ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021 Page 1 of 30 RFP 19021 ANNEX B-1 MUHAMMAD KHAIL - SCHOOL NO 13 BILL OF QUANTITIES S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM White Wash All School 1 White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor Rooms 2.0 30 10 600 " 2.0 20 10 400 Bounday wall 2.0 300 8 4800 5800 Sft 2 Painting with paint mixed at site using ingredients and pigment to produce required texture and shade in two or more coats on wood work over and including the cost of priming coat, surface preparation, rubbing down smooth, knotted, filling cracks, holes and joints in ground floor or basement. Door 2 3 7 42 windows 4 5 4 80 Gate 1 8 8 64 186 Sft 3 Supply and Changing of Steel Girder 3 KG per rft NSR 1.0 20 20.00 Rft 4 Good quality plastic sheeting NSR 2.0 30 20 1200.00 Sft 1200.00 Sft 5 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer 2.0 30 20 1200.00 Front wall 1.0 60 9 540.00 1740.00 Cft
Transcript
Page 1: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 1 of 30

RFP 19021 ANNEX B-1

MUHAMMAD KHAIL - SCHOOL NO 13

BILL OF QUANTITIES

S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

White Wash All School

1 White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

Rooms 2.0 30 10 600

"

2.0 20 10 400

Bounday wall 2.0 300 8 4800

5800 Sft

2 Painting with paint mixed at site using ingredients and pigment to produce required texture and shade in two or more coats on wood work over and including the cost of priming coat, surface preparation, rubbing down smooth, knotted, filling cracks, holes and joints in ground floor or basement.

Door

2 3 7 42

windows

4 5 4 80

Gate

1 8 8 64

186 Sft

3 Supply and Changing of Steel Girder 3 KG per rft NSR 1.0 20 20.00 Rft

4 Good quality plastic sheeting NSR 2.0 30 20 1200.00 Sft

1200.00 Sft

5 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

2.0 30 20 1200.00

Front wall

1.0 60 9 540.00

1740.00 Cft

Page 2: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 2 of 30

RFP 19021 ANNEX B-2

MUHAMMAD KHAIL - SCHOOL NO 14

BILL OF QUANTITIES

S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

1 White Wash All School

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

Rooms

2.0 30 10 600

" 2.0 20 10 400

Bounday wall

2.0 300 8 4800

5800 Sft

Painting with paint mixed at site using ingredients and pigment to produce required texture and shade in two or more coats on wood work over and including the cost of priming coat, surface preparation, rubbing down smooth, knotted, filling cracks, holes and joints in ground floor or basement.

Door 2 3 7 42

windows 4 5 4 80

Gate 1 8 8 64

186 Sft

2 Roof covering materials For Toilet Roof replacement.

Supplying bamboos.11.5 ft. (3.5 m.) long and 3" (75 mm) dia 20.0 1.0 20.00

Chick over bamboos NSR 5.0 14.0 7 490.00

Total 490.00 Sft

Good quality plastic sheeting NSR 5.0 14.0 7 490.00

Total 490.00 Sft

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster

5.0 14.0 7 490.00

Total 490.00 Cft

Page 3: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 3 of 30

3 Repair of winodows Frame and Glass 3 mm and color NSR 4.0 5 4 80.00 Sft

4 Roof Mud Layer

Good quality plastic sheeting NSR 2.0 30 20 1200.00 Sft

1200.00 Sft

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

2.0 30 20 1200.00

Front wall

1.0 60 9 540.00

1740.00 Cft

RFP 19021 ANNEX B-3

CHAGHI - SCHOOL NO 40

BILL OF QUANTITIES

S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

A Verandah

1 Supplying bamboos.11.5 ft. (3.5 m.) long and 3" (75 mm) dia 70.0 1 70.00 No

2

Chick over bamboos NSR 1.0 70 10 700.00 Sft

3

Good quality plastic sheeting NSR 1.0 70 10 700.00 Sft

4 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster 1.0 70 10 700.00 Cft

B Roof Mud Layer

Good quality plastic sheeting 1.0 100 25 2500.00 Sft

"

1.0 105 25 2625.00

"

1.0 100 25 2500.00

7625.00 Sft

Page 4: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 4 of 30

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

1.0 100 25 2500.00

"

