+ All Categories
Home > Documents > ASME Project Plan

ASME Project Plan

Date post: 07-Nov-2015
Category:
Upload: ilham-widyasa
View: 7 times
Download: 0 times
Share this document with a friend
Description:
ASME Project Plant
Popular Tags:
49
___________________________________ South East Gippsland University ___________________________________ Automated Student Management System (ASMS) Project Plan Date: 20/08/2012 Prepared by ITPM Group 2 University of Colombo School of Computing
Transcript
  • ___________________________________

    South East Gippsland University ___________________________________

    Automated Student

    Management System

    (ASMS)

    Project Plan

    Date: 20/08/2012

    Prepared by ITPM Group 2

    University of Colombo School of Computing

  • 2 | P a g e

    Table of Contents 1. Introduction and Objectives of the Project Plan ................................................................................. 4

    1.1 Overview of the Organization ....................................................................................................... 4

    1.2 Current Situation and Problem/ Opportunity Statement ............................................................... 4

    1.3 Project Objectives ......................................................................................................................... 5

    2. Project ................................................................................................................................................. 6

    2.1 Project Information ....................................................................................................................... 6

    2.2 Project Objectives ......................................................................................................................... 6

    2.3 Project Approach .......................................................................................................................... 7

    2.4 Roles and Responsibilities ............................................................................................................ 7

    2.5 Project Constraints ........................................................................................................................ 8

    2.6 Assumptions .................................................................................................................................. 8

    2.7 Preliminary Schedule and Budget Estimates ................................................................................ 9

    2.7.2 Preliminary Budget Estimate ............................................................................................... 10

    2.8 Plan Modification Rules ............................................................................................................. 10

    2.9 Approval Signatures .................................................................................................................... 10

    3. Project Scope Management Plan....................................................................................................... 11

    3.1 Product description ..................................................................................................................... 11

    3.2 Project Deliverables .................................................................................................................... 11

    3.3 Scope Statement .......................................................................................................................... 12

    3.31 Within Scope ......................................................................................................................... 12

    3.3.2 Out of Scope ........................................................................................................................ 13

    3.3.3 Project Success Criteria ....................................................................................................... 13

    3.4 Work Breakdown Structure Development .................................................................................. 14

    3.5 Scope Change Management Process ........................................................................................... 15

    3.5.1 Scope of Change Requests ................................................................................................... 15

    3.5.2 Change Request Process ...................................................................................................... 16

    3.5.3 Change Control Team .......................................................................................................... 16

    3.6 Plan Modification Rules ............................................................................................................. 17

    4. Schedule management plan ............................................................................................................... 17

    4.1 Project Schedule .......................................................................................................................... 17

    Assumptions .................................................................................................................................. 17

    5. Cost Management Plan ..................................................................................................................... 17

    5.1 Project Budget ............................................................................................................................. 19

    5.2 Budget Constraints ...................................................................................................................... 19

    6. Quality Management plan ................................................................................................................. 21

  • 3 | P a g e

    6.1 Quality Standards ........................................................................................................................ 21

    6.2 Quality Metrics ........................................................................................................................... 23

    6.3 Quality Management Approach .................................................................................................. 23

    6.4 Quality Assurance ....................................................................................................................... 24

    6.5 Quality Control ........................................................................................................................... 25

    6.5.1 Quality Control Reviews ...................................................................................................... 25

    6.5.2 Quality Control Activities .................................................................................................... 25

    6.5.3 Measures of Software Quality .............................................................................................. 26

    7. Risk management plan ...................................................................................................................... 27

    7.1 Risk Management Strategies ....................................................................................................... 27

    7.2 Risk Management Tools ............................................................................................................. 28

    7.3 Data Sources ............................................................................................................................... 29

    7.4 Risk Categories ........................................................................................................................... 30

    7.5 Risk Probability and Impact ........................................................................................................ 32

    8. HR management plan ........................................................................................................................ 33

    8.1 Project Organization ................................................................................................................... 33

    8.1.1 Project Team ........................................................................................................................ 33

    8.1.2 Organization Structure ......................................................................................................... 34

    8.1.3 Stakeholders ......................................................................................................................... 35

    8.2Resource Requirements ............................................................................................................... 37

    8.3 Resource Assignment .................................................................................................................. 38

    9. Communication plan ......................................................................................................................... 45

    9.1 Stakeholder Analysis .................................................................................................................. 45

    9.2 Project Reports ............................................................................................................................ 47

    9.3 Project Meetings ......................................................................................................................... 48

    9.4 Project Information Accessibility ............................................................................................... 48

    9.5 Communications Summary ......................................................................................................... 49

    List of Figures

    1. WBS

    2. Organizational Structure

    3. Resource Histogram

  • 4 | P a g e

    1. Introduction and Objectives of the Project Plan

    1.1 Overview of the Organization

    South East Gippsland University is a modern academic organization. The Student

    Management System of the University provides support for the universitys endeavours,

    teaching and research. The goal of the management of the University is to continue with the

    improvement of its systems to achieve service excellence and cost advantages. The proposed

    project is attempting to revolutionize the service delivery to key stakeholders and foster

    excellence in teaching, research, and public service that will establish the University as a

    leader among the nation's major research universities.

    The University currently has an aging student management system. It currently runs on old

    technology, which is difficult and expensive to maintain, and does not provide the flexibility

    and services needed in a modern academic organization. Implementing an appropriate

    replacement presents an opportunity to integrate new technology such as SMS

    communication with students (i.e. for the delivery of results), and use of social media (such

    as Facebook, You Tube and Twitter), therefore increasing the overall ability of students to

    communicate with the university and to facilitate the university with better communication

    and feedback with students.

    1.2 Current Situation and Problem/ Opportunity Statement

    Currently at South East Gippsland University there is a separate and costly infrastructure for

    student enrolments, students updates, alumni management and results publishing services.

    Some of the systems rely on out-dated and unsupported equipment. The current technology

    has limited flexibility for new, expanded and integrated services. A system is required to

    support all the communications, infrastructure, and services to students and staff. Therefore

    they are going to implement a new Automated Student Management System (ASMS) to

    avoid those limitations.

    The ASMS Project will renew the student management services and infrastructure at South

    East Gippsland University. The University will implement a state-of-the-art web based

    system to provide a higher level of service at lower cost for University customers. The system

    will integrate the use of SMS and other social media technology with the student

    management system. The ASMSs strategy is to change all of its obsolete student

    management systems (student enrolment system, student reporting system (for lecturers and

    administrative staff to view results), the results submission system (for lecturers to submit

    results) and the results publication system that publish results to students.

    The new implementation will provide one integrated system instead of an assortment of

    systems, integration with other technologies (such as SMS), applications and social media,

    availability of trained systems-developers and Lower operational costs for the University.

  • 5 | P a g e

    The existing student management suite cannot utilize cost-effective new technology (SMS

    and other social media) and cannot be effectively maintained due to a scarcity of trained

    systems-developers due to the age of the system and the compartmentalised nature of

    previous enhancements of the systems.

    In this situation, the University will update its aging student management suite of systems.

    The existing systems will be replaced with a modern, integrated system. This modernization

    is expected to enhance service delivery to faculty, students and staff in ways that cannot

    effectively be accomplished with the existing core technology resources in place.

    1.3 Project Objectives

    Objectives

    Transform and advance quality in teaching, research, and public service.

    Enable new voice and data applications to support the University's mission.

    Provide a robust, flexible, ways of communication between students and the university

    to meet the communications requirements of the instructional faculty, researchers, and

    students.

    Upgrade technology infrastructure and support the organization.

    Potential Benefits new ASMS.

    A modern, state-of-the-art student management system. Integration with other

    technologies and applications.

    Improved services for all staff and students

    Quicker and more responsive action on new and change service requests and

    troubleshooting.

    Simplified billing.

