+ All Categories
Home > Documents > Analysis to Inform CA Grid Integration Rules for PV© 2014 Electric Power Research Institute, Inc....

Analysis to Inform CA Grid Integration Rules for PV© 2014 Electric Power Research Institute, Inc....

Date post: 14-May-2018
Category:
Upload: doantu
View: 214 times
Download: 1 times
Share this document with a friend
21
CSI4 Kick Off Meeting June 26, 2014 Analysis to Inform CA Grid Integration Rules for PV CSI4 RD&D Project Jeff Smith, EPRI Program Manager Lindsey Rogers, EPRI Senior Engineer
Transcript

CSI4 Kick Off MeetingJune 26, 2014

Analysis to Inform CA Grid Integration Rules for PV

CSI4 RD&D Project

Jeff Smith, EPRIProgram Manager

Lindsey Rogers, EPRISenior Engineer

2© 2014 Electric Power Research Institute, Inc. All rights reserved.

Which Smart Inverter Setting is Most Appropriate for My Situation?

0 5 10 15 20 25

1.024

1.026

1.028

1.03

1.032

1.034

1.036

1.038

1.04

1.042

1.044

Hour

Vol

tage

(pu)

Voltages with different voltvar settings

---- Voltvar

---- No PV---- PV base

115 unique volt/var control settings

3© 2014 Electric Power Research Institute, Inc. All rights reserved.

Overview• Background: CA utilities are participating in an EPRI/CPUC

study to determine the distribution “hosting capacity” of PV and streamline analysis of interconnection requests with high pen. This effort will build on prior work to recommend settings for smart inverter functions considered in Rule 21.

• Objective: Use power system analysis tools, measurement data, and distribution engineering experience to develop practical operational parameters for smart inverters to effectively provide grid-support.

• Team:with support from SCE, SDG&E, PG&E, CAISO, PJM

4© 2014 Electric Power Research Institute, Inc. All rights reserved.

Leveraging Work Throughout Industry

From Research to Application

Develop “Hosting Capacity” Method for Hi-Pen PV Analysis

EPRI Project

Hi-res PV Monitoring and Hosting Capacity Analysis

(2 feeders)DOE/VT/EPRI Hi-Pen Phase

II Project

Hosting Capacity Analysis>20 feeders throughout US

EPRI Project

Develop Alternate Screening Methods using Hosting

Capacity Analysis15 feeders

CPUC/EPRI/DOE Project

Hosting Capacity with Smart Inverters

(1 feeder)DOE/VT/EPRI Hi-Pen Phase III

Project

2010 2011 2012 2013

Smart inverter settings for demo sites

(4 PV sites/feeders)DOE/EPRI SEGIS AC

Project

Smart inverter settings for to inform CA integration

CPUC/EPRI/DOE Project

2014

Develop open-source models of smart

inverters in OpenDSSEPRI Project

5© 2014 Electric Power Research Institute, Inc. All rights reserved.

Task

•Task 1: Project Management •Task 2: Feeder Selection •Task 3: Distribution Requirements for Smart Inverters

•Task 4: Bulk System Requirements for Smart Inverters

•Task 5: Outreach & Engagement

6© 2014 Electric Power Research Institute, Inc. All rights reserved.

Task 2: Feeder Selection

• Task Purpose– Select representative feeders from CA feeder types to

simulate wide range of smart inverter functional need. • Approach

– Select 7-10 feeders to capture a wide range of hosting capacities

• Leveraging: CSI3 feeder clustering, selection, modeling, and hosting capacity evaluations

• Deliverable: report summarizing feeders & generic feeder models made public

7© 2014 Electric Power Research Institute, Inc. All rights reserved.

Circuit Performance Characterization22 Feeders Selected within CSI3 award

020406080

100120

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

miles

Feeder

Total 3‐ph ckt miles

0

2

4

6

8

10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

#

Feeder

Number of Regulators

 ‐

 5,000

 10,000

 15,000

 20,000

 25,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

#

Feeder

Connected kVA

020406080100120

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

miles

Feeder

Total 2‐ph and 1‐ph ckt miles

Voltage Class

4

12

16

21

33

8© 2014 Electric Power Research Institute, Inc. All rights reserved.

