J 19 'J ,) G 0,ztl! ,) I BICOL SECONDARY & FEED,ER ROADS PACKAGE III PROGRESS REPORT July. 1979 DceD <i, ENGINEERING CORPORATION ---
Transcript
Page 1: BICOL SECONDARY FEED,ER ROADS

J 19 J ~ ) G 0ztl ~ ) ~ I

BICOL SECONDARY amp FEEDER ROADS PACKAGE III

PROGRESS REPORT July 1979

DceD lti ENGINEERING CORPORATION

---

MINISTRY OF PUBLIC HIGHWAYS BRBDP ROAD COMPONENT

PROJECT MANAGEMENT OFFICE

PROGRESS REPORT July 1979

DCCD ENGINEERING CORPORATION

Prepared by

ANITO R VILLAMIL Resident EnginCcr

Submitted by

TABLE OF CONTENTS

Page

1 GENERAL 1

2 PROGRESS 1

3 MISCELLANEOUS 7

4 ATTACHMENTS

A

B

C

D

PROGRESS CHARTS

CONSULTANTS STAFF

CONTRACTORS STAFF

CONTRACTORS EQUIPMENT ON SITE

MONTHLY PROGRESS REPORT July 31 1979

1 GENERAL

This report covers the adivities for the CONSTRUC-

TION SUPERVISION of the BICOL SECONDARY AND

FEEDER ROADS PROJECT Package III This

Package is composed of Subprojects i~- 8 12 amp 13

The lack of fueladverse weather condition acquili-

tion of Right-Of- Way and delayed payments have

contributed to the slippages in the progres s of

the various proj ects for which the Contractors have

submitted requests for time extension and are now

being checked reviewed and evaluated by the

Consultant

2 PROGRESS

Subproject No 7 (Sto Domingo-Bula-Ombao)

The accomplishment for the month is 681 making

a total completion to date of 48 61 The total

slippage if now 6 09 compared to last months

total of 7 7 or a rcc overy of 1 61

SR-7

Stations 21()()

Z425

31

Roadwork - On Secondary Road hauling spread-

ing and compaction of borrow between

Stas 6 I 000 and 7 I 000 continue to

correct deficiency in shoulder width

Feeder Roads - continue hauling

spreading and c ompactiun of aggregate

subbase of FR-7A between Stas a I

000 and 0 1470 Spreading of aggre-

gate subbase to final grade in progre88

at feeder roads FR-7B and FR-7C

Structur es (Box Culverts) - Conc rete has been

poured for apron wingwalls side-

walls innerwalls cut-off walls and

top slab of RCBC No2

Structures (Drainage) - Continue toasting of

RCPCls Started and continue excava-

tion for end walls of pipes laid at

Secondary and Feeder Roads The

following pipes were laid

0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia

L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc

12 pcs

L-Side Rmiddot Side

12 pcs

11 061 m dia 091 m dia 1 07 m dh 1 2L m dia

Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid

FR-7A

o 433 5 pcs (Add1 )

FR-7B

o 280 5 pcs

o 396 10 pel

o 700 5 pcs 5 pcs

FR-7C

2 024 1 pc 1 pc

1 900 9 pcs (Full length)

1 757 9 pcs (Full length)

Structures (Bridges) - Completed driving of 14 regular concrete

piles at Polpog Bridge Started cuttingdriven piles

to cut-off elevation Installation of falsework and

formwork in progress

Surface Courses amp Pavement - On Secondary Road placed 1 13064

sq m of concrete pavement between Stas 5 37850

and 5 446 00 left lane between Stas 5 225 12 and

5 41450 right lane and between Stas 5 53400 and

5 65400 left lane for a total of 1990 14 sq m of

PCC Pavement poured to date

Subproject No 12 (Iriga-Salvacion-Bato)

Based on contract amount the Contractor has accomshy

plished 071 progress since the Notice to Proceed

took effed on May lB 1979 The Contractor has

not yet submitted his corrected progress schedule

General - Laboratory equipment submitted Lythe

Contractor is 81 B complete

Roadwork - Roadway and Drainage Excavation has

started between Stas 5 400 and 9 100

with an accomplishment involving 1 968 cu

m Trimming of side s lo~ _s and ditching

in progress between said above stationo

Continue survey work for verification of

vertical control elevations

SUbproj ect No l3-A (Polangui- Lidong)