    Upgrade of systems will reduce maintenance overheads on current old systems

    A more dependable, robust and secure network.

    University staff will benefit as they will not have to use multiple systems.

    New technology already used by students will be utilised for student management

    processes. This will provide the university with immediate feedback about the service

    quality and what students think about the degrees and units taught.

  • 6 | P a g e

    2. Project

    2.1 Project Information

    Project Start Date: 2nd of May, 2012

    Project Manager: Mr. Waruna Kodituwakku

    Project Sponsor: Information Technology Services (ITS), South East Gippsland University.

    2.2 Project Objectives

    Objectives

    Transform and advance quality in teaching, research, and public service.

    Enable new voice and data applications to support the University's mission.

    Provide a robust, flexible, ways of communication between students and the university

    to meet the communications requirements of the instructional faculty, researchers, and

    students.

    Upgrade technology infrastructure and support the organization.

    Potential Benefits new ASMS.

    A modern, state-of-the-art student management system. Integration with other

    technologies and applications.

    Improved services for all staff and students

    Quicker and more responsive action on new and change service requests and

    troubleshooting.

    Simplified billing.

    Upgrade of systems will reduce maintenance overheads on current old systems

    A more dependable, robust and secure network.

    University staff will benefit as they will not have to use multiple systems.

    New technology already used by students will be utilised for student management

    processes. This will provide the university with immediate feedback about the service

    quality and what students think about the degrees and units taught.

    Project End Date: 30th of May, 2014

  • 7 | P a g e

    2.3 Project Approach

    Project Approach Phase Description

    Project Initiation & Planning In this phase all initiation activities such

    as resource allocation, planning and

    approving project charter will be done.

    Project Execution In this phase following activities will be

    done.

    1. Monitoring & Control

    1. Requirement Analysis & Specification

    2. Design

    3. Implementation

    4. Quality Management

    5. Training

    Installation Install all the software, database and

    hardware components.

    Maintenance Monitor and take actions to solve issues

    and gather requirement for further

    enhancements.

    2.4 Roles and Responsibilities

    Name Role Position Contact Information

    Waruna Kodituwakku Project Manager Project Manager [email protected]

    Charaka Hettiarachchi Accountant Accountant [email protected]

    Shanika Udeshini Human

    Resources

    Manager

    Human Resources

    Manager

    [email protected]

    m

    Aloka Weerasuriya Communications

    Manager

    Communications

    Manager

    alokaweerasooriya07@

    gmail.com

    Dasitha Wijesundara Business Analyst Business Analyst [email protected]

    Harshani

    Wickramarachchi

    Quality

    Assurance

    Analyst

    Quality Assurance

    Analyst

    [email protected]

  • 8 | P a g e

    NimalBandara Network

    Engineer

    Network Engineer [email protected]

    Kumudu Lokuge Assistant

    Network

    Engineer

    Assistant Network

    Engineer

    [email protected]

    m

    Sadishani Rangika Network

    Operators

    Network Operators [email protected]

    m

    Sunil de zoysa Security

    Specialist

    Security Specialist [email protected]

    Nirmal Perera User Interface

    Designer( LMS

    expertise)

    User Interface

    Designer( LMS

    expertise)

    [email protected]

    2.5 Project Constraints

    Resource Constraints

    Some staff resources will be available only on a part-time basis.

    Budgetary Constraints

    Salary scheme for employees will be based on the current market situation and total

    employee costs will be at around 60% of the project budget.

    No additional cost for Wireless broadband hardware and software apart from $50,000.

    Schedule Constraints

    Project requires to be implemented within 24 months or less time frame and the

    existing services have to be maintained continuously.

    Project Team does not work on weekends.

    Quality Constraints

    Deliverables of the project plan and ASMS System should be subject to quality review

    process throughout the designing and implementation process.

    2.6 Assumptions

    Resource Assumptions

    Project staff resources will be available when and as they are needed. Required hardware resources will be available when and as they are needed.

  • 9 | P a g e

    Required customer resources will be available when and as they are needed. A significant percentage of the project staff will be experienced with the technical

    environment.

    Access to industry experts and specialized skills will occur as needed.

    Delivery Assumptions

    Deliverables will be subject to no more than a specific number of review cycles. Software and Equipment order lead times are known and can be expected to be met.

    Environmental Assumptions

    No industrial action will be taken that will affect the project. Issues will be resolved in a timely manner.

    Budgetary Assumptions

    The statistics used in preparing the estimates are accurate within a given percent. Outsourced consulting will be limited to a specified number of days at a specified rate per

    day.

    Functionality Assumptions

    The scope of the project is limited to that described in the project scope statement.

    2.7 Preliminary Schedule and Budget Estimates

    2.7.1 Preliminary Schedule

    Phase Estimated Duration

    (Days)

    Project Initiation & Planning 48 days

    Monitoring & Control 130 days

    Requirement Analysis &

    Specification

    55 days

    Quality Management 10 +176 days (parallel)

    Design 50 days

    Implementation 100 days

    Installation 25 days

  • 10 | P a g e

    Testing 110 days (parallel)

    Training 30 days (parallel)

    Maintenance 65 days(parallel)

    2.7.2 Preliminary Budget Estimate

    2.8 Plan Modification Rules

    Only the project manager has the authority to change this project charter. Before getting approval by

    the sponsor any change will be informed to project team members via email. After getting approval

    there will be any change will be not approved.

    2.9 Approval Signatures

    Project Manager:

    As project manager on Automated Student Management Project, I have reviewed the information

    contained in the Project Charter and agree to its content.

    Name Position Signature Date

    Cost Areas $

    Total Employee cost 1,700,000.00

    Total software cost 1,100,000.00

    Total Hardware cost 100,000.00

    Total service charges 20,000.00

    Total Overhead cost 30,000.00

    Total Outsourced Costs 50,000.00

    Total 3,000,000.00

  • 11 | P a g e

    The signatures above represent stakeholders agreement and acknowledgement of the information contained in this document.

    3. Project Scope Management Plan

    3.1 Product description

    The new Automated Student Management System (ASMS) will be a web based software

    application for the administration, documentation, tracking, reporting, communication and

    delivery of education courses or training programs online. The ASMS will be able to do the

    following.

    Centralize and automate administration

    Use self-service and self-guided services

    Assemble and deliver learning content rapidly

    Consolidate training initiatives on a scalable web-based platform

    Support portability and standards

    Personalize content and enable knowledge reuse

    Deliver online training and webinars

    Communication through SMS and social media such as Face book and YouTube.

    ASMSs range from systems for managing training and educational records, to software for

    distributing and delivering of online courses, augment on-campus courses and deliver online

    training, as well as automate record-keeping and student registration. Student self-service

    (e.g., self-registration on instructor-led training), training workflow (e.g., user notification,

    manager approval, wait-list management), the provision of on-line learning (e.g., computer-

    based training, read & understand), on-line assessment, management of continuous

    professional education (CPE), collaborative learning (e.g., application sharing, discussion

    threads), and training resource management (e.g., instructors, facilities, equipment), are all

    important dimensions of the Student Management System.

    3.2 Project Deliverables

    Software Documentation

    o System Documentation

    o User Documentation (User Manual)

    Project documentation

    o Software Requirements Specification (SRS)

    o Software Design Specification (SDS)

  • 12 | P a g e

    o Software Project Management Plan (SPMP)

    o Software Test Plan (STP)

    o Software Quality Assurance Plan (SQAP)

    o Software Configuration Management Plan (SCMP)

    o Software Verification and Validation Plan (SVVP)

    3.3 Scope Statement

    Project Title : Automated Student Management System (ASMS)

    Prepared by : Waruna Kodituwakku, Project Manager ([email protected])

    Project Justification:

    The South East Gippsland University, requested this project be done to support the

    management of students of university in meeting its strategic goals. This system will help to

    reduce operational costs and improve profitability of the university by providing One

    integrated system instead of an assortment of systems, integration with other technologies

    such as SMS communication (i.e. for the delivery of results) and applications and social

    media (Facebook, YouTube) and availability of trained systems-developers.

