17
at the Palm Bay Parkway Southern Interchange Project Development & Environment (PD&E) Study Project Development & Environment (PD&E) Study Space Coast TPO – July 2011
Transcript
Page 1: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

at the Palm Bay Parkway Southern InterchangeProject Development & Environment (PD&E) StudyProject Development & Environment (PD&E) Study

Space Coast TPO – July 2011

Page 2: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Project Purpose & Need

System Linkage

Transportation Demand

Social & Economic Demand

Operational Capacity Operational Capacity

Safety

Emergency Response

Page 3: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Proposed Typical Sections

Micco Road

Page 4: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Alignment Alternatives 1&2

4 Alignments Considered – 2 Viable

Page 5: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Compressed Diamond Interchange AlternativeCompressed Diamond Interchange Alternative

2 Lane EB Left to I 95 NB (1000 VPH) 2 Lane EB Left to I-95 NB (1000 VPH)

8 lanes on Overpass Bridge

Least Land Area

Intersections Projected LOS “D”

Page 6: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Spread Diamond Interchange Alternative

2 Lane EB Left to I 95 NB (1000 VPH) 2 Lane EB Left to I-95 NB (1000 VPH)

6 lanes on Overpass Bridge

Most Land Area

Intersections Projected LOS “D”

Page 7: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

PARCLO Interchange Alternative

Loop Ramp to Accommodate

(1000 VPH) EB Left Turn

7 Lanes on Overpass Bridge

Land Area

< Spread Diamond < Spread Diamond

> Compressed Diamond

Intersections Projections Intersections Projections

LOS “D” (West)

LOS “B” (East)

Page 8: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Evaluation Matrix

Page 9: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Evaluation Matrix

Page 10: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Locally Preferred Alternative – Alignment 1 w/ PARCLO Interchange

Suburban Typical SectionSuburban Typical Section50 mph Design Speed50 mph Design Speed

ock

Stre

etoc

k St

reet

Bab

coB

abco

InsetInset

Micco RoadMicco Road

Page 11: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Recommended Palm Bay Parkway Typical SectionsSuburban Typical Section-50mph Design SpeedSuburban Typical Section-50mph Design Speed

Urban Typical Section-45mph Design SpeedUrban Typical Section 45mph Design Speed

Page 12: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Locally Preferred Alternative

Alignment 1 w/ PARCLO Interchange

– More Consistent with Local Comprehensive Plans

– Lower Wetland Impacts

– Slightly More Floodplain Impacts than Lowest

Alternative

– Approximately 3% more than Lowest Project Cost

– Best Traffic Service

Page 13: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Locally Preferred Alternative

Engineering Refinements

– Overall Cost $87 Million

- Palm Bay Parkway - $44.5 Million

- Interchange - $42.5 Million

– Potential ROW Donations (included above)

- Palm Bay Parkway - $5.5 Million

- Interchange - $14.8 Million

Page 14: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Environmental Evaluations

Cultural / Historical Sites

– No Impacts / SHPO Concurrence Received

Contamination Sites

– No Impacts

Floodplains

– 27 Acres of Compensating Storage Required for Floodplain Impacts

Wetlands

– 24.3 Acres of Impacts

Page 15: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Wildlife and HabitatUSFWS Coordination Ongoing

– No Affect

– Lakela’s Mint

– May Affect but not Adversely Affect

– American Alligator

– Carter’s Mustard

Chaffseed– Chaffseed

– Everglades Snail Kite

– Red Cockaded Woodpecker

– May Affect May Affect

– Audubon’s Crested Caracara

– Florida Scrub Jay

– Eastern Indigo Snake

– Wood Stork

Continued Coordination Required During Design &

Permitting

Page 16: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Current Project Status

Environmental Documents

– Submitted to FHWA on June 2 2011Submitted to FHWA on June 2, 2011

Awaiting Review Comments

Palmbayinterchange.com

Updates– Updates

Page 17: at the Palm Bay Parkway Southern Interchangeparkwaypatriots.weebly.com/uploads/2/1/4/0/2140400/...50 mph Design Speed o ck Street Babc Inset Micco Road. Recommended Palm Bay Parkway

Next Steps

Public Hearing – Late Summer / Early Fall

Finalize Study – Late 2011 / Early 2012Finalize Study – Late 2011 / Early 2012

Federal Funds Available for Final Design

ROW and Construction Phases

C l U f d d– Currently Unfunded


Recommended