+ All Categories
Home > Documents > AS 2885.1 – 2007 - apia.net.au Venton - AS2885...28/02/07 Phil Venton AS 2885.1 2007 Revision –...

AS 2885.1 – 2007 - apia.net.au Venton - AS2885...28/02/07 Phil Venton AS 2885.1 2007 Revision –...

Date post: 25-May-2018
Category:
Upload: hacong
View: 217 times
Download: 1 times
Share this document with a friend
46
28/02/07 Phil Venton AS 2885.1 AS 2885.1 – 2007 Launch Seminar Philip Venton
Transcript

28/02/07 Phil Venton

AS 2885.1

AS 2885.1 – 2007

Launch Seminar

Philip Venton

28/02/07 Phil Venton

AS 2885.1

ME38-1 ConstitutionAmey, A Andrews, D Balendran, BBhatia, M Coates, M Colvin, PCope, G Dunn, M Ebdon, MFletcher, M Hourmozi, M Ihdayhid, KJaques, S Karunakaran, V Kempster, PMcDonough, R Moss, H Piper, JPugh, A Roach, I Schultz, RTuft, P Upritchard, P Venton, P

28/02/07 Phil Venton

AS 2885.1

Current Revision

28/02/07 Phil Venton

AS 2885.1

Current Revision Highlights

• 38 Meetings Since 1999• AS 2885.1 1997 Amendment 1, 2001• 87 “Issue” Papers• 12/2004 Public Comment Draft• 11/2006 Postal Ballot• Today “Final” Draft

28/02/07 Phil Venton

AS 2885.1

2007 Revision – 0.8 Design Factor• Change considered potentially

controversial• Decide to Rationally Analyse the

impact of a change on each component of Standard

• Issue Papers• Research

28/02/07 Phil Venton

AS 2885.1

2007 Revision – 0.8 Design Factor

• 12 Papers – Materials• 14 Papers – Safety• 8 Papers – Fracture• 30 Papers – Mechanical• 21 Papers – Operations / Procedure• 2 Papers – Electrical/Corrosion

28/02/07 Phil Venton

AS 2885.1

2007 Revision – 0.8 Design Factor• Paper Written• Debated in Committee – Revised• Research undertaken where Rqd.• Papers published on APIA Web• Public Comment Sought• Presentations at Seminars/Conf• International Conference

28/02/07 Phil Venton

AS 2885.1

2007 Revision – 0.8 Design Factor• Agreed Change Incorporated in

Standard• Changes Recorded• Issue Papers record reasoning• Final changes will provide basis for

companion document

28/02/07 Phil Venton

AS 2885.1

2007 Revision• Complete Revision• Structure revised into Logical Sections• Text rewritten to clarify intent• Stress and Strain – clarify • Extensive Informative Appendixes• Expert advice sought from international

experts• APIA Research Outcomes incorporated

28/02/07 Phil Venton

AS 2885.1

AS 2885.1Is it Prescriptive?

YESPrescriptive about the PROCESSPrescriptive about COMPETENCEPrescriptive about RECORDSPrescriptive about DESIGN PROCESSNOT generally prescriptive about DETAIL (ie not COOK BOOK)

28/02/07 Phil Venton

AS 2885.1

Preface • Interim• Contains the Scope of the AS 2885

Standard – which will be incorporated into Part 0

• Major changes identified

28/02/07 Phil Venton

AS 2885.1

Section 1 - General•Text Common to each Part moved to

new Part 0•Definitions revised•Nomenclature standardised and

tabulated – not defined in document•Retrospective application of specific

safety requirements

28/02/07 Phil Venton

AS 2885.1

Section 2 - Safety•Complete revision to reflect

experience since 1997•Rewrite to clearly define obligation

for robust process• Flowsheet Rewritten•Clearly identify other safety processes•Much detail moved to Appendices

28/02/07 Phil Venton

AS 2885.1

Section 2 - Safety• Input from AS 4360 Committee•Process restructured into 2 parts•Safety Management Study•Risk Assessment (AS 4360)

•Risk Matrix Revised from 4 x 6 to 5 x 5•Obligations for ALARP• Integrity of Process

28/02/07 Phil Venton

AS 2885.1

Section 3 - Materials• Referenced Standards Updated• CRA and Fibreglass Materials Permitted• Yield strength defined• Pipe strength derating with temperature• Minimum fracture toughness for ≥ DN100• Trim limits for ERW pipe defined• Temperature affected items• Traceability, Records Clarified