    3.3.1. Within Scope

    1. Requirement gathering and defining: Project team will contact university lecturers,

    administrative staff and students to determine the best interface and website content. This

    will be backed up by prototypes of the major parts of the software and existing system for

    more feedback.

    2. System capacity: The systems capacity to hold files for the staff, student and

    management will be unlimited by the software, but by the hardware capacity therere

    using.

    3. Expert Database: Since ASMS will be receiving many user requests, a dedicated

    database is required to record and organize requests in order for best possible response

    time and the ability to quickly and easily review past complaints or suggestions.

    4. Installation: Once the system is completely implemented and agreed on, System

    Development team will install it on all of the necessary components.

  • 13 | P a g e

    5. Testing: Testing will include the development of test plans to document how the system

    will be tested, who will do the testing, and how bugs will be reported. We will provide

    additional Network security for the University Network to prevent unauthorized accesses.

    6. Maintenance: We will provide maintenance for the system and the website for 1 year of

    the installation date. There will be a well-defined plan for rolling out the new system,

    supporting users, and providing updates, enhancements, or other support, as required.

    7. Security: All services must be secure with restricted access rights.

    8. Training: A 40 days training period will be available of the universitys staff and system

    administrative staff on how to use the system. Starting from top level staff and covering

    all other relevant parties of the university staff.

    9. User Manual: A user manual for the staff will be available. Also, an online user manual

    on the website will be available for the users.

    3.3.2 Out of Scope

    1. All retraining and further maintenance will be responsible of the university

    2. All data entering, registration of users, course delivery and etc will be undertaken by

    universitys administrative processes as part of operations.

    3. Any upgrades required to other systems to enable them to work with the new ASMS.

    4. Any social media element such as User Generated Content, communities or moderated

    forums.

    5. The network room/space, proposed will be delivered by the university.

    6. All advertising and marketing required for launch and on an ongoing basis will not be

    delivered or paid for by this project

    7. Any recruitment required of resources for university purposes once the new system

    launches and training and testing completed.

    3.3.3 Project Success Criteria

    Our goal is to complete the project within 24 months. The initial budget will not be exceeded.

    In order to meet this goal each team member must put in three work hours per week.

    Deliverables must be completed on time and within the sponsors specifications. Late

    completion of the project is not acceptable.

  • 14 | P a g e

    3.4 Work Breakdown Structure Development

    Work Breakdown Structure (WBS) is developed as a chart in which the critical work

    elements, called tasks, of the project are illustrated to portray their relationships to each other

    and to the project as a whole. This WBS will assist key personnel in the effective allocation

    of resources, project budgeting, procurement management, scheduling, quality assurance,

    quality control, risk management, product delivery and service oriented management.

    The project tasks are categorized into ten phases. Each of these phases is then subdivided

    further down to sub phases. Each sub phase of the main phases may be subdivided into at

    most two sub phases. Here we have used top-down approach to create the WBS.

    Project Manager, Software Architect, Programmer, Business Analyst, Quality Assurance

    Analyst, Database Administrator, Software Designer Technical writers, Human Resources

    Manager and Web Developers engaged in developing the WBS.

    (For detailed WBS refer Appendix B)

  • 3.5 Scope Change Management Process

    The purpose of the Scope Change Management Plan is to:

    1. Manage and control scope change during the implementation of the Project.

    2. Ensure that the project is implemented on time and within the approved budget and

    scope.

    3. Evaluate and prioritize all changes to the project implementation plan at the

    institutional level.

    4. Provide a process for implementing change required by the system.

    3.5.1 Scope of Change Requests

    The following change requests will be addressed by the Scope and Change Management

    Plan:

    1. Modifications to software.

    2. Purchase of 3rd party software.

    3. Changes to contracted professional services (e.g. additional consulting visits).

    4. Scope (includes modules, data conversion and migration, interfaces, etc.).

    5. Milestone dates, including interim milestones and major go-lives.

    6. Additional project spending (hardware, training, conferences, etc).

    7. Functionality required by policy changes at the university and/or external mandates.

    The following change requests will not be addressed by the Scope and Change Management

    Plan:

    1. Policy / process changes. May occur as a result of a change request.

    2. Requests for modifications to current systems which are not to be replaced. Changes

    may occur as a result of integration, migration, and conversion decisions.

    3. Re-allocation of contracted professional services hours. May occur due to a change

    request, but specific requests to re-allocate service hours will not be accepted without

    justification based on the change.

    4. Changes to existing systems

  • 16 | P a g e

    3.5.2 Change Request Process

    Step1 - Person who wants to initiates Change Request by completing the Change Request

    Information section on the Change Request Form and submitting to Project Manager.

    Step 2- Project Manager Reviews the request identifies needed information and next steps to

    complete; enters into Change Request Log. Project manager communicates and coordinates

    with appropriate personnel to gather required information.

    Step 3 - Project Manager prepares and submits Change Request Impact Analysis section and

    submits it to the Change Control Team.

    Step 4 - Development Team receives weekly updates of pending change requests and

    provides input as needed / requested.

    Step 5 - Change Control Team approves/denies change request, provides Final

    Recommendation on the Change Request Form and advises project Manager and If

    appropriate, forward for review and disposition.

    Step 7 - Project Manager communicates the decision to:

    a. The person who is making the request of the Change Review Team decision.

    b. Development Team/ Designers/ Analysts

    c. All Project members and appropriate interested parties.

    d. Makes appropriate entries into the Change Management Request Log.

    Step 8 - Modify Implementation plan and documentation as needed to incorporate approved

    change.

    Requests resulting in changes to the vendor contract require approval from the Project

    Sponsor and no changes to the contract should be acted upon or conveyed as an approved

    change until we have verified that we are in compliance with the original contract. Changes

    to software, budget, or contracted hours will be reviewed, managed and approved by the

    Project Manager. First priority will be given to change requests for mission-critical functions

    and/or services. Other criteria for evaluating change requests will be approved by the Change

    Review Team. Documents using in this process will be Change Request Form, Change

    Request Log and Scope Change Management Plan

    3.5.3 Change Control Team

    Following personnel will be the members of the Change Control Team

    1. Project Manager

    2. Business Analyst

    3. Software Developing Manager

    4. Change Review Team members

  • 17 | P a g e

    3.6 Plan Modification Rules

    Only the project manager has the authority to change this plan. Notification of scheduled and

    unscheduled updates to the plan will be communicated via e-mail to all project participants.

    The plan will only receive further baselines if significant change in scope occurs.

    4. Schedule management plan

    4.1 Project Schedule

    Milestone Completion Date

    Project Charter Approved 07/08/2012

    All project deliverables have been delivered 03/01/2013

    All deliverables have been delivered 22/03/2013

    Evaluate project quality Starting from 24th of 2013

    After that once a week

    Create Software Design Specification (SDS) 14/06/2013

    Implementation Completed 01/11/2013

    Installation Completed 06/12/2013

    Director view of the system 03/01/2014

    Upload current data to the system 30/04/2014

    Testing Completed 09/05/2014

    Training Completed 30/05/2014

    (For detailed schedule plan (Gantt chart) refer Appendix A)

    Assumptions

    Project Team does not work on weekend days.

    We outsource Security Specialist , Legal consultant, Network Engineer, Network

    Operator, User Interface Designer ( LMS Expertise ) for the project

    Assume following team members will work on the project to achieve the goals as mentioned

    bellow.

    CIO - He works First week of the May 2012 and some additional 15 hours. All

    together 55 hours.

  • 18 | P a g e

    IT Project Manager He works through all stages of the project, Project Monitoring

    and Control, Project Initiation and additional 22 hours.

