ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for
Extended Loss of AC Power Event
Technical Report
November 2014
AREVA Inc.
(c) November 2014 AREVA Inc.
Copyright © November 2014
AREVA Inc. All Rights Reserved
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page i
Nature of Changes
Rev Section(s) or Page(s) Description and Justification
000 All Initial Issue 001 All Miscellaneous editorial changes (e.g. Changed “secondary side
feed and bleed cooling” to “primary to secondary heat transfer” throughout).
001 2.1 In Item 1, established that containment pressure and temperature will remain below containment design basis limits. Clarified Item 2 (SG depressurization) and deleted Item 3.
001 3.7 – 3.9 Added statement that Recommendation 7.2 is satisfied through compliance with EA-12-049 in accordance with COMSECY-13-0002.
001 4.1.3 Analytical Bases revised to summarize core cooling in Modes 1 to 5 with steam generators (SGs) available and core cooling in Modes 5 and 6 with SGs unavailable. Cooldown is with four SGs for first six hours when SGs are available.
001 4.1.3 Added Table 4–2 which summarizes breakdown of operating modes, analyses performed, initial conditions, and operator actions. Lower mode initial conditions include low temperature overpressure protection (LTOP) enabled and no credit for accumulators.
001 4.1.3 Increased discharge head of Primary Coolant Injection Pump (PCIP).
001 4.1.3.4 Deleted containment venting strategy. Revised discussion on containment heat removal.
001 4.1.3.5 Updated Safeguard Buildings Heatup analyses. 001 4.1.3.8 Updated Spent Fuel Pool time to boil analysis. 001 4.1.4 Clarified and updated Reasonable Protection requirements. 001 4.1.5 Revised simplified diagrams and updated FLEX summary
tables. 001 4.1.5 Revised electrical distribution system from ELAP DG. 001 4.1.5 Added discussion of mitigation strategies in all plant modes. 001 4.1.5 Deleted mitigation strategy for containment venting. Revised
discussion on mitigation strategy for containment heat removal. 001 4.1.5.1 Added list of ELAP diesel generator loads. 001 4.1.5.6 Updated Instrumentation and Controls. 001 4.1.6 Updated Sequence of Event tables. 001 4.1.7 Updated portable equipment performance requirements and
added performance requirements for safety related and non-safety related components used in mitigation strategy.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page ii
Rev Section(s) or Page(s) Description and Justification
001 4.2 Deleted Section 4.2.2, “NTTF 7.3, Plant Technical Specification,” and Section 4.2.3, “NTTF 7.4, Seismically Qualified Spent Fuel Pool Spray System.”
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page iii
Contents
Page
1.0 INTRODUCTION ............................................................................................... 1-1
1.1 Description of Fukushima Daiichi Accident ............................................. 1-2
1.2 Purpose .................................................................................................. 1-2
2.0 REGULATORY OVERVIEW.............................................................................. 2-1
2.1 NRC Order EA-12-049, Interim Staff Guidance JLD-ISG-2012-01, and NEI 12-06, Revision 0 ....................................................... 2-3
2.2 NRC Order EA-12-051, Interim Staff Guidance JLD-ISG-2012-03, and NEI 12-02, Revision 1 ....................................................... 2-5
3.0 APPLICABLE TIER 1 AND TIER 2 RECOMMENDATIONS .............................. 3-1
3.1 NTTF Recommendation 2.1, Tier 1 ........................................................ 3-1
3.2 SECY-12-0025, Enclosure 3 Recommendation, Tier 2 ........................... 3-2
3.3 NTTF Recommendation 4.1, Tier 1 ........................................................ 3-2
3.4 NTTF Recommendation 4.2, Tier 1 ........................................................ 3-2
3.5 SECY-12-0025, Enclosure 2 Recommendation, Tier 1 ........................... 3-3
3.6 NTTF Recommendation 7.1, Tier 1 ........................................................ 3-3
3.7 NTTF Recommendation 7.2, Tier 2 ........................................................ 3-3
3.8 NTTF Recommendation 7.3, Tier 2 ........................................................ 3-4
3.9 NTTF Recommendation 7.4, Tier 2 ........................................................ 3-4
3.10 NTTF Recommendation 8, Tier 1 ........................................................... 3-4
3.11 NTTF Recommendation 9.3 .................................................................... 3-5 3.11.1 Tier 1 Recommendations ............................................................. 3-5 3.11.2 Tier 2 Recommendations ............................................................. 3-5
4.0 MITIGATION ASSESSMENT ............................................................................ 4-1
4.1 NTTF 4.2, Mitigation of Beyond Design Basis External Events ..................................................................................................... 4-1 4.1.1 Overview ...................................................................................... 4-1 4.1.2 Acceptance Criteria ...................................................................... 4-2 4.1.3 Analytical Bases ........................................................................... 4-3 4.1.4 Reasonable Protection of Installed and Portable
Equipment .................................................................................. 4-65 4.1.5 Mitigation Strategies ................................................................... 4-70 4.1.6 Sequence of Events/Critical Operator Actions ......................... 4-121
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page iv
4.1.7 Functional Performance Requirements for Key Equipment ................................................................................ 4-147
4.2 NTTF 7.1, Safety-Related Spent Fuel Pool Level Instrumentation ................................................................................... 4-154 4.2.1 Overview .................................................................................. 4-154 4.2.2 Conformance............................................................................ 4-154 4.2.3 Arrangement ............................................................................ 4-155 4.2.4 Qualification ............................................................................. 4-155 4.2.5 Power Supplies ........................................................................ 4-156 4.2.6 Accuracy .................................................................................. 4-156 4.2.7 Display ..................................................................................... 4-156 4.2.8 Training .................................................................................... 4-157
4.3 NTTF 9.3, Enhanced Emergency Preparedness ................................ 4-157 4.3.1 Overview .................................................................................. 4-157 4.3.2 Conformance............................................................................ 4-157
5.0 REFERENCES .................................................................................................. 5-1
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page v
List of Tables
Table 4–1—Mitigation Strategy Acceptance Criteria .................................................... 4-2
Table 4–2—ELAP States ............................................................................................. 4-6
Table 4–3—Reasonable Protection of ELAP Event Mitigation Equipment ................. 4-69
Table 4–4—ELAP Loads ............................................................................................ 4-77
Table 4–5—ELAP Electrical Bus Alignments ............................................................. 4-78
Table 4–6—FLEX Capability – Core Cooling Summary – Modes 1 through 5 with SGs Available ....................................................................................... 4-82
Table 4–7—Primary Coolant Injection Valve Alignment ............................................. 4-84
Table 4–8—Fire Water to SGs Valve Alignment ........................................................ 4-89
Table 4–9—FLEX Capability – Primary Feed and Bleed Core Cooling Summary ..... 4-96
Table 4–10—Primary Feed and Bleed Cooling Valve Alignment ............................. 4-100
Table 4–11—FLEX Capability – Containment Summary .......................................... 4-103
Table 4–12—SAHRS Spray Valve Alignment .......................................................... 4-105
Table 4–13—SAHRS Portable Cooling Water Valve Alignment ............................... 4-106
Table 4–14—FLEX Capability – Spent Fuel Cooling Summary ............................... 4-109
Table 4–15—SICS Controls ..................................................................................... 4-113
Table 4–16—FLEX Capability – Support Functions Summary ................................. 4-115
Table 4–17—Sequence of Events – ELAP Initiated in Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer (ELAP States A, B, and C) ............................................................................. 4-123
Table 4–18—Sequence of Events – ELAP Initiated in Mode 5 or Mode 6 with SGs Unavailable (ELAP States D, E, and F) ...................................... 4-138
Table 4–19—Performance Requirements for Key Portable Equipment ................... 4-148
Table 4–20—Performance Requirements for Key Safety Related Equipment ......... 4-150
Table 4–21—Performance Requirements for Key Non-Safety Related Equipment . 4-153
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page vi
List of Figures
Figure 4-1— ELAP State A Pressurizer Pressure ...................................................... 4-17
Figure 4-2— ELAP State A Cold Leg Temperatures .................................................. 4-17
Figure 4-3— ELAP State A Pressurizer Level ............................................................ 4-18
Figure 4-4— ELAP State A Steam Generator Pressure ............................................. 4-18
Figure 4-5— ELAP State A Steam Generator Levels ................................................. 4-19
Figure 4-6— ELAP State A Core Region Levels ........................................................ 4-19
Figure 4-7—ELAP State B Pressurizer Pressure ....................................................... 4-24
Figure 4-8—ELAP State B Cold Leg Temperatures ................................................... 4-25
Figure 4-9—ELAP State B Pressurizer Level ............................................................. 4-25
Figure 4-10—ELAP State B Steam Generator Pressure ............................................ 4-26
Figure 4-11—ELAP State B Steam Generator Level ................................................. 4-26
Figure 4-12—ELAP State B Core Region Levels ....................................................... 4-27
Figure 4-13—ELAP State C RCS Pressures .............................................................. 4-31
Figure 4-14—ELAP State C RCS Cold Leg Temperatures ........................................ 4-32
Figure 4-15—ELAP State C Steam Generator Levels................................................ 4-32
Figure 4-16—ELAP State C RCS Levels ................................................................... 4-33
Figure 4-17—ELAP State D RCS Pressures .............................................................. 4-37
Figure 4-18—ELAP State D Primary Temperatures ................................................... 4-38
Figure 4-19—ELAP State D RPV Volume Fractions .................................................. 4-38
Figure 4-20—ELAP State E RCS Pressures .............................................................. 4-42
Figure 4-21—ELAP State E Primary Temperatures ................................................... 4-42
Figure 4-22—ELAP State E RPV Volume Fractions .................................................. 4-43
Figure 4-23—ELAP State F Fuel Temperature for a 60 Minute Delay in the Start of Injection ............................................................................................ 4-46
Figure 4-24—Boron Precipitation Analysis Results .................................................... 4-50
Figure 4-25—Containment Pressure with Containment Spray ................................... 4-54
Figure 4-26—Containment Temperature with Containment Spray ............................. 4-55
Figure 4-27—ELAP Battery Discharge Duration ........................................................ 4-65
Figure 4-28—Electrical Distribution and Repowering EUPS ...................................... 4-80
Figure 4-29—RCP SSSS ........................................................................................... 4-86
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page vii
Figure 4-30—Primary to Secondary Heat Transfer Simplified Diagram ..................... 4-89
Figure 4-31—Core Cooling in Mode 5 with SGs Unavailable and Mode 6 (Head On) Simplified Diagram ......................................................................... 4-97
Figure 4-32—Core Cooling in Mode 6 (Head Off) Simplified Diagram ....................... 4-98
Figure 4-33—Containment Spray and Containment Heat Removal Simplified Diagram .............................................................................................. 4-105
Figure 4-34—Spent Fuel Spray System Simplified Diagram .................................... 4-108
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page viii
Nomenclature
Acronym Definition
AC Alternating Current
ANPR Advance Notice of Proposed Rulemaking
BDBEE Beyond Design Basis External Event
COMS Communication System
DC Direct Current
EDG Emergency Diesel Generator
EFW Emergency Feedwater
ELAP Extended Loss of AC Power
E-LGT Emergency Lighting
EP Emergency Preparedness
EPSS Emergency Power Supply System
EUPS Class 1E Uninterruptible Power Supply
FB Fuel Building
FLEX Diverse and Flexible Coping Strategies
FPS Fire Protection System
FSAR Final Safety Analysis Report
GOTHIC Generation of Thermal-Hydraulic Information for Containments
HVAC Heating, Ventilation, and Air Conditioning
I&C Instrumentation and Control
IRWST In-Containment Refueling Water Storage Tank
ISG Interim Staff Guidance
LOCA Loss of Coolant Accident
LOOP Loss of Offsite Power
LTOP Low Temperature Overpressure Protection
MCC Motor Control Center
MCR Main Control Room
MHSI Medium Head Safety Injection
MSRCV Main Steam Relief Control Valve
MSRIV Main Steam Relief Isolation Valve
MSRT Main Steam Relief Train
NEI Nuclear Energy Institute
NRC U.S. Nuclear Regulatory Commission
NTTF Near-Term Task Force
PA Public Address
PACS Priority and Actuator Control System
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page ix
Acronym Definition
PCIP Primary Coolant Injection Pump
PDS Primary Depressurization System
PRT Pressurizer Relief Tank
PS Protection System
PSRV Pressurizer Safety Relief Valve
PZR Pressurizer
RCP Reactor Coolant Pump
RCS Reactor Coolant System
RHR Residual Heat Removal
RSS Remote Shutdown Station
RV Reactor Vessel
SAHRS Severe Accident Heat Removal System
SAS Safety Automation System
SB Safeguard Building
SBO Station Blackout (event)
SBVSE Electrical Division of Safeguard Building Ventilation System
SCDS Signal Conditioning and Distribution System
SFP Spent Fuel Pool
SFPS Spent Fuel Pool Spray
SG Steam Generator
SICS Safety Information and Control System
SSC Structures, Systems, and Components
SSE Safe Shutdown Earthquake
SSSS Standstill Seal System
UHS Ultimate Heat Sink
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page x
ABSTRACT
After the March 2011 accident at the Fukushima Daiichi Nuclear Power Plant in Japan,
the U.S. Nuclear Regulatory Commission (NRC) commissioned a Near-Term Task
Force (NTTF) to evaluate the event. The NTTF recommended specific regulatory
actions in areas of nuclear power plant design and emergency planning to improve the
availability and reliability of plant safety systems to mitigate a beyond design basis
event from external hazards. This technical report addresses applicable Tier 1 and
Tier 2 NTTF recommendations.
The NRC issued Order EA-12-049, “Order Modifying Licenses with Regard to
Requirements for Mitigation Strategies for Beyond-Design-Basis External Events”
(Reference 1), on March 12, 2012, which requires reactor licensees to develop,
implement, and maintain guidance and strategies to maintain or restore core cooling,
containment integrity, and spent fuel pool cooling capabilities following a beyond design
basis external event (BDBEE). The BDBEE discussed in Order EA-12-049 is assumed
to cause a simultaneous loss of all alternating current (AC) power sources and loss of
normal access to the ultimate heat sink that can occur in any operating mode. The
NRC also issued Order EA-12-051, “Order Modifying Licenses with Regard to Reliable
Spent Fuel Pool Instrumentation” (Reference 2), on March 12, 2012, which requires
reactor licensees to provide sufficiently reliable instrumentation to monitor spent fuel
pool water level and be capable of withstanding design-basis natural phenomena.
This technical report addresses measures incorporated into the U.S. EPR design to
improve nuclear safety in response to the Fukushima Daiichi Nuclear Power Plant
accident. For the U.S. EPR design, the BDBEE evaluated is an extended loss of AC
power event, which assumes a simultaneous loss of all AC power sources (loss of
offsite power plus loss of emergency diesel generators plus loss of alternate AC
sources) plus loss of normal access to the ultimate heat sink. It also demonstrates how
the U.S. EPR design provides baseline coping capability with installed equipment,
describes permanent plant connections, and identifies performance and interface
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page xi
requirements for portable equipment to support long-term event mitigation. Critical
operator actions and their timing are also provided.
The U.S. EPR mitigation strategies are capable of mitigating BDBEEs initiated in all
plant operating modes. These strategies have been verified to be acceptable by
analytical methods and evaluations.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 1-1
1.0 INTRODUCTION
The purpose of this technical report is to describe the U.S. EPR mitigation strategies for
beyond design basis external events (BDBEEs). The BDBEE evaluated is an extended
loss of alternating current (AC) power (ELAP) event, which assumes a simultaneous
loss of all offsite AC power sources plus loss of onsite emergency diesel generators
(EDGs) plus loss of alternate AC sources plus loss of normal access to the ultimate
heat sink (UHS).
In response to the events at Fukushima, the U.S. Nuclear Regulatory Commission
(NRC) Near-Term Task Force (NTTF) recommended specific regulatory actions. The
regulatory actions were prioritized as Tier 1, Tier 2, and Tier 3 recommendations. This
technical report addresses applicable Tier 1 and Tier 2 recommendations. The
regulatory requirements for Tier 3 NTTF recommendations are not addressed in this
report.
NTTF Recommendation 4.2 resulted in NRC Order EA-12-049 (Reference 1), which
requires reactor licensees to develop, implement, and maintain guidance and strategies
to maintain or restore core cooling, containment integrity, and spent fuel pool (SFP)
cooling capabilities following a BDBEE. These strategies must be capable of mitigating
a simultaneous loss of all AC power and loss of normal access to the UHS and must be
applicable in all operating modes. Reasonable protection for mitigating equipment must
also be provided. This technical report addresses Nuclear Energy Institute (NEI) 12-06,
“Diverse and Flexible Coping Strategies (FLEX) Implementation Guide” (Reference 3),
which addresses FLEX Phase 1 event mitigation (installed equipment), describes
permanent plant connections as needed, and identifies performance requirements for
portable equipment to support long-term event mitigation (interface provisions for
Phase 2 and 3 actions). The term “portable equipment” as used in this report includes
pre-staged FLEX equipment.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 1-2
1.1 Description of Fukushima Daiichi Accident
On March 11, 2011, the Fukushima Daiichi plant in northern Japan was subjected to
two BDBEEs:
1. A beyond design basis earthquake with peak ground accelerations at the site in the
0.5g-0.6g range.
2. A tsunami, triggered by the earthquake, that struck the plant about 40 minutes later
with an approximately 45-foot high wave, which was approximately 32 feet above
the intake building level, 26 feet above the top of the plant seawall, and 12 feet
above plant grade level.
Units 1, 2, and 3 were in power operation at the time of the earthquake, while Units 4, 5,
and 6 were shut down for routine refueling and maintenance activities. The beyond
design basis earthquake resulted in a loss of offsite power (LOOP), a reactor trip, and
an automatic startup of the EDGs. The beyond design basis tsunami resulted in a total
loss of heat sink due to debris on all units, a total loss of AC emergency power due to
flooding on most units, and a total loss of direct current (DC) emergency power due to
flooding on one unit. As a result of the loss of emergency power for an extended period
of time, Units 1, 2, and 3 experienced some core damage with radiological releases and
hydrogen gas explosions. Releases of combustible gases from adjacent units into Unit
4 resulted in an explosion in Unit 4 as well, however there was no significant fuel
damage. Units 5 and 6 remained shut down without any fuel damage.
1.2 Purpose
This technical report addresses the applicable Tier 1 and Tier 2 NTTF
recommendations.
Section 2.0 provides an overview of the applicable regulatory criteria and bases.
Section 3.0 provides a synopsis of the method that the U.S. EPR design uses to
address each of the applicable Tier 1 and Tier 2 NTTF Recommendations.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 1-3
Section 4.1 summarizes the U.S. EPR mitigation strategy for NTTF Recommendation
4.2 (mitigation of beyond design basis external hazards).
Section 4.2 summarizes the U.S. EPR mitigation strategy for NTTF Recommendation 7
(enhancing SFP makeup and SFP instrumentation).
Section 4.3 summarizes the U.S. EPR mitigation strategy for NTTF Recommendation
9.3 (enhanced emergency preparedness (EP) staffing and communications).
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 2-1
2.0 REGULATORY OVERVIEW
This section describes the regulatory criteria and regulatory basis for the U.S. EPR
design certification post-Fukushima Daiichi mitigation strategy. The NRC orders
(Reference 1 and Reference 2) and NEI guidance documents (Reference 3) determined
the mitigation strategy.
Following the events at the Fukushima Daiichi Nuclear Power Plant on March 11, 2011,
the NRC established a senior-level agency task force known as the NTTF. The NTTF
was tasked with conducting a systematic and methodical review of the NRC regulations
and processes, and then determining whether the agency should make additional
improvements to these programs considering the events at Fukushima Daiichi. The
NTTF provided these recommendations in SECY-11-0093, “Recommendations for
Enhancing Reactor Safety in the 21st Century, the Near-Term Task Force Review of
Insights from the Fukushima Daiichi Accident” (Reference 4).
The NRC identified a subset of the NTTF recommendations that should be undertaken
without unnecessary delay in SECY-11-0124, “Recommended Actions to be Taken
without Delay from the Near-Term Task Force Report” (Reference 5).
Subsequently, the NRC issued SECY-11-0137, “Prioritization of Recommended Actions
to be taken in Response to Fukushima Lessons Learned” (Reference 6). As a result of
the prioritization and assessment process of the NRC staff, the NTTF recommendations
were prioritized into the following three tiers:
• Tier 1 consists of the NTTF recommendations that the NRC staff determined should
be started without unnecessary delay, and for which sufficient resource flexibility
exists, including availability of critical skill sets.
• Tier 2 consists of the NTTF recommendations that cannot be initiated in the near
term due to factors that include the need for further technical assessment and
alignment, dependence on Tier 1 issues, or availability of critical skill sets. These
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 2-2
actions do not require long-term study and can be initiated when sufficient technical
information and applicable resources become available.
• Tier 3 consists of the NTTF recommendations that require further NRC staff study to
support a regulatory action, have an associated shorter-term action that needs to be
completed to inform the longer-term action, are dependent on the availability of
critical skill sets, or are dependent on the resolution of NTTF Recommendation 1
(Reference 9). Given this, the NTTF Tier 3 recommendations are not addressed in
this report.
In SECY-12-0025, “Proposed Orders and Requests for Information in response to
Lessons Learned from Japan’s March 11, 2011, Great Tohoku Earthquake and
Tsunami” (Reference 7), the NRC described its process to disposition:
• Six additional NRC staff recommendations described in SECY-11-0137.
• Other issues that continue to arise as part of ongoing NRC staff deliberations,
stakeholder interactions, and interactions with the Advisory Committee on Reactor
Safeguards.
In SECY-12-0095, “Tier 3 Program Plans and 6-Month Status Update in Response to
Lessons Learned from Japan’s March 11, 2011, Great Tohoku Earthquake and
Subsequent Tsunami” (Reference 8), the NRC provided an updated list of
recommendations that are being addressed under the Japan lessons learned project.
In March of 2012, the NRC issued two orders and a 10 CFR 50.54(f) letter to
pressurized water reactor operating plant licensees and Combined License holders:
• NRC Order EA-12-049, “Mitigation Strategies for Beyond Design Basis External
Hazards” (Reference 1).
• NRC Order EA-12-051, “Reliable Spent Fuel Pool Instrumentation” (Reference 2).
• 10 CFR 50.54(f) letter requesting additional information, Recommendations 2.1, 2.3,
and 9.3.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 2-3
2.1 NRC Order EA-12-049, Interim Staff Guidance JLD-ISG-2012-01, and NEI 12-06, Revision 0
In response to NTTF Recommendation 4.2, NRC Order EA-12-049, “Order Modifying
Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-
Basis External Events” (Reference 1), was issued on March 12, 2012. The Order
requires guidance and strategies to be available to prevent fuel damage in the reactor
and SFP if all units at a site simultaneously experience a loss of power, motive force,
and normal access to the UHS.
NRC Order EA-12-049 requires a three-phase approach for mitigating BDBEEs. The
initial phase, referred to as Phase 1, requires the use of installed equipment and
resources to maintain or to restore core cooling, containment integrity, and SFP cooling
capabilities. The transition phase, referred to as Phase 2, requires that sufficient
portable onsite equipment and consumables be available to maintain or restore these
functions until they can be achieved with resources brought from offsite. The final
phase, referred to as Phase 3, requires that sufficient offsite resources sustain Phase 1
and Phase 2 functions indefinitely.
The NRC issued Interim Staff Guidance (ISG) JLD-ISG-2012-01, “Compliance with
Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation
Strategies for Beyond-Design-Basis External Events” (Reference 11), on August 29,
2012. This ISG endorses, with clarifications, the methodologies described in the
industry guidance document, NEI 12-06 (Reference 3), as an acceptable means to
comply with NRC Order EA 12-049 (Reference 1).
NEI 12-06 provides FLEX to establish an indefinite coping capability to prevent damage
to the fuel in the reactor and SFPs, and to maintain the containment function by using
installed equipment, onsite portable equipment, and prestaged offsite resources. This
coping capability is based on strategies that focus on an assumed simultaneous
extended loss of all AC power sources (LOOP plus loss of EDGs plus loss of alternate
AC sources) plus loss of normal access to the UHS caused by unspecified events.
These mitigating strategies must be implementable for all modes.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 2-4
NEI 12-06 states that permanent plant equipment contained in structures with designs
that are robust with respect to seismic events, floods, high winds and associated
missiles, and extreme temperatures are assumed to be available. Onsite portable or
prestaged mitigating equipment must also be reasonably protected from external
events.
The U.S. EPR design conforms to NRC Order EA-12-049 (Reference 1), NRC JLD-ISG-
2012-01 (Reference 11), and NEI 12-06, Revision 0 (Reference 3) with the following
clarifications:
1. JLD-ISG-2012-01 and NEI 12-06 do not specify an acceptance criterion for the
containment function. To fulfill the containment function, the U.S. EPR mitigation
strategy has conservatively established an acceptance criterion for these BDBEEs
that the containment be maintained below its design basis limits (i.e., pressure below
62.9 psig and temperature below 310°F).
2. Table D-1 of NEI 12-06 states that emergency feedwater (EFW)/auxiliary feedwater
should “provide SG makeup sufficient to maintain or restore SG level with installed
equipment and power supplies to the greatest extent possible to provide core
cooling.” For some operating modes, the U.S. EPR mitigation strategy requires dry
out of the steam generators (SGs) to enable feedwater delivery from a fire water
pump. Core heat removal is then accomplished using the main steam relief trains
(MSRTs) to maintain the SGs below the shutoff head of the diesel driven fire water
pumps. Dryout of the SGs causes a reduction in SG pressure sufficient to allow
feed flow. During this brief period when primary to secondary heat transfer is
interrupted, reactor coolant system (RCS) circulation continues due to momentum
which facilitates restoration of primary to secondary heat transfer once feedwater is
delivered to the SGs. Heat transfer is restored; however, SG levels will not recover
until approximately 1.2 hours after feedwater initiation in ELAP events initiated in
Mode 1.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 2-5
2.2 NRC Order EA-12-051, Interim Staff Guidance JLD-ISG-2012-03, and NEI 12-02, Revision 1
In response to NTTF Recommendation 7.1, NRC Order EA-12-051, “Issuance of Order
to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation”
(Reference 2), was issued on March 12, 2012. This order states that reactor licensees
must provide sufficiently reliable instrumentation that is capable of withstanding design-
basis natural phenomena to monitor SFP water level.
Attachment 2 to NRC Order EA-12-051 (Reference 2) requires reliable water level
instrumentation in associated spent fuel storage pools that is capable of supporting
identification by trained personnel of the following pool water level conditions:
• A level that is adequate to support operation of the normal fuel pool cooling system.
• A level that is adequate to provide substantial radiation shielding for a person
standing on the SFP operating deck.
• A level at which fuel remains covered and actions to implement makeup water
addition should no longer be deferred.
The NRC issued ISG JLD-ISG-2012-03, “Compliance with Order EA-12-051, Reliable
Spent Fuel Pool Instrumentation” (Reference 12), on August 29, 2012. This ISG
endorses, with exceptions and clarifications, the methodologies described in the
industry guidance document NEI 12-02, “Industry Guidance for Compliance with NRC
Order EA-12-051, To Modify Licenses with Regard to Reliable Spent Fuel Pool
Instrumentation” (Reference 13).
The U.S. EPR design conforms to NRC Order EA-12-051 (Reference 2), NRC JLD-ISG-
2012-03 (Reference 12), and NEI 12-02, Revision 1 (Reference 13).
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 3-1
3.0 APPLICABLE TIER 1 AND TIER 2 RECOMMENDATIONS
The NRC issued a letter, “Implementation of Fukushima Near-Term Task Force
Recommendations,” to AREVA NP Inc. (AREVA) on April 25, 2012 (Reference 14),
which indicated that AREVA would be requested to provide information related to the
Fukushima Tier 1 Recommendations in SECY-12-0025 (Reference 7) and
SRM-12-0025, “Proposed Orders and Requests for Information in Response to Lessons
Learned from Japan’s March 11, 2011, Great Tohoku Earthquake and Tsunami”
(Reference 15), that are applicable to the U.S. EPR design. The four recommendations
identified in the letter were:
• Recommendation 2.1—Seismic Hazards Analysis.
• Recommendation 4.2—Protection of Equipment from External Hazards.
• Recommendation 7.1—Spent Fuel Pool Instrumentation.
• Recommendation 9.3—Enhanced Emergency Preparedness.
Because the NRC letter of April 25, 2012 only addressed Fukushima Tier 1
recommendations, AREVA proposed a plan to the NRC at a September 19, 2012 public
meeting to address all Tier 1 and Tier 2 Fukushima recommendations. This plan
concluded that only a subset of the Tier 1 and Tier 2 Fukushima recommendations are
applicable to the U.S. EPR design.
The following subsections summarize how the applicable Fukushima Tier 1 and Tier 2
recommendations are met for the U.S. EPR design.
3.1 NTTF Recommendation 2.1, Tier 1
NTTF Recommendation 2.1 is a Tier 1 recommendation that requests reactor licensees
reevaluate the seismic and flooding hazards at their sites against current NRC
requirements and guidance and, if necessary, that they update the design basis of
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 3-2
structures, systems, and components (SSC) important to safety to protect against the
updated hazards.
Subsequent to the April 25, 2012 letter (Reference 14), the NRC staff determined that
this recommendation would be addressed by reactor licensees. No further action on
this recommendation is required for the U.S. EPR design certification.
3.2 SECY-12-0025, Enclosure 3 Recommendation, Tier 2
Enclosure 3 of SECY‐12‐0025 (Reference 7) is a Tier 2 recommendation that requests
the reevaluation of other natural external hazards against current regulatory
requirements and guidance and that the design basis be updated accordingly.
The U.S. EPR design satisfies current regulatory requirements and guidance. U.S.
EPR FSAR Tier 2, Section 2.1 discusses the U.S. EPR site characteristics design
parameters. The U.S. EPR design satisfies this recommendation and no further action
on this recommendation is required for the U.S. EPR design certification.
3.3 NTTF Recommendation 4.1, Tier 1
NTTF Recommendation 4.1 is a Tier 1 recommendation that resulted in an Advance
Notice of Proposed Rulemaking (ANPR). The ANPR requests that icensees strengthen
their station blackout (SBO) mitigation capability (10 CFR 50.63) under conditions
involving significant natural disasters.
The scope and timing of rulemaking cannot be predicted at this time. The U.S. EPR
design features for SBO are addressed as part of the response to NTTF
Recommendation 4.2 in Section 4.1.
3.4 NTTF Recommendation 4.2, Tier 1
Recommendation 4.2 is a Tier 1 recommendation that resulted in the issuance of NRC
Order EA-12-049 (Reference 1), which requires reactor licensees to enhance SBO
mitigation capabilities for beyond design basis external hazards.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 3-3
The U.S. EPR mitigation strategy for this recommendation is addressed in Section 4.1.
