22
André van Es 2 nd SKADS Workshop 10-11 October 2007 Review on Deliverables Review on Deliverables and forward look and forward look André van Es
Transcript

André van Es2nd SKADS Workshop 10-11 October 2007

Review on DeliverablesReview on Deliverables

and forward lookand forward look

André van Es

André van Es2nd SKADS Workshop 10-11 October 2007

Review of deliverablesReview of deliverables

Three levels of deliverables:

Level 3: Deliverable at Tasks

Level 2: Deliverable at Design Study

Level 1: Deliverable at Project

Level 0: Deliverable at Board Level

We present progress in terms of the Level 0 deliverables

André van Es2nd SKADS Workshop 10-11 October 2007

DS-1DS-1ASTRONASTRON

University of University of ManchesterManchester

Observatoire Observatoire de Parisde Paris

DS-2DS-2Rijks Universiteit Rijks Universiteit

GroningenGroningen

ASTRONASTRON

INAF-IRAINAF-IRA

MPIfRMPIfR

Universidad de ValenciaUniversidad de Valencia

CSIROCSIRO

SwinburneSwinburne

Leiden ObservatoryLeiden Observatory

ChalmersChalmers

OxfordOxford

University of University of ManchesterManchester

Observatoire de ParisObservatoire de Paris

CambridgeCambridge

University of MelbourneUniversity of Melbourne

Natal UniversityNatal University

PRAO-LPIPRAO-LPI

University of LeedsUniversity of Leeds

University of GlasgowUniversity of Glasgow

University of AdelaideUniversity of Adelaide

DS-3DS-3University of University of CambridgeCambridge

ASTRONASTRON

University of University of ManchesterManchester

CSIROCSIRO

INAF-IRAINAF-IRA

University of University of OxfordOxford

Cambridge Cambridge UniversityUniversity

Observatoire Observatoire de Parisde Paris

National National Research Research

FoundationFoundation

DS-4DS-4University of University of ManchesterManchester

ASTRON ASTRON

Observatoire Observatoire de Parisde Paris

INAF-IRAINAF-IRA

FG-IGNFG-IGN

University of University of OxfordOxford

CSIROCSIRO

National National Research Research CouncilCouncil

University of University of CambridgeCambridge

University of University of OrléansOrléans

CNRSCNRS

OMMIROMMIR

DS-5DS-5ASTRONASTRON

University of University of ManchesterManchester

Observatoire Observatoire de Parisde Paris

JIVEJIVE

INAF-IRAINAF-IRA

MPIfRMPIfR

Oxford Oxford UniversityUniversity

CSIROCSIRO

National National Research Research

FoundationFoundation

UMKUMK

University of University of CambridgeCambridge

OMMICOMMIC

DS-6DS-6INAF-IRAINAF-IRA

ASTRONASTRON

JIVEJIVE

CSIROCSIRO

Univ. SydneyUniv. Sydney

DS-7: DS-7: University of Manchester, Observatoire de ParisUniversity of Manchester, Observatoire de Paris

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-1Review on deliverables: DS-1

Deliverable/ Milestone No

Planned (in months)

Achieved (in months)

Deliverable/Milestone Name

DS1 1. 1-oct-05 Nov-05 Organize kick-off DS1 2. 1-oct-05 1-jan-06 Implement adequate management tools DS1 - ongoing Continuous coordination and management DS1 - ongoing Continuous assessment and control DS1 3 1-Nov-05 30-June-

06 Document on outreach policy

DS1 4 1-Apr-05 1-Oct-05 Establish web-page DS1 5 1-Nov-05 1-Feb-06 Document on IPR Policy DS1 6 1-Apr-06 4-Sep-06 SKADS international workshop 2006 DS1 7 1-Apr-07 10-Oct-07 SKADS international workshop 2007 DS1 8 1-Apr-08 Sep 08 SKADS international workshop 2008 DS1 9 1-Apr-09 Sep 09 SKADS international workshop 2009

André van Es2nd SKADS Workshop 10-11 October 2007

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-2Review on deliverables: DS-2

Nominal

Completion Date

Actual/ Planned

completion Date

Milestone

DS2 1 1-jun-07 1-jun-07 Conclusion on Science Drivers

DS2 2 1-dec-08 1-dec-08 Conclusion on Year in the Life for different SKA realizations

DS2 3 1-jul-08 1-jul-08 Optimised Configuration for the SKA

DS2 4 1-mei-09 1-mei-09 Demonstration of new calibration and imaging Techniques

André van Es2nd SKADS Workshop 10-11 October 2007

A Report and Proceedings...A Report and Proceedings...

