+ All Categories
Home > Documents > “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and...

“Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and...

Date post: 03-Jan-2021
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
25
“Common Challenges Encountered On Sediment Remediation Projects – with Lessons Learned” “Common Challenges Encountered On Sediment Remediation Projects – with Lessons Learned” August 2008 August 2008 George L. Hicks, V.P. Market Segment Director Sediment Management CH2M HILL
Transcript
Page 1: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

“Common Challenges Encountered On Sediment Remediation Projects

– with Lessons Learned”

“Common Challenges Encountered On Sediment Remediation Projects

– with Lessons Learned”

August 2008August 2008

George L. Hicks, V.P. Market Segment DirectorSediment Management

CH2M HILL

Page 2: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

2

Common challenges (and decisions) on sediment remediation projects - including “lessons learned”:

•Dredging and Dewatering •Subaqueous Capping•In-Situ Monitored Natural Attenuation •Making Disposal vs. Beneficial Re-Use Decisions•Balancing Remediation Costs with Risk Reduction

AGENDAAGENDA

Page 3: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

3

Start by Evaluating the Appropriate Technologies:

• Dredging• Water depths, currents & tidal fluctuations• Production Rates (Cys/hr; 24/7, etc.)• Sediment Characteristics

• Dewatering• Dredge Productivity Rates• Available Laydown Area for Dewatering Technology• Available Schedule Duration (limited dredge “windows”)

• Water Treatment• Discharge Criteria (NPDES; Pre-treatment for POTW, etc.)• Re-circulation to dredge prism area

• Transport and Disposal• Hazardous; Non-hazardous; Beneficial Reuse

Dredging and DewateringDredging and Dewatering

Page 4: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

4

Select Dredging Method for Site-Specific Conditions & Regulatory Acceptability

Reference: EPA/OSRTI Sediment Remedies: Dredging – Technical Considerations for Evaluation and Implementation - Michael R. Palermo, PhD

Dredging and DewateringDredging and Dewatering

Page 5: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

5

Select Dewatering Method Based on Site-Specific Conditions and Regulatory Conditions

• Passive dewatering– Lagoon– Confined disposal facility (includes final disposal)

• Active dewatering– Mechanical dewatering (e.g., filter and belt presses, centrifuges )– Geotextile tubes

• May need amendments to increase strength and % solids for disposal

Geotextile TubesFilter Presses

Dredging and DewateringDredging and Dewatering

Page 6: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

6

Plate & Frame Filter Press Operations: Fox River – “Phase I”

Hydraulic Auger Cutter Head Dredge 1,500 – 3,000 GPM @ 5-15% solids

20,000 Gal V-Bottom Screw Auger Tank w/Hydocyclones, Coarse & Fine Liner Motion

Shaker Screens

10 – 18,000 Gal. Agitated Mix Tanks

Filter Press Fast Feed Pumps10 - Plate & Frame Filter Presses (219 ft3 each)

Dewatered PCB Sediment & Filter Cake for Off-site Regulated Disposal

Equalization/Filtration ModuTank – 75,000 Gals. Sand Media Filters & Granular Activated Carbon Contactors

Multiplex Bag Filter Unit

Magnetic Flow Meter

Treated Water Discharge Return

to Fox River

Dredging and Dewatering; ExampleDredging and Dewatering; Example

Page 7: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

7

Dredging and Dewatering; ExampleDredging and Dewatering; Example

Ashtabula River Dredging ProjectWorld’s Largest Geotextile Dewatering Tube Pyramid

14 acres, 50’ deep containing 505,000 Cys of PCB Sediments in 457 tubes – 75’ – 90’ circumference – 100’

to 375’ long

Page 8: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

8

When Selecting Environmental Dredging and Dewatering Technologies - Evaluate Total Project Costs!

• Investigations, lab, pilot tests, and engineering studies• Administrative—cost, schedule, work plans• Mobilization and demobilization• Shore facilities—docks, roads, storage, processing• Silt containment and turbidity mitigation• Water treatment and air pollution control• Solid waste treatment and disposal• Sampling, monitoring, and regulatory compliance • Health and safety• Dredging equipment and operations

Dredging and Dewatering – Lessons LearnedDredging and Dewatering – Lessons Learned

Page 9: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

9

• Imperative that the production rates from the dredge matches thethroughput capabilities of the dewatering (and water treatment) process. Ideally both the dredging and dewatering are controlled by one contractor to eliminate the “blame game” for poor production rates.

• With hydraulic dredging a sophisticated mass flow / polymer delivery system is needed due to the variability of sediment characteristics across most sites. The optimum operating point is a constantly shifting target as the dredging operation proceeds.

• Unexpected debris can make startup and shakedown all the more difficult. On past projects, we have encountered materials that include; animal hides and carcasses, scrap metal and auto parts,heavy equipment tires, sunken timbers, and treated utility poles.

