regard to the siting of Windy Flats 138S substation, AltaLink’s preferred location
for the substation would have lower overall impacts than the alternate site or locations suggested
by Ronald and Laurie Conner (the Conners), and potential impacts identified by the Conners can
be mitigated. The impacts to the Conners’ gravel extraction can be mitigated by setbacks,
side-slopes around towers and compensation for any sterilized gravel reserves.146 AltaLink also
attempted to minimize impacts to the gravel operation through tower placement, siting as few
towers as possible on the gravel deposits.147
729. AltaLink stated that it considered various options with the Conners, including routing the
transmission line along the east side of the Peigan reserve and locating the substation off of the
Conners property.148 AltaLink concluded the preferred location was the lowest impact, but
developed an alternate site, west of the Conners’ property.
10.2.2 Views of interveners
730. The Commission received submissions from 648825 Alberta Ltd., Ron and
Bonnie Atkinson, Neil and Ginger Besplug, Debra Bronson, Donald and Carol Brunner, Wayne
and Jeanne Burnham, Ronald and Laurie Conner, Doug Umscheid Farms Ltd., Art and Pat
Fisher, Kathleen Fisher, Gary and Diane Hutton, R. Garry and Mayanne Johnson, Judith and
Michael Lelek, Betty and Lee Mainprize, Collin Markle, Gregory and Marjory Martin,
M.E. Meyerhoffer, Elizabeth Jean Mulholland, Gary Murray, Nanesco Sales Ltd., Karen
Needham, Dennis Nelson, Mildred Nelson-Pugh, James and Bev Senos, and Lynda and Bill
Thiessen. All participants along the preferred route, with the exception of Mr. Markle and the
Conners, combined to form CERC. The Conners are located on a common portion of the
preferred and alternate route near the southern terminus and their evidence is discussed below in
the alternate route section.
139
Exhibit 590.03, page 8. 140
Exhibit 720.01, page 9, paragraph 26. 141
Exhibit 720.02, pdf page 1. 142
Exhibit 587 and 588, Expert report from Bob Berrien. 143
Exhibit 720.01, pages 6-7, paragraphs 9 to 13. 144
Exhibit 854.01, page 42, paragraph 90. 145
Exhibit 854.01, page 42, paragraph 92. 146
Transcript, Volume 4, page 616, lines 1-4. 147
Transcript, Volume 4, page 613, lines 9-14. 148
Transcript, Volume 4, pages 606-607, lines 16-25, 1-6.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 159
731. The members of CERC primarily own land on or near Fifth Street East on the east edge
of the town of Claresholm. The members’ primary concerns were visual impacts and decreased
property value. The CERC members argued a route paralleling the 911L line to the west of
Claresholm is a superior route.
732. The CERC group retained Mr. Berrien, Mr. Wallis and Mr. Donaldson to prepare reports
comparing the preferred route to the CERC route. Mr. Berrien stated that the CERC route has
minimal incremental impacts, fully parallels an existing route, is a route that existed earlier in the
process and is a superior route with the lowest overall impact.149 CERC argued that the preferred
route does not follow an existing linear disturbance150 because the proposed highway alignment
has not been approved and may not be built.151
733. Mr. Berrien testified that he was mandated to evaluate the preferred route near
Claresholm and that he did not study the alternate route to the extent that he could form a decent
opinion on it.152
734. In Mr. Wallis’ report, prepared on behalf of CERC, he evaluated both the preferred and
alternate routes from an environmental perspective and concluded that there is no clear choice;
both routes could be considered equal in their impacts, depending on how the different attributes
were weighted.153 The Wallis report concluded that the preferred route contains fewer wetlands
and parallels the existing 240-kV transmission line for a greater distance and that the alternate
route contains a lower proportion of environmentally significant areas, native uplands and known
rare plant locations.
735. CERC submitted that the preferred route is a longer and more expensive route. The
Berrien report estimated the increased cost to be no less than $10 million.154 In addition to the
preferred route being 5.3 kilometres longer, CERC argued that seven temporary poles are
required at a cost of $1 million, which would not be required in the CERC route.155 CERC added
that although the preferred route parallels the 911L line for over half the route, it deviates to a
greenfield route near the town of Claresholm.156
736. CERC stated that the CERC route is the lower impact route from an agricultural
perspective; it would be parallel to the 911L line, where farming practices have developed over
time in the presence of towers, while the preferred route would be a greenfield scenario where
farming around transmission towers would be a new impact.157 The CERC route would also
require fewer structures to farm around.
149
Exhibit 587.02, Section 3.2.1.5 Final Opinion and Recommendations. 150
Exhibit 857.01, page 13, paragraph 23. 151
Exhibit 587.02, page 33. 152
Transcript, Volume 5, page 803, lines 17-22. 153
Exhibit 591.02, page 1. 154
Exhibit 587.02, page 43. 155
Transcript, Volume 3, pages 426-427, lines 23-25, 1-10 and page 456, lines 12-23. 156
Exhibit 857.01, page 11, paragraph 25. 157
Transcript, Volume 5, page 771, lines 6-13.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
160 • AUC Decision 2013-369 (October 7, 2013)
737. CERC submitted that while the CERC route has more residences within 800 metres, the
impact is lower because it would be incremental due to the presence of an existing line. AltaLink
agreed with CERC on this.158 In contrast, CERC stated that the preferred route would impact
newly exposed residences. CERC pointed out that AltaLink indicated that a benefit of paralleling
the 911L line is that the line has been in place for 49 years and that local land use had evolved
and been carried out through the years in the presence of the line.159 In addition, Mr. Berrien
argued that given the current population growth rate, little additional residential land would be
required in the future.160
738. CERC argued that the preferred route would result in a new visual impact to the
residences on the east side of Claresholm while residences along the CERC route have had a
power line in their view and would be newly exposed. CERC contended that AltaLink’s
evidence on the home orientation was either incorrect161 or that the house orientation did not
indicate the direction of views from other parts of the house, such as kitchen windows and
outdoor patios.162
739. CERC stated that its route is better from an environmental perspective. In addition to
being a shorter route, the Wallis report stated that the preferred route is in proximity of wetlands
and native upland habitats while the CERC route contains a tiny area of degraded grassland.163 A
CERC member testified that the concentration of multiple lines in multiple directions, like the
preferred route, poses a greater risk for avian collisions than a single north-south alignment such
as paralleling the existing 911L line.164
740. CERC contended that the preferred route did not accord with the Town of Claresholm’s
municipal development plan because paragraph 11.4.4 of the municipal development plan states
that the town is opposed to any utility development that could negatively impact future growth. It
submitted that the preferred route would negatively impact industrial development in
NW 24-12-27-W4M due to the setbacks from the transmission line and the existing pipelines,
therefore, the preferred route was in contradiction with the plan.165
741. CERC stated that its route would not negatively impact the town’s future growth.
Mr. Berrien testified that the existing approved Prairie Shores area structure plan provides
enough residential development for the town, and the CERC route would not constrain
residential development to the west towards the 911L line.166 Mr. Donaldson added that
residential development is an acceptable land use in proximity to power lines.167 Mr. Donaldson
submitted that the Claresholm land-use bylaws do not regulate views or the protection of views
and do not implement the policies of the municipal development plan regarding the desire of the
town to relocate the transmission line to the east side of town.168
158
Transcript, Volume 3, pages 477-478, lines 24-25, 1-5. 159
Exhibit 348, page 5, paragraph 18. 160
Exhibit 587.02, page 32. 161
Transcript, Volume 3, pages 529-530, lines 23-25, 1-10. 162
Transcript, Volume 3, page 529, lines 8-12. 163
Exhibit 591.02, page 18. 164
Transcript, Volume 4, pages 683-684, lines 19-25, 1-8. 165
Transcript, Volume 3, pages 497-499, lines 24-25, 1-25, 1-3. 166
Transcript, Volume 5, pages 765-766, lines 22-25, 1-8. 167
Transcript, Volume 5, page 747, lines 7-11. 168
Exhibit 590.02, page 12.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 161
742. Mr. Berrien stated that, although the primary driver for the preferred route is the
paralleling of a future highway alignment, the highway alignment is not approved and has no
start date. Except for transmission utility corridors, transmission lines paralleling highways is not
seen as viable routing.169 Mr. Berrien testified by putting the transmission line in first, there is a
risk that it would have to be moved if it interfered with the highway.170 He also recommended the
use of monopole structures due west of the populated area of Claresholm.171
743. CERC argued that the absence of consultation should not be viewed as a shortcoming in
Mr. Berrien's approach. According to Mr. Berrien, individual preferences should not trump good
siting principles.172
744. Mr. Wallis stated that the CERC route was shorter in length and intersected significantly
less native habitat than the preferred route.173
745. CERC requested that the Commission send AltaLink back to investigate the CERC route
and require it to file an amendment to the application.
746. Mr. Markle submitted concerns that the transmission line would cross the west end of his
primary aircraft runway, rendering it unusable. Mr. Markle wished to relocate the runway, but
deemed AltaLink’s compensation to be inadequate to secure the land required to develop a new
runway.
747. The Conners filed submissions on the location of the Windy Flats 138S substation along
the common portion of the preferred and alternate route. The Conners, who operate a cattle
operation, and whose lands are used for grazing and growing hay, objected to the proposed
Windy Flats 138S substation location because the transmission line would dissect their land. The
transmission line would also traverse their gravel desposit which is excavated by McNally
Contractors (2011) Ltd. The Conners argued they would suffer a material reduction in their
income due to the loss of grazing land and, more significantly, from the impact to their mining
operation. The Conners stated that 50 per cent of their income comes from gravel royalties, and
they were unsure how these royalties would be affected by a loss in the mineable area of the
gravel deposits.
748. The Conners also expressed concerns with noise, stating their lands already contain wind
turbines and transmission lines, and the noise would increase with the new line.
749. The Conners submitted that should the transmission facilities be approved, they would
suffer encumbrances on the affected sections of land where there are none currently; they would
lose the ability to develop these sections of land, and would suffer visual impacts.174 They also
stated that their residence is within close proximity of the proposed substation location and
would be subjected to visual and noise impacts.
169
Exhibit 587.02, page 45. 170
Transcript, Volume 5, page 768, lines 17-23. 171
Exhibit 587.02, page 47. 172
Exhibit 587.02. page 46. 173
Exhibit 591.02, page 1. 174
Exhibit 853.01, page 7, paragraph 41.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
162 • AUC Decision 2013-369 (October 7, 2013)
750. The Conners contended that the southern termination point of the transmission line and
the Windy Flats substation discriminates between land, and not with particular landowners, and
that the indirect effect of the applications, if approved, is to deny benefits and protections to both
the Conners and the Piikani First Nation due to their race, in breach of Section 15 of the
Charter of Canadian Rights and Freedom. They argued that they would lose the benefit and
protection which would result from the detailed environmental assessment prescribed by the
Canadian Environmental Assessment Act, and become subject to a less favourable framework for
compensation for lands taken for public purposes than those which apply under the Indian Act. In
terms of the Piikani First Nation, the Conners alleged that the Piikani lose the opportunity to
allow the further use of Reserve lands, already encumbered with electrical transmission facilities.
