+ All Categories
Home > Documents > Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The...

Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The...

Date post: 09-Aug-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
50
Appendix 3 Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 8 th November 2017 APPLICATION No: J/2010/0481/F APPLICATION TYPE: Full PROPOSAL: Planning permission to erect six wind turbines with an overall height from ground to blade tip of 111m, 33kv substation and compound, construction of internal site tracks and associated works and ancillary works, access points on the Glenmornan Road and the relocation of the temporary turbine supply compound - FEI AMENDED PROPOSAL - includes the relocation of internal access tracks, reduction in turbine numbers from nine to six and the relocation of two turbines. LOCATION: Townland of Craignagapple, approx 650m west of Legalougha Bridge and approx 200m east of Owenmore Bridge 8.5km east of Strabane, BT82 0SR APPLICANT: Brookfield Energy Systems Ltd (formerly Bord Gais Energy) ADVERTISEMENT: 23.12.2010 and 8.12.2016 STATUTORY EXPIRY: 8.1.2017 RECOMMENDATION: Approval REASON FOR PRESENTATION TO COMMITTEE: Major Application All planning application forms, drawings, letters etc. relating to this planning application are available to view on www.planningni.gov.uk This application is returned to Committee following a site inspection by members on the 17 th July 2017 Attendees: Ald Hamilton, McClintock, Bresland, Kerrigan Cllrs Hastings, Boyle, Kelly, Jackson, Gardiner, Logue, Maguire Planning: S McCracken, R McMenamin, K Donaghey
Transcript
Page 1: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Derry City and Strabane District Council Planning Committee Report

COMMITTEE DATE: 8th November 2017

APPLICATION No: J/2010/0481/F

APPLICATION TYPE: Full

PROPOSAL: Planning permission to erect six wind turbines with an overall height from

ground to blade tip of 111m, 33kv substation and compound, construction

of internal site tracks and associated works and ancillary works, access

points on the Glenmornan Road and the relocation of the temporary turbine

supply compound - FEI AMENDED PROPOSAL - includes the relocation of

internal access tracks, reduction in turbine numbers from nine to six and the

relocation of two turbines.

LOCATION: Townland of Craignagapple, approx 650m west of Legalougha Bridge and

approx 200m east of Owenmore Bridge 8.5km east of Strabane, BT82 0SR

APPLICANT: Brookfield Energy Systems Ltd (formerly Bord Gais Energy)

ADVERTISEMENT: 23.12.2010 and 8.12.2016

STATUTORY EXPIRY: 8.1.2017

RECOMMENDATION: Approval

REASON FOR PRESENTATION TO COMMITTEE: Major Application

All planning application forms, drawings, letters etc. relating to this planning application are

available to view on www.planningni.gov.uk

This application is returned to Committee following a site inspection by members on the 17th July

2017

Attendees:

Ald Hamilton, McClintock, Bresland, Kerrigan

Cllrs Hastings, Boyle, Kelly, Jackson, Gardiner, Logue, Maguire

Planning: S McCracken, R McMenamin, K Donaghey

Page 2: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

1. Description of Proposed Development

This proposal is for the erection of six wind turbines with an overall height from ground to blade

tip of 111m, 33kv substation and compound, construction of internal site tracks and associated

works and ancillary works, access points on the Glenmornan Road and the relocation of the

temporary turbine supply compound.

The associated infrastructure is as follows:

six three-bladed, horizontal axis wind turbines, each up to 111m blade tip height;

voltage transformers and related switchgear located inside each turbine;

turbine foundations;

hard-standing areas for the erection of cranes at each turbine location (crane pads);

drainage infrastructure;

upgrade of existing access points and existing internal access tracks;

construction of new internal access tracks;

a wind farm sub-station compound containing a control building;

an on-site electrical and control network of buried cables; and

a temporary turbine supplier’s compound and temporary construction compound.

The overall height from ground to blade tip will not exceed 111m. The rated electrical output of

each turbine is approximately 2.3 megawatts (MW) giving the wind farm a potential installed

capacity of 13.8MW, which is comparable to the electricity generation for 7,728 homes annually

or the displacement of 14,462 tonnes of CO2 per annum. This project will be an extension to the

existing operational Owenreagh Wind Farm (J/2004/1015/F).

Page 3: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1 – Site location plan

Figure 2 – Turbine layout (revised)

Page 4: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 3 – Comparison of 2011 layout vs 2016 amendment

Figure 4 – Turbine design

Page 5: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

2. Site and Surrounding Area

The proposed development is situated on Owenreagh Hill in the western foothills of the Sperrin

mountain range within Strabane District and the townlands of Owenreagh and Craignagapple,

approximately 7km to the east of the town of Strabane. Local land use includes Owenreagh Wind

Farm which has sixteen operational wind turbines, a sub-station building and the associated

infrastructure and low level sheep grazing. Areas of turbary are set out on the eastern edge of the

hill. There is a small coniferous forestry plantation on the west facing slope of Owenreagh Hill.

Figure 5 – showing windfarm site in context of proximate designates sites (AONB shown in yellow)

The proposed development lies within the Sperrin Mountains LCA 29 as described in the Northern

Ireland Landscape Character Assessment Series, 2000. Owenreagh Hill forms part of a complex of

outlying hills west of the main Sperrin ridge. Owenreagh Hill forms part of an outlying complex of

lower lying hills with different characteristics to the main Sperrins range. The hills are smoother

and more rounded and whilst used for extensive grazing and moorland, the intervening valleys

are settled and the character of the local area is less wild and rugged.

Page 6: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an overall

high sensitivity to change associated with wind energy development. However, with reference to

the specific characteristics and values within the LCA the document states that “The scale and

landform of at least parts of the area are in theory well-suited to wind energy development.”

The SPG goes on to state that: “Owenreagh, in the west of this LCA, is the specific area in this LCA

that is most suited to wind energy development. Consideration should be given to siting turbines

on hill flanks where they might be seen against a backdrop of land.”

The SPG states that “care should be taken to avoid adverse impacts on skylines, views and the

visual amenity, recreational value and wild character of this LCA. Care should be taken to ensure

that wind energy developments do not dominate and flatten this topographically complex

landscape.”

3. EIA Determination

The application was submitted with a voluntary Environmental Statement received in December

2010.

Further Environmental Information was submitted in November 2014 and November 2016. Both

the Environmental Statement and the Further Environmental Information were advertised, in

accordance with the Planning (Environmental Impact Assessment) Regulations (Northern Ireland)

1999 (as amended).

4. Site Constraints

Sperrins Area of Outstanding Natural Beauty

Q200 pluvial ponding

Unmodelled River Buffer

Archaeological/monument sites:

TYR 006:015 – Lisnaragh Irish

TYR 006:007 - Meendamph Stone Circle

TYR 007:048 – Silverbrook House, Tirkemaghan

TYR 005:010 – Evish Wedge Tomb

Page 7: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

TYR 005:014 – Knocknahorna Stone Circle

Figure 6 – Showing archaeological and monument sites in proximity to windfarm (fig 11.1 of ES)

5. Neighbour Notification Report

Reference Number

Neighbour Address Date Neighbour

Notified

1

J/2010/0481/F 46 Crockan Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HZ, 11/29/16

2

J/2010/0481/F

109 Hollyhill

Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HY, 11/29/16

3

J/2010/0481/F 113 Hollyhill Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HY, 11/29/16

4

J/2010/0481/F

Glenmornan

Road,Craignagapple,Strabane,Tyrone,BT82 0EX, 11/29/16

5

J/2010/0481/F 112 Hollyhill Road,Lagavadder,Strabane,Tyrone,BT82 0HY, 11/29/16

Page 8: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

6

J/2010/0481/F

44 Crockan

Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HZ, 11/29/16

7

J/2010/0481/F 39 Crockan Road,Lagavittal,Strabane,Tyrone,BT82 0HZ, 11/29/16

8

J/2010/0481/F

105 Hollyhill

Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HY, 11/29/16

9

J/2010/0481/F 101 Hollyhill Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HY, 11/29/16

10

J/2010/0481/F

38 Crockan

Road,Lagavittal,Strabane,Tyrone,BT82 0HZ, 11/29/16

11

J/2010/0481/F 31 Napple Road,Craignagapple,Dunnamanagh,Tyrone,, 11/29/16

12

J/2010/0481/F

96 Hollyhill

Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HY, 11/29/16

13

J/2010/0481/F 131 Moorlough Road,Knocklnarvoer,Strabane,Tyrone,BT82 0ES, 11/29/16

14

J/2010/0481/F

111 Hollyhill

Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HY, 11/29/16

15

J/2010/0481/F 100 Hollyhill Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HY, 11/29/16

16

J/2010/0481/F

106 Hollyhill

Road,Knocklnarvoer,Strabane,Tyrone,BT82 0HY, 11/29/16

6. Relevant Site History

Reference Location Proposal Status Date

J/2010/0194/F Erection of 1 no. meteorological mast of 70m in height for the purpose of monitoring wind and climate conditions. Planning permission for a period of 5 years is requested.