1.0 105 25 2625.00

"

1.0 100 25 2500.00

7625.00 Sft

RFP 19021 ANNEX B-4

CHAGHI - SCHOOL NO 41

BILL OF QUANTITIES

S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

1 Supplying bamboos.11.5 ft. (3.5 m.) long and 3" (75 mm) dia 70.0 1.0 70.00

2 Supplying bamboos.16.5 ft. (5 m.) long and 3.5" to 4" (87.5 mm to 100 mm 80.0 1 80.00

Total 150.00 Rft

3 Chick over bamboos NSR 1.0 70.0 10 700.00

1.0 80 15 1200.00

Total 1900.00 Sft

4 Good quality plastic sheeting NSR 1.0 70.0 10 700.00

1.0 80 15 1200.00

Total 1900.00 Sft

5 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer 1.0 70.0 10 700.00

1.0 80 15 1200.00

Total 1900.00 Cft

Roof Mud Layer

6 Good quality plastic sheeting NSR 2.0 20 15 600.00 Sft

600.00 Sft

7 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

2.0 20 12 480.00 Cft

Page 5: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 5 of 30

480.00 Cft

RFP 19021 ANNEX B-5

CHAGHI - SCHOOL NO 42 - Lejay

BILL OF QUANTITIES

S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

1 Repair of Roof Mud Layer & Plastic sheet ,

Good quality plastic sheeting 1.0 80 25 2000.00

NSR

1.0 80 25 2000.00

1.0 40 25 1000.00

Total 5000.00 Sft

2 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

1.0 80.0 25.0 2000.00

1.0 80.0 25.0 2000.00

1.0 40.0 25.0 1000.00

Total 5000.0 Cft

3 Providing and laying sundried clay bricks set in mud mortar including scaffolding in ground floor superstructure Above 4.5" (115mm) nominal thick brickwor

1.0 70.0 9.0 0.8 472.5 CFT

RFP 19021 ANNEX B-6

CHAGHI - SCHOOL NO 43

BILL OF QUANTITIES

S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

1 Excavation in foundation of buildings,bridges and other structures, depth upt 4 meters including dag bellings dressing,refilling around structures with excavated earth, watering and ramming lead upto 30 m lift up to 1.5 m.

S.i.No 3-21-A-II 1 36 1 1 36 Cft

Borrow pit excavation depth upto 10 ft. (3 m) undressed lead upto 100 ft. (30m)

Page 6: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 6 of 30

3-4/D 2 3 3 15 270 CFT

2 Providing and laying cement concrete thick and down 1:4:8 ratio using gauge in foundation including levelling compacting and curing. Extra if crushed stone 19mm (3/4”) and down gauge is used in place of shingle or bajri

S.i.No 5-4-b 1 36 1 0.3 9 Cft

3 Providing and laying first class solid burnt brick masonry including scaffolding, raking out joints and curing in ground floor superstructure with ratio 1:4.

11-19-b-iv 1 36 1 1 36

1 36 0.75 7 189

225 Cft

Providing and fixing fully glazed steel door with frame single leaf with M.S bottom or kick rail 6" (150mm) wide and top rail of 4" (100mm) wide painted with two coats of red oxide paint, brass oxidized fittings of lugs, cutting holed, and making good the damages to walls.

S.No 28-3-1 2 2.5 7 35

2 2 1.5 6

Total 41 Sft

6 Roof covering materials

Fabrication of heavy steel work with angle, tees, flat iron, round iron and sheet iron for making trusses, girders, tanks etc. including cutting, drilling riveting, handling, assembling and fixing but excluding erection

S.i.No 28-45-1

Steel Girders beam (size 3" x 7" x 6.5') at 2 kg

2 6 24

T. Iron at 1 kg 8 13 104

Total 128 rft/kg

Providing and laying roof insulation comprising single layer of first class burnt brick tile 12"x6"x1.25" laid with 1:6 cement sand mortar and grouted with 1:3 cement sand mortar laid over 4inches (100mm) thick earth and 1inch (25mm) thick gobri leaping over two coats of hot bitumen @ 34 lbs. per 100 Sq.ft.(1.65 Kg/Sq.m) sand blended covered

13-1-a 2 5.75 5.75 66.125 SFT

Page 7: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 7 of 30

Providing and laying 1:2:4 cement concrete using approved coarse sand and crushed aggregate 3/4" (19mm) and down gauge in beams,lintels and cantilevers of required shape or section including formwork and its removal compacting and curing in basement and ground floor.