The accomplishment for the month is 73 making a

total completion to date of 63 B The total slippage

is now 229 compared to last months total of 2340

or a recovery of O 5

Roadwork - On Secondary Road work continue on excashy

vation of portions of road where material

excavated are being utilized to bring embaJkshy

ment to grade Hading spreading and

compacting aggregate subbase in progress

between Stas 2 340 and 2 640 between

Stas 2 900 and 3 900 between Stas

7 320 and 7 400 between Stas 7 440

and 7 800 between Stas 7 880 and 8

560 and between Stas 9 120 and 9 700

and aggregate base course work between

Stas 3 000 and 3 256 7 460 and 7 780

7 900 and 8 500 and 9 140 and 9 600

Feeder Roads - Continue survey work for

staking stationing and alignment Work

continue on hauling spreading and compactshy

ing of aggregate subbas c betwen Stas 0 I

400 and 1 00 at FR-13B Roadway and

Drainage Excavation is complete up to Sta

5 020 at FR-13C

Structures (Bridges) - Concrete placed for backwall and

wingwall at 2nd approach of Pintor Bridge

pile cap at 1 st approach of Pinagdapogan

Bridge and backwall at 2nd approach of

l

Mainaga Bridge Installation of rebar for

backwall at 1 st approach of Pintor Bridge

started and continuing

Structures (Culverts) - Completed placing of concrete

ior exterior sidewalls of RCBC No 1 at

feeder road FR -13 B Preparation of forms

and rebars for bottom B lab of RC Be No 2

at feeder road FR-13C in progress

Surface Courses and Pavement - Secondary Road -

Applied bituminous prime coat and placed

as phalt conc rete between Stas 0 758 and

0820 left lane and between Stas 0855

and 2 220 left and right lanes

Subproject No 13-BLidong-Buhi)

The accomplishment for the month is 43400 making a

total completion to datL of 3206 The total slippage

gt

is now 24 06

Roadwork - On Secondary Road the placing of aggregate

subbas c between Stas 13 200 and 13 500

continue with the same work going on at feeder

road FR-13G b(tw((n Stas 0 800 and Z I

200 Conlinlll11 rVly work

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 2: BICOL SECONDARY FEED,ER ROADS

MINISTRY OF PUBLIC HIGHWAYS BRBDP ROAD COMPONENT

PROJECT MANAGEMENT OFFICE

PROGRESS REPORT July 1979

DCCD ENGINEERING CORPORATION

Prepared by

ANITO R VILLAMIL Resident EnginCcr

Submitted by

TABLE OF CONTENTS

Page

1 GENERAL 1

2 PROGRESS 1

3 MISCELLANEOUS 7

4 ATTACHMENTS

A

B

C

D

PROGRESS CHARTS

CONSULTANTS STAFF

CONTRACTORS STAFF

CONTRACTORS EQUIPMENT ON SITE

MONTHLY PROGRESS REPORT July 31 1979

1 GENERAL

This report covers the adivities for the CONSTRUC-

TION SUPERVISION of the BICOL SECONDARY AND

FEEDER ROADS PROJECT Package III This

Package is composed of Subprojects i~- 8 12 amp 13

The lack of fueladverse weather condition acquili-

tion of Right-Of- Way and delayed payments have

contributed to the slippages in the progres s of

the various proj ects for which the Contractors have

submitted requests for time extension and are now

being checked reviewed and evaluated by the

Consultant

2 PROGRESS

Subproject No 7 (Sto Domingo-Bula-Ombao)

The accomplishment for the month is 681 making

a total completion to date of 48 61 The total

slippage if now 6 09 compared to last months

total of 7 7 or a rcc overy of 1 61

SR-7

Stations 21()()

