Roads Branch PublicWorks Department Malaysia Jalan Sultan Salahuddin 50582 Kuala Lumpur Guidelines on the Estimation Procedures for Traffic Management during Construction
Transcript
Page 1: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Roads BranchPublic Works Department Malaysia

Jalan Sultan Salahuddin50582 Kuala Lumpur

5.0m5.0m

7.0m7.0m

Guidelines on theEstimation Procedures for

Traffic Managementduring Construction

Page 2: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 1

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

TABLE OF CONTENTS

1. INTRODUCTION

2. OBJECTIVE

3. PRACTICES IN ESTIMATING BQ FOR TRAFFIC MANAGEMENT

3.1 PREVIOUS PRACTICE

3.2 CURRENT PRACTICE

4. ESTIMATION PROCEDURES

4.1 Case 1: Construction On Both Sides On Existing 2 Lane Single Carriageway To 4 LaneDual Carriageway (Urban Roads)

4.2 Case 2: Construction On Both Sides On Existing 2 Lane Single Carriageway To 4 LaneDual Carriageway (Rural Roads)

5. CONCLUSION

APPENDIX A - STANDARD BQ FOR TRAFFIC MANAGEMENT DURING CONSTRUCTION

APPENDIX B -BQ FOR THE ESTIMATION QUANTITIES FOR TRAFFIC MANAGEMENT DURING CONSTRUCTION

APPENDIX B1 - CASE 1 : EXPANSION FOR URBAN ROAD FROM 2 LANE TO 4 LANEDUAL CARRIAGEWAY

APPENDIX B2 - CASE 2 : EXPANSION FOR RURAL ROAD FROM 2 LANE TO 4 LANE DUAL CARRIAGEWAY

APPENDIX C -DRAWINGS ON TYPICAL APPLICATION OF STANDARD TEMPORARYSIGNS

APPENDIX D -NEW TEMPORARY SIGNBOARDS

JKR 20400-0681-03NOTA TEKNIK (JALAN) 23/03

FOR INTERNAL USE ONLY

Page 3: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 2

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

1.0 INTRODUCTIONTraffic Management during construction hasbeen a great concern lately on all JKR roadprojects that are being constructed. The qualityof the Traffic Management varies from projectto project depending on the amount allocatedfor the Traffic Management, method ofconstruction and the implementation of theTraffic Management.

The inadequate amount allocated for the TrafficManagement are due to the non-standardizedestimation procedures for different category ofroads and the difficulty in estimating TrafficManagement during project costing due to thelack of information on method of construction.

The methods of construction usually are notspecified in the tender documents. This willlater affect the Traffic Management for theprojects when it is constructed on the ground.If the method of construction can be specifiedbefore the construction commences, the TrafficManagement can then be planned properly sothat the construction site is safe and give lessdisruption to the road users. This will also beeasier for the implementation of the TrafficManagement to the site officer.

2.0 OBJECTIVEThe objective of this guideline is to provide astandard Bill of Quantities (BQ) for TrafficManagement during construction. Thisguideline will also give examples on theestimation procedures in estimating thequantities for the items specified in the standardBQ for Traffic Management duringconstruction. This standard BQ and theestimation procedures will be a basis for theengineers coordinating the design process toestimate the costs of the Traffic Managementso that adequate funds can be allocated to giveproper traffic management during construction.

3.0 PRACTICES IN ESTIMATINGBQ FOR TRAFFIC MANAGEMENT

3.1 PREVIOUS PRACTICE

Previously, the Traffic Management cost waspriced as a Lump Sum in Preliminaries item inthe BQ. It was found that the problems facedlater during construction with this procedurewere:

Inadequate funds allocated for Traffic Management

Details for Traffic Management items were not specified in the BQ

Materials to be used were not specified

Since the Traffic Management costs was part ofthe Preliminaries BQ, the costs allocated wasquite limited since it will increase the overallcost of the Preliminaries. The totalPreliminaries cost usually has a maximum percentage to the Builders Works. Therefore,the amount needed for the Traffic Managementsometimes was not priced adequately by thecontractor.

Through this procedure, the details for theTraffic Management items and materials to beused and the quantities were not specified.The supervision officers on site will then haveproblems in implementing and enforcing thetraffic management since they do not haveguidelines to what items, quantities and theright materials to be used.

3.2 CURRENT PRACTICE

Due to the many problems faced and the poorquality provided by the contractors on TrafficManagement through the previous procedure,the Traffic Management items has now beentaken out from the Preliminaries bill as aseparate bill on its own. All the quantities forthe items specified in the bill will beProvisional Quantities except for the provisionof the Traffic Management plan and safety

FOR INTERNAL USE ONLY

Page 4: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 3

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

report that will be priced as Lump Sum.Through this procedure, the detailed items,materials and quantities to be provided onsite are specified in the bill.