5-16-a 2 6 6 0.3 18 CFT

13 mm (1/2") thick cement plaster on walls and columns in basement, plinth and ground floor including making edges, corners and curing. The mix ratio is 1:4 cement sand.

15-1-a-ii 2 6 7 84

2 5 7 70

154 SFT

Providing, laying, cutting, jointing, testing and disinfecting PPRC pipes confirming to ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust pipe 4"

27-47-a-IX 2 8 16 RFT

Providing and laying 1:2:4 cement concrete using approved coarse sand and crushed aggregate 3/4" (19mm) and down gauge in beams,lintels and cantilevers of required shape or section including formwork and its removal compacting and curing in basement and ground floor.

5-16-a

Slab pit 1 5 5 0.33 8.333 Sft

RFP 19021 ANNEX B-7

CHAGHI - SCHOOL NO 46 - Posti

BILL OF QUANTITIES

S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

Roof Mud Layer

1 Good quality plastic sheeting NSR 1.0 70 25 1750.00 Sft

"

1.0 40 25 1000.00

"

1.0 70 25 1750.00

4500.00 Sft

2 Repair of mud wall by mud bricks and plaster with mud.

2.0 30 8 480.00 Sft

3 White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

Page 8: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 8 of 30

10.0 20 14 10 6800.00 Sft

4 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

1.0 70 25 1750.00

"

1.0 40 25 1000.00

"

1.0 70 25 1750.00

4500.00 Sft

RFP 19021 ANNEX B-8

MALGAGI RV - SCHOOL NO 24

BILL OF QUANTITIES

S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

1 Repair of Roof Mud Layer & Plastic sheet ,

Good quality plastic sheeting 7.0 22.0 18.0 2772.00

1.0 110.0 10.0 1100.00

Total 3872.00 Sft

2 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

7.0 22.0 18.0 2772.00

1.0 110.0 10.0 1100.00

Total 3872.0 Cft

3 Providing and laying sundried clay bricks set in mud mortar including scaffolding in ground floor superstructure Above 4.5" (115mm) nominal thick brickwor

1.0 25.0 8.0 0.8 150.0

1.0 50.0 2.5 0.8 93.8

1.0 154.0 1.0 0.8 115.5

359.3 CFT

3 White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

7.0 22 15 10 5180.00 Sft

4 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

Page 9: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 9 of 30

2.0 25.0 8.0 400.00

2.0 50.0 2.5 250.00

650.0 CFT

RFP 19021 ANNEX B-9

MALGAGAI RV - SCHOOL NO 25

BILL OF QUANTITIES 6 toilets, verdanh pcc and roof mud plaster

Based on CSR 2018 S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

1 Excavation in foundation of buildings,bridges and other structures, depth upt 4 meters including dag bellings dressing,refilling around structures with excavated earth, watering and ramming lead upto 30 m lift up to 1.5 m.

S.i.No 3-21-A-II 1 106.75 1 1 106.75 Cft

2 Borrow pit excavation depth upto 10 ft. (3 m) undressed lead upto 100 ft. (30m)

3-4/D 6 3 3 15 810 CFT

3 Providing and laying cement concrete thick and down 1:4:8 ratio using gauge in foundation including levelling compacting and curing. Extra if crushed stone 19mm (3/4”) and down gauge is used in place of shingle or bajri

S.i.No 5-4-b 1 106.75 1 0.25 26.6875 Cft

4 Providing and laying first class solid burnt brick masonry including scaffolding, raking out joints and curing in ground floor superstructure with ratio 1:4.

11-19-b-iv 1 106.75 1 1 106.75

9 inch wall 1 82.25 0.75 7 431.8125

3 inch wall 1 23 0.375 7 60.375

Total 598.9375 Cft

5 Providing and fixing fully glazed steel door with frame single leaf with M.S bottom or kick rail 6" (150mm) wide and top rail of 4" (100mm) wide painted with two coats of red oxide paint, brass oxidized fittings of lugs, cutting holed, and making good the damages to walls.