751. McNally Contractors (2011) Ltd. submitted concerns with the routing of the south
Foothills line stating that the line may impact the gravel extraction operation, potentially
sterilizing the land.175 It requested that the Commission consider compensation for lost
extraction, relaxation of setback from the line, potential crossing and encroachment conflicts,
gradelines of the line’s right-of-way, and potential grant of easements to access the gravel when
evaluating the south Foothills project.
752. Sabrina and Jason Paradis submitted their concerns regarding health effects, property
value and visual impacts. They stated that there was no guarantee that transmission lines do not
impact health, and that their property value would decrease because the transmission line would
be directly in front of their property. The Paradis, who did not attend the hearing, added that they
did not want the transmission line on the alternate route and that it should be placed by the
existing 911L line.176
10.3 Hybrid A versus Hybrid B
10.3.1 Views of AltaLink
753. AltaLink developed two hybrid routes utilizing the Claresholm Connector. Hybrid A
consists of the south portion of the preferred route, the Claresholm Connector, and the north
portion of the alternate route. Hybrid B consists of the south portion of the alternate route, the
Claresholm Connector, and the north portion of the preferred route.
175
Exhibit 437.02, McNally Rule 001 Section 24 response to notice. 176
Exhibit 707.01, Paradis Rule 001 Section 24 response to notice.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 163
Table 9. Project assessment metrics for the hybrid routes177
Major aspects and considerations Hybrid A Hybrid B
Total right-of-way length (km) 135 125
Agriculture
Cultivated Land Crossed (km) 77 94
Cultivated land crosses where there is no existing parallel transmission line (km) 23 41
Forage land (tame pasture) crossed (km) 11 2
Irrigated parcels crossed (km) 7 2
Residential
Residences within 150 m of centreline (#) 2 1
Residences within 800 m from right-of-way edge (#) 105 83
Environmental
Surface water in or within 800 m of right-of-way (ha) 486 249
GVI - total native prairie crossed (km) 28 19
Protected or provincially designated areas and environmentally sensitive areas in or within 800 m of right-of-way (#) 2 2
Species of management concern and Species at Risk Act listed species observations in or within 800 m of right-of-way (#) 162 44
Special considerations
LSDs with listed historical values in or within 800 m of right-of-way (#) 520 299
Class 1 0 0
Class 2 0 0
Class 3 0 0
Class 4 40 20
Class 5 480 279
Airfields in or within 800 m of right-of-way edge (#) 1 0
Aggregate areas in or within 800 m of right-of-way edge (#) 1 0
Opportunity to parallel transmission line to be salvaged (#) 40 46
Technical considerations
Number of heavy angles or dead-end structures (#) 70 47
754. AltaLink stated that, when comparing the two routes which utilized the
Claresholm Connector, Hybrid B appears to be superior based on the metrics set out above.
Hybrid B is the shorter route, has fewer residential and environmental impacts and fewer special
considerations.
755. When comparing agricultural impacts, Hybrid A would cross fewer cultivated lands, both
in total and where there is no existing parallel transmission line. However, Hybrid A would cross
more forage land and more irrigated parcels than Hybrid B.
177
Exhibit 793.01, AML undertaking 008.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
164 • AUC Decision 2013-369 (October 7, 2013)
756. Both residential impacts and environmental impacts favour the Hybrid B route. Hybrid B
had fewer residences within 150 metres and 800 metres, and outperformed Hybrid A from an
environmental perspective. In addition, Hybrid B contains fewer sections of land with listed
historical resource values, airfields and aggregated areas within 800 metres of the edge of the
right-of-way, parallels existing transmission lines for a greater length and utilizes fewer heavy
angle or dead-end structures.
757. Hybrid A would impact all interveners who objected to the projects, while Hybrid B
would bypass both the CERC group and the Paradis lands. Because the Conners are located on a
common portion of the preferred and alternate routes, they would be impacted by both hybrid
options. Mr. Mark Lamb, whose residence is located along the Claresholm Connector, would
also be impacted by both hybrid routes.
10.3.2 Views of the interveners
758. Mr. Lamb submitted his concerns, in writing, that the transmission line would interfere
with his haystacks and calf operation. He was also concerned about decreased cellphone
reception and decreased property value. The transmission line right-of-way would run in
between two of his sections of land. He did not file any evidence and did not attend the hearing.
No other comments or evidence on the hybrid routes was submitted by any of the interveners.
10.4 Preferred versus Hybrid B
10.4.1 Views of AltaLink
759. The Hybrid B route consisted of the north portion of the preferred route, the
Claresholm Connector, and the south portion of the alternate route. To compare the two routes,
the south portion of the preferred route could be compared with the south portion of the alternate
route in combination with the Claresholm Connector. AltaLink provided a route assessment
metric of the half routes in its undertaking 008; however, this table did not factor in the
Claresholm Connector.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 165
Table 10. Project assessment metrics for the south portion of the preferred and alternate routes178
Major aspects and considerations Preferred route -
south Alternate route -
south
A100-A60 A100-B64-B50
Total right-of-way length (km) 58 57
Agriculture
Cultivated land Crossed (km) 25 38
Cultivated land crosses where there is no existing parallel transmission line (km) 16 38
Forage land (tame pasture) crossed (km) 11 2
Irrigated parcels crossed (km) 7 2
Residential
Residences within 150 m of centreline (#) 1 0
Residences within 800 m from right-of-way edge (#) 55 32
Environmental
Surface water in or within 800 m of right-of-way (ha) 228 205
GVI – Total native prairie crossed (km) 18 13
Protected or provincially designated areas and environmentally sensitive areas in or within 800 m of right-of-way(#) 1 1
Species of management concern and Species at Risk Act listed species observations in or within 800 m of right-of-way (#) 114 34
Special considerations
LSDs with listed historical values in or within 800 m of right-of-way (#) 367 211
Class 1 0 0
Class 2 0 0
Class 3 0 0
Class 4 17 17
Class 5 350 194
Airfields in or within 800 m of right-of-way edge (#) 1 1
Aggregate areas in or within 800 m of right-of-way edge (#) 1 1
Opportunity to parallel transmission line to be salvaged (#) 24 0
Technical considerations
Number of heavy angles or dead-end structures (#) 28 19
760. When comparing the preferred route to the Hybrid B route, AltaLink stated that the
preferred route is the route with the lowest overall impact179 because there are fewer agricultural,
residential, and environmental impacts on the preferred route and that costs would be similar.
761. AltaLink argued that while the Hybrid B route has 16 fewer residences within
800 metres, all residences along the Claresholm Connector and south alternate route (five and
32 residences, respectively) would be newly exposed to transmission lines because the
178
Exhibit 793.01, AML undertaking 008. 179
Exhibit 854.01, page 25, paragraph 52.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
166 • AUC Decision 2013-369 (October 7, 2013)
residences are not near existing lines.180 The Hybrid B route has one less residence within
150 metres of the centreline.
762. AltaLink stated the preferred route provides greater opportunities to minimize potential
agricultural impacts than the Hybrid B route as the preferred route crosses less cultivated land.181
763. AltaLink also argued that the preferred route has less environmental impacts. While
Hybrid B has fewer species of management concern and Species at Risk Act listed species
observations within 800 metres, the majority of these are hawks nesting on the existing 911L line
structures, which will be salvaged regardless of which route is selected. It pointed out that an
advantage of the preferred route is that new structures will be constructed near the 911L line,
allowing the hawks an opportunity to relocate nests on the new structures in the area. With the
Hybrid B route, the existing 911L line structures would be removed but the new structures would
not be erected in the area, removing the potential for hawks to relocate in the existing area.182
764. AltaLink added that Hybrid B has fewer sections of land with listed historic resource
value in or within 800 metres but noted that the majority of these historic resources have a value
of Class 5, which are limited in terms of significance.183
765. According to AltaLink, the cost of the two options would be similar. While Hybrid B is a
longer route, it requires fewer dead-end structures.184
766. AltaLink indicated that 80 per cent of landowners along the preferred route have agreed
to the siting of the preferred route and that land procurement has not occurred for the
Claresholm Connector or the alternate south route. It also stated that Mr. Lamb, located on the
Claresholm Connector, would have the right-of-way across all three of his quarter sections and
four structures located on his lands.
767. Overall, AltaLink views the preferred route as a better route because a large portion of
the line is parallel to the 911L line. For Hybrid B, a portion of the line would be a new impact,
siting a line where none previously existed.185
10.5 Commission findings
10.5.1 Preferred versus alternate route
768. In making its decision, the Commission took into account that for a majority of the route,
the preferred route parallels the existing 911L line which is scheduled to be salvaged at the end
of the SATR development. As a result, the majority of the route would continue to have similar
impacts, with the new 1037L/1038L line replacing the 911L line.
769. The Commission also finds the preferred route is a better route as it is shorter in length,
has fewer agricultural impacts, and because it will cross less cultivated lands and a majority of
these cultivated lands are lands where the existing 911L line is paralleled. Farming activity in
180
Exhibit 854.01, page 26, paragraph 54 (b). 181
Exhibit 854.01, page 26, paragraph 54 (a). 182
Exhibit 854.01, page 26, paragraph 54 (c). 183
Exhibit 854.01, page 26, paragraph 54 (d). 184
Exhibit 854.01, page 26, paragraph 54 (e). 185
Exhibit 854.01, page 27, paragraph 57.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 167
these areas has adapted in the presence of the existing lines and the impact to agriculture is
viewed as an incremental impact. The Commission views impacts on agriculture where no line
currently exists as having a greater potential impact. The alternate route crosses nearly three
times more agricultural lands with no existing transmission lines than the preferred route. While
more irrigated parcels are crossed by the preferred route, the incremental impact on irrigation
pivots is higher on the alternate route than the preferred route.
770. The preferred route also crosses significantly fewer lands with nearby surface water.
While the preferred route has a high number of observed species of concern or listed species, this
is a lower impact given the amount of the transmission line that is parallel to the 911L line. In
contrast, the alternate route would be sited on a greenfield route and potentially has a greater
impact to these species. In making this finding, the Commission considered the following
evidence by Mr. Wallis:
Of the proposed routes, the preferred route is considered more suitable from a biophysical
perspective primarily because it:
• Parallels a greater length of transmission lines and, therefore, contributes to less
overall fragmentation of habitat;186
771. While the preferred route contains more sections of lands with listed historical resource
values within 800 metres of the right-of-way, the majority of these resources are designated as
Historical Resource Value (HRV) 5. In addition, the impacts to these historic resource values can
be mitigated.