In order to ensure that the standard itemsand devices needed for Traffic Managementwill be provided for all the projects, theRoads Branch has prepared a Standard BQfor Traffic Management during constructionto be used for all new projects. Thisstandard BQ consists of basic items usuallyused in Traffic Management. Extra specialitems needed to be used for certain projectscan be added to the Standard BQ. Thestandard BQ is as in Appendix A.

4.0 ESTIMATION PROCEDURES

For the estimation of the quantities fordevices used in Traffic Management duringconstruction, the typical standard applicationdrawings for specific works duringconstruction can be used as a basis.

The existing 'Application of StandardTemporary Signs 1 - 4' numbered asKPKR/J/R/STD/AM 206 - 209' in theStandard Drawings for Road Constructionhas been revised. The revised applicationdrawings will supersede the existingdrawings in the Standard Drawings for RoadConstruction documents and also theapplication drawings incorporated in theexisting Arahan Teknik (Jalan) 2C/85. Apartfrom the existing typical application draw-ings, there is some additional typicalapplication drawings added for other specific works. The revised and new typicalapplication drawings are as shown inAppendix C.

During the revision process for the existingtypical application drawings, there is a needfor new temporary signboards to be added.The new temporary signboards added are asshown in Appendix D. These new signboards will be added to the existingStandard Temporary Signboards numbered

KPKR/J/R/STD/AM 204 in the StandardDrawings for Road Construction.

Examples on the estimation procedures forthe quantities of Traffic Management areshown in 4.1 and 4.2. The estimationsprocedures are calculated for the Urban andRural expansion from 2 lane singlecarriageway to 4 lane dual carriageway.

The BQ for the estimation quantities are inAppendix B1 for Case 1: Construction OnBoth Sides On Existing 2 Lane SingleCarriageway To 4 Lane Dual Carriageway(Urban Roads) and Appendix B2 for Case 2:Construction On Both Sides On Existing 2Lane Single Carriageway To 4 Lane DualCarriageway (Rural Roads).

The estimations are based on the typicalapplication for Works on Shoulder andTypical Application On A 2-Lane HighwayWhere The Entire Roadway Is Closed AndA Bypass Detour Is Provided (temporaryroad diversion). The drawings for both theapplications are as in Appendix C drawingnumber KPKR/J/R/STD/AM 208A andKPKR/J/R/STD/AM 207A, respectively.

4.1 Case 1: Construction On Both SidesOn Existing 2 Lane Single CarriagewayTo 4 Lane Dual Carriageway (UrbanRoads)

4.1.1 Assumptions:-

i. There is no street lighting in the contractarea.

ii. 5 km length of construction areas.

iii. The construction area shall be segregatedfrom the traffic way from commencement of work to completion time to prevent uncontrolled disruption to the traffic movements. Continuous barriers shall be used to segregate the working areas from the traffic way.

iv. The excavation area (work site) shall be

FOR INTERNAL USE ONLY

Page 5: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 4

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

carried out at 200m length at one time at4 locations along the 5 km.

v. There will be 1 traffic diversion at every5km. The length of temporary traffic diversion is assumed to be 30m length.

vi. The traffic diversion costs exclude theearthworks and pavement costs. It com prises cost for traffic signs, devicesfor traffic management and road markings.

vii. For estimation purposes, the signboardquantities are based on per work siteapplications. For example, if the total work site is 4 locations, the quantities installed for one work site is multipliedby 4.

viii.The quantities do not take intoconsideration the percentage of lossesand damages.

4.1.2 Estimation on BQ Items

i. Item 1. 1. 1 : Movable ReinforcedConcrete Barrier (NJB) or equivalent

To be used where excavation on the roadside is 1m deep or more.

Since each work site is 200m length, there-fore the number of concrete barriers neededfor each work site is 200 nos.

For 4 locations =200*4 = 800 nos. This set(800 nos.) can be use repeatedly throughoutthe construction area.

Total = 800 nos.

ii. Item1.1.2 : Light Weight MovableBarrier (Plastic Barrier)

To be used where excavation on road side isless than 1m deep.

To replace movable barricade at transitionarea, buffer area and termination area.

To be placed along the road side continuous-ly and at the centre of the two way traffic.

Therefore the numbers of barriers needed :-

a. Along the construction area.

Length of construction area less the lengthof 4 work site @ 200m at each work siteand less the length for the temporary roaddiversion @30m (30 x 2 - for both side ofthe road ).

= (5000 x 2 ) - (200 x 4 ) - 60 = 9140 nos.

Along the median less 30m for the tempo-rary road diversion= 5000 - 30 = 4970 nos.

b. For temporary traffic diversion 10nos. of barrier is assumed (as shown in thetypical application drawing for temporarydiversion in Appendix C).

Total = 14120 nos.

iii. Item1.1.4. : Warning Lamp / Blinkers.

