SECONDARY CONSTRUCTION PROGRAMSTATE HIGHWAY ADMINISTRATION -- Anne Arundel County -- Line 1
Urban Minor Arterial
Urban Minor Arterial
Secondary
25,900
65,700
CLASSIFICATION:
STATE -
FEDERAL -
STATE SYSTEM :
Annual Average Daily Traffic (vehicles per day)
CURRENT (2013) -
PROJECTED (2030) -
This project will relieve traffic congestion on this failing intersection as a result of the projected volumes resulting from BRAC expansion.EXPLANATION:
STATE GOALS :
Quality of ServiceSystem PreservationX Community VitalitySafety & SecurityX Environmental Stewardship
Maryland Transportation Plan (MTP) Goals/Selection Criteria:
Economic ProsperityX
MD 175, Annapolis Road
Construct intersection capacity improvements from west of MD 713 (Rockenbach Road/Ridge Road) to east of Disney Road/26th Street. (BRAC intersection improvement).
MD 175, at Mapes and Reece Roads (Line 2)MD 175, MD 295 to MD 170 (Line 7)BRAC Intersection Improvements near Fort Meade (Statewide Line 6)
Construction underway.
None.
The project will improve safety and operations along MD 175 and ease growing congestion resulting from BRAC expansion.PURPOSE & NEED SUMMARY STATEMENT:
PROJECT:
DESCRIPTION:
ASSOCIATED IMPROVEMENTS:
STATUS:
SIGNIFICANT CHANGE FROM FY 2013 - 18 CTP:
SMART GROWTH STATUS: Project Not Location Specific
Project Inside PFAX GrandfatheredProject Outside PFA
Exception GrantedPFA Status Yet To Be DeterminedException Will Be Required
Not Subject to PFA Law
FEDERALXPOTENTIAL FUNDING SOURCE:
PHASE
PlanningEngineeringRight-of-wayConstructionTotalFederal-Aid
TOTALESTIMATED
COST($000)
EXPENDTHRU
CURRENTYEAR YEAR
SIXYEARTOTAL
BALANCETO
COMPLETEFOR PLANNING PURPOSES ONLY
00
4,0928,890
12,98212,531
00
3,7826,1179,8999,626
00
3102,7733,0832,905
000000
000000
000000
000000
000000
00
3102,7733,0832,905
000000
BUDGET
SPECIALX GENERAL OTHER
2013 2014 2015 ....2016.... ....2017.... ....2018.... ....2019....
PROJECT CASH FLOW
PAGE ____________SHA-AA-1STIP REFERENCE #AA5803 12/01/2013
SECONDARY CONSTRUCTION PROGRAMSTATE HIGHWAY ADMINISTRATION -- Anne Arundel County -- Line 2
Urban Minor Arterial
Urban Minor Arterial
Secondary
24,700
65,700
CLASSIFICATION:
STATE -
FEDERAL -
STATE SYSTEM :
Annual Average Daily Traffic (vehicles per day)
CURRENT (2013) -
PROJECTED (2030) -
This project will relieve traffic congestion at these failing intersections, as a result of the projected volumes from BRAC.EXPLANATION:
STATE GOALS :
Quality of ServiceSystem PreservationX Community VitalitySafety & SecurityX Environmental Stewardship
Maryland Transportation Plan (MTP) Goals/Selection Criteria:
Economic ProsperityX
MD 175, Annapolis Road
Construct intersection capacity improvements at Mapes Road/Charter Oaks Boulevard and Reece Road (MD 174) (BRAC intersection improvement.) This project includes construction of a new security fence along Fort Meade and also includes Fort Meade tree buffer.
MD 175, MD 713 to Disney Road (Line 1)MD 175, MD 295 to MD 170 (Line 7)BRAC Intersection Improvements near Fort Meade (Statewide Line 6)
Right-of-Way underway. Construction to begin during current fiscal year.
The cost increase of $5.9 million is due to additional utility needs because of prior rights issues.
