Date post: | 03-Jun-2018 |
Category: |
Documents |
Upload: | waldemar-ziomek |
View: | 218 times |
Download: | 0 times |
of 22
8/12/2019 Areva 2006 - International Developments in HVDC
1/22
PNWER Edmonton July 20061 1
International Developments in HVDC
Neil KirbyBusiness Development Manager
HVDC and FACTS, N AmericaAREVA T&D Inc
16th Annual PNWER ConferenceEdmonton, AB
Tuesday July 18th 2006
8/12/2019 Areva 2006 - International Developments in HVDC
2/22
PNWER Edmonton July 20062 2
International HVDC Projects
Introduction to HVDC across the worldCase Studies
KontiSkan 1
Gulf States Interconnection
Southern Africa Regional Interconnections
8/12/2019 Areva 2006 - International Developments in HVDC
3/22
PNWER Edmonton July 20063 3
The World of HVDC
Classic HVDC . Its been around for 50 years
OTHER HVDC CCC = 2400 MW RCC = 0 MW VSC = 943 MW
USA T = 7720 MW
C = 0 MW B = 1900 MW
Canada T = 6000 MW C = 312 MW B = 1820 MW
Europe T = 0 MW C = 8155 MW B = 1750 MW
India T = 5600 MW C = 0 MW B = 3000 MW
China T = 16250 MW C = 0 MW B = 0 MW
Asia T = 2100 MW C = 2150 MW B = 1800 MW
Australasia T = 0 MW C = 2160 MW B = 0 MW
Africa T = 2480 MW C = 0 MW B = 0 MW
S America
T = 6300 MW C = 0 MW B = 175 MW
TOTAL T = 46,450 MW C = 12,797 MW B = 10,620 MW Sum = 69,867 MW
8/12/2019 Areva 2006 - International Developments in HVDC
4/22
PNWER Edmonton July 20064 4
Back-to-BackHVDC Links
Point-to-PointHVDC Links
(Cable / OHL)
ERCOT
Central/EasternSeaboard System
West CoastSystem
Quebec
Existing HVDC in North America
8/12/2019 Areva 2006 - International Developments in HVDC
5/22
PNWER Edmonton July 20065 5
Northern EuropeKontiSkan HVDC Project
8/12/2019 Areva 2006 - International Developments in HVDC
6/22
PNWER Edmonton July 20066 6
KontiSkan HVDC
Svenska Kraftnt - owns and operatesSwedens transmission network
Energinet - owns and operates the 400kVtransmission network for Jutland and Funen
in Denmark
www.svk.se
www.energinet.dk
8/12/2019 Areva 2006 - International Developments in HVDC
7/22
8/12/2019 Areva 2006 - International Developments in HVDC
8/22
PNWER Edmonton July 20068 8
KontiSkan 1 Upgrade / Refurbishment
Multiple Cable / OHL Sections
Scope
Sweden - Turnkey addition toexisting s/s
Denmark - Excludingbuildings and AC switchyard
SwedenStenkullenSubstation,
Gothenburg
DenmarkVester Hassing
Substation
SwedenLindomeSubstation
Route Length = 150 km
Cable23 km
OHL34 km
310 mm2310 mm2
310 mm2
DenmarkMainland
LaesoeIsland
OHL9 km
Cable64 km
1200 mm2
SwedenMainland
OHL17 km
Cable23 km
500 mm2310 mm2
500 mm2Cable64 km
1200 mm2
ElectrodeLine
CommonTowers
CommonTowers
CommonTowers
Pole 2285 kV
@ 1050 A300 MW
ElectrodeLine
Pole 1285 kV
@ 1000 A250 MW
MercuryArc
Valves
MercuryArc Valves
130kV50Hz
400kV50Hz
150 kV50 Hz
400 kV50 Hz
130kV50Hz
Pole 1285 kV
@1000 A250 MW
OHL31 km
RouteLength=
180km
OHL34 km
OHL9 km
OHL17 km
Pole 2285 kV
@ 1050 A300 MW
Lindome Station, Sweden
Thyristor Valves
8/12/2019 Areva 2006 - International Developments in HVDC
9/22
PNWER Edmonton July 20069 9
Middle EastGulf States Interconnection Project
