+ All Categories
Home > Documents > ANNEXES ATTACHED TO RP

ANNEXES ATTACHED TO RP

Date post: 18-Mar-2022
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
24
1 ANNEXES ATTACHED TO RP ANNEX 1 CLASSIFICATION OF AFFECTED LAND - THAN GIAP HPP .................................2 ANNEX 2 PROJECT INFORMATION CENTER (PIB)...................................................................3 ANNEX 3 TERMS OF REFERENCE FOR EXTERNAL MONITORING CONSULTANT ........7 ANNEX 4 CONSULTATION MEETING MINUTES......................................................................13 SFG2158 V7 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript

1

ANNEXES ATTACHED TO RP

ANNEX 1 CLASSIFICATION OF AFFECTED LAND - THAN GIAP HPP ................................. 2

ANNEX 2 PROJECT INFORMATION CENTER (PIB) ................................................................... 3

ANNEX 3 TERMS OF REFERENCE FOR EXTERNAL MONITORING CONSULTANT ........ 7

ANNEX 4 CONSULTATION MEETING MINUTES ......................................................................13

SFG2158 V7

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

2

ANNEX 1 CLASSIFICATION OF AFFECTED LAND - THAN GIAP HPP

No. Item Total affected

area (m2)

The number

of AHHs

Land for

rice

Land for

annual

crops

Forest land River land

1 Permanently affected land: 351,251.6 2,987.7 3,171.1 235,549.2 109,543.6

Reservoir area 149,742.0 12 0.0 0.0 76,368.4 73,373.6

Headwork dam 83,832.2 10 740.6 0.0 53,891.9 29,199.7

Canal 36,828.3 22 744.2 422.8 35,661.3 0.0

Factory, discharge canal 28,137,8 7 1,502.9 744,1 18,920,5 6,970,3

Factory, distribution station, operation

management building 26,880,0 5 0.0 578,1 26,301,9 0.0

Site road to manage the operation 25,831,3 21 0.0 1,426,1 24,405,2 0.0

2 Temporarily affected land: 63,373,2 0.0 226.6 52,874,3 10,272.3

Auxiliary works, camp, production

area 15,778.2 6 0.0 226.6 15,551.6 0.0

Dug soil and rock storage area 47,595,0 13 0.0 0.0 37,322.7 10,272.3

Total 414,624.8 2,987.7 3,397.7 288,423.5 119,815.9

3

ANNEX 2 PROJECT INFORMATION CENTER (PIB)

MINISTRY OF INDUSTRY AND

TRADE

TRUONG MINH LIMITED COMPANY

SOCIALIST REPUBLIC OF VIETNAM

Independence - Freedom - Happiness

PROJECT INFORMATION CENTER

THAN GIAP HYDROPOWER PLANT

Cao Bang province

Introduction about Than Giap Hydropower Plant

Than Giap Hydropower Plant is a new construction project on the tributary of Bac

Vong river in the area of Than Giap commune, Trung Khanh district and An Lac

commune, Ha Lang district, Cao Bang province. It is far around 70km away from Cao

bang city, and 12km away from Trung Khanh town in the South.

Bac Vong River originates from China and flows into Vietnam in Tri Phuong

Commune, Tra Linh District, Cao Bang Province. The total length of the river is about

35 kilometers, the width is from 20 to 30m. Water flow varies by the seasons: in the

rainy season, the flow is 85m3/s, in the dry season, the flow is 5 m3/s. The main source

of this river flows from China, through Tri Phuong and Quang Trung Communes in Tra

Linh district, and then Trung Phuc, Thong Hue, Than Giap communes in Trung Khanh

district, An Lac commune in Ha Lang district, Hong Dai and Trieu Au communes in

Phuc Hoa district and then merges with Bang river in Ta Lung town, Phuc Hoa district,

Cao Bang province.

Geographical location of the project area:

+ Geographical coordinates of the dam: 22o44'09 '' North latitude 106

o32’43’’

East longitude.

+ Geographical coordinates of the plant: 22o43’19’’ North latitude 106

o33’51’’

East longitude.