772. It was noted that none of the interveners advocated for the alternate route. During
testimony, the experts of the CERC group commented that they either did not evaluate the
alternate route,187 or that both routes were equal.188
10.5.2 Hybrid A route versus Hybrid B route
773. According to the assessment criteria provided by AltaLink, the Hybrid B option is better
in nearly every aspect. Hybrid B is shorter, has fewer residential and environmental impacts,
fewer impacts on historical resources, and parallels more existing transmission than Hybrid A.
Hybrid B is also less costly189 because it is shorter and contains significantly fewer heavy angle
and dead-end structures.
10.5.3 Preferred route versus Hybrid B route
774. The Hybrid B route consists of the same north portion as the preferred route, but
incorporates the Claresholm Connector and the south portion of the alternate route.
775. The Commission finds that the preferred route and the Hybrid B route appear to be
similar in terms of route length, agricultural impacts, residential impacts, environmental impacts,
and cost. When considering the benefits of paralleling existing linear disturbances, the preferred
route appears to have fewer overall impacts. Hybrid B consists of the south alternate route,
which does not parallel the existing 911L line.
186
Exhibit 591.02, Cliff Wallis Expert Report, page 19. 187
Transcript, Volume 5, page 803, lines 13-25. 188
Transcript, Volume 5, pages 743-744, lines 19-25, 1. 189
Exhibit 794.01, AML undertaking 009.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
168 • AUC Decision 2013-369 (October 7, 2013)
776. The Commission considers that while the raw number of residences within 150 metres
and 800 metres appear to favour the Hybrid B route, Hybrid B would newly impact more
residences. The potential environmental impacts appear to be similar between the preferred route
and the Hybrid B route with the exception of the observed listed species metric. As a significant
proportion of the preferred route is parallel to the 911L line, many potential impacts on wetlands
and native prairie along the preferred route are incremental. Along the Hybrid B route potential
impacts on wetlands and native prairie would be new. More listed species were observed along
the preferred route than the Hybrid B route, but approximately half of the preferred route is
parallel to the 911L line. Where the observed listed species are viewed along the section of the
preferred route which parallels the 911L line, observed species on the equivalent segment of the
Hybrid B route would be along a greenfield route. However, the evidence submitted was that
hawks, which were the observed species, are able to relocate their nests in a similar area on the
preferred route, which offers an additional reduction of environmental impacts.
777. The Commission finds that the preferred route has lower agricultural impacts because it
crosses less cultivated land, both overall and where there is no existing parallel transmission line.
The Hybrid B route crosses much more cultivated land where no existing transmission line is
present. For lands with historical resource value, the equivalent south portions of the Hybrid B
route and the preferred route contain the same number of sections of land with a historical
resource value of 1, 2, 3 and 4 while the preferred route has more HRV 5 lands, which tend to be
less significant. AltaLink estimates that both the preferred and Hybrid B routes will be similar in
cost; therefore cost is not a significant factor in choosing the better route.
778. The Commission finds that overall, the preferred route will be of lower impact than the
Hybrid B route. In the longer term the preferred route would result in incremental impacts, where
the line would be sited next to the existing 911L line, followed by a substitution impact, once the
911L line is salvaged; whereas for portions of the Hybrid B route, there would be a new impact
on a greenfield route. In addition, the approval of the Hybrid B route would result in a delay in
construction and the AESO has stated that the need for the 911L line rebuild is urgent.190
10.5.4 Preferred route versus CERC route
779. The proposed CERC route appears to be a shorter option compared to the preferred route,
and would parallel the 911L line. However, the preferred route has lower agricultural impacts
because there are fewer towers in cultivated fields.
780. The preferred route does not have any residences within 150 metres, while the CERC
route has two residences within 150 metres. Similarly, the preferred route has considerably fewer
residences within 800 metres. While the new towers are larger than the existing 911L line
towers, the CERC route would generally result in similar visual impacts to what is currently
experienced. On the preferred route, the transmission line would result in a new visual impact.
AltaLink’s evidence was that there are more unobstructed views of the transmission line along
the CERC route than there would be on the preferred route. There are more residences on the
west side of Claresholm and many of the residences on the east side have trees and buildings
obstructing the view of the line on the proposed route to the east. The future Highway 2 bypass
will be situated between the residences along the east side of town and the transmission line.
Based on the above, the Commission finds that the overall residential impact is lower on the
190
Transcript, Volume 2, page 235, lines 1-11.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 169
preferred route and that the visual impact is similar along both routes, given the subjective nature
of visual impacts. Despite the fact that more residences are situated along the CERC route than
the preferred route, the Commission finds that the CERC route would generally result in
incremental residential and visual impacts due to the existence of the 911L line. Further, the
preferred route is a greenfield route, which would result in new residential and visual impacts.
781. The Commission finds that the environmental impact is slightly greater on the preferred
route because it crosses more wetlands and is longer. The preferred route is also a greenfield
route, despite the fact that a future highway will be situated nearby.
782. The Commission encourages the paralleling of existing linear disturbances because it
reduces impacts. The CERC route parallels the 911L line for the entire length. While the
preferred route moves away from the 911L line near the town of Claresholm, it will be parallel to
the future Highway 2 bypass. The Commission agrees with AltaLink and the Town of
Claresholm that transmission lines are compatible with commercial and industrial land uses. The
Commission does not agree with CERC that the transmission line will interfere with commercial
and industrial development because it views them as compatible developments.
783. CERC argued that there is uncertainty that the Highway 2 bypass will be built and that
the transmission line could impede the highway because it would be built first. The Commission
has not heard evidence regarding the status of the highway project, but notes that Alberta
Transportation supports the preferred route. Further, AltaLink’s evidence is that it has worked,
and will continue to work, with Alberta Transportation on the alignment of the transmission line
with the highway.
784. The Commission finds that AltaLink’s preferred route may be the lower impact route of
the two, given its lesser residential impact. In the longer term, the preferred route will be
paralleling a major linear structure; whereas, the CERC route will not. The preferred route also
more adequately aligns with the Town of Claresholm’s development plans and is supported by
the M.D. of Willow Creek. The preferred route is however a greenfield route, in a location where
an existing transmission line is not present, while the CERC route would be situated next to an
existing transmission line where land use has evolved with the presence of the line. The
Commission does find the argument for the CERC route to be compelling, because the route
parallels the 911L line as it passes the town of Claresholm, resulting in a shorter and less
expensive route. Further, the Commission took into account the submissions of AltaLink
regarding the paralleling of the 911L line and the reduction in impacts in relation to a greenfield
route. The Commission considers that paralleling an existing transmission line or using an
existing right-of-way results in fewer impacts as discussed above and finds merit in the CERC
submissions. However, as AltaLink did not apply for the CERC route, additional information on
this route such as stakeholder consultation is not on the record. Consequently, while the
Commission approves the preferred route over the alternate route in this area, the Commission
also directs AltaLink to examine the CERC route in accordance with the requirements of AUC
Rule 007.
785. AltaLink is directed to file a report with the Commission describing the progress of this
investigation by December 31, 2013. If the CERC route can be achieved with a reduction in
overall impact, the Commission will determine whether AltaLink will be required to file an
amendment to the permit and licence.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
170 • AUC Decision 2013-369 (October 7, 2013)
10.5.5 Windy Flats 138S substation
786. With regard to the siting of the Windy Flats 138S substation, the alternate substation site
would require the transmission line to pass close to the Conners’ residence, while at the preferred
substation site the transmission line would be further from the residence, but closer to the gravel
pit. The Commission has taken into account that any gravel that is sterilized by the transmission
line may be compensated and finds that the potential impacts on the Conners’ residence would
be greater than on the gravel pit.
787. The Commission views grazing and hay farming activities as not incompatible with the
presence of a transmission line. Considering that there is an operating gravel pit in the vicinity of
the proposed substation, as well as existing wind turbines, and that the gravel pit is closer to the
residence than the proposed substation, the Commission did not accept the Conners' submissions
on potential visual impacts and noise impacts of the proposed substation and transmission line on
their land. In addition, the substation and proposed transmission line satisfy the noise
requirements of AUC Rule 012.
788. As a result, the Commission finds that the preferred location is the lowest impact location
for the proposed Windy Flats 138S substation.
789. Regarding the alleged breach of Section 15 of the Charter of Canadian Rights and
Freedoms, a person who alleges the breach must show discrimination "in the sense that it denies
human dignity or treats people as less worthy".191 There is no evidence in this proceeding of any
such discrimination. The Conners did not submit any evidence of any such discrimination nor
can any such conclusion be drawn from any other evidence before the Commission in this
proceeding. Further, the Commission is of the view that there is no basis for the argument that
the effect of the SATR NID approval amendment is to discriminate against the Conners or the
Piikani First Nation due to their race. The Commission is satisfied that the reason for the change
in the substation location is due to the potential for delay associated with the Peigan substation
upgrades on federal lands, which poses scheduling implications and risks that are unacceptable to
the AESO as the transmission system planner.
790. The fact that the process for acquiring access to federal lands is different than the process
for acquiring access to lands that are subject to provincial jurisdiction results in the delay has
nothing to do with the race of either the Conners or the Piikani First Nation. The fact that
different legal regimes apply to the Piikani First Nation and other Crown lands, and to the
Conners, is reflective of the division of powers set out in sections 91 and 92 of the
Canadian Constitution.
791. Accordingly, the Commission finds that the Conners have not shown that a breach of
Section 15 of the Charter exists.
191
Gosselin v. Quebec (Attorney General) [2002] 4 S.C.R. 429, paragraph. 17. See also Canadian Foundation for
Children, Youth and the Law v. Canada [2004] 1 SCR 76 at paragraph 53.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 171
11 ENMAX Application No. 1608649
11.1 Discussion
792. The Alberta Electric System Operator identified a need to reinforce the transmission
system in the south Calgary and High River planning areas. This reinforcement would alleviate
the existing and anticipated constraints arising from the expected load growth and integration of
the proposed generation capacity within the applications area, as well as facilitate the
transmission of generation from southern Alberta.
793. The ENMAX portion of the proposed system upgrade has three main components.
Modifications to both the ENMAX No. 65 and ENMAX No. 25 substations as well as the
construction and operation of a 240-kV transmission line designated as 1064L/1065L, which will
be within the ENMAX service territory from the Langdon and Janet substations.
794. The ENMAX No. 65 substation is located at 9100 Marquis of Lorne Trail S.E., Calgary,
Alberta. The AESO has requested that ENMAX modify the ENMAX No. 65 substation by
disconnecting the existing AltaLink 240-kV 911L line, and terminating three new AltaLink
240-kV transmission lines 1106L, 1107L and 1109L.