This project will improve safety and operations along MD 175 and ease growing congestion resulting from BRAC expansion at Fort Meade.PURPOSE & NEED SUMMARY STATEMENT:
PROJECT:
DESCRIPTION:
ASSOCIATED IMPROVEMENTS:
STATUS:
SIGNIFICANT CHANGE FROM FY 2013 - 18 CTP:
SMART GROWTH STATUS: Project Not Location Specific
Project Inside PFAX GrandfatheredProject Outside PFA
Exception GrantedPFA Status Yet To Be DeterminedException Will Be Required
Not Subject to PFA Law
FEDERALXPOTENTIAL FUNDING SOURCE:
PHASE
PlanningEngineeringRight-of-wayConstructionTotalFederal-Aid
TOTALESTIMATED
COST($000)
EXPENDTHRU
CURRENTYEAR YEAR
SIXYEARTOTAL
BALANCETO
COMPLETEFOR PLANNING PURPOSES ONLY
00
13,72514,20027,92522,039
00
9470
947849
00
1,700753
2,4531,974
00
5,1567,010
12,1669,542
00
5,0766,437
11,5139,009
00
8460
846665
000000
000000
00
12,77814,20026,97821,190
000000
BUDGET
SPECIALX GENERAL OTHER
2013 2014 2015 ....2016.... ....2017.... ....2018.... ....2019....
PROJECT CASH FLOW
PAGE ____________SHA-AA-2STIP REFERENCE #AA5806 12/01/2013
SECONDARY CONSTRUCTION PROGRAMSTATE HIGHWAY ADMINISTRATION -- Anne Arundel County -- Line 3
Local
Urban Local
Secondary
7,800
9,000
CLASSIFICATION:
STATE -
FEDERAL -
STATE SYSTEM :
Annual Average Daily Traffic (vehicles per day)
CURRENT (2013) -
PROJECTED (2030) -
The existing structure is structurally deficient.EXPLANATION:
STATE GOALS :
Quality of ServiceSystem PreservationX Community VitalitySafety & Security Environmental Stewardship
Maryland Transportation Plan (MTP) Goals/Selection Criteria:
Economic Prosperity
MD 648, Baltimore Annapolis Boulevard
Replace small structure 02080XX over Cattail Creek.
Engineering and Right-of-Way underway. Construction to begin during current fiscal year.
Added to the Construction Program.
The existing structure is structurally deficient.PURPOSE & NEED SUMMARY STATEMENT:
PROJECT:
DESCRIPTION:
ASSOCIATED IMPROVEMENTS:
STATUS:
SIGNIFICANT CHANGE FROM FY 2013 - 18 CTP:
SMART GROWTH STATUS: Project Not Location Specific
Project Inside PFAX GrandfatheredProject Outside PFA
Exception GrantedPFA Status Yet To Be DeterminedException Will Be Required
Not Subject to PFA Law
FEDERALXPOTENTIAL FUNDING SOURCE:
PHASE
PlanningEngineeringRight-of-wayConstructionTotalFederal-Aid
TOTALESTIMATED
COST($000)
EXPENDTHRU
CURRENTYEAR YEAR
SIXYEARTOTAL
BALANCETO
COMPLETEFOR PLANNING PURPOSES ONLY
0536333903
1,772769
0334
40
338143
0202169735
1,106626
00
160168328
0
000000
000000
000000
000000
0202329903
1,434626
000000
BUDGET
SPECIALX GENERAL OTHER
2013 2014 2015 ....2016.... ....2017.... ....2018.... ....2019....
PROJECT CASH FLOW
PAGE ____________SHA-AA-3STIP REFERENCE #AA7581 12/01/2013
PRIMARY DEVELOPMENT AND EVALUATION PROGRAMSTATE HIGHWAY ADMINISTRATION -- Anne Arundel County -- Line 4
Principal Arterial
Other Principal Arterial
Primary
63,300 - 81,275
78,375 - 124,800
CLASSIFICATION:
STATE -
FEDERAL -
STATE SYSTEM :
Annual Average Daily Traffic (vehicles per day)
CURRENT (2013) -
PROJECTED (2030) -
MD 3, Robert Crain Highway
Study to upgrade MD 3 from US 50 to MD 32 to address safety and capacity concerns (8.89 miles). Bicycle and pedestrian access will be provided where appropriate.