To be placed on the barriers at 30m intervalalong the construction area (excluding thework site area and temporary roaddiversion).

To be placed at 10m interval along theexcavation work site and at signboards asshown in the typical application drawing inAppendix C.

The number of warning light needed:-

a. At the construction area = (15000 - (200 x 4 ) - 90)/ 30 = 470.3 = 471 nos.

b. Along the work site area = (20 nos. x 4 site) + (11 (at signboards )

x 4 )= 124 nos

FOR INTERNAL USE ONLY

Page 6: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 5

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

c. Along the temporary traffic diversion construction site = 28 nos

Total = 623 nos.

iv. Item1.1.5. : Beacon Light.

To be placed at the start and end of aspecific work site.

The number of beacon light needed.:-

a. At the specific work site = 2 nos. * 4 site = 8 nos

b. Along the temporary traffic diversionconstruction site = 2 nos

Total = 10 nos.

v. Item 1.1.7. : Barrier Delineators

To be pasted on each barrier on one side.For median barrier, pasted on both side.Alternative to the string delineators.

Numbers needed :-

a. Based on Item 1. 1. 1

No. of delineators =800 nos

b. Based on Item 1. 1. 2

No. of delineators for barriers along theconstruction area= 9140 nos

No. of delineators for median barriers= 4970 * 2 = 9940 nos

c. No. of barriers along temporary trafficdiversion = 10 nos.

Total number of barrier delineators= 19890 nos.

vi. Item1.1.8. : Flashing Arrow.

To be placed at traffic diversion inconstruction area.

The number of flashing arrows needed.:-

a. At the work sites = 2 nos. x 4 sites = 8 nos.

b. Along the temporary road diversionsite = 2 nos

c. Total = 10 nos.

vii. Item 1. 1. 10. : Guardrails

Used at temporary road diversionapproximately 50 m

Total = 50 m

viii. Item1.1. 11. : Temporary Lighting.

To be placed at the start and end of aspecific work site.

The number of temporary lighting needed.:-

a. At the specific work site = 2 nos. * 4 site = 8 nos

b. Along the temporary road diversion site= 2 nos

Total = 10 nos.

xi. Item1.2. : Temporary Signs

a. Not exceeding 1 sq. m

At the work site = 7 * 4 sites = 28 nosAlong the temp. road diversion work area= 22 nos.

Total = 50 nos

b. Exceeding 1 sq. m but not exceeding 2 sq. m

FOR INTERNAL USE ONLY

Page 7: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 6

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

At the work excavation site = 4 * 4 sites = 16 nos

Along the temp. road diversion work area = 4 nos.

Along the construction area = 4 nos.

Total = 24 nos

xii. Item 1.5. : Road Markings

For temporaray road diversions - 30 m

a. Edge lines = 30 * 2 = 60 m

Total = 60 m

b. Centre lines = 30 m

Total = 30 m

4.2 Case 2: Construction On Both SidesOn Existing 2 Lane Single CarriagewayTo 4 Lane Dual Carriageway (RuralRoads)

4.2.1 Assumptions:-

i. There is no street lighting in the contractarea.

ii. 5 km length of construction areas.

iii. The excavation work area shall be carried out at 200m length at one time at4 locations along the 5 km (assuming 2locations on each side of the road).

iv. Paving works shall be done after the roadbase works has been completed for thewhole 5 km. Therefore, the NJB plasticbarriers shall be installed along the 5 kmat spacing of 4 m apart.

v. There will be 1 traffic diversion at every5 km. The length of temporary traffic

diversion is assumed to be 30m length.

vi. The traffic diversion costs exclude the

the earthworks and pavement costs. Itcomprises cost for traffic signs, devicesfor traffic management and road markings.

vii. For estimation purposes, the signboardquantities are based on per work siteapplications. For example, if the totalwork site is 4 locations, the quantitiesinstalled for one work site is multipliedby 4.

viii.The quantities do not take into considerations the percentage of lossesand damages.

4.2.1 Estimation on BQ items

i. Item 1.1.1 : Movable Reinforced concrete Barriers (NJB) or equivalent

To be used where excavation on the roadside is 1m deep or more.

Since each work site is 200m length, there-fore the number of concrete barriers neededfor each work site is 200 nos.

For 4 locations =200*4 = 800 nos. This set(800 nos.) can be use repeatedly throughoutthe construction area.

Total = 800 nos.

ii. Item 1.1.2 Light Weight Movable Barriers (Plastic Barrier)

To be used where excavation on road side isless than 1m deep.To replace movable barricade at transitionarea, buffer area and termination area.To be placed along the road side at intervaluntil the constructed area are paved.

Therefore the numbers of barriers needed :-

a. Along the construction area.

Say the plastic barrier is placed at 4m interval.