S.No 28-3-1 6 2.5 7 105

6 2 1.5 18

Total 123 Sft

Roof covering materials

Page 10: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 10 of 30

6 Fabrication of heavy steel work with angle, tees, flat iron, round iron and sheet iron for making trusses, girders, tanks etc. including cutting, drilling riveting, handling, assembling and fixing but excluding erection

S.i.No 28-45-1

Steel Girders beam (size 3" x 7" x 6.5') at 2 kg

2 22 88

T. Iron at 1 kg 15 12 180

Total 268 Rft

7 Providing and laying roof insulation comprising single layer of first class burnt brick tile 12"x6"x1.25" laid with 1:6 cement sand mortar and grouted with 1:3 cement sand mortar laid over 4inches (100mm) thick earth and 1inch (25mm) thick gobri leaping over two coats of hot bitumen @ 34 lbs. per 100 Sq.ft.(1.65 Kg/Sq.m) sand blended covered

13-1-a 1 22 15 330 SFT

8 Providing and laying 1:2:4 cement concrete using approved coarse sand and crushed aggregate 3/4" (19mm) and down gauge in beams,lintels and cantilevers of required shape or section including formwork and its removal compacting and curing in basement and ground floor.

5-16-a 1 22 15 0.25 82.5 CFT

9 13 mm (1/2") thick cement plaster on walls and columns in basement, plinth and ground floor including making edges, corners and curing. The mix ratio is 1:4 cement sand.

15-1-a-ii 6 6 7 252

6 5 7 210

2 22 8 352

Total 814 SFT

10 Providing, laying, cutting, jointing, testing and disinfecting PPRC pipes confirming to ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust pipe 4"

27-47-a-IX 6 8 48 RFT

11 Providing and laying 1:2:4 cement concrete using approved coarse sand and crushed aggregate 3/4" (19mm) and down gauge in beams,lintels and cantilevers of required shape or section including formwork and its removal compacting and curing in basement and ground floor.

5-16-a

Slab pit 6 6 5 0.333 60 Sft

12 Repair of Roof Mud Layer & Plastic sheet ,

Page 11: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 11 of 30

Good quality plastic sheeting 2 20 16 640

NSR Total 640 Sft

13 Providing and laying 1:2:4 cement concrete using approved coarse sand and crushed aggregate 3/4" (19mm) and down gauge in beams,lintels and cantilevers of required shape or section including formwork and its removal compacting and curing in basement and ground floor.