3.5 SECY-12-0025, Enclosure 2 Recommendation, Tier 1
Recommendation from SECY-12-0025 (Reference 7), Enclosure 2 is a Tier 1
recommendation that is related to NTTF 2.1, 2.3, 4.1, and 4.2. This recommendation
requests that the reactor licensee include the loss of normal access to the UHS as a
design assumption in conjunction with strategies for dealing with prolonged SBO, and
address loss of normal access to UHS in conjunction with measures taken to deal with
BDBEE.
The U.S. EPR mitigation strategy for this recommendation is addressed in Section 4.1
as part the of mitigation strategy for NTTF 4.2.
3.6 NTTF Recommendation 7.1, Tier 1
Recommendation 7.1 is a Tier 1 recommendation that resulted in the issuance of NRC
Order EA-12-051 (Reference 2). This Order stated that reactor licensees must provide
sufficiently reliable instrumentation to monitor SFP water level and be capable of
withstanding design basis natural phenomena.
The U.S. EPR mitigation strategy for this recommendation is discussed in Section 4.2.
3.7 NTTF Recommendation 7.2, Tier 2
Recommendation 7.2 is a Tier 2 recommendation that requests reactor licensees
provide safety-related AC electrical power for SFP makeup.
In accordance with COMSECY-13-0002 (Reference 28), the intent of this
recommendation is satisfied through the Order EA-12-049 SFP strategy that uses
AC-independent (self-powered), reliable, portable pumps. The U.S. EPR mitigation
strategy associated with EA-12-049 is addressed in Section 4.1.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 3-4
3.8 NTTF Recommendation 7.3, Tier 2
Recommendation 7.3 is a Tier 2 recommendation that requests that plant Technical
Specifications require one train of emergency onsite electrical power to be operable for
SFP makeup/instrumentation when there is irradiated fuel in the SFP, regardless of
plant operating mode.
In accordance with COMSECY-13-0002 (Reference 28), the intent of this
recommendation is satisfied through the EA-12-049 SFP strategy which must be
capable of being implemented in all modes and uses programmatic controls for
availability of strategies with specified out-of-service times. The U.S. EPR mitigation
strategy associated with EA-12-049 is addressed in Section 4.1.
3.9 NTTF Recommendation 7.4, Tier 2
Recommendation 7.4 is a Tier 2 recommendation that requests that reactor licensees
provide a seismically qualified means to spray water into SFPs, including an easily
accessible connection to supply water, such as using a portable pump or pumper truck,
at grade outside of the building.
In accordance with COMSECY-13-0002 (Reference 28), the intent of this
recommendation is satisfied through the EA-12-049 SFP strategy which uses a spray
strategy and two access locations for providing makeup to the SFP. The U.S. EPR
mitigation strategy associated with EA-12-049 is addressed in Section 4.1.
3.10 NTTF Recommendation 8, Tier 1
Recommendation 8 is a Tier 1 recommendation that will result in an ANPR.
Recommendation 8 requests that reactor licensees strengthen and better integrate
Emergency Operating Procedures, Severe Accident Management Guidelines and
Extensive Damage Mitigation Guidelines. As stated in SECY-12-0025 (Reference 7),
the ANPR activities are in progress within the NRC, but the ANPR has not been issued.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 3-5
The intent of this recommendation is fulfilled through U.S. EPR FSAR Tier 2, Sections
13.5 and 19.2.5 which include guidance for Emergency Operating Procedures, Severe
Accident Management Guidelines, and Extensive Damage Mitigation Guidelines. U.S.
EPR FSAR Tier 2, Section 13.5 provides the U.S. EPR design requirements for use of
site-specific information for administrative, operating, emergency, maintenance, and
other operating procedures. U.S. EPR FSAR Tier 2, Section 19.2.5 describes the
Operating Strategies for Severe Accidents methodology and requirements for
development and implementation of severe accident management guidelines prior to
fuel loading using this methodology for the U.S. EPR design.
3.11 NTTF Recommendation 9.3
3.11.1 Tier 1 Recommendations
A portion of Recommendation 9.3 is a Tier 1 recommendation that requires reactor
licensees to provide enhanced EP staffing and communications.
The U.S. EPR mitigation strategy for this recommendation is discussed in Section 4.3.
3.11.2 Tier 2 Recommendations
The remaining portion of Recommendation 9.3 is a Tier 2 recommendation that requires
reactor licensees to enhance their Emergency Plan (e.g., multiunit dose assessments,
periodic training).
U.S. EPR FSAR Tier 2, Section 13.3 discusses the U.S. EPR design requirements for
development of an Emergency Plan in accordance with 10 CFR 50.47 and 10 CFR
Part 50, Appendix E.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-1
4.0 MITIGATION ASSESSMENT
4.1 NTTF 4.2, Mitigation of Beyond Design Basis External Events
4.1.1 Overview
In NTTF Recommendation 4.2 and NRC Order EA-12-049 (Reference 1), it is
postulated that a BDBEE can deterministically result in a simultaneous ELAP and loss
of normal access to the UHS. An ELAP event assumes a simultaneous loss of AC
power sources (LOOP plus loss of EDGs plus loss of alternate AC sources) for an
indefinite period. An evaluation of an ELAP event caused by a BDBEE was performed
for the U.S.EPR design. Mitigation strategies for the ELAP event have been developed
based on the guidance of NEI 12-06 (Reference 3). This FLEX guidance has been
endorsed by the NRC, with certain exceptions and clarifications provided in NRC
JLD-ISG-2012-01 (Reference 11). The U.S. EPR design conforms with
JLD-ISG-2012-01 (Reference 11) and NEI 12-06 (Reference 3), with certain
clarifications as discussed in Section 2.1 of this report.
For new plant designs, the scope of NRC Order EA-12-049 (Reference 1) spans both
the Design Certification and the Combined License. Accordingly, Section 4.1 focuses
on providing a baseline coping capability with installed equipment (Phase 1), providing
permanent plant connections, and identifying performance requirements for portable
equipment to support long-term event mitigation (interface provisions for Phase 2 and 3
actions).
Section 4.1 is divided into the following subsections:
• Section 4.1.2 summarizes the acceptance criteria for core cooling, containment
integrity, and spent fuel cooling.
• Section 4.1.3 describes the analytical codes and methods, key assumptions, and
results of the analyses performed.
• Section 4.1.4 summarizes the reasonable protection requirements of installed and
portable equipment.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-2
• Section 4.1.5 provides the mitigation strategies for core cooling, containment
integrity, and SFP cooling capabilities following an ELAP event. These strategies
are based upon the analytical results provided in Section 4.1.3.
• Section 4.1.6 summarizes the sequence of events and critical operator actions.
• Section 4.1.7 summarizes the performance requirements for safety related,
non-safety related, and portable equipment used to implement the mitigation
strategies.
4.1.2 Acceptance Criteria
The acceptance criteria for the ELAP mitigation strategies are summarized in Table 4-1.
Table 4–1—Mitigation Strategy Acceptance Criteria
Function Acceptance Criteria
Core Cooling Fuel in core remains covered with liquid or two phase mixture – no fuel damage. Criticality – maintain core subcritical throughout the event.
Spent Fuel Cooling Fuel in SFP remains covered – no fuel damage.
Containment Integrity Containment pressure and temperature remain below design basis pressure and temperature limits.
These criteria are consistent with NEI 12-06 (Reference 3) which has been endorsed by
the NRC in JLD-ISG-2012-01 (Reference 11).
Adequate containment integrity is provided for these BDBEEs by conservatively
maintaining the containment pressure and temperature below the Reactor Containment
Building design basis limits. As described in U.S. EPR FSAR Tier 2, Section 3.8.1.1,
the containment design basis pressure limit is 62.9 psig (77.6 psia) and the containment
design basis temperature limit is 310°F. These criteria were chosen for the U.S. EPR
design since neither JLD-ISG-2012-01 (Reference 11) nor NEI 12-06 (Reference 3)
specify acceptance criteria for the containment function.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-3
4.1.3 Analytical Bases
Order EA-12-049, “Order Modifying Licenses with regard to Requirements for Mitigating
Strategies for Beyond-Design-Basis External Events,” states that reactor licensees must
be capable of implementing the ELAP mitigation strategies in all modes.
This section provides information about the analyses performed that provide the basis
for the ELAP event mitigation strategies, including codes and methods used, key
assumptions, and the results of the analyses.
The scope of Section 4.1.3, Analytical Bases, is further divided into the following
subsections:
• Section 4.1.3.1 summarizes the transient core cooling analyses performed with
S-RELAP5.
• Section 4.1.3.2 summarizes the primary feed and bleed injection requirements.
• Section 4.1.3.3 summarizes the reactor coolant pump (RCP) seal leakage
evaluation.
• Section 4.1.3.4 summarizes the containment temperature and pressure analyses
performed with the GOTHIC (Generation of Thermal-Hydraulic Information for
Containments) computer code.
• Section 4.1.3.5 summarizes the Safeguard Buildings (SBs) heatup analysis.
• Section 4.1.3.6 summarizes the main control room (MCR) heatup analysis.
• Section 4.1.3.7 summarizes the main control room portable cooler sizing evaluation.
• Section 4.1.3.8 summarizes the SFP time to boil and makeup analysis.
• Section 4.1.3.9 summarizes the DC load shedding analysis.
Table 4-2 summarizes the key equipment status and operator actions for the various
operating Technical Specification modes and demonstrates how core cooling is
achieved in all modes. The operating Technical Specification modes are further broken
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-4
down for analytical purposes based on RCS initial conditions (e.g., RCS intact,
pressure, temperature, pressurizer (PZR) level), decay heat at time of ELAP event,
equipment availability changes within a mode (e.g., number of RCPs operating,
accumulators isolated, or low temperature overpressure protection (LTOP) enabled),
and potential differences between heatup and cooldown equipment operation. These
various modes were then grouped into “ELAP States” (i.e., ELAP State A, ELAP State
B, etc.). The ELAP States are further classified by their respective core cooling method:
• Steam Generators Available: Mitigation Strategy = Primary to Secondary Heat
Transfer (ELAP States A, B, and C).
• Steam Generators Not Available: Mitigation Strategy = Primary Feed and Bleed
(ELAP States D, E, and F).
Some of the key differences between the various ELAP States for the S-RELAP5
analyses are as follows:
ELAP State A: Trip from 100% power. All four RCPs were initially operating, RCS at
nominal PZR level, and all accumulators credited. This ELAP State
includes Modes 1 to 3.
ELAP State B: Decay heat at one hour after reactor shutdown. All four RCPs were
initially operating, RCS at nominal PZR level, and no accumulators
credited (although one is available). This ELAP State includes Modes
3 and 4.
ELAP State C: Mode 4 decay heat at seven hours after reactor shutdown, and Mode 5
decay heat at 15 hours after reactor trip. LTOP enabled. All four
RCPs were initially operating and one accumulator credited (at 320
psia). PZR level is at ~ 90%.
ELAP State D: Mode 5 decay heat at 16.67 hours after reactor shutdown. RCS intact
(pressurized). LTOP enabled. Four residual heat removal (RHR) trains
were initially in operation. No RCPs were initially operating and no
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-5
accumulators credited. PZR level is at ~ 100%. The SGs were
deterministically assumed to be unavailable due to outage conditions.
ELAP State E: Mode 5 decay heat at 16.67 hours after reactor shutdown. RV head
on and RCS vented (primary depressurization system (PDS) valves
open to pressurizer relief tank (PRT)). LTOP enabled, two RHR trains
were initially in operation. No RCPs were initially operating and no
accumulators credited.
ELAP State F: Mode 6 decay heat at 41.67 hours after reactor shutdown. RCS open
to containment (RV head removed). LTOP enabled. Two RHR trains
were initially in operation. No accumulators credited.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-6
Table 4–2—ELAP States
Group Mode RCS Condition at time of ELAP
RCP Status
Accumulator Status
RCS Status
RCS Inventory
Key Operator Actions
STEAM GENERATORS AVAILABLE MITIGATION STRATEGY = PRIMARY TO SECONDARY HEAT TRANSFER
EL
AP
S
TA
TE
A
Mode 1 Power Operation 100% Power
Tavg = 594°F Pressure = 2250 psia
4 RCPs operating
4 accumulators active and available
Closed PZR nominal
level
• 4 SG cooldown at 90°F/hour to 100 psia secondary pressure
• Fire water to 4 SGs at 150 gpm for first 6 hours. Maintain SG level at 82.2% WR (+0%, -10%)
• After 6 hours, isolate fire water to SGs 3 and 4, bypass SGs 3 and 4 MSRIV solenoids to maintain valves open, and leave MSRCVs in current position. Feed SGs 1 and 2 to maintain level and control SG pressure at 100 psia with MSRCVs.
• Replenish Fire Water Storage Tank
Mode 1 Power Operation 5% - 100% Power
594°F ≥ Tavg ≥ 580°F Pressure = 2250 psia
Mode 2 Startup Power Decrease to 0%, Keff < 0.99
580°F ≥ Tavg ≥ 578°F Pressure = 2250 psia
Mode 3 Hot Standby Cooldown to 1015 psia
578°F ≥ Tavg > 350°F 2250 psia ≥ Pressure > 1015 psia Reactor is subcritical
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-7
Group Mode RCS Condition at time of ELAP
RCP Status
Accumulator Status
RCS Status
RCS Inventory
Key Operator Actions
STEAM GENERATORS AVAILABLE MITIGATION STRATEGY = PRIMARY TO SECONDARY HEAT TRANSFER
EL
AP
S
TA
TE
B
Mode 3 Hot Standby Cooldown to 350°F
578°F ≥ Tavg > 350°F 1015 psia ≥ Press > 435 psia
4 RCPs operating
3 accumulators isolated, but
available; 1 active, but
depressurized to 320 psia.
No accumulators
credited
Closed PZR nominal
level
• 4 SG cooldown at 90°F/hour to 60 psia
• Fire water to 4 SGs at 150 gpm for first 6 hours. Maintain SG level at 82.2% WR (+0%, -10%)
• After 6 hours, isolate fire water to SGs 3 and 4, bypass SGs 3 and 4 MSRIV solenoids to maintain valves open, and leave SGs 3 and 4 MSRCVs in current position. Feed SGs 1 and 2 to maintain level and control SG pressure at 60 psia with MSRCVs.
• Start PCIP for RCS makeup at approximately 3 hours. Secure after regaining PZR level
Mode 4 Hot Shutdown Cooldown to 250°F
350°F > Tavg > 250°F 435 psia > Pressure > 370 psia
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-8
Group Mode RCS Condition at time of ELAP
RCP Status
Accumulator Status
RCS Status
RCS Inventory
Key Operator Actions
STEAM GENERATORS AVAILABLE MITIGATION STRATEGY = PRIMARY TO SECONDARY HEAT TRANSFER
EL
AP
S
TA
TE
C
Mode 4 Hot Shutdown Cooldown to 200°F
250°F > Tavg > 200°F 435 psia > Pressure > 370 psia RHR connection point (~ 250°F and ~ 360 psia - Mode 4) LTOP overpressure protection by two PSRVs active at 248°F (P17) (525/541 psig)
RCPs 2 and 3
operating (RCPs 1
and 4 tripped at
250°F)
3 accumulators isolated, but
available; 1 active, but
depressurized to 320 psia.
One accumulator
credited (320 psia)
Closed PZR level is raised to
~ 90%
• Steam through MSRTs once SG pressure reaches 40 psia. Position MSRCVs as necessary to maintain 40 psia.
• Fire water to 4 SGs for first 6 hours. Maintain SG level at 82.2% WR (+0%, -10%)
• After 6 hours, isolate fire water to SGs 3 and 4, bypass SGs 3 and 4 MSRIV solenoids to maintain valves open, and leave SGs 3 and 4 MSRCVs in current position. Feed SGs 1 and 2 to maintain level and control SG pressure at 40 psia with MSRCVs.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-9
Group Mode RCS Condition at time of ELAP
RCP Status
Accumulator Status
RCS Status
RCS Inventory
Key Operator Actions
STEAM GENERATORS AVAILABLE MITIGATION STRATEGY = PRIMARY TO SECONDARY HEAT TRANSFER
EL
AP
S
TA
TE
C
Mode 5 Cold Shutdown Cooldown to 130°F
200°F > Tavg > 130°F 370 psia > Pressure > 14.7 psia 4 RHR trains in operation LTOP overpressure protection by two PSRVs active at 248°F (P17) (525/541 psig)
Below 158°F,
only RCP 3 in
operation Below
131°F, no RCPs
3 accumulators isolated, but
available; 1 active, but
depressurized to 320 psia.
One accumulator
credited (320 psia)
Closed PZR level is raised to
~ 90%
• Steam through MSRTs once SG pressure reaches 40 psia. Position MSRCVs as necessary to maintain 40 psia.
• Fire water to 4 SGs for first 6 hours. Maintain SG level at 82.2% WR (+0%, -10%)
• After 6 hours, isolate fire water to SGs 3 and 4, bypass SGs 3 and 4 MSRIV solenoids to maintain valves open, and leave SGs 3 and 4 MSRCVs in current position. Feed SGs 1 and 2 to maintain level and control SG pressure at 40 psia with MSRCVs.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-10
Group Mode RCS Condition at time of ELAP
RCP Status
Accumulator Status
RCS Status
RCS Inventory
Key Operator Actions
STEAM GENERATORS NOT AVAILABLE MITIGATION STRATEGY = PRIMARY FEED AND BLEED
EL
AP
S
TA
TE
D
Mode 5 Cold Shutdown Cooldown to 130°F RCS pressure > 14.7 psia. SGs are unavailable
Tavg = 130°F 370 psia > Pressure > 14.7 psia 4 RHR trains in operation LTOP overpressure protection by two PSRVs active at 248°F (P17) (525/541 psig) SGs deterministically assumed to be unavailable due to outage conditions
No RCPs operating
4 accumulators isolated, but
available No
accumulators credited
Closed PZR at 100%
(PZR level is raised to 100% after last RCP is
tripped)
• Latch each PSRV open on its second lift
• PDS valve opened at 60 min
• PCIP activated at 60 min
EL
AP
S
TA
TE
E
Mode 5 and Mode 6 (RV head not removed, but detensioning started) Cold Shutdown Begin draindown and Midloop operation PDS Valves Opened RCS vented and SGs are unavailable
Tavg = 130°F Pressure = 14.7 psia LTOP overpressure protection by two PSRVs 2 RHR trains operating 1 set of PDS valves open
No RCPs operating
4 accumulators isolated, but
available No
accumulators credited
Open to PRT
Drain to Midloop (Inlet to
PZR surge line
covered)
• PCIP activated at 60 min
• Flow path is to PRT via 1 set of PDS valves
EL
AP
S
TA
TE
F
Mode 6 Refueling RV Head removed
Tavg < 130°F Pressure = 14.7 psia LTOP overpressure protection by two PSRVs 1 set of PDS valves open
No RCPs operating
4 accumulators isolated, but
available No
accumulators credited
Open to PRT or open at
RV flange
Flange level or Canal
flooded
• PCIP activated at 60 min
• Flow path is either out of RV flange or to PRT via 1 set of PDS valves
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-11
4.1.3.1 Core Cooling S-RELAP5 Analyses
The transient analyses of the core response for ELAP events initiated in Modes 1
through 6 were performed using S-RELAP5. ANP-10263(P)(A), “Codes and Methods
Applicability Report for the U.S. EPR” (Reference 16), justifies the use of S-RELAP5 on
the U.S. EPR design. S-RELAP5 is a thermal hydraulic simulation code that utilizes a
two-fluid (plus non-condensables) model with conservation equations for mass, energy,
and momentum transfer. For the ELAP State A analysis, the reactor core is modeled
with heat generation rates determined from reactor kinetics equations (point kinetics)
with reactivity feedback, and with actinide and decay heating. For the rest of the ELAP
States, the core power is modeled as a decay heat versus time including actinide
contributions.
The two-fluid formulation uses a separate set of conservation equations and constitutive
relations for each phase. The effects of one phase on another are accounted for by
interfacial friction and heat and mass transfer interaction terms in the conservation
equations. The conservation equations have the same form for each phase; only the
constitutive relations and physical properties differ.
The modeling of plant components is performed by following guidelines developed to
provide accurate accounting for physical dimensions and the dominant phenomena
expected during the transient. The basic building blocks for modeling are the hydraulic
volumes for fluid paths and the heat structures for heat transfer surfaces. In addition,
special purpose components exist to represent specific components such as the RCPs
and the SG moisture separators. Plant geometry is modeled at the resolution
necessary to resolve the flow field and the phenomena being modeled within practical
computational limitations.
S-RELAP5 models used in the performance of the ELAP analyses include heat
structures which represent the reactor and pressurizer vessels, RV internals, RCS loop
piping, fuel pellets and cladding, and the SG tubes, tubesheet, and wrapper. Model
enhancements, such as adding a PRT model, were included as necessary to ensure
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-12
that the problem solution included the pertinent plant equipment for each transient.
Simplifications to the models were also made as warranted, such as removing the
portion of the input that models the secondary side (during ELAP States D, E, and F), to
improve computational runtime performance. The topical reports that justify application
of the S-RELAP5 methodology and models to the U.S. EPR design are provided in
References 16, 17, and 19.
4.1.3.1.1 ELAP State A – Core Cooling for Events Initiated in Mode 1, Mode 2, and Mode 3 RCS >1000 psig
Analytical Methods
The analysis of the core response for ELAP events initiated in Modes 1 through 3
(ELAP event initiated at 100% power and SGs available) was performed using
S-RELAP5. The S-RELAP5 thermal hydraulic modeling code is described in
Section 4.1.3.1
Key Assumptions and Modeling Highlights
The analysis of core cooling for ELAP events initiated in ELAP State A that rely on the
SGs for heat removal was performed using the following key assumptions:
• The S-RELAP5 model was used with the following best estimate (or conservative)
assumptions and modeling highlights:
- Non-safety system capabilities (such as fire water system) are included in the
model, as appropriate (best estimate assumption).
- End of cycle core reactor kinetics (conservative assumption due to greater
positive reactivity insertion during cooldown).
- Best-estimate core decay heat (best estimate assumption).
- No stuck control rods (best estimate assumption).
- No single failures (best estimate assumption).
- No equipment out of service prior to event initiation (best estimate assumption).
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-13
These analysis assumptions are consistent with the requirements of Section 3.2.1,
“General Criteria and Baseline Assumptions,” of NEI 12-06 (Reference 3) as endorsed
by JLD-ISG-2012-01 (Reference 11) with the exception that the U.S. EPR design uses
end-of-cycle core reactor kinetics rather than an assumed 100 day power history (which
is less limiting).
• The ELAP event assumes a simultaneous loss of all AC power sources (LOOP, loss
of all EDGs, and loss of all alternate AC sources) in combination with a loss of
normal access to the UHS.
• The initiating ELAP event is assumed to occur when the plant is operating normally
at 100% full power.
• The ELAP event causes an immediate loss of power to the RCPs and main
feedwater pumps, followed by a reactor trip.
• The initial conditions of the RCS are as follows:
- PZR level is at nominal level (54.3%).
- RCS pressure is at 2250 psia.
- RCS average temperature is 594°F.
- All four accumulators are operable and pressurized to 681.7 psia.
• RCS leakage was assumed from the following two sources:
- Allowable RCS leakage per Plant Technical Specifications (11 gpm).
- RCP seal leakage. RCP seal leakage was modeled consistent with the SBO
analysis described in U.S. EPR FSAR Tier 2, Section 8.4. The RCP standstill
seal system (SSSS) is credited with limiting RCP seal leakage.
• The MSRTs are used to control pressure in the SGs so that the low head diesel-
driven fire water pump(s) can supply water to the SGs via the EFW header.
• Core decay heat is removed by means of primary to secondary heat transfer. Core
heat is transferred from the fuel to the reactor coolant, transported to the SGs by
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-14
natural circulation, transferred to the secondary side of the SGs, and transported to
the atmosphere by steaming the SGs through the MSRTs. The SGs will be fed from
the diesel-driven fire pump(s) when the SGs have been depressurized below the fire
pump discharge pressure.
• The following key operator actions are assumed in the analysis:
- The operator ensures that the automatic closure of all three seal leak-off isolation
valves for each RCP has occurred upon detection of simultaneous loss of seal
injection and thermal barrier cooling. At 15 minutes after the RCP trip occurs, the
operator ensures that the standstill seal has closed.
- RCS cooldown starts at 30 minutes after the initialization of ELAP. The pressure
in all four SGs is lowered at a rate that results in an RCS cooldown rate of
90°F/hour until SG pressure decreases to 100 psia. MSRTs are then throttled as
required to control SG pressures at 100 psia.
- Fire water is fed to four SGs at 150 gpm (each) when SG pressure is less than
fire pump discharge pressure. SG levels are controlled at 82.2% WR
(+0%, -10%) in each SG after level recovers.
- After six hours, fire water to SGs 3 and 4 is isolated, the SGs 3 and 4 MSRIV
solenoids are bypassed to maintain the valves open, and the associated main
steam relief control valves (MSRCVs) are left in their current position. Fire water
flow is continued to SGs 1 and 2 for the remainder of the analysis to maintain SG
levels, and the MSRCVs continue to be throttled to control SG 1 and 2 pressure
at 100 psia.
Results
S-RELAP5 cases were run to characterize the RCS response, timing of operator
actions, and latitude in potential FLEX mitigating strategies. With no mitigation actions,
core uncovering occurs in ELAP State A (Modes 1 through 3) at ~ 2.8 hours. Therefore,
operator actions are required to mitigate the consequences of an ELAP event in ELAP
State A. To mitigate these events, the operators are relied upon to control SG pressure
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-15
using the MSRTs and to control SG level with supply from the diesel driven fire water
pump. The acceptance criteria that the core remains covered and subcritical are met.
RCS makeup from the Primary Coolant Injection Pump (PCIP) is required after the first
24 hours to maintain PZR level and primary system subcooling.
The results of the Mode 1 through 3 (ELAP State A) case are depicted in Figure 4-1
through Figure 4-6. The key transient highlights for this case are as follows:
• At 30 minutes, an RCS cooldown of 90°F/hour is initiated with all four SGs. Once
SG pressure decreases to 100 psia, SG pressure will be controlled at 100 psia.
Cooldown with all four SGs provides a symmetric RCS response.
• During the initial cooldown, the RCS depressurizes due to RCS contraction.
• At ~ 1.2 hours, the PZR vessel empties due to RCS cooldown contraction and
assumed RCS leakage.
• At ~ 1.32 hours, the SGs are empty. SG3 empties slightly earlier than the other
three SGs due to the effects of the PZR and the slightly hotter fluid reaching the SG.
• Once the SGs are empty, the secondary pressure rapidly decreases as the MSRTs
try to maintain the cooldown rate. Approximately 10 seconds after SG dryout, SG
pressures reach 100 psia and fire water is delivered to all four SGs. SG level is not
recovered for another 1.2 hours.
• Accumulators begin to discharge at ~ 2.0 hours. The accumulators do not empty
during the analyzed duration of the transient.
• At ~ 2.53 hours, SG levels begin to recover. The levels are not on scale, but level is
beginning to increase. As decay heat decreases, the SG levels are increased to the
control point of 82.2% WR (+0%, -10%).
• At 3.75 hours, PZR level begins to recover. The pressurizer level initially recovers
due to accumulator injected fluid that expands. The expansion of the accumulator
fluid moves fluid into the pressurizer. As the cooler fluid reaches the RV upper
head, the upper head void partially collapses, once again leading to the loss of
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-16
pressurizer level. Eventually, the accumulator flow and its expansion lead to the
upper head void collapsing and the pressurizer level recovers again. However, this
does not occur for another six hours.
• Fire water flow to SGs 3 and 4 is terminated at 6 hours. The inventory in SGs 3
and 4 continue to boil off.
• SG 1 and 2 levels reach the control point of 82.2% WR (+0%, -10%) at ~ 7.4 hours
and then fire water flow is reduced to maintain SG levels.
• PZR level is regained at ~ 9.4 hours and remains above zero for the remainder of
the transient.
• SG 3 and SG 4 are empty at ~ 10.8 hours. The inventory has boiled off and has
once again led to a dryout condition.
• At ~16.8 hours, the fire water storage tank is replenished. Approximately 90% of the
300,000 gallons has been used.
The analysis was terminated at 24 hours since a viable mitigation strategy was
demonstrated. The Table 4-1 core cooling acceptance criteria that the core remains
covered and subcritical were met.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-17
Figure 4-1— ELAP State A Pressurizer Pressure
Figure 4-2— ELAP State A Cold Leg Temperatures
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-18
Figure 4-3— ELAP State A Pressurizer Level
Figure 4-4— ELAP State A Steam Generator Pressure
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-19
Figure 4-5— ELAP State A Steam Generator Levels
Figure 4-6— ELAP State A Core Region Levels
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-20
4.1.3.1.2 ELAP State B – Core Cooling for Events Initiated in Modes 3 and 4 with RCS < 1000 psig and RCS > LTOP Enable Temperature
Analytical Methods
The analysis of the core response for ELAP events initiated in Modes 3 and 4
(accumulators isolated, LTOP not enabled, and SGs available) was performed using
S-RELAP5. The S-RELAP5 thermal hydraulic modeling code is described in
Section 4.1.3.1
Key Assumptions and Modeling Highlights
The analysis of core cooling for ELAP events initiated in ELAP State B that rely on the
SGs for heat removal was performed using the following key assumptions and modeling
highlights:
• The S-RELAP5 model was used with the following best estimate assumptions:
- Non-safety system capabilities (such as fire water system) are included in the
model, as appropriate.
- Best-estimate core decay heat.
- No stuck control rods.
- No single failures.
- No equipment out of service prior to event initiation.
These analysis assumptions are consistent with the requirements of Section 3.2.1,
“General Criteria and Baseline Assumptions,” of NEI 12-06 (Reference 3) as endorsed
by JLD-ISG-2012-01 (Reference 11).
• The ELAP event assumes a simultaneous loss of all AC power sources (LOOP, loss
of all EDGs, and loss of all alternate AC sources) in combination with a loss of
normal access to the UHS.
• The initiating ELAP event was assumed to occur when the reactor has been shut
down for one hour.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-21
• The ELAP event causes an immediate loss of power to the RCPs and main
feedwater pumps.
• The initial conditions of the RCS are as follows:
- PZR level is at nominal level (34%).
- RCS pressure is at 1015 psia.
- RCS average temperature is 500°F.
- All four accumulators are isolated and are not credited in the analysis.
• RCS leakage was assumed from the following two sources:
- Allowable RCS leakage per Plant Technical Specifications (11 gpm).
- RCP seal leakage. RCP seal leakage was modeled consistent with the SBO
analysis described in U.S. EPR FSAR Tier 2, Section 8.4. The RCP SSSS is
credited with limiting RCP seal leakage.
• The MSRTs are used to control pressure in the SGs so that the low head, diesel-
driven fire water pump(s) can supply water to the SGs via the EFW header.