Installation capacity of Than Giap hydropower plant is 6 MW, average annual output

is approximatetly 21.49 million kWh, is diversion hydropower plant with daily regulated

reservoir. The main specifications are: catchment area to the slected route: 496.8 km2,

total average annual flow is Qo: 8.93 m3/s; reservoir area at normal water level is 8 ha;

normal water level is 465m; dead water level is 460m; volume of the whole reservoir is

0.702 x106m3; useful volume is 0.285x106m3; dead volume is 0.416 x106 m3; the

largest flow Qmax: 14.10 m3/s; ensure flow is Q đb: 0.94 m3/s, output voltage is 35 kV.

The project shall be implemented for 2.5 years, open in June 2016 and complete in

the second quarter of 2018.

Truong Minh Limited Company is responsible for construction, management and

operation of the plant. Funding source for the project implementation is from World

Bank (WB).

4

Necessary scope to recover land and other assets for the project. According to

inventory of loss (IOL), there is 351,251.4m2 land of many types that are affected

permanently, 63,373.2 m2 is affected temporarily. No damage of house, no household has

to replace.

What will happen to the households losing property and livelihoods? Affected people

will be compensated in cash at replacement cost for land and assets on land (eg, trees,

crops...) along with other supports, including support for livelihood recovery based on

the impact level.

The benefits of households affected by the project? After considering the factors

affecting the market price, replacement cost calculations for compensation of land and

property on the land, Cao Bang PPC issued Decision No. 40/2014 / QD-Committee

December 19, 2014 about the issuance of price list for land in Cao Bang province.

Table 1 –Summary of benefits from the project

Stt Loại tác động Chính sách

1 Loss in

income/livelihood

due to land lost

Allowances for stabilizing livelihood and job creation

Assistance equal to 5 times of agricultural land price for entire

acquired land – regardless the rate of land loss (area to get

assistance is not exceeded local land handing limit).

Assistance to HHs whose total area of agricultural land is

acquired from 0% to 10% is equal to 3 months in case of non-

relocation, 6 months in case of relocation). Assistance in cash is

equal to 30kg of rice /member/month. Assistance is provided

for 6 months basis. Further assistance to HHs whose total area

of agricultural land is acquired from 10% to 70% is equal to 6

months in case of non-relocation, 24 months in case of

relocation; whose total area of acquired agricultural land is

more than 70% is equal to 12 months in case of non-relocation

and 36 months in case of relocation. Assistance in cash is equal

to 30kg of rice /member/month. Assistance is provided for 6

months basis.

Compensated by land.

Affected HHs are compensated in land, assistant rate for

production is VND5,000,000/labor, for the HHs with more than

one at working age, the second one onward will get the

assistance of VND2,000,000/labor.

2 Lose house, must

replace

Material Transportation assistance

Di chuyển trong tỉnh không quá 20 km, được hỗ trợ 3.000.000

VNĐ/hộ

Di chuyển trong tỉnh cự ly trên 20km được hỗ trợ 5.000.000

VNĐ/hộ

Di chuyển sang tỉnh khác, nếu đến các tỉnh miền Bắc được hỗ trợ

5

Stt Loại tác động Chính sách

8.000.000 VNĐ/hộ, nếu đến các tỉnh miền Trung và miền Nam

được hỗ trợ 10.000.000 VNĐ/hộ

Move no more than 20 km in the province: assist 3,000,000

VND / HH

Move more than 20km in the province: assist 5,000,000 VND /

HH

Move to another province, to the northern provinces: assist

8,000,000 VND/ household, to the southern provinces and

Central province: assit 10 million VND /HH

House leasing assistance

House leasing assistance in cash includes: (i) for HH with 5 and

less than 5 members: VND 800,000 /month; (ii) for HH with

more than 5 members: VND 1,000,000/month; and single

member HH: VND 600,000 /month.

Period of time to get assistance is from land handing to the

investor to receive land for resettlement.

Assistance to house leasing HHs

Relocation assistance fee: VND 2,000,000 /HH and transition

subsistence allowance in cash equal to 30kg of rice/member/month

for 3 month period.