Approx. 1040m SW of the junction of Glenmornan Road and Napple Road in the townland of Craignagapple, Strabane

Approved 6.9.2010

J/2010/0030/F Retention for period of 5 years of 1 No. meteorological mast of 70m in height for the purpose of monitoring wind and climate conditions

Approximately 700m East of Glenmornan Road, Townland of Craignagapple, Strabane

Approved 12.05.2010

Page 9: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

(previously permitted under planning ref. J/2008/0581/F).

J/2008/0581/F Erection of 1 No. tubular meteorological mast of 70m in height for the purpose of monitoring wind speed data.

Approx 700m East of 60 Glenmornan Road, Townland of Craignagapple, Strabane

Approved 10.08.2009

J/2004/1015/F Substitution of 6 approved (unconstructed) wind turbines (total height of 60 metres ground to blade tip) with 6 wind turbines with slight specification alterations (total height of 66 metres ground to blade tip) and 475 metres of service roads linking with existing wind farm at Owenreagh Hill and with development taking place within existing site boundary

Owenreagh Hill, Craignagapple, Strabane, Co Tyrone

Approved 29.09.2005

J/1994/0058 Retention of temporary latex tower with wind measurement sensors

CRAIGNAGAPPLE, STRABANE

Approved 24.10.1995

J/1993/0286 Erection of 16 turbine windfarm and associated works

CRAIGNAGAPPLE, STRABANE

Approved 26.09.1995

Page 10: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

7. Policy Framework

Strabane Area Plan 2001

Regional Development Strategy (RDS) – Northern Ireland 2035

Strategic Planning Policy Statement for Northern Ireland (SPPS)

PPS 2 – Planning and Nature Conservation

PPS 3 – Access, Movement and Parking (Revised)

PPS 6 – Planning, Archaeology and the Built Heritage

PPS 15 – Planning and Flood Risk

PPS 16 – Tourism

PPS 18 – Renewable Energy (Best Practice Guide)

PPS 21 – Sustainable Development in the Countryside

Best Practice Guidance to PPS18

Supplementary Planning Guidance - Wind Energy Development in Northern Ireland’s Landscapes

8. Consultee Responses

Consultee

Responses Response dates

Issues Final position

Environmental Health

4 19.05.17 24.01.17 21.05.15 07.04.11

Cumulative noise setting with Owenreagh 1 and 2. Impact on residential amenity

No objection subject to conditions

City of Derry Airport

2 21.11.11 18.08.11

Turbines 1 and 9 to be fitted with aviation warning lights. Issues in respect of turbines 5 and 6.

No objection

Belfast International Airport

1 18.0211 None No objection

CAA - Directorate of Airspace Policy

1 14.03.11 None No objection

National Air Traffic Service

1 22.07.11 None No objection

Council for nature conservation and countryside

1 22.07.11 None No comment

Page 11: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

DARD – Forest Service

1 08.0311 None No objection

DARDNI – Fisheries Division

1 17.02.11 None No objection

DCAL – Inland Fisheries

1 10.03.11 None No objection

Strabane District Council

1 10.03.11 No expressions of opinions by members

No objection

Loughs Agency

1 08.04.11 no objection in principle, provided that all mitigation measures are implemented

Approve with conditions

Transport NI

2 12.01.17 01.03.11

Detailed information required re haulage route, passing bays etc

Linked to additional application

Shared Environmental Services

2 23.05.17 16.10.15

Proposal passed stage 2 HRA, no significant impacts on designated sites.

CEMP required prior to commencement. Approve with conditions.

NIEA - Natural Heritage

4 22.05.17 12.05.17 14.12.16 01.09.11

Active Peatland Impact on ASSI/SAC re drain/watercourse. Badgers Comments on objections

Approve subject to conditions

NIEA – Protecting Historic Monuments

1 07.03.11 Impacts on identified monument sites.

Approve with conditions

NIEA – Water Management Unit

2 22.05.17 04.03.11

Storage of fuel etc in relation to watercourse,

Approve with conditions

Rivers Agency

5 29.07.17 23.12.16 15.10.15 28.02.11 17.02.11

Access track within 100 year flood plain. Surface water run off issues. Comment on FRA

Approve with informatives

NIEA- Landscape Architects Branch

3 22.05.17 07.01.15 08.03.11

Significant impact upon Landscape Quality re juxtaposition with existing windfarms

Objections to proposal

DETI – Energy Branch

1 05.04.11 Comment of PFG targets No objection

DETI – Geological Survey

1 23.01.14 17.02.11

Risk assessment of peat slide. Turbines have been moved from areas of active peat.

No objection

Page 12: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

RSPB

2 12.01.17 16.05.11

Ornithological monitoring plan

No objection

OFCOM (NI)

1 09.08.11 Arquiva and Energis links identified as in proximity to turbines

Further consultation with link owners.

Arquiva 1 16.02.11 Proximity to Derry – Strabane links (105m clearance)

No objection

NIE (Windfarm Developments)

1 19.05.11 Proximity of overhead lines Possibility of provision of further overhead and underground lines Grid issues.

No objection

Vodafone (cable and wireless, Energis)

1 01.03.11 Proximity of link identified by OFCOM

No objections

Northern Ireland Tourist Board

1 24.03.11 Impacts or turbine development upon tourist attitudes.

No objection

DRD Economics Branch

1 22.12.14 Agrees in relation to economic benefit. Several benefits are uncertain, possibly over estimated.

No objection

UK Crown Bodies D.I.O safeguarding

2 18.12.14 18.12.14

No objection No objection

UK Crown Bodies D.I.O defence estates

1 17.07.11 Turbine warning lights to be fitted

No objection

9. Representations Consideration

2 no letters of objection have been received from the general public in relation to this proposal.

The matters raised can be summarised as;

Impact on landscape quality

Impact on biodiversity

Impact on road safety

Impact on tourism

Consideration will be given to these matters in section 11 of this report.

10. Planning Assessment and Other Material Considerations

Section 6 (4) of the Planning Act (Northern Ireland) 2011 requires Council to make planning decisions in

accordance with the Local Development Plan unless other material considerations indicate otherwise. The

Page 13: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

site is located in the countryside, outside any settlement as defined in the Strabane Area Plan. The

Strabane Area Plan has no policies for wind farm development in the countryside.

The provisions of the Strategic Planning Policy Statement for Northern Ireland (SPPS) are a material

consideration. This policy document sets out the transitional arrangements that will operate until Council

has adopted a Plan Strategy for the whole of the council area. During this transitional period Council will

apply the SPPS and retained planning policy statements. In addition to the Strabane Area Plan and SPPS

the relevant policy context to be considered is also contained within:

• Planning Policy Statement 2 – Planning and Nature Conservation

• Planning Policy Statement 3 – Access, Movement and Parking (Revised)

• Planning Policy Statement 6 – Planning, Archaeology and the Built Heritage

Planning Policy Statement 15 – Planning and flood risk

• Planning Policy Statement 16 Tourism (PPS16)

• Planning Policy Statement 18 Renewable Energy (PPS18)

• Planning Policy Statement 21 Sustainable Development in the Countryside (PPS21).

• Supplementary planning guidance is also set out in the ‘Best Practice Guidance to PPS18

Renewable Energy’ BPG and ‘Wind Energy Development in Northern Ireland Landscapes’ (SPG)

published by the Northern Ireland Environment Agency (NIEA).

Policy CTY1 of PPS21 states there are a range of types of development which in principle are considered

acceptable in the countryside and that will contribute to the aims of sustainable development. It states

that planning permission will be granted for non-residential development in the countryside for renewable

energy projects in accordance with PPS18.

