Arion Dresses Limited (10556) Klarion Designs Limited Adhunik Chawk Super Market (3rd floor), Chalk Bazar, Chittagong (+ 22.357644N, 91.840028E) 20.MAY.2014
Transcript
Page 3: Arion Dresses Limited (10556) Klarion Designs Limitedbangladeshaccord.org/wp-content/uploads/Arion-Dresses-Limited... · - Cracks appeared underside of roof slab and column and ...

1st Priority 1 Concern

The interior columns, C1, at grid line F/4 of Main Building is supporting 5 storeys with 6.25 m and 5.84

span length and part of the weight of a water storage on top.

In situ

Size 18” x 18”

Vertical rebar 14 – ϕ 16 mm (1.39%)

Aggregate Brick

Water Storage

6.50 x 2.30 x 1.95 m

From the result obtained, calculation check of

column at grid line F/4 appears to be overstressed

(FoS = 1.29). Other columns probably have

similar levels of overstress.

Remark: Check at ground floor

Page 6: Arion Dresses Limited (10556) Klarion Designs Limitedbangladeshaccord.org/wp-content/uploads/Arion-Dresses-Limited... · - Cracks appeared underside of roof slab and column and ...

2nd Priority 2 Concern

These cracks are found underside

roof slab and exterior column along

the balcony on 1st floor. It is not clear

whether these cracks are structural

cracks. We require that these items

be investigated in a Detail

Engineering Assessment.

Page 12: Arion Dresses Limited (10556) Klarion Designs Limitedbangladeshaccord.org/wp-content/uploads/Arion-Dresses-Limited... · - Cracks appeared underside of roof slab and column and ...

The building does not feature any

shear walls; lateral stability is

provided only through rigid frame

action of beams and columns but it is

unclear if a design to BNBC seismic

provisions was done.

We require that these items be

investigated in a Detail Engineering

Assessment.

Page 16: Arion Dresses Limited (10556) Klarion Designs Limitedbangladeshaccord.org/wp-content/uploads/Arion-Dresses-Limited... · - Cracks appeared underside of roof slab and column and ...

Problems Observed Summary

ITEM 1: (Priority 1) Columns at grid line F/4 of Main Building

appear to be overstressed.

ITEM 2: (Priority 2) Inconsistencies between the drawings provided

and the actual as-built conditions.

ITEM 3: (Priority 2) Cracks appeared underside of roof slab and

column.

ITEM 4: (Priority 2) Diagonal cracks on the storage wall on 4th floor.

ITEM 5: (Priority 2) Overall stability system.

ITEM 6: (Priority 2) Distress due to water ingress.

ITEM 7: (Priority 3) Reinforcement left exposed at roof level.

ITEM 8: (Priority 3) Waterproofing material at roof level to be

maintained/applied.

Page 17: Arion Dresses Limited (10556) Klarion Designs Limitedbangladeshaccord.org/wp-content/uploads/Arion-Dresses-Limited... · - Cracks appeared underside of roof slab and column and ...

Item No. Observation Recommended Action Plan Recommended Timeline

1

Columns at grid line F/4 of Main Building appear to be

overstressed.

Load in this area does not exceed 2.0kPa on every floor.

Factory Engineer to review design, loads and columns stresses ifor the

entire building.

Verify in-situ concrete stresses either by cores or existing cylinder

strength data for [the identified columns / cores from 4 columns].

A Detail Engineering Assessment of Factory to be commenced

immediately.

Immediate – Now

2

Columns at grid line F/4 of Main Building appear to be

overstressed.

Produce and actively manage a loading plan for all floor plates within

the factory giving consideration to floor capacity and column capacity.

Detail Engineering Assessment to be completed

6-weeks

3Columns at grid line F/4 of Main Building appear to be

overstressed.

Continue to implement load plan.

Implement any strengthening works recommended by the DEA.6-months

4Inconsistencies between the drawings provided and the actual as-

built conditions.

Factory Engineer to survey the actual conditions and revise the

drawings.

Factory Engineer to review design, loads and columns stresses to

confirm suitability for loads applied.

Produce and actively manage a loading plan for all floor plates within

this area giving consideration to floor capacity and column capacity.

6-weeks

5Inconsistencies between the drawings provided and the actual as-

built conditions.Continue to implement load plan 6-months

6 Cracks appeared underside of roof slab and column.

The Factory Engineer to investigate the cause of cracks by appropriate

methods.

The distress found is to be suitably rectified and then repaired.

6-weeks

7 Cracks appeared underside of roof slab and column.Maintain standards of quality control to ensure that loading plan is

correctly followed so that problems do not arise in the future.6-months

Page 18: Arion Dresses Limited (10556) Klarion Designs Limitedbangladeshaccord.org/wp-content/uploads/Arion-Dresses-Limited... · - Cracks appeared underside of roof slab and column and ...

Item No. Observation Recommended Action Plan Recommended Timeline

8 Diagonal cracks on the storage wall on 4th floor.The Factory Engineer to monitor the cracks by appropriate methods.

The distress found is to be suitably rectified and then repaired.6-weeks

9 Overall stability system.

Request that the Detail Engineering Assessment of the overall building

to be carried out and in particular, stability and foundation aspects

should be investigated in detail.

6-weeks

10 Distresses due to water ingress.Factory Engineer to inspect water damaged structures and repair with a

suitable method. 6-weeks

11 Distresses due to water ingress.

For both durability and serviceability, rustproofing is recommended.

Waterproofing on the roof slab is recommended. Moreover the slab

drainage system should be investigated.

Maintain standard of quality control.

6-months

12 Reinforcement left exposed at roof level.For both durability and serviceability, rust proof paint or any

appropriate methods is recommended.6-months

13 Waterproofing material at roof level to be maintained/applied.

Engineer to inspect whether waterproofing material is applied or

where it can be maintained.

For both durability and serviceability, waterproofing on the roof slab is

recommended. Moreover the roof slab drainage system should be

investigated.

6-months


Recommended