US 301, South Corridor Transportation Study (Prince George's County - Line 20)US 301, North of Mount Oak Road to US 50 (Prince George's County - Line 21)MD 450, Stonybrook Drive to west of MD 3 (Prince George's County - Line 28)
Project Planning underway.
None.
This project would improve safety and operations and relieve congestion in this heavily traveled corridor.JUSTIFICATION:
PROJECT:
DESCRIPTION:
ASSOCIATED IMPROVEMENTS:
STATUS:
SIGNIFICANT CHANGE FROM FY 2013 - 18 CTP:
SMART GROWTH STATUS: Project Not Location Specific
Project Inside PFAX GrandfatheredProject Outside PFA
Exception GrantedPFA Status Yet To Be DeterminedException Will Be Required
Not Subject to PFA Law
FEDERALXPOTENTIAL FUNDING SOURCE:
PHASE
PlanningEngineeringRight-of-wayConstructionTotalFederal-Aid
TOTALESTIMATED
COST($000)
EXPENDTHRU
CURRENTYEAR YEAR
SIXYEARTOTAL
BALANCETO
COMPLETEFOR PLANNING PURPOSES ONLY
3,9780
4,6730
8,6512,944
3,8710
4,6730
8,5442,865
600064
50000
5037
51000
5138
000000
000000
000000
107000
10779
000000
BUDGET
SPECIALX GENERAL OTHER
2013 2014 2015 ....2016.... ....2017.... ....2018.... ....2019....
PROJECT CASH FLOW
PAGE ____________SHA-AA-4The estimated cost is for the entire project in Anne Arundel and Prince George's counties.STIP REFERENCE #AT1981 12/01/2013
PRIMARY DEVELOPMENT AND EVALUATION PROGRAMSTATE HIGHWAY ADMINISTRATION -- Anne Arundel County -- Line 5
Principal Arterial
Freeway/Expressway
Primary
98,700
134,700
CLASSIFICATION:
STATE -
FEDERAL -
STATE SYSTEM :
Annual Average Daily Traffic (vehicles per day)
CURRENT (2013) -
PROJECTED (2030) -
MD 295, Baltimore Washington Parkway
Study to widen MD 295 from 4 to 6 lanes from MD 100 to I-195 including an interchange at Hanover Road and improvements to Hanover Road from the CSX railroad tracks in Howard County to MD 170 (3.27 miles).
Project Planning complete.
None.
This project would help ease congestion and improve access to one of the State's economic engines, the Baltimore-Washington International Thurgood Marshall Airport.JUSTIFICATION:
PROJECT:
DESCRIPTION:
ASSOCIATED IMPROVEMENTS:
STATUS:
SIGNIFICANT CHANGE FROM FY 2013 - 18 CTP:
SMART GROWTH STATUS: Project Not Location Specific
Project Inside PFAX GrandfatheredProject Outside PFA
Exception GrantedPFA Status Yet To Be DeterminedException Will Be Required
Not Subject to PFA Law
FEDERALXPOTENTIAL FUNDING SOURCE:
PHASE
PlanningEngineeringRight-of-wayConstructionTotalFederal-Aid
TOTALESTIMATED
COST($000)
EXPENDTHRU
CURRENTYEAR YEAR
SIXYEARTOTAL
BALANCETO
COMPLETEFOR PLANNING PURPOSES ONLY
2,554000
2,5542,043
2,554000
2,5542,043
000000
000000
000000
000000
000000
000000
000000
000000
BUDGET
SPECIALX GENERAL OTHER
2013 2014 2015 ....2016.... ....2017.... ....2018.... ....2019....