PPS18 is consistent with the aim of the SPPS for the siting of renewable energy facilities. Policy RE1

Renewable Energy Development of PPS18 states that development that generates energy from renewable

sources will be permitted provided the proposal will not result in an unacceptable adverse impact on five

criteria.

a) Public safety, human health, or residential amenity;

b) Visual amenity and landscape character

c) Biodiversity, nature conservation or built heritage interests

d) Local natural resources, such as air quality, water quality or quantity; and

e) Public access to the countryside

Page 14: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Policy RE 1 also states applications for wind energy development will also be required to demonstrate a

further seven criteria:

(i) the development will not have an unacceptable impact on visual amenity or landscape character

through the number, scale, size and siting of turbines;

(ii) that the development has taken into consideration the cumulative impact of existing wind turbines,

those which have permissions and those that are currently the subject of valid but undetermined

applications;

(iii) that the development will not create a significant risk of landslide or bog burst;

(iv) that no part of the development will give rise to unacceptable electromagnetic interference to

communications installations; radar or air traffic control systems; emergency services

communications; or other telecommunication systems;

(v) that no part of the development will have an unacceptable impact on roads, rail or aviation safety;

(vi) that the development will not cause significant harm to the safety or amenity of any sensitive

receptors (including future occupants of committed developments) arising from noise; shadow flicker;

ice throw; and reflected light; and

(vii) that above-ground redundant plant (including turbines), buildings and associated infrastructure

shall be removed and the site restored to an agreed standard appropriate to its location.

Paragraph 1.12 of the SPPS indicates that any conflict between it and any retained policy must be resolved

in favour of the SPPS. Policy RE1 of PPS18 states that the wider environmental, economic and social

benefits of all proposals for renewable energy projects are material considerations that will be given

‘significant’ weight in determining whether planning permission should be granted. Paragraph 6.225 of the

SPPS however, now states that the wider environmental, economic and social benefits of all proposals for

renewable energy projects are material considerations that will be given ‘appropriate’ weight in

determining whether planning permission should be granted.

Paragraph 6.219 goes on to identify that the regional strategic objectives for renewable energy are to;

ensure that the environmental, landscape, visual and amenity impacts associated with or arising from

renewable energy development are adequately addressed; ensure adequate protection of the region’s

built, natural, and cultural heritage features; and facilitate the integration of renewable energy technology

into the design, siting and layout of new development and promote greater application of the principles of

Passive Solar Design.

Environmental, Economic and Social Benefits

Paragraph 6.218 of the SPPS states that the aim of the SPPS in relation to renewable energy is to facilitate

the siting of renewable energy generating facilities in appropriate locations within the built and natural

Page 15: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

environment in order to achieve Northern Ireland’s renewable energy targets and to realise the benefits

of renewable energy without compromising other environmental assets of acknowledged importance.

In determining all wind farm proposals, the Council is aware of the government thrust towards renewable

energy targets. Northern Ireland has a target of 40% of energy from renewable sources by 2020. The

Council has been informed (source DETI) that currently in the region of 32% is provided by renewable

sources. The proposal is a wind farm development with the potential to produce 13.8MW providing a

sustainable renewable energy supply, which will contribute towards the renewable energy target and to

carbon reduction by the displacement of 14,462 tonnes of carbon dioxide. The proposal also includes

measures to protect and, through mitigation measure, enhance the natural environment. It is considered

that risks of damage to the environment have been understood and suitable mitigation is proposed within

the ES where it is required. Following consultation with expert bodies within DAERA it is considered

potential impacts have been addressed and adequately mitigated and the proposal is considered to meet

the policy requirements of PPS18 and the SPPS.-

The SPPS also contains guidance on the materiality of community funds such as those associated with Wind

Farm proposals; Paragraph 5.71 states that “in some circumstances, community benefits may be offered

voluntarily by developers to communities likely to be affected by a development. Community benefits can

take a variety of forms including payments to the community; in-kind benefits; and shared ownership

arrangements. Whilst the Council is committed to ensuring that local communities benefit from

development schemes in their area, such community benefits cannot be considered material

considerations in decision-taking and are distinct from developer contributions and planning conditions.”

In terms of the proposed economic benefits of the proposal, it is estimated that circa £139,900 will be

generated in annual business rates equating to approx. £3.5 million for the lifetime of the project. The FEI

acknowledges that this is a gross impact as this rate payable may displace other energy producers. It is

estimated that the proposal will generate 38 job years within Northern Ireland, with an estimated 8 job

years within this figure being supported within the Derry City and Strabane District Council area. As with

any wind farm development there is the potential for leakage of these projected jobs outside the local

area. Similarly, 10 of the job years identified are for the feasibility and planning of the project which have

already been realised. A community benefit fund will be shared between community organisations around

the proposed 13.8MW Craignagapple Windfarm, at a rate of £5000 per MW, equivalent to an annual

payment of £69,000 for the 25 year lifespan of the windfarm. This is towards the upper scale of the

recommended Northern Ireland Renewables Industry Group (NIRIG) guidelines. Community Benefit

Funding would commence in the first year of operation of the windfarm if granted. The total estimated

capital value of this community fund for the lifetime of the project equates to £1,725,000.

Page 16: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Each application must therefore be considered on its merits in terms of the impacts experienced as a result

of the proposal and of those wider benefits that it potentially offers. It is thus a matter of professional

judgement in each individual case to judge the quantifiable benefits (e.g. annual rates, potential jobs, direct

and indirect benefits, reduction in fossil fuels and contribution to the SEF targets) against the

unquantifiable benefits (e.g. community funds). This then allows that the weight to be afforded to the

specific benefits of the renewable project is determined by the local authority. Similar to the previous

approach, consideration in affording weight to the wider environmental, economic and social benefits of

this proposal is therefore based on the evidential presentation of the specific benefits of this scheme.

Council acknowledges the wider benefits as stated i.e. £139,900 generated in annual business rates & a

community fund of £1,725,000 generated across the 25 year project life.

Public Safety, Human Health, or residential amenity

Consultation with Geological Survey Northern Ireland (GSNI) and DAERA was undertaken and their

comments in relation to peat, peat stability etc indicate that subject to the appropriate mitigation detailed

within the ES documents and through condition the proposal is acceptable and meets the policy

requirements of RE1 of PPS18 and the SPPS.

In terms of electromagnetic interference consultation with CODA, Ofcom, Energis, Arquiva and other

telecoms providers have indicated that the proposal will not impact on their systems.

In order to assess the noise impacts, a noise assessment (NA) was submitted within the ES and

consequently revised with each of the FEI submissions. Figure 9.1 in the submitted FEI (shown below)

identifies noise sensitive receptors within the vicinity of the application site. The details of the NA have

been considered by the Councils Environmental Health Department (EHD) who have confirmed that they

broadly concur with its findings and offer no objection to the proposal. Furthermore EHD raised no issue

in relation to public safety or human health.

Page 17: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 7 – showing NSR in relation to amended turbine layout (Figure 9.1 within FEI)

In relation to shadow flicker for windfarm developments, a separation distance of 10 times rotor

diameter to occupied property, with a minimum distance not less than 500m, will generally apply.

Shadow flicker has the potential to impact properties within 130 degrees either side of north. At

distances greater than 10 times rotor diameter from a turbine the potential for shadow flicker is very

low. The 2014 FEI advises in para 2.1 that ‘Brookfield Renewable Energy Group identified 227

properties within the immediate vicinity of the Craignagapple Wind Farm: 208 in existence and 19

in planning. Of the 208 existing buildings, 95 are occupied. Out of these 227 properties, 1 is within

the 10 rotor diameter zone’. Having undertaken a shadow flicker analysis within the ES documents

the applicant has advised that the Likely Annual Duration Per Annum of potential shadow flicker at the

property (H1) will be approximately 13.5 hours. Considering the property is 819m from the closest

turbine, the fact that the property is owned by the project landowner and unoccupied, there will be

no significant impact in relation to shadow flicker. It is therefore my considered opinion that the

proposal will not have a significantly adverse impact upon human health or residential amenity.