5-16-a 1 65 8 0.25 130 CFT

14 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

roof 2 20 16

640

wall 2 200 8

3200

Total 3840 Cft

15 White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

7 20 16

4536

2 200 8

3200

Total 7736 Cft

RFP 19021 ANNEX B-10

MALGAGAI - SCHOOL NO 26

BILL OF QUANTITIES

S.NO DESCRIPTION NO LENGTH WIDTH H/D QUANTITY UoM

1 Repair of Roof Mud Layer & Plastic sheet ,

Good quality plastic sheeting

NSR Total 4071 Sft

2 White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

total quantitiy 10420 sft

3 Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

1 28 16

448

Class Rooms 1 10 10

100

Class Rooms 1 22 30

660

Class Rooms 1 22 15

330

Page 12: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 12 of 30

Class Rooms 1 48 22

1056

Class Rooms 1 13 22

286

Class Rooms 1 22 18

396

Class Rooms 1 26 18

468

Class Rooms 1 25 18

450

Class Rooms 1 26 10

260

Total 4454 Cft

RFP 19021 ANNEX B-11

LORALAI - BOYS HIGH SCHOOL 29

BILL OF QUANTITIES

S. No DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

ROOF PLASTER

ROOF 1 1 200.00 15.00 3000.00 SFT

TOTAL QUANTITY A-B 3000.00 SFT

4

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF PLASTER

3000.00 3000.00 SFT

TOTAL QUANTITY Total 3000.00 SFT

RFP 19021 ANNEX B-12

LORALAI - Girls Primary School No 30

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF PLASTER

Page 13: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 13 of 30

ROOF 1 1 300.00 22.00 0.33 2178.00 SFT

TOTAL QUANTITY A-B 2178.00 SFT

4 Supplying bamboos.11.5 ft. (3.5 m.) long and 3" (75 mm) dia

NSR

Bam Bo 5" Dia 10 1 10.00 Rft

Total 10.00 Rft

5

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF

PLASTER

3000.00 3000.00 SFT

TOTAL QUANTITY Total 3000.00 SFT

RFP 19021 ANNEX B-13

LORALAI - BOYS HIGH SCHOOL NO 31

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

1

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF PLASTER

ROOF 1 1 600.00 25.00 0.33 4950.00 SFT

TOTAL QUANTITY A-B 4950.00 SFT

2

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF

PLASTER

4950.00 2.00 9900.00 SFT

Page 14: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 14 of 30

TOTAL QUANTITY Total 9900.00 SFT

3

Construction of mud wall with mud brick work in mud motor and plaster on both sides as per instruction of engineer

NSR

Boundary wall 1 110 0.75 8.00 660.00

Total 660.00 Cft

RFP 19021 ANNEX B-14

LORALAI - BOYS HIGH SCHOOL NO 33

BILL OF QUANTITIES

S. No DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF PLASTER

ROOF 1 1 250.00 15.00 0.25 937.50 SFT

TOTAL QUANTITY A-B 937.50 SFT

5

Construction of mud wall with mud brick work in mud motor and plaster on both sides as per instruction of engineer

NSR

Boundary wall 1 50 0.75 7.00 262.50

Total 262.50 Cft

RFP 19021 ANNEX B-15

LORALAI - BOYS HIGH SCHOOL NO 34

BILL OF QUANTITIES

S. No DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

1

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF PLASTER

Page 15: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 15 of 30

ROOF 1 1 130.00 30.00 0.33 1287.00 SFT

19 mm THICK PLASTER ON WALL

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

BATH ROOM 1 2 7.00 5.00 10.00 240.00 SFT

19 mm THICK PLASTER ON WALL

FRONT WALLS 1 1 100.00 7.00 700.00 SFT

RIGHT SIDE WALLS 1 1 80.00 7.00 560.00 SFT

BACK WALLS 1 1 100.00 7.00 700.00 SFT

LEFT SIDE WALLS 1 1 80.00 7.00 560.00 SFT

TOTAL 5907.00 SFT

sub total A 5907.00 SFT

DEDUCTION DOOR/WINDOW

Ded: Doors D1 7 1 3.00 6.00 18.00 CFT

Ded: Win: W1 14 1 4.00 5.00 20.00 CFT

sub total B 38.00

TOTAL QUANTITY A-B 5869.00 SFT

RFP 19021 ANNEX B-16

LORALAI - SCHOOL NO 35

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF PLASTER

Page 16: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 16 of 30

ROOF 1 1 200.00 20.00 0.33 1320.00 SFT

TOTAL QUANTITY A-B 1320.00 SFT

4 Providing and laying of instllation of BamBo with complet all work

NSR

Bam Bo 5" Dia 1 25 25.00

Total 25.00

Providing layer of mud on bounadary wall and mud brick work where requried as per instruction of engineer

NSR

Boundary wall 1 550 0.75 8.00 4400.00

Total 4400.00 Cft

RFP 19021 ANNEX B-17

SURKHAB - MIDDLE SCHOOL NO 1

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF 1 1 180.00 15.00 0.33 891.00 CFT

BATH ROOM 1 4 7.00 5.00 10.00 480.00 SFT

TOTAL QUANTITY A 1371.00 SFT

4

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF

PLASTER

3000.00 1.00 1.00 1.00 3000.00 SFT

TOTAL QUANTITY Total 3000.00 SFT

Page 17: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 17 of 30

5

construction of mud on bounadary wall and mud brick work where requried as per instruction of engineer

NSR

BOUNDARY WALL 1 150 1.00 1.00 8.00 1200.00

Total 1200.00 Cft

6

Construction of mud wall with mud brick work in mud motor and plaster on both sides as per instruction of engineer

NSR

CLASS ROOM 1 1 5.00 0.75 12.00 45.00

BAT ROOM 1 2 5.00 0.75 7.00 52.50

Total 97.50 Cft

RFP 19021 ANNEX B-18

SURKHAB - MIDDLE SCHOOL NO 2

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF 1 1 230.00 0.33 13.00 986.70 CFT