• Core decay heat is removed by means of primary to secondary heat transfer. Core
heat is transferred from the fuel to the reactor coolant, transported to the SGs by
natural circulation, transferred to the secondary side of the SGs, and transported to
the atmosphere by steaming the SGs through the MSRTs. The SGs will be fed from
the diesel-driven fire pump(s) when the SGs have been depressurized below the fire
pump discharge pressure.
• The following key operator actions are assumed in the analysis:
- The operator ensures that the automatic closure of all three seal leak-off isolation
valves for each RCP has occurred upon detection of simultaneous loss of seal
injection and thermal barrier cooling. At 15 minutes after the RCP trip occurs, the
operator ensures that the standstill seal has closed.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-22
- RCS cooldown starts at 30 minutes after the initialization of ELAP. Steam
pressure in all four SGs is lowered at a rate that results in an RCS cooldown rate
of 90°F/hour until SG pressure decreases to 60 psia. MSRTs are then throttled
as required to control SG pressures at 60 psia.
- Fire water is fed to four SGs at 150 gpm (each) for the first six hours. SG level is
maintained at 82.2% WR (+0%, -10%) in each SG.
- After 6 hours, fire water to SGs 3 and 4 is isolated, the SG 3 and 4 MSRIV
solenoids are bypassed to maintain the valves open, and the associated
MSRCVs are left in their current position. Fire water flow is continued to SGs 1
and 2 for the remainder of the analysis to maintain SG levels, and the MSRCVs
continue to be throttled to control SG 1 and 2 pressure at 60 psia.
- The PCIP is started whenever pressurizer level is less than 60 inches (32 inches
indicated level) and RCS pressure is less than the PCIP shutoff head. The PCIP
will be stopped when RCS pressure approaches the PCIP shutoff head.
Results
S-RELAP5 cases were run to characterize the RCS response, timing of operator
actions, and latitude in potential FLEX mitigating strategies. With no mitigation actions,
core uncovering occurs in ELAP State B Modes 3 and 4 at ~ 6.6 hours. Therefore,
operator actions are required to mitigate the consequences of an ELAP event in ELAP
State B. To mitigate these events, the operators are relied upon to control SG pressure
using the MSRTs and to control SG level with supply from the diesel driven fire water
pump. The Table 4-1 core cooling acceptance criteria that the core remains covered
and subcritical are met. Primary system makeup from the PCIP is required three times
in the first 24 hours to maintain pressurizer level and primary system subcooling.
The results of the Mode 3 and 4 (ELAP State B) case are depicted in Figure 4-7 through
Figure 4-12. The key transient highlights for this case are as follows:
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-23
• At 30 minutes, an RCS cooldown of 90°F/hour is initiated with all four SGs. Once
SG pressure decreases to 60 psia, SG pressure will be controlled at 60 psia.
Cooldown with all four SGs provides a symmetric response.
• During this initial cooldown, the RCS depressurizes due to RCS contraction.
• At ~ 1.1 hours, the PZR empties due to RCS cooldown contraction and from
assumed RCS leakage.
• At 2.94 hours, the PCIP is started for the first time and is run for about one hour.
• At 3 hours, SG pressure reaches 60 psia and fire water is delivered to all four SGs.
• At 3.1 hours, the SGs are empty. SG3 empties slightly earlier than the other three
SGs due to the effects of the PZR and the slightly hotter fluid reaching the SG. SG
levels briefly go offscale but recover immediately (~ 5 minutes). As decay heat
decreases, the SG levels are increased to the control point of 82.2% WR (+0%, -
10%).
• Fire water flow to SGs 3 and 4 is terminated at 6 hours. The inventory in SGs 3
and 4 continues to boil off.
• At ~ 7.4 hours, the PCIP is started for the second time and is run for about
24 minutes.
• SGs 1 and 2 levels reach the control point of 82.2% WR (+0%, -10%) at ~ 8.1 hours
and then fire water flow is reduced to maintain SG levels.
• SG 3 and SG 4 are empty at ~ 10.1 hours. The SG inventory has continued to
slowly boil off and has once again led to a dryout condition.
• At ~ 19.7 hours, the PCIP is started for the third time and is run for about
42 minutes.
• At ~ 23.3 hours, the replenishment of the fire water storage tank is necessary.
Approximately 90% of the 300,000 gallons has been used.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-24
The analysis was terminated at 24 hours since a viable mitigation strategy was
demonstrated. The Table 4-1 core cooling acceptance criteria that the core remains
covered and subcritical were met.
Figure 4-7—ELAP State B Pressurizer Pressure
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-25
Figure 4-8—ELAP State B Cold Leg Temperatures
Figure 4-9—ELAP State B Pressurizer Level
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-26
Figure 4-10—ELAP State B Steam Generator Pressure
Figure 4-11—ELAP State B Steam Generator Level
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-27
Figure 4-12—ELAP State B Core Region Levels
4.1.3.1.3 ELAP State C – Core Cooling for Events Initiated in Modes 4 and 5 with RCS Pressurized and RCS < LTOP Enable Temperature
Analytical Methods
The analysis of the core response for an ELAP event initiated in Modes 4 and 5 (ELAP
State C – LTOP enabled and SGs available) was performed using S-RELAP5. The
S-RELAP5 thermal hydraulic modeling code is described in Section 4.1.3.1
Key Assumptions and Modeling Highlights
The analysis of core cooling for ELAP events initiated in ELAP State C that rely on the
SGs for heat removal was performed using the following key assumptions and modeling
highlights:
• The S-RELAP5 model was used with the following best estimate assumptions:
- Non-safety system capabilities (such as fire water system) are included in the
model, as appropriate.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-28
- Best-estimate core decay heat.
- No stuck control rods.
- No single failures.
- No equipment out of service prior to event initiation.
These analysis assumptions are consistent with the requirements of Section 3.2.1,
“General Criteria and Baseline Assumptions,” of NEI 12-06 (Reference 3) as endorsed
by JLD-ISG-2012-01 (Reference 11).
• The ELAP event assumes a simultaneous loss of all AC power sources (LOOP, loss
of all EDGs, and loss of all alternate AC sources) in combination with a loss of
normal access to the UHS.
• The initiating ELAP event was assumed to occur when the reactor has been shut
down for 7 hours for the Mode 4 case and 15 hours for the Mode 5 case. This is
conservative considering the amount of time necessary to reach these states from
the time of reactor shutdown.
• The ELAP event causes an immediate loss of power to the RCPs and all SG
feedwater pumps.
• The initial conditions of the RCS are as follows:
- PZR level is 90% full.
- For the Mode 4 case, RCS average temperature is 248°F. For the Mode 5 case,
RCS average temperature is 130°F.
- LTOP is enabled. The first pressurizer safety relief valve (PSRV) opens at
525 psig and the second PSRV opens at 541 psig.
- Three accumulators are isolated, but available; the fourth accumulator is active,
but depressurized to 320 psia.
- In Mode 4, two RCPs are operating and only one in Mode 5.
• RCS leakage was assumed from the following two sources:
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-29
- Allowable RCS leakage per Plant Technical Specifications (11 gpm).
- RCP seal leakage. RCP seal leakage was modeled consistent with the SBO
analysis described in U.S. EPR FSAR Tier 2, Section 8.4. The RCP SSSS is
credited with limiting RCP seal leakage.
• Core decay heat is removed by means of primary to secondary heat transfer. Core
heat is transferred from the fuel to the reactor coolant, transported to the SGs by
natural circulation, transferred to the secondary side of the SGs, and transported to
the atmosphere by steaming the SGs through the MSRTs. For these ELAP State C
cases, the RCS must heat up first in order to generate steam. The MSRTs are then
used to control the SGs at 40 psia. No secondary depressurization is required for
these ELAP State C cases because the fire pump discharge pressure exceeds the
SG control pressure.
• The following key operator actions are assumed in the analysis:
- The operator ensures that the automatic closure of all three seal leak-off isolation
valves for each RCP has occurred upon detection of simultaneous loss of seal
injection and thermal barrier cooling. At 15 minutes after the RCP trip occurs, the
operator ensures that the standstill seal has closed.
- MSRTs are opened and used to control SG pressure once the SG pressure
increases to 40 psia.
- Simultaneous with opening the MSRTs, fire water is initiated to the four SGs as
required to maintain SG levels at 82.2% WR (+0%, -10%) in each SG.
- After six hours, fire water to SGs 3 and 4 is isolated and the SG 3 and 4 MSRIV
solenoids are bypassed to maintain the valves open. The SG 3 and 4 MSRCVs
are left in the position they were in at the time of fire water isolation. Fire water
flow is continued to SGs 1 and 2 for the remainder of the analysis to maintain SG
levels. The SG 1 and 2 MSRCVs continue to be throttled as required to maintain
SG 1 and SG 2 pressures at 40 psia.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-30
Results
S-RELAP5 cases were run to characterize the RCS response, timing of operator
actions, and latitude in potential FLEX mitigating strategies. With no mitigation actions,
core uncovering occurs in both ELAP State C Modes 4 (~ 6.1 hours) and 5 (~ 10.1
hours) respectively. Therefore, operator actions are required to mitigate the
consequences of an ELAP event in ELAP State C. To mitigate these events, the
operators are relied upon to control SG pressure using the MSRTs and to control SG
level with supply from the diesel driven fire water pump. The Table 4-1 core cooling
acceptance criteria that the core remains covered and subcritical were met. Primary
system makeup from the PCIP is not required for at least 24 hours to maintain
pressurizer level and primary system subcooling.
Analyses were performed for ELAP events initiated in both Mode 4 and Mode 5 with the
steam generators available. The results for Mode 4 are more limiting than for Mode 5
because they consider a higher initial decay heat level and a higher initial RCS
temperature. Given this, the results of the limiting Mode 4 (ELAP State C) case are
depicted in Figure 4-13 through Figure 4-16. The key transient highlights for this case
are as follows:
• SG pressure initially increases and is then controlled at 40 psia for the remainder of
the transient. Steaming to the atmosphere is initiated at 0.6 hours.
• At 0.6, hours fire water flow is delivered to all four steam generators. SG levels are
then maintained at the control point of 82.2% WR (+0%, -10%).
• Fire water flow to SGs 3 and 4 is terminated at 6 hours. The inventory in SGs 3
and 4 continues to boil off.
• SG 3 and SG 4 are empty at 15.7 hours and 16.4 hours, respectively. The SG
inventory has continued to slowly boil off and led to a dryout condition.
• At 21 hours, flow from the one active accumulator begins to inject into the RCS. The
primary system pressure is then controlled by the accumulator. The accumulator
does not empty during the transient.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-31
• Sometime after 24 hours, the fire water storage tank must be replenished.
• Throughout this transient, LTOP is not actuated. Therefore, the PSRVs do not lift.
The analysis was terminated at 24 hours since a viable mitigation strategy was
demonstrated. The Table 4-1 core cooling acceptance criteria that the core remains
covered and subcritical were met.
Figure 4-13—ELAP State C RCS Pressures
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-32
Figure 4-14—ELAP State C RCS Cold Leg Temperatures
Figure 4-15—ELAP State C Steam Generator Levels
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-33
Figure 4-16—ELAP State C RCS Levels
4.1.3.1.4 ELAP State D – Core Cooling for Events Initiated in Mode 5 with RCS Filled and Pressurized (Steam Generators Unavailable)
Analytical Methods
The analysis of the core response for ELAP events initiated in Mode 5 (LTOP enabled
and SGs unavailable) was performed using S-RELAP5. The S-RELAP5 thermal
hydraulic modeling code is described in Section 4.1.3.1.
This S-RELAP5 model was used to calculate the time-to-boil and time-to-uncover the
core with the PZR level water solid. Cases were run to confirm successful primary feed
and bleed core cooling when injection of 300 gpm of water to the core was initiated at
60 minutes after event initiation.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-34
Key Assumptions and Modeling Highlights
The analysis of core cooling for ELAP events initiated in ELAP State D that rely on
primary side feed and bleed for heat removal was performed using the following key
assumptions and modeling highlights:
• S-RELAP5 was used with the following best estimate assumptions:
- Best-estimate core decay heat.
- No stuck control rods.
- No single failures.
- No equipment out of service prior to event initiation.
These analysis assumptions are consistent with the requirements of Section 3.2.1,
“General Criteria and Baseline Assumptions,” of NEI 12-06 (Reference 3) as endorsed
by JLD-ISG-2012-01 (Reference 11).
• The ELAP event assumes a simultaneous loss of all AC power sources (LOOP, loss
of all EDGs, and loss of all alternate AC sources) in combination with a loss of
normal access to the UHS.
• The initiating ELAP event was conservatively assumed to occur when the reactor
has been shut down for 16.67 hours. This is a conservative value of decay heat
assumed for this analysis; however, the overall timing constraint for entry into ELAP
State D is set by the containment GOTHIC analysis discussed in Section 4.1.3.4,
which assumed decay heat at 40 hours after shutdown.
• For the purposes of this analysis, the SGs were deterministically assumed to be
unavailable due to outage conditions.
• The ELAP event causes an immediate loss of power to the operating RHR system
pumps.
• The initial conditions of the RCS are as follows:
- PZR level is 100% full.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-35
- RCS average temperature is 130°F and RCS pressure is 370 psia.
- LTOP is enabled. The first PSRV opens at 525 psig and the second PSRV
opens at 541 psig.
- Four accumulators isolated, but available; (no accumulators are credited).
- The RCS is intact and not vented.
• RCS leakage was assumed from the following two sources:
- Allowable RCS leakage per Plant Technical Specifications (11 gpm).
- RCP seal leakage. RCP seal leakage was modeled consistent with the SBO
analysis described in U.S. EPR FSAR Tier 2, Section 8.4. The RCP SSSS is
credited with limiting RCP seal leakage.
• Since the SGs are assumed to be unavailable, core decay heat is removed by
primary feed and bleed cooling. Water from the in-containment refueling water
storage tank (IRWST) is injected into an RCS cold leg from the PCIP and then flows
through the core removing heat. The PCIP delivers at least 300 gpm at an RCS
pressure of 350 psia. Heated water, and eventually steam, from the core then flows
out the PZR PDS valves to the PRT. The PRT fills and pressurizes until one of the
PRT rupture discs bursts, which opens the RCS bleed flow path to the containment
atmosphere.
• The following key operator actions are assumed in the analysis:
- The operator ensures that the automatic closure of all three seal leak-off isolation
valves for each RCP has occurred upon detection of simultaneous loss of seal
injection and thermal barrier cooling. At 15 minutes after the RCP trip occurs, the
operator ensures that the standstill seal has closed.
- As needed, the operator latches the PSRV open after the second lift to minimize
repeated open/reseat cycles.
- At 60 minutes, the PDS valves are opened and the PCIP is started.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-36
Results
S-RELAP5 cases were run to characterize the RCS response, timing of operator
actions, and latitude in potential FLEX mitigating strategies. With no mitigation actions,
the time-to-boil was calculated as ~ 68.1 minutes and the time to uncover was
calculated at ~ 3.7 hours. Therefore, operator actions are required to mitigate the
consequences of an ELAP event in ELAP State D. To mitigate these events, the
operators are relied upon to open one set of PDS valves to provide a vent path and to
start the PCIP to establish primary side feed and bleed cooling. The Table 4-1 core
cooling acceptance criterion that the core remains covered was met as indicated by the
upper node in the core remaining below a 95% void fraction (5% liquid). The upper core
remained cooled by a two-phase mixture. The RCS was refilled from the IRWST, which
resulted in a high boron concentration in the reactor pressure vessel. As a result, the
Table 4-1 core cooling acceptance criterion for criticality was also met.
The results of the Mode 5 (ELAP State D) case are depicted in Figure 4-17 through
Figure 4-19. The key transient highlights are as follows:
• At ~ 1.2 minutes, the PSRV lifts for the first time due to LTOP actuation.
• At ~ 2.9 minutes, the PSRV lifts for the second time due to LTOP actuation. The
operator latches the PSRV open after the second lift to minimize repeated
open/reseat cycles.
• At ~ 30.5 minutes, one of the PRT rupture discs fails. The peak RCS pressure after
PRT rupture disc failure occurs at ~ 3.37 hours.
• At 60 minutes, the operators open the PDS valves and start the PCIP.
• At ~ 63.9 minutes the RCS begins to boil. Note that this time to boil is slightly
shorter than with no mitigating actions since the PCIP flow reduces the RCS
pressure, which in turn reduces the RCS saturation temperature.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-37
The analysis was terminated at ~ 5.6 hours since a viable mitigation strategy was
demonstrated. The Table 4-1 core cooling acceptance criteria that the core remains
covered and subcritical were met.
Figure 4-17—ELAP State D RCS Pressures
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-38
Figure 4-18—ELAP State D Primary Temperatures
Figure 4-19—ELAP State D RPV Volume Fractions
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-39
4.1.3.1.5 ELAP State E – Core Cooling for Events Initiated in Mode 5 with RCS Drained and Mode 6 with the RV Head Not Removed
Analytical Methods
The analysis of the core response for an ELAP event initiated in Mode 5 (RCS drained)
and Mode 6 (RV head not removed, LTOP enabled, and SGs unavailable), was
performed using S-RELAP5. The S-RELAP5 thermal hydraulic modeling code is
described in Section 4.1.3.1.
Key Assumptions and Modeling Highlights
The analysis of core cooling for ELAP events initiated in ELAP State E that rely on
primary side feed and bleed for heat removal was performed using the following key
assumptions and modeling highlights:
• S-RELAP5 was used with the following best estimate assumptions:
- Best-estimate core decay heat.
- No stuck control rods.
- No single failures.
- No equipment out of service prior to event initiation.
These analysis assumptions are consistent with the requirements of Section 3.2.1,
“General Criteria and Baseline Assumptions,” of NEI 12-06 (Reference 3) as endorsed
by JLD-ISG-2012-01 (Reference 11).
• The ELAP event assumes a simultaneous loss of all AC power sources (LOOP, loss
of all EDGs, and loss of all alternate AC sources) in combination with a loss of
normal access to the UHS.
• The initiating ELAP event was conservatively assumed to occur when the reactor
has been shut down for 16.67 hours.
• The ELAP event causes an immediate loss of power to the operating RHR system
pumps.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-40
• The initial conditions of the RCS are as follows:
- Prior to draining the RCS, the PDS valves are opened to vent the RCS to the
PRT.
- The RCS is intact with the exception of the open PDS flowpath. The pressurizer
manway will not be used as a vent during the draindown or assumed open in the
analysis.
- RCS water level at 1 foot below RV flange.
- RCS average temperature is 140°F and RCS pressure is 14.7 psia. The RCS is
vented to the PRT via the PDS valves.
- LTOP is enabled. However, the PSRVs are not actuated because the PDS flow
path provides sufficient venting.
- Four accumulators isolated, but available; (no accumulators are credited).
• Since the steam generators are unavailable, core decay heat is removed by primary
feed and bleed cooling. Water from the IRWST is injected into RCS loop 1 cold leg
from the PCIP and then flows through the core removing decay heat. The PCIP
delivers at least 300 gpm at an RCS pressure of 350 psia. Heated water, and
eventually steam, from the core then flows out of the RCS through the PZR PDS
valves to the PRT. The PRT fills and pressurizes until one of the PRT rupture discs
bursts, and then the RCS bleed flow path is directed to the containment atmosphere.
• The following key operator actions are assumed in the analysis:
- The operator ensures that the automatic closure of all three seal leak-off isolation
valves for each RCP has occurred upon detection of simultaneous loss of seal
injection and thermal barrier cooling. At 15 minutes after the RCP trip occurs, the
operator ensures that the standstill seal has closed.
- At 60 minutes, the PCIP is started.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-41
Results
S-RELAP5 cases were run to characterize the RCS response, timing of operator
actions, and latitude in potential FLEX mitigating strategies. With no mitigation actions
and the RCS at an initial water level of 1 foot below the RV flange, the time-to-boil was
calculated as ~ 2.9 minutes and the time to uncover was calculated at ~ 2 hours.
Therefore, operator actions are required to mitigate the consequences of an ELAP
event in ELAP State E. To mitigate these events, the operators are relied upon to start
the PCIP to establish primary side feed and bleed cooling. The RCS vent path is
established prior to entering ELAP State E by opening one set of PDS valves. The
Table 4-1 core cooling acceptance criterion that the core remains covered was met as
indicated by the upper node in the core remaining below a 95% void fraction (5% liquid).
The upper core remained cooled by a two-phase mixture. The RCS was refilled from
the IRWST, which resulted in a high boron concentration in the RV. As a result, the
Table 4-1 core cooling acceptance criterion for criticality was also met.
The results of the Mode 5 and 6 (ELAP State E) cases are depicted in Figure 4-20
through Figure 4-22. The key transient highlights are as follows:
• At ~ 2.9 minutes, the RCS begins to boil.
• At 60 minutes, the operators start the PCIP.
• At ~75.4 minutes, the RCS pressure peaks at 336 psia and one of the PRT rupture
discs bursts.
• Throughout this transient, LTOP is not actuated. Therefore, the PSRVs do not lift.
The analysis was terminated at ~ 5.6 hours since a viable mitigation strategy was
demonstrated. The Table 4-1 core cooling acceptance criteria that the core remains
covered and subcritical were met.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-42
Figure 4-20—ELAP State E RCS Pressures
Figure 4-21—ELAP State E Primary Temperatures
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-43
Figure 4-22—ELAP State E RPV Volume Fractions
4.1.3.1.6 ELAP State F – Core Cooling for Events Initiated in Mode 6 with the RV Head Removed
Analytical Methods
The analysis of the core response for ELAP events initiated in Mode 6 with the RCS
drained and RV head removed was performed using S-RELAP5. The S-RELAP5
thermal hydraulic modeling code is described in Section 4.1.3.1.
Key Assumptions and Modeling Highlights
The analysis of core cooling for ELAP events initiated in ELAP State F that rely on
primary side feed and bleed for heat removal was performed using the following key
assumptions and modeling highlights:
• The S-RELAP5 model was used with the following best estimate assumptions:
- Best-estimate core decay heat.
- No single failures.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-44
- No equipment out of service prior to event initiation.
These analysis assumptions are consistent with the requirements of Section 3.2.1,
“General Criteria and Baseline Assumptions,” of NEI 12-06 (Reference 3) as endorsed
by JLD-ISG-2012-01 (Reference 11).
• The ELAP event assumes a simultaneous loss of all AC power sources (LOOP, loss
of all EDGs, and loss of all alternate AC sources) in combination with a loss of
normal access to the UHS.
• The initiating ELAP event was assumed to occur when the reactor has been shut
down for 41.67 hours.
• The ELAP event causes an immediate loss of power to the operating RHR system
pumps.
• The initial conditions of the RCS are as follows:
- RV head is off.
- RCS water level is at 1 foot below the RV flange.
- RCS average temperature is 140°F and RCS pressure is 14.7 psia.
- Four accumulators isolated, but available; (no accumulators are credited).
• Since the steam generators are unavailable, core decay heat is removed by primary
feed and bleed cooling. Water from the IRWST is injected into an RCS cold leg from
the PCIP and then flows through the core removing decay heat. The PCIP delivers
at least 300 gpm at an RCS pressure of 350 psia. Heated water and steam from the
core then flows out of the top of the RV flange to the containment atmosphere.
• The following key operator actions are assumed in the analysis:
- At 60 minutes, the PCIP is started.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-45
Results
With no mitigation actions and the RCS at an initial water level of 1 foot below the RV
flange, the time-to-boil was calculated as ~ 3.3 minutes and the time to uncover was
calculated at ~ 73 minutes. Therefore, operator actions are required to mitigate the
consequences of an ELAP event in ELAP State F. To mitigate these events, the
operators are relied upon to start the PCIP to establish primary side feed and bleed
cooling. The RCS vent path is provided by the open RPV head. The Table 4-1 core
cooling acceptance criterion that the core remains covered was met. The core remains
subcritical as a result of injection of IRWST water with the PCIP. As a result, the
Table 4-1 core cooling acceptance criterion for criticality was also met.
The results of the Mode 6 (ELAP State F) case are depicted in Figure 4-23. The key
transient highlights are as follows:
• At ~ 3.3 minutes, the RCS begins to boil. Note that due to the low RCS inventory
and rapid boiling, there is a large liquid water swell from the RV into the containment
(approximately half of the RCS initial liquid inventory).
• At 60 minutes, the operators start the PCIP.
• Because the RV head is removed, LTOP is not actuated and the PSRVs do not lift.
The analysis was terminated at ~ 5.6 hours since a viable mitigation strategy was
demonstrated. The Table 4–1 core cooling acceptance criteria that the core remains
covered and subcritical were met.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-46
Figure 4-23—ELAP State F Fuel Temperature for a 60 Minute Delay in the Start of Injection
4.1.3.2 Primary Feed and Bleed Injection Requirements
For an ELAP event initiated in ELAP State D, E, or F, primary side feed and bleed
cooling is used as the method to remove core decay heat. With this core cooling
method, two types of analyses were performed:
• Core cooling analyses to determine heat removal requirements.
• Boron precipitation analyses to determine long-term core cooling requirements to
prevent boron precipitation.
4.1.3.2.1 Heat Removal Requirements
Key Assumptions
The analysis of core cooling for an ELAP event initiated in ELAP State D, E, or F was
performed using the following key assumptions:
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-47
• The RCS is adequately vented to remove core decay heat in the primary feed and
bleed mode. Methods to vent the RCS in ELAP States D, E, and F are summarized
in Table 4-2.
• Boiling in the core is acceptable for core cooling, provided the core remains covered
with liquid or two phase mixture (refer to Section 4.1.2).
• Best estimate decay heat.
• The earliest time to enter Mode 5 or Mode 6 following a normal plant shutdown is
16.67 hours. This conservative time establishes the maximum amount of core
decay heat that must be removed in ELAP State D, E, or F.
Methodology
For short-term core cooling in ELAP State D, E, or F, analysis was performed to
determine injection flow requirements.
The injection flow requirements to replace boil off was determined using:
Q = W (ho – hi)
where,
Q (BTU/hour) = Decay heat.
W (lbm/hour) = Injection flow rate.
ho (BTU/lbm) = Core exit enthalpy (this corresponds to the enthalpy of saturated
steam at 212°F).
hi (BTU/lbm) = Injection flow enthalpy corresponding to the injection flow
temperature.
Results
The calculated injection flow required to replace boil off at 16.67 hours after shutdown
was approximately 230 gpm assuming an injection flow temperature of 212°F.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-48
Based on these results, the following insights can be drawn:
• RCS makeup should be restored as quickly as practicable. At a minimum, a
continuous RCS injection rate of 230 gpm is needed to maintain adequate
inventory above the top of the fuel and remove core decay heat.
• Borated makeup water should be used as the injection source. The boron
concentration should be equivalent to the concentration of the IRWST to ensure
long-term subcriticality.
4.1.3.2.2 Boron Precipitation
Key Assumptions
The analysis of boron precipitation for an ELAP event initiated in ELAP State D, E, or F
was performed using the following key assumptions:
• The earliest time to enter ELAP State D or E following a normal plant shutdown is
approximately 16.67 hours. The earliest time to enter ELAP State F is
approximately 41.67 hours. Utilizing the decay heat at 16.67 hours after shutdown
conservatively establishes the maximum amount of core decay heat that must be
removed.
• RCS makeup flow in excess of boil off refills the RCS, and conservatively, only once
the cold-side is refilled, increases the mixing volume.
• The following additional assumptions were made consistent with U.S. EPR FSAR
Tier 2, Chapter 15, loss of coolant accident (LOCA) boron precipitation analysis:
- The boron solubility limit is 38,500 ppm based on mixing with cold IRWST water
and saturated core water at 14.7 psia.
- The boil-off rate is based on the ANS 1973 decay heat standard with 20%
uncertainty.
- There is no credit for inlet subcooling.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-49
Methodology
In ELAP State D, E, or F, core cooling is maintained in the long term by pumped flow
from the IRWST. The borated water from the IRWST provides a means for the core to
remain subcritical, but causes a boron precipitation concern because of an increase in
concentration from the decay heat boil off. An analysis was performed based on the
U.S. EPR FSAR Tier 2, Chapter 15, LOCA boron precipitation methodology to
determine the minimum injection flow rate needed to preclude boron precipitation.
The minimum flow rate to reach the solubility limit was determined. Sensitivity studies
were also performed with different flow rates and a best estimate decay heat model.
Results
Summary results of these analyses are presented in Figure 4-24. Based on these
results and the analyses performed, the following insights can be drawn:
• Even with conservative decay heat assumptions, boron solubility limits are not
approached for at least eight hours from the start of the ELAP event.
• A minimum RCS makeup flow rate of 300 gpm is sufficient to remove core decay
heat and preclude boron precipitation using the conservative assumptions of this
analysis. This result is reflected in the S-RELAP5 transient analyses for ELAP
States D, E, and F described in Section 4.1.3.1.
• An RCS makeup flow rate of 330 gpm provides margin to remove core decay heat
and preclude boron precipitation, and is recommended for long-term event
mitigation. This result is reflected in the sizing of the PCIP as shown in Table 4–21.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-50
Figure 4-24—Boron Precipitation Analysis Results
4.1.3.3 RCP Seal Leakage
Following a BDBEE that results in an ELAP event, the normal methods of cooling the
RCP seals with the RCP thermal barrier coolers and RCP seal injection are lost. The
ELAP transient is similar to the SBO event that has been evaluated in U.S. EPR FSAR
Tier 2, Section 8.4. In the U.S. EPR SBO mitigation strategy, the RCP SSSS is relied
upon to close to limit RCP seal leakage. A similar strategy can be applied to the ELAP
transient provided the plant parameters are maintained within the RCP SSSS
qualification envelope.
For SBO mitigation, qualification testing was performed to demonstrate that the RCP
SSSS would limit seal leakage to less than 0.5 gpm per pump for 24 hours. During the
qualification tests, the RCP SSSS was subjected to the temperature and pressure
profile which would bound an SBO event.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-51
Based on the qualification test results, an evaluation was performed to confirm that the
SBO qualification testing envelope bounded the ELAP primary to secondary heat
transfer cooling transient for events initiated in Modes 1 through 5 during the initial
24-hour time period. For long-term ELAP event mitigation (i.e., beyond 24 hours),
additional loss of RCP seal cooling tests are required for the standstill seal. Test
conditions will bound the full range of RCS conditions (temperature and pressure) that
are expected for long-term mitigation of an ELAP event initiated in ELAP States A, B,
and C (with SGs available for cooling).
The purpose of this qualification testing is to validate the RCP SSSS leak rate and
integrity of the SSSS when exposed to ELAP conditions on a long term basis.
ITAAC 7.9 in Table 2.2.1-5 of U.S. EPR FSAR Tier 1, Section 2.2.1 has been
established to validate the results of this testing prior to fuel load.