Due to the size of the application site and the specific hazards attributed to the site (pluvial ponding),

a surface water management plan, drainage assessment and flood risk assessment have been included

within the ES and FEI documentation. These assessments indicated the following; the site is not in a

Page 18: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

sensitive flood risk area; the development itself is not sensitive to flooding; and the site has a relatively

high natural run-off and as such the “hard-standing” element of the proposal will not be totally

impermeable therefore the proposal will not alter the existing situation significantly in terms of flood

risk. The proposal also includes SUDS (sustainable draining) measures to minimise local drainage

pattern changes and provide an element of storage for the local increased run-off. The drainage design,

which incorporates dams, local soakaways and settlement ponds will also work to limit rapid transfer

of run-off to downstream watercourses. DAERA have considered the detail of the Drainage Assessment

and are content with the details contained within subject to condition.

Rivers Agency was consulted and following a consideration of the detail contained within both the

Drainage Assessment and the Flood Risk Assessment which accompanied the application, they offered

no objection to the proposal. The proposal is therefore considered to be in compliance with the

requirements of FLD1 of PPS15 in that all sources of flood risk have been identified and there is

adequate measures to manage and mitigate and increase in flood risk. Rivers Agency were also

consulted at the request of the Planning Committee as a consequence of the significant flooding event

in this Council area, they reiterated their previous position that this development will not have a

significant effect on flood risk within the local area.

It is therefore my considered opinion that the proposal is in conformity with policy requirements of

RE1 of PPS18, FLD1 of PPS 15 and the SPPS in terms of Public Safety, Human Health and Residential

Amenity.

Visual Amenity and Landscape Character

The Landscape and Visual Impact Assessment (LVIA) contained within the ES and Addendum

documents concludes that;

“The landscape and visual assessment has established that the proposed Development would

cause differing degrees of change to the landscape and visual baseline conditions during the

operational phase of the proposed Development. Visibility mapping and viewpoint analysis

indicate that the proposed wind farm extension, despite the use of taller turbines, adds in only a

very minor way to the overall visual footprint of the development. There will be opportunities for

direct visibility from the scattered rural settlement and villages within Burn Dennet Valley,

Faughan Valley and Foyle Valleys. Whilst local significant effects are identified the Development

will be seen within the context of the existing Owenreagh Wind Farm as a coherent group of

development.”

On receipt of the application the DOE consulted with Landscape Architects in consideration of

landscape and visual amenity. Landscape Architect are now not a statutory consultee, however

Page 19: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

council is considering their comments as material in this case. Having considered the detail of

both the ES and Addendum documents they advise that considering the sensitivity of the

landscape (AONB) and due to the juxtaposition of the proposed turbines with the existing 16

turbines at Owenreagh, the proposed development would have an unacceptable adverse impact

on visual amenity and landscape character and contend that this is supported by the guidance

outlined in the Supplementary Planning Guidance (SPG). NIEA LAB have advised specifically that;

‘In conclusion we would broadly concur with the analysis in the FEI that this wind farm may

appear like an extension to the existing Owenreagh wind farm, an area outlined clearly in the

SPG as being the most suitable within the LCA. However we consider that the addition of 6

turbines of a larger scale, height, spacing and rotational speed would be visually inconsistent

with the existing ones ie:- one set of turbines would visually jar with another. This would, in

our opinion, have a negative impact on the AONB. This is well illustrated in photomontages 4

and 20 in particular. You may wish to request the agent/applicant to look at this aspect

again and put forward appropriate solution if this is possible. There is also an issue with

overall cumulative impact on the AONB, and if the council were to approve this proposal

(which would mean a total of 22 no. turbines in the Owenreagh complex) we would wish to

state that any more extensions to this complex would be unlikely to be considered favourably

by the NED Protected Landscapes Team’.

In order that this issue be considered and weighted appropriately a full assessment must be made

of the particular public vantage points relative to the proposal, particular reference is made to the

viewpoints identified by NIEA LAB (VP 4 and 20). These have been provided as part of the LVIA by

the agent and are considered below.

Page 20: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 8

– sho

win

g locatio

n o

f viewp

oin

ts.

Page 21: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 9

– View

po

int 4

: Mo

or Lo

ugh

Picn

ic Area (w

itho

ut p

rop

osed

turb

ines)

Page 22: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1

0 –

View

po

int 4

: Mo

or Lo

ugh

Picn

ic Area (w

ith p

rop

osed

turb

ines sh

ow

n)

Page 23: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1

1 –

View

po

int 5

: Ho

lyhill R

oad

(with

ou

t pro

po

sed tu

rbin

es)

Page 24: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1

2 – V

iewp

oin

t 5: H

olyh

ill Ro

ad (w

ith p

rop

osed

turb

ines)

Page 25: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1

3 –

View

po

int 1

0: Sleiveb

eg Ro

ad (w

itho

ut p

rop

osed

turb

ines)

Page 26: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1

4 – V

iewp

oin

t 10

: Slievebeg R

oad

(with

pro

po

sed tu

rbin

es sho

wn

)

Page 27: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1

5 - V

iewp

oin

t 11

:Ballyn

amallagh

t, B4

8 (p

rop

osed

turb

ines n

ot sh

ow

n)

Page 28: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1

6 –

View

po

int 1

1: B

allynam

allaght B

48 (w

ith p

rop

osed

turb

ines sh

ow

n)

Page 29: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1

7- V

iewp

oin

t 20

: Mee

nd

amp

h R

oad

(pro

po

sed tu

rbin

es no

t sho

wn

)

Page 30: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 1

8- V

iewp

oin

t 20

: Mee

nd

amp

h R

oad

(pro

po

sed tu

rbin

es sho

wn

)

Page 31: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

The photomontages show the varying visual impacts of the proposal from numerous locations both

short range and long range views, although the visuals demonstrate that there is an impact locally this

is widely acknowledged in wind farm developments. The proposed wind farm is within the western

fringes of the Sperrins AONB, views of the site which are more critical in terms of an adverse impact

are reasonably localised, views from the south west of the proposed wind farm are broadly screened

by the existing landforms at Koram Hill and Owenreagh Hill, as such views into the AONB from western

and southern vantage points do not represent a significantly adverse impact on landscape character

and do not represent a significant impact upon the particular character of the AONB.

The table below is taken from the Best Practice Guidance and outlines the general perceptions of wind

farms within landscapes. In relation to this scheme, the turbines are undoubtedly a prominent feature

in the landscape when viewed from Glenmornan Road, however in consideration of the guidance it is

accepted that this is a likely outcome and therefore determining weight cannot be placed on such short

range views.

Viewpoint Synopsis

VP4 This viewpoint is from the public picnic area at Moor Lough. This viewpoint is approx.

2.4km from the nearest proposed turbine. All six of the proposed turbines can be seen

from this location along with all 16 operational turbines at Owenreagh.

VP5 This viewpoint is from Holyhill Road looking eastward. This viewpoint is approx. 4.5km

from the nearest proposed turbine. Three of the proposed turbines are visible with

approx. 9 of the existing turbines at Owenreagh.

VP10 This viewpoint is taken from the Slievebeg Road looking towards the north west. The

viewpoint is approx. 8.6km from the nearest proposed turbine. All six of the proposed

turbines are visible. The turbines at Owenreagh are not visible from this location.

VP11 This viewpoint is taken from the Ballynamallaght Road looking towards the west. The

viewpoint is approx. 5.8km from the nearest proposed turbine. All six of the proposed

turbines are visible along with all 16 operational turbines at Owenreagh.

VP20 This viewpoint is taken Meendamph Road looking towards the west. The viewpoint is

approx. 2.2km from the nearest proposed turbine. All six of the turbines are visible from

this location along with all 16 operational turbines at Owenreagh.

Page 32: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Figure 19: Para 1.3.25 of Best Practice Guidance to Planning Policy Statement 18.

Viewpoints 4, 5 and 20 shown above fall within the second band of the table, i.e they are within 2-

5kms of the nearest turbines. Therefore it is accepted that the turbines are likely to be relatively

prominent features in the landscape at this distance. From these viewpoints Landscape Architects

Branch (LAB) are less concerned with the prominence of the proposed wind farm but rather its

relationship with the existing turbines at Owenreagh 1 and 2.