PROJECT CASH FLOW
PAGE ____________SHA-AA-5STIP REFERENCE #AA3721 12/01/2013
PRIMARY DEVELOPMENT AND EVALUATION PROGRAMSTATE HIGHWAY ADMINISTRATION -- Anne Arundel County -- Line 6
Principal Arterial
Urban Freeway/Expressway
Primary
126,450
159,900
CLASSIFICATION:
STATE -
FEDERAL -
STATE SYSTEM :
Annual Average Daily Traffic (vehicles per day)
CURRENT (2013) -
PROJECTED (2030) -
US 50, John Hanson Highway
Study to investigate options for alleviating congestion on US 50 from MD 70 to MD 2 (north), including the Severn River/Pearl Harbor Memorial Bridge. (1.7 miles)
Feasibility Study complete. Planning to begin during current fiscal year.
Added $2.0 million to Planning due to the Transportation Infrastructure Investment Act of 2013.
The approaches to the Severn River/Pearl Harbor Memorial Bridge experience severe congestion, particularly the eastbound direction during the evening peak period.JUSTIFICATION:
PROJECT:
DESCRIPTION:
ASSOCIATED IMPROVEMENTS:
STATUS:
SIGNIFICANT CHANGE FROM FY 2013 - 18 CTP:
SMART GROWTH STATUS: Project Not Location Specific
Project Inside PFA GrandfatheredProject Outside PFAX
Exception GrantedPFA Status Yet To Be DeterminedException Will Be RequiredX
Not Subject to PFA Law
FEDERALXPOTENTIAL FUNDING SOURCE:
PHASE
PlanningEngineeringRight-of-wayConstructionTotalFederal-Aid
TOTALESTIMATED
COST($000)
EXPENDTHRU
CURRENTYEAR YEAR
SIXYEARTOTAL
BALANCETO
COMPLETEFOR PLANNING PURPOSES ONLY
2,563000
2,5630
563000
5630
150000
1500
1,000000
1,0000
850000
8500
000000
000000
000000
2,000000
2,0000
000000
BUDGET
SPECIALX GENERAL OTHER
2013 2014 2015 ....2016.... ....2017.... ....2018.... ....2019....
PROJECT CASH FLOW
PAGE ____________SHA-AA-6STIP REFERENCE #AA2211 12/01/2013
SECONDARY DEVELOPMENT AND EVALUATION PROGRAMSTATE HIGHWAY ADMINISTRATION -- Anne Arundel County -- Line 7
Urban Minor Arterial
Urban Minor Arterial
Secondary
24,700 - 38,000
54,300 - 82,200
CLASSIFICATION:
STATE -
FEDERAL -
STATE SYSTEM :
Annual Average Daily Traffic (vehicles per day)
CURRENT (2013) -
PROJECTED (2030) -
MD 175, Annapolis Road
This study will identify traffic flow improvements on MD 175 from MD 295 to MD 170 including the MD 175/MD 295 interchange (5.2 miles). Bicycles and pedestrian accommodations will be provided where appropriate. (BRAC Related)
MD 175, MD 713 to Disney Road (Line 1)MD 175, at Mapes and Reece Roads (Line 2)MD 198, MD 295 to MD 32 (Line 8)BRAC Intersection Improvements at Fort Meade (Statewide Line 6)
Partial Engineering underway. The Engineering shown is for the design of the MD 295 interchange. Right-of-Way for the MD 295 interchange to begin during current fiscal year.
Added $28.5 million to Right-of-Way due to the Transportation Infrastructure Investment Act of 2013.
This project would address current and future congestion along MD 175 and will improve access to Fort Meade.JUSTIFICATION:
PROJECT:
DESCRIPTION:
ASSOCIATED IMPROVEMENTS:
STATUS:
SIGNIFICANT CHANGE FROM FY 2013 - 18 CTP:
SMART GROWTH STATUS: Project Not Location Specific
Project Inside PFAX GrandfatheredProject Outside PFA
Exception GrantedPFA Status Yet To Be DeterminedException Will Be Required
Not Subject to PFA Law
FEDERALXPOTENTIAL FUNDING SOURCE:
PHASE
PlanningEngineeringRight-of-wayConstructionTotalFederal-Aid
TOTALESTIMATED
COST($000)
EXPENDTHRU
CURRENTYEAR YEAR
SIXYEARTOTAL
BALANCETO
COMPLETEFOR PLANNING PURPOSES ONLY
2,5858,527
28,4670
39,57910,470
2,5852,836
00
5,4214,797
01,0001,000
02,0001,000
01,0002,000
03,000
982
01,000
11,0000
12,0001,000
02,691
10,0000
12,6912,691
00
4,4670
4,4670
000000
05,691
28,4670
34,1585,673
000000
BUDGET
SPECIALX GENERAL OTHER
2013 2014 2015 ....2016.... ....2017.... ....2018.... ....2019....