795. The ENMAX No. 25 substation is located at 9500-100 Street S.E. Calgary, Alberta. This
substation will require the interconnection of two new AltaLink 240-kV transmission lines
1109L and 985L.
796. ENMAX will also be the owner and operator of the portion of 240-kV 1064L/1065L line
in the ENMAX service territory. ENMAX and AltaLink have agreed that AltaLink would
perform all consultation and construction on behalf of ENMAX. ENMAX will be the owner and
have joint operating procedures with AltaLink to ensure safe reliable operation of the lines.
797. ENMAX stated that the cost for the project modifications of the ENMAX No. 25 and
ENMAX No. 65 substations is $4.3 million based on a +20%/-10% contingency.
798. ENMAX indicated that the construction for the ENMAX No. 65 substation would be
contained entirely within the substation fence. Construction for the ENMAX No. 25 substation
would take place within the substation, and would consist of the installation of additional
protection and control equipment within the substation control building to accommodate the
240-kV line additions. No outdoor construction would be required for the ENMAX No. 25
substation. ENMAX added that the potential environmental impacts and noise impact assessment
for both the ENMAX No. 25 and ENMAX No. 65 substations had not changed since these
substations were approved in AUC Decisions 2012-283 and 2011-435, respectively.
11.2 Commission findings
799. The Commission accepts ENMAX's submissions that there would be no new
environmental impacts caused by the modifications of the ENMAX No. 25 and ENMAX No. 65
substations, because the modifications would be entirely within the substation fence for the
ENMAX No. 65 substation and within the control building for the ENMAX No. 25 substation.
800. The Commission is satisfied that the technical information submitted by ENMAX fulfills
the requirements of AUC Rule 007 and that the participant involvement program was conducted
in accordance with AUC Rule 007.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
172 • AUC Decision 2013-369 (October 7, 2013)
801. No persons objected to the ENMAX application.
802. The Commission further finds that the modification to the substation is consistent with
the need identified in the FATD NID.
803. Based on the forgoing, the Commission approves the applications to modify both the
ENMAX No. 25 and No. 65 substations and finds that the modifications are in the public interest
pursuant to Section 17 of the Alberta Utilities Act.
12 Decision
804. After careful consideration of the record of the proceeding and for the reasons set out
above, the Commission finds that the approval of the project, as follows, is in the public interest
having regard to the technical, social and economic effect of the project, and its effects on the
environment.
805. Pursuant to Section 34 of the Electric Utilities Act and Section 38 of the
Transmission Regulation, the Commission approves the following applications and grants the
AESO the needs identification document approvals which will be distributed separately:
Application No. 1608620, application of the Alberta Electric System Operator for
approval of the needs identification document for 240-kV and 138-kV transmission
system expansion in the vicinities of southeast Calgary, Okotoks and High River –
Foothills Area Transmission Development Plan
Application No. 1608846, Windy Flats Amendment to the Alberta Utilities Commission
Southern Alberta Transmission System Reinforcement (SATR) Approval No. U2011-115
(SATR NID Approval)
806. Pursuant to sections 14, 15, 18, 19 and 21 of the Hydro and Electric Energy Act, the
Commission approves the following applications and grants permits and licences with specific
conditions as detailed below to AltaLink, and ENMAX, respectively. The approvals will be
distributed separately.
Application No. 1608642 Langdon to Janet project
Application No. 1608637 north Foothills transmission project
Application No. 1608643 Foothills 138-kV project
Application No. 1608861 south Foothills transmission project
Application No. 1608862 Windy Flats 138S substation and line reconfiguration
Application No. 1608649 ENMAX alterations to ENMAX No. 25 and No. 65 substations
807. With respect to Application No. 1608642, the Langdon to Janet project, the preferred
route is approved for the proposed 1064L/1065L line. However, the approval is subject to the
following condition:
The use of monopole structures immediately adjacent to Mr. Mattson’s property from
route marker B260 to route marker B265 across the northwest quarter of Section 13,
Township 23, Range 28, west of the Fourth Meridian if Mr. Mattson declines the buyout
option offered by AltaLink.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 173
808. With respect to Application No. 1608637 north Foothills transmission project, the
following is approved:
the D12 site for the Foothills 237S substation site
the preferred route for the proposed 1106L/1107L line
the one-tower option at the Bow River crossing
809. However, the approval is subject to the following conditions:
AltaLink will file with the Commission the written consent of the Minister of
Infrastructure, to construct the portion of the 1106L/1107L line within the transmission
utility corridor on the east side of Calgary .
810. With respect to Application No. 1608643, the Foothills 138-kV project, the hybrid route
as described below is approved for the double-circuit portion of the proposed 434/646L line.
To start from the D12 site of the Foothills 237S substation, follow the
stakeholder-suggested route to route marker B20, then follow the preferred route to route
marker A39, and finally follow the alternate route to the High River 65S substation.
811. Lastly, with respect to Application No. 1608861, the south Foothills transmission project,
the preferred site is approved for the proposed Windy Flats 138S substation and the preferred
route is approved for the proposed 1037L/1038L line. However, the approval is subject to the
following:
AltaLink will examine the CERC route in accordance with the requirements of AUC
Rule 007 and is directed to file a report with the Commission describing the progress of
this investigation by December 31, 2013. If this route can be achieved with a reduction in
overall impact, the Commission will determine whether AltaLink will be required to file
an amendment to the permit and licence.
Dated on October 7, 2013.
The Alberta Utilities Commission
(original signed by)
Anne Michaud
Panel Chair
(original signed by)
Neil Jamieson
Commission Member
(original signed by)
Patrick Brennan
Acting Commission Member
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 175
Appendix A: Proceeding participants who have registered a statement of intent to
participate
Name of Person or group Counsel or Representative
Alberta Electric System Operator D. Davies and J. Cusano
AltaLink Management Ltd. P. Feldberg
ENMAX Power Corporation D. Wood
590140 Alberta Limited C. Simonelli
1297833 Alberta Inc. S. FitzGerald
Alberta Tourism Parks and Recreation
M. Arca
Astral Media Radio B. Stovold
Benign Energy Canada II Inc. A. Kettles
B.F.W. Holdings (2006) Ltd. Syd Mantler
Bow River Crossing group S. Stenbeck
Bow Vista Farms Ltd. S. Stenbeck
J. Camacho
Camrock Capital Partners GP (40) Ltd
A. Chehabeddine
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
176 • AUC Decision 2013-369 (October 7, 2013)
Name of Person or group Counsel or Representative
M. Chehabeddine
Committee for East Route Conservation (CERC)
R. and L. Conner C. McGarvey
D. Coonfer
T. Dawson
Diagonal Group G. Fitch
ENMAX Green Power Inc. R. McKee
ENMAX Shepard Inc. J. Schlauch
Foster Family Trust N. Patterson
F.L. and E. Fowler
Abdul and Mohamed Hage J. Tannahill
Industrial Power Consumers Association of Alberta M. Forster and V. Bellissimo
H. Jackson
B. Joneja
F. Kaaki
J. Kyle
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 177
Name of Person or group Counsel or Representative
G. Lamb
K. Lamb
M. Lamb
Louson Investment Ltd. and Glen Eagles Investments Ltd. G. Fitch
F. Lozeman
J. and D. MacLellan
C. Markle
Mattson Group M. Niven and N. Ramessar
The McLaren and Carlson group J. Price and J. Bolton
D. Meier, D. Meier and M. Meier S. FitzGerald
R. Miller
L. Moor
W. Moore
D. Nauta
R. and G. Nauta
J. and S. Paradis
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
178 • AUC Decision 2013-369 (October 7, 2013)
Name of Person or group Counsel or Representative
H. Park
R. and R. Pearson J. Laycraft
D. Pope
Powerex Corp. C. Ferguson
Randle group J. Laycraft
P. Robertson G. Fitch and M. Barbero
Scandinadian Development Consultants C. Hansen
B. Schnarr
J. Shutiak
V. Steele
Y. Shin
J. Taplin
TD&T Properties D. Leeds
Town of High River K. Mohammed
TransAlta Corporation
TransCanada Energy Limited S. Kley
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 179
Name of Person or group Counsel or Representative
M. Vandervalk
Volker Stevin/McNally Contractors (2011) Ltd.
T. Wallace
A. Weeks
C. and C. Woolridge
D. Zuck
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
180 • AUC Decision 2013-369 (October 7, 2013)
Appendix B: Oral hearing
Name of Person or Group Counsel or Representative
Witnesses
Alberta Electric System Operator D. Davies A. Culos
J. Doering G. Lam L. Papworth A. Rehman
AltaLink Management Ltd. P. Feldberg J. Liteplo B. Hunter J. Yearsley
L. Erdreich H. Foley M. Gahbauer C. Harvey D. Hoover J. Howland W. Mundy J. Power A. Reimer S. Sutherland
ENMAX Power Corporation D. Wood
S. Kumar M. Wong
1297833 Alberta Inc. S. FitzGerald
B.F.W. Holdings (2006) Ltd. S. Mantler
Benign Energy Canada II Inc. A. Kettles
Bow River Crossing group S. Stenbeck
R. Berrien J. Brunen L. Klatzel-Muldry D. Pate C. Wallis
Bow Vista Farms Ltd. S. Stenbeck
L. Azevedo R. Berrien M. Janzen C. Malgedhem C. Wallis
Committee for East Route Conservation (CERC) R. Secord
R. Berrien C. Brunner D. Brunner J. Burnham W. Burnham G. Donaldson A. Fisher K. Fisher P. Fisher E. Mulholland D. Nelson J. Senos C. Wallis
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 181
R. and L. Conner C. McGarvey
L. Conner R. Conner
Diagonal Group G. Fitch
S. Acteson T. Cline L. Dugdale R. Dugdale K. Friesz G. Harmeson S. McMurray
Foster Family Trust N. Patterson
Industrial Power Consumers Association of Alberta N. Patterson
V. Bellissimo J. Cheng P. Kos
Louson Investment Ltd. and Glen Eagles Investments Ltd. G. Fitch
Mattson Group M. Niven and N. Ramessar
J. Beck V. Bretin S. Buckley R. Levesque T. Mattson K. Schemenauer
The McLaren and Carlson group J. Price and J. Bolton
S. Carlson D. McLaren P. McLaren R. Telford
D. Meier S. FitzGerald
R. and G. Nauta
R. and R. Pearson J. Laycraft
R. Pearson
Powerex Corp. C. Ferguson L. Manning
G. Dobson-Mack K. Kabiri
Randle group J. Laycraft
R. Berrien F. Randle C. Wallis
P. Robertson G. Fitch and M. Barbero
S. Acteson T. Cline P. Robertson
TD&T Properties D. Leeds
Town of High River K. Mohammed
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
182 • AUC Decision 2013-369 (October 7, 2013)
TransCanada Energy Ltd. S. Kley
Alberta Utilities Commission Commission Panel A. Michaud, Panel chair N. Jamieson, Commission member P. Brennan, Acting Commission member Commission Staff
G Bentivegna (Commission Counsel) T. Chan S. Jiang V. Choy K. Taylor E. Neuhart L. Charest J. Law
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 183
Appendix C: Abbreviations
2012LTO AESO’s 2012 Long-Term Outlook Load and
Generation Forecast
2012LTOU AESO 2012 Long-Term Outlook Update
AESO Alberta Electric System Operator
AltaLink AltaLink Management Ltd.