The turbines at Owenreagh are approx. 60m and 70m in height and have been operational for a period

in excess of ten years. There is already an impact upon the landscape character from these turbines,

this impact is not significantly adverse. The assertion by LAB that the proposed turbines would not

necessarily appear as an extension to Owenreagh is indeed correct. To require that the proposed

turbines match the size and scale of Owenreagh would place an unnecessary burden upon the

proposed operator. LAB have used guidance written by Scottish Natural in determining the nature of

the impacts in relation to the relationship between the turbines, whilst this is indeed best practice it is

not legislation to which this Council must attach weight. The particular relationship between the

windfarms is only adverse at shorter range when the disparity between scale and size of the turbines

is evident, viewpoint 4 is the most critical viewpoint when assessing this level of detriment.

Viewpoints 10 and 11 show the lessening impact that distance has upon this impact. Viewpoint 10 is

8.6km from the nearest turbine and at this distance, whilst one may be aware that the turbines are of

a different size, the juxtaposition between them does not cause an adverse visual impact. The most

pronounced impacts are therefore at short range towards the north of the proposed wind farm, these

impacts are limited to Moorlough Road and Hollyhill Road at the stretches which are adjacent to the

proposed wind farm. The reasonably localised nature of these impacts does not have a wider

significant impact upon the setting and landscape character of the AONB.

Page 33: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

In considering the cumulative impact of the proposal along with existing wind turbine development, it

is my opinion that the existing landform has the capacity to absorb the proposal with no significant

detriment to visual impact. Having considered the requirements of RE1 of PPS18 I am of the opinion

that the proposal is in compliance in that the number, scale, size and siting of turbines will not have an

adverse impact when considered in the landscape both in isolation and in accumulation with other

wind farm developments in the area.

It is acknowledged that the surrounding wider landscape accommodates existing wind farm

development, the existing cluster at Slieve Kirk sits approx. 5km to the north of this site which contains

over 30 turbines. The existing wind farm at Bessy Bell sits approx. 10 km to the south and contains over

10 turbines. Given the separation distances between these identified existing wind farms it is my

considered opinion that there will be no resultant unacceptable cumulative visual impact.

Landscape Architects remain of the opinion that the landscape and visual impacts of the proposal are

unacceptable and they have expressed concern about the cumulative impact of the growing number

of wind farms within this area as well as its impact upon the AONB, it must be considered that they are

no longer a statutory consultee and the assessment of visual impact is one for the Council to consider.

The proposal is located on the western fringes of the Sperrins AONB, and having regard to the

Supplementary Planning Guidance (SPG) it is considered that the proposal will not detract from its

character or have a significant detrimental impact on the amenity of the AONB designation.

Notwithstanding the concerns raised by Landscape Architects and the guidance afforded in the SPG,

on balance I consider the development to be acceptable in overall landscape terms, in that the impacts

will be localised and will not have an adverse impact on the integrity of the Sperrins AONB.

Biodiversity, Nature Conservation or Built Heritage interests

Following consultation with relevant expert bodies including DAERA Natural Environment Division

(NED), it is considered that the proposal is not contrary to PPS2. The reduction of the scheme to 6

turbines, the subsequent removal of T5, 6 and 7 the reorientation of T4 has moved development away

from any areas of ‘active peat’. This then has reduced the impact that the proposal will have on priority

habitat.

NED advised in their latest consultation response that;

“NED acknowledges that the revised 6 turbine layout and the FEI which has been submitted has addressed the concerns raised in our previous consultation letter, dated 12 October 2015, in particular with regard to impacts on Northern Ireland priority habitats (including active

Page 34: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

blanket bog), peat slide risk, peat management, ornithology and habitat management measures.

Following assessment of the FEI, NED is largely content with the revisions made to the layout and the substantial additional information which has been provided. Although some minor concerns remain with some of the detail provided we consider that these can be addressed in final versions of the documents to be submitted and agreed by the planning authority and NIEA prior to any works commencing”.

A Habitats Regulations Assessment has also been undertaken by DAERA and they are content that any

impact can be adequately mitigated.

It is therefore considered, subject to condition that the proposal is in conformity with policy NH2 &

NH5 of PPS2, RE1 of PPS18 and the SPPS in respect of biodiversity and nature conservation.

In respect of built heritage interests, the site assessment indicated that there are no known

archaeological sites located within the proposed development area. Therefore no direct physical

impact will be placed on any sites of archaeological interest.

A total of 21 known archaeological sites and monuments are located within a 5km radius of the area

of proposed development, eight of which have been designated as of regional importance. While there

will be no direct physical impact upon any of these archaeological sites within the 5km search area,

the presence of these sites suggests that the proposed development area is located within an area of

possible archaeological interest. As such there is the potential for previously undiscovered sub-surface

archaeological remains to exist within the proposed development area. To minimise any potential

impact an appropriate mitigation and management strategy is recommended.

A total of five archaeological sites were identified for the purposes of a visual impact assessment. In all

cases it was found that the existing Owenreagh Wind Farm was visible within the same angle of view

of the identified monuments. As such the proposed new wind farm will have no discernible effect on

the setting of these monuments. The archaeological assessment submitted in the 2010 ES was

reviewed by NIEA Historical Monuments Unit (NIEA-HMU) who were satisfied that the proposed wind

farm would not adversely affect the setting of any of the identified monuments. The NIEA-HMU

response (dated 7th March 2011) also stated that NIEA-HMU was satisfied that the mitigation

measures proposed for any physical impact the development may have on archaeological features

were appropriate for a development of this nature, and made the following recommendation.

“Prior to construction commencing, an archaeological programme of works should be presented

to and approved by the Northern Ireland Environment Agency: Built Heritage. This approved

Page 35: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

programme should be incorporated into a pre-build Construction Method Statement, prepared by

the developer. The written scheme should specify the methodology and timetable for a

programme of work covering the investigation and evaluation of archaeological remains within

the site, for mitigation of any impacts through excavation or recording and preservation of the

remains in situ.”

NIEA-HMU submitted a response to this council on 13th January 2015 in relation to the 2014 FEI stating

that;

“While this development will be visible from a number of archaeological sites and monuments,

NIEA-HMU would accept the information provided by the applicant and consider that the

development would not adversely impact upon the setting of those sites and monuments.”

In relation to Listed Buildings, 11.6.4 of the 2010 Environmental Statement advised that a review of the

Historic Buildings Records was conducted. This review identified a single building recorded in the

Historic Buildings Record within the 5km search area. The building HB/10/11/7 is St Joseph’s Roman

Catholic Church. It is recorded as having been built in 1792 and is described as a five bay hall with

adjoining tower. The existing turbines at Owenreagh are visible from this location therefore the

additional turbines will also be visible, the separation distance between the proposed turbines and the

church are such that the proposed turbines will not have a significantly detrimental impact upon the

setting of the listed structure. Also given the positioning of the Church on the roadside of the Moorlough

Road, any views of the church from the public road network do not feature the existing or proposed

turbines.

Local natural resources, such as air quality or water quality

The ES documents contain chapters in relation to Hydrology and Hydrogeology; Ecology; Peat and Flora

& Fauna.

Following consultation with relevant expert bodies including DAERA Natural Environment Division

(NED) Loughs Agency and NIEA Water Management Unit, it is considered that the proposal is not

contrary to PPS2. NED initially requested the removal of turbines 2, 5 and 9 as they were within

areas of currently active peat. This amendment was provided within the FEI submitted November

2016, having considered the revised information NED has no objections to the proposed

development site subject to mitigation measures, incorporated into conditions, which have been

set out at section 11 below. A Habitats Regulations Assessment has also been undertaken by

DAERA and they are content that any impact can be adequately mitigated.

Page 36: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

NIEA Water Management Unit and Loughs Agency have also cleared the proposal in relation to

any potential impacts upon the aquatic environment and water quality. The conditions

recommended by these agencies have also been outlined in section 11.

Public access to the countryside

Access to the countryside is not hampered or impeded by the operational nature of this proposal. The

construction and delivery stage of the proposal has the potential to temporarily inconvenience public

road users for the duration of this stage, however through appropriate mitigation measures the haul

route would not represent a significant impediment for access to the countryside.

Haul Route

The ES documents include the proposed haulage routes a well as access arrangements and passing

bays for the application. Subject to final design, it is proposed to follow the haulage route as used for

the delivery of the Owenreagh turbines.