3 Loss of income/

livelihood due to

relocation of

business

Economic organizations, family business enterprises with

registered industries are to stop production due to land

acquisition for the project, they are entitled to get assistance

equivalent to 30% of 1 year’s income after taxes, calculated

according to the average income level for last three years.

4 Assistance for

vulnerable groups

Local policies on families are entitled to social assistance when

the State acquires land and relocate

The revolutionary activists prior to 1945, Hero of the People's

Armed Forces, Vietnam heroic mother, Labor Hero, relatives

of martyrs receiving monthly assistance, invalids, sick soldiers,

social policy beneficiaries such as war invalids losing 81%

onward of labor is assisted with 5,000,000 VND/householder

Invalids and policy beneficiaries such as war invalids and sick

soldiers losing 61% to 80% of labor is assisted with

4,000,000VND / householder

Invalids and policy beneficiaries such as war invalids and sick

soldiers losing 11% to 60% of labor is assisted with

3,000,000VND / householder

Invalids and policy beneficiaries such as war invalids and sick

soldiers losing 21% to 40% of labor is assisted with

2,000,000VND / householder

The people awarded Feat Order Grade I, Victory Order Grade I

are assisted with 1,000,000 VND/ householder

Familywhose members are entitled to social benefits and other

State support is assisted with 2,000,000 VND / HH

6

Stt Loại tác động Chính sách

Assistance policy of the project

(i) Assistance for job transformation (Working at the factory)

and (ii) recovery of income by livestock technical training

Grievance and grievance redress mechanism.

Grievances related to any aspect of Than Giap Hydropower project will be handled through

negotiation aimed at achieving consensus. (i) Stage 1: At commune level, the APs will address

the complaint to the reception office of CCP for guidelines on necessary procedure. CCP will

work with the APs and CCP has 30 days after receiving the complaint to solve. CCP is

responsible for documenting and storing documents on all complaints that it handles.

When CPC makes a decision that the household can appeal within 30 days. If the second

decision has been issued and the household is still not satisfied with the decision, they can

appeal to District People’s Committee (DPC). (ii) Stage 2: At district level: Upon receipt of

complaint from the household, the DPC will have 30-45 days after receiving the complaint to

resolve the case. DPC is responsible for documenting and storing documents on all complaints

that it handles. When DPC makes decision, households can appeal within 30 days. If the second

decision has been issued and the household is still not satisfied with the decision, they can

appeal to the PPC. (iii) Stage 3: At provincial level: Upon receipt of complaint from the

household, PPC will have 30 - 45 days after receiving the complaint to resolve the case. PPC is

responsible for documenting and storing documents on all complaints that it handles. When

PPC DPC makes decision, the households can appeal within 30 days. If the second decision has

been issued and the household is still not satisfied with the decision, they can appeal to the

court within 45 days. (iv) Stage 4: Civil Court: If the APs submit the case to the court and the

court’s decision to side with the APs, provincial government will have to increase the

compensation as much as the level decided by the court. In case the court sided with PPC, the

APs will be refunded with the amount paid to the court.

Where can AHHs get more information related to resettlement?

The RP with the detail about benefits, the compensation unit price is published in the media of

the CPC, and district and Truong Minh Limited Company.

Who we can contact for more information about the project?

Mr.………………………..Position………………………………Tel:-----------------

(Representative of Compensation Committee of Trung Khanh district).

Mr.………………………..Position………………………………Tel:-----------------

(Representative of Compensation Committee of Ha Lang district).

Mr.………………………..Position………………………………Tel:-----------------

(Representative of Truong Minh Limited Company).

7

ANNEX 3 TERMS OF REFERENCE FOR EXTERNAL MONITORING

CONSULTANT

TERMS OF REFERENCE FOR EXTERNAL MONITORING CONSULTANCY OF

RESETTLEMENT

I. Introduction

1. The general objective of the Renewable Energy Development Project is to support the

development of renewable energy sources producing electricity with lowest costs in sharing

with the national total electricity generation under commercial sustainability and ensuring

social and environmental sustainability.