Arrow Arrow Archaeology Limited
Astral Astral Media Radio GP
AUC Alberta Utilities Commission
AUC Rule 007 AUC Rule 007: Applications for Power Plants,
Substations, Transmission Lines, and Industrial System
Designations
AUC Rule 012 AUC Rule 012: Noise Control
Benign Energy Benign Energy Canada II Inc.
CERC Committee for East Route Conservation
CERC route Route option preferred by the CERC group
CO2 Carbon dioxide
Commission Alberta Utilities Commission
dBA decibels A-weighted
EATL Eastern Alberta Transmission Line
EMF electric and magnetic fields
ENMAX ENMAX Power Corporation
EGPI ENMAX Green Power Inc.
ESA environmentally significant area
ESI ENMAX Shepard Inc.
ESR Environmental Specifications and Requirements
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
184 • AUC Decision 2013-369 (October 7, 2013)
EUB Alberta Energy and Utilities Board
FATD Foothills Area Transmission Development
FC2009 AESO’s 2009 Corporate Load Forecast
GHG greenhouse gas
Gleneagles Gleneagles Investments Ltd.
GPS global positioning system
Grid Power Grid Power Development and Design Inc.
ha hectares
HRV Historical Resource Value
HVDC High-voltage direct-current
ICNIRP International Commission on Non-Ionizing Radiation
Protection
ISO Independent System Operator
IPCAA Industrial Power Consumer Association Alberta
km kilometres
kV kilovolt
kV/m Kilovolts per metre
Leq equivalent sound level
Louson Louson Investments Ltd.
m metres
M.D. Municipal district
Meiers Daniel, Julie, Deborah and Michael Meier
mG milli gauss
MVA megavolt ampere
MW megawatt
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2013-369 (October 7, 2013) • 185
NID Needs Identification Document
OPP Operating Policies and Procedures
Powerex Powerex Corp.
Powertech Powertech Labs Inc.
SATR Southern Alberta Transmission Reinforcement
Stantec Stantec Consulting Ltd.
TransAlta TransAlta Corporation
TransCanada TransCanada Energy Ltd.
TTC total transfer capability
WATL Western Alberta Transmission Line
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
186 • AUC Decision 2013-369 (October 7, 2013)
Appendix D: Process meeting Decision 2012-360
Decision 2012-360.pdf
(consists of 27 pages)
Decision 2012-360
Alberta Electric System Operator, AltaLink Management Ltd. and ENMAX Power Corporation Foothills Area Transmission Development Process Meeting Decision December 24, 2012
The Alberta Utilities Commission
Decision 2012-360: Alberta Electric System Operator, AltaLink Management Ltd.
and ENMAX Power Corporation
Foothills Area Transmission Development - Process Meeting
Applications No. 1608620, No. 1608637, No. 1608642, No. 1608643,
No. 1608649, No. 1608846, No. 1608861 and No. 1608862
Proceeding ID No. 2001
December 24, 2012
Published by
Alberta Utilities Commission
Fifth Avenue Place, Fourth Floor, 425 First Street S.W.
Calgary, Alberta
T2P 3L8
Telephone: 403-592-8845
Fax: 403-592-4406
Website: www.auc.ab.ca
AUC Decision 2012-360 (December 24, 2012) • i
Contents
1 Introduction and background .............................................................................................. 1 1.1 Details of the applications .............................................................................................. 1 1.2 Applications filed by the AESO ..................................................................................... 1 1.3 Applications filed by AltaLink....................................................................................... 1 1.4 Application filed by ENMAX ........................................................................................ 2
1.5 Commission’s process .................................................................................................... 3
2 Legislative framework .......................................................................................................... 4 2.1 Assessment of need ........................................................................................................ 4 2.2 Assessment of the facility applications .......................................................................... 5
3 Issues ...................................................................................................................................... 7 3.1 Issues related to the AESO’s applications ..................................................................... 7
3.2 Issues for the facility applications .................................................................................. 8
4 Standing ................................................................................................................................. 9 4.1 Standing for the AESO applications .............................................................................. 9
4.2 Standing for the AltaLink and ENMAX facility applications ..................................... 11 4.2.1 Landowners or residents within 800 metres of a proposed right-of-way ....... 11
4.2.2 Landowners or residents outside of 800 metres .............................................. 11 4.2.3 Landowners with insufficient information...................................................... 12 4.2.4 Landowner groups .......................................................................................... 12
4.2.5 Other parties .................................................................................................... 13
4.2.6 Further written process for standing ............................................................... 13
5 Hearing process, schedule and location ............................................................................ 13 5.1 Hearing process and schedule ...................................................................................... 14
5.2 Written submissions ..................................................................................................... 14 5.3 Hearing location ........................................................................................................... 14
5.4 Staged proceeding ........................................................................................................ 14
Schedule A – Process meeting participants .............................................................................. 17
Schedule B – Persons with standing .......................................................................................... 19
Schedule C – Persons outside of 800 metres ............................................................................. 21
Schedule D – Persons with insufficient information ................................................................ 22
Schedule E – Groups with members that have standing ......................................................... 23
AUC Decision 2012-360 (December 24, 2012) • 1
The Alberta Utilities Commission
Calgary, Alberta
Alberta Electric System Operator
AltaLink Management Ltd. and
ENMAX Power Corporation Decision 2012-360
Foothills Area Transmission Development Proceeding ID No. 2001
1 Introduction and background
1.1 Details of the applications
1. In this proceeding the Alberta Utilities Commission (AUC or the Commission) is
considering eight applications. These include: two applications filed by the Alberta Electric
System Operator (AESO), five facility applications filed by AltaLink Management Ltd.
(AltaLink) and one facility application filed by ENMAX Power Corporation (ENMAX).
1.2 Applications filed by the AESO
2. The AESO filed need Application No. 1608620 with the AUC on July 5, 2012,
requesting approval of the needs identification document for the proposed 240-kilovolt (kV)
and 138-kV transmission system expansion in the vicinities of southeast Calgary, Okotoks and
High River.
3. The AESO also filed Application No. 1608846 with the AUC on September 21, 2012,
seeking approval to amend the existing need approval for the Southern Alberta Transmission
Reinforcement (SATR). In the application, the AESO proposed to replace upgrades at the Peigan
substation with construction of the new Windy Flats substation and associated transmission lines
in southern Alberta.
1.3 Applications filed by AltaLink
4. AltaLink filed three facility applications on July 12, 2012, proposing new facilities to
meet the needs identified in the AESO’s need Application No. 1608620. Each project is
described in detail in its respective application.
5. Application No. 1608642 is for the Langdon to Janet project. The major components of
this project are:
a) The construction of approximately 18 kilometres of double-circuit 240-kV transmission
line from Langdon 102S substation to Janet 74S substation.
b) Modifications to some existing transmission lines and/or substations.
c) Modifications to transmissions lines approved in AUC Proceeding ID No. 1229.
d) Modifications to a proposed substation currently being considered in AUC
Proceeding ID No.1045.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
2 • AUC Decision 2012-360 (December 24, 2012)
6. Application No. 1608637 is for the North Foothills Transmission Project. The major
components of this project are:
a) The construction of a new 240-kV Foothills 237S substation, located west of Frank Lake.
b) The construction of approximately 51 kilometres of double-circuit 240-kV transmission
line from Foothills 237S substation to ENMAX No. 65 substation.
c) The relocation of some existing transmission lines.
7. Application No. 1608643 is for the Foothills 138-kV Transmission Project. The major
components of this project are:
a) The addition of two new 240/138-kV transformers at the Foothills 237S substation.
b) Construction of two new 138-kV transmission lines from Foothills 237S substation to
High River 65S substation and to Okotoks 678S substation including 14 kilometres of
new double-circuit lines.
c) Alterations to some existing transmission line and substations.
8. On September 25, 2012, AltaLink filed two additional facility applications. These
applications are intended to implement the transmission system upgrades proposed in the
AESO’s Application No. 1608846. Each project is described in detail in its respective
application.
9. Application No. 1608861 is for the South Foothill Transmission Project. The major
components of this project are:
a) The construction of a new 240-kV Windy Flats 138S substation located southwest of
Fort McLeod in the southwest quarter of Section 17, Township 8, Range 26, west of the
Fourth Meridian.
b) The construction of approximately 120 kilometres of double-circuit 240-kV transmission
line from Windy Flats 138S substation to Foothills 237S substation.
c) Construction of a new series capacitor station SC1 266S.
d) Modifications to some existing transmission lines to facilitate the interconnection of the
Windy Flats substation to the grid.
10. Application No. 1608862 is for the Windy Flats 138-kV Project. The major components
of this project are:
a) The construction of new 138-kV substation equipment at Windy Flats 138S substation.
b) The re-termination of existing 138-kV transmission lines 603L and 608L to Windy
Flats 138S substation from the existing Peigan 59S substation.
1.4 Application filed by ENMAX
11. ENMAX filed facility Application No. 1608649 with the AUC on July 13, 2012,
requesting approval to modify ENMAX No. 25 substation and ENMAX No. 65 substation. The
proposed system reinforcement includes the following major components:
a) Addition of two 240-kV circuit breakers at ENMAX No. 65 substation.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 3
b) Termination of transmission lines 1106L, 1107L and 1109L at ENMAX No. 65
substation.
c) Termination of transmission lines 1109L and 985L at ENMAX No. 25 substation.
d) Disconnection of transmission line 911L at ENMAX No. 65 substation.
1.5 Commission’s process
12. The proposed development, including all of the applications noted above, will be referred
to as the Foothills Area Transmission Development (FATD) project.
13. The Commission issued its notice of applications for the FATD project on
August 28, 2012, after receiving the first five applications in July 2012. The notice was mailed
directly to landowners, residents and other interested parties within the Commission’s
notification zone for the project. In addition, the notice was delivered to all residences and
addresses in the project area by way of a general postal code drop. The notice of applications was
also published in five newspapers in the area of application.
14. Upon receipt of the second application filed by the AESO, as well as the additional two
facility applications filed by AltaLink described above in paragraphs 3, 9 and 10, respectively, in
September 2012 the Commission determined that it would combine these eight applications
under the same proceeding due to the related nature of the Foothills 237S substation in both
filings. The Commission issued its revised notice of applications for the FATD project on
October 19, 2012. The revised notice outlined the date and location for the process meeting.