The following outlines the proposed haulage route from the A5:

In the village of Ballymagorry the haul route will take the eastern spur from the A5 onto the

Woodend Road;

The haul will then turn east on the B49 - Berryhill Road. The haul route will continue along the

B49 for a distance of approximately 1.8km before making a southward turn onto the

unclassified Art Road;

At the first intersection on the Art Road, after approximately 600m, the route again turns

eastward onto Sentry Road for a distance of approximately 250m before merging onto the

Moorlough Road;

The route will then follow the Moorlough Road for a distance of approximately 1.4km before

branching south onto the Glenmornan Road; and

The route will follow the single lane Glenmornan Road for an approximate distance of 4.3km

until the first site entrance or 5.5km to the fourth site entrance.

The Council has sought comments from TNI, the competent statutory body regarding roads

infrastructure. Following the submission of additional information in relation to details of passing bays

Page 37: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Transport NI required more information, in order to facilitate the extent of TNI’s request additional

lands are required.

The agent has advised that they intend to submit an additional application for the entire operational

development associated with the haul route. This approach is reasonable as it can be adequately

conditioned.

The particular accesses off Glenmornan Road onto the turbine site are of a standard which is

satisfactory to Transport NI, this is an element of the proposal which is cleared by Transport NI.

Tourism

In consideration of Tourism, TSM 8 of PPS16 states that planning permission will not be granted for

development that would in itself or in combination with existing and approved development in the

locality have an adverse impact on a tourism asset such as to significantly compromise its tourism

value. The application site is located within the AONB which is a tourism asset. Consideration must be

given to whether the proposed wind farm would significantly compromise the overall tourism value of

the asset.

A 2011 visitor attitude survey (NITB, 2011) revealed that the predominant demographic for leisure

visitors to the Tyrone and Sperrins region are families and couples on a day trip. This suggests that

there is unlikely to be any significant impact on tourism activity in this area. This view is supported by

page 15 of the Northern Ireland Onshore Renewable Energy Action Plan (OREAP, (DETI 2013)) which

states that the:

“Increasing deployment of renewables, in particular onshore wind, could, if not appropriately sited,

have the potential impacts on scenic areas that are valued as a recreation and tourist resource. Various

studies have been conducted to assess the possible impact on tourism of wind farm developments and

there has been no evidence of actual negative impacts on tourism.

There are instances where wind farms have themselves become tourist attractions, bringing wider

positive tourism impacts and have improved access to the countryside. More widely, increasing levels

of renewable energy usage with a reduction in carbon emissions could build on Northern Ireland’s

image as a clean and green tourist destination.”

The study (NITB, 2011) also found little evidence of positive effects on tourism occurring in practice,

but maintained that there are opportunities for wind farms to enhance visitor attractions or become

an attraction in their own right through investment in visitor facilities.

The local views of the proposal would have the greatest visual impact, however these views would be

localised within the fringes AONB. The long range views of the application site would be from areas

Page 38: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

beyond the AONB, however there are also a number of other wind farm developments within the area

that can also be seem from within the AONB. Whilst there is the potential for the turbines to be visible

from both within and outside of the AONB it is my considered opinion that this impact would not be

so significant as to compromise the wider strategic nature of the tourism asset. The proposal is

therefore in accordance with PPS16.

PPS 18 Wider Benefits and Weighting

There is no standard formula for assessing the negative environmental impacts against the potential

wider benefits of the renewable energy project in question and thus it is a matter of professional

judgement for the decision maker in each individual case.

In this particular case the Social, economic and environmental benefits of renewable energy are

discussed throughout the submitted environmental information, but most recently in chapter 10 of

the 2016 FEI. In terms of potential environmental benefits, the ES refers to the dependence on fossil

fuels in NI and their negative environmental impacts. Renewable sources of power such as wind create

no operational waste materials. The expected installed capacity of the six turbines at Craignagapple

Wind Farm is approx. 13.8 megawatts (MW). The ES details the offset of CO2 emissions would equate

to 14,462 tonnes p.a. The importation of fossil fuels is seen as a financial burden on the NI economy

and the Srategic Energy Framework seeks to create a greater security of supply. This scheme would

therefore contribute to the SEF targets. Based on nominal 2.3 MW capacity turbines the wind farm

would be capable of 13.8MW total capacity and would produce electrical energy equivalent to the

average requirements of approximately 7,728 homes every year. This would be the equivalent

electricity demand of approximately 19% of the households in the Local Government District of Derry

and Strabane.

The FEI also estimates that there will be 8 direct job years accrued in the Derry City and Strabane

District with a further 38 nationally. The FEI does not indicate if any of these job years will be sustained

outside of the operational phase of the development. Similarly it indicates that some 7% of the overall

capital expenditure for the project will be within the DCSDC area with a further 31% being spent within

Northern Ireland. The overall cost of the project is £17.1 million which then equates to a spend of

£1.2million locally and £5.5 million regionally. These figures and allocations are based on industry

standard reports. Whilst these figures are difficult to rebut, they must be cautiously used, it is down to

my own professional judgement to weight them in the overall decision. A recent appeal decision at

Altgolan Wind Farm (J/2006/0840/F) had a similar power output and economic profile. The

commissioner advised in relation to similar economic reports used to estimate local and regional

economic impacts that:

Page 39: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

‘Whilst the Council argued that these benefits are overstated, I am satisfied they are

substantial and that it is appropriate to attach significant weight to these considerations in

the determination of this appeal’.

With this in mind it is reasonable to attach important weight to the anticipated social, economic and

environmental benefits of the proposal.

The ES considers that the benefits to the community will be of ‘significant beneficial impact’. The main

benefits as presented are considered to be in the form of local landowner payments and rate payments

(a standard rateable income of £17000 per mw, per annum equates to a minimum income £234,600 -

£3.5 Million over the duration of the project) The ES also advises of a community fund, of £5000 per

MW for the 25 year duration of the project. However, the provision of a fund and community benefits

is on a purely voluntary basis with no connection to the planning application process.

The Council is aware that wind farm developments do have the potential to attract significant

economic, social and environmental benefits in the form of rates, land rents, displacement of fossil

fuels, and contribution towards the SEF targets. These would accrue irrespective of the siting of the

wind farm and so are not necessarily particular to this site. However, they represent a significant

contribution to the NI economy if all are realised. In some instances, leakage of the stated benefits can

occur – this may be in the form of companies from outside NI coming into an area to construct the

wind farm. It must be stressed that whilst an applicant may state that it is their intention to use local

labour/companies to build out a site, there is no control over this business aspect once planning

permission has been granted. There is, therefore, no guarantee that local benefits will accrue locally

and a real possibility that financial benefits are overstated and/or open to leakage. The benefits that

are ‘known’ tend to be those such as contribution to targets, reduction in fossil fuel dependence and

reduction in greenhouse gases. Local rates will accrue and of course these will be a significant

contribution to the local Council. Some local jobs are also likely to be either created on a temporary

basis or sustained. Again it is difficult to place figures on these as it is often the case that a specialist

firm will construct the wind farm (thereby sustaining existing jobs rather than creating new ones). They

will also only be for the construction period. Some local businesses may benefit directly from purchase

of products (e.g. construction materials, aggregates, plant hire etc.) and this would be a direct benefit

to the local economy as would any indirect benefits from monies spent locally.

PPS 18 states that its aim is to facilitate the siting of renewable energy generating facilities in

appropriate locations within the built and natural environment in order to achieve NI’s renewable

energy targets and to realise the benefits of renewable energy. It is important to consider, therefore,

Page 40: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

where we are in terms of the 40% target set out by the SEF. Currently NI produces approx. 32% of its

energy requirements from renewable sources (mainly onshore wind), this application has the potential

to contribute 0.5% to this target. This application already avails of a grid connection due to its proximity

to Owenreagh 1 and 2 and as such is in a position to contribute to the targets without being

encumbered by grid issues that have affected the wider region.

In attaching significant weight to these benefits, they must then be weighed against the potential

impacts of the proposal. The main impact of the proposal is the visual impact and resultant impact on

landscape character of the AONB. The assessment outlined above demonstrates that the critical views

of the proposal are reasonably short range and in accordance with para 1.3.25 of the Best Practice

guidance, limited weight should be afforded to short range views. It is at short range views that the

juxtaposition between the existing and proposed wind farm is more evident and this impact is noted

as adverse, I would not however consider it as significantly adverse due to the short range nature of

these views.

11 Summary of Key Issues, Conclusion and Recommendation

Environmental, Economic and Social Benefits

Through consultation with DAERA it has been determined that any potential environmental

impacts can be successfully mitigated.