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-3Review on deliverables: DS-3

Nominal

Completion Date

Actual/ Planned

completion Date

Milestone

DS3 1 30-jun-08 31-dec-08 Delivery of prototype phase transfer link DS3 2 31-dec-08 31-dec-08 Development cost of model for the network DS3 3 30-mei-09 30-mei-09 Report on technology roadmapping and costing DS3 4 1-jul-07 1-jul-07 Delivery of framework for functional simulator DS3 5 30-mei-09 30-mei-09 Report on network achtitecture DS3 6 30-jun-08 30-jun-08 Overview reports on site selection DS3 7 31-dec-08 31-dec-08 Final reports on site selection DS3 8 30-jun-08 30-jun-08 Reports on SKA for the user

DS3 9 30-dec-05 30-dec-05 Model driven architecture specification of control and data processing

DS3 10 30-jun-08 30-jun-08 Report MDA constructs, interfaces and platforms DS3 11 30-dec-07 30-dec-07 report on scalable platform specific composition DS3 12 30-jun-08 30-jun-08 MDA assessment and scalability recommendations

André van Es2nd SKADS Workshop 10-11 October 2007

SKADS Design & Costing SKADS Design & Costing Paper (SKA Memo 93)Paper (SKA Memo 93)

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-4Review on deliverables: DS-4

Nominal

Completion Date

Planned Completion

Milestone

DS4 1 30-dec-06 done SiGe band pass filter using PIC technology prototype DS4 2 30-dec-07 31-dec-08 ADC performance evaluation

DS4 3 1-jul-07 1-jul-08 Hybrid LNA first devices

DS4 4 1-jul-06 1-jul-08 Inventory of RFI mitigation techniques and applicability to SKA

DS4 5 1-jul-07 1-jul-08 Evaluation of impact of moving interference sources on SKA DS4 6 31-okt-07 1-mrt-08 Characterised antenna element DS4 7 1-mrt-08 1-jul-08 antenna element with integrated MMIC prototype

DS4 8 1-jul-07 1-mrt-08 Simulated Digital beamformer for 2-PAD

DS4 9 30-dec-06 done Prototype low cost SiGe analogue beamformer DS4 10 29-dec-08 2-feb-09 Prototype complete 2-PAD digital tile

DS4 11 30-jun-09 30-jun-09

Final reports on semiconductor technologies, RFI mitigation strategies, antenna element design, digital beamformer design 2-PAD performance (T1-T6)

André van Es2nd SKADS Workshop 10-11 October 2007

Prototype of Low Cost SiGe Prototype of Low Cost SiGe BeamformerBeamformer

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-5Review on deliverables: DS-5

Nominal

Completion Date

Planned Completion

Milestone

DS5 1 30-dec-05 30-dec-05 Completion of System Requirements DS5 2 1-mrt-06 15 May-06 Design Review of First Tile

DS5 3 1-jul-06 1-jul-06 Delivery of first manufactured tile

DS5 4 1-mrt-07 1-okt-07 completion of 10 tile system DS5 5 31-mei-08 1-sept-2008 completion of first 100 tiles DS5 6 1-jan-09 1-jan-2009 completion of m anufacturing of all tiles

André van Es2nd SKADS Workshop 10-11 October 2007

EMBRACE 10 tile prototypeEMBRACE 10 tile prototype

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-5Review on deliverables: DS-5

Nominal

Completion Date

Planned Completion Milestone

DS5 1 30-dec-05 30-dec-05 Completion of System Requirements DS5 2 1-mrt-06 15 May-06 Design Review of First Tile