    Accountant Works for 4 hours per month for entire project. And some additional

    hours regarding when its needs for the project.

    Human Resource Manager - He works especially on managing human resources

    and training university staff. 320 hours on whole project.

    System Administration - He works specially on Installation, Resolve technical

    problems, Resolve technical problems. We allocate 200 days for him

    System Architect - He assign to work on Design stage from April 2013 up to June

    2013 other and additional hours spend for the iterations 200 hours on whole project.

    Software Development Manager He works for additional plugins that integrate for

    the student management system and the design. We allocate 200 hours for him.

    Software Engineer / Developer - He works for additional plugins that integrate for

    the student management system and the design. We allocate 340 hours for each.

    Test Manager - He works in System testing stage we allocate 1120 hours for each of

    them. Starting from December 9 2013.

    Technical Writers He works 120 days specially the areas of Requirement Analysis,

    Specification ,Design and User Documentation

    Help Desk level 2 - Allocate for 60 days for training the staff starting from February

    2014 and ends May 2014. (2 steps)

    Quality Assurance (QA) Analyst He works on Quality Plan and Monitor product

    quality .( Meet the company deliverables together with web developer, Database

    Admin, Data warehouse Engineer and Business analysis) we allocate 480 hours with

    Additional hours for referring the quality of the project

    Business Analyst He specially works on Requirement Analysis, Specification,

    Develop Software Quality Management Plan and Manage Risk areas and with

    additional hours we allocate 560 hours for him.

    Network Operator - Work 2 month (June 2013 and August 2013) 160 hours per each

    with additional hours apply for maintenance.

    Network Engineer - Work 2 month (June 2013 and August 2013) 60 hours with

    additional hours apply for maintenance.

    Database Administrator - He works specially on Installation, Design and Monitor

    product quality. (Meet the out project deliverables together with web developer,

  • 19 | P a g e

    Database Admin, Data warehouse Engineer and Business analysis) with additional

    hours we allocate 560 hours for him.

    Data - warehouse Engineer - He works specially on Installation, Design and Monitor

    product quality. (Meet the out project deliverables together with web developer,

    Database Admin, Data warehouse Engineer and Business analysis) with additional

    hours we allocate 580 hours for him.

    Web Developer

    o He works June 2013 October 18 2013.He works 8 hours per week. 1920 hours

    per each. And he also allocate for 60 days for training the staff .He got to have

    some extra hours to train the staff and other developing purposes.

    5. Cost Management Plan

    5.1 Project Budget

    Cost Areas $

    Total Employee cost 1,650,670.00

    Total software cost 932,487.95

    Total Hardware cost 96,910.00

    Total service charges 14,670.00

    Total Overhead cost 27,044.00

    Total Outsourced Costs 49,204.00

    Total 2,770,985.95

    (For detailed budget refer Appendix D)

  • 20 | P a g e

    5.2 Budget Constraints

    We use Budgetary Estimate for almost all cost fields.

    We use following professional tools for the ASMS project and we purchase them - Web

    Studio 5.0 (15 users) , CS Adobe 6 Master Collection 2 yrs (with renewal ), Database and

    DB Firewall (Oracle), MyEclips Bling Edition (2 yrs) , Security software (Kaspersky) ,

    MS Project Standard 2010. They are Budget Estimates.

    Web Developers may use for staff training also.

    Student management System cost includes the all license fees and the integration

    modules of it. Has no additional cost apart from what allocates from budget.

    IT work desk Implementation has no additional cost apart from what allocates from

    budget.

    We never allow any amount of Money for the maintenance of the system after the June

    2014

    We do abide for the security of the network system for 6 months after 2014 June(as

    standard procedure)

    No additional cost for Wireless broadband hardware and software apart from $50,000

    No additional cost for Wireless broadband maintenance e apart from $5,000/annual

    5.3 Budget Assumptions

    The currency use for calculations is US dollars.

    Administration costs not exceed $5000

    Reserves $6,806 as Reserves for use unexpected costs that when project is going on.

    We outsource Security Specialist , Legal consultant, Network Engineer, Network

    Operator, User Interface Designer ( LMS Expertise ) for the project

    Security Specialist assign for security testing purposes.

    We consider that there are no more additional money to spend on training the staff but as

    if they need we will negotiate it with Utility and System and functional Testing Cost.

    We didnt include additional food and beverages cost the final budget as they appear on

    utility cost.

    We assume that current network system of the University has to be upgrade (we already

    examined) so we include Hardware maintenance & implementation for it.

    We add 10 PC maintenance cost and the software renewal cost to the budget.( developers

    usages)

  • 21 | P a g e

    6. Quality Management plan

    6.1 Quality Standards

    Project process/ Reports Quality Standards

    Project Planning and Management

    Project Plan

    Configuration Management

    Plan

    Quality Assurance Plan

    Project Status

    Reports/ongoing Project

    Management

    Technology Assessment

    Report

    Feasibility Report

    Team members will go through the case study and

    understand the current situation and the project manager

    will closely monitor the process of collecting of project

    information for the status reports.

    IEEE 1058

    Requirements Analysis Process

    Prototypes and other

    diagrams

    Flowcharts

    System Requirements

    Specification Document

    (SRS)

    Functional Specifications

    Document (FS)

    Requirements Traceability

    Matrix

    Use Cases

    Once the requirement analysis process is complete in that

    case team members provide comprehensive documentation

    covering all requirements gathered.

    IEEE 830

    Design

    System Design Document

    System Security Consensus

    Document (SSCD)

    Security Plan

    Data Retention Plan

    Disaster Recovery Plan

    Unit and Integration Test

    plan (Begin)

    Conversion Plan (Begin)

    Transform the requirements into complete and detailed

    system design specifications. Once the design is approved,

    the Development Team begins the Development Phase.

    IEEE 1016

  • 22 | P a g e

    Implementation Plan

    Operation or System

    Administration Manual

    (Begin)

    Maintenance Manual

    (Begin)

    Training plan

    User Manual (Begin)

    Requirements Traceability

    Matrix (Update)

    Implementation

    Finalized System

    Documentation

    Post-Implementation

    Review Summary

    Methodology Compliance

    Form

    System Manual

    Program Manual

    Data Manual

    Application Operation

    Manual

    Application User Manual

    Computer Operating

    Procedures Manual

    By using the architecture document from the design phase

    and the requirement document from the analysis phase, the

    team will build exactly what has been requested.

    Testing

    Unit and Integration Test

    plan

    Software Validation and

    Verification Plan (SVVP)

    Software Test

    Documentation (STD)

    The team will be test the system in the relevant

    environment and fix the errors.

    IEEE 1012

    IEEE 829

    Maintenance

    Maintenance Manual

    Maintenance and Support

    Services From

    Keeps the system up to date with environment changes and

    changing user requirements.

    IEEE1993

  • 23 | P a g e

    6.2 Quality Metrics

    Project Deliverables Quality Metrics

    Tensile Strength The system will be used in various industrial environments

    under high material stress loads.

    Shear Strength The system will be subject to potentially high stress torque

    loads in various applications.

    Customer Satisfaction The customers should be given the customer satisfaction

    form and the customer satisfaction of the system should

    reach the expected level.

    Material Scrap The system should ensure whether it is following the metrics

    which internally established for measuring and controlling

    material scrap for manufacturing efforts of it.

    Product Defect Rate The system should ensure whether it is following the metrics

    which internally established for measuring and controlling

    product defects.

    6.3 Quality Management Approach

    Tool Use of Tool Person Responsible

    Total Quality

    Management (TQM)

    Aims to produce product and service

    specifications with zero defects.

    TQM creates a virtuous cycle of

    continuous improvement that boosts

    production, customer satisfaction

    and profits.