2. Than Giap Hydropower Plant is a new construction project on the tributary of Bac

Vong river in the area of Than Giap commune, Trung Khanh district and An Lac commune,

Ha Lang district, Cao Bang province. It is far around 70km away from Cao bang city, and

12km away from Trung Khanh town in the South.

3. Bac Vong River originates from China and flows into Vietnam in Tri Phuong

Commune, Tra Linh District, Cao Bang Province. The total length of the river is about 35

kilometers, the width is from 20 to 30m. Water flow varies by the seasons: in the rainy

season, the flow is 85m3/s, in the dry season, the flow is 5 m3/s. The main source of this

river flows from China, through Tri Phuong and Quang Trung Communes in Tra Linh

district, and then Trung Phuc, Thong Hue, Than Giap communes in Trung Khanh district,

An Lac commune in Ha Lang district, Hong Dai and Trieu Au communes in Phuc Hoa

district and then merges with Bang river in Ta Lung town, Phuc Hoa district, Cao Bang

province.

4. Geographical location of the project area:

5. + Geographical coordinates of the dam: 22o44'09 '' North latitude 106

o32’43’’ East

longitude.

6. + Geographical coordinates of the plant: 22o43’19’’ North latitude 106

o33’51’’ East

longitude.

7. Installation capacity of Than Giap hydropower plant is 6 MW, average annual output

is approximatetly 21.49 million kWh, is diversion hydropower plant with daily regulated

reservoir. The main specifications are: catchment area to the slected route: 496.8 km2, total

average annual flow is Qo: 8.93 m3/s; reservoir area at normal water level is 8 ha; normal

water level is 465m; dead water level is 460m; volume of the whole reservoir is 0.702

x106m3; useful volume is 0.285x106m3; dead volume is 0.416 x106 m3; the largest flow

Qmax: 14.10 m3/s; ensure flow is Q đb: 0.94 m3/s, output voltage is 35 kV.

8. This resettlement plan is prepared to ensure that: (i) Involuntary resettlement must be

avoided where possible, or be reduced to the lowest possible extent by selecting appropriate

design options, (ii) Where involuntary resettlement is unavoidable, the resettlement

activities must be prepared and executed with sustainable development programs and

sufficiently provided investment supports, enabling displaced people to benefit from the

subproject. The displaced people will be fully consulted and allowed to participate in

preparing and implementing activities in Resettlement Plan.

II. Objectives

9. The general objective of the external monitor is to provide a third party periodic

review and assessment of:

(i) Resettlement activities, including:

- Achievement of resettlement objectives;

8

- Changes in living standards and livelihoods;

- Restoration of the economic and social base of the affected people;

- Effectiveness, impact and sustainability of entitlements and income restoration

programs; and

- Strategic lessons for future policy formulation and planning will also be drawn from

the monitoring and evaluation of resettlement;

(ii) The issues relevant to development for ethnic minority groups:

- How are the mitigation measures proposed and implemented;

- Is there any other negative impace on ethnic minorities that have not been evaluated,

not identified mitigation measures;

- How are the Community Development Supports for ethnic minorities set and

implemented;

- Is the information provided adequately, is the consultation process with ethnic

minorities implemented or implement effectively or not; and

- The grievance redress process about the development plan for ethnic minorities and

other issues that they are facing.

III. Approaches

10. The methods for external monitoring and evaluation of land acquisition, compensation

and resettlement activities include:

- Review of Detailed Measurement Survey (DMS): As soon as the detailed design is

finalized and staked to the ground by Truong Minh Limited Company and CARB,

data collection from all APs to establish their eligibility and entitlements will be

carried out. The data that will be entered into a database to document the following:

a) socio-economic status of affected households; b) nature and extent of losses; and

c) entitlements to compensation and other assistance. These data will be made

available to the EMA, to enable them to establish a baseline for monitoring and

evaluating project benefits. During the conduct of the DMS, the EMA will also

monitor the DMS process to determine and assess if DMS activities are being

carried out in a participatory and transparent manner

- Socio-Economic Survey (SES): The SES is designed to provide a clear comparison

of the success and/or failure of the resettlement program to restore their livelihoods