PROJECT CASH FLOW
PAGE ____________SHA-AA-7STIP REFERENCE #AA4361 12/01/2013
SECONDARY DEVELOPMENT AND EVALUATION PROGRAMSTATE HIGHWAY ADMINISTRATION -- Anne Arundel County -- Line 8
Other Principal Arterial
Other Principal Arterial
Secondary
26,000
42,300
CLASSIFICATION:
STATE -
FEDERAL -
STATE SYSTEM :
Annual Average Daily Traffic (vehicles per day)
CURRENT (2013) -
PROJECTED (2030) -
MD 198, Laurel Fort Meade Road
Study to address capacity needs on MD 198 from MD 295 to MD 32 (2.66 miles). Bicycle and pedestrian access will be provided where appropriate. (BRAC Related)
MD 175, MD 713 to Disney Road (Line 1)MD 175, at Mapes and Reece Roads (Line 2)MD 175, MD 295 to MD 170 (Line 7)BRAC Intersection Improvements at Fort Meade (Statewide Line 6)
Project Planning underway. County contributing up to $3.5 million for the planning phase.
None.
MD 198 is a key link to Fort Meade from points south and west. The area in and around Fort Meade will experience substantial growth as a result of BRAC.JUSTIFICATION:
PROJECT:
DESCRIPTION:
ASSOCIATED IMPROVEMENTS:
STATUS:
SIGNIFICANT CHANGE FROM FY 2013 - 18 CTP:
SMART GROWTH STATUS: Project Not Location Specific
Project Inside PFAX GrandfatheredProject Outside PFA
Exception GrantedPFA Status Yet To Be DeterminedException Will Be Required
Not Subject to PFA Law
FEDERALXPOTENTIAL FUNDING SOURCE:
PHASE
PlanningEngineeringRight-of-wayConstructionTotalFederal-Aid
TOTALESTIMATED
COST($000)
EXPENDTHRU
CURRENTYEAR YEAR
SIXYEARTOTAL
BALANCETO
COMPLETEFOR PLANNING PURPOSES ONLY
000000
000000
000000
000000
000000
000000
000000
000000
000000
000000
BUDGET
SPECIALX GENERAL OTHERX
2013 2014 2015 ....2016.... ....2017.... ....2018.... ....2019....
PROJECT CASH FLOW
PAGE ____________SHA-AA-8STIP REFERENCE #AA5101 12/01/2013
SAFETY, CONGESTION RELIEF, HIGHWAY AND BRIDGE PRESERVATION PROGRAM
ITEM NO. DESCRIPTION AND IMPROVEMENT TYPE
CONSTRUCTIONTOTALESTIMATED
COST($000's)
STATE HIGHWAY ADMINISTRATION -- ANNE ARUNDEL COUNTY LINE 9
ROUTE NO.