Z425

31

Roadwork - On Secondary Road hauling spread-

ing and compaction of borrow between

Stas 6 I 000 and 7 I 000 continue to

correct deficiency in shoulder width

Feeder Roads - continue hauling

spreading and c ompactiun of aggregate

subbase of FR-7A between Stas a I

000 and 0 1470 Spreading of aggre-

gate subbase to final grade in progre88

at feeder roads FR-7B and FR-7C

Structur es (Box Culverts) - Conc rete has been

poured for apron wingwalls side-

walls innerwalls cut-off walls and

top slab of RCBC No2

Structures (Drainage) - Continue toasting of

RCPCls Started and continue excava-

tion for end walls of pipes laid at

Secondary and Feeder Roads The

following pipes were laid

0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia

L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc

12 pcs

L-Side Rmiddot Side

12 pcs

11 061 m dia 091 m dia 1 07 m dh 1 2L m dia

Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid

FR-7A

o 433 5 pcs (Add1 )

FR-7B

o 280 5 pcs

o 396 10 pel

o 700 5 pcs 5 pcs

FR-7C

2 024 1 pc 1 pc

1 900 9 pcs (Full length)

1 757 9 pcs (Full length)

Structures (Bridges) - Completed driving of 14 regular concrete

piles at Polpog Bridge Started cuttingdriven piles

to cut-off elevation Installation of falsework and

formwork in progress

Surface Courses amp Pavement - On Secondary Road placed 1 13064

sq m of concrete pavement between Stas 5 37850

and 5 446 00 left lane between Stas 5 225 12 and

5 41450 right lane and between Stas 5 53400 and

5 65400 left lane for a total of 1990 14 sq m of

PCC Pavement poured to date

Subproject No 12 (Iriga-Salvacion-Bato)

Based on contract amount the Contractor has accomshy

plished 071 progress since the Notice to Proceed

took effed on May lB 1979 The Contractor has

not yet submitted his corrected progress schedule

General - Laboratory equipment submitted Lythe

Contractor is 81 B complete

Roadwork - Roadway and Drainage Excavation has

started between Stas 5 400 and 9 100

with an accomplishment involving 1 968 cu

m Trimming of side s lo~ _s and ditching

in progress between said above stationo

Continue survey work for verification of

vertical control elevations

SUbproj ect No l3-A (Polangui- Lidong)

The accomplishment for the month is 73 making a

total completion to date of 63 B The total slippage

is now 229 compared to last months total of 2340

or a recovery of O 5

Roadwork - On Secondary Road work continue on excashy

vation of portions of road where material

excavated are being utilized to bring embaJkshy

ment to grade Hading spreading and

compacting aggregate subbase in progress

between Stas 2 340 and 2 640 between

Stas 2 900 and 3 900 between Stas

7 320 and 7 400 between Stas 7 440

and 7 800 between Stas 7 880 and 8

560 and between Stas 9 120 and 9 700

and aggregate base course work between

Stas 3 000 and 3 256 7 460 and 7 780

7 900 and 8 500 and 9 140 and 9 600

Feeder Roads - Continue survey work for

staking stationing and alignment Work

continue on hauling spreading and compactshy

ing of aggregate subbas c betwen Stas 0 I

400 and 1 00 at FR-13B Roadway and

Drainage Excavation is complete up to Sta

5 020 at FR-13C

Structures (Bridges) - Concrete placed for backwall and

wingwall at 2nd approach of Pintor Bridge

pile cap at 1 st approach of Pinagdapogan

Bridge and backwall at 2nd approach of

l

Mainaga Bridge Installation of rebar for

backwall at 1 st approach of Pintor Bridge

started and continuing

Structures (Culverts) - Completed placing of concrete

ior exterior sidewalls of RCBC No 1 at

feeder road FR -13 B Preparation of forms

and rebars for bottom B lab of RC Be No 2

at feeder road FR-13C in progress

Surface Courses and Pavement - Secondary Road -

Applied bituminous prime coat and placed

as phalt conc rete between Stas 0 758 and

0820 left lane and between Stas 0855

and 2 220 left and right lanes

Subproject No 13-BLidong-Buhi)

The accomplishment for the month is 43400 making a

total completion to datL of 3206 The total slippage

gt

is now 24 06

Roadwork - On Secondary Road the placing of aggregate

subbas c between Stas 13 200 and 13 500

continue with the same work going on at feeder

road FR-13G b(tw((n Stas 0 800 and Z I

200 Conlinlll11 rVly work

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 3: BICOL SECONDARY FEED,ER ROADS