and living standards. In general, if a lag of 3-5 years or more occurs between census

and SES and actual land acquisition, demographic and socio-economic factors may

change significantly. In this Project, if land acquisition is not carried out within two

years after SES, Truong Minh Limited Company and CARBs will carry out another

SES. A post resettlement survey will also be undertaken by the EMA 6-12 months

following completion of resettlement activities. Special attention will be paid to the

inclusion of women, ethnic groups, the very poor, the landless and other vulnerable

groups, with set questions for women and other target groups; and, the database

disaggregates information by gender, vulnerability and ethnicity.

- Participatory rapid appraisals (PRA): The PRA will involve obtaining information,

identifying problems and finding solutions through participatory means including: a)

key informant interviews; b) focus group discussions on specific topics such as

compensation payment, income restoration and relocation; c) community public

meetings to discuss community losses, integration of resettled households in host

communities or construction work employment; d) structured direct field

observations, for example, of resettlement site development; e) formal and informal

9

interviews with affected households, women, ethnic minority, and other vulnerable

groups; and, f) in-depth case studies of problems are identified by internal or

external monitoring and required special efforts to resolve

- Verification of Replacement cost survey: The EMA will also verify whether

compensation paid were at replacement cost. A special market study to validate

whether the rates used in compensation in land and other non-land assets were at

replacement cost will be undertaken.

IV. Capacity requirements to external monitoring agency (EMA)

11. External monitoring agency is a unit who is capable and experienced in the field of

resettlement and social development or ethnic minority. External monitoring agency is

established from those who have experience of implementing monitoring of resettlement,

social and ethnic minority development projects funded by ADB, World Bank, and JICA.

They must have a University degree/postgraduate (social sciences or related field), with at

least 5 years experience in preparation and implementation of resettlement plans,

development plans for EM and can use English very well (writtingn and read).

V. Report

12. The external monitoring agency or EMA, conducted by an experienced resettlement

and social development consultant and selected by PMU (under MOIT). External

monitoring, inspection and evaluation will be made on a yearly basis, except for the first

stage, it is requested to be made twice/year. All external monitoring reports will be made

available to the affected households by placing reports in the commune / ward and field

offices and will be uploaded on WB website. Table 1 and Table 2 below describe

Monitoring and Evaluation Indicators for implementation of resettlment pland and ethnic

minority development plan.

Table 1 Monitoring and Evaluation Indicators for RP

Type Indicator Examples of Variables

Process

Indicators

(By district

and

commune)

Staffing The number Truong Minh Limited Company staff and

field staff on Project assigned by job function; and

The number of other line agency officials available for

tasks

Consultation,

Participation and

Grievance

Resolution

The number of consultation and participation programs

held with various stakeholders;

Separate consultation with women (Kinh), female headed

households and ethnic minority women;

Grievances by type and resolution;

The number of field visit by EPMU staff; and

The number of local organizations participating in project

Procedures in

Operation

Review of DMS , including verification/quantification

procedures in place and effectiveness of compensation

delivery system;

The number of land transfer taking effect; and

10

Type Indicator Examples of Variables

Coordination among Than Giap HHP, relevant provincial

departments, and provincial and district officials,

Output

Indicators

(By district

and

commune)

Acquisition of

Land

Area of productive land assets acquired (crop land,

aquaculture ponds, garden land, etc.);

Area of residential and other non-agricultural lands

acquired;

Area of communal/government lands acquired; and

Area of other lands acquired.

Structures Quantity, type and size of private structures acquired;

Quantity, type and size of community structures acquired;

and

Quantity, type and size of government structures acquired.

Trees and Crops Quantity and type of private crops and trees acquired;

Quantity and type of government/community crops and

trees acquired; and

Destroyed crops by area, type and the number of owner.