FOR INTERNAL USE ONLY

Page 8: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 7

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

Length of construction area = 5000 x 2 = 10000Length of work site = 200 x 4 = 800 Length of temp. road diversion= 30 x 2 sides= 60

No. of barriers needed = (10000 - 800 - 60)/4 = 2285 nos.

b. For temporary traffic diversion 10nos of barrier is assumed.

Total = 2295 nos.

iii. Item 1.1.4. : Warning Lamps/ Blinkers

To be placed on the barriers at 30m intervalalong the construction area (excluding thework site area and temporary road diversion).

To be placed at 10m interval along the excavation work site and at signboards asshown in the typical application drawing inAppendix C.

The number of warning light needed.:-

a. At the construction area = (10000 - 800 - 60)/30 = 304.7 = 305 nos.

b. Along the work site area = (20 nos. x 4 site) + (11 (at signboards )

x 4 )= 124 nos

c. Along the temporary traffic diversionconstruction site = 28 nos

Total = 457 nos.

iv. Item1.1.5. : Beacon Light.

To be placed at the starting and end of a spe-cific work site.

The number of beacon light needed.:-

a. At the specific work site = 2 nos. * 4 site = 8 nos

b. Along the temporary traffic diversion construction site = 2 nos

Total = 10 nos.

v. Item 1.1.7 : Barrier Delineators

To be pasted on each barrier on one side.Alternative to the string delineators.

Numbers needed :-

a. Based on Item 1. 1. 1

No. of delineators =800 nos.

b. Based on Item 1. 1. 2

No. of delineators for barriers along the construction area = 2285 nos.

c. No. of barriers along temporary traffic diversion = 10 nos.

Total number of barrier delineators = 3095 nos.

vi.Item1.1.8. : Flashing Arrow.

To be placed at traffic diversion in con-struction area.

The number of flashing arrows needed.:-

a. At the work sites = 2 nos. x 4 sites = 8 nos.

b. Along the temporary road diversion site = 2 nos

c. Total = 10 nos.

vii. Item 1. 1. 10. : Guardrails

Used at temporary road diversionapproximately 50 m

Total = 50 m

FOR INTERNAL USE ONLY

Page 9: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 8

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

viii. Item1.1. 11. : Temporary Lighting.

To be placed at the start and end of aspecific work site.

The number of temporary lighting needed.:-

a. At the specific work site = 2 nos. * 4 site = 8 nos

b. Along the temporary road diversion site= 2 nos

Total = 10 nos.

xi. Item1.2. : Temporary Signs

a. Not exceeding 1 sq. m

At the work site = 7 * 4 sites = 28 nosAlong the temp. road diversion work area= 22 nos.

Total = 50 nos

b. Exceeding 1 sq. m but not exceeding 2 sq. m

At the work excavation site = 4 * 4 sites = 16 nosAlong the temp. road diversion work area = 4 nos.Along the construction area= 4 nos.

Total = 24 nos

xii. Item 1.5. : Road Markings

For temporaray road diversions - 30 m

a. Edge lines = 30 * 2 = 60 m

Total = 60 m

b. Centre lines = 30 m

Total = 30 m

5.0 CONCLUSION

Due to the inconsistencies in the quality ofTraffic Management for road constructionprojects, there is a need for a standarddetailed itemized BQ and estimationprocedures. This standard BQ andestimation procedures will be used as aguide for the engineers involved in thedesign procedures to estimate the TrafficManagement costs for a project. It is also aguide for the supervision officer on site toensure that a proper Traffic Managementwith enough items and devices be installedon site during construction.

FOR INTERNAL USE ONLY

Page 10: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 9

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

APPENDIX A

STANDARD BQ FORTRAFFIC

MANAGEMENTDURING

CONSTRUCTION

FOR INTERNAL USE ONLY

Page 11: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 10

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.0

1.11.1.1

1.1.2

1.1.3

TRAFFIC MANAGEMENT TEAMProvide for the appointment of a full time traffic diversion and safety officer as specified.

Traffic management team 1. Traffic Safety Officer (……..Persons)2. Supervision/foreman (……..Persons)3. Traffic Controller (……persons)

TEMPORARY ROAD FURNITURESPrecast Movable Reinforced ConcreteBarriers or equivalentSupply precast reinforced concrete movable,"New Jersey Barriers" as shown on theDrawings and /or as directed by the S.O. andas specified installation at the first position asshown on the drawings and storage, mainte-nance and replacement during constructionperiod including moving from point to point,and removal at the completion of the road-works.

Light Weight Movable BarriersSupply light weight movable "New JerseyBarriers" as shown on the Drawings and/or asdirected by the S.O. including installing in thefirst position as shown on the drawing andstorage, maintenance and replacement duringConstruction Period including moving frompoint to point removal on completion of theroadworks.

Light Weight Movable Traffic GuidanceConesSupply movable cones as shown on theDrawings and/or as directed by the S.O. and asspecified including installing in the first posi-tion as shown on the drawings and storage,maintenance and replacement during the con-struction period and removal on completion ofroad works.