    Quality Assurance Analyst

    Quality Management

    Framework (QMF)

    The QMF standardizes processes,

    allowing for increased efficiencies.

    These processes strengthen supplier

    management techniques in addition

    to robust cost control, thereby

    improving overall profit. And by

    implementing the QMF we ensure

    security compliance across a project

    lifecycle.

    Project Manger

  • 24 | P a g e

    Six Sigma Improve the quality of process

    outputs by identifying and removing

    the causes of defects (errors) and

    minimizing variability in

    manufacturing

    Quality Assurance Analyst

    6.4 Quality Assurance

    Stage Deliverable Work Product QA Activity

    Planning Project Plan Project Schedule ISA Process- (review

    process and audit contents )

    Preparation Functional Requirements

    Document

    Acquisition Plan

    Installation Plan

    Revised Project

    Plan

    ISA Process- (review

    process and audit contents )

    Software Design Functional Design

    Document

    Security Plan

    Training Plan

    System Test Plan

    Acceptance Plan

    Conf. Mgmt. Plan

    Conversion Plan

    Traceability

    Matrix

    Revised Project

    Plan

    ISA Process- (review

    process and audit contents )

    Trace design components to

    requirements

    Trace requirements to

    design components

    Programming and

    Integration

    Site Installation Plan,

    System Documentation

    Revised Project

    Plan

    ISA Process- (review

    process and audit contents )

    System Testing and

    Acceptance

    Test results, System

    Documentation

    Operational System

    Revised Project

    Plan

    ISA Process- (review

    process and audit contents )

  • 25 | P a g e

    6.5 Quality Control

    6.5.1 Quality Control Reviews

    Bendability Reviews:

    These reviews are initialized by Project Management Team. These reviews can take

    place as part of the Final Plans Processing.

    Constructability and Right of Way Reviews:

    These reviews allow input from the departments, for constructability reviews and

    assist in the Right of Way Office in reducing right of way costs.

    Checking procedures

    Checking Reports

    o Avoid redundant data.

    o Support for focusing on major issues.

    o Makes data & structures consistent.

    Checking Drawings

    o Provides the design according to the requirement of project.

    o Provides complete & clear idea of project.

    o Provides coordination with other aspects of the project.

    o Gives compatible standards and good plans preparation practice

    Checking Calculations

    Checking Correspondence

    6.5.2 Quality Control Activities

    1. Check that assumptions and criteria for the selection of data and the different factors

    related to data are documented.

    2. Check for transcription errors in data input and reference.

    3. Check the integrity of database files.

    4. Check for consistency in data.

    5. Check that the movement of inventory data among processing steps is correct.

    6. Check for uncertainties in data, database files etc.

    7. Undertake review of internal documentation.

    8. Check methodological and data changes resulting in recalculations.

    9. Undertake completeness checks.

    10. Compare results to previous results.

    11. Defining and classifying the severity of defects.

    12. Inspecting documents.

    13. Inspecting code .(either manually or via automatic static code analysis)

    14. Testing executable software. For example: module, unit, integration, system and

    acceptance testing.

  • 26 | P a g e

    15. Recording of defects.

    16. Setting quality control limits outside of which corrective action must be taken.

    17. Tracking corrective action on defects.

    18. Defect data analysis tracking defect trends over time.

    6.5.3 Measures of Software Quality

    Where:

    KLOC = Thousand Lines of Code

    NDT = Number of Defects Detected in Testing

    NDO = Number of Defects Detected in Operation

    Assumptions

    We have to ensure the quality of the data of the existing system and the data entering process

    of the new system. So we are using a Data Base Administrator (DBA) and a Data

    Administrator (DA). As we have to increase the communication process of the system, we

    have to use some extra plug-in so we are using two Software Engineers and one Software

    Manager (SM) to supervise them. Once a week we are conducting a meeting to ensure the

    quality of the process. So DBA, DA, SM and the two Quality Assurance Analysts are

    participating to the meeting and they are finally providing a weekly Status Report to the

    Quality Manager.

    Metric Formula Significance

    Code defect

    density

    (in system test)

    NDT/KLOC Indicates the quality of the code presented to the

    system test group

    Code defect

    density

    (in operation)

    NDO/KLOC Indicates the quality of the code delivered to the

    customer

    Defect removal

    efficiency

    NDT/(NDT +

    NDO)

    Indicates the effectiveness of the test function in

    removing defects from the delivered software product

  • 27 | P a g e

    7. Risk management plan

    7.1 Risk Management Strategies

    When developing a system, an area of uncertainty that comes along with developing system.

    The purpose of the risk management plan is to establish the framework in which the project

    team will identify risks and develop strategies to reduce or avoid those risks.

    Process Name Process Description

    Risk Identification Risk identification should be done in initial step of the

    project. So we going to held a project risk assessment

    meeting at the beginning. There are few methods to

    identify risks. Such as Brainstorming, Delphi Technique,

    NGT, Crawford slip etc here we planned to use

    Crawford method. In risk assignment meeting Project

    manager distribute slips among all team members and

    asked to write down every possible risks which related to

    the our project within 5 minutes.

    Risk Qualification and

    Prioritization

    In order to determine the effectiveness of the risks

    identified by the team, a probability and impact factor

    assign to each risk. This process allows the project

    manager to prioritize risks based on the effect they may

    have on the project. The project manager develops a

    probability impact matrix to facilitate the team in moving

    each risk to the appropriate place on the chart. Once the

    risks were assigned a probability and impact and placed in

    the appropriate position on the chart, the recorder

    captured the finished product and the project manager

    moved the process on to the next step: risk

    mitigation/avoidance planning.

    Risk Monitoring In this step the identified greatest risks have been added to

    the project plan and ensure that they are monitoring at the

    appropriate time in the project schedule. During team

    meetings the Risk manger discussed the status of that risk.

    Here we take the risk which is relevant to that time period

    according to the schedule. Risk monitoring will be a

    continuous process throughout the life of this project.

    According to the project schedule The Project manager

    ensured that the Risk manager provide the necessary

    updates about risk status, trigger conditions,

    documentation about risk response etc

  • 28 | P a g e

    Risk Mitigation and Avoidance The project manager led the team to develop responses to

    each identified risk. Then the project team develops

    avoidance and mitigation strategies. Those risks will be

    added to the Risk register and the project plan to ensure

    that they are monitored at the appropriate time and

    responded to the particular risk. All risks which are

    relevant to this project will be managed and controlled

    within the project time, scope & cost. All identified risks

    will evaluated in order to determine the best way to

    respond to each risk to ensure compliance with these

    constraints. In extreme cases it may be necessary to allow

    flexibility to one of the projects constraints. Here time

    and scope are not flexible constrains. Otherwise it will

    affect the whole project schedule. Cost is the only flexible

    constrain which can change.

    Risk Register The risk register is a record of all identifies risks, their

    probability and impact, risk categories, mitigation

    strategies etc The risk register also will create at the

    initial step of the project. During risk management

    meeting, team will identified and categorized each risk.

    Based on identified risks and time frames in the risk

    register each risk been added to the project plan. Risk

    manager will assign a risk manager to ensure agreed

    mitigation strategy. Risk manager will provide status

    reports of assigned risks according to the planned

    timeframe.

    7.2 Risk Management Tools

    Tool Name Tool Description

    Risk Audits Risk audits examine and document the effectiveness of

    risk responses in dealing with identified risks and their

    root causes, as well as the effectiveness of the risk

    management process.

    Risk Status Report Weekly report generated by the project team to provide

    stakeholders with regular updates on risks and actions

    taken to mitigate risks.

    Status Meetings Project risk management can be an agenda item at

    periodic status meetings. That item may take no time or

  • 29 | P a g e

    a long time, depending on the risks that have been

    identified, their priority, and difficulty of response. Risk

    management becomes easier the more often it is

    practiced, and frequent discussions about risk make

    talking about risks, particularly threats, easier and more

    accurate.