4.1.3.4 Containment Temperature and Pressure Control (Integrity)
Analytical Methods
Containment temperature and pressure control were evaluated using the GOTHIC
computer code. GOTHIC is a general purpose thermal-hydraulics software package for
design, licensing, safety, and operating analysis of nuclear power plant containments
and other confinement buildings. Appropriate heat transfer and fluid flow correlations
are used depending on fluid state. Special process models are used for components
such as doors, valves, heat structures, and break junctions. GOTHIC solves the
conservation equations for mass, momentum, and energy for multi-component, multi-
phase flow. The phase balance equations are coupled by mechanistic models for
interface mass, energy, and momentum transfer that cover the entire flow regime from
bubbly flow to film/drop flow, as well as single phase flows. The interface models allow
for the possibility of thermal non-equilibrium between phases and unequal phase
velocities.
GOTHIC has previously been used to analyze the containment response as discussed
in U.S. EPR FSAR Tier 2, Section 6.2. BAW-10252PA-00, “Analysis of Containment
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-52
Response to Pipe Ruptures using GOTHIC” (Reference 19), and ANP-10299P,
Revision 2, “Applicability of AREVA NP Containment Response Evaluation Methodology
to the U.S. EPR™ for Large Break LOCA Analysis Technical Report” (Reference 20),
are topical reports that justify application of the GOTHIC methodology to the U.S. EPR
design. Because the ELAP scenario is characterized by a slow, but continuous
containment pressurization and heatup, the GOTHIC containment response
methodology is an appropriate choice for this ELAP analysis.
Key Assumptions and Modeling Highlights
The GOTHIC analysis of containment response was performed using the following key
assumptions and inputs:
• The GOTHIC subdivided multi-node containment model was used as the base
model.
• As discussed in Section 4.1.2, containment integrity is conservatively ensured by
maintaining the containment pressure and temperature below the Reactor
Containment Building design basis limits (62.9 psig (77.6 psia) and 310°F).
• ELAP events were assumed to occur in states where the steam generators are
relied upon for core decay heat removal (ELAP States A, B, and C), as well as in
states where primary feed and bleed cooling is relied upon for core decay heat
removal (ELAP States D, E, and F). Plant conditions in these various ELAP States
are summarized in Table 4-2. Mass and energy releases from RCS leakage were
modeled, along with sensible energy from the primary side and secondary side.
Mass and energy releases from RCS leakage were based on the pertinent core
cooling analysis for events initiated in modes with SGs available (refer to ELAP
States A, B, and C in Section 4.1.3.1), as well as in modes with SGs unavailable
(refer to ELAP States D, E, and F in Section 4.1.3.1).
• For ELAP State D with steam generators unavailable, containment analyses
assumed a best estimate value of decay heat at 40 hours after shutdown for these
conditions.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-53
• Peak containment temperature and pressure will be limited using containment spray.
The containment spray will transport heat from the containment atmosphere into the
IRWST, which increases the IRWST temperature. Heat from the IRWST will then be
rejected to the environment through the severe accident heat removal system
(SAHRS) heat exchanger which will be cooled using a portable component cooling
water source. Using this mitigation strategy, the GOTHIC analyses were performed
subject to the following assumptions:
- The SAHRS pump is re-powered and has a nominal flow rate of 232 lb/s.
- The portable cooling water source has the same flow rate as the dedicated
component cooling water system, which is nominally 307 lb/s (~ 2218 gpm). The
temperature of the portable cooling water source is assumed to be a constant
90°F.
- The SAHRS pump is not started until 16.67 hours after the ELAP event occurs.
- For the ELAP State D case (which is the enveloping case), the ELAP event is
assumed to occur 40 hours after shutdown.
Results
GOTHIC analyses were performed to determine the general timing of containment
heatup and pressurization, to determine the limiting mode for the ELAP event accident
initiation relative to containment response, and to assess the overall feasibility of using
the containment spray to manage the containment temperature and pressure response.
Based on these analyses, the following insights can be drawn:
• For an event initiated in ELAP States A, B, and C with SGs available for core decay
heat removal, the GOTHIC analysis was run to 24 hours with no operator action.
The maximum containment pressure at 24 hours was 20.1 psia. The projected time
to reach the containment design basis pressure and temperature was greater than
48 hours.
• For an event initiated in ELAP States D, E, and F, the SAHRS pump, heat
exchangers, and portable cooling water are placed in service at 16.7 hours after the
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-54
ELAP event. The GOTHIC analyses demonstrate that the containment pressure
and temperature can be maintained within design basis limits indefinitely. Therefore,
this mitigation strategy fulfills the Table 4-1 containment acceptance criterion.
• The limiting case from a containment heat removal perspective is for ELAP events
initiated in ELAP State D. The results of the GOTHIC analysis for this limiting case
are depicted in Figure 4-25 and Figure 4-26.
• The GOTHIC containment analyses demonstrated that containment heatup and
pressurization following an ELAP event is a slow transient that provides ample time
for operator action. Containment spray represents a viable mitigation strategy to
maintain containment integrity.
Figure 4-25—Containment Pressure with Containment Spray
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-55
Figure 4-26—Containment Temperature with Containment Spray
4.1.3.5 Safeguard Buildings Heatup Analysis
Analytical Methods
The GOTHIC computer code was used to evaluate heatup of the SBs. Refer to
Section 4.1.3.4 for a description of the GOTHIC code.
• SB 1 and SB 2 were evaluated for a loss of all forced ventilation resulting from an
ELAP event. The ELAP event mitigation strategies described in Section 4.1.5
generally rely on equipment located in SB 1 and SB 2 in the long-term.
• The initial heatup of SB 3 and SB 4 was also evaluated as it relates to short-term
ELAP event mitigation. For long-term ELAP event mitigation, the only equipment
relied upon in these buildings are the SAHRS pump and associated equipment (e.g.,
switchgear). For long-term ELAP event mitigation using equipment in SB 3 and
SB 4, note that cooling of the SB 4 switchgear room that houses the switchgear that
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-56
powers the SAHRS pump is required if the portable 480V generator is used to
repower the SAHRS pump instead of the ELAP diesel generator.
SB 1 was modeled by dividing the building into homogeneous temperature regions
(control volumes) corresponding to rooms, which were evaluated individually with heat
transfer to adjoining regions being considered. These control volumes included all
rooms on the +26ʹ-7ʺ elevation and the battery room on the +15ʹ elevation. Heat loads
were modeled as heaters within each control volume. Further, note that SB 1 is
physically symmetric to SB 4.
SB 2 was modeled by dividing the building into homogeneous temperature regions
(control volumes), which were evaluated individually with heat transfer to adjoining
regions being considered. In areas with insignificant heat loads that were not expected
to challenge equipment operability limits, these areas were grouped together into a
single control volume for model simplification. Heat loads were modeled as heaters
within each control volume. Further, note that SB 2 is physically symmetric to SB 3.
Key Assumptions
The GOTHIC analyses of the SBs response were performed using the following key
assumptions and inputs:
• Since SB 1 is physically symmetric to SB 4 and SB 2 is physically symmetric to
SB 3, it was only necessary to analyze the symmetric pair with the higher heat loads
(i.e., either SB 1 and SB 2 or SB 3 and SB 4). Since the heat loads in SB 1 and
SB 2 were higher than the heat loads in SB 3 and SB 4, the GOTHIC analysis was
limited to heatup of SB 1 and SB 2. This modeling assumption ensures that the
analyzed temperatures for SB 3 and SB 4 initially (before 7 hours) remain below
acceptable limits if SB 1 and SB 2 temperatures remain below acceptable limits.
• Initially, air flow between rooms is not modeled for conservatism. The warmer
rooms will pressurize slightly resulting in a small amount of air flow through
doorways to cooler rooms. One exception to this is flow between a switchgear room
and another control volume consisting of the other switchgear room and the hall in
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-57
SB 2. The door to the switchgear room contains a two-foot by four-foot grating in it
to allow airflow. A similar door grating is also provided on the corresponding door to
the SB 3 switchgear room.
• Room temperatures begin at the maximum normal temperature and 60% humidity.
Additionally, the ambient temperature is 100°F, consistent with Section 4.1.4.1.5.
• Radiation heat transfer is neglected.
• The maximum heat input of 8.3 kW for the SB 4 switchgear room occurs when the
portable 480V generator, instead of the ELAP diesel generator, is used to power the
SAHRS pump. If the portable 480V generator is used to power the SAHRS pump, a
portable cooler with at least 8.3 kW heat removal capacity must be placed in service
to ensure that the temperature in the switchgear room remains below the
acceptance criteria. The portable cooler must be placed in service at the same time
as the Division 4 portable 480V generator.
• Since the ELAP transient is similar to the SBO event that has been evaluated in U.S.
EPR FSAR Tier 2, Section 8.4, the SBO equipment temperature acceptance criteria
were used for this evaluation. This approach is consistent with Section 3.2.1.8 of
NEI 12-06 (Reference 3).
• The following key operator actions are assumed in the analysis:
- At 30 minutes, three specified doors on the +26ʹ-7ʺ elevation of SB 1 and SB 4,
and five specified doors on the +26ʹ-7ʺ elevation of SB 2 and SB 3 are opened.
- At 7 hours, forced ventilation to SB 1 and SB 2 is restored. SB supply and
exhaust fans are not re-started for SB 3 and SB 4.
- At 25 hours, seven specified doors on the +39ʹ elevation of SB 2 are opened to
ensure that the temperature in these rooms remain below the acceptance
criteria.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-58
Results
The results of the analyses indicated that all areas of SB 1 and SB 2 were maintained
less than the acceptance criterion of 131°F. The acceptance criterion of 131°F is based
upon the temperature limit for indefinite operation of battery chargers and inverters.
The most limiting room in SB 1 was the switchgear room, which reached a temperature
of 129.1°F. The most limiting room in SB 2 was the switchgear room, which reached a
temperature of 127.2°F. After initiation of forced flow at seven hours, the temperature
trends in all areas of SB 1 and SB 2 indicated that temperatures would be maintained
less than 131°F indefinitely.
4.1.3.6 Main Control Room Heatup Analysis
Analytical Methods
The GOTHIC computer code was used to conduct a parametric study of heatup of the
MCR following a loss of forced ventilation. Refer to Section 4.1.3.4 for a description of
the GOTHIC code. The MCR was modeled as a single node with a single heat
structure comprised of concrete with a painted surface. The concrete surfaces of the
room, as well as the free volume of air, served as heat sinks. The heat load was
modeled as a heater. The parametric study examined changes in free volume, heat
source, and concrete surface area.
Key Assumptions and Modeling Highlights
The GOTHIC analysis of MCR response was performed using the following key
assumptions and inputs:
• The MCR and the shift office were assumed to constitute a single, homogeneous,
free volume with concrete walls, ceiling, and floor.
• The MCR was assumed to have a drop ceiling that reduced the available free
volume and concrete surface area. Additionally, the free volume of the MCR was
further reduced for conservatism.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-59
• The thickness of the concrete walls, floor, and ceiling was conservatively assumed
to be half the thickness. The wall was conservatively treated as an insulated
boundary, which thermally isolated the MCR from the surrounding rooms.
• The surface area of the walls, floor, and ceiling was reduced for conservatism.
• The concrete surface was assumed to be painted, with the thickness and properties
of the coating typical for painted surfaces.
• The initial room temperature was conservatively assumed to be 80°F.
Results
The parametric study demonstrated that if ventilation or cooling is not restored to the
MCR for at least seven hours following an ELAP event, then:
• The MCR temperature would not exceed 110°F for at least seven hours during an
ELAP event with a heat load less than 10 BTU/sec and an initial temperature less
than 80°F.
• The MCR temperature would not exceed 95.1°F if the heat load is not more than
5 BTU/sec.
4.1.3.7 Main Control Room Portable Cooler Sizing Evaluation
Analytical Methods
An evaluation was performed to determine the total heat input to the U.S. EPR MCR
following an ELAP event to determine the minimum performance requirements for a
portable cooler (air conditioner) for the MCR. The evaluation considered the heat loads
from personnel and MCR equipment energized during an ELAP event to determine the
total MCR heat load. This total MCR heat load was then compared against the
GOTHIC parametric study results described in Section 4.1.3.6 to confirm that heatup of
the MCR was acceptable. Additionally, this total MCR heat load was used to size a
portable cooler for the MCR.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-60
Key Assumptions
• The total heat load for the MCR is estimated at 4.36 BTU/sec. This reflects the
following assumptions:
- Five operators were assumed in the MCR with heat input from each operator
assumed to be 475 BTU/hr.
- Heat input to the MCR from emergency lighting (E-LGT) is 1.5 kW.
- Heat input from the safety information and control system (SICS) cabinets in the
MCR is assumed to be 2.4 kW.
Results
The evaluation determined that the MCR heat input rate was 4.36 BTU/sec, or about
16,000 BTU/hour. Examination of the results of the MCR heatup parametric study
described in Section 4.1.3.6 indicated that with a heat load of 5.0 BTU/sec, the MCR
temperature will rise at most to 95.1°F within seven hours. Based on these results, the
minimum portable cooler size was conservatively set at 32,000 BTU/hr (i.e., twice the
expected heat load) to provide the capability to cool down the MCR. The portable MCR
cooler would need to be placed in service within seven hours of the ELAP initiating
event to maintain acceptable temperatures in the MCR.
4.1.3.8 Spent Fuel Pool Time to Boil and Makeup Analysis
Key Assumptions and Modeling Highlights
The SFP time to boil and makeup analysis was performed using the following key
assumptions and inputs:
• During an ELAP event, spent fuel cooling by the SFP cooling system heat
exchangers is lost. Heatup of the SFP and boiling can be credited to cool the spent
fuel, provided the water level is maintained above the top of the spent fuel (refer to
Section 4.1.2). This spent fuel cooling strategy is consistent with the NRC staff
guidance given in Question 5.8.4 in NUREG-1628, “Staff Responses to Frequently
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-61
Asked Questions Concerning Decommissioning of Nuclear Power Reactors”
(Reference 25).
• SFP initial temperature is 120°F.
• The maximum SFP heat load was assumed at 130 hours after reactor shutdown
based on a full core off-load. This SFP heat load conservatively assumes at least
15% excess margin.
• Heat losses from the SFP are conservatively neglected.
• Initial SFP water level is conservatively assumed to be 55ʹ 6". This value is
conservative because it is below the elevation of the lowest non-seismic Category 1
piping penetration.
• It is assumed that the total volume of water in the SFP remains constant during
heatup. Water level increase due to density decrease is neglected.
• Ten feet of water above the top of the fuel is considered the minimum level for
adequate radiation shielding. Radiation levels in the SFP area will begin to increase
dramatically when level decreases below this point.
Analytical Methods
The SFP time to boil and makeup analysis was performed to determine the bulk SFP
heatup time and boil-off rate.
The SFP bulk heat-up time is conservatively calculated using:
Δt = MCpΔT/Q
where,
Δt (hours) is the time to complete the temperature rise.
M (lbm) is the mass of water in the SFP.
Cp (BTU/lbm°F) is the specific heat of water.
ΔT (°F) is the temperature rise.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-62
Q (BTU/hr) is the heat added to the SFP from the spent fuel stored in the pool.
The boil-off rate is calculated using:
Boil off Rate = Q / hfg
where,
Boil off Rate (lbm/hr) is the rate that mass is lost from the SFP due to boiling.
Q (BTU/hr) is the heat added to the SFP from the spent fuel stored in the pool.
hfg (BTU/lbm) is the latent heat of evaporation of water.
The evaporation time is calculated using:
Tevap = M / Boil off Rate
where,
Tevap (hours) is the time to boil down to the specified level.
M (lbm) is the mass of water above the specified level.
Boil off Rate (lbm/hr) is the rate that mass is lost from the SFP due to boiling.
Results
Based on these analyses, the following insights can be drawn:
• During a full core offload refueling condition, the time to reach SFP bulk boiling
following the loss of all SFP cooling is approximately 3.5 hours. The initial boil-off
rate is 140 gpm. The boil-off rate decreases over time as the spent fuel decay heat
decreases.
• If spent fuel cooling is not restored, then an additional 22.6 hours is available to boil
off the pool inventory while maintaining the level above the top of the spent fuel
racks (refer to Section 4.1.2). Therefore, the total time to uncover the spent fuel
(from a temperature of 120°F) is approximately 3.5 + 22.6 hours = 26.1 hours.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-63
• SFP level will boil down to 10 feet above the top of the fuel in the fuel racks 12 hours
after boiling begins (15.5 hours after initiation of the event).
• Since the operators have approximately 26.1 hours to restore cooling and/or
makeup to the SFP, boiling of the SFP can be credited as the Phase 1 event
mitigation method, and cooling and/or makeup to the SFP can be credited for
Phases 2 and 3 event mitigation.
• For conservatism, operator action at 15.5 hours after ELAP event initiation will
ensure that the SFP level remains at least 10 feet above the top of the fuel in the
fuel racks. This conservatively meets the Table 4-1 spent fuel cooling acceptance
criterion and protects the operators for local actions in proximity to the SFP.
4.1.3.9 DC Load Shedding
Analytical Methods
To determine how long the Class 1E uninterruptible power supply (EUPS) system
battery capacity can be extended during an ELAP event, the following process was
used:
• The loads on the EUPS battery were identified based on the design basis accident
EUPS battery sizing calculation and the Electrical Load List.
• Loads required for ELAP Phase 1 scenario mitigation were identified and their
operation defined.
• Loads to be shed from the EUPS battery for an ELAP event were identified.
• The time elapsed before ELAP load shedding takes place was identified.
• The ELAP EUPS duty cycle was defined by applying the ELAP Phase 1 equipment
operation and load shedding sequence to the loads supplied by the EUPS battery.
• The margins to apply for the EUPS batteries during an ELAP event were
determined.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-64
• The duration of battery discharge availability until the minimum acceptable cell
voltage is reached was determined using the EUPS battery cell type, the ELAP
EUPS duty cycle, and the ELAP margins.
Key Assumptions and Modeling Highlights
The DC load shedding analysis was performed using the following key assumptions and
inputs:
• No additional accidents or failures are assumed to occur immediately prior to or
during the event, other than those causing the ELAP event.
• Electrical equipment installed within the SBs is reasonably protected and is assumed
to remain available for the ELAP event. This equipment includes, but is not limited
to, the EUPS inverters (31/32/33/34BRU01), EUPS battery chargers
(31/32/33/34BTP02), 480V buses (31/32/33/34BRA), 250V DC switchboards
(31/32/33/34BUC), and associated cabling.
• ELAP event is identified at 10 minutes after initiation of the event after offsite power
is lost, all EDGs fail to start or load, and all SBO diesel generators fail to start or
load.
• DC load shedding is assumed to take 60 minutes to complete and is completed by
70 minutes after ELAP event initiation.
• Only those containment isolation valves identified in the U.S. EPR SBO coping
strategy (refer to U.S. EPR FSAR Tier 2, Section 8.4) and the PCIP containment
isolation valve (30JND11 AA012) are assumed to be operated for the ELAP event,
consistent with Section 3.2.1.11 of NEI 12-06.
Results
Based on this analysis, it was determined that the EUPS battery discharge duration can
be extended from two hours to eight hours and 30 minutes. The overall timeline for DC
load shedding is provided in Figure 4-27. To extend the EUPS battery capacity to this
duration, the following operator actions are required:
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-65
• Identify the ELAP event and begin DC load shedding in all four divisions of the
EUPS within 10 minutes after initiation of the ELAP event.
• Complete shedding of non-ELAP loads in all four divisions of the EUPS within 70
minutes after initiation of the ELAP event.
• Before the EUPS divisions are depleted at eight hours and 30 minutes, re-energize
credited EUPS Divisions 1 and 2 for long-term event mitigation in Phases 2 and 3
(see Section 4.1.5.1).
Figure 4-27—ELAP Battery Discharge Duration
4.1.4 Reasonable Protection of Installed and Portable Equipment
The term “reasonable protection,” within the context of this technical report, means that
the design of the SSC it is describing either meets the U.S. EPR design basis for the
applicable external hazards, or has been shown by analysis or test to meet or exceed
the U.S. EPR design basis. This definition is consistent with the definition of “robust” in
NEI 12-06 (Reference 3).
Additionally, NEI 12-06 (Reference 3) provides the following guidance:
Section 3.2, Performance Attributes, states:
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-66
“…installed equipment that is designed to be robust with respect to DBEE
is assumed to be fully available”.
Section 3.2.1.3, Initial Conditions, (6) states:
“Permanent plant equipment that is contained in structures with designs
that are robust with respect to seismic events, floods and high winds and
associated missiles are available.”
Section 3.2.1.3 (8) states:
“Installed electrical distribution systems…remain available provided they
are protected…”
Non-safety-related SSC (for example, diesel-driven fire water pump, discharge piping,
portable equipment, Fire Protection Building, and the fire water storage tanks) that are
relied upon to mitigate an ELAP event are designed to meet the FLEX reasonable
protection standards.
NEI 12-06 (Reference 3) provides the following guidance:
Section 2.3 states:
“Considering the external hazards applicable to the site, the FLEX
mitigation equipment should be stored in a location or locations such that
it is reasonably protected such that no one external event can reasonably
fail the site FLEX capability. Reasonable protection can be provided for
example, through provision of multiple sets of portable on-site equipment
stored in diverse locations or through storage in structures designed to
reasonably protect from applicable external events.”
The following subsections comprise a list of external hazards defined in Section 2 of
NEI 12-06 (Reference 3) and a description of the way in which the installed plant
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-67
equipment, both safety-related and non-safety-related, and portable equipment meet
the FLEX reasonable protection requirements.
4.1.4.1 External Hazards
4.1.4.1.1 Seismic
The Fire Protection Building and the fire water storage tanks are the only non-safety-
related structures that are credited for mitigation of an ELAP event. The Fire Protection
Building is designed for the safe shutdown earthquake (SSE) as required by Regulatory
Guide 1.189 (Reference 26) using a limiting acceptance condition characterized as
essentially elastic behavior with no damage (i.e., Limit State D per ASCE 43-05)
(Reference 23). The fire water storage tanks are designed for the SSE using
ANSI/AWWA D100-2005 (Reference 29). Design for the SSE is consistent with the
FLEX guidance.
Equipment that is credited for ELAP event mitigation is either safety-related Seismic
Category I equipment, or is non-safety-related equipment that is installed in a Seismic
Category I structure or a conventional seismic structure that is designed for the SSE
with the following clarification:
To provide adequate functionality following an SSE, the following supplemental
seismic requirements are imposed:
- For valves and piping – ANSI/ASME B31.1-2004 (Reference 24). For example,
this includes the non-safety-related piping and valves from the diesel-driven fire
water pumps to the EFW system.
- For other SSC – ASCE 43-05, “Seismic Design Criteria for Structures, Systems,
and Components in Nuclear Facilities” (Reference 23). For example, this
includes the ELAP diesel generator.
This seismic qualification strategy for non-safety-related equipment is consistent with
the seismic qualification strategy used for the non-safety-related fire protection system
(FPS) as described in U.S. EPR FSAR Tier 2, Section 9.5.1.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-68
4.1.4.1.2 Flooding
The U.S. EPR design uses a “dry site concept,” which means that the plant grade level
is located one foot above the flood elevation. This definition refers to the Seismic
Category I safety-related structures. The Fire Protection Building and the fire water
storage tanks are the only non-safety-related structures that are credited for Phase 1
event mitigation of an ELAP event. Taking this into account, the Fire Protection Building
and the fire water storage tanks will be similarly designed and constructed at least one
foot above the flood elevation.
4.1.4.1.3 Severe Storms with High Winds / Missile Protection
The Fire Protection Building and fire water storage tanks are designed for high wind
loads per ASCE 7-10 (Reference 22). In accordance with NEI 12-06 FLEX
requirements, the Fire Protection Building and the fire water storage tanks are missile
protected. The hurricane wind speed and missile spectra are defined in Regulatory
Guide 1.221 (Reference 21). The tornado wind speed and missile spectra are defined
in Regulatory Guide 1.76 (Reference 30). Selection of the high wind hazard is
consistent with U.S. EPR FSAR Tier 2, Sections 3.3 and 3.5.
4.1.4.1.4 Snow, Ice, and Extreme Cold
The Fire Protection Building and fire water storage tanks are designed for snow and ice
loading per ASCE 7-10 (Reference 22), consistent with the FLEX guidance. Minimum
temperatures for design of non-safety systems in the U.S. EPR design are based on a
best estimate, 1% exceedance value of -10°F. Because of the beyond design basis
nature of the ELAP event, design evaluations of equipment performance (safety-related
or non-safety-related) are similarly based on a best estimate, 1% exceedance value
of -10°F.
4.1.4.1.5 High Temperatures
In accordance with NEI 12-06 (Reference 3), equipment should be maintained at a
temperature within a range to support its likely function when called upon. Maximum
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-69
temperatures for design of non-safety systems are based on a best estimate, 1%
exceedance value of 100°F dry bulb / 77°F wet bulb coincident. Because of the beyond
design basis nature of the ELAP event, design evaluations of equipment performance
(safety-related or non-safety-related) are similarly based on a best estimate, 1%
exceedance value of 100°F dry bulb / 77°F wet bulb coincident.
4.1.4.2 Summary of Reasonable Protection of Installed Equipment
Table 4-3 provides a summary of the reasonable protection requirements for installed
plant equipment:
Table 4–3—Reasonable Protection of ELAP Event Mitigation Equipment
Hazard Applicability General Approach
Seismic Structure Seismic Category I or conventional seismic structures designed for the site specific SSE with limiting acceptance condition as specified in ASCE 43-05 or AWWA D100-2005 for Fire Protection Storage Tanks.
Systems and Components
Seismic Category I or reasonable protection of non-safety-related installed equipment in Seismic Category I and Conventional Seismic structures. Reasonable protection of non-safety-related equipment installed in Seismic Category I, or Conventional Seismic structures designed for the hazards in this table. The system and component design includes use of:
• ASME B31.1 – piping, valves, and supports.
• ASCE 43-05 – other equipment (e.g., pumps, diesels, electrical).
Flooding Structure Seismic Category I or Conventional Seismic structures located 1 foot above the maximum flood elevation. Note: U.S. EPR design uses a “dry site” concept for Seismic Category I structures.
High Wind Structure Seismic Category I or ASCE 7-10 for Conventional Seismic structures with wind speeds and missiles based on Regulatory Guide 1.76 and Regulatory Guide 1.221.
Snow, Ice, and Cold
Structure Seismic Category I or ASCE 7-10 for Conventional Seismic structures.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-70
Hazard Applicability General Approach Temperatures Systems and
Components Equipment (safety-related or non-safety-related) evaluated for best estimate 1% exceedance temperatures (-10°F) or reasonable protection of non-safety related equipment by storing in a Seismic Category I structure or Conventional Seismic structure designed for the hazards of this table.
High Temperatures
Structure Seismic Category I or ASCE 7-10 for Conventional Seismic structures.
Systems and Components
Equipment (safety-related or non-safety-related) evaluated for best estimate 1% exceedance temperatures (100°F dry bulb/77°F wet bulb coincident) or reasonable protection of non-safety related equipment by storing in a Seismic Category I structure or Conventional Seismic structure designed for the hazards of this table.
4.1.4.3 Reasonable Protection of Portable Equipment
The COL applicant shall provide reasonable protection for portable equipment utilized in
ELAP event mitigation. NEI 12-06, Section 2.3 provides the following guidance:
“Considering the external hazards applicable to the site, the FLEX
mitigation equipment should be stored in a location or locations such that
it is reasonably protected such that no one external event can reasonably
fail the site FLEX capability. Reasonable protection can be provided for
example, through provision of multiple sets of portable on-site equipment
stored in diverse locations or through storage in structures designed to
reasonably protect from applicable external events.”
4.1.5 Mitigation Strategies
Based on the analytical bases provided in Section 4.1.3 and the reasonable protection
requirements provided in Section 4.1.4, mitigation strategies were developed to satisfy
the overall acceptance criteria given in Section 4.1.2.
The mitigation strategies were grouped as follows:
• AC and DC Power (Section 4.1.5.1).
• Core Cooling with Primary to Secondary Heat Transfer (Section 4.1.5.2).
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-71
• Core Cooling with Primary Feed and Bleed (Section 4.1.5.3).
• Containment Integrity and Heat Removal (Section 4.1.5.4).
• Spent Fuel Cooling (Section 4.1.5.5).
• Instrumentation and Controls (Section 4.1.5.6).
• Support Functions (Section 4.1.5.7).
Details of the mitigation strategy for each of these groupings are provided in the
following subsections.
4.1.5.1 AC and DC Power
During an ELAP event, DC power is required for remote operation of electrical
switchgear, for instrumentation and control (I&C) systems, and for operation of essential
AC motor-operated valves that are battery backed. The only power sources available
during Phase 1 event mitigation are the two-hour batteries and their associated EUPS
buses. Actions are required to extend the period of time that this DC power is available.
In the U.S. EPR EUPS design, each of the 250V DC two-hour batteries
(31/32/33/34BTD01) (this form of abbreviation indicates one per division, four total
throughout the discussion) is connected to a 250V DC switchboard (31/32/33/34BUC).
One of two redundant battery chargers (31/32/33/34BTP01 or 31/32/33/34BTP02) is
connected to each 250V DC switchboard. The EUPS battery chargers BTP01 and
BTP02 are normally supplied 480V AC input power by the emergency power supply
system (EPSS). Battery charger BTP01 is supplied by EPSS load center BMC in
Divisions 1 and 4 and by EPSS motor control center (MCC) BNA02 in Divisions 2 and 3.
Battery charger BTP02 is supplied by EPSS load center BMB in all four divisions. The
battery chargers rectify the 480V AC power to 250V DC power and furnish electrical
energy for the steady-state operation of loads connected to 250V DC switchboards,
while returning its battery to a full state of charge or maintaining its battery in a fully
charged state.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-72
Each 250V DC switchboard provides input power to an inverter (31/32/33/34BRU01).
The inverter is used to transform the DC power to three phase AC power to the EUPS
buses.
For the mitigation of an ELAP event, all non-essential loads with the exception of the
I&C cabinets are segregated from essential loads on separate AC and DC buses,
referred to as “load shed buses.” Refer to U.S. EPR FSAR Tier 2, Figure 8.3-5. Each
load shed bus is connected to the associated EUPS bus or 250V DC switchboard by an
isolation device that can be remotely operated from the MCR. An ELAP condition is
identified shortly after it has been determined that the EPSS buses cannot be energized
from the EDGs or the SBO diesel generators. All load shed bus infeed isolation devices
are opened from the MCR within 60 minutes after determination that an ELAP event is
in progress to conserve the stored energy in the batteries. Nine safety automation
system (SAS) cabinets in Divisions 1 and 4, six SAS cabinets in Divisions 2 and 3, and
one SICS remote shutdown station (RSS) workstation cabinet in Divisions 1 and 4 are
de-energized locally by opening isolation devices at the cabinets. These actions extend
battery availability to eight hours and 30 minutes as discussed in Section 4.1.3.9.