TABLE OF CONTENTS

Page

1 GENERAL 1

2 PROGRESS 1

3 MISCELLANEOUS 7

4 ATTACHMENTS

A

B

C

D

PROGRESS CHARTS

CONSULTANTS STAFF

CONTRACTORS STAFF

CONTRACTORS EQUIPMENT ON SITE

MONTHLY PROGRESS REPORT July 31 1979

1 GENERAL

This report covers the adivities for the CONSTRUC-

TION SUPERVISION of the BICOL SECONDARY AND

FEEDER ROADS PROJECT Package III This

Package is composed of Subprojects i~- 8 12 amp 13

The lack of fueladverse weather condition acquili-

tion of Right-Of- Way and delayed payments have

contributed to the slippages in the progres s of

the various proj ects for which the Contractors have

submitted requests for time extension and are now

being checked reviewed and evaluated by the

Consultant

2 PROGRESS

Subproject No 7 (Sto Domingo-Bula-Ombao)

The accomplishment for the month is 681 making

a total completion to date of 48 61 The total

slippage if now 6 09 compared to last months

total of 7 7 or a rcc overy of 1 61

SR-7

Stations 21()()

Z425

31

Roadwork - On Secondary Road hauling spread-

ing and compaction of borrow between

Stas 6 I 000 and 7 I 000 continue to

correct deficiency in shoulder width

Feeder Roads - continue hauling

spreading and c ompactiun of aggregate

subbase of FR-7A between Stas a I

000 and 0 1470 Spreading of aggre-

gate subbase to final grade in progre88

at feeder roads FR-7B and FR-7C

Structur es (Box Culverts) - Conc rete has been

poured for apron wingwalls side-

walls innerwalls cut-off walls and

top slab of RCBC No2

Structures (Drainage) - Continue toasting of

RCPCls Started and continue excava-

tion for end walls of pipes laid at

Secondary and Feeder Roads The

following pipes were laid

0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia

L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc

12 pcs

L-Side Rmiddot Side

12 pcs

11 061 m dia 091 m dia 1 07 m dh 1 2L m dia

Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid

FR-7A

o 433 5 pcs (Add1 )

FR-7B

o 280 5 pcs

o 396 10 pel

o 700 5 pcs 5 pcs

FR-7C

2 024 1 pc 1 pc

1 900 9 pcs (Full length)

1 757 9 pcs (Full length)

Structures (Bridges) - Completed driving of 14 regular concrete

piles at Polpog Bridge Started cuttingdriven piles

to cut-off elevation Installation of falsework and

formwork in progress

Surface Courses amp Pavement - On Secondary Road placed 1 13064

sq m of concrete pavement between Stas 5 37850

and 5 446 00 left lane between Stas 5 225 12 and

5 41450 right lane and between Stas 5 53400 and

5 65400 left lane for a total of 1990 14 sq m of

PCC Pavement poured to date

Subproject No 12 (Iriga-Salvacion-Bato)

Based on contract amount the Contractor has accomshy

plished 071 progress since the Notice to Proceed

took effed on May lB 1979 The Contractor has

not yet submitted his corrected progress schedule

General - Laboratory equipment submitted Lythe

Contractor is 81 B complete

Roadwork - Roadway and Drainage Excavation has

started between Stas 5 400 and 9 100

with an accomplishment involving 1 968 cu

m Trimming of side s lo~ _s and ditching

in progress between said above stationo

Continue survey work for verification of

vertical control elevations

SUbproj ect No l3-A (Polangui- Lidong)