TOTAL QUANTITY A 986.70 SFT

4

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY

OF PLASTER

3500.00 1.00 1.00 1.00 3500.00 SFT

TOTAL QUANTITY Total 3500.00 SFT

Page 18: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 18 of 30

RFP 19021 ANNEX B-19

SURKHAB - BOYS SCHOOL NO 5

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF 1 1 100.00 0.33 22.00 726.00 CFT

19 mm THICK PLASTER ON WALL

FRONT WALLS 1 1 100.00 1.00 12.00 1200.00 SFT

RIGHT SIDE WALLS 1 1 60.00 1.00 12.00 720.00 SFT

BACK WALLS 1 1 100.00 1.00 12.00 1200.00 SFT

LEFT SIDE WALLS 1 1 60.00 1.00 12.00 720.00 SFT

TOTAL 4566.00 SFT

sub total A 4566.00 SFT

DEDUCTION DOOR/WINDOW

Ded: Doors D1 4 1 3.00 1.00 6.00 72.00 SFT

Ded: Win: W1 8 1 4.00 1.00 5.00 160.00 SFT

sub total B 232.00 SFT

TOTAL QUANTITY A-B 4334.00 SFT

4

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF

PLASTER

3608.00 1.00 1.00 1.00 3608.00 SFT

TOTAL QUANTITY Total 3608.00 SFT

Page 19: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 19 of 30

RFP 19021 ANNEX B-20

SURKHAB - SCHOOL NO 6

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF PLASTER 2170.00 1.00 1.00 1.00 2170.00 SFT

TOTAL QUANTITY Total 2170.00 SFT

3

Providing layer of mud on bounadary wall and mud brick work where requried as per instruction of engineer

NSR

BOUNDARY WALL 1 300 1.00 1.00 7.00 2100.00

Total 2100.00 Cft

RFP 19021 ANNEX B-21

SURKHAB - MIDDLE SCHOOL NO 7

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF 1 1 250.00 22.00 0.33 1815.00 CFT

TOTAL QUANTITY A-B 1815.00 SFT

4

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

Page 20: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 20 of 30

SAME AS QUANTITY OF PLASTER 5000.00 1.00 1.00 1.00 5000.00 SFT

TOTAL QUANTITY Total 5000.00 SFT

5

Providing layer of mud on bounadary wall and mud brick work where requried as per instruction of engineer

NSR

BOUNDARY WALL 1 300 1.00 1.00 7.00 2100.00

Total 2100.00 Cft

6

Construction of mud wall with mud brick work in mud motor and plaster on both sides as per instruction of engineer

NSR

CLASS ROOM 1 1 5.00 12.00 1.00 60.00

Total 60.00 Cft

RFP 19021 ANNEX B-22

SURKHAB - BOYS MIDDLE SCHOOL NO 8

BILL OF QUANTITIES

GROUND FLOOR ESTIMATE

S. No DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

4

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF PLASTER 2000.00 2000.00 SFT

TOTAL QUANTITY Total 2000.00 SFT

5 Provding and layin mud plaste on front side of school as per engineer isntruction

NSR

BOUNDARY WALL 1 120 1.00 1.00 7.00 840.00

Total 840.00 Cft

Page 21: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 21 of 30

RFP 19021 ANNEX B-23

SURKHAB - MIDDLE SCHOOL NO 9 CO EDUCATION

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

BATH ROOM 6 2 7.00 5.00 7.00 1008.00 SFT

TOTAL QUANTITY A-B 1008.00 SFT

4 Providing and laying of instllation of BamBo with complet work

NSR

Bam Bo 5" Dia 25 25.00

Total 25.00 no

5

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF PLASTER 5000.00 5000.00 SFT

TOTAL QUANTITY Total 5000.00 SFT

Construction of two mud stuctre toilets with 20 feet pits and covering material with Bamboo and sheet with mut plaster

NSR

BATH ROOM COMPLET 2 6 5.00 2.00

Total 2.00 Cft

Page 22: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 22 of 30

RFP 19021 ANNEX B-24

SURKHAB - PRIMARY SCHOOL NO 10

BILL OF QUANTITIES

GROUND FLOOR ESTIMATE

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

1

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF 1 1 130.00 15.00 0.33 643.50 CFT