15. The revised notice was again mailed directly to landowners, residents and other interested
parties within the Commission’s notification zone for the project. In addition, the revised notice
was delivered to all residences and addresses in the project area by way of a general postal code
drop and was also published in 11 area newspapers.
16. The Commission held three information sessions prior to the process meeting for the
FATD project; the first was held at Highwood Memorial Centre in High River, Alberta on
September 24, 2012, the second at the Indus Recreational Centre in Indus, Alberta on
September 25, 2012, and the third at the Claresholm Community Centre in Claresholm, Alberta
on November 13, 2012.
17. The process meeting was held on November 26, 2012, at the Heritage Inn Hotel &
Convention Centre before Commission Member Anne Michaud. Those interested parties who
appeared at the process meeting are set out in Schedule A to this decision.
18. At the process meeting, interested parties were invited to make a brief appearance before
the Commission to identify their interest in the application, their intended scope of participation,
the issues relevant to the application, and to comment on the preliminary process schedule.
19. In reaching the determinations set out in this decision, the Commission has considered
the record of the process meeting, and the submissions and statements of intention to participate
provided by each party. References in this decision to specific parts of the record are intended to
assist the reader in understanding the Commission’s reasoning relating to a particular matter and
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
4 • AUC Decision 2012-360 (December 24, 2012)
should not be taken as an indication that the Commission did not consider all relevant portions of
the record as it relates to that matter.
2 Legislative framework
20. New transmission facilities that do not meet the definition of critical transmission
infrastructure require two separate approvals from the AUC: an approval of the need for
expansion or enhancement to the Alberta Interconnected Electric System pursuant to Section 34
of the Electric Utilities Act, and a permit to construct and licence to operate a transmission
facility pursuant to sections 14 and 15 of the Hydro and Electric Energy Act.
2.1 Assessment of need
21. The AESO, in its capacity as the independent system operator established under the
Electric Utilities Act, is responsible for preparing a needs identification document (NID) and
filing an application for approval of the NID with the AUC pursuant to Section 34 of the Electric
Utilities Act, which states:
34(1) When the Independent System Operator determines that an expansion or
enhancement of the capability of the transmission system is or may be required to meet
the needs of Alberta and is in the public interest, the Independent System Operator must
prepare and submit to the Commission for approval a needs identification document that
(a) describes the constraint or condition affecting the operation or performance of
the transmission system and indicates the means by which or the manner in
which the constraint or condition could be alleviated …
22. Section 38 of the Transmission Regulation sets out the matters to which the Commission
must have regard when considering a needs identification document:
38 When considering whether to approve a needs identification document under
section 34(3) of the Act, the Commission must
(a) have regard for the principle that it is in the public interest to foster
(i) an efficient and competitive generation market,
(ii) a transmission system that is flexible, reliable and efficient and
preserves options for future growth, and
(iii) geographic separation for the purposes of ensuring reliability of the
transmission system and efficient use of land, including the use of
rights of way, corridors or other routes that already contain or provide
for utility or energy infrastructure or the use of new rights of way,
corridors or other routes, notwithstanding that geographic separation
for the purposes of ensuring reliability of the transmission system or
efficient use of land may result in additional costs,
(b) have regard for the following matters when it considers an application for a
transmission facility upgrade or expansion, or operations preparatory to the
construction of a transmission facility, namely, the contribution of the
proposed transmission facility:
(i) to improving transmission system reliability;
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 5
(ii) to a robust competitive market;
(iii) to improvements in transmission system efficiency;
(iv) to improvements in operational flexibility;
(v) to maintaining options for long term development of the transmission
system;
(vi) to a project to which section 27 applies to provide system access service,
(c) take into account the transmission system plan filed with the Commission,
(d) take into account the ISO’s responsibilities under any enactment
(e) consider the ISO’s assessment of the need to be correct unless an interested
person satisfies the Commission that
(i) the ISO’s assessment of the need is technically deficient, or
(ii) to approve the needs identification document would not be in the
public interest.
23. Need applications filed by the AESO have generally been organized into two parts. The
first part describes the need for the proposed transmission upgrade. The discussion is based on
load forecasts, generation forecasts and system studies. The second part of a need application
describes the AESO’s preferred technical solution to address the identified need. This includes a
comparative analysis of the various options, based on three general criteria: technical attributes
and functional capability, costs and a high level assessment of land use impacts.
24. In Decision 2004-087,1 the AUC’s predecessor, the Alberta Energy and Utilities Board
(EUB or the Board), described the NID process as follows:
It is the Board’s view that section 34 contemplates a two-stage consideration of an NID.
In the first stage, the Board must determine whether an expansion or enhancement of the
capability of the transmission system is necessary to alleviate constraint, improve
efficiency, or respond to a request for system access…
If it is determined that expansion or enhancement of the system is required to address
constraint, inefficiency, system access requests, or any combination thereof, the Board
must then assess, in the second stage, whether enhancement or expansion measures
proposed by AESO are reasonable and in the public interest.2
25. The Commission has followed this two stage assessment process for all subsequent need
applications.
2.2 Assessment of the facility applications
26. The facility applications for the FATD were filed under sections 14, 15, 18 and 21 of the
Hydro and Electric Energy Act which include, in part:
1 EUB Decision 2004-084: ECNG Limited Partnership – Temporary Exemption from Requirement to Obtain
Board Approval for Compliance Plan in Accordance with Section 30(1) of the Gas Code of Conduct Regulation,
Application No. 1359872, September 29, 2004. 2 EUB Decision 2004-087, pages 13-14.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
6 • AUC Decision 2012-360 (December 24, 2012)
14(1) No person shall construct a transmission line or any part of a transmission line
unless the person is the holder of a permit issued by the Commission.
…
15 No person shall operate a transmission line unless the person is the holder of a
subsisting licence to operate the transmission line, issued by the Commission.
18(1) The owner or operator of a power plant, transmission line or electric distribution
system shall not connect that power plant, transmission line or electric distribution
system, or cause or permit it to be connected,
(a) to any other power plant, transmission line or electric distribution
system, unless the connection is in accordance with an order under this
section, or
(b) to any industrial system or other service where the connection may
seriously affect the operation of an interconnected electric system or a
communications system as prescribed in the regulations.
…
21(1) No holder of an approval, permit or licence under this Part, and no person who
operated a hydro development, power plant or transmission line on June 1, 1971, shall
discontinue the operation of, or dismantle or remove any works or installations forming
part of, the holder’s or person’s hydro development, power plant or transmission line
unless the holder or person has obtained the authority in writing of the Commission to do
so.
27. Facility applications are prepared by a transmission facility owner assigned by the AESO.
In this case, both AltaLink and ENMAX prepared their respective facility applications based on
their designated service territories. The transmission facility owner files the facility application
with the AUC for consideration. The AUC may approve or deny the application, or approve it
subject to any terms or conditions it prescribes.
28. When deciding upon a transmission facility application, the Commission is directed, by
Section 17 of the Alberta Utilities Commission Act, to consider whether construction and
operation of the proposed transmission facilities is in the public interest, having regard for their
social, economic and environmental effects. The Commission described its public interest
mandate as follows, in Decision 2009-028:3
When considering an application for a transmission line the Commission is obliged by
section 17 of the Alberta Utilities Commission Act to consider whether the proposed
project is in the public interest having regard to its social and economic effects and its
effect on the environment. The Commission recognizes that there is no universal
definition of what comprises the “public interest” and that its meaning cannot be derived
from strictly objective measures. The Commission acknowledges that the ultimate
determination of whether a particular project is in the “public interest” will largely be
dictated by the circumstances of each transmission facility application.
3 Decision 2009-028: AltaLink Management Ltd. - Transmission Line from Pincher Creek to Lethbridge,
Application No. 1521942, Proceeding ID No. 19, March 10, 2009.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 7
In the Commission’s view, assessment of the public interest requires it to balance the
benefits associated with upgrades to the transmission system with the associated impacts,
having regard to the legislative framework for transmission development in Alberta. This
exercise necessarily requires the Commission to weigh impacts that will be experienced
on a provincial basis, such as improved system performance, reliability, and access, with
specific routing impacts upon those individuals or families that reside or own land along
a proposed transmission route as well as other users of the land that may be affected. This
approach is consistent with the EUB’s historical position that the public interest standard
will generally be met by an activity that benefits the segment of the public to which the
legislation is aimed, while at the same time minimizing, or mitigating to an acceptable
degree, the potential adverse impacts on more discrete parts of the community.
3 Issues
29. Interveners identified the issues they intend to pursue in the hearing in their statements of
intention to participate and also in their oral submissions at the process meeting.
3.1 Issues related to the AESO’s applications
30. As noted above, the AESO filed two applications in this proceeding. Application
No. 1608620, is a new application that describes the need for transmission upgrades between
south Calgary and High River (FATD need application). For this application, the issues the
Commission must consider are whether the AESO’s assessment of the need for this project is
technically sufficient, and whether approval of the needs identification document is in the public
interest.
31. The Commission considers the relevant issues for Application No. 1608846, which is an
application by the AESO to amend its existing SATR need approval, to be slightly different. The
amendment proposed by the AESO in this application is not to its assessment of the need to
expand or enhance the transmissions system in southern Alberta. Rather, the AESO is seeking to
amend the technical solution it proposed to address that need. Accordingly, the Commission
finds that neither the AESO’s assessment of the need for transmission reinforcement in southern
Alberta, nor the Commission’s previous approval of that need in Decision 2009-1264 are issues
associated with this application. The issue that this application does raise, however, is whether
the specific amendments proposed by the AESO to its need approval for the Southern Alberta
Transmission Reinforcement are in the public interest. In other words, the Commission will not
be considering whether the the construction of a new 240-kV Windy Flats 138S substation and
its associated transmission lines are required to meet the need, but whether the technical solution
(Windy Flats solution) proposed is the most appropriate technical solution to meet that need.
32. Mr. Gavin Fitch, counsel for the Diagonal Group, Louson Investments Ltd. and Glen
Eagles Investment Ltd., and P. Robertson, submitted that another issue that the Commission
should consider in this proceeding is whether the SATR need approval should be reviewed in its
entirety. He argued that the SATR need approval was based on earlier forecasts of wind power
generation submitted by the AESO, which may no longer be accurate due to recently approved
4 Decision 2009-126: Alberta Electric System Operator – Needs Identification Document Application –
Southern Alberta Transmission System Reinforcement, Application No. 1600862, Proceeding ID No. 171,
September 8, 2009.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
8 • AUC Decision 2012-360 (December 24, 2012)
transmission development plans. Mr. Fitch proposed that this issue should be considered by the
Commission as a preliminary matter. Many interveners, including the Industrial Power
Consumers Association of Alberta (IPCAA), expressed support for a review of the SATR need
approval as a preliminary matter.
