ARSENAL 201 – PHASE 2 LAWRENCEVILLE NEIGHBORHOOD MEETING| JULY 11 TH , 2019
Transcript
Page 1: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

PROJECT UPDATE

ARSENAL 201 – PHASE 206.06.16

LAWRENCEVILLE NEIGHBORHOOD MEETING| JULY 11TH, 2019

Page 2: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

DISCUSSION HIGHLIGHTS

▪ Introduce Milhaus

▪ Recap timeline

▪ Arsenal Phase 1 Review

▪ Introduce Arsenal Phase 2

▪ Share concept designs

▪ Affordable Housing Initiative

▪ Discuss next steps

▪ Q & A

7/11/2019 Project Update 2

Page 3: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

MILHAUS

▪ Headquartered in Indianapolis, Indiana

▪ Established in 2010

▪ Focus on Class A, Urban, Multifamily Residential Buildings

▪ Long Term Owners

7/11/2019 Project Update 3

Page 4: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

7/11/2019 Project Update 4

PROJECT TIMELINE RECAP

▪ Sept 2016 Milhaus Purchases Land for Phase 1 & 2

▪ June 2018 Arsenal 201 Phase 1 Opens

▪ January 2019 Lawrenceville United/Corporation & Mayor’s Office Meeting

▪ Feb 2019 Lawrenceville United/Corporation Meeting

▪ March 2019 Councilwoman Deb Gross Meeting

▪ May 2019 Lawrenceville United/ Corporation Meeting

▪ June 2019 Councilwoman Deb Gross Meeting Lawrenceville Real Estate Committee Meeting City Planning CDAP Review

▪ July 11th, 2019 Lawrenceville Neighborhood Meeting

Page 5: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

ARSENAL PHASE 1

▪ Opened June 2018

▪ 243 Units▪ Micros, Studios, 1’s, 2’s, & 3’s

▪ 19k sf of Retail along Butler Street

▪ Currently 99% Leased

7/11/2019 Project Update 5

Page 6: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

▪ Projected Opening Fall 2021

▪ 343 Units▪ Micros, Studios, 1’s, 2’s, & 3’s

▪ 35 Affordable Units

▪ Parking Garage

▪ Public Green Space and Dog Park

▪ Green Trail Access Through Site

▪ Historical Renovation of Officer’s Quarters

ARSENAL PHASE 2

7/11/2019 Project Update 6

Page 7: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

7/11/2019 Project Update 7

BUILDING PROGRAM

RESIDENTIAL

MICROS 10%

STUDIOS 22%

ONE-BEDROOM 47%

ONE-BEDROOM + DEN 6%

TWO-BEDROOM 14%

THREE BEDROOM 1%

TOTAL RESIDENCES 343

PARKING SPACESSTRUCTURED/GARAGE 445

SURFACE 3

BIKE PARKING 200

Page 8: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

7/11/2019 Project Update 8

AFFORDABLE HOUSING

▪ Milhaus to provide 35 affordable units (10%) per the standards set forth in the Inclusionary Zoning Housing Legislation

▪ Monthly Rent shall not exceed 30% of the monthly income

▪ Households earning 50% of AMI

Page 9: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

AFFORDABLE HOUSING BUILDING PROGRAM

RESIDENTIAL

MICROS 5

STUDIOS 7

ONE-BEDROOM 18

TWO-BEDROOM 5

TOTAL RESIDENCES 35

7/11/2019 Project Update 9

Page 10: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

LOCATION MAP

7/11/2019 Project Update 10

Page 11: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

ARSENAL PHASE 2 SITE PLAN RENDERING

7/11/2019 Project Update 11

Page 12: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

BUILDING PERSPECTIVES

FOSTER STREET AND 39TH STREET

WIL

LO

WS

TR

EE

T

39TH STREET

FO

ST

ER

ST

RE

ET

ARSENAL ALLEY

Page 13: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

BUILDING PERSPECTIVES

39TH STREET AND WILLOW STREET

WIL

LO

WS

TR

EE

T

39TH STREET

FO

ST

ER

ST

RE

ET

ARSENAL ALLEY

Page 14: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

BUILDING PERSPECTIVES

WILLOW STREET AND ARSENAL ALLEY

WIL

LO

WS

TR

EE

T

39TH STREET

FO

ST

ER

ST

RE

ET

ARSENAL ALLEY

Page 15: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

BUILDING PERSPECTIVES

ARSENAL ALLEY AND FOSTER STREET

WIL

LO

WS

TR

EE

T

39TH STREET

FO

ST

ER

ST

RE

ET

ARSENAL ALLEY

Page 16: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019
Page 17: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019
Page 18: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019
Page 19: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019
Page 20: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019
Page 21: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

