August 27, 2012August 27, 2012
CTA North Main Line (Red Line) CTA North Main Line (Red Line) Station Rehabilitation Project Station Rehabilitation Project 4848thth Ward – Alderman Harry Osterman Ward – Alderman Harry Osterman
Existing Conditions
Project Overview
Public Impact
Q & A
AgendaAgenda
Trackwork & ViaductsTrackwork & Viaducts
Platforms & StationhousesPlatforms & Stationhouses
Project OverviewProject OverviewTrackwork:New waterproofing and drainage systemNew track in area of viaductRepair concrete trackbed and wall
Viaducts:Concrete repairs to station viaductsPainting/coating in viaduct areasNew, brighter lighting under viaducts
Platforms:Platform deck structure and foundation replacementPlatform fixtures, furnishings, and canopy improvementsNew customer communication system
(Excludes Lawrence)
Project OverviewProject Overview
Stationhouses:
New windows, doors and exterior lighting Exterior tuck pointing Improved station layouts New turnstiles New interior finishes (tile, floor, walls and ceiling) New signage and interior lighting Site improvements including sidewalk repairs and new bike racksSecurity camera system will be maintained and/or added
Public ImpactPublic Impact
CTA Station Closures
Street Closures / Lane Closures• Track Replacement
• Viaduct Repairs and Painting
• Streetscape
CTA Station ClosuresCTA Station Closures
CTA Station
Station Closes
Station Re-Opens
Work Complete
Thorndale August 16 September 28 November 30
Argyle August 23 October 5 December 28
Berwyn October 5 November 16 November 30
Lawrence October 14 November 25 December 28
Argyle StationArgyle Station Station Closure – August 24 – October 5Station Closure – August 24 – October 5
Full Street closures for weekend activities Full Street closures for weekend activities Thursday, August 30, 8:00 a.m. – Monday, September 3, Noon – Platform Installation Thursday, August 30, 8:00 a.m. – Monday, September 3, Noon – Platform Installation Thursday, September 6, 8:00 a.m. – Monday, September 10, Noon – Platform Installation Thursday, September 6, 8:00 a.m. – Monday, September 10, Noon – Platform Installation Thursday, September 20, Noon – Monday, September 24, Noon – Platform InstallationThursday, September 20, Noon – Monday, September 24, Noon – Platform Installation Thursday, September 27, 8:00 a.m.– Monday, October 1, Noon – Platform / Furnishing Thursday, September 27, 8:00 a.m.– Monday, October 1, Noon – Platform / Furnishing
Single Lane closures for Viaduct work Single Lane closures for Viaduct work October 4 – December 28 - East Bound traffic on Argyle will be detoured on Broadway Avenue October 4 – December 28 - East Bound traffic on Argyle will be detoured on Broadway Avenue
to Lawrence if heading north on Broadway Avenueto Lawrence if heading north on Broadway Avenue to Foster if heading south on Broadway Avenueto Foster if heading south on Broadway Avenue
Other Single Lane ClosuresOther Single Lane Closures • Foster Avenue (nightly) September 4 – September 7, 9 p.m. – 5 a.m.Foster Avenue (nightly) September 4 – September 7, 9 p.m. – 5 a.m.• Foster Avenue September 8, 9 p.m. – 9:00 a. m.Foster Avenue September 8, 9 p.m. – 9:00 a. m.