DS5 3 1-jul-06 1-jul-06 Delivery of first manufactured tile

DS5 4 1-mrt-07 1-okt-07 completion of 10 tile system DS5 5 31-mei-08 1-sept-2008 completion of first 100 tiles DS5 6 1-jan-09 1-jan-2009 completion of manufacturing of all tiles

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-6Review on deliverables: DS-6

Nominal

Completion Date

Planned Completion

Milestone

DS6 1 1-jul-06 done Design Report on Analog Optical link DS6 2 30-apr-07 done Design Report on Analog and digital optical link

DS6 3 31-aug-08 31-aug-08 Report on data handling for large telescopes

DS6 4 30-sep-08 30-sep-08 Wide band high dynamic range A/D FX correlator, small

prototype DS6 5 30-sep-08 30-sep-08 Software beamforming and multibeaming on BEST-x DS6 6 30-sep-08 30-sep-08 Algorithms for RFI mitigation DS6 7 1-jul-08 1-jul-08 Calibration methods for large array DS6 8 30-sep-08 30-sep-08 report on High sensitivity astronomical tests

André van Es2nd SKADS Workshop 10-11 October 2007

BEST Report on optical linksBEST Report on optical links

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS-7Review on deliverables: DS-7

Task number Deliverable No

Deliverable Name Planned (in months)

Achieved (in months)

DS7-T1 1 SKADS Quarterly Report Q4/2006

19 19

DS7-T1 2 SKADS Quarterly Report Q1/2007

22 22

DS7-T1 3 SKADS Quarterly Report Q3/2007

25 25

DS7-T1 4 SKADS Quarterly Report Q4/2007

19 19

DS7-T1 5 SKADS Quarterly Report Q1/2008

22 22

DS7-T1 6 SKADS Quarterly Report Q3/2008

25 25

DS7-T1 7 SKADS Quarterly Report Q4/2008

19 19

DS7-T1 8 SKADS Quarterly Report Q1/2009

22 22

DS7-T1 9 2007 Annual Report to International SKA Project Office

24 25

DS7-T1 10 2008 Annual Report to International SKA Project Office

24 25

DS7-T1 11 2009 Annual Report to International SKA Project Office

24 25

André van Es2nd SKADS Workshop 10-11 October 2007

A Quarterly Report...A Quarterly Report...

André van Es2nd SKADS Workshop 10-11 October 2007

Updated PlanUpdated Plan

Prior to 2nd Annual Report project planning was updated

All Design Studies submitted new milestone/deliverable table

New milestone dates were discussed and agreed with DS leaders

SKADS on track to finish on 30th June 2009

André van Es2nd SKADS Workshop 10-11 October 2007

Deliverables/Milestones planned Deliverables/Milestones planned (update 2(update 2ndnd annual report) annual report)

Level 0 Deliverables

0

10

20

30

40

50

60

0,5 1 1,5 2 2,5 3 3,5 4

Time

Tot. N

r. o

f D

eliv

era

ble

s

Planned (DoW)

Current Plan

André van Es2nd SKADS Workshop 10-11 October 2007

Next 18 months Next 18 months (major milestone for each DS)(major milestone for each DS)

DS2: Final Report on SKA configurations

DS 3: – Implementation of Cost and Functional simulator tool

– Selection of networking and computing technologies

DS 4: Completion of 2-PAD design

DS 5: Build and first testing of EMBRACE at Westerbork and Nancay (100 tiles)

DS 6: BEST demonstrating beamforming and Hl sensitivity astronomical tests

DS 8 : First iteration of Overall System Design and Project plan

André van Es2nd SKADS Workshop 10-11 October 2007

Review on deliverables: DS 8Review on deliverables: DS 8

Design Study 8 produces the major deliverables of the project (the focal and cohering point of SKADS):

1. Overall System Design

2. Preliminary SKA Plan

3. White Paper for the ISSC

It is the collection of all activities and will show and establish the direction towards the SKA