The accomplishment for the month is 73 making a

total completion to date of 63 B The total slippage

is now 229 compared to last months total of 2340

or a recovery of O 5

Roadwork - On Secondary Road work continue on excashy

vation of portions of road where material

excavated are being utilized to bring embaJkshy

ment to grade Hading spreading and

compacting aggregate subbase in progress

between Stas 2 340 and 2 640 between

Stas 2 900 and 3 900 between Stas

7 320 and 7 400 between Stas 7 440

and 7 800 between Stas 7 880 and 8

560 and between Stas 9 120 and 9 700

and aggregate base course work between

Stas 3 000 and 3 256 7 460 and 7 780

7 900 and 8 500 and 9 140 and 9 600

Feeder Roads - Continue survey work for

staking stationing and alignment Work

continue on hauling spreading and compactshy

ing of aggregate subbas c betwen Stas 0 I

400 and 1 00 at FR-13B Roadway and

Drainage Excavation is complete up to Sta

5 020 at FR-13C

Structures (Bridges) - Concrete placed for backwall and

wingwall at 2nd approach of Pintor Bridge

pile cap at 1 st approach of Pinagdapogan

Bridge and backwall at 2nd approach of

l

Mainaga Bridge Installation of rebar for

backwall at 1 st approach of Pintor Bridge

started and continuing

Structures (Culverts) - Completed placing of concrete

ior exterior sidewalls of RCBC No 1 at

feeder road FR -13 B Preparation of forms

and rebars for bottom B lab of RC Be No 2

at feeder road FR-13C in progress

Surface Courses and Pavement - Secondary Road -

Applied bituminous prime coat and placed

as phalt conc rete between Stas 0 758 and

0820 left lane and between Stas 0855

and 2 220 left and right lanes

Subproject No 13-BLidong-Buhi)

The accomplishment for the month is 43400 making a

total completion to datL of 3206 The total slippage

gt

is now 24 06

Roadwork - On Secondary Road the placing of aggregate

subbas c between Stas 13 200 and 13 500

continue with the same work going on at feeder

road FR-13G b(tw((n Stas 0 800 and Z I

200 Conlinlll11 rVly work

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 4: BICOL SECONDARY FEED,ER ROADS

MONTHLY PROGRESS REPORT July 31 1979

1 GENERAL

This report covers the adivities for the CONSTRUC-

TION SUPERVISION of the BICOL SECONDARY AND

FEEDER ROADS PROJECT Package III This

Package is composed of Subprojects i~- 8 12 amp 13

The lack of fueladverse weather condition acquili-

tion of Right-Of- Way and delayed payments have

contributed to the slippages in the progres s of

the various proj ects for which the Contractors have

submitted requests for time extension and are now

being checked reviewed and evaluated by the

Consultant

2 PROGRESS

Subproject No 7 (Sto Domingo-Bula-Ombao)

The accomplishment for the month is 681 making

a total completion to date of 48 61 The total

slippage if now 6 09 compared to last months

total of 7 7 or a rcc overy of 1 61

SR-7

Stations 21()()

Z425

31

Roadwork - On Secondary Road hauling spread-

ing and compaction of borrow between

Stas 6 I 000 and 7 I 000 continue to

correct deficiency in shoulder width

Feeder Roads - continue hauling

spreading and c ompactiun of aggregate

subbase of FR-7A between Stas a I

000 and 0 1470 Spreading of aggre-

gate subbase to final grade in progre88

at feeder roads FR-7B and FR-7C

Structur es (Box Culverts) - Conc rete has been

poured for apron wingwalls side-

walls innerwalls cut-off walls and

top slab of RCBC No2

Structures (Drainage) - Continue toasting of

RCPCls Started and continue excava-

tion for end walls of pipes laid at

Secondary and Feeder Roads The

following pipes were laid

0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia

L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc

12 pcs

L-Side Rmiddot Side

12 pcs

11 061 m dia 091 m dia 1 07 m dh 1 2L m dia

Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid

FR-7A

o 433 5 pcs (Add1 )

FR-7B

o 280 5 pcs

o 396 10 pel

o 700 5 pcs 5 pcs

FR-7C

2 024 1 pc 1 pc

1 900 9 pcs (Full length)

1 757 9 pcs (Full length)

Structures (Bridges) - Completed driving of 14 regular concrete

piles at Polpog Bridge Started cuttingdriven piles

to cut-off elevation Installation of falsework and

formwork in progress

Surface Courses amp Pavement - On Secondary Road placed 1 13064

sq m of concrete pavement between Stas 5 37850

and 5 446 00 left lane between Stas 5 225 12 and

5 41450 right lane and between Stas 5 53400 and

5 65400 left lane for a total of 1990 14 sq m of

PCC Pavement poured to date

Subproject No 12 (Iriga-Salvacion-Bato)

Based on contract amount the Contractor has accomshy

plished 071 progress since the Notice to Proceed

took effed on May lB 1979 The Contractor has

not yet submitted his corrected progress schedule

General - Laboratory equipment submitted Lythe

Contractor is 81 B complete

Roadwork - Roadway and Drainage Excavation has

started between Stas 5 400 and 9 100

with an accomplishment involving 1 968 cu

m Trimming of side s lo~ _s and ditching

in progress between said above stationo

Continue survey work for verification of

vertical control elevations

SUbproj ect No l3-A (Polangui- Lidong)