Prior to depletion of the batteries, the batteries in Divisions 1 and 2 are recharged from
either a prestaged, permanently installed dedicated diesel generator or by portable
480V generators using the Divisions 1 and 2 battery chargers. Refer to Figure 4-28.
The dedicated diesel generator is located in the Fire Protection Building and is referred
to as the ELAP diesel generator. The ELAP diesel generator is also used to power
plant equipment that is credited for Phase 2 and 3 event mitigation (for example, the
PCIP). This ELAP diesel generator is provided with a diesel fuel storage tank with a
minimum capacity corresponding to eight hours of fully loaded operation. The ELAP
diesel fuel storage tank is provided with external fill connections to allow replenishment
in Phases 2 and 3.
The ELAP diesel generator has a minimum load capability of 1.2 MW. The ELAP diesel
generator minimum load capability was determined by summing all of the individual
loads to be powered from this source and adding approximately 15% margin. The loads
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-73
considered when sizing the ELAP diesel generator are listed in Table 4–4. The ELAP
diesel generator connects to 6.9kV bus 30BBH, located in the Fire Protection Building.
Bus 30BBH can provide power to Class 1E 6.9kV switchgear buses 31BDB and 34BDB.
If the ELAP diesel generator is not available, portable 480V generators will be used to
power the loads listed in Table 4–4. Three 480V portable generators are required.
Each portable generator’s minimum load capability was determined by summing all of
the individual loads in the division to be powered from the generator and adding
approximately 15% margin. The Division 1 portable generator has a minimum load
capability of 550 kW and connects to 1E 480V load center 31BMB. The Division 2
portable generator has a minimum load capability of 350 kW and connects to 1E 480V
load center 32BMB. The Division 4 portable generator has a minimum load capability of
350 kW and connects to 1E 480V load center 34BMB. Refer to Figure 4-28.
The timing of energizing the buses is dictated by when the equipment powered from the
bus is required to operate to support the ELAP mitigation strategy. This can vary
depending on plant conditions at the initiation of the ELAP event. The overall sequence
of events for equipment operation timing requirements is provided in Table 4–17 and
Table 4–18. When operation of equipment not powered from the EUPS buses or the
250V DC system is required, refer to Table 4–4 to determine the power supply for that
equipment and then refer to Table 4–5 to determine the electrical alignment necessary
to energize the required equipment power supply. Refer to U.S. EPR FSAR Tier 2,
Figures 8.3-2 and 8.3-6 for electrical single line drawings. The buses must be
energized in the order given in the applicable Table 4–5 sequence. It is possible that
some of the buses in the sequence may have already been energized when aligning
power to other equipment earlier. If that is the case, then the buses must be energized
in the required sequence, starting with the first deenergized bus in the sequence. Prior
to energizing each bus, all loads on the bus except those listed in Table 4–4 must be
stripped from the bus. These operator actions will ensure that required loads are
powered, unnecessary loads are stripped, and EUPS battery capacity is extended in a
manner consistent with the analysis.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-74
This AC and DC repowering mitigation strategy for ELAP event mitigation reflects the
following considerations:
• At least two 250V DC switchboards (Divisions 1 and 2) and their associated EUPS
buses must be powered from the ELAP diesel generator because all systems are
not four-division or four-train redundant, and certain equipment requires power from
a minimum of two EUPS divisions to be operable. The main steam relief isolation
valves (MSRIVs), for example, each require two EUPS divisions to be operable.
Other required ELAP event mitigation equipment, like the communications
equipment and special E-LGT, is not four-division or four-train redundant.
• Events utilizing primary to secondary heat transfer require all four divisions of EUPS
buses to be operable for the first six hours to allow the use of four SGs during
symmetric cooldown of the primary system.
• The Division 3 and Division 4 250V DC switchboards and their associated EUPS
buses are de-energized by eight hours and 30 minutes after initiation of the event
prior to depletion of their associated batteries. All loads are stripped from the
Division 3 and Division 4 250V DC switchboards and EUPS buses, and then the
associated battery isolation device is opened. These actions are performed for
equipment protection of the batteries and are not required for event mitigation.
• The plant operators have ample time (eight hours and 30 minutes after initiation of
the event) to repower EUPS Divisions 1 and 2.
• During ELAP event mitigation, an exception exists to the use of the ELAP DG or the
portable generators to repower electrical buses for equipment operation. When
primary feed and bleed cooling is relied upon to mitigate events initiated in ELAP
State D (refer to Table 4-2), operator action is required to open one set of PDS
valves. To accomplish this action, the Division 4 EUPS bus 34BRA is used to
backfeed power to 34BRB via 34BNB02 and 34BNB03 to energize the Division 4
powered valves. In this event, the PDS valves must be opened within one hour, and
the backfeed alignment requires fewer operator actions than using the ELAP diesel
generator or a portable generator.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-75
• The voltage regulating transformers feeding 31BNB02 and 32BNB02 and the
downstream buses (31/32BNB03, 31/32BRB) will only be energized long enough to
align the required loads and will then be de-energized. As a result, the long term
heat load from the voltage regulating transformers feeding 31BNB02 and 32BNB02
was not included in the SB heatup analyses described in Section 4.1.3.5.
• Various AC powered valves are used for ELAP event mitigation that are powered
from their respective EUPS “valve” buses (31/32/33/34 BRA). In Divisions 1 and 2,
the 31BRA and 32BRA “valve” buses will be repowered from the Division 1 and 2
battery chargers (31BTP02 and 32BTP02). These battery chargers are included on
the Table 4–4 ELAP load list. In Divisions 3 and 4, the valves will be placed in their
required position prior to depletion of the Division 3 and 4 batteries. Given this, the
following valves were also credited for ELAP event mitigation, but are not included in
Table 4–4 since they are powered from their respective EUPS “valve” buses
(31/32/33/34 BRA).
- EFW discharge header cross-connect valves.
- Fire water to EFW discharge header isolation valves.
- PCIP motor operated discharge throttle valve (30JND11 AA012).
- RCP seal No. 1, No. 2, and No. 3 seal leak-off isolation valves.
- RCP SSSS nitrogen injection isolation valves.
- Accumulator injection isolation valves.
- Accumulator vent control valves.
- Accumulator vent line isolation valves.
- Pressurizer continuous degasification isolation valves.
- Pressurizer safety relief valves.
- Main steam isolation valves.
- Main steam relief isolation valves.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-76
- Main steam relief control valves.
- Letdown line isolation valve.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-77
Table 4–4—ELAP Loads
ELAP Loads Description ELAP Loads ID Power Supply
Battery Charger 2 Div 1 31BTP02 31BMB Div 1 Class 1E 480V Load Center
Battery Charger 2 Div 2 32BTP02 32BMB Div 2 Class 1E 480V Load Center
IRWST 3-Way Valve 30JNG10 AA001 31BNB02 Div 1 1E 480V MCC
MHSI Control Valve Train 1 30JND10 AA103 31BNB02 Div 1 1E 480V MCC
MHSI Large Minimum Flow Isolation Valve Train 1 30JND10 AA005 31BNB02 Div 1 1E 480V MCC
MHSI Outside Containment Isolation Valve Train 1 30JND10 AA002 31BNB03 Div 1 1E 480V MCC
MHSI Small Minimum Flow Isolation Valve Train 1 30JND10 AA004 31BNB02 Div 1 1E 480V MCC
PDS Line 1 First Isolation Valve 30JEF10 AA004 31BRB Div 1 Non-1E 480V MCC
PDS Line 1 Second Isolation Valve 30JEF10 AA005 34BRB Non-1E 480V MCC
PDS Line 2 First Isolation Valve 30JEF10 AA006 31BRB Div 1 Non-1E 480V MCC
PDS Line 2 Second Isolation Valve 30JEF10 AA007 34BRB Non-1E 480V MCC
Portable Cooler for Control Room N/A 32BNB01 Div 2 1E 480V MCC
Portable Cooler for Switchgear Room Div 4 N/A 34BNB01 Div 4 1E 480V MCC
PCIP 30JND11 AP002 31BMB Div 1 Class 1E 480V Load Center
SAHRS Pump 30JMQ40 AP001 34BDC Div 4 Class 1E 6.9 KV Switchgear
SBVSE (Electrical Division of SB Ventilation System) Train 1 Battery Room Fan
30SAC51 AN001 31BNB01 Div 1 1E 480V MCC
SBVSE Train 1 Exhaust Fan 30SAC31 AN001 31BNB01 Div 1 1E 480V MCC
SBVSE Train 1 Supply Fan 30SAC01 AN001 31BNB01 Div 1 1E 480V MCC
SBVSE Train 2 Battery Room Fan 30SAC52 AN001 32BNB01 Div 2 1E 480V MCC
SBVSE Train 2 Exhaust Fan 30SAC32 AN001 32BNB01 Div 2 1E 480V MCC
SBVSE Train 2 Supply Fan 30SAC02 AN001 32BNB01 Div 2 1E 480V MCC
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-78
Table 4–5—ELAP Electrical Bus Alignments
To Energize Bus From ELAP DG From Portable 480V
Generator (PG) From Division 4
EUPS Bus 34BRA
34BDC Div 4 Class 1E 6.9 KV Switchgear
ELAP DG 30BBH 34BDB 34BDCPG4 34BMB 34BDB 1 34BDC
N/A
31BMB Div 1 Class 1E 480V Load Center
ELAP DG 30BBH 31BDB 31BMB PG1 31BMB N/A
32BMB Div 2 Class 1E 480V Load Center
ELAP DG 30BBH 31BDB 32 BDA 32BDB 32BMB
PG2 32BMB N/A
31BNB01 Div 1 1E 480V MCC ELAP DG 30BBH 31BDB 31BMB 31BNB01
PG1 31BMB 31BNB01 N/A
31BNB02 Div 1 1E 480V MCC ELAP DG 30BBH 31BDB 31BMB 31BNB02 3
PG1 31BMB 31BNB02 3N/A
31BNB03 Div 1 1E 480V MCC ELAP DG 30BBH 31BDB 31BMB 31BNB02 3 31BNB03 3
PG1 31BMB 31BNB02 3 31BNB03 3
N/A
32BNB01 Div 2 1E 480V MCC ELAP DG 30BBH 31BDB 32 BDA 32BDB 32BMB 32BNB01
PG2 32BMB 32BNB01 N/A
34BNB01 Div 4 1E 480V MCC N/A PG4 34BMB 34BNB01 N/A
31BRB Div 1 Non-1E 480V MCC 4 ELAP DG 30BBH 31BDB 31BMB 31BNB02 3 31BNB03 3 31BRB 3
PG1 31BMB 31BNB02 3 31BNB03 3 31BRB 3
N/A
34BRB Non-1E 480V MCC 4 N/A N/A 34BRA 34BNB02 1, 3 34BNB03 3 34BRB 1, 2, 3
Table Notes:
1. Backfeed to bus.
2. Mechanical interlock must be defeated to close both feeder breakers on 34BNB03.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-79
3. Deenergize after using.
4. Alignment is only required if power from the 12 hour battery is not available. This alignment allows the PDS valves to
be repowered.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-80
Figure 4-28—Electrical Distribution and Repowering EUPS
4.1.5.2 Core Cooling with Primary to Secondary Heat Transfer
Primary to secondary heat transfer is utilized for core cooling whenever the SGs are
available. This corresponds to plant ELAP States A, B, and C (refer to Table 4-2). The
timing of transient events and required action times may vary depending on the ELAP
state at the time of ELAP event initiation. For ELAP events that rely on primary to
secondary heat transfer for core cooling, refer to the sequence of events in Table 4–17
for required action times.
During primary to secondary heat transfer, heat is transferred from the fuel to the
reactor coolant, transported to the SGs by natural circulation, transferred to the
secondary side of the SGs, and then transported to the atmosphere by steaming the
SGs through the MSRTs.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-81
Three main functional objectives must be satisfied to effectively provide core cooling for
events initiated in Modes 1 through 5 with SGs available (i.e., ELAP States A, B, and C)
using primary to secondary heat transfer:
• RCS inventory control.
• Primary heat removal.
• Reactivity control.
An overview of the mitigation strategies for these functional objectives is provided in
Table 4–6. Details of the mitigation strategies for each of these functional objectives
are provided in the following subsections.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-82
Table 4–6—FLEX Capability – Core Cooling Summary – Modes 1 through 5 with SGs Available
ELAP Function Method Phase 1 Phase 2 and 3
Co
re C
oo
ling
Reactor Core Cooling and Heat Removal (Events initiated in Modes 1 through 5 with SGs available)
• Use primary to secondary heat transfer for decay heat removal with diesel-driven fire pump to feed SGs via EFW header.
• Depressurize SGs with MSRTs to facilitate feedwater delivery (if required).
• Throttle MSRCVs to control SG pressure.
• Provide sustained source of feedwater.
• Seismically qualified diesel-driven fire pump to EFW header.
• Steam lines are isolated by closing MSIVs.
• SGs are depressurized symmetrically using MSRTs if required.
• After secondary feed established, MSRCVs throttled to control SG pressure.
• SG feed is sufficient to restore SG level with installed equipment following SG dryout (ELAP States A and B).
• SG feed is sufficient to maintain SG level with installed equipment (ELAP State C).
• Fire water storage tanks and building designed for FLEX reasonable protection requirements.
• Permanent connections (primary and alternate) for portable, self-powered, SG feed pump.
• Portable means to refill fire water storage tank to extend baseline coping.
• Portable means to refill fire pump diesel tanks and lube oil to extend baseline coping.
RCS Inventory Control/Long-Term Subcriticality
• Low leakage RCP seals.
• Borated RCS makeup.
• RCS inventory loss pathways (e.g., letdown) isolated during initial event mitigation.
• RCP SSSS actuated to limit RCP seal leakage during initial event mitigation.
• In initial plant ELAP States A and C, borated RCS makeup provided by the accumulators.
• Seismically qualified RCP SSSS equipment.
• PCIP is used for makeup when RCS pressure is < 350 psi. PCIP is powered from either ELAP diesel generator in the Fire Protection Building or from a portable generator.
• Borated water source is provided from IRWST.
• Seismically qualified PCIP.
Key Reactor Parameters
• SG level.
• SG pressure.
• RCS pressure.
• RCS temperature.
• Instruments powered by Class 1E DC bus.
• DC load shedding used to extend baseline coping.
• Power Divisions 1 and 2 Class 1E batteries using either the ELAP diesel generator in the Fire Protection Building or by portable generators.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-83
4.1.5.2.1 RCS Inventory Control
Adequate core cooling is provided by maintaining the liquid or two-phase mixture level
in the RV above the top of the fuel in the core (refer to Section 4.1.2). RCS inventory
control is challenged during an ELAP event by the loss of all AC powered RCS injection
sources and by the potential for increased RCP seal leakage resulting from overheating
of the RCP seals. Mitigation of the challenge to core cooling requires a source of
makeup to the RCS, as well as minimization of RCS inventory losses.
Accumulators are not available in all ELAP States as shown in Table 4-2. Specifically,
note the following:
• Four accumulators are available and are credited during events initiated in ELAP
State A.
• One accumulator may be available and depressurized to 320 psia, but is not
credited during events initiated in ELAP State B.
• One accumulator is available and depressurized to 320 psia, and is credited during
events initiated in ELAP State C.
The reduction in RCS pressure resulting from primary to secondary heat transfer during
SG depressurization enables the accumulators to inject borated water for RCS
inventory makeup and reactivity control. In ELAP State A, approximately 37,000 gallons
of accumulator inventory is available to make up for RCS contraction and leakage until
pumped injection can be placed into service. In ELAP State C, approximately 9,250
gallons of accumulator inventory is similarly available.
Section 4.1.3.1 describes analyses that were performed to characterize the RCS
response to an ELAP event initiated in Modes 1 through 5 with SGs available (i.e.,
ELAP States A, B, and C). These results indicated that some accumulator injection did
occur in ELAP States A and C, but the accumulators did not empty. The injection of
accumulator inventory allows later start of the PCIP for RCS makeup for these ELAP
states. This combination of accumulators and PCIP for borated makeup allows the
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-84
accumulators to be isolated or vented to prevent nitrogen injection into the RCS when
the PCIP is placed in service.
The PCIP will be operated as required to maintain adequate RCS inventory in Phase 2
and Phase 3 of the event. To implement primary makeup using the PCIP, the following
valve lineup in Table 4–7 will be performed. The power supplies and their alignment to
the PCIP and the respective motor operated valves during the ELAP event are
described in Section 4.1.5.1.
Table 4–7—Primary Coolant Injection Valve Alignment
Valve ID Description Position
30JNK10 AA001 IRWST Three-way Isolation Open to PCIP
suction 2
30JND11 AA008 Manual PCIP Suction Isolation Open
30JND11 AA009 Manual PCIP Suction Isolation Open
30JND11 AA012 PCIP Motor Operated Discharge Throttle Valve Open 1
30JND10 AA002 MHSI Outside Containment Isolation Valve Train 1 Closed
30JND10 AA004 MHSI Small Minimum Flow Isolation Valve Train 1 Closed
30JND10 AA005 MHSI Large Minimum Flow Isolation Valve Train 1 Closed
30JND10 AA103 MHSI Control Valve Train 1 Open
Table Notes:
1. Motor-operated discharge throttle valve (30JND11 AA012) is administratively closed
and de-energized in Modes 1 to 4.
2. Valve is normally open to PCIP suction and fails as is.
Once the valve alignment is complete, the PCIP will be operated as required to maintain
adequate RCS inventory when RCS pressure is less than 350 psia. The analyses for
these ELAP States indicated that RCS pressure will be below 350 psia by the time
pumped primary injection is required to maintain RCS inventory.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-85
Control of RCS leakage is required for adequate RCS inventory control. RCS inventory
loss can occur through three pathways:
• RCS letdown.
• PZR continuous degasification line.
• RCP seals.
The letdown line isolation valve (30KBA10 AA001) is automatically closed upon
detection of low EDG bus voltage in all four electrical divisions for greater than
30 seconds (refer to U.S. EPR FSAR Tier 2, Figure 9.3.4-1, Sheet 1 of 9). The letdown
line isolation valve is powered from the Division 1 EUPS (31BRA) and fails as-is upon a
loss of power after isolation.
The flow through the PZR continuous degasification line is limited to a small value by a
flow restriction. The PZR continuous degasification isolation valves (30JEF10 AA503
and 30JEF10AA504) are closed by the operator when time is available (refer to U.S.
EPR FSAR Tier 2, Figure 5.1-4, Sheet 3 of 7). The PZR continuous degasification
isolation valves are powered from the Division 1 and Division 4 EUPS buses (31BRA
and 34BRA) and fail as-is upon a loss of power after isolation.
The RCPs are provided with an SSSS to limit RCP seal leakage during loss of seal
cooling events (refer to Figure 4-29). The SSSS is a static seal located above the
Number 3 seal, between the Number 3 seal housing and the pump coupling sleeve. It
consists of a ring piston surrounding the pump shaft, which moves up under nitrogen
pressure to land on the counter-ring of the shaft (closing annular space “E” in
Figure 4-29). When the static seal is open, the piston is located on the bottom side of
the Number 3 seal housing. To engage the SSSS, the piston is raised by injecting
nitrogen under the piston until it comes into contact with the counter-ring. The leak
tightness is created by metal to metal contact. The standstill seal is kept closed by both
gas pressure and RCS pressure. If the gas pressure is lost, the RCS pressure can
maintain the standstill seal in a closed position provided the RCS pressure is greater
than or equal to 218 psig. The static seal is equipped with springs between the top of
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-86
the piston and the end of the static seal housing. These springs are designed to return
the piston to the down position when there is no actuation pressure and no pressure
downstream of the Number 3 seal. Static sealing between the components (for
example, piston and housing) is provided by O-rings designed for high temperatures.
Consistent with the strategy used for SBO mitigation (see U.S. EPR FSAR Tier 2,
Section 8.4), the seal leak-off isolation valves are automatically closed upon detection of
simultaneous loss of seal injection and thermal barrier cooling. The standstill seal will
automatically close 15 minutes later, after the RCP shaft has stopped rotating. The
operators will ensure that all three seal leak-off isolation valves on each RCP have
closed. At 15 minutes after the RCP trip occurs, the operators will verify that the
standstill seal has closed. All of the valves required to change position for SSSS
closure and seal return isolation are powered from the EUPS two-hour batteries and fail
as-is upon a loss of power after actuation. Closure of the SSSS and seal return
isolation valves on all four RCPs limits total RCP seal leakage to less than or equal
to 2 gpm.
Figure 4-29—RCP SSSS
4.1.5.2.2 Primary Heat Removal
Primary heat removal is required to remove the decay heat transferred from the core to
the RCS. Additional primary heat removal, in excess of core decay heat, is required in
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-87
ELAP States A and B to depressurize the RCS to allow low pressure makeup sources
(accumulators, PCIP) to be used for RCS inventory control during an ELAP event. The
mitigation strategy for an ELAP event initiated when SGs are available in Modes 1
through 5 (i.e., ELAP States A, B, and C) utilizes primary to secondary heat transfer for
primary heat removal. Primary to secondary heat transfer requires a source of
feedwater to the SGs and a path to relieve steam from the SGs. Refer to simplified
Figure 4-30.
The fire water storage tanks are used as a source of feedwater to the SGs during
Phase 1 of the event. Two 300,000 gallon steel lined concrete storage tanks are
provided (Tank 1 is assumed to be available for supplying a feedwater source, while
Tank 2 is assumed to be available for firefighting). These tanks meet the NEI FLEX
standards for reasonable protection. Each tank is provided with a six-inch seismically
qualified connection to allow the tanks to be refilled using a portable self-powered pump
during Phase 2 and Phase 3 event mitigation.
The diesel-driven fire pumps are used to pump fire water to the EFW discharge
cross-connect header to supply feed to the SGs during event mitigation. Refer to U.S.
EPR FSAR Tier 2, Figure 9.5.1-1 and Figure 10.4.9-1. The diesel-driven fire pumps
take suction on the fire water storage tanks. These diesel-driven fire pumps and their
associated diesel fuel storage tanks are located in the Fire Protection Building. The Fire
Protection Building meets the FLEX standards for reasonable protection. The diesel
fuel storage tanks for the fire pumps are provided with external fill connections to allow
fuel replenishment during Phases 2 and 3 of event mitigation.
A permanently installed, seismically qualified six-inch pipe is provided between the fire
pump discharge header and the EFW discharge cross-connect header. This piping
includes a manual isolation valve (30SGA01 AA091) inside the Fire Protection Building.
The line is routed underground into SB 1. Routing the line underground provides
reasonable protection of the line. Two motor-operated isolation valves
(30LAR55 AA005 and 30LAR55 AA002) are provided on this line inside SB 1. Both
motor-operated isolation valves are powered from EUPS Train 1 bus 31BRA. A check
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-88
valve (30LAR55 AA001) is also provided between the downstream motor-operated
valve and the EFW discharge cross-connect header to prevent reverse flow from the
EFW system. Motor operated isolation valve 30LAR55 AA002 and check valve
30LAR55 AA001 are safety related and provide redundant isolation between the safety
related EFW system and the non-safety related fire water system.
A hose connection is provided on a four-inch vent valve (30LAR54 AA501) on the EFW
discharge cross-connect header in SB 4. This connection provides additional defense-
in-depth by allowing the FPS in SB 4 to supply feed to the SGs by manually connecting
a hose between the fire system and the EFW discharge header vent.
Provisions are included for installation of a portable self-powered pump to supply SG
feedwater during Phases 2 and 3. Two connections (N+1) are provided for the portable
pump discharge on the line connecting the fire pump discharge header to the EFW
discharge cross-connect header. One of these connections is located at the Fire
Protection Building and the other is located at the exterior of SB 1. A connection is also
provided on the fire water storage tanks outlet cross-connect line to provide suction to
the portable pump from the fire water storage tanks.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-89
Figure 4-30—Primary to Secondary Heat Transfer Simplified Diagram
The valve alignment listed in Table 4–8 is performed to align fire water to the SGs. The
power supplies and alignment to the respective motor operated valve during the ELAP
event for loads not powered from EUPS buses or the 250V DC system are described in
Section 4.1.5.1.
Table 4–8—Fire Water to SGs Valve Alignment
Valve ID Description Position
30SGA01 AA091 Fire Water to EFW Manual Isolation Valve Open
30LAR55 AA005 Fire Water to EFW Motor Operated Isolation Valve Open
30LAR55 AA002 Fire Water to EFW Motor Operated Isolation Valve Open
30LAR14 AA001 EFW Discharge Cross-Connect Valve to Train 1 Open
30LAR24 AA001 EFW Discharge Cross-Connect Valve to Train 2 Open
30LAR34 AA001 EFW Discharge Cross-Connect Valve to Train 3 Open
30LAR44 AA001 EFW Discharge Cross-Connect Valve to Train 4 Open
30LAR11 AA105 EFW SG Level Control Valve Train 1 Open 1
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-90
Valve ID Description Position
30LAR21 AA105 EFW SG Level Control Valve Train 2 Open 1
30LAR31 AA105 EFW SG Level Control Valve Train 3 Open 1
30LAR41 AA105 EFW SG Level Control Valve Train 4 Open 1
30LAR11 AA006 SG Isolation Valve Train 1 Open 1
30LAR21 AA006 SG Isolation Valve Train 2 Open 1
30LAR31 AA006 SG Isolation Valve Train 3 Open 1
30LAR41 AA006 SG Isolation Valve Train 4 Open 1
Table Notes:
1. Valve is normally open and fails in position.
Manual isolation valve (30SGA01 AA091) inside the Fire Protection Building is normally
maintained open.
The EFW discharge cross-connect valves are closed during normal operation. These
valves are also used to throttle flow to the SGs when required. The valves are powered
from their respective divisional EUPS buses. The valves can be manually positioned
locally if power is not available.
The EFW SG level control valves and the SG isolation valves are open during normal
operation and fail as-is when power is lost to the valves as a result of DC load shedding.
The SG steaming paths are provided by the MSRTs. Each SG is provided with an
MSRT that consists of an MSRIV in series with an MSRCV. Steaming one of the SGs
requires opening the MSRIV and throttling the MSRCV to achieve the desired steam
flow.
The MSRIVs (30LBA13/23/33/43 AA001) are pilot-operated valves and are opened by
venting pressure from the area above the main operating piston. Since the MSRIVs are
pilot operated valves, SG pressure must be maintained above a minimum of
approximately 40 psia to provide the motive force to open the MSRIVs. Each MSRIV
has four solenoid-operated pilot valves that are arranged as two pilot valves in series on
each of the two redundant control lines. Two pilot valves in series must be energized to
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-91
vent the steam pressure and maintain the MSRIV open. If the pilot valves are de-
energized, they close and, if at least one pilot valve in each control line is closed, the
MSRIV closes. Each of the four solenoid-operated pilot valves is powered from a
different EUPS division. The solenoid power supplies are assigned in such a way that
Divisions 1 and 2 powered solenoids are in series on one control line, and Divisions 3
and 4 powered solenoids are in series on the other control line. Therefore, the MSRIVs
can be remotely opened from the MCR whenever SG pressure is greater than 34.7 psia
using control power from Divisions 1 and 2. Additionally, note that none of the
automatic functions of the MSRIVs are available due to DC load shedding of the SAS
cabinets.
Additional defense-in-depth is provided by a third control line that is arranged in parallel
with the other two control lines. The third control line has two manual valves in series to
provide a power independent means to open the MSRIV locally. The MSRIV opens
when both of the manual valves in the third control line are opened.
The MSRCVs are powered from their respective divisional EUPS buses. Power from all
four EUPS buses is available during the period of SG depressurization. The MSRCVs
can be remotely controlled from the MCR as long as their associated EUPS bus is
energized, but no automatic functions of the valve are operable due to DC load
shedding of the SAS cabinets. The valves fail as-is if power is lost, and are provided
with the capability for local manual control.
To mitigate ELAP events initiated in ELAP States A and B, the results of analyses
described in Sections 4.1.3.1.1 and 4.1.3.1.2 demonstrate that the core can be
adequately cooled if all four SGs and MSRTs are used for controlled depressurization.
All four MSIVs are closed to isolate downstream non-safety related piping. A controlled
depressurization of all SGs is initiated at 30 minutes by opening all four MSRIVs
(30LBA13 AA001, 30LBA23 AA001, 30LBA33 AA001, and 30LBA43 AA001) and by
remotely controlling all four MSRCVs (30LBA13 AA101, 30LBA23 AA101,
30LBA33 AA101, and 30LBA43 AA101) from the MCR to achieve an RCS cooldown
rate of 90°F/hr.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-92
The analysis of an ELAP event initiated in ELAP States A and B indicated that dryout of
the SGs occurs because SG pressures cannot be reduced fast enough to allow feed
from fire water prior to depleting the SG secondary inventory. SG dryout would be
detected by rapidly decreasing SG pressures and SG levels near zero. When SG
dryout is detected, the operators will remotely adjust all four MSRCVs from the MCR to
control SG pressures at the required pressure. Additionally, note that one diesel-driven
fire pump will be started and aligned to the SGs prior to dryout.
When dryout occurs, SG pressures rapidly decrease. As SG pressures drop below the
shutoff head of the diesel-driven fire pumps, flow begins to the SGs. The diesel-driven
fire pumps were conservatively assumed to have a capacity of greater than 2500 gpm
at 185 psi (capacity of the pumps is 2500 gpm at 213 psi). A minimum of 600 gpm
(150 gpm to each of the four SGs) is delivered to the SGs when SG pressures are
100 psia.
Feed flow to the SGs is reestablished and the RCS starts cooling again. SG levels
begin to recover at some later time (refer to Table 4–16 for transient event timing).
When SG levels have reached normal level (82.2% wide range), the EFW discharge
cross-connect valves (30LAR14 AA001, 30LAR24 AA001, 30LAR34 AA001, and
30LAR44 AA001) are throttled from the MCR to control level between 72.2% and 82.2%
wide range to prevent overfill.
ELAP events initiated in ELAP State C require a somewhat different sequence of
actions because the RCS must heat up first before primary to secondary heat transfer
can be established. The results of analyses described in Section 4.1.3.1.3 for ELAP
events initiated in ELAP State C demonstrate that the core can be adequately cooled.
For ELAP State C, MSRTs are used to control all four SG pressures at 40 psia and
adequate feedwater is provided from fire water to maintain SG levels.
In ELAP State C, the SGs are low enough in pressure to allow immediate fire water feed
to the SGs at the start of the event. SGs are initially at the required level and are
maintained using the feedwater from fire water.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-93
All four MSIVs are closed to isolate downstream non-safety related piping. The RCS
will begin to heat up due to loss of heat removal by RHR. Once RCS Thot exceeds
212°F, SG pressures will begin to increase. When SG pressures increase to 40 psia, all
four MSRIVs are opened and all four MSRCVs are throttled as necessary to control SG
pressures at 40 psia. A fire water pump is started and aligned to feed all four SGs. As
SG levels begin to decrease due to steaming through the MSRTs, the EFW discharge
cross-connect valves are throttled as required to maintain SG levels between 72.2%
and 82.2% wide range level.