Compensation and

resettlement

The number of household affected (for land, buildings,

trees, crops);

The number of owner compensated by type of loss;

Amount compensated by type and owner;

Quantity and amount of allowances paid;

The number of replacement houses constructed by

concerned owners;

The number of replacement business constructed by

concerned owners;

The number of owner requesting assistance to purchase

replacement land, and the number of successful purchase;

The number of individual site and levels of development

of sites;

The number of entitlement delivered;

The number of entitlement used by APs;

Suitability of entitlements to affected households as per

RP objectives;

The number of non-titled AHH receiving replacement

land; and

The number of severely affected, very poor or other

vulnerable household receiving special assistance and

participating in income restoration programs.

Impact

Indicators

(by district

Household

Earning Capacity

Employment status of economically active members;

Landholding size, area cultivated and production volume,

11

Type Indicator Examples of Variables

and

commune)

by crop;

Selling of cultivation land;

Changes to livestock ownership – pre- and post

disturbance;

Changes to income-earning activities (farm and off-farm)

– pre- and post disturbance; and

Amount and balance of income and expenditures.

Changes to Status

of Women

Commune/Village Resettlement Committees include

Women’s Union and Women from affected households;

Involvement of women in the process of preparation of

IOL;

The number of grievance complaint filed by women and

resolution

The number of woman (including female headed

households and ethnic minority women) negotiated

compensation effectively;

Joint registration of land in the name of husband and wife;

The number of meeting held by women from affected

households in planning of livelihood activities;

The number of woman engaged in gainful livelihood

activities/income earning activities/employment in

Industrial zones (including female headed households and

ethnic minority women);

The number of woman participated in capacity building

workshop/ training;

The number of woman understand the process of

resettlement activities (entitlement, compensation process,

etc);

The number of woman participated in discussion of

resettlement site selection;

Participation in commercial enterprises; and

Participation in community decision-making

Changes to Status

of Children

School attendance rates (male/female); and

Participation in plant construction.

Settlement,

Community and

Population

Growth in number and size of settlements;

Growth in market areas;

Influx of new settlers, including those with and without

land rights;

Changes in economic activities and income-generation

opportunities; and

Changes in social, cultural and community conditions.

12

Table 2 Monitoring and Evaluation Indicators for EMDP

Monitoring and Evaluation

Issues

Basic indicators

1. The progress of EMDP

implementation

- The plan has been shared with the community.

- The plan is in line with the implementation conditions

of ethnic minority people and is joined by them.

- The plan is relevant to the progress of other activities.

- Adequate human resources available to implement the

plan.

- Sufficient funding for implementing the plan.

2. Implementing community

consultations and local people’s

participation

- Local EM community, commune authorities and

village leaderships and mass organizations are provided

sufficient information on EMDP, implementation plan

and grievance mechanisms.

- Local EM community, commune authorities and

village leaderships and mass organizations are involved

in relevant activities, especially monitoring the

implementation of EMDP.

3. Implementation of measures

to mitigate negate impacts from

the facility.

- All measures for mitigating negative impacts from the

facility are effectively implemented.

- There are no additional negative impacts arising from

the facility, and if otherwise, there must be a community

consultation on mitigation measures and implementation

of the same.

- Various sectors and branches effectively collaborate in

implementing measures to mitigate negative impacts

from the facility.

4. Implementation of specific

developmental interventions for

local ethnic minority people

- All activities that support the EM development as set

out in the EMDP are implemented effectively.

- Various sectors and branches effectively collaborate in

implementing interventions for community development.

5. Grievance Mechanisms - Ethnic minority community has a clear understanding

of the grievance mechanism.

- District Resettlement Compensation Committee,

commune-level social organizations and commune

people’s committee have a clear understanding of

grievance mechanism and are able to assist EM people to

implement such mechanisms.

13

ANNEX 4 CONSULTATION MEETING MINUTES

14

15

16

17

18

19

20

21

22

ANNEX 5 SOME PHOTOS OF CONSULTATION

Than Giap Communal People’s

Committee

Consultant meeting in Than Giap commune

Doai Con Communal People’s Committee Consultant meeting in Doai Con commune

23

An Lac Communal People’s Committee

24

Consultant meeting in An Lac commune


Recommended