Man-Months

Nos

Nos

Nos

To Collection

STANDARD BQ FOR TRAFFIC MANAGEMENT DURING CONSTRUCTIONBIL NO.1-TRAFFIC MANAGEMENT

Page 12: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 11

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.1.4

1.1.5

1.1.6

1.1.7

1.1.8

BlinkersSupply warning lamp/blinker with batteries asshown in the drawing and/or as directed by theS.O. and as specified including installing in thefirst position as shown on the drawings andstorage, maintenance and replacement duringconstruction period including removal fromsite at the end of each stage and at thecompletion of the road works.

Beacon LightSupply beacon light with batteries as shown inthe drawing and/or as directed by the S.O. andas specified including installing in the firstposition as shown on the drawings and storage,maintenance and replacement duringconstruction period including removal fromsite at the end of each stage and at thecompletion of the road works.

String DelineatorsSupply double sided reflective string delin-eators as shown on the drawings and or /asdirected by the S.O. and as specified includinginstalling in the first position as shown on thedrawings and storage, maintenance andreplacement during the construction periodincluding removal from site at the end of eachstage and at the completion of the road works.

Barrier DelineatorsSupply barrier delineators to be attached ateach barrier as shown in the drawing and/or asdirected by the S.O. and as specified includinginstalling, maintenance and replacement duringconstruction period.

Flashing ArrowSupply flashing arrow as shown on thedrawing and so/as directed by the S.O. and asspecified including installing in the firstposition as shown on the drawing and storage,maintenance and replacement during theconstruction period including removal fromsite at the end of each stage and at thecompletion of the road works.

Nos

Nos

Lin.m

Nos

Nos

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 13: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 12

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.1.9

1.1.10

1.1.11

1.2

Sand BagSupply sand bag as directed by the S.O. and asspecified including installing in the firstposition and storage, maintenance andreplacement during the construction periodincluding removal from site at the end of eachstage and at the completion of the road works.

Temporary GuardrailsSupply temporary guardrails with reflectors asshown on the drawings and/or as directed bythe S.O. and as specified including installingin the first position as shown on the drawingsand storage, maintenance and replacement dur-ing the construction period including removalfrom site at the end of each stage and at thecompletion of the road works.

Temporary LightingSupply temporary flood light as shown on thedrawings and or /as directed by the S.O. and asspecified including installing in the first posi-tion as shown on the drawings and storage,maintenance and replacement during the con-struction period including removal from site atthe end of each stage and at the completion ofthe road works.

TEMPORARY SIGNSSupply and install in position all temporarytraffic signs of fluorescent orange prismaticretro-reflective sheeting including all postsbrackets, painting and everything complete asshown on the Drawing and/or as directed bythe S.O. including removal from site at the endof each stage and at the completion of the roadworks..i. Not exceeding 1 sq. mii. Exceeding 1 sq. m but not exceeding 2 sq.miii Exceeding 2 sq. m but not exceeding 3 sq.miv.Exceeding 3 sq. m but not exceeding 4 sq.mv. Exceeding 4 sq. m

Cu.m

Lin.m

Nos

NosNosNosNosNos

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 14: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 13

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.31.3.1

1.3.1.1

1.3.1.2

1.3.1.3

1.3.1.4

1.3.21.3.2.1

1.3.2.2

1.3.2.3

1.3.2.4

1.3.3

TEMPORARY ROAD DIVERSIONEarthworkSupply all labour, plants, materials, transportsetc for the proposed work in accordance withthe Specifications and Drawings

Excavate unsuitabe material at temporary roaddiversion

Provide, place spread, level and compact inlayers suitable fill materials at temporary roaddiversion from contractor's own source

Excavate earth drain at temporary road

Provide close turfing on slopes

PavementPreparation of formation as specified and asdirected by the S.O for receiving temporaryroad pavement

Supply, spread and compact crushed aggregatebase course to a minimum compacted thickness of ….. mm

Prime coat to crusher run road base using cut-back bituminous material (MC 70 OR SS-1)spraying rate shall be 0.5 to 1.0 liter per sq.m.

Supply, lay and compact asphaltic concretebinder course to a minimum compacted thick-ness of 60 mm

Road MarkingsInstall temporary road marking as shown onthe drawings and or/as directed by the S.O.and as specified during the constructionperiod.i. Edges linesii. Centre linesiii. Blackening existing road marking

Cu.m

Cu.m

Cu.m

Cu.m

sq.m

sq.m

sq.m

sq.m

Lin.mLin.mLin.m

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 15: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 14

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.4

1.4.1

1.4.2

1.5

REPORT & TRAFFIC MANAGEMENTPLANAllow for the preparation submission of trafficmanagement plan and method of statement forapproval when and where as requested by theS.O.