For all ELAP States (A, B, C) in which primary to secondary heat transfer is used for
core cooling, certain long term actions are required to maintain core cooling. Battery
chargers are not reenergized on Divisions 3 and 4, so the Division 3 and 4 EUPS buses
and 250V switchgear will be depleted at approximately 8.5 hours. This results in loss of
power to the Division 3 and 4 EFW cross-connect valves and MSRCVs. The MSRIVs
will remain open as long as SG pressure is greater than approximately 40 psia because
all four MSRIVs have the pilot valves in one of their pilot flow paths powered from
Divisions 1 and 2. At six hours, the EFW cross-connect valves to SG 3 and SG 4 will be
closed. The MSRCVs will be left in their throttled position. This alignment will allow the
existing SG 3 and SG 4 inventory to be boiled off until the MSRIVs on those SGs close
due to low steam pressure.
The fire water storage tank will eventually approach depletion. The fire water storage
tank must be replenished from other sources using the fill connections provided, or a
portable pump and water supply must be placed in service prior to tank depletion.
The diesel-driven fire pump fuel oil storage tanks require replenishment prior to
depletion utilizing the provided external fill connections. The fuel oil storage tank sizing
and diesel fuel usage at the required fire water flow rates provide reasonable assurance
that replenishment is not required until three and a half days after the event.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-94
4.1.5.2.3 Reactivity Control
Reactivity control is required to provide reasonable assurance that criticality does not
occur due to the positive reactivity addition caused by RCS cooling. During events
initiated in ELAP State A, the reduction in RCS pressure resulting from primary to
secondary heat transfer enables the accumulators to inject borated water for RCS
inventory makeup and reactivity control. During events initiated in ELAP State B,
operator actions to start the PCIP with suction from the IRWST are relied upon for
inventory control as described in Section 4.1.5.2.1. These actions also provide
reactivity control in ELAP State B. ELAP State C is a heatup event. The analysis
described in Section 4.1.3.1.3 verified that adequate shutdown margin was available to
maintain the reactor subcritical, even considering the most positive moderator
temperature coefficient value at beginning of life. Reactivity control in Phase 2 of event
mitigation in ELAP States A, B, and C is accomplished by operation of the PCIP for
RCS inventory control, which will inject borated water into the RCS.
Section 4.1.3.1 describes the analyses that were performed to characterize the core
response to an ELAP event initiated in all ELAP States. These results indicated that the
reactor is maintained subcritical throughout the event.
4.1.5.3 Core Cooling with Primary Feed and Bleed
Primary feed and bleed cooling is utilized for core cooling whenever the SGs are not
available. This corresponds to ELAP States D, E, and F (refer to Table 4-2). The timing
of transient events and required action times may vary depending on the plant state at
the time of event initiation. Refer to Table 4–18 to determine required action times.
During primary feed and bleed cooling, heat is transferred from the fuel to the reactor
coolant in the RV. The reactor coolant in the vessel will heat up to saturation
temperature and then begin to boil. The high enthalpy steam leaving the RV via the
PDS valve vent path or open RV head will transport the heat to the containment
atmosphere. The heat will be removed from the containment atmosphere by
containment spray and spray cooling. Low enthalpy water is injected into the RCS from
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-95
the IRWST using the PCIP to replace the coolant boiled off in the RV and maintain the
core covered with water or two phase mixture.
Primary feed and bleed cooling requires a source of makeup to the RCS and an
adequate RCS vent path. A pre-staged PCIP (30JND11 AP002) installed in parallel
with the Train 1 medium head safety injection (MHSI) pump (30JND10 AP001) is used
to pump borated water from the IRWST into RCS cold leg 1. Refer to U.S. EPR FSAR
Tier 2, Figure 6.3-2. The injected water flows down the RV downcomer and up through
the reactor core, removing heat from the fuel. The steam that is generated is released
through a vent path to provide heat removal from the RCS. In ELAP State D, both PDS
valves are opened in one of the PDS flowpaths to provide a vent path when the PCIP is
started. Prior to draining the RCS in Mode 5 (ELAP State E), a flowpath from the PZR
to the PRT is aligned by opening both valves in one PDS flowpath. Utilization of this
flowpath requires the RCS to repressurize until the PRT rupture disc fails, which then
provides a flowpath to containment atmosphere. Events initiated when the RV head is
removed (ELAP State F) utilize the open top of the RV as the vent path to containment
atmosphere.
An overview of the primary feed and bleed mitigation strategy is provided in Table 4–9.
Simplified diagrams of the core cooling paths are provided in Figure 4-31 and
Figure 4-32. Details of the mitigation strategies are provided below.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-96
Table 4–9—FLEX Capability – Primary Feed and Bleed Core Cooling Summary
ELAP Function Method Phase 1 Phase 2 and 3
Co
re C
oo
ling
Core Cooling and Heat Removal
• Boil-off of excess RCS inventory.
• Primary side feed and bleed cooling with RCS vented to containment.
• Boil-off of RCS inventory above the top of the fuel provides core cooling in Phase 1.
• RCS is vented with one open seismically qualified PDS flowpath from the PZR to the containment atmosphere via the PRT rupture disc (ELAP State E) or from the open vessel when the RV head is removed (ELAP State F).
• PSRVs are latched open on the second lift (ELAP State D).
• Pre-staged seismically qualified PCIP installed in parallel with Train 1 MHSI pump with suction from the IRWST and discharge through the Train 1 MHSI discharge line.
• PCIP is powered from either the ELAP diesel generator in the Fire Protection Building or by portable generator.
• RCS is vented with one open seismically qualified PDS flow path from the PZR to the containment atmosphere via the PRT rupture disc (ELAP States D, E, and F) or from the open vessel when the RV head is removed (ELAP State F).
Key Reactor Parameters
• RCS pressure.
• RCS temperature.
• Instruments powered by Class 1E DC bus.
• DC load shedding used to extend baseline coping.
• Power Divisions 1 and 2 Class 1E batteries using either the ELAP diesel generator in the Fire Protection Building or by portable generators.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-97
Figure 4-31—Core Cooling in Mode 5 with SGs Unavailable and Mode 6 (Head On) Simplified Diagram
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-98
Figure 4-32—Core Cooling in Mode 6 (Head Off) Simplified Diagram
Core cooling in Phase 1 event mitigation is provided by boil off of the liquid in the RV
above the top of the core and the liquid in the hot and cold legs that drains into the RV
(refer to Section 4.1.2). For Phase 2 event mitigation, actions to place a source of
pumped injection into service are required prior to uncovering the core. Additional
inventory must be added to the RCS at a rate greater than or equal to the rate of boil off
to prevent uncovering the core. A calculation was performed to determine makeup flow
requirements to maintain core cooling in ELAP States D, E, and F. As discussed in
Section 4.1.3.2.1, this calculation determined that a minimum makeup flow rate of 230
gpm is required for core cooling. As discussed in Section 4.1.3.2.2, an injection flow of
300 gpm provides margin to the minimum flow required for core cooling (230 gpm) and
represents the minimum flow required to prevent boron precipitation. A 10% margin
was added to this value, resulting in the PCIP sized for a flow of 330 gpm. The required
discharge head of the PCIP (857 feet) was then calculated based on the peak RCS
pressure in the analyzed shutdown states, static head, and line losses. Analyses
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-99
described in Sections 4.1.3.1.4 (ELAP State D), 4.1.3.1.5 (ELAP State E), and 4.1.3.1.6
(ELAP State F) indicate that initiation of RCS injection at a minimum of 300 gpm within
one hour will prevent uncovering the core. The required injection initiation time of one
hour provides margin to actually uncovering the core. Finally, note that only one PCIP
is necessary to meet the FLEX N +1 requirement because the installed pump is
reasonably protected in SB 1 and it has two independent power sources (i.e., ELAP
diesel generator and portable diesel generator).
During Phase 1 of ELAP event mitigation in ELAP States D, E, and F, reactivity control
is accomplished by control rod insertion and required RCS boron concentration.
Additional margin to criticality is provided over time by the concentration of boron in the
core due to water boil off with no RCS injection flow. During Phases 2 and 3 of event
mitigation, reactivity control is accomplished by injection of borated water from the
IRWST using the PCIP.
In ELAP States D and E when the RCS is intact and the SGs are unavailable, primary
heat removal is accomplished by releasing high enthalpy steam from the RCS to the
containment atmosphere and by replacing the released inventory with low enthalpy
RCS makeup from the IRWST using the PCIP. The RCS will initially begin to heat up
and repressurize during this evolution. Steam from the PZR will flow through the open
PDS flowpath (or the PSRVs if the PDS valves are not yet open) to the PRT. (Refer to
U.S. EPR FSAR Tier 2, Section 5.4.11.2 for a description of the PRT and U.S. EPR
FSAR Tier 2, Figure 5.4-7 for a diagram of the PRT.) The PRT is equipped with two
redundant rupture discs with a rupture pressure setpoint of 300 psid. The RCS will heat
up and pressurize until at least one of the rupture discs fails, providing a flowpath for the
steam to the containment atmosphere.
In ELAP State F when the RV head is removed from the RV, the RCS vent path will be
through the open RV to containment. When the RV head has not yet been removed
from the RV, the RCS vent path will be either the open PDS pathway established in
ELAP State E or through the de-tensioned RV head flange to RV interface. The high
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-100
enthalpy steam released through either of the RCS vent paths is replaced with cold
water pumped from the IRWST by the PCIP.
To implement primary feed and bleed cooling in ELAP States D, E, or F with SGs
unavailable, the following valve lineup in Table 4–10 will be performed. The power
supplies and alignment to the respective motor operated valve during the ELAP event
for loads not powered from EUPS buses or the 250V DC system are described in
Section 4.1.5.1.
Table 4–10—Primary Feed and Bleed Cooling Valve Alignment
Valve ID Description Position
30JNK10 AA001 IRWST Three-way Isolation Open to PCIP
suction 1
30JND11 AA008 Manual PCIP Suction Isolation Open 1
30JND11 AA009 Manual PCIP Suction Isolation Open 1
30JND11 AA012 PCIP Motor Operated Discharge Throttle Valve Open 3, 4
30JND10 AA002 MHSI Outside Containment Isolation Valve Train 1 Closed 3
30JND10 AA004 MHSI Small Minimum Flow Isolation Valve Train 1 Closed 3
30JND10 AA005 MHSI Large Minimum Flow Isolation Valve Train 1 Closed 3
30JND10 AA103 MHSI Control Valve Train 1 Open 3
30JEF10 AA004 (30JEF10 AA006)
PDS Valve Open 2, 3
30JEF10 AA05 (30JEF10 AA007)
PDS Valve Open 2, 3
Table Notes:
1. Pre-position equipment upon entry into Mode 5.
2. Pre-position equipment prior to lowering RCS level in Mode 5. These valves will be
administratively maintained open throughout the period that the RCS is drained
down to ensure an adequate vent path for primary feed and bleed cooling exists.
3. Action to implement primary feed and bleed cooling following an ELAP event.
4. Motor-operated discharge throttle valve (30JND11 AA012) is administratively closed
and de-energized in Modes 1 to 4.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-101
4.1.5.4 Containment Integrity and Heat Removal
Containment parameters must be managed during an ELAP event to ensure integrity of
the containment, prevent damage to equipment located inside containment, and
maintain sufficient inventory for core cooling. Containment pressure and temperature
must be maintained less than the design basis limits provided in Section 4.1.2.
Following an ELAP event, normal methods of active containment heat removal and
pressure control are lost when AC power sources are lost. To assess the effects of
losing containment heat removal during an ELAP event, analyses described in
Section 4.1.3.4 were performed to determine the rate of containment heatup and
pressurization as well as required compensatory actions. The timing associated with
these analyses is dependent upon the plant state at the onset of the ELAP event.
Further, note that if the containment equipment hatch is open when an ELAP event
occurs, it must be closed to maintain containment integrity.
• For ELAP events initiated with SGs available for decay heat removal (i.e., ELAP
States A, B, and C), the containment pressurizes very slowly due to ambient heat
losses and RCS leakage.
• For ELAP events initiated with SGs unavailable for decay heat removal (i.e., ELAP
States D, E, and F), the containment heats up and pressurizes more rapidly due to
ambient heat losses and primary feed and bleed cooling, which transports all of the
core decay heat to the containment.
Heat from the containment atmosphere and IRWST will be removed using the SAHRS.
The SAHRS is conceptually similar to the containment spray system used on most
pressurized water reactors. From a timing perspective, these cases that rely on primary
feed and bleed cooling (i.e., ELAP States D, E, and F) are more limiting for containment
heat removal than for cases with SGs available (i.e., ELAP States A, B, and C) as
discussed in Section 4.1.3.4.
An overview of the containment heat removal mitigation strategy is provided in
Table 4-11. A simplified diagram of the containment heat removal strategy is provided
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-102
in Figure 4-33. Details of the containment heat removal mitigation strategy are provided
in the following sections.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-103
Table 4–11—FLEX Capability – Containment Summary
ELAP Function Method Phase 1 Phases 2 and 3
Co
nta
inm
ent
Containment Function, Containment Heat Removal
• Containment spray
• IRWST cooling
• Analysis
• Analysis demonstrates that containment pressure and temperature increases at slow rate.
• As needed, close the containment equipment hatch.
• Re-power seismically qualified SAHRS pump and provide flow to seismically qualified containment spray header. SAHRS pump takes suction from IRWST. SAHRS pump will be re-powered using either the ELAP diesel generator in the Fire Protection Building or by a portable generator.
• Provide portable cooling water to the seismically qualified SAHRS heat exchangers to cool the SAHRS pump discharge (IRWST fluid).
Key Containment Parameters
• Containment pressure
• Instruments powered by Class 1E DC bus.
• DC load shedding used to extend baseline coping.
• Power Divisions 1 and 2 Class 1E batteries using either the ELAP diesel generator in the Fire Protection Building or by portable generators.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-104
4.1.5.4.1 Containment Spray and Heat Removal
NRC Order EA-12-049 requires a three-phase approach for mitigating BDBEEs. During
the initial phase, referred to as Phase 1, the containment will be allowed to heat up and
pressurize at a slow rate. Later, in Phase 2 and Phase 3, containment heat will be
removed by the SAHRS. To avoid exceeding the containment design basis peak
temperature and pressure limits (see Section 4.1.2), the required timing for placing the
SAHRS into service is dependent upon the plant conditions at the onset of the ELAP
event:
• For ELAP events initiated with SGs available for decay heat removal (i.e., ELAP
States A, B, and C), the SAHRS must be placed in service within 36 hours.
• For ELAP events initiated with SGs unavailable for decay heat removal (i.e., ELAP
States D, E, and F), the SAHRS must be placed in service within approximately
16.7 hours.
The SAHRS pump (30JMQ40 AP001) will be re-powered and portable cooling water will
be provided to the SAHRS heat exchangers (30JMQ40 AC001 and 30JMQ40 AC004)
via flanged connections on the supply and return lines of the dedicated component
cooling water system. Actions required to re-power the SAHRS pump from either the
ELAP diesel generator or from a portable generator are provided in Table 4–4 and
Table 4–5. Only one SAHRS pump and heat exchanger set are necessary to meet the
FLEX N +1 requirement because the installed pump and heat exchanger are reasonably
protected in SB 4 and the pump has two independent power sources (i.e., ELAP diesel
generator and portable diesel generator).
With this containment heat removal strategy, containment inventory is not challenged
since the IRWST fluid is recirculated through the SAHRS heat exchangers and there is
no external source of water added to the RCS or containment.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-105
Figure 4-33—Containment Spray and Containment Heat Removal Simplified Diagram
To place the SAHRS in service during an ELAP event, the motor operated valves listed
in Table 4–12 must be opened to align the SAHRS pump to the IRWST and
containment spray header (refer to U.S. EPR FSAR Tier 2, Figure 19.2-22).
Table 4–12—SAHRS Spray Valve Alignment
Valve ID Description Position
30JNK11 AA009 IRWST Isolation to SAHRS Open
30JMQ40 AA001 SAHRS Containment Isolation for IRWST Suction Line Open
30JMQ41 AA001 SAHRS Containment Isolation for Spray Line Open
As needed, these valves may be locally opened manually since they are located outside
containment and the power source may not be energized at the time SAHRS spray is
initiated.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-106
The flanged connection points (with manual isolation valves 30KAA80 AA091 and
30KAA80 AA092) to the supply and return lines of the dedicated component cooling
water system are shown in U.S. EPR FSAR Tier 2, Figure 9.2.2-4. The portable cooling
water supply also provides cooling water for the SAHRS pump seal cooler, bearing
cooler, and motor cooler. The nominal portable cooling water flow rate is 307 lbm/s
(~ 2218 gpm).
To provide portable cooling water to the SAHRS heat exchangers, SAHRS pump seal
cooler, SAHRS bearing cooler, and SAHRS motor cooler, the manual or motor operated
valves listed in Table 4–13 must be aligned. All valves are manual valves with the
exception of 30KAA80 AA020, which is a motor operated valve. This valve may be
locally opened manually since it is located outside containment and the power source
may not be energized at the time SAHRS cooling is initiated. Further, note that the
pre-throttled valves to the SAHRS Pump seal cooler, SAHRS bearing cooler, and
SAHRS motor cooler do not need to be adjusted for ELAP event mitigation since the
cooling water flow is equivalent to the nominal dedicated component cooling water flow
under normal conditions.
Table 4–13—SAHRS Portable Cooling Water Valve Alignment
Valve ID Description Position
30KAA80 AA091 Portable CCW Supply Open
30KAA80 AA092 Portable CCW Supply Open
30KAA80 AA004 Dedicated CCW Pump Discharge Isolation Closed
30KAA80 AA020 Dedicated CCW Surge Tank Isolation Closed
30KAA80 AA002 Dedicated CCW Pump Motor Cooler Isolation Closed
After the cooling water flow path has been aligned, the portable cooling water pump is
started. After cooling water flow has been established, the SAHRS pump is started to
initiate containment spray. Additionally, note that the SAHRS pump will have to be
started by manually closing the pump motor breaker locally since control power will not
be available from Division 4 at the time the SAHRS pump is started.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-107
To ensure proper operation of the SAHRS pump for an extended period of time, a
pressurized demineralized water source must be provided to the seal water supply
system buffer tank (30GHW44 BB001) for makeup to the SAHRS pump mechanical
seals (refer to U.S. EPR FSAR Tier 2, Figure 9.2.7-1). The seal water buffer tank
GHW44 BB001 has a 40 gallon capacity, which is adequate to accommodate expected
seal leakage for 7,000 hours (291 days). The buffer tank pressure is required to be a
minimum of 102 psig. For long term event mitigation, the COL applicant will provide a
portable pressurized demineralized water source that will be connected to 1 inch valve
30GHW44 AA010.
Portable cooling water hoses to the SAHRS heat exchangers are routed through the
Nuclear Auxiliary Building at grade level to the supply and return lines of the dedicated
component cooling water system. The portable cooling water pump, hoses, suction
source, and discharge sink will be provided by COL applicant. The portable cooling
water suction source must be maintained at less than 90°F for the duration of ELAP
event mitigation, consistent with the analysis described in Section 4.1.3.4.
4.1.5.4.2 Containment Closure
The equipment hatch is provided with manual closure capability to allow closure during
a loss of electrical power, using permanently installed manual hydraulic pumps, portable
battery powered screwdrivers, and manual hand wheels. The equipment hatch can be
closed in 91 minutes using six workers. Four of the workers are required for the full
91 minutes, and the two additional workers are only required during the last 15 minutes.
This manpower requirement is acceptable because the action is only required during
selected outage modes when additional staffing is available.
4.1.5.5 Spent Fuel Cooling
In Section 4.1.3.8, analyses are described that determined the bulk SFP heatup time
and boil-off rate. For a worst-case full core off-load, these analyses concluded the
following:
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-108
• To maintain the fuel assemblies covered with water (refer to Section 4.1.2), makeup
to the SFP must be provided within 26.1 hours. Boiling of the SFP can be credited
as the Phase 1 event mitigation method because ample time is available to take
compensatory action.
• The operators have approximately 15.5 hours to restore cooling and/or makeup to
the SFP in order to maintain at least 10 feet of water inventory over the fuel
assemblies.
• For Phase 2 and 3 event mitigation, an SFP makeup rate of 140 gpm is needed to
match the initial boil-off rate. The boil-off rate decreases over time as the spent fuel
decay heat decreases.
Based on this information, an overview of the spent fuel cooling mitigation strategy is
provided in Table 4–14. A simplified diagram of the spent fuel cooling strategy is
provided in Figure 4-34. Details of the spent fuel cooling mitigation strategies are
provided in the following sections.
Figure 4-34—Spent Fuel Spray System Simplified Diagram
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-109
Table 4–14—FLEX Capability – Spent Fuel Cooling Summary
ELAP Function Method Phase 1 Phase 2 and 3
Sp
ent
Fu
el C
oo
ling
Spent Fuel Cooling
• Makeup through connection to SFP makeup piping or other suitable means (e.g., sprays).
• Makeup with portable injection source.
• Vent pathway for steam.
• Analysis demonstrates that spent fuel heats up slowly and remains cooled by water inventory above the top of the spent fuel.
• Vent path from SFP area to environment established for removal of steam.
• Seismically qualified permanent connections (primary and alternate) provided for portable, self-powered, SFP makeup pump.
• Two seismically qualified permanent connections provided for makeup from FPS.
• Vent path established in Phase 1 is maintained open to provide a vent path for steam.
SFP Parameters
• SFP Level. • Instruments powered by Class 1E DC bus.
• U.S. EPR design includes redundant, safety-related wide range level sensors in SFP that fulfill Order EA-12-051 order.
• Power Divisions 1 and 2 Class 1E batteries using either a pre-staged ELAP diesel generator in the Fire Protection Building or by portable generators.
• Power SFP level instruments using portable battery powered indication device in accordance with Order EA 12-051.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-110
For Phase 1 event mitigation, a vent path from the SFP area must be established prior
to the onset of SFP boiling to allow release of steam from this area to the environment.
Based on the analyses in Section 4.1.3.8, SFP boiling is calculated to occur no sooner
than 3.5 hours after the ELAP event occurs. Alignment of the vent path within three
hours provides margin to the analytical limit to ensure the action is completed while the
area is habitable. The vent path to the environment is provided by opening selected
doors from the SFP area to the material lock area (refer to U.S. EPR FSAR Tier 2,
Figures 3.8-41 and 3.8-46). The following actions, none of which require an external
source of electrical power, are performed to provide the required vent path:
• On the +64ʹ elevation, open the double doors and the single door between the fuel
pool operating floor and the laydown area.
• On the +64ʹ elevation, open the rollup door between the laydown area and the
material lock area.
• On the +64ʹ elevation, unlatch the material lock (labeled “Removable Floor” on U.S.
EPR FSAR Tier 2, Figure 3.8-41) and the lock doors will fall open.
• On the 0ʹ elevation, open the rollup door at grade level in the material lock room to
provide a vent path to the environment.
The vent path for the spent fuel area that is established in Phase 1 is maintained open
in Phases 2 and 3.
For Phase 2 and 3 event mitigation, makeup is required to the SFP. Based on the
Section 4.1.3.8 analyses, a minimum flow rate of 140 gpm is required to match the SFP
boil-off rate.
Flow from the self-powered, portable SFP makeup pump is provided to the SFP as
shown in simplified Figure 4-34 and U.S. EPR FSAR Tier 2, Section 9.3.3.2.1 and
Figure 9.3.3-1. The spent fuel pool spray (SFPS) system provides both a spray cooling
function and an alternate fill pipe for makeup to the SFP. Flow paths in the SFPS
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-111
system are aligned using manual valves. The SFPS system is a dry system consisting
of two separate but redundant trains that are physically located on opposite sides of the
SFP. Two separate and independent hose connections, located at grade elevation level
on the exterior of the Fuel Building (FB), are provided on opposite sides of the building
to attach a pumper truck or portable pump. The two external connections satisfy the
FLEX N+1 criterion because the FB is adequately protected and the two connections
are located on opposite sides of the FB.
Alternatively, flow to the SFP can be provided by the FPS as shown in simplified
Figure 4-34 and U.S. EPR FSAR Tier 2, Figure 9.5.1-1. This portion of the FPS
consists of two separate but redundant trains that are physically located on opposite
sides of the SFP. Each of these redundant trains contains connections from the FPS
within the FB, SB 1, and SB 4. Flow paths to the SFP for this portion of the FPS are
aligned using manual valves.
When an ELAP event is identified, the following actions are taken to ensure spent fuel
cooling:
• During Phase 1 event mitigation, align the vent path from the SFP area to the
material lock area.
• During Phase 2 and 3 event mitigation, align manual valves (as appropriate) to
provide flow from either a portable pump or the FPS to the SFP.
• Monitor level in the SFP using the SFP level instrumentation described in
Section 4.2.1.
4.1.5.6 Instrumentation and Controls
Mitigation of the ELAP event is accomplished using safety-related I&C systems (i.e.,
SICS, priority and actuator control system (PACS), signal conditioning and distribution
system (SCDS), and protection system (PS)). Operator actions are performed using
SICS. SICS provides the human-system interface that is used to perform control and
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-112
indication functions that are needed to monitor the safety status of the plant, and bring
the unit to and maintain it in a safe shutdown state.
The SICS provides conventional I&C controls and indications needed to mitigate the
consequences of accidents. The SICS human-system interface is located in the MCR.
4.1.5.6.1 Instrumentation
The following minimum set of instruments required to support ELAP event mitigation are
provided on SICS:
• Containment pressure.
• Containment temperature.
• Core exit thermocouple temperatures.
• EFW flow (downstream of discharge cross-ties).
• Fire water storage tank levels.
• IRWST level.
• MHSI Train 1 flow.
• PZR level.
• RCS cold leg temperature.
• RCS hot leg pressure.
• RCS hot leg temperature.
• SG pressures.
• SG wide range levels.
• SFP level.
• Source range neutron flux.
• Subcooling margin monitors.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-113
4.1.5.6.2 Controls
Components utilized for ELAP mitigation that are provided with controls and status
indication on SICS are listed in Table 4–15:
Table 4–15—SICS Controls
Component Description Component ID Control Positions
250V DC Switchboard Load Shed Breakers Divisions 1, 2, 3, 4
(Not Assigned) Open / Close
Accumulator Isolation Valves 30JNG13/23/33/43 AA008 Open / Close / Throttle
Accumulator Vent Control Valves 30JNG13/23/33/43 AA101 Open / Close / Throttle
Accumulator Vent Isolation Valves 30JNG13/23/33/43 AA502 Open / Close
CVCS Letdown Isolation Valve 30KBA10 AA001 Open / Close
Diesel-driven Fire Water Pumps (Not Assigned) Start / Stop
EFW Discharge Cross-Connect Valves 30LAR14/24/34/44 AA001 Open / Close / Throttle
ELAP Diesel Generator 30XKA60 AG100 Start / Stop
EUPS Bus Load Shed Breakers Divisions 1, 2, 3, 4
(Not Assigned) Open / Close
FPS to EFW Isolation Valves 30LAR55 AA002/005 Open / Close
IRWST 3-Way Isolation Valve Train 1 30JNK10 AA001 Open / Close
Main Steam Isolation Valves 30LBA10/20/30/40 AA002 Open / Close
MSRCVs 30LBA13/23/33/43 AA101 Open / Close / Throttle
MSRIVs 30LBA13/23/33/43 AA001 Open / Close
MHSI Large Miniflow Valve Train 1 30JND10 AA005 Open / Close
MHSI Outside Containment Isolation Valve Train 1
30JND10 AA002 Open / Close
MHSI Small Miniflow Valve Train 1 30JND10 AA004 Open / Close
MHSI Throttle Valve Train 1 30JND10 AA103 Open / Close / Throttle
PCIP Discharge Throttle Valve 30JND11 AA012 Open / Close / Throttle
PZR Continuous Degasification Isolation Valves
30JEF10 AA503/504 Open / Close
PZR Safety Relief Valves 30JEF10 AA191/192/193 Open / Close
PCIP 30JND11 AP002 Start / Stop
PDS Valves 30JEF10 AA004/5/6/7 Open / Close
RCP No. 1 Seal Leak Off Isolation Valves
30JEB10/20/30/40 AA009 Open / Close
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-114
Component Description Component ID Control Positions
RCP No. 2 Seal Leak Off Isolation Valves
30JEB10/20/30/40 AA010 Open / Close
RCP No. 3 Seal Leak Off Isolation Valves
30JEB10/20/30/40 AA017 Open / Close
RCP SSSS Nitrogen Injection Isolation Valves
30JEB10/20/30/40 AA018 Open / Close
RCP SSSS Nitrogen Vent Isolation Valves
30JEB10/20/30/40 AA020 Open / Close
SBVSE Battery Room Exhaust Fans (Div. 1 and 2)
30SAC51/52 AN001 Start / Stop
SBVSE Exhaust Fans (Div. 1 and 2) 30SAC31/32 AN001 Start / Stop
SBVSE Supply Fans (Div. 1 and 2) 30SAC01/02 AN001 Start / Stop
4.1.5.7 Support Functions
To support the overall functional requirements of NRC Order EA-12-49 (Reference 1)
(i.e., core cooling, containment, and spent fuel cooling), five main support functions
must be provided:
• AC Power –refer to Section 4.1.5.1.
• DC Power –refer to Section 4.1.5.1.
• Lighting.
• Communications.
• Heating, Ventilation, and Air Conditioning (HVAC).
An overview of the mitigation strategies for each of these support functions is provided
in Table 4–16. Details of the mitigation strategies for each of these support functions
are provided in the following subsections.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-115
Table 4–16—FLEX Capability – Support Functions Summary
Safety Function Method Phase 1 Phase 2 and 3
Su
pp
ort
Fu
nct
ion
s
AC power • AC distribution system
• AC distribution system housed in reasonably protected structures.
• Power Division 1, 2, and 4 ELAP mitigation equipment using either a pre-staged ELAP diesel generator in the Fire Protection Building or by portable generators.
DC power • Batteries
• DC distribution system
• Batteries and DC distribution system housed in reasonably protected structures.
• Power Divisions 1 and 2 Class 1E batteries using either a pre-staged ELAP diesel generator in the Fire Protection Building or by portable generators.
Lighting • Emergency lighting
• Applicable E-LGT powered by DC power system.
• Applicable E-LGT systems housed in reasonably protected structures.
• Power Divisions 1 and 2 Class 1E batteries using either a pre-staged ELAP diesel generator in the Fire Protection Building or by portable generators.
• Utilize portable lighting equipment.
Communications • Plant communication systems
• Applicable communication systems powered by DC power system.
• Applicable plant communication systems housed in reasonably protected structures.
• Power Divisions 1 and 2 Class 1E batteries using either a pre-staged ELAP diesel generator in the Fire Protection Building or by portable generators.
• Utilize portable communication equipment.