33. A number of interveners also expressed concern regarding the increased cost of SATR.
For these reasons, some interveners recommended that a preliminary hearing is required to assess
the SATR need approval prior to the commencement of the hearing to consider the facility
applications for the Foothills Area Transmission Development project.
34. AltaLink and the AESO both objected to a complete review of the SATR need approval
within the FATD proceeding. AltaLink noted that none of the interveners has brought forward an
application to review the SATR need approval. AltaLink questioned the foundation for such an
application and noted that the SATR need approval was issued following a public hearing with a
substantial record.
35. AltaLink stated that the AESO’s application to amend the SATR need approval to take
into account the new Windy Flats substation does not result in a complete re-opening of the
SATR need approval and emphasized that the amendment proposed by the AESO relates to a
specific technical solution to meet the need for area upgrades approved in the SATR need
approval, not to the need itself.
36. As stated above, the AESO’s application to amend the SATR need approval does not, in
itself, give rise to a complete review of that need approval. Rather, it requires the Commission to
consider only one aspect of that approval, i.e. whether the Windy Flats substation option is the
best option to address the identified need. Further, and as AltaLink and the AESO have pointed
out, the Commission has not received an application to review and vary the SATR need
approval. Accordingly, the Commission finds that continued viability of the SATR need
approval is not an issue that it can or should address in this proceeding at this time.
3.2 Issues for the facility applications
37. Interveners at the process meeting stated that they intend to raise the following issues
with respect to the FATD project:
route selection
human and animal health and safety
property value
impacts on the environment
social and economic impacts of the proposed line
land use and visual impacts
public consultation
impacts on agricultural operations
impacts on existing business operations
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 9
38. The Commission finds the issues above to be relevant for consideration at the public
hearing in accordance with the public interest consideration identified under Section 17 of the
Alberta Utilities Commission Act. The Commission does not consider this list to be exhaustive
and does not preclude the consideration of other relevant issues at the hearing.
4 Standing
39. Persons, including individuals and corporations, who may be directly and adversely
affected by the Commission’s decision on the applications are entitled to participate in a public
hearing. These persons are said to have standing to participate in the process.
40. Participants with standing are eligible to apply for cost recovery and will be able to fully
participate in the public hearing, which includes submitting evidence, cross-examining
witnesses, including those of the applicant, and submitting final argument.
41. Standing before the Commission is determined by subsection 9(2) of the Alberta Utilities
Commission Act which states:
(2) If it appears to the Commission that its decision or order on an application may
directly and adversely affect the rights of a person, the Commission shall
(a) give notice of the application in accordance with the Commission rules,
(b) give the person a reasonable opportunity of learning the facts bearing on the
application as presented to the Commission by the applicant and other parties to
the application, and
(c) hold a hearing.
42. In Cheyne v. Alberta (Utilities Commission), the Alberta Court of Appeal characterized
subsection 9(2) as the equivalent of subsection 26(2) of the Energy Resources Conservation
Act and confirmed that the two-part test for standing under subsection 26(2) applies to
subsection 9(2). The Alberta Court of Appeal described that test as follows:5
…s. 26(2) has two branches. First is a legal test, and second is a factual one. The legal
test asks whether the claim right or interest being asserted by the person is one known to
the law. The second branch asks whether the Board has information which shows that the
application before the Board may directly and adversely affect those interest or rights.
The second test is factual.
4.1 Standing for the AESO applications
43. The AESO filed two applications in this proceeding: Application No. 1608620, the
FATD need application and Application No. 1608846, the application to amend the SATR need
approval.
44. It is the Commission’s view that the approval of a need application has the potential to
effect all Alberta electricity ratepayers as they bear the costs of new transmission facilities
approved in conjunction with a NID approval. Need applications also have the potential to affect
those persons that own or occupy lands within those areas (sometimes referred to as swathes) of
land identified by the AESO for the transmission options described in the need application.
5 Cheyne v. Alberta (Utilities Commission), 2009 ABCA 94 (CanLII), at paragraph 13.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
10 • AUC Decision 2012-360 (December 24, 2012)
When, as in this case, a need application is being considered concurrently with an associated
facility application, it is clear that those that may be potentially affected by the Commission’s
decision on a facility application may also be potentially affected by the associated need
decision.
45. Several interested persons expressed concern with respect to the FATD need application.
Most of the concerns expressed were general in nature and provided little information regarding
the technical sufficiency of the application or whether its approval is in the public interest.
However, given the fact that this need application is so closely related to its companion facility
applications, the Commission finds that those persons who have standing in relation to the
companion facility applications, as outlined below in Section 4.2.1, should also be granted
standing for this need application. Accordingly, persons granted standing with respect to facility
Application No. 1608642: Langdon to Janet project, Application No. 1608637: North Foothills
Transmission project and Application No. 1608643: Foothills138-kV Transmission project, will
be granted standing for the FATD need application.
46. A number of interested parties also expressed concern with the application to amend the
SATR need approval. The Commission is prepared to grant standing with respect to this
application to those parties that have standing in the companion facility applications. Therefore,
persons granted standing, as outlined below in Section 4.2.1, with respect to facility
Application No. 1608861: South Foothill Transmission project and Application No. 1608862:
Windy Flats 138 kV project, will be granted standing for the application to amend the SATR
need approval. However, the Commission considers it important to emphasize that intervener
submissions on this application should address the proposed amendment to the SATR need
approval, i.e. the substitution of the Windy Flats solution for the previously approved Peigan
solution, and should not address the underlying need that the solution is designed to address.
47. The Diagonal group, Louson Investment Ltd., Glen Eagles Investment Ltd.,
Phyllis Robertson, the Mattson group, the Randle group and Reece and Richard Pearson
expressed general concerns about the FATD need application and the application to amend the
SATR need approval. The Commission is prepared to grant these groups standing with respect to
both AESO applications.
48. Benign Energy II Inc., Powerex Corp. and TransCanada Energy Ltd. expressed concerns
that their interests may be potentially impacted by the AESO applications to the extent that the
assessment of the proposed transmission system expansion may affect their generation
opportunities in the region. The Commission is of the view that its decision with respect to either
of the AESO applications has the potential to impact the interests of these parties. Accordingly,
the Commission grants standing to Benign Energy II Inc., Powerex Corp. and TransCanada
Energy Ltd., with respect to both applications filed by the AESO.
49. In its statement of intention to participate, IPCAA did not specify which of the AESO’s
applications it was objecting to. Further, IPCAA’s objection appears to be predicated upon its
concerns about the continued viability of the existing SATR need approval. As stated earlier, the
Commission is of the view that the viability of the SATR need approval is not an issue raised in
this proceeding at this time. Accordingly, the Commission cannot grant standing to IPCAA
based on the information it has filed to date. Should IPCAA wish to further pursue standing with
respect to some or all of the applications being considered in this proceeding, it must file
additional information with the Commission specifying which applications it is objecting to and
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 11
describing the grounds for those objections. Such information must be filed by no later than
January 21, 2013.
50. A number of persons without standing in any of the five facility applications, as outlined
below in Section 4.2.2, also expressed concerns or objected to one or both of the AESO’s
applications. These persons did not indicate what aspect of the AESO’s applications it was
objecting to. Therefore, the Commission cannot grant standing to persons for either of these two
applications where these persons were not given standing with respect to any of the five facility
applications. However, as stated above in paragraph 44, the Commission notes that the approval
of the FATD need application as well as the application to amend the SATR need approval may
affect all Alberta electricity rate-payers because they bear the costs of new transmission
facilities. Therefore, should these persons wish to pursue standing with respect to the FATD need
application or the application to amend the SATR need approval, they must file additional
information with the Commission specifying which application they are objecting to and
describing the grounds for those objections. This information must be filed by no later than
January 21, 2013.
4.2 Standing for the AltaLink and ENMAX facility applications
51. In this proceeding the Commission has decided to grant standing to persons that own or
reside on property that is within 800 metres of a transmission facility (transmission line or
substation)6 proposed in the facility applications filed by AltaLink and ENMAX, subject to there
not being any objections to that standing from another party. The Commission also finds that
persons that own or reside on property located within 800 metres of the transmission facility are
local interveners, who qualify for intervener funding under the Alberta Utilities Commission Act,
subject to any objections from another party.
52. If there is an objection to a person’s standing to participate or status as a local intervener,
the Commission will make a decision on whether the person has standing or qualifies for local
intervener costs based on the facts and evidence presented by both parties. Any persons that own
property or reside on property located outside the 800-metre zone may apply to the Commission
for standing or for local intervener status. The Commission will make a determination on
standing or local intervener status on a case-by-case basis by determining whether that person
may be directly and adversely affected by any one of the applications.
4.2.1 Landowners or residents within 800 metres of a proposed right-of-way
53. As stated above, the Commission finds that persons that own or reside on property
within 800 metres of the transmission facilities proposed in the AltaLink and ENMAX
applications have standing to participate in this proceeding pursuant to Section 9 of the
Alberta Utilities Commission Act. Persons falling into this category are set out in Schedule B to
this decision.
4.2.2 Landowners or residents outside of 800 metres
54. At this time, persons do not have standing if they own or reside on property that is more
than 800 metres from either the preferred or alternate right-of-way edge. Based on the record, it
is not clear to the Commission how these individuals may be directly and adversely affected by
6 For transmission lines the 800 metres has been measured from the edge of the right-of-way. For substations the
800 metres is measured from the substation boundary.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
12 • AUC Decision 2012-360 (December 24, 2012)
the Commission’s decision on the applications. Accordingly, the Commission cannot grant
standing to these participants at this time, however, participants can apply to the Commission for
standing by demonstrating how they may be directly and adversely affected as outlined in
Section 4.2.6 below. Persons that fall into this category are set out in Schedule C to this decision.
55. These persons may also participate in this proceeding without a further ruling on
standing, by joining one of the groups identified in Section 4.2.4, subject to the limitations
described in paragraph 62 of that section.
4.2.3 Landowners with insufficient information
56. Some persons who filed statements of intent to participate in the proceeding did not
indicate whether they own or reside on land that is within 800 metres of the right-of-way edge.
The Commission has insufficient information to determine whether these parties may be directly
or adversely affected by the Commission’s decision on the FATD applications. Accordingly, the
Commission cannot grant standing to these participants at this time. These persons are set out in
Schedule D to this decision.
57. Any person whose name appears in Schedule D who wishes to assert standing should
provide their legal land description and state whether they reside upon or own land within
800 metres of the edge of a preferred or alternate right-of-way when they file supplemental
information with the Commission even though they may have indicated, in their statement of
intent to participate, where their land is located (i.e. legal land location).
