REMINDER Check in on the COLLABORATE mobile app An Introduction to Oracle’s Primavera Risk Analysis Prepared by: Paul Monaghan 1st Milestone Ltd Overview via Slideshow Product Demonstration Session ID#: 15487
Transcript

REMINDER

Check in on the

COLLABORATE mobile app

An Introduction to Oracle’s Primavera Risk Analysis

Prepared by:

Paul Monaghan

1st Milestone Ltd

Overview via Slideshow

Product Demonstration

Session ID#: 15487

Agenda for the Session

■ Primavera Risk Analysis and Management Overview via Slideshow

■ Primavera Risk Analysis – Product Demonstration

▪ Schedule checks and schedule improvement

▪ Using basic schedule uncertainty

▪ Running a Monte Carlo risk analysis

▪ Understanding the results

▪ What-if scenarios

▪ Impact of risks from a risk register

▪ Comparing pre and post mitigation scenarios

▪ Combined schedule and cost modelling

1st Milestone Ltd Oracle Platinum Partner Specializing in Oracle’s Primavera Applications

■ Representing Primavera for 20 years

■ Our Focus:

▪ Application / Business Consulting

▪ Oracle University Primavera Training

▪ Integration Consulting

▪ IT Support and Hosting

■ Our credentials are proof of our commitment to quality, and they help demonstrate

our deep understanding and proactive assessment of Resource, Project, Programme

and Portfolio Management solutions.

▪ Oracle University – Education Partner

▪ PRINCE2 Practitioners

■ Milestone announced the winners of the UKOUG Primavera and Oracle Projects

Partners of the Year:

▪ Gold Award 2011 & 2012!

▪ Silver Award 2010

Primavera Risk Analysis

■ Focus

▪ Specialist product for project risk analysis and management

▪ An ‘add-on’ package for Primavera P6PPM and EPPM

■ Pinpoint key facts

▪ Likelihood of delivering the project on time and budget

▪ Most important tasks and risks in the schedule

■ Understand overall cost/schedule risk exposure

▪ The impact of delay

▪ Determine contingency and mitigation

■ Better decision making

▪ Increased accuracy of project schedules

▪ Reduce exposure to risk for more successful project execution

Risk Analysis Output

■ Risk Histogram

▪ Displays likelihood of

project delivery

■ Risk Tornado chart

▪ Displays task and risk

drivers

Risk Analysis Process

■ Risk ready schedule

▪ Check the schedule for

sound logic and errors

■ Risk inputs

▪ Estimate uncertainty

▪ Risk events/Risk register

■ Risk impact

▪ Map risks to tasks

■ Risk analysis

▪ Monte Carlo simulation

■ Risk response

▪ Determine contingency

▪ Mitigation scenarios

Risk Management

Process

Checking a Schedule

Three Point Estimates

Duration/Cost

■ Estimate Uncertainty

Three Point Estimates: Input

■ Quickly input 3 point estimates using “Quick Risk” templates

Task Existence and Branching

■ Task Existence

■ Branching: Probabilistic

Outcome C

Outcome A

? Outcome B

?

Project Risk Events – Risk Register

■ Estimate Uncertainty + Risk Events = Total Risk Exposure

▪ Uncertainty (3 point estimates)

▪ Risks from a risk register

▪ Monte Carlo simulation

Primavera Risk Analysis Product Demonstration