December 1, 2013
STARTStatus as of
Fiscal Year 2013 Completions
Bridge Replacement/Rehabilitation
5,3101 CompletedWest Nursery Road; over MD 295 (NB and SB); bridge rehabilitation
Safety/Spot Improvement
5442 CompletedSouthern MD Boulevard; various locations at MD 4 and MD 408 interchange; drainage improvements
MD 4
1,8503 CompletedWest Street; MD 2 to MD 435; ADA improvementsMD 450
1754 CompletedBaltimore Annapolis Boulevard; Edgewood Road to Hammonds Lane; ADA improvements (ARRA PROJECT)
MD 648
Enhancements
Environmental Mitigation
4075 CompletedFunctional Enhancement of SWM facilities along MD 4 in Anne Arundel County; SWM facilities improvements
Fiscal Years 2014 and 2015
Resurface/Rehabilitate
3866 Under constructionAt Various locations in Anne Arundel County; joint sealing
10,4827 Under constructionVarious locations in Southern Anne Arundel County; mill/grind, patch and resurface pavement
9,3458 Under constructionVarious locations in Northern Anne Arundel County; mill/grind, patch and resurface pavement
PAGE _________SHA-AA-9
SAFETY, CONGESTION RELIEF, HIGHWAY AND BRIDGE PRESERVATION PROGRAM
ITEM NO. DESCRIPTION AND IMPROVEMENT TYPE
CONSTRUCTIONTOTALESTIMATED
COST($000's)
STATE HIGHWAY ADMINISTRATION -- ANNE ARUNDEL COUNTY LINE 9 (cont'd)
ROUTE NO.
December 1, 2013
STARTStatus as of
Fiscal Years 2014 and 2015 (cont'd)
Resurface/Rehabilitate (cont'd)
7,9299 Under constructionVarious locations in Northern Anne Arundel County
55010 FY 2014Solomons Island Road; At MD 214; resurfaceMD 2
79511 CompletedHoward County Line to MD 713; resurfacing (ARRA PROJECT)MD 100 EB
74212 Under constructionDefense Highway; Housley Road to Generals Highway; resurfaceMD 450
Bridge Replacement/Rehabilitation
1,53913 FY 201411 Existing bridges on MD 295 and MD 100; clean and paint bridges
3,35814 Under constructionCleaning and Painting of bridges on MD 176, MD 174, MD 32, MD 2 and MD 10 in Anne Arundel County
2,08515 Under constructionFort Smallwood Road; bridge 02045 over Stoney Creek; clean paint bridgeMD 173
3,64916 Under constructionBaltimore Beltway; bridge over Patapsco River and Hammonds Ferry Road; clean and paint bridgesI 695
Safety/Spot Improvement
7317 Under constructionCrain Highway; Business 3 at 11th Avenue; landscape
1,42118 Under constructionSolomon's Island Road; Jewel Road/MD 423; safetyMD 2
3,30019 FY 2014Solomons Island Road; at Owensville Sudley Road; geometric improvementsMD 2
2,20020 FY 2015Solomons Island Road; at MD 256; geometric improvementsMD 2
PAGE _________SHA-AA-10
SAFETY, CONGESTION RELIEF, HIGHWAY AND BRIDGE PRESERVATION PROGRAM
ITEM NO. DESCRIPTION AND IMPROVEMENT TYPE
CONSTRUCTIONTOTALESTIMATED
COST($000's)
STATE HIGHWAY ADMINISTRATION -- ANNE ARUNDEL COUNTY LINE 9 (cont'd)
ROUTE NO.
December 1, 2013
STARTStatus as of
Fiscal Years 2014 and 2015 (cont'd)
Safety/Spot Improvement (cont'd)
2,61521 FY 2014Solomon's Island Road; at MD 255; geometric improvements(Transportation Infrastructure Investment Act of 2013)
MD 2
2,20022 FY 2015Solomon's Island Road; at Harwood Drive; geometric improvements(Transportation Infrastructure Investment Act of 2013)
MD 2
45323 Under constructionAt Lower Pindell Road; geometric improvementsMD 4 SB
1,31924 FY 2014Arundel Expressway; MD 177 to MD 695; guardrailMD 10
2625 FY 2015Mayo Road; MD 214 to MD 2 northbound; ADA improvementsMD 253 NB
1,54426 FY 2014Davidsonville Road; MD 3 to MD 450; sidewalks(Transportation Infrastructure Investment Act of 2013)
MD 424
99127 CompletedEast Ordnance Road; at VEIP entrance; geometric improvementsMD 710
Community Safety and Enhancements
30028 Concepts UnderwayWest Street; Goodwill Store to MD 2; reconstruction(Funded for concepts only) (Transportation Infrastructure Investment Act of 2013)
MD 450
29 Baltimore Annapolis Boulevard; MD 2 to MD 10; urban reconstruct (Project on hold)MD 648
Streetscapes and Minor Reconstruction
48630 UnderwayBladen Street; College Creek Park to College Avenue (Bloomsbury Square); streetscape(Note: The cost shown represents SHA share of project cost)
PAGE _________SHA-AA-11
SAFETY, CONGESTION RELIEF, HIGHWAY AND BRIDGE PRESERVATION PROGRAM
ITEM NO. DESCRIPTION AND IMPROVEMENT TYPE
CONSTRUCTIONTOTALESTIMATED
COST($000's)
STATE HIGHWAY ADMINISTRATION -- ANNE ARUNDEL COUNTY LINE 9 (cont'd)
ROUTE NO.
