E2SHI•
The Future Ain't What It Used to Be: What Variable Renewables Mean for
Conventional Generation
NY Association for Energy EconomicsAugust 23, 2012
Benjamin F. HobbsSchad Professor of Environmental Management, Whiting School of Engineering
Director, Environment, Energy, Sustainability & Health Institute (E2SHI)The Johns Hopkins University
Chair, Market Surveillance CommitteeCalifornia Independent System Operator
E2SHI•
Outline
I. Our goals: economy, environmentII. The challenge of variable output & pricesIII. Investment impactsIV. Why won’t the market provide needed
capacity? And how can it be fixed?
E2SHI•
A Lesson about Electricity
E2SHI•
1. Min cost / max net economic benefits
2. Min emissions & other environmental impacts
I. Fundamental Goals of Market Design
E2SHI•
K1. ?
• “a2. S
Source: Kay, 2011
Proxy Goals
• Maximizing proxies not same as maximizing fundamental efficiency & environmental objectives
E2SHI•
Renewable Portfolio Standard Policies, June 2012
29 states,+ Washington DC and 2 territories,have
Renewable Portfolio Standards
(8 states and 2 territories have
renewable portfolio goals).
Source; DSIRE, NCSU, www.dsireusa.org/summarymaps
E2SHI•
Outline
I. Our goals: economy, environmentII. The challenge of variable output & pricesIII. Investment impactsIV. Why won’t the market provide needed
capacity? And how can it be fixed?
E2SHI•
II. The Challenge of Variability:Dispatch Conventional Gen to Net Load
M. Rothleder, CAISO, Operational Flexibility Study Update, 6/22/2012 Market Surv. Comm. Mtg.
8
Load
& N
et L
oad
(MW
)
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
20,000
22,000
24,000
26,000
28,000
30,000
32,000
34,000
36,000
38,000
40,000
42,000
44,000
46,000
0:00 1:30 3:00 4:30 6:00 7:30 9:00 10:30 12:00 13:30 15:00 16:30 18:00 19:30 21:00 22:30 0:00
Load Net Load Wind Solar
Load, Wind & Solar Profiles – High Load Case, Jan. 2020
Win
d &
Sol
ar (M
W)
8,000 MW in 2 hours
6,300 MW in 2 hours
13,500 MW in 2 hours
E2SHI•
Can increase both costs and emissions• KU-Leuven stochastic unit commitment (De Jonghe, Hobbs, Belmans 2011):
■ Minimizing wind spill increases fuel costs & CO2 (relative to dispatch under 0 €/MWh wind bid)
• 17% reduction in spill possible• Per MWh of spill reduction:
0.71 t CO2 increase (+1.5% total CO2) 49 € cost increase (+1.3% total cost)
Example of Fundamental vs. Proxy Goals: Absolute Priority for Wind in Dispatch Makes
No Economic or Environmental Sense
E2SHI•
What’s Happened To Prices? Texas
David J. Maggio, ERCOT, Presentation IEEE PES, 7/2012
E2SHI•
What’s Happened to Prices? South Australia: 17% Wind
Cutler, Boerema, MacGill & Outhred, Energy Policy, 2011; I. MacGill, IEEE PES Mtg, 7/2012
• Revenue by gen type 47 $AU for wind 90 $AU for other
Load (MW) Duration Price ($/MW) Duration
Wind MW
Wind MW
E2SHI•
What Might Happen to Prices? CaliforniaCAISO 20% Penetration Study (2010)
Gas weekly MW generation
2012 Base Casevs.
20% Wind Case
Spring Energy Price Distribution
20% RPS 2.5% Lower Prices
Steam Gas CC Gas CT Gas0
10
20
30
40
% Revenue Loss under 20% RPS
Hour
E2SHI•
What Might Happen to Prices? NYISO2010 NYISO “Growing Wind” integration study
Price Duration Curve for 1275 and 8000 MW Wind Capacity(Superzones A-E)
E2SHI•
Why Revenues Diverge Among Gen Types
2000Net Load, MW
1000
timeFast 0 0 400 0 MWSlow 1000 1000 1600 2000 MWWind 600 500 200 100 MW LMP: 30 -10 70 30 $/MWh
• E.g., a system with two types of thermal generation: – 1000 MW of quick start peakers @ $70/MWh– 2100 MW of slow thermal @ $30/MWh; Max ramping = 600 MW/hr
• Morning ramp up and resulting generation:
W W
W W
Avg. Price Received$70$34.3$18.6
Spot prices reward flexibility!