    Preparing Resource Scope

    Statements

    Defines all project inputs that need to be analyzed as a

    part of the risk analysis procedure and this includes

    defining expected performance levels.

    Risk Trigger Questions Lists of situations or events in a particular area of a

    municipality that can lead to risk identification. These

    are situations or areas where risks have been discovered

    within the organization. These trigger questions may be

    grouped by areas such as performance, cost, schedule,

    software etc

    Risk Lists Usually lists of risks that have been found in similar

    municipalities and/or similar situations. Caution must

    be used when using this type of information to ensure it

    is relevant and applicable to the current situation.

    Technical Performance

    Measurement

    Technical performance measurement compares

    technical accomplishments during project execution to

    the project management plan's schedule of technical

    achievement. Deviation, such as demonstrating more or

    less functionality than planned at a milestone, can help

    to forecast the degree of success in achieving the

    project's scope.

    7.3 Data Sources

    Data Source Name Data Source Description

    Surveys Technique where lists of questions are developed to seek

    out risk in a particular area. A limitation of this method

    is that people inherently don't like to complete surveys

    and may not provide accurate information. The value of

    the surveys may be difficult to determine due to

    subjectivity in the answers or because of the focus of the

    questions themselves.

    Lessons Learned Database Project Manager maintained database with previous risk

    management documentation from earlier projects

  • 30 | P a g e

    Experiential Knowledge The collection of information that a person has obtained

    through their experience. Caution must be used when

    using any knowledge based information to ensure it is

    relevant and applicable to the current situation.

    Documented Knowledge The collection of information or data that has been

    documented about a particular subject. This is a source

    of information that provides insight into the risks in a

    particular area of concern.

    Historical Information Basically the same as documented knowledge. The

    difference is that historical information is usually widely

    accepted as fact.

    Engineering Templates A set of flow charts for various aspects of the

    development process. These templates are preliminary in

    nature and are intended as general guidance to

    accomplish a top down assessment of activities.

    7.4 Risk Categories

    Categories Description

    Schedule Risk Wrong time estimation

    Unexpected project scope expansions

    Budget Risk Wrong budget estimation

    Cost overruns

    Operational Risks

    Insufficient resources

    No proper system training

    No proper resource planning

    Less communication in team

    Technical Risks Changing requirements

    System is complex to implement

    o The number of features

    o The volume of content

    o The levels of permissions required

    o The expected volume of traffic

    o The expected number of users

    o The expected response times

  • 31 | P a g e

    Client or target environment Risk The level of internet access

    The level of interaction with the system required

    The impact of the solution on the people using it

    The quality of the equipment being used, SMS

    gateway/plug-in required etc

    Production System Risk

    The provision for support and maintenance

    The experience of the production support team

    members

    The age of the production system and versions of

    software

    The level of supporting documentation and

    training

  • 32 | P a g e

    7.5 Risk Probability and Impact

    Item Probability (P) Impact (I) Total Risk

    Score(PxI)

    Software & Hardware changes 0.8 8 6.4

    Poor schedule estimation 0.6 7 4.2

    Poor budget estimation and cost

    overruns

    0.6 7 4.2

    High response time of the system 0.6 5 3.0

    System breakdowns 0.5 10 5.0

    High volume of traffic to the system 0.5 6 3.0

    Insufficient resources 0.4 8 3.2

    Lack of communication between team

    members

    0.3 6 1.8

    Changing requirements & scope

    expansions

    0.3 7 2.1

    Employee turnover 0.3 4 1.2

    Lack of skills in selected team members 0.3 7 2.1

    Conflict between team members and

    university management

    0.2 5 1.0

    Conflicts between team members 0.2 5 1.0

    Difficulties in training university staff

    to the new system

    0.2 3 0.6

    Team member changes 0.1 3 0.3

    University not satisfy about final

    outcome

    0.1 8 0.8

    Unexpected sudden project closedown 0.1 9 0.9

    Changes in University management 0.1 4 0.4

  • 33 | P a g e

    8. HR management plan

    8.1 Project Organization

    8.1.1 Project Team

    Name Role Phone Number Email Address

    Waruna

    Kodituwakku

    Project Manager,

    System Admin

    System Architect

    +94712092875 [email protected]

    Harshani

    Wickramaarac

    hi

    Quality Assurance

    Analysis, Test

    Manager, Database

    Admin

    +94717652239 [email protected]

    Aloka Lakmali Communication

    Specialist, Web

    Developer, Help

    Desk officers

    +94774409754 alokaweerasooriya07@g

    mail.com

    Dasitha

    Wijesundara

    Business Analyst,

    Database warehouse

    Engineer

    +94718774454 [email protected]

    Shanika

    Udeshini

    HR Manager,

    Software Developer,

    Help Desk officers

    +94776786279 [email protected]

    Charaka

    Hettiaarachchi

    Accountant, Software

    Development

    Manager, Technical

    Writer

    +94714438974 [email protected]

    NimalBandara Network Engineer +94784568454 [email protected]

    Kumudu Lokuge Assistant Network

    Engineer

    +94778763944 [email protected]

    Sadishani Rangika Network Operators +94714424587 [email protected]

    Sunil de zoysa Security Specialist +94753546291 [email protected]

    Nirmal Perera User Interface

    Designer( LMS

    expertise)

    +94779752638 [email protected]

  • 34 | P a g e

    8.1.2 Organization Structure

    (For detailed Resource Allocation Plan refer Appendix C)

  • 35 | P a g e

    8.1.3 Stakeholders

    Information

    Technology

    Services

    Priyantha

    Galpaya

    Waruna

    Harshana

    Dasitha Wijeysundara

    Charaka Hettiaarachchi

    Shanika Udeshinii

    Aloka Lakmali

    Harshani Wickramarachchi

    Nimal Bandara

    Kumudu Lokuge

    Sadishani Rangika

    Nirmal Perera

    Sunil De Zoyza

    Students,

    Lecturers,

    Administra

    tive Staff

    Thomas

    Andrewson

    ChandanaIru

    galbandara

    Dr. David

    Gibson

    Role on

    Project

    Project

    Sponsor

    Chief

    Information

    Officer

    (CIO)

    Project

    Manager

    Project Team Key

    Stakeholde

    r

    Change

    Control

    Board

    Legal

    consultant

    Steering

    Committee

    Organization South East

    Gippsland

    University

    Exilesoft

    (Pvt.) Ltd.

    Exilesoft

    (Pvt.) Ltd.

    Exilesoft (Pvt.) Ltd. South East

    Gippsland

    University

    Information

    Technology

    Services

    Ruhunu

    Legal

    solutions pvt

    ltd

    South East

    Gippsland

    University

    Contact

    Information

    priyantha197

    [email protected]

    m

    vharshana

    @gmail.com

    [email protected] Itsdep.ymail

    .com

    chan24@ym

    ail.co

    davefast@ya

    hoo.com

  • 36 | P a g e

    Unique Facts Prefers use of

    email for

    project

    documents

    Responsible

    for Develop,

    maintain, and

    facilitate

    implementati

    on of a sound

    and

    integrated IT

    architecture

    as such they

    require more

    detailed

    communicati

    ons

    Manages day

    to day

    resources,

    provides

    project

    guidance and

    monitors and

    reports on the

    projects

    metrics

    Need to have a clear

    understanding of the work

    to be completed and the

    framework in which the

    project is to be executed.

    reviews

    technical

    specificatio

    ns and

    authorizes

    changes

    within the

    organization

    s

    infrastructur

    e

    Interest about

    the legal

    facet of the

    project

    Ensure that

    changes

    within the

    organization

    are effected

    in such a way

    that it

    benefits the

    organization

    as a whole

    Suggestions

    for managing

    relationships

    Keep

    informed of

    all project

    progress

    Keep all

    information

    about the

    project

    progress.