The project contributes to national targets for the production of renewable energy and

reducing CO2 emissions. The calculations show that a 6 turbine wind farm with a total rated

capacity of 13.8MW would offset 14,462 tonnes of CO2 per year and produce enough

electricity to supply 7,728 homes.

In terms of other economic and social benefits, it has been stated in the 2016 FEI that the

proposed wind farm is likely to generate:

a combined impact during the construction and development phase of £1.3

million and 9 job years in Derry City and Strabane;

a combined impact during the construction and development phase of £5.8

million and 44 job years in Northern Ireland;

a combined impact during the operations and maintenance of £0.3 million

and 3 jobs in Derry City and Strabane;

a combined impact during the operations and maintenance of £0.5 million

and 5 jobs in Northern Ireland;

Page 41: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

potential for local industries to diversify into, or strengthen their existing

experience, in the installation of renewable technologies;

revenue for the land owners, and other parties with interest in the wind farm

development;

rates payments of approximately £3.5 million over 25 years;

contribution to a Community Benefit Fund over the operating life of the wind

farm, which would be distributed to local community based groups, in

addition to operational effects and landowner diversification;

no significant increase or decline in the number of tourism visits to the area;

electricity output of 13.8 MWh per year;

the development complies with existing policy and strategy at an

international, European, national regional and local level; and

the project contributes to a more sustainable and secure energy supply for

the Northern Ireland region;

Public Safety, Human Health, or residential amenity

Through consultation with Environment Health, DAERA and Rivers Agency it has been

determined that potential impacts by way of noise, shadow flicker, drainage and flooding can

be successfully mitigated. It is therefore my considered opinion that the proposal is compliant

with the relevant policies in relation to safety human health and residential amenity.

Visual Amenity and Landscape Character

Notwithstanding the concerns raised by Landscape Architects and the guidance afforded in

the SPG, on balance I consider the development to be acceptable in overall landscape terms,

in that the impacts will be localised and will not have an adverse impact on the integrity of the

Sperrins AONB.

Local natural resources, such as air quality or water quality

Through consultation with DAERA it has been determined that the potential environmental

impacts can be successfully mitigated. It is therefore my considered opinion that the proposal

is compliant with the relevant policies in relation to natural resources.

Public access to the countryside

Through consultation with TransportNI it has been determined that the proposal is

compliant with the relevant policies in relation to access.

Page 42: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

CONCLUSION

In summary I have considered the proposal is acceptable. It will not cause significant harm to public

safety, human health or residential amenity. The visual amenity assessment on the landscape

concludes that whilst the proposed turbines will have a visual impact, it is not considered an

unacceptable either individually or cumulatively. The biodiversity, nature conservation and built

heritage issues have been mitigated against and will not be detrimentally impacted upon by the

proposal. Local natural resources, such as air quality or water quality will not be detrimentally

impacted upon and the public access to the countryside can be provided in accordance with the policy

guidelines.

Whilst I have considered there to be some impacts on the visual amenity and landscape character

area, bio- diversity and conservation interests of the site and the residential amenity of the area, it is

concluded that they do not give rise to an unacceptable adverse impact. These impacts must be

balanced against the wider public interest including the outlined environmental, economic and social

benefits of the proposal which I consider are substantial. Subject to the implementation of the

conditions set out below I am satisfied that the proposal meets the requirements of PPS18, PPS2 and

the relevant policies contained in the SPPS. Accordingly the proposal therefore represents a form of

development that in principle is acceptable in this area of countryside and on this basis this proposed

wind farm is recommended for approval.

12 Proposed Conditions

1. The development hereby permitted shall be begun before the expiration of 5 years from

the date of this permission.

Reason: As required by Section 61 of the Planning Act (Northern Ireland) 2011.

2. No development activity, including ground preparation or vegetation clearance, shall take

place until a final Construction and Environmental Management Plan (CEMP) has been

submitted to and approved in writing by the Planning Authority. The approved CEMP shall

be implemented in accordance with the approved details and all works on site shall

conform to the approved CEMP, unless otherwise approved in writing by the Planning

Authority. The CEMP shall include the following:

Page 43: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

a) Pollution Prevention Plan, including details of the establishment of buffer zones to

watercourses and details of watercourse crossings;

b) Site Drainage Management Plan, including Sustainable Drainage Systems (SuDS), foul

water disposal and silt management measures;

c) Peat Management Plan, including identification of peat/spoil storage areas and details

of the reinstatement of excavated peat/spoil;

d) Mitigation measures for construction in peatland habitats;

e) Water Quality Monitoring Plan;

f) Environmental Emergency Plan;

g) Details of the appointment of an Ecological Clerk of Works (ECoW) and their roles and

responsibilities;

h) Draft Decommissioning Plan detailing the removal of infrastructure, protection of

habitats, pollution prevention measures and the restoration of habitats and natural

hydrological processes on the site.

Reason: To protect Northern Ireland priority habitats and species, to ensure implementation

of mitigation measures identified within the Environmental Statement and to prevent likely

significant effects on designated sites.

3. No development activity, including ground preparation or vegetation clearance, shall take

place until a final Habitat Management and Enhancement Plan (HMEP) has been submitted to

and approved in writing by the Planning Authority. The approved HMEP shall be implemented

in accordance with the approved details and all works on site shall conform to the approved

HMEP, unless otherwise approved in writing by the Planning Authority. The HMEP shall

include the following:

a) Details of pre-construction baseline habitat surveys;

b) Appropriate maps, clearly identifying habitat management areas;

c) Detailed methodology and prescriptions of habitat management measures, including

timescales and with defined criteria for the success of the measures;

d) Details of regular monitoring of habitat management measures and contingency

measures should monitoring reveal unfavourable results;

e) Details of the production of monitoring reports to be submitted to the Planning

Authority at the end of each monitoring year.

Page 44: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

Reason: To compensate for the loss of and damage to Northern Ireland priority habitats and

to mitigate for impacts to breeding birds.

4. No development activity, including ground preparation or vegetation clearance, shall take

place on site between 1 March and 31 August in any year until an Ornithological Mitigation

Strategy (OMS) has been prepared by a suitably experienced and competent ornithologist and

approved in writing by the Planning Authority. The approved OMS shall be implemented in

accordance with the approved details and all works must conform to the approved OMS,

unless otherwise approved in writing by the Planning Authority. The OMS shall include:

a) Details of the appointment of a suitably experienced and competent ornithologist, with

the power to halt works, to supervise works during the bird breeding season;

b) Details of pre-construction bird surveys, including the location of any recorded active

nests or breeding activity;

c) Details of appropriate mitigation measures to be implemented prior to any works

commencing, including the establishment of species specific buffer zones to active nests

or breeding territories (to be agreed with NIEA) and the phasing of works to avoid any

development activity within these breeding bird buffer zones;

d) Details of the timing of ground preparation and vegetation clearance to avoid

disturbance to breeding birds;

e) Details of weekly bird surveys to be conducted during the construction phase;

f) Details of appropriate mitigation measures to be implemented during the construction

phase, including, temporarily halting works and the establishment of species specific

buffer zones to active nests or breeding territories (to be agreed with NIEA);

g) Provisions for the reporting of the implementation of the OMS to the Planning Authority

after construction has commenced and at the end of each bird breeding season during

which works take place.

Reason: To protect breeding birds during the construction phase.

5. No development activity, including ground preparation or vegetation clearance, shall take

place until an Ornithological Monitoring Plan (OMP) has been prepared by a suitably

experienced and competent ornithologist and approved in writing by the Planning Authority.

Page 45: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

The approved OMP shall be implemented in accordance with the approved details and all

works must conform to the approved OMP, unless otherwise approved in writing by the

Planning Authority. The OMP shall include:

a) Details of a programme of long term bird monitoring of breeding and wintering birds,

using appropriate survey methodology, in the year of construction (year 0), and in years

1, 3, 5, 10 and 15;

b) Details of the production of monitoring reports to be submitted to the Planning

Authority within 6 months of the end of each monitoring year, including details of any

additional mitigation measures deemed necessary.

Reason: To monitor the impact of the proposal on sensitive bird species.