7/11/2019 Project Update 21

CONCLUSION AND Q&A

Page 22: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

EXHIBITS

7/11/2019 Project Update 22

Page 23: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

MASTER DEVELOPMENT PLAN

ARSENAL PHASE II

Page 24: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

PHASE 1 & 2 VEHICLE PARKING CALCULATIONS

ARSENAL PHASE II

Page 25: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

BUILDING INFORMATION

TOTAL PER BUILDING

463,315 SF

BUILDING AREAS RESIDENTIAL GARAGE

LEVEL 0 40,575 SF 9,650 SF

LEVEL 1 61,980 SF 28,755 SF

LEVEL 2 61,980 SF 28,755 SF

LEVEL 3 61,980 SF 28,755 SF

LEVEL 4 61,980 SF 28,755 SF

LEVEL 5 21,400 SF 28,755 SF

309,895 SF 153,420 SF

PROJECT TOTAL

BUILDING INFORMATION

TOTAL NUMBER OF UNITS: 343

PARKING INFORMATION

PHASE 1 EXISTING SURFACE AND GARAGE 177

SPACES

PHASE 2 PROPOSED PARKING GARAGE 445

SPACES

TOTAL PROVIDED PARKING SPACES 622

SPACES

TEMPORARY AND STREET PARKING INFORMATION

TEMPORARY PARKING LOT

75 SPACES

WILLOW STREET (PUBLIC PARKING) 24

SPACES

FOSTER STREET (PUBLIC PARKING) 14

SPACES

TOTAL TEMPORARY & STREET PARKING 113

SPACES

Page 26: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

BUILDING PERSPECTIVES

1 MAIN ENTRANCE AT 39TH STREET & FOSTER STREET

2 ENTRANCE FROM ARSENAL ALLEY & WILLOW STREET

2

1

3 SECONDARY ENTRANCE WILLOW STREET ENTRANCE

4 MAIN COURTYARD FROM 39TH STREET

3

4

Page 27: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

MAIN BUILDINGENTRANCE

EXISTING STONE

WALLEXISTING OFFICERS

QUARTERS

0809130604

03

02 12

BUILDING ELEVATION

435' - 9"

01 - 39TH STREET BUILDING ELEVATION

WIL

LO

WS

TR

EE

T

39TH STREET

1

FO

ST

ER

ST

RE

ET

ARSENAL ALLEY

TAG NO. MATERIAL INFORMATION

01 MODULAR VENEER BRICK

02 GROUND FACE MASONRY VENEER

03 CEMENTITIOUS PANEL - 1

04 CEMENTITIOUS PANEL - 2

05 CEMENTITIOUS

PANEL -

3

06 CEMENTITIOUS LAP SIDING

07 ACCENT CEMENTITIOUS SIDING / PANEL

08 CORRUGATED METAL PANEL SYSTEM

09 METAL PANEL SYSTEM

10 PRECAST CONCRETE - 1

11 PRECAST CONCRETE - 2

12 RAILING SYSTEM

13 W INDOW SYSTEM

14 ALUMINUM STOREFRONT SYSTEM

15 METAL CANOPY SYSTEM

16 METAL SCREEN SYSTEM

08 08MAX. BLDG

HEIGHT

811.0' MAX. BLDGHEIGHT811.0'

AVERAGE GRADE:

(747.5 + 734.5) / 2 = 741.0'

MAX BUILDING HEIGHT ALLOWED

741.0'+ 60' + 10' BONUS = 811.0' ALLOWED810.2' PROVIDED

70' ALLOWED

69.2' PROVIDED

RRAAMM

PP @@

88..33%%

747.5'734.5'BONUS POINT FOR INCLUSION OF PARK - SEC.

905.04.K.1 - RIVERFRONT PUBLIC ACCESS

EASEMENTS, TRAILS & AMENITIES SEC. 915.07.D.7.a-

7.f

LEVEL0

0'-0"

LEVEL1

10'-8"

LEVEL2

21'-4"

LEVEL3

32'-0"

LEVEL4

42'-8"

T.O. PARAPET

14 01

LEVEL1

0'-0"

LEVEL2

10'-8"

LEVEL3

21'-4"

LEVEL4

32'-0"

LEVEL 5

42'-8"

T.O. PARAPET

61'-4"

810.2'ELEVATION

AVE GRADE

741.0'

69

.2' B

UIL

DIN

GH

EIG

HT

60'-10"

799.5'ELEVATION

AVE GRADE

741.0'

58

.5' B

UIL

DIN

GH

EIG

HT

Page 28: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

04061309

02 12

LOADING TRASH

03

BUILDING ENTRANCE

1507

BUILDING ELEVATION1

287' - 5"

01 - WILLOW STREET BUILDING ELEVATION

WIL

LO

WS

TR

EE

T

39TH STREET

FO

ST

ER

ST

RE

ET

ARSENAL ALLEY

811.0' MAX. BLDG HEIGHT

LEVEL0

0'-0"

LEVEL1

10'-8"

LEVEL2

21'-4"

LEVEL3

32'-0"