28/02/07 Phil Venton

AS 2885.1

Section 4 – Design General• Route & ROW• Location Classes (R1, R2, T1, T2) redefined• Secondary Classes (S, CIC, I HI, W)• Marking obligations revised• Minimum obligations for Design Basis• MAOP – Test Pressure Factor• Isolation Plan

28/02/07 Phil Venton

AS 2885.1

Section 4 – Design General• Special Provisions in High Consequence

Areas• No Rupture• Maximum Energy Release Rate

• Obligation to satisfy these requirements for changed location class (encroachment)

• Where ALARP is used – Demonstrate robust process

28/02/07 Phil Venton

AS 2885.1

Section 4 – Design General• Fracture Control • Fully revised • Peer review from overseas expert paid by

APIA research & standards• Critical defect length calculation

• Low temperature excursions• Energy discharge rate calculation• Appendix L Expanded

28/02/07 Phil Venton

AS 2885.1

Section 4 – Design General• Resistance to Penetration• Process defined in DR04561 revised• Found to be very conservative• Mandatory requirement removed except

for high consequence areas• Pen. Resistance to satisfy SMS • New process to recognise that different

locations require different Penetration Resistance

28/02/07 Phil Venton

AS 2885.1

Section 5 – Pipeline• Major Change – Wall Thickness is required

to satisfy the governing load condition at each location along a pipeline

• Pressure design thickness is the minimum wall thickness

• Maximum design factor = 0.80• Pipeline Assemblies = 0.67

Note: Stress analysis limit of 0.72*SMYS nothing to do with design factor

28/02/07 Phil Venton

AS 2885.1

Section 5 – Pipeline• Allowances redefined• Tolerance for pipe manufactured from

plate and from seamless process

28/02/07 Phil Venton

AS 2885.1

Section 5 – Pipeline

28/02/07 Phil Venton

AS 2885.1

Section 5 – Pipeline• Thickness for external pressure• External interference protection revised• Cover in rock strengthened• Pre-qualified design introduced

28/02/07 Phil Venton

AS 2885.1

Section 5 – Pipeline• Stress and Strain full revision• Equations – transparent & defined• Limits tabulated• API 1102 for Road & Rail X, with

modified limits • Limit State Design concepts permitted• Extensive informative Appendices with

equations

28/02/07 Phil Venton

AS 2885.1

Section 5 – Pipeline• Special Construction Revised• Above ground construction permitted in

specific locations• Branch connection reinforcement

provisions of AS 2885 – 1987 reintroduced• “O”- let fitting use restricted

28/02/07 Phil Venton

AS 2885.1

Section 5 – Pipeline• “O”- let fitting use restricted

28/02/07 Phil Venton

AS 2885.1

Section 5 – Pipeline• “O”- let fitting use restricted

• Designed to MSS SP 97 for thick wall pipe• Use on anything other than seamless, schedule

pipe to ASME B31.3 is outside scope of MSS SP97

• Specific assessment required to determine whether reinforcement complies

• Risk of failure when there is differential settlement, moments and fatigue

• Minimum line pipe thickness 6.4 mm

28/02/07 Phil Venton

AS 2885.1

Section 6 – Stations• Separated from “Pipeline”• Design basis for Stations introduced• General tidy-up

28/02/07 Phil Venton

AS 2885.1

Section 7 – Instrument-Control• Separated from “Pipeline General”• Obligation for Transient Pressure analysis

and control defined• Pressure control obligations clarified• Fluid property limit compliance• General obligations relating to SCADA

28/02/07 Phil Venton

AS 2885.1

Section 8 – Corrosion• Essentially Section 5• Revised & updated• Rate of degradation concepts• Links to Appendices which are revised &

updated

28/02/07 Phil Venton

AS 2885.1

Section 9 – MAOP Uprating• New Section • Uprating permitted in existing standard

but no process defined• Expectation in industry that with

introduction of 0.8 design factor, some pipelines may be able to be uprated

• Recent pipelines designed/tested for this• Existing pipelines designed for 0.6 could

be uprated to 0.72

28/02/07 Phil Venton

AS 2885.1

Section 9 – MAOP Uprating• Section defines the minimum obligations

for demonstrating the capability of the pipeline to be safely operated at a pressure other than the licensed MAOP