Dredging and Dewatering – Lessons LearnedDredging and Dewatering – Lessons Learned

Page 10: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

10

•Advantages-Quickly reduces exposure

-Risks during capping can be less then those during dredging

-Easier to implement than dredging

-Residual risk (after capping) can be less than after dredging alone

-Can be utilized where debris is present

-Cost Effective

•Disadvantages-Contaminants remain in the aquatic environment

-Water depth is reduced

-Potential erosion

-Long-term monitoring and maintenance is required

-Institutional controls are required

Subaqueous CappingSubaqueous Capping

Page 11: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

11

Many Issues Must Be Considered for an Effective Cap

Factors that must be evaluated during the feasibility study and design stages. Early identification of data needs is essential to cost-effective

project execution and successful remedy negotiations.

Subaqueous CappingSubaqueous Capping

Page 12: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

12

Subaqueous Capping; ExampleSubaqueous Capping; Example

Cap Material Placement at

Fox River OU1

2” Core Sample

Page 13: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

13

Subaqueous Capping – Lessons LearnedSubaqueous Capping – Lessons Learned

Requirements for Capping

•Level bottom slopes•Stable Sediment•Mild water currents•Water deep enough for cap and navigation•Not susceptible to ice scour and flooding•No obstructions or structures•Groundwater and/or NAPL discharge is low•Use restrictions can be implemented and enforced to protect cap•Suitable capping material is readily available•Sediment bearing capacity is great enough to support cap

St. Louis River Interlake Duluth Tar Site

Page 14: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

14

Permitting Requirements Can be Extensive

Subaqueous Capping – Lessons LearnedSubaqueous Capping – Lessons Learned

•Federal Regulations-Section 404 Clean Water Act (33 U.S.C. 1344)

-Section 10 of the Rivers and Harbor Act of 1899 (33 U.S.C. 403)

•State and/or Local Regulations-Inland Lakes and Streams

-Wetlands Protection

-Great Lakes Submerged Lands

-Water Resources Protection

-Floodplain Regulations/Protection

-Sand Dunes Protection and Management

-Shoreland Protection and Management

Page 15: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

15

In-Situ Monitored Natural AttenuationIn-Situ Monitored Natural Attenuation

• USEPA recognizes Monitored Natural Attenuation (MNR) as an effective and permanent remedy

• MNR should be considered initially for all sediment sites• Minimizes ecological impacts associated with remedy implementation • Cost-effectively reduces risk by incorporating natural processes into

remedy decision making • The impulse to remove contaminated sediments from the environment

does not always reflect proper environmental stewardship and risk management

Page 16: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

16

In-Situ Monitored Natural AttenuationIn-Situ Monitored Natural Attenuation

Monitored Natural Recovery (MNR) involves leaving contaminated sediment in place and allowing ongoing aquatic, sedimentary, and biological processes to reduce the bioavailability of the contaminants in order to protect receptors

NRC, 1997. Contaminated Sediments in Ports and Waterways

MNR…uses known, ongoing, naturally occurring processes to contain, destroy, or otherwise reduce the bioavailability or toxicity of contaminants in sediment.

MNR…includes…monitoring to assess whether risk is being reduced as expected.

USEPA, 2005. Contaminated Sediment Remediation Guidance for Hazardous Waste Sites

Page 17: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

17

In-Situ Monitored Natural AttenuationIn-Situ Monitored Natural Attenuation

• Biological (or chemical) oxidation/reduction• Sorption and sequestration • Geochemical precipitation (metals)

Contaminant weathering, transformation and risk attenuation

• Source control• Sediment deposition and burial • Consolidation • Benthic mixing processes

Containment and dilution through natural sedimentation

Long-term monitoring and ecological recovery

Modeling to predict long-term recovery

Sediment stability / resuspension

MNR Approach Lines of Evidence

• Demonstrate achievement of remedial objectives• Demonstrate long-term recovery processes• Demonstrate long-term ecological recovery

• Hydrodynamic models • 1-D sediment modeling • Complex chemical transport modeling

• Desorption or dissolution • Hydrodynamic studies • Sediment critical shear strength• Modeling

Page 18: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

18

Monitored Natural Recovery - Lessons LearnedMonitored Natural Recovery - Lessons Learned

Remedy Comparison• Compare MNR with capping and dredging

– What is a “reasonable time frame” for MNR? – Compare to the realistic time tables for dredging and/or capping to be

fully implemented– When are risk-levels acceptable for MNR?– Balancing costs: Is it worth accelerating MNR?

• When Should I Consider/Use MNR?– Natural processes are always ongoing– Maximize MNR to reduce negative impacts of more aggressive

remedies– Make sure remedies complement MNR processes– Integrate MNR with other remedies– Monitor to reduce uncertainty

Page 19: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

19

Sand[>.0625 mm]

Clay[<.0039 mm]

Silt[>.0039 mm][<.0625 mm]

Clean3

Contaminated2

•Manufactured Soil•Aggregate•Intermediate Landfill Cover•Ocean Disposal•Beach Nourishment1

•Habitat Restoration/Creation•Upland Fill•Highway Construction

•Manufactured Soil•Ocean Disposal•Landfill Final Cap•Landfill Liner•Upland Fill•Nearshore Fill •Brownfield Cover•Habitat Restoration/Creation•Highway Construction

•Upland Fill•Brownfield Cover•Habitat Restoration/Creation•Nearshore Fill•Manufactured Soil•Highway Construction

•Intermediate Landfill Cover•Confined Aquatic Disposal•Confined Upland Disposal•Upland Fill•Nearshore Fill (with Capping)

•Confined Aquatic Disposal•Confined Upland Disposal•Nearshore Fill (with Capping)•Landfill Cap (with Clean Cover)•Brownfield Cap (with Clean Cover)•Mine Reclamation

•Confined Aquatic Disposal•Confined Upland Disposal•Nearshore Fill (with Capping)•Landfill Intermediate Cover•Mine Reclamation•Brownfield Cap (with Clean Cover)•Decontamination and Disposal

What Happens to Our Dredged Material?