LEVEL 4

42'-8"

T.O. PARAPET

60'-6"

T.O.PARAPET

60'-10"

LEVEL0

0'-0"

LEVEL 1

0710'-8"

TAG NO. MATERIAL INFORMATION

01 MODULAR VENEER BRICK

02 GROUND FACE MASONRY VENEER

03 CEMENTITIOUS PANEL - 1

04 CEMENTITIOUS PANEL - 2

05 CEMENTITIOUS PANEL - 3

06 CEMENTITIOUS LAP SIDING

07 ACCENT CEMENTITIOUS SIDING / PANEL

08 CORRUGATED METAL PANEL SYSTEM

09 METAL PANEL SYSTEM

10 PRECAST CONCRETE - 1

11 PRECAST CONCRETE - 2

12 RAILING SYSTEM

13 WINDOW SYSTEM

14 ALUMINUM STOREFRONT SYSTEM

15 METAL CANOPY SYSTEM

16 METAL SCREEN SYSTEM

LEVEL2

21'-4"

LEVEL3

32'-0"

LEVEL 4

42'-8"

Page 29: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

07

09

15 02

06

04121303

02

BUILDING ELEVATION1

426' - 4"

01 - ARSENAL ALLEY BUILDING ELEVATION

WIL

LO

WS

TR

EE

T

39TH STREET

FO

ST

ER

ST

RE

ET

ARSENAL ALLEY

TAG NO. MATERIAL INFORMATION

01 MODULAR VENEER BRICK

02 GROUND FACE MASONRY VENEER

03 CEMENTITIOUS PANEL - 1

04 CEMENTITIOUS PANEL - 2

05 CEMENTITIOUS PANEL - 3

06 CEMENTITIOUS LAP SIDING

07 ACCENT CEMENTITIOUS SIDING / PANEL

08 CORRUGATED METAL PANEL SYSTEM

09 METAL PANEL SYSTEM

10 PRECAST CONCRETE - 1

11 PRECAST CONCRETE - 2

12 RAILING SYSTEM

13 WINDOW SYSTEM

14 ALUMINUM STOREFRONT SYSTEM

15 METAL CANOPY SYSTEM

16 METAL SCREEN SYSTEM

08

LEVEL0

0'-0"

LEVEL1

10'-8"

LEVEL2

21'-4"

LEVEL3

32'-0"

LEVEL4

42'-8"

07

T.O. PARAPET

60'-6"

LEVEL1

0'-0"

LEVEL2

10'-8"

LEVEL3

21'-4"

LEVEL4

32'-0"

LEVEL5

42'-8"

T.O.PARAPET

60'-8"

Page 30: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

BUILDING ELEVATION1

TAG NO. MATERIAL INFORMATION

01 MODULAR VENEER BRICK

02 GROUND FACE MASONRY VENEER

03 CEMENTITIOUS PANEL - 1

04 CEMENTITIOUS PANEL - 2

05 CEMENTITIOUS PANEL - 3

06 CEMENTITIOUS LAP SIDING

07 ACCENT CEMENTITIOUS SIDING / PANEL

08 CORRUGATED METAL PANEL SYSTEM

09 METAL PANEL SYSTEM

10 PRECAST CONCRETE - 1

11 PRECAST CONCRETE - 2

12 RAILING SYSTEM

13 WINDOW SYSTEM

14 ALUMINUM STOREFRONT SYSTEM

15 METAL CANOPY SYSTEM

16 METAL SCREEN SYSTEM

04 12

13

TRASHPARKING ENTRANCE

1011070604

01 1402 16

WIL

LO

WS

TR

EE

T

39TH STREET

FO

ST

ER

ST

RE

ET

ARSENAL ALLEY

287' - 0"

01 - FOSTER STREET BUILDING ELEVATION

9'-6" CLEAR HEIGHT ATGROUNDLEVEL

811.0' MAX. BLDGHEIGHTVEHICLES TO BE

SCREENED FROM

ADJACENT VIEWS

LEVEL1

0'-0"

LEVEL2

10'-8"

LEVEL3

21'-4"

LEVEL4

32'-0"

LEVEL5

42'-8"

T.O. PARAPET

60'-8"

T.O.PARAPET

61'-4"

LEVEL1

0'-0"

LEVEL2

10'-8"

LEVEL3

21'-4"

LEVEL4

32'-0"

LEVEL5

42'-8"

Page 31: ARSENAL 201 PHASE 2 - Lawrenceville United · project update arsenal 201 –phase 2 lawrenceville neighborhood meeting| july 11 06.06.16 th, 2019

BUILDING MATERIALS

MODULAR VENEER BRICK

GROUND FACE MASONRY

PRECAST CONCRETE

CEMENTITIOUS SIDING

CEMENTITIOUS PANEL

ACCENT CEMENTITIOUS PANEL

METAL PANEL SYSTEM

CORRUGATED METAL PANEL