E2SHI•
Outline
I. Our goals: economy, environmentII. The challenge of variable output & pricesIII. Investment impactsIV. Why won’t the market provide needed
capacity? And how can it be fixed?
E2SHI•
III. What do those Prices Imply for Long Run Generation Mix? The WECC Case
J. Bushnell, “Building Blocks: Investment in Renewable & Nonrenewable Technologies,” Iowa State U, 2010
Baseload CC Peakers
MW MW
E2SHI•
What do those Prices Imply for Long Run Generation Mix? The UK Case (15% Wind)R. Green & N. Vasilakos, Imperial College, The Long-Term Impact of Wind
Power on Electricity Prices and Generating Capacity
Wind
Peakers
CombinedCycle
Baseload
E2SHI•
CAISO: 33% Wind in 2020 Potentially 4,600MW of Upward Flexible Resources Needed (Hi-Load Scenario)
M. Rothleder, CAISO, Operational Flexibility Study Update, 6/22/2012 Market Surveillance Comm. Mtg.
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
Trajectory, Environmental, Cost, Time Constraint Cases
(1-in-2 year load, 5,688 MW of incremental DR, 5,145 MW of
Energy Efficiency)
2020 LTPP Operational Case (10% (5,500 MW) Higher Load)
2020 LTPP Operational Case(3,173 MW Local Capacity
Resources)
2018 Sensitivity Risk of Retirement Case
Capa
city
(MW
)
Generic Upward Capacity Needs to Meet Observed A/S Load Following Shortages
Local Capacity Needs (Based on LCR Studies of OTC Retirement) System Neeeds
18
E2SHI•
Outline
I. Our goals: economy, environmentII. The challenge of variable output & pricesIII. Investment impactsIV. Why won’t the market provide needed
capacity? And how can it be fixed?
E2SHI•
IV. CAISO Needs It, But Are They Getting It?
www.calpine.com/power/plant.asp?plant=28
- Announced intent to retire new (2001) CC Plant (Sutter)
- Losing 11 GW of Once-Through Cooled Capacity?
E2SHI•
Why Doesn’t the CAISO Get Its Needed Capacity?
Spot Market Failures: Markets suppress price variability
Flexibility not rewarded- 5-15-60 minute averaging times- Risk disregarded in scheduling- Public/operator distaste for price spikes
Bid & price caps
“Missing Money”
E2SHI•
Fixes?I. Operational market fixes
- Shorter intervals- Ramp constraints/products in spot markets
- MISO- CAISO: Twice as costly as spin in Q2 2012
- Stochastic unit commitment/dispatch?
II. Capacity market fixes- Different flavors of capacity- Longer horizon & liquid capacity market
E2SHI•
New York: Monthly Capacity Market
S. Harvey, S. Pope, W. Hogan, Preliminary Evaluation of the New York ISO Capacity Market, New York ISO ICAP Working Group, 7/31/2012
E2SHI•
More thanenough capacity …..
PJM Capacity Market (RPM): Eliciting Capacity Investment from Surprising Sources
Brattle, Second Performance Assessment of PJM’s Reliability Pricing Model Market Results 2007/08 through 2014/15, Aug.2011
…At prices lower than “CONE”
E2SHI•
PJM RPM: Surprising Capacity SourcesBrattle, Second Performance Assessment of PJM’s Reliability Pricing Model Market Results 2007/08 through 2014/15, Aug.2011
GainsLosses
Target
E2SHI•
Conclusions
Variable net loads and prices • Lower margins from spot energy for
thermal generation
To get an economic & clean gen mix, more revenues needed from:
• Ancillary services E.g., CAISO flexiramp
• Capacity markets E.g., PJM RPM