Berwyn StationBerwyn Station
Station Closure October 5 – November 16Station Closure October 5 – November 16
Full Street closures for weekend activities Full Street closures for weekend activities Thursday, August 30, 8:00 a.m. – Monday, September 3, Noon - TrackworkThursday, August 30, 8:00 a.m. – Monday, September 3, Noon - Trackwork Thursday, September 6, 8:00 a.m. – Monday, September 10, Noon - TrackworkThursday, September 6, 8:00 a.m. – Monday, September 10, Noon - Trackwork Friday, October 5, Noon – Monday, October 8, Noon – Station / Platform demolitionFriday, October 5, Noon – Monday, October 8, Noon – Station / Platform demolition Thursday, October 11, 8:00 a.m. – Monday, October 15, Noon – Platform InstallationThursday, October 11, 8:00 a.m. – Monday, October 15, Noon – Platform Installation Thursday, October 18, 8:00 a.m. – Monday, October 22, Noon – Platform InstallationThursday, October 18, 8:00 a.m. – Monday, October 22, Noon – Platform Installation Thursday, October 25, 8:00 a.m. – Monday, October 29, Noon – Platform InstallationThursday, October 25, 8:00 a.m. – Monday, October 29, Noon – Platform Installation Friday, November 1, Noon – Monday, November 5, Noon – Platform / Furnishing deliveryFriday, November 1, Noon – Monday, November 5, Noon – Platform / Furnishing delivery
Single Lane closures for Viaduct work Single Lane closures for Viaduct work August 20 – October 12 & November 16 – 30 August 20 – October 12 & November 16 – 30
West Bound traffic on Berwyn will be detoured to Foster AvenueWest Bound traffic on Berwyn will be detoured to Foster Avenue
Thorndale StationThorndale Station
Station Closure August 17– September 28Station Closure August 17– September 28
Full Street closures for weekend activities Full Street closures for weekend activities Thursday, August 30, 8:00 a.m. – Monday, September 3, Noon – Platform Installation Thursday, August 30, 8:00 a.m. – Monday, September 3, Noon – Platform Installation Thursday, September 6, 8:00 a.m. – Monday, September 10, Noon – Platform InstallationThursday, September 6, 8:00 a.m. – Monday, September 10, Noon – Platform Installation Thursday, September 20, 8:00 a.m.– Monday, September 24, Noon – Platform / Furnishing Thursday, September 20, 8:00 a.m.– Monday, September 24, Noon – Platform / Furnishing Thursday, October 18, 8:00 a.m. – Monday, October 22, Noon – TrackworkThursday, October 18, 8:00 a.m. – Monday, October 22, Noon – Trackwork
Single Lane closures for Viaduct work Single Lane closures for Viaduct work October 1 – November 30 East Bound traffic on Thorndale will be detoured on Broadway AvenueOctober 1 – November 30 East Bound traffic on Thorndale will be detoured on Broadway Avenue to Bryn Mawr if heading north on Broadway Avenueto Bryn Mawr if heading north on Broadway Avenue to Granville if heading south on Broadway Avenueto Granville if heading south on Broadway Avenue
Additional Slow Zone RemovalAdditional Slow Zone Removal Track Replacement (Full Street Closures)Track Replacement (Full Street Closures)
Granville / GlenlakeGranville / Glenlake• Friday, September 7, 8:00 a.m. – Monday, September 10, NoonFriday, September 7, 8:00 a.m. – Monday, September 10, Noon
• Thursday, October 11, 8:00 a.m. – Monday, October 15, NoonThursday, October 11, 8:00 a.m. – Monday, October 15, Noon
• Thursday, October 18, 8:00 a.m. – Monday, October 22, NoonThursday, October 18, 8:00 a.m. – Monday, October 22, Noon
Bryn MawrBryn Mawr• Thursday, October 18, 8:00 a.m. – Monday, October 22, NoonThursday, October 18, 8:00 a.m. – Monday, October 22, Noon
LawrenceLawrence• Thursday, October 18, 8:00 a.m. – Monday, October 22, Noon (tentative)Thursday, October 18, 8:00 a.m. – Monday, October 22, Noon (tentative)
• TBDTBD
RosemontRosemont• Friday, November 23, 8:00 a.m. – Monday, November 26, NoonFriday, November 23, 8:00 a.m. – Monday, November 26, Noon
• Thursday, December 6, 8:00 a.m. – Monday, December 10, NoonThursday, December 6, 8:00 a.m. – Monday, December 10, Noon
Questions & AnswersQuestions & Answers