• At the completion of the process, the new MAOP will be determined

• May be higher (or lower) than licensed MAOP

28/02/07 Phil Venton

AS 2885.1

Section 9 – MAOP Uprating

• Interaction with Regulator through process

• Regulator must ultimately approve any change

• Obligation to “commission” pipeline at new operating pressure

28/02/07 Phil Venton

AS 2885.1

Section 9 – MAOP Uprating Issues• Concern within Committee that

experience with new pipelines at 80%SMYS needed before upratingexisting pipelines

• Committee considers the section an essential part of this Revision

• Maximum uprated pressure limit - 0.72 design factor equivalent

• This may be removed with experience

28/02/07 Phil Venton

AS 2885.1

Section 10 – Construction•Section Revised•As-built survey accuracy limits•Cad-Weld limits•Backfill and water crossings •Gauging plate use in confirming

compliance with dent limits

28/02/07 Phil Venton

AS 2885.1

Section 11 – Testing• Revised to address obligations for 0.8

design factor• Require use of Software particularly when

testing to ≥ 100% SMYS• Testing with Gas• Some material may be moved to Part 5

when it is revised

28/02/07 Phil Venton

AS 2885.1

Section 12 – Records

• Obligations for new pipeline at handover revised

• Believed to be compatible with Part 3• Recognise electronic format

28/02/07 Phil Venton

AS 2885.1

Appendices• Complete revision• Informative and Normative• Some may say “too much”• Additional Appendixes may be added by

amendment after publication

28/02/07 Phil Venton

AS 2885.1

Appendices – Safety (B, C, D, E, F, G, H, I)

• Combination of Normative and Informative

• Much of the detail material in Section 2 of AS 2885.1 – 1997 and HB 105

• HB 105 will be withdrawn

28/02/07 Phil Venton

AS 2885.1

Appendices – Safety (B, C, D, E, F, G, H, I)

• Appx. B –Safety Management Study process• Appx. C – Threats• Appx. D – External interference protection• Appx. E - Effective of EIP Controls• Appx. F – Qualitative Risk Assessment

• In accordance with AS 4360• Severity and Frequency updated• Risk Matrix now 5 x 5• Risk Treatment includes Extreme risk

28/02/07 Phil Venton

AS 2885.1

Appendices – Safety (B, C, D, E, F, G, H, I)

• Appx. G – ALARP• ALARP is serious• It is legally defined• Sentencing a risk as ALARP cannot be done

without conscious decision and;• Sufficient work to be able to demonstrate (in

court if necessary) that the solution truly complies with the ALARP principle

• Important when evaluating encroachment effects

28/02/07 Phil Venton

AS 2885.1

Appendices – Safety (B, C, D, E, F, G, H, I)

• Appx. H – Integrity of Safety Management• Appx. I – Environmental Mgt. (Risk Approach)

28/02/07 Phil Venton

AS 2885.1

Appendices – Other• Appx. L – Fracture (Revised)• Appx. M – Resistance to Penetration (New)• Appx. N – Fatigue (New)• Appx. T – Bolt Tensioning (New)• Appx. U – Stress type definitions• Appx. V – External Loads• Appx. W – Combined Equivalent Stress• Appx. X – Pipe Stress Analysis• Appx. Y – Radiation Contour• Appx. Z – Reinforcement of Branch Conn.

28/02/07 Phil Venton

AS 2885.1

Technology Maintenance• ISO TC67/SC2 Participating membership• ME38-1 member attends annual meeting• Active contribution to ISO development• APIA Research & Standards program• International Research via PRCI & EPRG• Joint Technical Meeting Canberra 16-20

April 2007

28/02/07 Phil Venton

AS 2885.1

Conclusion• ME38-1 undertook an exhaustive investigation

to understand the issues associated with pipeline pressure design at 80% of SMYS

• Conclusion that it was safe

• Outcome is a thoroughly revised, modern, world class Standard for energy pipelines

• Issue papers record the investigations and thinking – benefit for the future

28/02/07 Phil Venton

AS 2885.1

Next Task• Publish Part O

• Amend Part 1 (Preface) to reflect Part O

• Amend Section 11 (testing) to make it compatible with Part 5

• Amend other parts to reflect standard symbology and definitions

• Do it all again for 2012 (but it should be easier)


Recommended