    He is the

    primary

    communicator

    for the project

    distributing

    information

    according to

    this

    Communicati

    ons

    Management

    Plan

    Require a detailed level of

    communications which is

    achieved through day to

    day interactions with the

    Project Manager and other

    team members along with

    weekly team meetings.

    Keep

    informed

    about

    current

    changes

    and can get

    feedback to

    assist the

    progress

    Technical

    design

    documents,

    user impact

    analysis and

    implementat

    ion

    strategies

    are used to

    communicat

    e with them.

    Keep

    informed

    about the

    legal facts of

    the project

    Steering

    Committee

    requires

    communicati

    on on matters

    which will

    change the

    scope of the

    project and

    its

    deliverables

  • 37 | P a g e

    8.2Resource Requirements

    0

    5

    10

    15

    20

    25M

    ay Jun

    Jul

    Au

    g

    Sep

    Oct

    No

    v

    De

    c

    Jan

    Feb

    Mar

    Ap

    r

    May Jun

    Jul

    Au

    g

    Sep

    Oct

    No

    v

    De

    c

    Jan

    Feb

    Mar

    Ap

    r

    May Jun

    Jul

    Au

    g

    Sep

    Oct

    No

    v

    De

    c

    2013 2014

    No

    of

    Emp

    loye

    es

    year/Month

    SW developer

    CIO

    SW development manager

    Technical Writer

    Security Specialist

    Test Manager

    Help Desk Officers

    Web Developer

    Data-Warehouse Eng:

    Database Admin

    Network Operator

    Assistant Network Engineer

    Network Engineer

    Business Analyst

    HR manager

    Accountant

    QA Analyst

    System Admin2012

  • 38 | P a g e

    8.3 Resource Assignment

    ID T

    ask

    Nam

    e Sub Task 1 Sub Task 2

    Waru

    na H

    ars

    han

    a

    Hars

    han

    iWath

    sala

    Alo

    kaL

    ak

    mali

    Dasi

    tha W

    ijes

    un

    dara

    Sh

    an

    ikaU

    des

    hin

    i

    Ch

    ara

    kaH

    etti

    ara

    chi

    Nim

    alB

    an

    dara

    Ku

    mu

    du

    Lok

    uge

    Sad

    ish

    an

    iRan

    gik

    a

    Su

    nil

    de

    zoysa

    Nir

    malP

    erer

    a

    1 Project Initiation and

    Planning

    1.1 Start Project

    1.2 Define Project Scope

    1.3 Project Planning

    1.3.1 Create task list

    1.3.2 Create estimates

    1.3.3 Create network diagram (PERT)

    1.3.4 Create work breakdown structure (WBS)

    1.3.5 Create schedule (GANTT)

    1.3.6 Create milestone plan

    1.3.7 Create organization plan

    1.3.8 Allocate resources

    1.3.9 Assign Roles and responsibilities

    1.4 Establish Project Environment

    1.4.1 Identify & acquire equipment and tools for the

    project

    1.4.2 Supporting Staff

  • 39 | P a g e

    1.4.3 Communication Procedure

    1.4.4 Documentation Procedure

    1.4.5 Workplace

    1.5 Develop Project Charter

    1.6 Project Charter Approved

    2 Project Monitoring and Control

    2.1 Manage Risk

    2.1.1 Monitor risks

    2.1.2 Specify responses

    2.2 Manage Human Resources

    2.2.1 Develop HR Plan

    2.2.2 Form project team

    2.2.3 Train project team

    2.2.4 Adapt team

    2.3 Manage scope / cost / schedule

    2.3.1 Monitor product changes

    2.3.2 Monitor project changes

    2.3.3 Renegotiate scope / cost / schedule

    commitments

    2.4 Manage communications

    2.4.1 Implement communications methods and

    strategies

    2.4.2 Distribute information

    2.5 Documentation

    2.5.1 Project team meetings

    2.5.2 Retain records

    2.5.3 Maintain project charter

  • 40 | P a g e

    2.5.4 document updates

    2.6 Request for proposal submitted

    2.7 Response from the client

    2.8 Manage integration

    2.8.1 Update project plan

    2.8.2 Update communications plan

    2.8.3 Update quality plan

    2.8.4 Update risk management plan

    2.8.5 Update HR plan

    2.9 Manage user acceptance

    2.10 Finalize the conformation

    from the university

    2.11 All project deliverables have been delivered

    2.11.1 project closeout

    3 Requirement Analysis and Specification

    3.1 Requirement

    Identification

    3.1.1 Prepare research instruments

    3.1.2 Interview users

    3.1.3 Draft requirements document

    Review requirements document

    Finalize requirements document

    3.2 Domain Analysis

    3.2.1 Technical feasibility

    Operational feasibility

    Economic feasibility

    Legal feasibility

  • 41 | P a g e

    3.3 Software Requirement Specification (SRS)

    3.3.1 Identify general background of the project

    3.3.2 Requirement analysis and elicitation

    3.3.3 Requirement specification

    3.4 All deliverables have been delivered

    4 Quality Management

    4.1 Develop Software Quality Management Plan

    4.1.1 Define quality criteria

    4.1.2 Define quality assessment methods

    4.2 Monitor product quality

    4.2.1 Analyze defects reported

    4.2.2 Analyze change requests submitted

    4.2.3 Analyze tests failed

    4.2.4 Analyze requirements revised

    4.4 Perform audits/ Quality Improvements

    4.5 Evaluate project quality

    5 Design

    5.1 Architectural Design

    5.1.1 Develop use cases

    5.1.2 Create data architecture

    5.1.3 Create hardware architecture

    5.2 Purchase student management system

    5.3 Design the Database

    5.3.1 Design database for sub system

    5.3.2 design central database system

    5.3.3 Provide weekly updates

    5.4 Interface Designing

  • 42 | P a g e

    5.4.1 Design user interfaces

    5.4.2 Design software interfaces

    5.4.3 Design additional plug-ins

    5.5 Develop System Architecture

    5.6 Create Software Design Specification (SDS)

    6 Implementation

    6.1 Develop Prototype with Purchased student management system

    6.2 Wireless communication

    6.2.1 Check the drawbacks of the wireless broadband

    6.2.2 Implement wireless broadband hardware &

    software

    6.2.3 Integration it to the current university network

    6.3 Develop System

    6.3.1 Develop UI

    6.3.2 Develop objects

    6.3.3 Develop workflow

    6.3.4 Develop rules

    6.3.5 Develop middle tier

    6.3.6 Develop database

    6.3.7 Develop connections with other systems

    6.3.8 Develop permissions

    6.3.9 Develop migration scripts

    6.3.10 Develop System Documentation

    6.4 IT service help desk establish

    6.5 Create User Documentation

    6.6 Implementation Completed

  • 43 | P a g e

    7 Installation

    7.1 Develop Installation Plan

    7.2 Install Software

    7.3 Database

    7.3.1 Migrate data (previous)

    7.3.2 Back up databases

    7.4 Install Hardware components

    7.5 Installation Completed

    8 Testing

    8.1 Develop Tests

    8.1.1 Develop Unit Tests

    8.1.2 Develop System Tests

    8.1.3 Develop integration tests

    8.1.4 Develop environment tests

    8.1.5 Develop migration tests

    8.2 Configure test environment

    8.3 Select Testing tools

    8.4 Execute tests

    8.4.1 Execute manual tests

    8.4.2 Execute automated tests

    8.4.3 Execute beta test

    8.4.4 Execute user acceptance test

    8.5 Analyze test results

    8.6 Compile test statistics

    8.7 Version finalized

    8.8 Version approved for deployment

    8.9 Upload current data to the system

  • 44 | P a g e

    8.10 Testing Completed

    9 Training

    9.1 Form Staff

    9.1.1 Identify project HR requirements

    9.1.2 Select staff members

    9.1.3 Recruit consultants

    9.1.4 Hire new staff

    9.2 Schedule training

    9.3 Train Staff

    9.3.1 Develop project training materials

    9.3.2 Attend business orientation

    9.3.3 Attend technical orientation

    9.3.4 Attend internal class

    9.3.5 Attend external class

    9.4 Adapt team

    9.4.1 Attend team-building activity

    9.4.2 Support remote/virtual/telecommuting work

    9.5 Training Completed

    10 Maintenance

    10.1 Perform impact analysis

    10.2 Monitor user acceptance

    10.3 Monitor performance

    10.4 Monitor defects

    10.5 Resolve training and support issues

    10.6 Resolve technical problems

    10.7 Analyze statistics

    10.8 Gather requirements for enhancements

  • 45 | P a g e

    9. Communication plan

    9.1 Stakeholder Analysis

    Information

    Technology

    Services

    Priyantha

    Galpaya

    Waruna

    Kodituwakku

    Dasitha Wijeysundara

    Charaka Hettiaarachchi

    Shanika Udeshinii

    W.L.A.T.A.Lakmali

    Harshani

    Wickckramaarachchi

    Nimal Bandara

    Kumudu Lokuge

    Sadishani Rangika

    Nirmal Perera

    Sunil De Zoyza

    Students,

    Lecturers,

    Administrative

    Staff

    Thomas

    Andrewson

    ChandanaIrug

    albandara

    Dr. David

    Gibson

    Role on

    Project

    Project

    Sponsor

    Chief

    Information

    Officer (CIO)

    Project Manager Project Team Key Stakeholder Change

    Control

    Board

    Legal

    consultant

    Steering

    Committee

    Organization South East

    Gippsland

    University

    Exilesoft (Pvt.)

    Ltd.

    Exilesoft (Pvt.)

    Ltd.

    Exilesoft (Pvt.) Ltd. South East

    Gippsland

    University

    Information

    Technology

    Services

    Ruhunu Legal

    solutions (Pvt)

    ltd

    South East

    Gippsland

    University

    Contact

    Information

    Priyantha1978

    @gmail.com

    vharshana

    @gmail.com

    itpm-group-

    [email protected]

    itsdep.ymail.c

    om

    chan24@ymai

    l.co

    davefast@yah

    oo.com

    Unique Facts Prefers use responsible for manages day to Need to have a clear reviews Interest about Ensure that

  • 46 | P a g e

    of email for

    project

    documents

    Develop,

    maintain, and

    facilitate

    implementation

    of a sound and

    integrated IT

    architecture as

    such they

    require more

    detailed

    communication

    s

    day resources,

    provides project

    guidance and

    monitors and

    reports on the

    projects metrics

    understanding of the

    work to be completed

    and the framework in

    which the project is to be

    executed.

    technical

    specifications

    and

    authorizes

    changes

    within the

    organizations

    infrastructure

    the legal facet

    of the project

    changes within

    the

    organization

    are effected in

    such a way

    that it benefits

    the

    organization

    as a whole

    Level of

    Interest

    High High High High Medium High High High

    Level of

    Influence

    High High High High Low High High High

    Suggestions

    for managing

    relationships

    Keep

    informed of

    all project

    progress

    Keep all

    information

    about the

    project

    progress.

    He is the primary

    communicator for

    the project

    distributing

    information

    according to this

    Communications

    Management Plan

    Require a detailed level

    of communications

    which is achieved

    through day to day

    interactions with the

    Project Manager and

    other team members

    along with weekly team

    meetings.

    Keep informed

    about current

    changes and can

    get feedback to

    assist the progress

    Technical

    design

    documents,

    user impact

    analysis and

    implementati

    on strategies

    are used to

    communicate

    with them.

    Keep informed

    about the legal

    facts of the

    project

    Steering

    Committee

    requires

    communicatio

    n on matters

    which will

    change the

    scope of the

    project and its

    deliverables

  • 47 | P a g e

    9.2 Project Reports

    Data Needed Frequen

    cy of

    Collectio

    n

    Responsible Party

    for Data Collection

    & Analysis

    Report Media

    & Format

    Responsible

    Party for

    Distributing

    Report

    Trend

    Analysis

    Past project

    data,Previous Status

    reports

    Monthly Project Team Printed

    document with

    calculations

    Project Manager

    Variance

    Analysis

    Proposed

    results,actual results

    Bi-

    weekly

    Project Team Through e-

    mail,

    favourable and

    adverse

    mentioned

    Project Manager

    Earned

    Value

    Analysis

    Previous

    records,estimations,

    proposed bugdet

    Monthly Project Team Printed

    copy,handed

    individually

    Project Manager

    Schedule

    Status

    Tracking Gantt Chart Bi-

    Weekly

    Project Team Status Form Project Manager

    Project

    progress

    Report

    Work has been

    completed and works

    to be completed

    through the meetings

    that have among

    project team

    Bi-

    Weekly

    Project Team Printed

    document

    Project Manager

    Project

    Status

    Report

    Status of the project

    including activities,

    progress, costs and

    issues, e-mails (sent

    by team members),

    Analyzing the

    workload

    Monthly Project Sponsor

    Project Team

    Stakeholders

    Printed

    document

    Project Manager

  • 48 | P a g e

    9.3 Project Meetings

    Purpose Frequenc

    y

    Attendees Reporting

    Requirements

    Kickoff

    Meeting

    Introduce the project team and

    the project. Review project

    objectives and management

    approach

    Once Project Sponsor,

    Project Manager,

    Project Team,

    Stakeholders, CIO

    Meeting

    Minutes

    Status

    Review

    Meeting

    Update on project status Weekly Project Manager,

    Project Team

    Meeting

    Minutes,

    variance and

    trend analysis,

    Status report

    Monthly

    Project Status

    Meetings

    Report on the status of the

    project to management

    Monthly Project Manager, PMO Monthly Status

    Report

    Project Status

    Reports

    Report the status of the project

    including activities, progress,

    costs and issues

    Monthly Project Sponsor,

    Project Team, Project

    manager, CIO,

    Stakeholders

    Project Status

    Report

    Technical

    Design

    Meeting

    Discuss and develop technical

    design solutions for the project

    As needed Project Technical staff Design

    specification

    documents,Req

    uirement

    specification

    documents

    9.4 Project Information Accessibility

    It is important to keep project information secured from outsiders and it is critical to the

    success of the project. Considering about the ASMS project of South East Gippsland

    University it is very important to keep all information in a secured place and allow access

    those information to relevant persons. So consider about those facts we are going to store all

    the information related with the ASMS project in a web site that created for the project. Team

    members and stakeholders can access that information by log in to the site to do that first they

    have to register to the site and create user accounts. Administrator of the site will grant the

    relevant privileges to the users according to their user level.

  • 49 | P a g e

    In addition to that all the documents that related to the project will be e-mailed to the project

    management group mail. For an example people who responsible to do the work allocated by

    project manager, after completing the work he can send it to the group mail. So anyone

    interest with it can access it according to their necessity.

    9.5 Communications Summary

    Stakeholder Type Communication

    Medium

    Frequency Responsible Party

    Project Sponsor

    Project Team

    Key Stakeholders

    Kickoff Meeting

    Face to Face

    Once

    Project Manager

    Project Team Project Team

    Meetings

    Face to Face

    Conference Call

    By Weekly Project Manager

    Project Technical

    Staff

    Technical Design

    Meetings

    Face to Face As Needed Project Technical Lead

    PMO(Project

    Management

    Office)

    Monthly Project

    Status Meetings

    Face to Face

    Conference Call

    Monthly Project Manager

    Project Sponsor

    Project Team

    Key Stakeholders

    PMO

    Project Status

    Reports

    Email Monthly Project Manager


Recommended