Feeder Modeling• Feeder models developed under

CSI3 award• Detailed distribution models

– Full three-phase– includes regulation equipment,

individual customer loads, existing PV, etc

• Worked with participating utility to obtain base feeder data– Add secondary transformers and

service drops– Incorporate time-series load data

• Converted model to OpenDSS (open source)

• Validated/verified model with measurement data

Feeder Voltage Heat

Map

9© 2014 Electric Power Research Institute, Inc. All rights reserved.

Detailed Hosting Capacity*Sample results from Subset of 22 Feeders

0 2 4 6 8 10

P1

P2

P3

P4

P5

Small Consumer PV (MW)

Feed

er

A – All penetrations in this region are acceptable, regardless of

location

B – Some penetrations in this region are acceptable, site specific

C – No penetrations in this region are acceptable, regardless of

location

*Feeders shown are not those chosen for CSI4

10© 2014 Electric Power Research Institute, Inc. All rights reserved.

Task 3: Distribution Requirements for Smart Inverters• Purpose of task

– Develop recommended configuration/implementation options for smart inverters to better integrate solar PV into distribution• Determine Recommended Smart Inverter Configuration Settings• Hosting Capacity Determinations with Smart Inverter Settings

• Approach– Evaluate a range of feeder configurations, penetration levels, and

potential inverters with existing feeder controls to develop default settings/parameters

– Includes curves (set points), inverter ratings, response times for:• Fixed power factor• Volt-watt• Volt-var• Ramp rate control• Soft start methods• Maximum generation limit

• Deliverable: report summarizing recommended settings & hosting capacity

11© 2014 Electric Power Research Institute, Inc. All rights reserved.

Method for Analysis

Step 1: Determine recommended settings– Combination of steady-state and time-series analysis– Consider range of load/PV scenarios

Step 2: Evaluate hosting capacity with new settings– Perform stochastic analysis of 1000’s of deployment

scenarios, observing feeder-wide impact• Voltage impacts• Regulation• Thermal• losses

– Repeat for different load conditions Step 3: Repeat step 2 with advanced inverter functions

12© 2014 Electric Power Research Institute, Inc. All rights reserved.

Inverter Settings are Critical

% Available Vars

% voltage

100%

0.95

1.05

‐100%

1.0V

% Available Vars

% voltage

100%

0.99

1.01

‐100%

1.0

Volt-var A

1

1.01

1.02

1.03

1.04

1.05

0 60 120 180 240 300 360 420 480 540

PV Te

rminal Voltage

 (pu)

Time (seconds)

1

1.01

1.02

1.03

1.04

1.05

0 60 120 180 240 300 360 420 480 540

PV Te

rminal Voltage

 (pu)

Time (seconds)

Unity Power Factor

Volt-var A

Volt-var B

1

1.01

1.02

1.03

1.04

1.05

0 60 120 180 240 300 360 420 480 540

PV Te

rminal Voltage

 (pu)

Time (seconds)

If wrong setpoints are used, adverse impacts can occur

0

0.5

1

PV Active 

Power 

Volt-var B

13© 2014 Electric Power Research Institute, Inc. All rights reserved.

Step 1 – Evaluation of Settings

*Sample Results from EPRI/DOE project

14© 2014 Electric Power Research Institute, Inc. All rights reserved.

Method for Analysis – Step 2

Step 1: Determine recommended settings– Combination of steady-state and time-series analysis– Consider range of load/PV scenarios

Step 2: Evaluate hosting capacity with new settings– Perform stochastic analysis of 1000’s of deployment

scenarios, observing feeder-wide impact• Voltage impacts• Regulation• Thermal• losses

– Repeat for different load conditions Step 3: Repeat step 2 with advanced inverter functions

15© 2014 Electric Power Research Institute, Inc. All rights reserved.