TOTAL QUANTITY A-B 643.50 SFT

4

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF PLASTER

3704.00 1.00 1.00 1.00 3704.00 SFT

TOTAL QUANTITY Total 3704.00 SFT

5

Construction of mud wall with mud brick work in mud motor and plaster on both sides as per instruction of engineer

NSR

BOUNDARY WALL 1 35 1.00 1.00 8.00 280.00

Total 280.00 Cft

RFP 19021 ANNEX B-25

SURKHAB - SCHOOL CO EDUCATION NO 11

BILL OF QUANTITIES

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

1

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF 1 1 80.00 15.00 0.33 396.00 CFT

Page 23: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 23 of 30

19 mm THICK PLASTER ON WALL

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 1.00 31.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

CLASS ROOM 1 1 19.00 12.00 10.00 310.00 SFT

BATH ROOM 1 2 7.00 5.00 9.00 216.00 SFT

19 mm THICK PLASTER ON WALL

FRONT WALLS 1 1 90.00 7.00 630.00 SFT

RIGHT SIDE WALLS 1 1 110.00 7.00 770.00 SFT

BACK WALLS 1 1 90.00 7.00 630.00 SFT

LEFT SIDE WALLS 1 1 110.00 7.00 770.00 SFT

TOTAL 5303.00 SFT

sub total A 5303.00 SFT

DEDUCTION DOOR/WINDOW

Ded: Doors D1 7 1 3.00 6.00 126.00 SFT

Ded: Win: W1 14 1 4.00 5.00 280.00 SFT

sub total B 406.00 SFT

TOTAL QUANTITY A-B 4897.00 SFT

2 Providing and laying of instllation of BamBo with complet work

NSR

Bam Bo 5" Dia 4 4 4.00 Rft

Total 4.00 Rft

3

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF

PLASTER

4897.00 4897.00 SFT

TOTAL QUANTITY Total 4897.00 SFT

Page 24: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 24 of 30

RFP 19021 ANNEX B-26

SURKHAB - HIGH SCHOOL NO 49

BILL OF QUANTITIES

GROUND FLOOR ESTIMATE

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

1

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF 1 1 130.00 20.00 0.33 858.00 CFT

TOTAL QUANTITY A-B 858.00 SFT

2

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

BOTH SIDES

NSR

White Wash

SAME AS QUANTITY OF PLASTER

3462.00 1.00 1.00 1.00 3462.00 SFT

TOTAL QUANTITY Total 3462.00 SFT

3

Providing layer of mud on bounadary wall and mud brick work where requried as per instruction of engineer