HVAC • Re-power SBVSE fans
• Portable Cooler for MCR
• Portable cooler for SB 4switchgear room
• Analysis demonstrates that areas housing ELAP event mitigation equipment heats up slowly without active ventilation (e.g., open doors in electrical division rooms in SB 1 and SB 2).
• Power ventilation equipment for Divisions 1 and 2 Class 1E batteries and EPSS 480V MCC 31/32BNB01 using either a prestaged ELAP diesel generator in the Fire Protection Building or by portable generators.
• Start SBVSE Trains 1 and 2 supply, exhaust, and battery room fans.
• Provide portable cooler in MCR with heat exhaust to staircase in SB 3.
• Provide portable cooler for switchgear room with heat exhaust to staircase in SB 4 if the SAHRS pump is powered by the portable 480V generator.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-116
4.1.5.7.1 Lighting
The plant lighting systems are divided into two main categories:
• Lighting for the MCR and RSS.
• Lighting outside of the MCR and RSS.
The impact on lighting in each of these areas following an ELAP event is as follows:
• The special E-LGT provides approximately 33% of the MCR and RSS lighting.
Special E-LGT loads (32UJK22GP401 and 33UJK22GP402) are located on
Divisions 2 and 3 of the EUPS. As discussed in Section 4.1.5.1, Division 2 of the
EUPS will remain energized throughout the duration of an ELAP event. The other
67 percent of the MCR and RSS lighting is provided by the E-LGT system and is
powered from the EPSS. The E-LGT would be lost following an ELAP event.
• Escape route-egress battery pack lighting will provide a minimum of 90 minutes of
illumination in areas such as stairwells, corridors, rooms, building exit ways, and/or
doors. Battery pack E-LGT will provide a minimum of eight hours of illumination and
the battery pack units are located in the access route from the MCR to the RSS.
• Portable lighting is provided to support implementation of ELAP event mitigation
strategies.
4.1.5.7.2 Communications
The plant communication system (COMS) consists of the following subsystems:
• Portable wireless communication system.
• Digital telephone system.
• Public address (PA) and alarm system.
• Sound-powered system.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-117
• Emergency offsite communication system.
• Security communication system.
Each communication subsystem provides an independent mode of communications. A
failure of one subsystem does not affect the capability to communicate using the other
subsystem. These diverse COMS are independent of each other to provide effective
communications, including usage in areas exposed to high ambient noise in the plant.
Electrical power from a Class 1E standby power source is provided for the portable
wireless COMS base station, emergency offsite communication capability, and plant
security communications. Portable wireless communication subsystem base stations
(30CYV10GW001 and 30CYV10GW002) are powered from Division 2 of the EUPS.
Portable wireless communication subsystem base stations (30CYV10GW003 and
30CYV10GW004) are powered from Division 3 of the EUPS. As a result of this
divisional arrangement of power supplies, at least two of the portable wireless
communication subsystem base stations have power available throughout the ELAP
event. The portable wireless communication subsystem base stations are located in
Seismic Category I structures in separate rooms. The location of the base station
equipment cabinets are physically separated from the other subsystem equipment (i.e.,
PABX/VoIP, PA, and alarm system) to provide for added protection against a single
accident or fire disabling multiple modes of communication throughout the plant.
4.1.5.7.3 HVAC
Following an ELAP event, all plant AC-powered forced ventilation is lost. The loss of
ventilation affects mitigation of an ELAP event in three plant areas:
• SBs (refer to Section 4.1.3.5 for SB heatup analysis).
• MCR (refer to Sections 4.1.3.6 and 4.1.3.7 for MCR heatup analysis).
• Fire Protection Building.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-118
4.1.5.7.3.1 Safeguard Buildings
Action is required to open three doors in SB 1 and SB 4 within 30 minutes; to open five
doors in SB 2 and SB 3 within 30 minutes; to restore forced ventilation flow to the
Division 1 and Division 2 SB electrical areas within seven hours; to provide portable
cooling to the SB 4 switchgear room within 16 hours 40 minutes (ELAP States D, E,
and F) or 36 hours (ELAP States A, B, and C) if the portable 480V generator is used to
repower the SAHRS pump; and to open seven doors in SB 2 within 25 hours after
initiation of the event. These actions will maintain temperatures in the SBs within
equipment operability limits.
The following doors are opened within 30 minutes of event initiation (refer to U.S. EPR
FSAR Tier 2, Figures 3.8-57, 3.8-68, and 3.8-79):
Safeguard Building 1 +27ʹ elevation:
• West switchgear room door to north staircase and elevator access.
• North staircase and elevator access door to east switchgear room.
• East switchgear room door to east I&C cabinet room.
Safeguard Building 4 +27ʹ elevation:
• East switchgear room door to north staircase and elevator access.
• North staircase and elevator access door to west switchgear room.
• West switchgear room door to west I&C cabinet room.
Safeguard Building 2 +27ʹ elevation:
• East switchgear room door to west switchgear room.
• East switchgear room door to staircase and elevator access area.
• West switchgear room door to staircase and elevator access area.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-119
• West switchgear room door to escape staircase.
• Staircase and elevator access area door to north staircase.
Safeguard Building 3 +27ʹ elevation:
• West switchgear room door to east switchgear room.
• West switchgear room door to staircase and elevator access area.
• East switchgear room door to staircase and elevator access area.
• East switchgear room door to escape staircase.
• Staircase and elevator access area door to north staircase.
Within seven hours after event initiation, EPSS 480V MCC 31BNB01 and 480V MCC
32BNB01 are energized from the ELAP diesel generator as described in
Section 4.1.5.1. Recirculation dampers (30SAC01 AA004 and 30SAC02 AA004) are
manually positioned full closed, and exhaust dampers (30SAC31 AA002 and
30SAC32 AA002) are manually positioned full open. Supply fans (30SAC01 AN001
and 30SAC02 AN001), exhaust fans (30SAC31 AN001 and 30SAC32 AN001), and
battery room fans (30SAC51 AN001 and 30SAC52 AN001) are then started to initiate
ventilation flow. SB supply and exhaust fans are not re-started for SB 3 and SB 4.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-120
For SB 4, action is also required to place a portable cooler in service in the switchgear
room if the 480V portable generator is used to repower the SAHRS pump. This action
is required due to the heat load of transformer 34BMT02, which is energized by the
portable generator when feeding from 34BMB to 34BDB. The portable cooler is not
required when energizing 34BDB from the ELAP diesel generator because transformer
34BMT02 is not energized in that electrical lineup. Exhaust air from the portable cooler
condenser is conveyed by portable ductwork to the north stairwell in SB 4 (refer to U.S.
EPR FSAR Tier 2, Figure 3.8-79). The following doors are opened to allow heat from
the stairwell to vent to SB 4 +81ʹ elevation (refer to U.S. EPR FSAR Tier 2,
Figure 3.8-83):
• North staircase door to the staircase service corridor.
• Staircase service corridor door to service corridor and staircase access area.
The SAHRS pump is the only equipment in SB 4 that is repowered during Phase 2
and 3 ELAP event mitigation. The cooler is required to be placed in service when the
480V portable generator is started to repower the SAHRS pump. This timing varies by
the plant conditions at ELAP event initiation. Portable cooling to the SB 4 switchgear
room must be provided within 16 hours 40 minutes for events initiated in ELAP
States D, E, or F or within 36 hours for events initiated in ELAP States A, B, or C if the
480V portable generator is used to repower the SAHRS pump.
Within 25 hours of event initiation, the following SB 2 doors on +39ʹ elevation are
opened (refer to U.S. EPR FSAR Tier 2, Figure 3.8-69):
• Switchgear room door to north interconnecting passageway.
• North interconnecting passageway door to access north staircase and elevator.
• Access to north staircase and elevator door to north staircase.
• Access to north staircase and elevator door to west interconnecting passageway.
• Access to north staircase and elevator door to cable duct.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-121
• West interconnecting passageway door to escape staircase.
• West cable duct door to cable floor.
4.1.5.7.3.2 Main Control Room
For the MCR, action is required to place a portable cooler in service within seven hours
to maintain habitability (refer to U.S. EPR FSAR Tier 2, Figure 3.8-70. Exhaust air from
the portable cooler condenser is conveyed by portable ductwork to the SB 3 escape
staircase.
4.1.5.7.3.3 Fire Protection Building
The Fire Protection Building is equipped with an HVAC system to ventilate the Fire
Protection Building during Phase 1, 2, and 3 event mitigation.
4.1.6 Sequence of Events/Critical Operator Actions
The overall sequence of events and critical operator actions to mitigate postulated
ELAP events can be divided into two basic sets of actions depending upon the method
used to remove core decay heat. Within each basic set of actions, the timing of
selected actions and events may be dependent upon the plant conditions at the time of
ELAP event initiation. Given this, the possible sets of plant initial conditions have been
grouped together, organized by similarity in required actions and event response, and
categorized into distinct plant states. Table 4-2 provides a listing of these six distinct
ELAP states.
• In modes relying on the steam generators for core cooling (i.e., ELAP States A, B,
and C), the overall sequence of events and critical operator actions is provided in
Table 4–17
• In modes relying on primary feed and bleed for core cooling (i.e., ELAP States D, E,
and F), the overall sequence of events and critical operator actions is provided in
Table 4–18.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-122
Actions or event timing that are applicable to only one or two of the ELAP States
included in the table is designated by a bold “ELAP State” label designating the
applicable state in the “Event” column of the table. If the action or event timing is
applicable to all three of the pertinent ELAP States included in the table, then no “ELAP
State” label will be present in the “Event” column.
The ELAP State is determined by plant conditions at the time of ELAP initiation. The
mitigation strategy described for that ELAP State is followed throughout the event. As
plant conditions change during mitigation, the ELAP State is not changed.
Phase 2 of event mitigation begins at the time the ELAP diesel generator or 480V
portable generators are started to power FLEX equipment. The time of ELAP diesel
generator or portable generator start is listed in Table 4–17 for ELAP States A, B,
and C; and in Table 4–18 for ELAP States D, E, and F.
In Reference 31 the NRC endorsed an NEI position paper (Reference 32) on an
acceptable approach to demonstrating that the reactor licensees are capable of
implementing mitigating strategies in all modes of operation including shutdown and
refueling modes. For example, personnel and equipment may be pre-staged in
shutdown and refueling modes. These factors were credited when evaluating the
feasibility of some actions required to mitigate ELAP events initiated in shutdown or
refueling modes.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-123
Table 4–17—Sequence of Events – ELAP Initiated in Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer (ELAP States A, B, and C)
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
LOOP with loss of all AC power except from battery backed inverters.
0 1 N N/A N/A
ELAP State A – Reactor trip procedure entered. Operators perform immediate actions for reactor trip before mitigating loss of power.
~ 1 min 2 N N/A N/A
RCP seal leakage is assumed to increase to 25 gpm per RCP.
2 min 1 N N/A N/A
Operators attempt to start EDGs.
~ 2 min 2 N N/A N/A
Four additional EDG start attempts fail.
~ 9 min 2 N N/A Note: 125 seconds between each start attempt, 15 seconds crank time.
SBO diagnosed – operators enter SBO procedure.
~ 9 min 2 N N/A N/A
Operators attempt to start SBO diesel generators.
~ 9 min 2 N N/A N/A
SBO diesel generators fail to start or connect to EPSS buses.
~ 10 min 2 N N/A N/A
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-124
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP event is diagnosed. 10 min 1 Y The SBO diesel generator is required to be capable of powering loads within 10 minutes of loss of all AC power. The ELAP event is diagnosed upon failure of the SBO diesel generator to start or load.
Operators are trained to place the SBO diesel generator in service within 10 minutes. Procedural guidance will direct initiation of ELAP mitigation upon failure of the SBO diesel generator to start or load.
Operators ensure RCP SSSS actuates and all RCP seal return valves close from MCR.
15 min 3 Y Analysis assumed reduction of leakage to 13 gpm (11 gpm RCS leakage plus 2 gpm total SSSS leakage) at 15 minutes as a result of this action.
The seal leak-off isolation valves are automatically closed upon detection of simultaneous loss of seal injection and thermal barrier cooling. The SSSS is automatically actuated 15 minutes after loss of seal cooling.
Plant personnel open three doors in SB 1, five doors in SB 2, five doors in SB 3, and three doors in SB 4 to limit temperature rise in switchgear room.
30 min 3 Y Analysis indicated that SB temperatures would remain below equipment operability limits if specified doors were opened 30 minutes after event initiation, and forced ventilation was initiated by seven hours after event initiation.
Personnel will be trained to open these doors within the required time.
Operators perform SBO containment isolation actions.
30 min 2 N N/A N/A
Operators manually close all four MSIVs from the control room.
30 min 1 Y Analysis assumed that MSIVs would be closed by 30 minutes after initiation of the event.
MSIVs can be closed from the control room.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-125
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State A, ELAP State B – Operators manually control all four SG MSRTs from the MCR to control RCS cooldown at 90°F/hr, and initiate controlled depressurization of all four SGs.
30 min 3 Y Analysis assumed initiation of 90°F/hr cooldown at 30 minutes. Delay in initiating cooldown results in lower inventory in the SGs at start of cooldown.
MSRTs are powered from EUPS buses, and can be operated from the MCR.
ELAP State C – Operators manually control all four SG MSRTs to control SG pressures at 40 psia.
35 min 5 Y Once the RCS has heated up enough to raise SG pressures to 40 psia (which is above the minimum required pressure to open MSRIVs), the MSRCVs are controlled to maintain SG pressures at 40 psia to initiate primary to secondary heat transfer and terminate the RCS heatup. This prevents loss of RCS inventory due to PSRV opening, which would begin at approximately 1 hour 6 minutes with no actions.
MSRTs are controlled from the control room.
ELAP State C – Operators position EFW valves from the MCR to align the diesel-driven fire pump discharge to all SGs. Operators start diesel-driven fire pump and manually control all four SG wide range levels between 72.2% and 82.2% from the control room.
35 min 1 Y Fire water addition to the SGs to make up for inventory lost through the MSRTs when steaming begins is an analysis assumption.
All required components are operated from the control room.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-126
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State A – Operators position EFW valves from the MCR to align the diesel-driven fire pump discharge to all SGs. Operators start diesel-driven fire pump.
1 hr 4 Y Analysis assumes feed supply is available when SGs dry out at approximately 4750 seconds. Feed supply to SGs required for primary to secondary heat transfer.
All valves required to align the flow path are motor operated from the MCR. The diesel-driven fire pump is started from the MCR.
ELAP State B – PZR empties. 1 hr 7 min 5
N N/A N/A
Action completed to shed non-essential loads from all four divisions of 250V DC switchboards and EUPS buses.
1 hr 10 min 3
Y Analysis of battery coping time assumed all non-essential loads were disconnected by 70 minutes after initiation of the event.
All non-essential loads, with the exception of the I&C cabinets, are segregated from essential loads on a separate load shed bus. Non-essential loads are shed by opening four breakers from the MCR. It is reasonable to assume that four breakers can be operated from the MCR within 60 minutes of recognition that an ELAP event has occurred. The I&C cabinets in each division are located in the same room. It is reasonable to assume that an operator can reach each room and de-energize the cabinets within 60 minutes of recognition that an ELAP event has occurred.
ELAP State A – PZR empties. 1 hr 11 min 5
N N/A N/A
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-127
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State A – All SGs are dry.
1 hr 19 min 5
N N/A N/A
ELAP State A – Operators detect SG dryout by observing rapidly decreasing SG pressures and SG levels near zero and throttle all four SG MSRCVs from the MCR as required to control pressure at 100 psia. Fire water flow of ~ 150 gpm per SG begins, restoring primary to secondary heat transfer.
1 hr 20 min 5
Y SG pressures must be reduced below diesel-driven fire pump discharge pressure before feed flow begins. Analysis assumed depressurization to 100 psia to ensure ~ 150 gpm per SG.
MCR operators monitor progression of cooldown and are trained to detect SG dryout. SG pressures rapidly decreasing and SG levels decreasing to zero provide an indicator of impending dryout.
ELAP State A – Accumulators begin to inject into the RCS.
1 hr 59 min 5
N N/A N/A
ELAP State B – Operators position EFW valves from the MCR to align the diesel-driven fire pump discharge to all SGs. Operators start diesel-driven fire pump.
2 hr 4 Y Analysis assumes feed supply is available when SGs dry out at approximately 9800 seconds. Feed supply to SGs required for primary to secondary heat transfer.
All valves required to align the flow path are motor operated from the MCR. The diesel-driven fire pump is started from the MCR.
ELAP State A – SG levels begin to recover.
2 hr 32 min 5
N N/A N/A
ELAP State B – PZR level is regained.
2 hr 55 min 3
N N/A N/A
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-128
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State B – Operators start the ELAP diesel generator.
2 hr 57 min 3
Y The ELAP diesel generator must be started by 2 hours 57 minutes to support operation of the PCIP at that time.
The ELAP diesel generator can be started from the MCR.
ELAP State B – Operators perform electrical and flow path alignments required to prepare PCIP for operation and block open the door to the PCIP room. Operators then start the PCIP when RCS pressure decreases to less than 350 psia.
2 hr 57 min 3
Y The PCIP must be started when RCS pressure decreases to less than 350 psia to prevent hot leg and steam generator tube boiling that could interrupt natural circulation. The analysis described in Section 4.1.3.1.2 showed that RCS pressure decreased below 350 psia at 2 hours and 57 minutes.
The PCIP and most valves, including valves in the containment, are operated from the MCR. Only two manual valves and one door in SB 1 are required to be aligned in the field. The electrical buses are located in the same building and can be aligned relatively quickly. Additional outage staffing will be available to ensure these actions can be completed within the required time for events initiated in this ELAP State.
FB doors are opened to provide vent path from SFP area to exterior.
3 hr 4 Y Vent path is required to prevent pressurization of FB.
Aligning vent path requires opening four doors, three of which are on the same elevation. Three hours is adequate time to accomplish this task.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-129
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State B – Operators observe rapidly decreasing SG pressures and SG levels near zero and throttle all four SG MSRCVs from the MCR as required to control pressure at 60 psia. Fire water flow of ~ 150 gpm per SG begins, restoring primary to secondary heat transfer.
3 hr 5 Y SG pressures must be reduced below diesel-driven fire pump discharge pressure before feed flow begins. Analysis assumed depressurization to 60 psia to ensure ~ 150 gpm per SG.
MCR operators monitor progression of cooldown and are trained to detect SG dryout. SG pressures rapidly decreasing and SG levels decreasing to zero provide an indicator of impending dryout.
ELAP State B – All SGs are dry.
3 hr 3 min 5
N N/A N/A
ELAP State B – SG levels begin to recover.
~ 3 hr 12 min 5
N N/A N/A
SFP boiling begins. 3 hr 30 min 5
N N/A Limiting time for heatup of SFP.
ELAP State B – Operators stop the PCIP when RCS pressure approaches PCIP shutoff head.
4 hr 5 N N/A Note: Operator guidance will be to stop the pump when PZR at desired level or RCS pressure approaches PCIP shutoff head.
Operators terminate fire water flow to SG-3 and SG-4 by closing the associated EFW cross-connect valves. SG-3 and SG-4 MSRCVs are left in their existing position.
6 hr 4 Y Fire water flow to SG-3 and SG-4 are terminated at this time to ensure that the EFW cross-connect valves are closed before power is lost to the valves at 8 hours 30 minutes.
Action only requires closing two valves from the control room.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-130
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State A, ELAP State C – Operators start the ELAP diesel generator.
7 hr 3 Y Power source is required to support operation of SB ventilation at 7 hours.
The ELAP diesel generator can be started from the MCR.
Electrical power and manual damper alignments are performed to support operation of SB ventilation. The SBVSE Divisions 1 and 2 supply and exhaust fans are started.
7 hr 3 Y Analysis indicated that SB temperatures would remain below equipment operability limits if specified doors were opened 30 minutes after event initiation and forced ventilation was initiated by seven hours after event initiation.
Action requires operators to access and position two dampers in the field. Since the installed fans are being repowered, only electrical alignment is required to place the fans in service once the dampers have been positioned. Seven hours is adequate time to position two dampers, and perform the required electrical alignment. The required SB ventilation fans can be started from the MCR.
Plant personnel route MCR portable cooler exhaust ductwork to SB 3 and place MCR portable cooler in service.
7 hr 3 Y Analysis assumed cooler placed in service to limit MCR temperature.
Doors are located in the vicinity of the MCR.
ELAP State A – Fire water flow throttled to control SG levels.
7 hr 23 min 5
N N/A N/A
ELAP State B – Operators start the PCIP when RCS pressure is less than 350 psia and indicated PZR level is less than 30 inches.
7 hr 24 min 5
N N/A PCIP is controlled remotely from the MCR.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-131
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State B – Operators stop the PCIP when RCS pressure approaches PCIP shutoff head.
7 hr 48 min 5
N N/A PCIP is controlled remotely from the MCR.
ELAP State B – Fire water flow throttled to control SG levels.
8 hr 7 min 5
N N/A N/A
Operators energize Division 1 and 2 250V DC switchboards and EUPS buses from ELAP diesel generator and battery room fans are started.
8 hr 30 min 3
Y Mitigation strategy assumes availability of Divisions 1 and 2 powered equipment. Divisions 1 and 2 must be powered from the ELAP diesel generator or portable generators prior to battery depletion.
Action requires placing two battery chargers in service. Eight hours and 30 minutes is sufficient time to allow performance of these actions.
Operators de-energize Division 3 and 4 250V DC switchboards and EUPS buses.
8 hr 30 min 5
N N/A Note: Action is performed for equipment protection and is not required for event mitigation. Action can be delayed if required to allow performance of actions that are required for event mitigation.
ELAP State A – PZR level is recovered.
9 hr 22 min 5
N N/A N/A
ELAP State B – SG-3 and SG-4 dry out.
10 hr 7 min 5
N N/A N/A
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-132
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State B – Replenish ELAP diesel generator fuel oil storage tank.
10 hr 57 min 4
Y ELAP diesel generator is required to power essential mitigation equipment. The ELAP diesel generator is provided with a minimum eight-hour fuel oil supply. The ELAP diesel generator is placed in service by two hours and 57 minutes. Requiring replenishment at 10 hours 57 minutes is conservative since the ELAP diesel generator will not be at full load until Division 1 and 2 250V DC switchboards and EUPS buses are connected.
A means of tank replenishment exists that is capable of filling the fuel oil storage tank within 10 hours 57 minutes. Note: If the ELAP diesel generator is started earlier than 2 hours 57 minutes, the required time of fuel replenishment is earlier by an equal amount.
ELAP State A – SG-3 dries out.
10 hr 47 min 5
N N/A N/A
ELAP State A – SG-4 dries out.
10 hr 53 min 5
N N/A N/A
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-133
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State A, ELAP State C – Replenish ELAP diesel generator fuel oil storage tank.
15 hr 4 Y ELAP diesel generator is required to power essential mitigation equipment. The ELAP diesel generator is provided with a minimum eight-hour fuel oil supply. The ELAP diesel generator is placed in service by seven hours. Requiring replenishment at 15 hours is conservative since the ELAP diesel generator will not be at full load until Division 1 and 2 250V DC switchboards and EUPS buses are connected.
A means of tank replenishment exists that is capable of filling the fuel oil storage tank within 15 hours. Note: If the ELAP diesel generator is started earlier than seven hours, the required time of fuel replenishment is earlier by an equal amount.
Makeup to the SFP is provided to maintain at least ten feet of water inventory above the fuel assemblies.
15 hr 30 min 3
Y Maintain adequate radiological shielding for access. If no makeup was provided, fuel would uncover at 26 hours 6 minutes.
Pre-installed engineered features are provided to facilitate pool replenishment.
ELAP State C – SG-3 dries out.
15 hr 41 min 5
N N/A N/A
ELAP State C – SG-4 dries out.
16 hr 25 min 5
N N/A N/A
ELAP State A – Fire water storage tank is replenished from other sources using the provided fill connections or a portable pump and water supply is placed in service.
16 hr 53 min 4
Y Analysis indicated that requiring replenishment or alternate source of feed at 19 hours 13 minutes provides a 10% volume margin to loss of suction.
A means of tank replenishment or alternate feed supply exists that is capable of being placed in service within 16 hours 53 minutes.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-134
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State B – Operators start the PCIP when RCS pressure is less than 350 psia and indicated PZR level is less than 30 inches.
19 hr 42 min 5
N N/A PCIP is controlled remotely from the MCR.
ELAP State B – Operators stop the PCIP when RCS pressure approaches PCIP shutoff head.
20 hr 24 min 5
N N/A PCIP is controlled remotely from the MCR.
ELAP State C – Accumulator injection begins.
21 hr 2 min 5
N N/A N/A
ELAP State B – Fire water storage tank is replenished from other sources using the provided fill connections or a portable pump and water supply is placed in service.
23 hr 20 min 4
Y Analysis indicated that requiring replenishment or alternate source of feed at 23 hours 20 minutes provides a 10% volume margin to loss of suction.
A means of tank replenishment or alternate feed supply exists that is capable of being placed in service within 23 hours 20 minutes.
ELAP State A, ELAP State C – Operators perform electrical and flowpath alignments required to prepare PCIP for operation and block open the door to the PCIP room. The PCIP begins to be cycled as required to maintain PZR level on scale.
24 hr 3 Y Analysis verified that accumulators will provide required RCS makeup for 24 hours. A source of RCS makeup is required after 24 hours.
The PCIP, and most valves, including valves in the containment, are operated from the MCR. Only two manual valves and one door in SB 1 are required to be aligned in the field. The electrical buses are located in the same building and can be aligned relatively quickly. The PCIP and the associated PCIP discharge valve can be operated from the control room.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-135
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
After the PCIP is available for RCS makeup, Division 1 and 2 accumulator outlet isolation valves are closed to prevent nitrogen injection into the RCS.
24 hr 4 Y Analysis verified that accumulators will provide required RCS makeup for 24 hours without emptying and injecting nitrogen into the RCS.
Division 1 and 2 accumulator outlet valves are powered from Division 1 and Division 2 EUPS buses and can be closed from the control room.
After the PCIP is available for RCS makeup, Division 3 and 4 accumulators are vented to prevent nitrogen injection into the RCS.
24 hr 4 Y Analysis verified that accumulators will provide required RCS makeup for 24 hours without emptying and injecting nitrogen into the RCS.
Division 3 and 4 accumulator vent valves are powered from Division 1 and Division 2 EUPS buses and can be opened from the control room.
Plant personnel open seven doors on the +39ʹ elevation of SB 2 to limit temperature rise in associated switchgear room.
25 hr 3 Y Analysis indicated that SB 2 temperatures would remain below equipment operability limits if specified doors were opened 25 hours after initiation of the event.
Action requires opening seven doors in the same area of SB 2.
ELAP State C – Fire water storage tank is replenished from other sources using the provided fill connections or a portable pump and water supply is placed in service.
31 hr 4 Y Conservative extrapolation of analysis indicated that requiring replenishment or alternate source of feed at 31 hours provides a 10% volume margin to loss of suction.
A means of tank replenishment or alternate feed supply exists that is capable of being placed in service within 31 hours.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-136
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
The SAHRS pump is powered from the ELAP DG or a 480V portable generator and cooling water is supplied to the SAHRS cooler from a portable cooling water pump. The SAHRS pump and the portable cooling water pump are started to provide containment spray and heat removal.
36 hr 4 Y Analysis indicated that the containment design basis peak temperature and pressure will not be challenged for several days. Initiating containment spray flow and cooling water prior to that time prevents exceeding the containment design basis peak temperature and pressure limits.
The SAHRS pump and heat exchanger are installed equipment. A portable cooling water pump that is capable of being placed in service within 36 hours will be provided.
If portable 480V generator is used to repower the SAHRS pump, plant personnel route SB 4 switchgear room portable cooler exhaust ductwork to SB 4 north staircase, open two doors on the +81ʹ elevation of SB4, and place SB 4 switchgear room portable cooler in service.
36 hr 4 Y Cooler must be placed in service to remove heat from the switchgear room to support long term operation of the SAHRS pump.
Action requires routing approximately 50 feet of portable ductwork, opening two doors, connecting the portable cooler to an installed power connection, and starting the cooler. These actions can be performed within 36 hours.
If diesel-driven fire pump is still being used as feed source, replenish fuel oil storage tank.
3.5 days 6 Y Fuel oil storage tank has a minimum capacity sufficient to fuel the pump for 84.4 hours at a pump flow of 660 gpm. Diesel-driven fire pump is placed in service within one hour after event initiation.
A means of tank replenishment exists that is capable of filling the fuel oil storage tank within 3.5 days. Note: If the diesel-driven fire pump is started earlier than 1 hour, the required time of fuel replenishment is earlier by an equal amount.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-137
Modes 1 through 5 with SGs Available for Primary to Secondary Heat Transfer
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
A pressurized demineralized water source is provided for makeup to the SAHRS pump mechanical seal.
250 days 4 Y Seal Water Buffer Tank GHW44 BB001 has a 40 gallon capacity, which can accommodate seal leakage for 7,000 hours (291 days).
A period of 250 days is considered adequate time to stage and install a pressurized demineralized water source.
Table Notes:
1. Event timing is an analysis assumption.
2. Event timing estimated based on engineering judgment.
3. Operator action time is the analytical limit (i.e., the time assumed for completion of the action in the relevant analysis).
Action must be completed by this time, but may be performed earlier to provide margin.
4. Operator action time includes margin to the analytical limit.
5. Event timing based on analysis results.
6. Operator action time based on expected fuel consumption at minimum required pump flow rate and minimum required
fuel storage capacity.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-138
Table 4–18—Sequence of Events – ELAP Initiated in Mode 5 or Mode 6 with SGs Unavailable (ELAP States D, E, and F)
Mode 5 or Mode 6 with SGs Unavailable – Primary Feed and Bleed Cooling
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
LOOP with loss of all AC power except from battery backed inverters.
0 1 N N/A N/A
ELAP State D – First PSRV cycle occurs.
~1 min 5 N N/A N/A
Operators attempt to start EDGs.
~ 2 min 2 N N/A N/A
ELAP State D – Second PSRV cycle occurs. Operators latch the PSRV open when the second cycle is observed.
~ 3 min 5 N N/A N/A
ELAP State E, ELAP State F – Core boiling begins
~ 3 min N N/A N/A
Four additional EDG start attempts fail.
~ 9 min 2 N N/A (125 seconds between each start attempt, 15 seconds crank time)
SBO diagnosed – operators enter SBO procedure.
~ 9 min 2 N N/A N/A
Operators attempt to start SBO diesel generators.
~ 9 min 2 N N/A N/A
SBO diesel generators fail to start or connect to EPSS buses.
~ 10 min 2 N N/A N/A
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-139
Mode 5 or Mode 6 with SGs Unavailable – Primary Feed and Bleed Cooling
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP event is diagnosed. 10 min 1 Y The SBO diesel generator is required to be capable of powering loads within 10 minutes of loss of all AC power. The ELAP event is diagnosed upon failure of the SBO diesel generator to start or load.