1 75% Sand; grainsize distribution must be equivalent to existing conditions2 Uses assume no decontamination3 Uses assume clean or decontaminated

Certain chemical constituents may preclude sediments from beneficial reuse applications

Making Disposal vs. Beneficial Re-Use DecisionsMaking Disposal vs. Beneficial Re-Use Decisions

Page 20: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

20

• Develop sampling and testing protocols for dredging projects and dredged material management consistent with potential upland end uses.

• Identify potential impacts to the environment and public health.

• Determine cost-benefit ratios• Regulate and manage proposed

activities to minimize adverse impacts.• Monitor and establish protocol for

potential adverse impacts.

Beneficial Reuse - Lessons Learned

Page 21: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

21

Balancing Remediation Costs with Risk ReductionBalancing Remediation Costs with Risk Reduction

BioturbationResuspension/TransportDepositionAdvectionDiffusion

Humans

Biota(e.g., invertebrates)

Historical Filling inYosemite Creek AreaHistorical Filling in

Yosemite Creek Area

Transport viaHistorical SloughTransport via

Historical Slough

GroundwaterDischarge/

Tidal Pumping

GroundwaterDischarge/

Tidal Pumping

ShorelineErosion/Runoff

ShorelineErosion/Runoff

SedimentSediment

Surface WaterSurface Water

IngestionIngestion

Upper Trophic Level Receptors(e.g., sport fish, piscivorous birds,invertebrate-eating birds, seals)

Direct ContactDirect Contact

Historical Parcel EFilling/Disposal Activities

Historical Parcel EFilling/Disposal Activities

Major pathway

Minor pathway

Active Source

IngestionIngestion

BioturbationResuspension/TransportDepositionAdvectionDiffusion

Humans

Biota(e.g., invertebrates)

Biota(e.g., invertebrates)

Historical Filling inYosemite Creek AreaHistorical Filling in

Yosemite Creek Area

Transport viaHistorical SloughTransport via

Historical Slough

GroundwaterDischarge/

Tidal Pumping

GroundwaterDischarge/

Tidal Pumping

ShorelineErosion/Runoff

ShorelineErosion/Runoff

SedimentSediment

Surface WaterSurface Water

IngestionIngestion

Upper Trophic Level Receptors(e.g., sport fish, piscivorous birds,invertebrate-eating birds, seals)

Upper Trophic Level Receptors(e.g., sport fish, piscivorous birds,invertebrate-eating birds, seals)

Direct ContactDirect Contact

Historical Parcel EFilling/Disposal Activities

Historical Parcel EFilling/Disposal Activities

Major pathway

Minor pathway

Active Source

Major pathway

Minor pathway

Active Source

IngestionIngestion

Onshore Filling/Disposal

Activities

Historical Filling in Adjacent Tributary

Page 22: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

22

Net Environmental Benefit Analysis (NEBA) for Site Remedy ConsiderationNet Environmental Benefit Analysis (NEBA) for Site Remedy Consideration

Net Environmental Benefit Analysis (NEBA) Defined: A Risk-Benefit Analysis Applied to Environmental Management Options• Analytical framework to quantify and compare the ecosystem service benefits

and/or losses associated with an environmental management option (e.g., remedial action)

• Uses formally quantified values to help identify the break-point between remedial alternatives

• Supports feasibility studies and decision-making • Demonstrate and maximize potential benefits

Origin: Oil Spill Response • Evaluation of tradeoffs associated with response actions

Prince William Sound Exxon Valdez

Page 23: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

23

When to Consider Net Environmental Benefit Analysis (NEBA) for Site Remedy Consideration When to Consider Net Environmental Benefit Analysis (NEBA) for Site Remedy Consideration

Balance of risks and benefits of remediation are ambiguous

• Site retains significant ecological value• Remediation will cause environmental damage creating NRD Liability?• Ecological risks are small, uncertain, or limited• Remediation or restoration may fail or not truly change risk scenario• Costs appear disproportionate to changes in the risk scenario

There are no unacceptable human health risks

Page 24: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

24

• QUESTIONS?

Page 25: “Common Challenges Encountered On Sediment Remediation ... HILL...2 Common challenges (and decisions) on sediment remediation projects - including “lessons learned”: •Dredging

25

George L. Hicks, V.P.Market Segment DirectorSediment ManagementCH2M HILL8501 W. Higgins, Suite 300Chicago, Illinois 60631-2801Mobile 812-946-1669www.ch2mhill.com

Contact InformationContact Information


Recommended