6. No turbine shall become operational until a Bat Monitoring Plan (BMP) has been submitted

to and approved in writing by the Planning Authority. The approved BMP shall be

implemented in accordance with the approved details, unless otherwise approved in writing

by the Planning Authority. The BMP shall include the following:

a) Details of the monitoring of bat activity across the site, using appropriate methodology,

between 1 April and 31 October, for a period of three years from when turbines become

operational;

b) Details of bat carcass searches at selected turbines, using appropriate methodology,

for a period of three years from when turbines become operational;

c) Details of the production of yearly monitoring reports, showing the results of bat

activity and carcass monitoring, to be submitted to the planning authority within 3 months

of the end of each monitoring year;

d) Provision for any contingency measures which may be deemed necessary depending

on the results of the monitoring and which shall be implemented if instructed by the

Planning Authority;

e) Provision for extending the monitoring period following review of the three years of

monitoring data and if instructed by the Planning Authority.

Reason: to monitor the impact of the proposal on bats.

Page 46: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

7. No development shall take place until details of the model of the turbine to be installed,

its noise specification, colour and finish, have been submitted to and approved in writing

by Derry City and Strabane District Council.

Reason: To protect residential amenity

8. The developer shall notify Derry City and Strabane District Council in writing of the date

of commencement of works on site and of the date when the turbines have become fully

operational.

Reason: To ensure compliance with appropriate conditions

9. The level of noise emissions at noise sensitive receptors from the combined effects of the

permitted Craignagapple wind turbines (including the application of any Tonal Penalty

when calculated in accordance with the procedures described on pages 104 - 109 of ETSU-

R-97 and any Amplitude Modulation penalty when calculated in accordance with the

procedures described in condition 8) shall not exceed the emissions values for the

approved development set out in the tables entitled ‘ETSU-R-97 Limits, Background Noise

Levels and Emission Levels’ within Appendix 9.7 of the ‘Craignagapple Wind Farm Further

Environmental Information Report’ dated the 14th November 2016.

Noise limits for any dwellings which lawfully exist or have planning permission for

construction at the date of this consent but are not listed in Appendix 9.7 shall be

represented by the physically closest locations listed in Appendix 9.7 unless otherwise

agreed by Derry City and Strabane District Council.

Reason: To protect residential amenity

10. Within 6 months of the development first becoming fully operational (unless otherwise

extended with Derry City and Strabane District Council) the wind farm operator shall at

his/her expense employ a suitably qualified and competent person to undertake a noise

survey to assess the level of noise emissions from the wind farm. The duration of such

monitoring shall be sufficient to provide comprehensive information on noise levels with

all turbines operating across the range of wind speeds referred to in Appendix 9.7 (4-12ms-

1) and covering a range of wind directions. Details of the noise monitoring survey shall be

submitted to Derry City and Strabane District Council for written approval prior to any

Page 47: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

monitoring commencing Derry City and Strabane District Council shall be notified not less

than 2 weeks in advance of the date of commencement of the noise survey.

Reason: To protect residential amenity

11. Within 4 weeks of a written request by Derry City and Strabane District Council, following

a noise complaint from the occupant of a dwelling which lawfully exists or has planning

permission at the date of this consent, the wind farm operator shall, at his/her expense

employ a suitably qualified and competent person, to assess the level of noise emissions

from the combined effects of the permitted wind turbines, at the complainant's property,

following the procedures described in Pages 102-109 of ETSU-R-97 and if necessary, those

described in condition 8. Details of the noise monitoring survey shall be submitted to

Derry City and Strabane District Council for written approval prior to any monitoring

commencing. Derry City and Strabane District Council shall be notified not less than 2

weeks in advance of the date of commencement of the noise monitoring.

Reason: To protect residential amenity

12. The wind farm operator shall provide to Derry City and Strabane District Council the

results, assessment and conclusions regarding the noise monitoring required by

Conditions 4 and 5, including all calculations, audio recordings and the raw data upon

which that assessment and conclusions are based. Such information shall be provided

within 3 months of the date of a written request of Derry City and Strabane District Council

unless otherwise extended in writing by Derry City and Strabane District Council.

Reason: To protect residential amenity

13. Wind speed, wind direction and power generation data shall be continuously logged

throughout the period of operation of the wind farm. This data shall be retained for a

period of not less than 12 months. The recorded wind data, standardised to 10m height

above ground level and relating to any periods during which noise monitoring took place

or any periods when there was a specific noise complaint, shall be provided within 3

months of the date of a written request of Derry City and Strabane District Council unless

otherwise extended in writing by Derry City and Strabane District Council.

Reason: To protect residential amenity

Page 48: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

14. Within 4 weeks from receipt of a written request from Derry City and Strabane District

Council, following an amplitude modulation (AM) complaint to it from the occupant of a

dwelling which lawfully exists or has planning permission at the date of this consent, the

wind farm operator shall submit a scheme for the assessment and regulation of AM to

Derry City and Strabane District Council for its written approval. The scheme shall be in

general accordance with:

a) Any guidance endorsed in National or Northern Ireland Planning Policy or Guidance

at that time, or in the absence of endorsed guidance,

b) Suitable published methodology endorsed as good practice by the Institute of

Acoustics; or in the absence of such published methodology,

c) The methodology published by Renewable UK on the 16th December 2013;

and implemented within 3 months of the written request of Derry City and Strabane

District Council unless otherwise extended in writing by Derry City and Strabane District

Council.

Reason: To protect residential amenity

15. Construction work, which is audible at any noise sensitive property outside the site, shall

only take place between the hours of 07.00 - 19.00 hours on Monday to Friday, 07.00 -

13.00 hours on Saturday with no such working on Sunday. Outwith these hours, work at

the site shall be limited to turbine erection, testing/commissioning works, emergency

works, or construction work that is not audible at any noise sensitive property.

Reason: To protect residential amenity

16. No in-stream river works may be carried out between 1 October and 30 April.

Reason: To avoid the salmonid spawning season and egg incubation phases.

17. Turbine micro siting must adhere to drawing 03 rev A (BHDN d002.1 Site layout, Rev L).

Reason: To ensure that turbine blades do not encroach on bat habitats and to protect

priority habitats.

Page 49: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

18. The developer shall notify the Planning Authority in writing of the date of commencement

of works on site and of the date when the turbines have become fully operational.

Reason: To ensure compliance with appropriate conditions.

19. All storm water from the development site should not be discharged to nearby

watercourses unless first passed through pollution interception and flow attenuation

measures. Storm water can carry pollutants into watercourses and high volume discharges

can alter the prevailing hydrological regime, both of which can impact on fisheries

interests.

Reason: To prevent pollution of surface waters.

20. All power lines within the site outlined in red on Figure 1a shall be located underground.

Reason: To minimise impact upon landscape character.

21. No site works of any nature or development shall take place until a programme of

archaeological work has been implemented, in accordance with a written scheme and

programme prepared by a qualified archaeologist, submitted by the applicant and

approved by the Department. The programme should provide for the identification and

evaluation of the archaeological remains within the site, for mitigation of the impacts of

the development through excavation recording or by preservation of remains and for the

preparation of an archaeological report.

Reason: To ensure that archaeological remains within the application site are properly

identified and protected or appropriately recorded.

22. There shall be no micro-siting of the turbines and ancillary development without prior

approval in writing from the Planning Authority.

Reason: To protect the integrity of priority habitats within the site.

23. This permission shall be for a limited period of 25 years from the date on which electricity

from the wind farm is first connected to the grid. Within 12 months of the cessation of

electricity generation from the site, or upon expiration of this permission, whichever is

sooner, all structures and access tracks shall be removed and all land affected by the

development restored in accordance with a decommissioning scheme submitted to and

approved in writing by the Planning Authority prior to the commencement of any

decommissioning works, or in accordance with any variation to the scheme which the

Planning Authority subsequently agrees in writing. This scheme shall include details of all

Page 50: Appendix 3meetings.derrycityandstrabanedistrict.com/documents... · 2017-11-08 · Appendix 3 The Sperrins LCA is considered in the Supplementary Planning Guidance (SPG) to have an

Appendix 3

works and measures to restore the site, the timeframe within which the works shall be

carried out along with proposals for aftercare for a period of 3 years after the completion

of the restoration works.

Reason: To allow effective restoration of the site.

24. No development on site shall commence until such times as the operational access details

including (but not limited to) haul route, passing bays, site access and traffic management

have been agreed in writing with Derry City and Strabane District Council.

Reason: To ensure the safety and convenience of road users.


Recommended