Operators are trained to place the SBO diesel generator in service within 10 minutes. Procedural guidance directs initiation of ELAP mitigation upon failure of the SBO diesel generator to start or load.
ELAP State D, ELAP State E – Operators ensure RCP SSSS actuates and all RCP seal return valves close from MCR.
15 min 3 Y Analysis assumed reduction of leakage to 13 gpm (11 gpm RCS leakage plus 2 gpm total SSSS leakage) at 15 minutes as a result of this action.
The seal leak-off isolation valves are automatically closed upon detection of simultaneous loss of seal injection and thermal barrier cooling. The SSSS is automatically actuated 15 minutes after loss of seal cooling.
Plant personnel open three doors in SB 1, five doors in SB 2, five doors in SB 3, and three doors in SB 4 to limit temperature rise in associated switchgear room.
30 min 3 Y Analysis indicated that SB temperatures would remain below equipment operability limits if specified doors were opened 30 minutes after event initiation and forced ventilation was initiated by seven hours after event initiation.
Personnel will be trained to open these doors within the required time.
ELAP State D – PRT rupture disc fails.
32 min 5 N N/A N/A
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-140
Mode 5 or Mode 6 with SGs Unavailable – Primary Feed and Bleed Cooling
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State D – Operators start the ELAP DG and perform electrical and flow path alignments required to prepare PCIP and PDS valves for operation. Operators then start the PCIP, open two PDS valves in one of the PDS flowpaths, and block open the PCIP room door.
1 hr 1, 4 Y The analysis assumed that the PCIP was started at one hour. The analysis estimated that PCIP injection must be started by approximately 3.5 hours to prevent uncovering the core.
The ELAP diesel generator, the PCIP, and most valves, including valves in the containment, are operated from the MCR. Only two manual valves in SB 1 are required to be operated in the field. The electrical buses are located in the same building and can be aligned relatively quickly. Additional outage staffing will be available to ensure these actions can be completed within the required time for events initiated in this plant state.
ELAP State E, ELAP State F – ELAP diesel generator started, power is aligned to the PCIP and associated flowpath valves, the PCIP flow path is aligned, the PCIP is started, and the door to the PCIP room is blocked opened.
1 hr 4 Y Without a source of pumped RCS injection, the core would become uncovered at ~2 hours 2 minutes in ELAP State E and ~ 1 hour 13 min in ELAP State F.
The ELAP diesel generator and the PCIP are started from the MCR. All manual valves in the PCIP flow path and the PDS valves are aligned prior to beginning draindown in Mode 5. Motor operated valves required to align the PCIP flowpath are operated from the MCR. These actions can be completed within one hour of event initiation. Additional staffing will be available for performance of these actions during outage conditions.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-141
Mode 5 or Mode 6 with SGs Unavailable – Primary Feed and Bleed Cooling
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
ELAP State D – Core boiling begins.
1 hr 4 min 5
N N/A N/A
Action completed to shed non-essential loads from all 250V DC switchboards and EUPS buses.
1 hr 10 min 3
Y Analysis of battery coping time assumed all non-essential loads were disconnected by 70 minutes after initiation of the event.
All non-essential loads, with the exception of the I&C cabinets, are segregated from essential loads on a separate load shed bus. Non-essential loads are shed by opening four breakers from the MCR. It is reasonable to assume that four breakers can be operated from the MCR within 60 minutes of recognition that an ELAP event has occurred. The I&C cabinets in each division are located in the same room. It is reasonable to assume that an operator can reach each room and de-energize the cabinets within 60 minutes of recognition that an ELAP event has occurred.
ELAP State E – Maximum RCS pressure of ~ 334 psia is reached and PRT rupture disc fails.
1 hr 15 min 5
N N/A N/A
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-142
Mode 5 or Mode 6 with SGs Unavailable – Primary Feed and Bleed Cooling
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
Equipment hatch is reinstalled if required.
1 hr 31 min 4
Y The equipment hatch can be reinstalled in one hour and 31 minutes.
Personnel will be trained and procedures will be provided to support installation of the equipment hatch in one hour 31 minutes. Additional staffing will be available for the performance of this task during outage conditions.
ELAP State D – Maximum RCS pressure (after PRT rupture disc failure) of ~ 191 psia is reached and RCS pressure begins to decrease.
2 hr 29 min 5
N N/A N/A
FB doors are opened to provide vent path from SFP area to exterior.
3 hr 4 Y Vent path is required to ensure that pressurization of FB does not occur.
Aligning vent path requires propping four doors open, three of which are on the same elevation. Three hours is adequate time to accomplish this task.
SFP boiling begins. 3 hr 30 min 5
N N/A Limiting time for heatup of SFP.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-143
Mode 5 or Mode 6 with SGs Unavailable – Primary Feed and Bleed Cooling
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
Electrical power and manual damper alignments are performed to support operation of Safeguards ventilation. The SBVSE Division 1 and 2 supply, exhaust, and battery room fans are started.
7 hr 3 Y Analysis indicated that SB temperatures would remain below equipment operability limits if specified doors were opened 30 minutes after event initiation, and forced ventilation was initiated by seven hours after event initiation.
Action requires operators to access and position two dampers in the field. Since the installed fans are being repowered, only electrical alignment is required to place the fans in service once the dampers have been positioned. Seven hours is adequate time to position two dampers and perform the required electrical alignment.
Plant personnel route MCR portable cooler exhaust ductwork to SB 3 and place MCR portable cooler in service.
7 hr 3 Y Analysis assumed cooler placed in service to limit MCR temperature.
Doors are located in the vicinity of the MCR.
Operators energize Division 1 and 2 250V DC switchboards and EUPS buses from ELAP diesel generator.
8 hr 30 min 3
Y Mitigation strategy assumes availability of Divisions 1 and 2 powered equipment. Divisions 1 and 2 must be powered from the ELAP diesel generator or portable generators prior to battery depletion.
Action requires placing two battery chargers in service. Eight hours 30 minutes is sufficient time to allow performance of these actions.
Operators de-energize Division 3 and 4 250V DC switchboards and EUPS buses.
8 hr 30 min 5
N N/A Action is performed for equipment protection and is not required for event mitigation. Action can be delayed if required to allow performance of actions that are required for event mitigation.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-144
Mode 5 or Mode 6 with SGs Unavailable – Primary Feed and Bleed Cooling
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
Replenish ELAP diesel generator fuel oil storage tank.
9 hr 4 Y ELAP diesel generator is required to power essential mitigation equipment. The ELAP diesel generator is provided with a minimum 8 hour fuel oil supply. The ELAP diesel generator is placed in service by one hour after event initiation to power the PCIP. Requiring replenishment at 9 hours is conservative since the ELAP diesel generator will not be at full load until Divisions 1 and 2 250V DC switchboards and EUPS buses are connected.
A means of tank replenishment exists that is capable of filling the fuel oil storage tank within 9 hours. Note: If the ELAP diesel generator is started earlier than 1 hour, the required time of fuel replenishment is earlier by an equal amount.
Makeup to the SFP is provided to maintain at least ten feet of water inventory above the fuel assemblies.
15 hr 30 min 3
Y Maintain adequate radiological shielding for access. If no makeup was provided, fuel would uncover at 26 hours 6 minutes.
Pre-installed engineered features are provided to facilitate pool replenishment.
The SAHRS pump is powered from the ELAP DG or the 480V portable generator and cooling water is supplied to the SAHRS cooler from a portable cooling water pump. The SAHRS pump and the portable cooling water pump are started to provide containment spray and heat removal.
16 hr 40 min 3
Y Analysis indicated that the containment design basis peak temperature and pressure will not be exceeded if containment spray flow and cooling water are initiated by 16 hours 40 minutes.
The SAHRS pump and heat exchanger are installed equipment. A portable cooling water pump that is capable of being placed in service within 16 hours and 40 minutes will be provided.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-145
Mode 5 or Mode 6 with SGs Unavailable – Primary Feed and Bleed Cooling
Event Time Limit
Time Constraint?
Technical Basis for Time Requirement
Description of Why Time is Reasonably Achievable
If the 480V portable generator is used to repower the SAHRS pump, plant personnel route SB 4 switchgear room portable cooler exhaust ductwork to SB 4 north staircase, open two doors on +81ʹ elevation of SB 4, and place SB 4 switchgear room portable cooler in service.
16 hr 40 min 3
Y Cooler must be placed in service to remove heat from the switchgear room to support long term operation of the SAHRS pump.
Action requires routing approximately 50 feet of portable ductwork, opening two doors, connecting the portable cooler to an installed power connection, and starting the cooler. These actions can be performed within 16 hours and 40 minutes.
Plant personnel open seven doors on the +39ʹ elevation of SB 2 to limit temperature rise in associated switchgear room.
25 hr 3 Y Analysis indicated that SB 2 temperatures would remain below equipment operability limits if specified doors were opened 25 hours after initiation of the event.
Action requires opening seven doors in the same area of SB 2.
A pressurized demineralized water source is provided for makeup to the SAHRS pump mechanical seal.
250 days 4 Y Seal Water Buffer Tank GHW44 BB001 has a 40 gallon capacity, adequate to accommodate seal leakage for 7,000 hours (291 days).
A period of 250 days is considered adequate time to stage and install a pressurized demineralized water source.
Table Notes:
1. Event timing is an analysis assumption.
2. Event timing estimated based on engineering judgment.
3. Operator action time is the analytical limit (i.e. the time assumed for completion of the action in the relevant analysis).
Action must be completed by this time, but may be performed earlier to provide margin.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-146
4. Operator action time includes margin to the analytical limit.
5. Event timing based on analysis results.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-147
4.1.7 Functional Performance Requirements for Key Equipment
Functional performance requirements for key equipment can be divided into three
categories: (1) portable equipment, (2) safety related equipment, and (3) non-safety
related equipment. Functional performance requirements for key equipment in each
category are addressed as follows:
Functional performance requirements for key portable equipment required for long-term
ELAP event mitigation (i.e., Phases 2 and 3) are summarized in Table 4–19.
Functional performance requirements for key safety related equipment required for
short and/or long-term ELAP event mitigation are summarized in Table 4–20.
Functional performance requirements for key non-safety related equipment required for
short and/or long-term ELAP event mitigation are summarized in Table 4–21.
Further, note that reasonable protection requirements for this ELAP event mitigation
equipment is discussed in Section 4.1.4.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-148
Table 4–19—Performance Requirements for Key Portable Equipment
Equipment Performance Requirements Interface Requirements
Core Cooling
Portable SG Feed Pump
• Portable SG feed pump is capable of providing a minimum of 150 gpm to each of the four SGs with a maximum SG pressure of 100 psia.
• Connections are sized for a flow rate of 660 gpm (150 gpm to each of four SGs with 10% flow margin).
• Connection points are outside the Fire Protection Building (30SGA01 AA092), outside SB 1 (30LAR55 AA004), inside SB 1 (30LAR55 AA003), or inside SB 4 (30LAR54 AA501).
Containment Integrity
Portable Cooling Water
• A nominal flow rate of 2218 gpm of portable cooling water shall be provided to the dedicated component cooling water piping to provide cooling to the SAHRS heat exchangers 30JMQ40 AC001 and 30JMQ40 AC004, and to the SAHRS pump bearing, seal water, and motor coolers.
• Connection points are flanged connections inside SB 4 at 30KAA80 AA091 and 30KAA80 AA092.
SFP Cooling
Portable SFP Makeup Pump and Water Source
• The pump shall be sized for a minimum flow rate of 140 gpm with a minimum discharge head of 130 feet.
• Connection points are outside FB (30KTC30 AA074 or 30KTC30 AA084).
Electrical and DC Load Shedding
Portable ELAP Generators
• The portable generator connected to Division 1 shall be 550 kW and the portable generators connected to Divisions 2 and 4 shall each be 350 kW.
• Output voltage shall be 480V AC.
• Connection points are in SB (breakers on 31BMB, 32BMB, and 34BMB buses).
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-149
Equipment Performance Requirements Interface Requirements
HVAC
Portable Cooler • The cooler (air conditioner) shall be sized to provide a minimum of 32,000 BTUs/hr of cooling to MCR while exhausting heat through approximately 140 feet of portable ductwork.
• Hot exhaust from cooler condensing unit is directed to SB 3.
Portable Cooler • A cooler (air conditioner) shall be sized to provide a minimum of 31,000 BTUs/hr of cooling to SB 4 switchgear room while exhausting heat through approximately 50 feet of portable ductwork.
• Hot exhaust from cooler condensing unit is directed to SB 4 north stairwell +27ʹ elevation and two doors are opened on the +81ʹ elevation of SB 4 to release the heat from the stairwell.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-150
Table 4–20—Performance Requirements for Key Safety Related Equipment
Equipment Performance Requirements Requirements Comparison
Core Cooling
Accumulators • Accumulator water volume, pressure, and boration requirements conform to U.S. EPR FSAR Tier 2, Technical Specification 3.5.1.
• Requirements for ELAP event mitigation are comparable to safety related design basis of equipment.
IRWST • IRWST water volume, temperature, and boration requirements conform to U.S. EPR FSAR Tier 2, Technical Specifications 3.5.4, 3.5.6, and 3.5.7.
• Requirements for ELAP event mitigation are comparable to safety related design basis of equipment.
MSRT • MSRTs are capable of (a) sufficiently depressurizing steam generators to allow RCS to be cooled down at 90°F/hour, and (b) controlling steam generator pressure.
• Requirements for ELAP event mitigation are bounded by safety-related design basis of equipment described in U.S. EPR FSAR Tier 2, Section 10.3.
Containment Integrity
IRWST • IRWST water volume, temperature, and boration requirements conform to U.S. EPR FSAR Tier 2, Technical Specifications 3.5.4, 3.5.6, and 3.5.7.
• Requirements for ELAP event mitigation are comparable to safety-related design basis of equipment.
SFP Cooling
SFP • SFP level, boration, enrichment, and burnup requirements conform to U.S. EPR FSAR Tier 2, Technical Specifications 3.7.14, 3.7.15, and 3.7.16.
• Requirements for ELAP event mitigation are comparable to safety-related design basis of equipment.
Instrumentation and Controls
Safety related I&C, including PS, SICS, PACS, and SCDS
• Safety related I&C including PS, SICS, PACS, and SCDS functions as described in U.S. EPR FSAR Tier 2, Sections 7.2, 7.3, and 7.5.
• Requirements for ELAP event mitigation are bounded by design basis for safety related I&C equipment.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-151
Equipment Performance Requirements Requirements Comparison
SFP level • Safety related SFP level instrumentation provided that fulfills NRC Order EA-12-051.
• Requirements for ELAP event mitigation using SFP level instrumentation are described in Section 4.2.
AC and DC Power
DC power distribution system, including EUPS buses, EUPS battery chargers (Divisions 1 and 2), and 2 hour batteries (Divisions 1 to 4)
• DC power distribution functions as described in U.S. EPR FSAR Tier 2, Section 8.3 with one exception. To mitigate events initiated in ELAP State D, operator action is required to open one set of PDS valves. This requires the Division 1 MCC 31BNB03 to be used to backfeed power to 31BRB to re-power the Division 1 PDS valves, and requires the Division 4 EUPS bus 34BRA to be used to backfeed power to 34BRB to re-power the Division 4 PDS valves.
• Requirements for ELAP event mitigation are generally comparable to the safety related design basis of the equipment. Backfeeding of the PDS valves is acceptable for this BDBEE because the electrical equipment can support backfeeding.
AC power distribution system, including transformers, breakers, and alternate feeds
• AC power distribution system functions as described in U.S. EPR FSAR Tier 2, Section 8.3 with one exception. If a portable AC source is used in Division 4 to repower the SAHRS pump, then this will require the load to be backfed through transformer 34BMT02.
• Requirements for ELAP event mitigation are generally comparable to the safety related design basis of the equipment. Backfeeding of the SAHRS pump through transformer 34BMT02 is acceptable for this BDBEE because the electrical equipment can support backfeeding.
HVAC
Division 1 and 2 battery room exhaust fans
• Battery room exhaust fans function as described in U.S. EPR FSAR Tier 2, Section 9.4.6.
• Requirements for ELAP event mitigation are bounded by safety-related design basis of equipment.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-152
Equipment Performance Requirements Requirements Comparison
Division 1 and 2 SB supply and exhaust fans
• SB supply and exhaust fans function as described in U.S. EPR FSAR Tier 2, Section 9.4.6 with one exception. For ELAP event mitigation, SB 1 and SB 2 will only be ventilated; chilled water will not be provided.
• Requirements for ELAP event mitigation are generally bounded by the safety-related design basis of the equipment. Ventilation only of the Safeguards Buildings is acceptable because equipment in these buildings will be maintained at acceptable temperatures for this BDBEE without chilled water.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-153
Table 4–21—Performance Requirements for Key Non-Safety Related Equipment
Equipment Performance Requirements Requirements Comparison
Core Cooling
Diesel Driven Fire Water Pump
• Diesel driven fire pumps are capable of providing a minimum of 150 gpm to each of the four SGs with a maximum SG pressure of 100 psia.
• Requirements for ELAP event mitigation are bounded by the design basis for the equipment described in U.S. EPR FSAR Tier 2, Section 9.5.1.
Fire Water Storage Tank
• The capacity of each of the two fire water storage tanks is a minimum of 300,000 gallons.
• Requirements for ELAP event mitigation are comparable to the design basis for the equipment described in U.S. EPR FSAR Tier 2, Section 9.5.1.
SSSS • RCP SSSS limits the RCP seal leakage of each of the four RCP seals to a maximum of 0.5 gpm.
• Requirements for ELAP event mitigation are comparable to the design basis for the equipment described in U.S. EPR FSAR Tier 2, Section 5.4.1.2.1.
PCIP • The PCIP is capable of providing a minimum 330 gpm injection flow to the RCS at a discharge head of 857 feet.
• The PCIP is a dedicated pump used only during an ELAP event.
Containment Integrity
SAHRS Pump and ancillary equipment
• The SAHRS pump is capable of providing a minimum flow of 232 lbm/sec to the containment spray nozzles.
• Requirements for ELAP event mitigation are comparable to the design basis for the equipment described in U.S. EPR FSAR Tier 2, Section 19.2.3.
SAHRS Heat Exchangers
• The SAHRS Heat Exchanger is capable of maintaining containment pressure less than 62 psig and containment temperature less than 310°F with a tube side flow rate of 232 lbm/sec and a shell side flow rate of 2218 gpm at a temperature of 90°F.
• Requirements for ELAP event mitigation are comparable to the design basis for the equipment described in U.S. EPR FSAR Tier 2, Section 19.2.3.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-154
Equipment Performance Requirements Requirements Comparison
Electrical and DC Load Shedding
ELAP Diesel Generator (DG)
• The ELAP DG is capable of generating 1.2 MW at an output voltage of 6.9kV.
• The ELAP DG is a dedicated diesel generator used only during an ELAP event.
4.2 NTTF 7.1, Safety-Related Spent Fuel Pool Level Instrumentation
4.2.1 Overview
Recommendation 7.1 is a Tier 1 recommendation that resulted in the issuance of NRC
Order EA-12-051 (Reference 2). This order stated that reactor licensees must provide
sufficiently reliable instrumentation to monitor SFP water level and be capable of
withstanding design basis natural phenomena.
4.2.2 Conformance
Consistent with the information in Attachment 3 to NRC Order EA-12-051
(Reference 2), the U.S. EPR design addresses the requirements in Attachment 2 to
Order EA-12-051 by providing two physically separate and independent divisions of
safety-related SFP level sensing with two redundant wide range level sensor channels
in each division. The instruments measure the level from the top of the SFP normal
operating range to below the top of the fuel racks. This span provides indication of:
• A level that is adequate to support operation of the normal SFP cooling system.
• A level that is adequate to provide substantial radiation shielding for a person
standing on the SFP operating deck.
• A level where fuel remains covered and actions to implement makeup water addition
should no longer be deferred.
The SFP level instrumentation is safety-related and has the following design features:
• Seismic and environmental qualification of the instruments.
• Independent power supplies.
• Electrical isolation and physical separation between instrument divisions.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-155
• Continuous display in the MCR.
• Routine calibration and testing.
In addition, the following requirements that are specified in Attachment 3 to NRC Order
EA-12-051 (Reference 2) are addressed in a manner consistent with JLD-ISG-2012-03
(Reference 12), NRC Order EA-12-051 (Reference 2), and NEI 12-02, Revision 1
(Reference 13) as endorsed by JLD-ISG-2012-03 (Reference 12).
4.2.3 Arrangement
The SFP includes four SFP wide range level sensors. The safety-related wide range
level sensors are Seismic Category I components. The sensors are located in separate
corners, or recesses, of the SFP to provide reasonable protection against missiles and
debris.
Refer to U.S. EPR FSAR Tier 2, Table 3.2.2-1 and Section 9.1.3.6.
4.2.4 Qualification
The wide range level sensors and cabling for the wide range level instrument channels
are qualified to operate for a minimum period of seven days under the following
conditions:
• Radiological conditions for a normal refueling quantity of freshly discharged
(100 hours) fuel with the SFP water level where fuel remains covered.
• Temperature of 212°F and 100% relative humidity.
• Boiling water and/or steam environment.
• Concentrated borated water environment.
Refer to U.S. EPR FSAR Tier 2, Table 3.11-1.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-156
4.2.5 Power Supplies
The primary instrument channels normally receive power from plant vital AC power.
Each of the two divisions of wide range level sensors includes the capability to connect
a sensor directly to a battery-operated portable indication device. The two portable
indication devices provide on demand push-button-activated indication of SFP level with
no dependence on other station power sources. Each portable indication device is
located in the associated division I&C room, which is protected and accessible during
normal operation, event, and post-event conditions. The portable indication device
batteries are maintained in a charged state during normal operation with a minimum
battery capacity of seven days of on-demand operation.
Refer to U.S. EPR FSAR Tier 2, Sections 9.1.3.1 and 9.1.3.3.2.
4.2.6 Accuracy
The accuracy of the wide range level instrument channels is less than ±1 foot over their
total instrument range of 33 feet (from +30ʹ 0" to +63ʹ 0" elevation). This configuration
provides reasonable assurance that the instrument channel indication demonstrates
that the stored fuel is covered with water. Accuracy is maintained without recalibration
following a power interruption, change in power source, or connection of a battery-
powered indication device.
Refer to U.S. EPR FSAR Tier 2, Section 9.1.3.6.
4.2.7 Display
Continuous display of the SFP level is available in the MCR.
On-demand indication of the SFP level is available in the I&C rooms in Divisions 1
and 4. On-demand display is provided by portable battery-powered indication devices
that can be operated independently of normal and emergency station power sources.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-157
4.2.8 Training
U.S. EPR FSAR Tier 2, Section 13.2 discusses the U.S. EPR design requirements for
development of a training program for plant personnel. The training program will
demonstrate that the SFP instrumentation is maintained available and reliable in an
ELAP event. Personnel will be trained in the use and the provision of alternate power to
the safety-related level instrument channels.
4.3 NTTF 9.3, Enhanced Emergency Preparedness
A portion of Recommendation 9.3 is Tier 1, and requires that enhanced EP staffing and
communications be addressed.
4.3.1 Overview
This section describes provisions for enhancing EP as it relates to staffing and
communications associated with Recommendation 9.3, outlined in Enclosure 5 of the
March 12, 2012 letter, “Request for information pursuant to Title 10 of the Code of
Federal Regulations 50.54(f) regarding Recommendations 2.1, 2.3, and 9.3, of the near-
term task force review of insights from the Fukushima Daiichi accident,” (Reference 9).
The letter requested that an assessment of the COMS and equipment used during an
emergency event be provided to identify any enhancements that may be needed to
ensure communications are maintained during a large scale natural event.
4.3.2 Conformance
4.3.2.1 Enhanced Emergency Plan Communications
The U.S. EPR design includes onsite COMS that are independent and diverse. The
COMS for the U.S. EPR design is described in U.S. EPR FSAR Tier 2, Section 9.5.2.
As noted in U.S. EPR FSAR Tier 2, Section 9.5.2, the COMS consists of the following
subsystems:
• Portable wireless COMS.
• Digital telephone system.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-158
• PA and alarm system.
• Sound-powered system.
• Emergency offsite communication.
• Security communication.
Each communication subsystem provides an independent mode of communications. A
failure of one subsystem does not affect the capability to communicate using the other
subsystem. These diverse COMS are independent of each other to provide effective
communications, including usage in areas exposed to high ambient noise in the plant.
As noted in U.S. EPR FSAR Tier 2, Section 9.5.2, electrical power from a Class 1E
standby power source is provided for the portable wireless COMS base station,
emergency offsite communication capability, and plant security communications. An
isolation device is placed between non-Class 1E COMS components and the Class 1E
power supply to provide the required independence per IEEE Std 384-1992. The
backup power supplies for other communication subsystems (with the exception of the
sound powered phone system) and components are either from integral DC power units
or other plant backup power supplies based on their operational significance and
location. Isolation of the non-safety-related AC sources to the EUPS is also provided as
described in U.S. EPR FSAR Tier 2, Section 8.3.1.1.9.
U.S. EPR FSAR Tier 2, Section 9.5.2.1.3 discusses the requirements for emergency
response facilities and associated communication capabilities.
U.S. EPR FSAR Tier 2, Section 9.5.2.1.3 describes the offsite COMS that interface with
the onsite COMS, including type of connectivity, radio frequency, normal and backup
power supplies, and plant security system interface.
U.S. EPR FSAR Tier 2, Section 9.5.2.1.3 discusses the requirements for emergency
response facilities and associated communication capabilities.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 4-159
4.3.2.2 Enhanced Emergency Plan Staffing
U.S. EPR FSAR Tier 2, Section 13.0 discusses requirements for adequate plant staff
size and technical competence.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 5-1
5.0 REFERENCES
NRC Order EA-12-049, “Order Modifying Licenses with Regard to 1.
Requirements for Mitigation Strategies for Beyond-Design-Basis
External Events,” March 12, 2012.
NRC Order EA-12-051, “Order Modifying Licenses with Regard to 2.
Reliable Spent Fuel Pool Instrumentation,” March 12, 2012.
NEI 12-06, Revision 0, “Diverse and Flexible Coping Strategies (FLEX) 3.
Implementation Guide,” Nuclear Energy Institute, August 2012.
SECY-11-0093, “Recommendations for Enhancing Reactor Safety in the 4.
21st Century, the Near-Term Task Force Review of Insights from the
Fukushima Daiichi Accident,” July 12, 2011.
SECY-11-0124, “Recommended Actions to be Taken without Delay from 5.
the Near-Term Task Force Report,” September 9, 2011.
SECY-11-0137, “Prioritization of Recommended Actions to be Taken in 6.
Response to Fukushima Lessons Learned,” October 3, 2011.
SECY-12-0025, “Proposed Orders and Requests for Information in 7.
Response to Lessons Learned from Japan’s March 11, 2011, Great
Tohoku Earthquake and Tsunami,” February 17, 2012.
SECY-12-0095, “Tier 3 Program Plans and 6-Month Status Update in 8.
Response to Lessons Learned from Japan’s March 11, 2011, Great
Tohoku Earthquake and Subsequent Tsunami,” July 13, 2012.
NRC Letter, “Request for Information Pursuant to Title 10 of the Code of 9.
Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and
9.3, of the Near-Term Task Force Review of Insights from the
Fukushima Dai-Ichi Accident,” March 12, 2012.
Deleted. 10.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 5-2
JLD-ISG-2012-01, “Compliance with Order EA-12-049, Order Modifying 11.
Licenses with Regard to Requirements for Mitigation Strategies for
Beyond-Design-Basis External Events,” August 29, 2012.
JLD-ISG-2012-03, Revision 0, “Compliance with Order EA-12-051, 12.
Reliable Spent Fuel Pool Instrumentation,” August 2012.
NEI 12-02, Revision 1, “Industry Guidance for Compliance with NRC 13.
Order EA-12-051, To Modify Licenses with Regard to Reliable Spent
Fuel Pool Instrumentation,” Nuclear Energy Institute, August 2012.
NRC Letter to AREVA NP Inc., “Implementation of Fukushima Near-14.
Term Task Force Recommendations,” ADAMS Accession Number -
ML121040163, April 25, 2012.
SRM-12-0025, “Proposed Orders and Requests for Information in 15.
Response to Lessons Learned from Japan’s March 11, 2011, Great
Tohoku Earthquake and Tsunami,” February 17, 2012.
ANP-10263(P)(A), “Codes and Methods Applicability Report for the 16.
U.S. EPR,” AREVA NP Inc., November 2007.
EMF-2328(P)(A), “PWR Small Break LOCA Evaluation Model, S-17.
RELAP5 Based.”
Deleted. 18.
BAW-10252PA-00, “Analysis of Containment Response to Pipe 19.
Ruptures using GOTHIC,” Framatome ANP, Inc., December 2005.
ANP-10299P, Revision 2, “Applicability of AREVA NP Containment 20.
Response Evaluation Methodology to the U.S. EPR™ for Large Break
LOCA Analysis Technical Report,” AREVA NP Inc., December 2009.
Regulatory Guide 1.221, Revision 0, “Design-Basis Hurricane and 21.
Hurricane Missiles for Nuclear Power Plants,” October 2011.
AREVA Inc. ANP-10329 Revision 1 U.S. EPR Mitigation Strategies for Extended Loss of AC Power Event Technical Report Page 5-3
ASCE 7-10, “Minimum Design Loads for Buildings and Other 22.
Structures,” American Society of Civil Engineers, 2010.
ASCE 43-05, “Seismic Design Criteria for Structures, Systems and 23.
Components in Nuclear Facilities,” American Society of Civil Engineers,
2005.
ANSI/ASME B31.1-2004, “Power Piping,” American National Standards 24.
Institute/The American Society of Mechanical Engineers, 2004.
NUREG-1628, “Staff Responses to Frequently Asked Questions 25.
Concerning Decommissioning of Nuclear Power Reactors”, Final Report,
June 2000.
Regulatory Guide 1.189, Revision 1, “Fire Protection for Nuclear Power 26.
Plants,” March 2007.
Deleted. 27.
COMSECY-13-0002, “Consolidation of Japan Lessons Learned Near-28.
Term Task Force Recommendations 4 and 7 Regulatory Activities,”
January 25, 2013.
ANSI/AWWA D100-2005, “Welded Steel Tanks for Water Storage.” 29.
Regulatory Guide 1.76, “Design Basis Tornado for Nuclear Power 30.
Plants”, March 2007.
Nuclear Energy Institute (NEI) position paper, “Position Paper: 31.
Shutdown/Refueling Modes” (Agencywide Documents Access and
Management Systems (ADAMS) Accession No. ML13273A514),
September 18, 2013.
NRC letter to Mr. Joseph E. Pollock, Vice President, Nuclear Energy 32.
Institute (NEI), dated September 30, 2013, Accession No.
ML13267A382.