Combining HVDC and AC
8/12/2019 Areva 2006 - International Developments in HVDC
10/22
PNWER Edmonton July 200610 10
Gulf States Interconnection
Main driver for the projectwas demand growthexpectations in the region:
2003: 32GW
2010: 49GW
2028: 94GW
Studies showed that interconnectionwould have many benefits:
Reduced capacity needed in each systemsince it would allow the sharing of energysupply
Allow sharing of spinning reserves
Allow exchange of energy, leading to loweroperating costs
Increase overall system reliability,especially under emergencies
Could ultimately lead to energy market
Source : GCCIA / SNC Lavalin .www.gccia.com.sa / www.snclavalin.ca
8/12/2019 Areva 2006 - International Developments in HVDC
11/22
PNWER Edmonton July 200611 11
Gulf States Interconnection
Gulf Cooperation Council Interconnection Authority (GCCIA)
Kuwait, Saudi Arabia, Bahrain, Qatar, United Arab Emirates (UAE) and Oman
Source : GCCIA / SNC Lavalin .www.gccia.com.sa / www.snclavalin.ca
8/12/2019 Areva 2006 - International Developments in HVDC
12/22
PNWER Edmonton July 200612 12
Gulf States Interconnection
First Studied 1990
RFQ Issued Feb 2005
Contracts Awarded Nov 2005
Scope of Packages - Phase 1 Six GIS substations
830 km of 400 kV transmission line
Two - 50 km of 400 kV submarine and land cables
3 x 600 MW HVDC back-to-back converter facility
Control Centre with Control, protection & SCADA andtelecommunication system
Phase 1 In Service by 2007
Phase 2 In Service by 2009
Phase 3 In Service by 2010
Source : GCCIA / SNC Lavalin .www.gccia.com.sa / www.snclavalin.ca
8/12/2019 Areva 2006 - International Developments in HVDC
13/22
PNWER Edmonton July 200613 13
Gulf States Interconnection
Design Philosophy
Failure of any one component will
not cause loss of power transfer
G8
LEGEND
Note: All Substations are GIS,
1-1/2 Breaker Scheme3 x 650 MVA
Umm
AnNa-S
an
Islan
d
RasA
l-Qura
yyah
Substat
ion
Qatari 132 kV
Network
Doha South
Substation
97 km
Projected Phase III
(Shuwaihat UAE)
Salwa
Substation
Qatari 220 kV
Network (4 circuits)
Doha south
(Qatar)1 x 125 MVAR
3 x 400 MVA
400 kV
2 x 150 MVA
220 kV
4 x 125 MVAR
400 kV
AL-FADHILI SUBSTATION
(KSA)
288 km
Ghunan
Substation
GCCIA
Control Centre
114 km
4 x 125 MVARAl Jasra
Substation
3 x 325 MVA
42.5 km (Submarine Cable)40 km
400 kV
2 x 125 MVAR +
2 x 300 MVAR
Bahraini 220 kV
Network (2 circuits)
400 kV
SEC-ERB 380 kV
Network (7 Circuits)
Al-Fadhili
Substation
292 km
Al-Zour
Substation
3 x 600 MW400 kV, 50 Hz
2 x 125 MVAR 2 x 125 MVAR
Back-to-Back
Converter Facility
2 x 125 MVAR
400 kV
Al Jasra
(Bahrain)
Bahraini66 kV
Network
2 x 150 MVA
220 kV
SEC-ERB 220 kV
Network
4 x 750 MVA
380 kV, 60 Hz
Shunt Reactor
Power Transformer
with OLTC
HVDC Converter
Overhead Line
Underground Cable
Submarine Cable
AL-ZOUR POWER STATION
(KUWAIT)
G1 G2
2500 MW
Kuwaiti 275 kV
network (6 Circuits)
275 kV
BAHRAIN
U.A.E.EMIRATES NATIONAL
GRIDAL OUHAH
220kV220kV
AL FADHILI 400kV
JASRA 400kVJASRA 400kVGHUNAN
400 kV
600MW
SALWA400kVSALWA400kV
QATAR750MW
90km90km