Submission of 6 sets Traffic ManagementSafety Report once in every 3 months

Removal of temporary road diversion andstructures upon completion of project

L.S

L.S

L.S

To Collection

Page 16: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 15

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

APPENDIX B

STANDARD ESTIMATION

QUANTITIES FOR TRAFFIC MANAGEMENT

DURING CONSTRUCTION

FOR INTERNAL USE ONLY

Page 17: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 16

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

APPENDIX B1

CASE 1: EXPANSION FORURBAN ROAD FROM 2

LANE TO 4 LANE DUALCARRIAGEWAY

FOR INTERNAL USE ONLY

Page 18: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 17

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.0

1.11.1.1

1.1.2

1.1.3

TRAFFIC MANAGEMENT TEAMProvide for the appointment of a full time traffic diversion and safety officer as specified.

Traffic management team 1. Traffic Safety Officer (……..Persons)2. Supervision/foreman (……..Persons)3. Traffic Controller (……persons)

TEMPORARY ROAD FURNITURESPrecast Movable Reinforced ConcreteBarriers or equivalentSupply precast reinforced concrete movable,"New Jersey Barriers" as shown on theDrawings and /or as directed by the S.O. andas specified installation at the first position asshown on the drawings and storage, mainte-nance and replacement during constructionperiod including moving from point to point,and removal at the completion of the road-works.

Light Weight Movable BarriersSupply light weight movable "New JerseyBarriers" as shown on the Drawings and/or asdirected by the S.O. including installing in thefirst position as shown on the drawing andstorage, maintenance and replacement duringConstruction Period including moving frompoint to point removal on completion of theroadworks.

Light Weight Movable Traffic GuidanceConesSupply movable cones as shown on theDrawings and/or as directed by the S.O. and asspecified including installing in the first posi-tion as shown on the drawings and storage,maintenance and replacement during the con-struction period and removal on completion ofroad works.

Man-Months

Nos

Nos

Nos

800

14120

To Collection

CASE 1: EXPANSION FOR URBAN ROAD 2 LANE TO 4 LANE DUALCARRIAGEWAY-BASED ON 5 KM LENGTHBIL NO.1-TRAFFIC MANAGEMENT

Page 19: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 18

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.1.4

1.1.5

1.1.6

1.1.7

1.1.8

BlinkersSupply warning lamp/blinker with batteries asshown in the drawing and/or as directed by theS.O. and as specified including installing inthe first position as shown on the drawingsand storage, maintenance and replacementduring construction period including removalfrom site at the end of each stage and at thecompletion of the road works.

Beacon LightSupply beacon light with batteries as shown inthe drawing and/or as directed by the S.O. andas specified including installing in the firstposition as shown on the drawings andstorage, maintenance and replacement duringconstruction period including removal fromsite at the end of each stage and at thecompletion of the road works.

String DelineatorsSupply double sided reflective stringdelineators as shown on the drawings and or/as directed by the S.O. and as specifiedincluding installing in the first position asshown on the drawings and storage,maintenance and replacement during theconstruction period including removal fromsite at the end of each stage and at thecompletion of the road works.

Barrier DelineatorsSupply barrier delineators to be attached ateach barrier as shown in the drawing and/or asdirected by the S.O. and as specified includinginstalling, maintenance and replacementduring construction period.

Flashing ArrowSupply flashing arrow as shown on thedrawing and so/as directed by the S.O. and asspecified including installing in the firstposition as shown on the drawing and storage,maintenance and replacement during theconstruction period including removal fromsite at the end of each stage and at thecompletion of the road works.

Nos

Nos

Lin.m

Nos

Nos

623

10

19890

10

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 20: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 19

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.1.9

1.1.10

1.1.11

1.2

Sand BagSupply sand bag as directed by the S.O. and asspecified including installing in the firstposition and storage, maintenance andreplacement during the construction periodincluding removal from site at the end of eachstage and at the completion of the road works.

Temporary GuardrailsSupply temporary guardrails with reflectors asshown on the drawings and/or as directed bythe S.O. and as specified including installingin the first position as shown on the drawingsand storage, maintenance and replacement dur-ing the construction period including removalfrom site at the end of each stage and at thecompletion of the road works.

Temporary LightingSupply temporary flood light as shown on thedrawings and or /as directed by the S.O. and asspecified including installing in the first posi-tion as shown on the drawings and storage,maintenance and replacement during the con-struction period including removal from site atthe end of each stage and at the completion ofthe road works.