NSR

BOUNDARY WALL 1 700 1.00 1.00 7.00 4900.00

Total 4900.00 Cft

Page 25: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 25 of 30

RFP 19021 ANNEX B-27

SARANAN - REPAIR OF COEDUCATION HIGH SCHOOL GAZGI NO 12 NEW CAMP OF SRANAN

BILL OF QUANTITIES

S. No DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

Rooof layer 1 1 200.00 20.00 4000.00 SFT

TOTAL QUANTITY A-B 4000.00 SFT

3

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

NSR

SAME QTY OF PLASTER 3/4" 4000.00 SFT

TOTAL QUANTITY 4000.00 SFT

4 Providing and laying of wood replacement of bamboo incoulding all work

NSR

Bamboo

1 1 25.00 25.00

TOTAL QUANTITY 25.00 NO

Page 26: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 26 of 30

RFP 19021 ANNEX B-28

SARANAN - REPAIR OF GIRLS PRIMARY SCHOOL NO 14 NEW CAMP OF SRANAN

BILL OF QUANTITIES

GROUND FLOOR

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF PLASTER

Room No 1 1 1 14.00 20.00 280.00 SFT

Room No 2 1 1 14.00 20.00 280.00 SFT

Room No 3 1 1 14.00 20.00 280.00 SFT

Room No 4 1 1 14.00 20.00 280.00 SFT

Room No 5 1 1 14.00 20.00 280.00 SFT

Room No 6 1 1 14.00 20.00 280.00 SFT

Room No 7 1 1 14.00 20.00 280.00 SFT

Room No 8 1 1 80.00 20.00 1600.00 SFT

TOTAL QUANTITY A-B 3560.00 SFT

3

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

NSR

SAME QTY OF PLASTER 3/4" 5000.00 SFT

TOTAL QUANTITY 5000.00 SFT

Page 27: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 27 of 30

RFP 19021 ANNEX B-29

SARANAN - REPAIR OF BOYS HIGH SCHOOL NO 15 OLD CAMP OF SRANAN

BILL OF QUANTITIES

GROUND FLOOR

S. No DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

Roof layer 1 1 400.00 20.00 8000.00 SFT

TOTAL QUANTITY A-B 8000.00 SFT

3

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

NSR

SAME QTY OF PLASTER 3/4" 8000.00 SFT

TOTAL QUANTITY 8000.00 SFT

RFP 19021 ANNEX B-30

SARANAN - REPAIR OF BOYS HIGH SCHOOL NO 13 OLD CAMP OF SRANAN

BILL OF QUANTITIES

S. No DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF PLASTER

Room No 1 1 1 14.00 20.00 280.00 SFT

Room No 2 1 1 14.00 20.00 280.00 SFT

Room No 3 1 1 14.00 20.00 280.00 SFT

Page 28: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 28 of 30

Room No 4 1 1 14.00 20.00 280.00 SFT

Room No 5 1 1 14.00 20.00 280.00 SFT

Room No 6 1 1 14.00 20.00 280.00 SFT

Room No 7 1 1 14.00 20.00 280.00 SFT

TOTAL QUANTITY A-B 1960.00 SFT

3

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

NSR

SAME QTY OF PLASTER 3/4" 5000.00 SFT

TOTAL QUANTITY 5000.00 SFT

RFP 19021 ANNEX B-31

SARANAN - REPAIR OF GIRLS PRIMARY SCHOOL NO 16 NEW CAMP OF SRANAN

BILL OF QUANTITIES

GROUND FLOOR

S. No

DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

1

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF PLASTER

Room No 1 1 1 14.00 20.00 280.00 SFT

Room No 2 1 1 14.00 20.00 280.00 SFT

Room No 3 1 1 14.00 20.00 280.00 SFT

Room No 4 1 1 14.00 20.00 280.00 SFT

Room No 5 1 1 14.00 20.00 280.00 SFT

Room No 6 1 1 14.00 20.00 280.00 SFT

Wall palster 1 1 150.00 10.00 1500.00 SFT

TOTAL QUANTITY A-B 3180.00 SFT

Page 29: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 29 of 30

2

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

NSR 0.00

SAME QTY OF PLASTER 3/4" 5000.00 SFT

TOTAL QUANTITY 5000.00 SFT

RFP 19021 ANNEX B-32

SARANAN - REPAIR OF HIGH SCHOOL NO 23 NEW CAMP OF SRANAN

BILL OF QUANTITIES

S. No DESCRIPTION No MEASUREMENT

QTY UoM L B H/D

2

Providing and filling earth over roof including watering, ramming, mud plastering with gobri leaping 3 inch thick earth filling and mud plaster /Mud Layer

NSR

ROOF PLASTER

Room No 1 1 1 14.00 20.00 280.00 SFT

Room No 2 1 1 14.00 20.00 280.00 SFT

Room No 3 1 1 14.00 20.00 280.00 SFT

Room No 4 1 1 14.00 20.00 280.00 SFT

Room No 5 1 1 14.00 20.00 280.00 SFT

Room No 6 1 1 14.00 20.00 280.00 SFT

Room No 7 1 1 14.00 20.00 280.00 SFT

Room No 8 1 1 14.00 20.00 280.00 SFT

Room No 9 1 1 70.00 20.00 1400.00 SFT

TOTAL QUANTITY A-B 3640.00 SFT

3

White washing three coats including dusting, filling the holes, cracks and removing inequalities, if any,windows and ventaltors at any height in any floor

Page 30: ANNEX B BILL OF QUANTITIES (BoQs) RFP/19/021...ISO 4427, PN-20, complete in all respects with specials and valves etc. including all fittings, connnections and jointing material.exust

ANNEX B – BILL OF QUANTITIES (BoQs) RFP/19/021

Page 30 of 30

NSR

SAME QTY OF PLASTER 3/4" 3640.00 SFT