DOHA SOUTH SUPER 400kVDOHA SOUTH SUPER 400kV
288km
SHUWAIHAT400kV400kV
900MW
OMANOMAN NORTHERN
GRIDAL WASSET
220 kV
400MW
52km
114km
97km
KUWAITAL ZOUR
400kVAL ZOUR400kV292km
1200
MWSAUDI ARABIA
SEC-ERBHVDC
BACK-TO-BACK1200MW
200km
Source : GCCIA / SNC Lavalin .www.gccia.com.sa / www.snclavalin.ca
8/12/2019 Areva 2006 - International Developments in HVDC
14/22
PNWER Edmonton July 200614 14
Gulf States Interconnection- Finance
GCCIA member countries have 100% ownership
Each responsible for its own financing risks
Each responsible for its designated share of investment
35% equity
65% from loans
Source : GCCIA / SNC Lavalin .www.gccia.com.sa / www.snclavalin.ca
8/12/2019 Areva 2006 - International Developments in HVDC
15/22
PNWER Edmonton July 200615 15
AfricaWestcor Project
Combining Multiple HVDC and AC interconnections
8/12/2019 Areva 2006 - International Developments in HVDC
16/22
8/12/2019 Areva 2006 - International Developments in HVDC
17/22
PNWER Edmonton July 200617 17
Western Corridor -Westcor Joint Venture
WESTCOR JV
20%
20%
20% 20%
20%
Equity from
Joint VenturePartners
Debt:International
Financiers
SADC
NEPAD
African Union
Support:Regional andContinental
Customers:
BPC;ENE;
ESKOM;NAMPOWER; and
SNEL
Inga 3
PowerPlant
HVAC
Substation
HVDCRectifier Station
HVDCInverter Station
HVACSubstation
SNELENE
NampowerBPC
Eskom
3500 MW
Source : ESKOM/SAPP/Westcor .www.eskom.co.za / www.sapp.co.zw
8/12/2019 Areva 2006 - International Developments in HVDC
18/22
PNWER Edmonton July 200618 18
Westcor Transmission
Evaluating 500 kV vs 800 kV HVDC500 kV maximum transfer 2 GW
over 3000km - 600 MW losses
800 kV and 2 GW 200 MW losses
800 kV and 3 GW
600 MW losses1000 kV and 3 GW
400 MW losses
1100 kV and 3 GW
200 MW losses
Source : ESKOM/SAPP/Westcor .www.eskom.co.za / www.sapp.co.zw
8/12/2019 Areva 2006 - International Developments in HVDC
19/22
PNWER Edmonton July 200619 19
WestcorTransmission
Evaluating 500 kV vs 800 kV HVDC800 kV : 3000 MW HVDC for 3400 km into Pegasus
500 MW losses on HVDC circuits
Overall Loss savings over AC = 75 MW
Multi-terminal Operation is planned
Extra high towers planned for reduced maintenance of ROW
Funding
Development 7 MUSD
Implementation 7 BUSD
Timeline
Studies under way 2005
Construction planned
for 2008
Source : ESKOM/SAPP/Westcor .www.eskom.co.za / www.sapp.co.zw
8/12/2019 Areva 2006 - International Developments in HVDC
20/22
PNWER Edmonton July 200620 20
African Grid and Continental Interconnections
Source : ESKOM/SAPP/Westcor .www.eskom.co.za / www.sapp.co.zw
8/12/2019 Areva 2006 - International Developments in HVDC
21/22
PNWER Edmonton July 200621 21
International Developments in HVDC
Neil KirbyBusiness Development Manager
HVDC and FACTS, N AmericaAREVA T&D Inc
16th Annual PNWER ConferenceEdmonton, AB
Tuesday July 18th 2006
Introduction to HVDC across the world
Case Studies
KontiSkan 1
Gulf States Interconnection
Southern Africa Regional Interconnections
8/12/2019 Areva 2006 - International Developments in HVDC
22/22
PNWER Edmonton July 200622 22