December 1, 2013
STARTStatus as of
Fiscal Years 2014 and 2015 (cont'd)
Traffic Management
39831 Under constructionMD 450 and Severn River/Naval Academy Bridge; lighting
1,55032 CompletedSignals along MD 2 and MD 710; reconstruct signals (ARRA PROJECT)
1,60233 FY 2015Baltimore Beltway; at I 895 and MD 2; lightingI 695
Environmental Preservation
7934 CompletedRowe Boulevard; Taylor Avenue to Farragut Road; landscapingMD 70 NB
25635 Under constructionDefense Highway; at Annapolis Shop; drainage improvementsMD 450
Commuter Action Improvements
1,12736 FY 2014Southern Maryland Boulevard; at MD 794; ridesharing facilitiesMD 4
1,86037 Under constructionDavidsonville Road; US 50 south of interchange; ridesharing lot expansionMD 424
Intersection Capacity Improvements
4,90038 FY 2014Governor Ritchie Highway; at Earleigh Heights Road/Magothy Bridge Road; geometric improvements (Transportation Infrastructure Investment Act of 2013)
MD 2
Bicycle Retrofit
1,52039 FY 2014Camp Meade Road; MD 648 to Andover Road; bicycle retrofitMD 170
PAGE _________SHA-AA-12
SAFETY, CONGESTION RELIEF, HIGHWAY AND BRIDGE PRESERVATION PROGRAM
ITEM NO. DESCRIPTION AND IMPROVEMENT TYPE
CONSTRUCTIONTOTALESTIMATED
COST($000's)
STATE HIGHWAY ADMINISTRATION -- ANNE ARUNDEL COUNTY LINE 9 (cont'd)
ROUTE NO.
December 1, 2013
STARTStatus as of
Fiscal Years 2014 and 2015 (cont'd)
TMDL Compliance
1,48740 FY 2015Aris T Allen Boulevard; Broad Creek Stream Restoration; wetlands replacement(Transportation Infrastructure Investment Act of 2013)
MD 665
Enhancements
Rehabilitation/Operation of Historic Transportation Structures
30041 FY 2015Historic Generals Highway Corridor Study; archaeology surveys, historic research and public outreach along Generals Highway
Environmental Mitigation
85642 FY 2014Rutland Road Fish Passage
61943 UnderwayWhitehall Creek and Windsor Ridge Stream stabilization; providing a total of 1,250 LF of stream restoration
1,00044 FY 2014Cowhide Branch stream restoration and Fish Passage; mitigation of water pollution due to highway runoff
65045 CompletedNorth Cypress Branch Stream Restoration; 2200 linear feet of stream restoration for creation of a one-acre stormwater wetland; restoration/creation of 3.3 acres of wetlands along the stream; environmental mitigation
Congressional Earmarks
046 Construct Broadneck Peninsula Trail; construct trail (Earmark $1.2 million; CO) (Complete)
047 South Shore Trail; construct trail from MD 3 to I-97 at Waterbury Road; construct trail (Earmark $1.6 million; PE, CO)
PAGE _________SHA-AA-13