TEMPORARY SIGNSSupply and install in position all temporarytraffic signs of fluorescent orange prismaticretro-reflective sheeting including all postsbrackets, painting and everything complete asshown on the Drawing and/or as directed bythe S.O. including removal from site at the endof each stage and at the completion of the roadworks..i. Not exceeding 1 sq. mii. Exceeding 1 sq. m but not exceeding 2 sq.miii Exceeding 2 sq. m but not exceeding 3 sq.miv.Exceeding 3 sq. m but not exceeding 4 sq.mv. Exceeding 4 sq. m

Cu.m

Lin.m

Nos

NosNosNosNosNos

50

10

5024

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 21: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 20

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.31.3.1

1.3.1.1

1.3.1.2

1.3.1.3

1.3.1.4

1.3.21.3.2.1

1.3.2.2

1.3.2.3

1.3.2.4

1.3.3

TEMPORARY ROAD DIVERSIONEarthworkSupply all labour, plants, materials, transportsetc for the proposed work in accordance withthe Specifications and Drawings

Excavate unsuitabe material at temporary roaddiversion

Provide, place spread, level and compact inlayers suitable fill materials at temporary roaddiversion from contractor's own source

Excavate earth drain at temporary road

Provide close turfing on slopes

PavementPreparation of formation as specified and asdirected by the S.O for receiving temporaryroad pavement

Supply, spread and compact crushed aggregatebase course to a minimum compacted thickness of ….. mm

Prime coat to crusher run road base using cut-back bituminous material (MC 70 OR SS-1)spraying rate shall be 0.5 to 1.0 liter per sq.m.

Supply, lay and compact asphaltic concretebinder course to a minimum compacted thick-ness of 60 mm

Road MarkingsInstall temporary road marking as shown onthe drawings and or/as directed by the S.O.and as specified during the constructionperiod.i. Edges linesii. Centre linesiii. Blackening existing road marking

Cu.m

Cu.m

Cu.m

Cu.m

sq.m

sq.m

sq.m

sq.m

Lin.mLin.mLin.m

6030

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 22: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 21

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.4

1.4.1

1.4.2

1.5

REPORT & TRAFFIC MANAGEMENTPLANAllow for the preparation submission of trafficmanagement plan and method of statement forapproval when and where as requested by theS.O.

Submission of 6 sets Traffic ManagementSafety Report once in every 3 months

Removal of temporary road diversion andstructures upon completion of project

L.S

L.S

L.S

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 23: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 22

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

APPENDIX B2

CASE 2: EXPANSION FORRURAL ROAD FROM 2

LANE TO 4 LANE DUALCARRIAGEWAY

FOR INTERNAL USE ONLY

Page 24: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 23

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.0

1.11.1.1

1.1.2

1.1.3

TRAFFIC MANAGEMENT TEAMProvide for the appointment of a full time traffic diversion and safety officer as specified.

Traffic management team 1. Traffic Safety Officer (……..Persons)2. Supervision/foreman (……..Persons)3. Traffic Controller (……persons)

TEMPORARY ROAD FURNITURESPrecast Movable Reinforced ConcreteBarriers or equivalentSupply precast reinforced concrete movable,"New Jersey Barriers" as shown on theDrawings and /or as directed by the S.O. andas specified installation at the first position asshown on the drawings and storage, mainte-nance and replacement during constructionperiod including moving from point to point,and removal at the completion of the road-works.

Light Weight Movable BarriersSupply light weight movable "New JerseyBarriers" as shown on the Drawings and/or asdirected by the S.O. including installing in thefirst position as shown on the drawing andstorage, maintenance and replacement duringConstruction Period including moving frompoint to point removal on completion of theroadworks.

Light Weight Movable Traffic GuidanceConesSupply movable cones as shown on theDrawings and/or as directed by the S.O. and asspecified including installing in the first posi-tion as shown on the drawings and storage,maintenance and replacement during the con-struction period and removal on completion ofroad works.

Man-Months

Nos

Nos

Nos

800

2295

To Collection

CASE 2: EXPANSION FOR RURAL ROAD 2 LANE TO 4 LANE DUALCARRIAGEWAY-BASED ON 5 KM LENGTHBIL NO.1-TRAFFIC MANAGEMENT

Page 25: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 24

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.1.4

1.1.5

1.1.6

1.1.7

1.1.8

BlinkersSupply warning lamp/blinker with batteries asshown in the drawing and/or as directed by theS.O. and as specified including installing inthe first position as shown on the drawingsand storage, maintenance and replacementduring construction period including removalfrom site at the end of each stage and at thecompletion of the road works.

Beacon LightSupply beacon light with batteries as shown inthe drawing and/or as directed by the S.O. andas specified including installing in the firstposition as shown on the drawings andstorage, maintenance and replacement duringconstruction period including removal fromsite at the end of each stage and at thecompletion of the road works.

String DelineatorsSupply double sided reflective stringdelineators as shown on the drawings andor/as directed by the S.O. and as specifiedincluding installing in the first position asshown on the drawings and storage,maintenance and replacement during theconstruction period including removal fromsite at the end of each stage and at thecompletion of the road works.