58. These persons may also participate in this proceeding without a further ruling on
standing, by joining one of the groups identified in Section 4.2.4, subject to the limitations
described in paragraph 62 of that section.
59. With respect to Benign Energy II Inc., Powerex Corp. and TransCanada Energy Ltd., the
Commission has insufficient information to determine whether these parties may be directly or
adversely affected by the Commission’s decision on any of the facility applications in this
proceeding. Accordingly, the Commission cannot grant standing to these participants at this
time. Should these parties wish to pursue standing with respect to any of the facility applications,
they must file additional information with the Commission describing how their rights may be
directly and adversely affected by the Commission’s decision on any of the facility applications.
4.2.4 Landowner groups
60. Groups of individuals that are comprised of one or more persons with standing and
persons who do not have standing may, at the discretion of the Commission, participate in this
proceeding. The basis for these groups’ participation is that one or more of its members have
standing. Groups that fall into this category are set out in Schedule E to this decision.
61. It is the practice of the Commission to allow such groups to participate in Commission
proceedings. However, please note that individuals who do not have standing on an individual
basis, but belong to a group that does have standing, are not eligible to apply for the recovery of
costs of their individual participation. For example, group members without standing (i.e. who
reside more than 800 metres from the edge of a proposed right-of-way) will not be eligible to
receive honoraria and reimbursement for out-of-pocket expenses incurred, nor will they be able
to appear before the Commission to put their individual interests forward to any extent greater
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 13
than that of an individual without standing who may participate by filing a written submission or
making a brief oral statement.
62. The Commission requests that individuals wishing to participate in this proceeding, over
and above their participation as members of a group, identify the scope of their individual
participation.
4.2.5 Other parties
63. The Commission continues to receive statements of intention to participate from
interested parties. The Commission will continue to process these statements as they are
received.
4.2.6 Further written process for standing
64. Persons listed on schedules C and D must provide further information to the Commission
if they wish to request standing in this proceeding. Parties must explain to the Commission what
rights they are claiming and how those rights may be directly and adversely affected by the
Commission’s decision on the application and, for those persons shown in Schedule D,
information regarding their land location. Until the Commission receives this further
information, parties listed in schedules C and D do not have standing in this proceeding but will
still be eligible to submit a written statement or make a brief oral statement at the formal hearing.
65. The Commission has established the following process schedule to receive requests for
standing that contain the information mentioned above:
1) Written submissions requesting standing must be submitted to the Commission on or
before January 21, 2013, to obtain standing in this proceeding.
2) The applicants may respond in writing to the submissions received on or before
January 28, 2013.
5 Hearing process, schedule and location
66. The Commission included a draft process schedule in its revised notice and asked
interested parties to comment on that schedule at the process meeting.
67. The majority of interveners stated that May 13, 2012, was a reasonable start date for the
formal hearing. No particular concerns were raised on the tentative process steps.
68. Many interveners were in favor of the phased hearing process and hearing locations close
to the project area. Several locations were proposed by interveners for the phased hearing,
including High River, Calgary, Okotoks, Claresholm, Fort MacLeod and Pincher Creek.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
14 • AUC Decision 2012-360 (December 24, 2012)
5.1 Hearing process and schedule
69. In setting the schedule for the hearing, the Commission is mindful that the process and
schedule must allow all participants sufficient time to prepare and review evidence or reply
evidence, draft and respond to information requests, and prepare witnesses for the formal
hearing. The Commission is of the view that the following schedule establishes a process that is
fair to all participants and includes all of the contemplated process steps
Date Process step
February 8, 2013 Deadline for intervener information requests to applicants
March 1, 2013 Information responses due from the applicants
March 22, 2013 Intervener evidence due
April 5, 2013 Deadline for information requests to interveners
April 19 , 2013 Information responses due from interveners
May 3, 2013 Reply evidence due from the applicants
May 14, 2013 Public hearing to commence
5.2 Written submissions
70. Parties who want to have an opportunity to express their views on the FATD project but
who do not wish to participate in the formal hearing may file a written submission with the
Commission or give a brief oral submission to the Commission at the public hearing. Written
submissions may be filed at any time up until the close of the evidentiary portion of the hearing.
As the Commission cannot predict when that might occur, it encourages parties to file their
written submissions prior to March 22, 2013.
5.3 Hearing location
71. In selecting the locations for the hearing, the Commission concurs with the interveners
that a phased hearing process is appropriate and convenient to consider the projects which
involve a large geographic area and diverse groups of interveners. It is the intention of the
Commission to first consider the applicants’ evidence in a location that is central to all the
participants and then consider interveners’ evidence at locations close to the interveners’
properties or residences.
72. The Commission has reviewed the venues in all the locations suggested by the
interveners and noticed that there is no suitable venue available in either Claresholm,
Fort McLeod, or in the south Calgary/Okotoks area between May and June 2013. At this time,
the Commission has determined that the hearing will commence on May 14, 2013, at the High
River Heritage Inn & Convention Centre, located at 1104 11 Street S.E., High River, Alberta.
The dates and venues for the remainder of the hearing will be determined at a later date. Further
details of the hearing dates and locations will be advised in the notice of hearing.
5.4 Staged proceeding
73. Given the scope of this proceeding, some interveners expressed concern that this
proceeding may be complicated in nature and thought that it would not be easy for them to fully
participate.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 15
74. The Commission is of the view that because the Foothills 237S substation is under
consideration in both the North Foothills Transmission Project and the South Foothills
Transmission Project, it would not be plausible to consider the additional facility applications in
a separate proceeding without causing prejudice to potentially affected stakeholders related to
applications in the other proceeding. The Commission observed that the proposed phased hearing
process was supported by interveners.
Dated on December 24, 2012.
The Alberta Utilities Commission
(original signed by)
Anne Michaud
Commission Member
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 17
Schedule A – Process meeting participants
Name of Organization (Abbreviation) Counsel or Representative
Alberta Electric System Operator J. Cusano
AltaLink Management Ltd. P. Feldberg
ENMAX Power Corporation
D. Wood
Diagonal Group
G. Fitch
Louson Investment Ltd. and Glen Eagles Investments Ltd.
G. Fitch
P. Robertson
G. Fitch
Bow Vista Farms Ltd.
S. Stenbeck
Mudry family and McHugh family
S. Stenbeck
T. and F. Thomson and Western Sky Land Trust
S. Stenbeck
Mattson Group
N. Ramessar on behalf of M. Niven
Randle Group J. Laycraft
R. and R. Pearson J. Laycraft
Committee for East Route Conservation (CERC)
R. Secord
D. and L. Conner D. Van Moorsel
C. Hansen
The McLaren and Carlson group
J. Price and J. Walton
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
18 • AUC Decision 2012-360 (December 24, 2012)
Name of Organization (Abbreviation) Counsel or Representative
Town of High River
K. Mohammed
ENMAX Green Power
R. McKee
TransCanada Energy Limited
R. Stevens
Benign Energy Canada II Inc.
A. Kettleson
Astral Media Radio
B. Stovold
R. and G. Nauta
H. Jackson
M. Chehabeddine
R. Miller
V. and P. Bretin
TD&T Properties
D. Leeds
Alberta Utilities Commission Commission Panel A. Michaud, Commissioner Commission Staff
JP Mousseau (Commission Counsel) M. Ali (Commission Counsel) T. Chan S. Jiang K. Taylor L. Charest
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 19
Schedule B – Persons with standing
Application No. 1608642: Langdon to Janet Transmission Project
197833 Alberta Ltd. Glen Eagles Investments Limited
590140 Alberta Limited / Simonelli, Carlo Joneja, Baldev
Beck, John Kyle, Janet
Bretin, Patricia Louson Investments Inc.
Bretin, Vern Mattson Group
Buckley, Sheila McLaren and Carlson Group
Camrock Capital Partners GP (40) Ltd. Steele, Vanessa
Application No. 1608637: North Foothills Transmission Project
Astral Media Radio MacLellan, Debra
Bow Vista Farms Ltd. Maldeghem, Charles
Chehabeddine, Afif Miller, Richard
Chehabeddine, Mustapha Moore, Wayne
Coonfer, Douglas Pearson, Reece
Diagonal Group Pearson, Richard
Hage, Abdul Randle Group
Hage, Mohamed Taplin, James L.
Jackson, Harvey E. Thomson, Frederick
Kaaki, Faten Thomson, Terry
Klatzel-Mudry, Louise / McHugh Family Western Sky Land Trust
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
20 • AUC Decision 2012-360 (December 24, 2012)
Application No. 1608643: Foothills 138-kV Transmission Project
B.F.W. Holdings (2006) Ltd. Nauta, Gerry
Chehabeddine, Afif Nuata, Randy
Chehabeddine, Mustapha Pope, David
ENMAX Green Power Inc. Randle Group
ENMAX Shepard Inc. Robertson, Phyllis
Kaaki, Faten Town of High River
Nauta, Dan
Application No. 1608861: South Foothills Transmission Project
Committee for East Route Conservation Paradis, Jason
Conner, Laurie Paradis, Sabrina
Conner, Ron Randle Group
Markle, Collin R. Volker Stevin / McNally Contractors (2011) Ltd.
Application No. 1608862: Windy Flats 138-kV Transmission Project
Conner, Laurie Conner, Ron
Application No. 1608649: ENMAX application for modifications to substations
ENMAX Green Power Inc. ENMAX Shepard Inc.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 21
Schedule C – Persons outside of 800 metres
Arca, Mavito
Fowler, F.L. & E.
Shutiak, James
TDT Properties Ltd.7
7 TDT Properties Ltd. is within 800 metres of another existing line. It does not appear to the Commission that it is
within 800 metres of any of the proposed FATD transmission line projects.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
22 • AUC Decision 2012-360 (December 24, 2012)
Schedule D – Persons with insufficient information
Benign Energy II Inc.
Brunner, Linda
Dawson, Tom
Jackson, Harvey E.8
Jeske, Jan
Lozeman, Fred
Powerex Corp.
Scandinadian Developments Consultants (Charles Hansen)9
Schnarr, Bill
TransCanada Energy Ltd.
Vandervalk, Marvin
Wallace, Todd
8 Mr. Havey E. Jackson referred to Application No.1608861 in the process meeting. However, based on the LSD
provided, it appears that his interests may be affected by Application No.1608637. 9 Mr. Hansen appeared at the process meeting and stated that he had discussed the matter with persons within
800 metres. However, it is not clear to the Commission that he owns or resides upon lands within 800 metres or
if he is representing persons who meet that criteria.
Alberta Electric System Operator, AltaLink Management Ltd. Foothills Area Transmission Development and ENMAX Power Corporation
AUC Decision 2012-360 (December 24, 2012) • 23
Schedule E – Groups with members that have standing
GROUP
Diagonal Group
Committee for East Route Conservation
Mattson Group
McLaren and Carlson Group
Randle Group