Increased Hosting Capacity using Smart InvertersPV at Unity Power Factor PV with Volt/var Control

2500 cases shownEach point = highest primary voltage

ANSI voltage limit

ANSI voltage limit

Increasing penetration (kW)

Max

imum

Fee

der V

olta

ge (p

u)

Max

imum

Fee

der V

olta

ges

(pu)

Increasing penetration (kW)

No observable violations regardless of PV size/location

Possible violations based upon PV size/location

Observable violations occur regardless of size/location

For voltage-constrained feeders, results indicate use of smart inverters can increase feeder hosting capacity for PV

Minimum Hosting CapacityMaximum Hosting Capacity

Minimum Hosting CapacityMax Hosting Capacity

16© 2014 Electric Power Research Institute, Inc. All rights reserved.

0 1000 2000 3000 4000 5000

Control Off

Volt‐Var 1

Volt‐Var 2

98% pf

95% pf

Volt‐Watt 1

Volt‐Watt 2

Dyn‐Var

Feeder Hosting Capacity (kW)

Control

Customer-Owned PV Advanced Inverter Summary

No observable violations regardless of PV size/location

Possible violations based upon PV size/location

Observable violations occur regardless of size/location

*Sample Results from EPRI/DOE project

17© 2014 Electric Power Research Institute, Inc. All rights reserved.

Task 4: Bulk System Requirements for Smart Inverters• Purpose of Task

– Select default voltage and frequency tolerance settings for distributed PV systems• Model Development and Transmission System Analysis• Impact of Bulk System Performance on Distribution Feeders

• Approach– Quantify the settings needed to reduce unacceptable voltage

recovery or frequency response• Voltage ride-through• Frequency ride-through• Frequency watt control

• Deliverable: report summarizing settings needed to bulk system

18© 2014 Electric Power Research Institute, Inc. All rights reserved.

Task 5: Outreach & Engagement

•Purpose of Task–ongoing coordination and information sharing

with the CEC/CPUC efforts regarding candidate DER capabilities for Rule 21

•Approach–Project outreach workshops–Involvement in smart inverter working group

meetings–Webcasts following analysis of each function

for feedback

19© 2014 Electric Power Research Institute, Inc. All rights reserved.

Schedule

1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12

Task 1 Project management, reporting, and technology transfer

Task 2 Feeder Selection

Task 3 Analys is  of Distribution Requirements  for Smart Inverters

Task 4 Analys is  of Bulk System Requirements  for Smart Inverters

Task 5 Outreach and Engagement

‐ internal  milestone/del iverable

‐ external  stakeholder del iverable

Participate  and Present in Meetings  (as  requested)

Quarterly status  report and invoice

Task 4 Report: Bulk System Requirements

Project Outreach webinars

Fina l  Report Informing Grid Codes

Task 5: Project Workshop: CA uti l i ties  and CPUC

One‐page  publ ic summary upon completion of project

Year 2

One‐page  publ ic summary at the  start of project

Task 3 Report: Distribution Requirements

Task Schedule

Key Project Milestones and Deliverables

Year 1

Dates set by Project Advisory Committtee or Stakeholders

20© 2014 Electric Power Research Institute, Inc. All rights reserved.

Project Team

Project ManagerJeff Smith, EPRI

Contract ManagerDavid Morrison, EPRI

Bulk System Requirements for Smart Inverters Daniel Brooks, EPRI

OutreachAbraham Ellis,

SandiaMichael

Coddington, NRELThomas Key,

EPRI Abraham Ellis, Sandia Michael Coddington, NREL Vikas Singvhi, EPRI Roger Dugan, EPRI

Distribution Requirements for Smart InvertersJeff Smith, EPRI

Barry Mather, NREL Robert Broderick, Sandia Matt Rylander, EPRI Wes Sunderman, EPRI Robert Arritt, EPRI Huijuan Li, EPRI Aminul Huque, EPRI

Utility Partners: PGE, SCE, SDGE, SMUD

Project CoordinationLindsey Rogers, EPRI

21© 2014 Electric Power Research Institute, Inc. All rights reserved.

Q &A and discussion

Jeff Smith (PI): [email protected] 865.218.8069Lindsey Rogers : [email protected] 865.218.8092


Recommended