Barrier DelineatorsSupply barrier delineators to be attached ateach barrier as shown in the drawing and/or asdirected by the S.O. and as specified includinginstalling, maintenance and replacementduring construction period.

Flashing ArrowSupply flashing arrow as shown on thedrawing and so/as directed by the S.O. and asspecified including installing in the firstposition as shown on the drawing and storage,maintenance and replacement during theconstruction period including removal fromsite at the end of each stage and at thecompletion of the road works.

Nos

Nos

Lin.m

Nos

Nos

457

10

3095

10

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 26: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 25

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.1.9

1.1.10

1.1.11

1.2

Sand BagSupply sand bag as directed by the S.O. and asspecified including installing in the firstposition and storage, maintenance andreplacement during the construction periodincluding removal from site at the end of eachstage and at the completion of the road works.

Temporary GuardrailsSupply temporary guardrails with reflectors asshown on the drawings and/or as directed bythe S.O. and as specified including installingin the first position as shown on the drawingsand storage, maintenance and replacement dur-ing the construction period including removalfrom site at the end of each stage and at thecompletion of the road works.

Temporary LightingSupply temporary flood light as shown on thedrawings and or /as directed by the S.O. and asspecified including installing in the first posi-tion as shown on the drawings and storage,maintenance and replacement during the con-struction period including removal from site atthe end of each stage and at the completion ofthe road works.

TEMPORARY SIGNSSupply and install in position all temporarytraffic signs of fluorescent orange prismaticretro-reflective sheeting including all postsbrackets, painting and everything complete asshown on the Drawing and/or as directed bythe S.O. including removal from site at the endof each stage and at the completion of the roadworks..i. Not exceeding 1 sq. mii. Exceeding 1 sq. m but not exceeding 2 sq.miii Exceeding 2 sq. m but not exceeding 3 sq.miv.Exceeding 3 sq. m but not exceeding 4 sq.mv. Exceeding 4 sq. m

Cu.m

Lin.m

Nos

NosNosNosNosNos

50

10

5024

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 27: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 26

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.31.3.1

1.3.1.1

1.3.1.2

1.3.1.3

1.3.1.4

1.3.21.3.2.1

1.3.2.2

1.3.2.3

1.3.2.4

1.3.3

TEMPORARY ROAD DIVERSIONEarthworkSupply all labour, plants, materials, transportsetc for the proposed work in accordance withthe Specifications and Drawings

Excavate unsuitabe material at temporary roaddiversion

Provide, place spread, level and compact inlayers suitable fill materials at temporary roaddiversion from contractor's own source

Excavate earth drain at temporary road

Provide close turfing on slopes

PavementPreparation of formation as specified and asdirected by the S.O for receiving temporaryroad pavement

Supply, spread and compact crushed aggregatebase course to a minimum compacted thickness of ….. mm

Prime coat to crusher run road base using cut-back bituminous material (MC 70 OR SS-1)spraying rate shall be 0.5 to 1.0 liter per sq.m.

Supply, lay and compact asphaltic concretebinder course to a minimum compacted thick-ness of 60 mm

Road MarkingsInstall temporary road marking as shown onthe drawings and or/as directed by the S.O.and as specified during the constructionperiod.i. Edges linesii. Centre linesiii. Blackening existing road marking

Cu.m

Cu.m

Cu.m

Cu.m

sq.m

sq.m

sq.m

sq.m

Lin.mLin.mLin.m

6030

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 28: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 27

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

ItemNo

Description of work Quantity Unit Rate Amount

1.4

1.4.1

1.4.2

1.5

REPORT & TRAFFIC MANAGEMENTPLANAllow for the preparation submission of trafficmanagement plan and method of statement forapproval when and where as requested by theS.O.

Submission of 6 sets Traffic ManagementSafety Report once in every 3 months

Removal of temporary road diversion andstructures upon completion of project

L.S

L.S

L.S

To Collection

BIL NO.1-TRAFFIC MANAGEMENT

Page 29: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 28

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

APPENDIX C

DRAWING ON TYPICALAPPLICATION OF

STANDARD TEMPORARYSIGN

FOR INTERNAL USE ONLY

Page 30: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 29

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 31: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 30

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 32: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 31

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 33: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 32

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 34: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 33

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 35: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 34

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 36: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 35

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 37: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 36

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 38: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 37

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 39: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 38

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 40: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 39

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 41: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 40

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 42: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 41

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 43: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 42

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 44: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 43

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 45: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 44

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 46: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 45

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 47: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 46

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 48: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 47

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 49: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 48

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 50: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 49

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 51: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 50

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY

Page 52: Arahan Teknik (Jalan) 23-03 - Guidelines on the Estimation Procedures for Traffic Management During Construction

Page 51

Guidelines On The Estimation Procedures For Traffic Management During Construction

Cawangan Jalan, Ibu Pejabat JKR, K.L

FOR INTERNAL USE ONLY