The accomplishment for the month is 73 making a

total completion to date of 63 B The total slippage

is now 229 compared to last months total of 2340

or a recovery of O 5

Roadwork - On Secondary Road work continue on excashy

vation of portions of road where material

excavated are being utilized to bring embaJkshy

ment to grade Hading spreading and

compacting aggregate subbase in progress

between Stas 2 340 and 2 640 between

Stas 2 900 and 3 900 between Stas

7 320 and 7 400 between Stas 7 440

and 7 800 between Stas 7 880 and 8

560 and between Stas 9 120 and 9 700

and aggregate base course work between

Stas 3 000 and 3 256 7 460 and 7 780

7 900 and 8 500 and 9 140 and 9 600

Feeder Roads - Continue survey work for

staking stationing and alignment Work

continue on hauling spreading and compactshy

ing of aggregate subbas c betwen Stas 0 I

400 and 1 00 at FR-13B Roadway and

Drainage Excavation is complete up to Sta

5 020 at FR-13C

Structures (Bridges) - Concrete placed for backwall and

wingwall at 2nd approach of Pintor Bridge

pile cap at 1 st approach of Pinagdapogan

Bridge and backwall at 2nd approach of

l

Mainaga Bridge Installation of rebar for

backwall at 1 st approach of Pintor Bridge

started and continuing

Structures (Culverts) - Completed placing of concrete

ior exterior sidewalls of RCBC No 1 at

feeder road FR -13 B Preparation of forms

and rebars for bottom B lab of RC Be No 2

at feeder road FR-13C in progress

Surface Courses and Pavement - Secondary Road -

Applied bituminous prime coat and placed

as phalt conc rete between Stas 0 758 and

0820 left lane and between Stas 0855

and 2 220 left and right lanes

Subproject No 13-BLidong-Buhi)

The accomplishment for the month is 43400 making a

total completion to datL of 3206 The total slippage

gt

is now 24 06

Roadwork - On Secondary Road the placing of aggregate

subbas c between Stas 13 200 and 13 500

continue with the same work going on at feeder

road FR-13G b(tw((n Stas 0 800 and Z I

200 Conlinlll11 rVly work

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 5: BICOL SECONDARY FEED,ER ROADS

SR-7

Stations 21()()

Z425

31

Roadwork - On Secondary Road hauling spread-

ing and compaction of borrow between

Stas 6 I 000 and 7 I 000 continue to

correct deficiency in shoulder width

Feeder Roads - continue hauling

spreading and c ompactiun of aggregate

subbase of FR-7A between Stas a I

000 and 0 1470 Spreading of aggre-

gate subbase to final grade in progre88

at feeder roads FR-7B and FR-7C

Structur es (Box Culverts) - Conc rete has been

poured for apron wingwalls side-

walls innerwalls cut-off walls and

top slab of RCBC No2

Structures (Drainage) - Continue toasting of

RCPCls Started and continue excava-

tion for end walls of pipes laid at

Secondary and Feeder Roads The

following pipes were laid

0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia

L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc

12 pcs

L-Side Rmiddot Side

12 pcs

11 061 m dia 091 m dia 1 07 m dh 1 2L m dia

Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid

FR-7A

o 433 5 pcs (Add1 )

FR-7B

o 280 5 pcs

o 396 10 pel

o 700 5 pcs 5 pcs

FR-7C

2 024 1 pc 1 pc

1 900 9 pcs (Full length)

1 757 9 pcs (Full length)

Structures (Bridges) - Completed driving of 14 regular concrete

piles at Polpog Bridge Started cuttingdriven piles

to cut-off elevation Installation of falsework and

formwork in progress

Surface Courses amp Pavement - On Secondary Road placed 1 13064

sq m of concrete pavement between Stas 5 37850

and 5 446 00 left lane between Stas 5 225 12 and

5 41450 right lane and between Stas 5 53400 and

5 65400 left lane for a total of 1990 14 sq m of

PCC Pavement poured to date

Subproject No 12 (Iriga-Salvacion-Bato)

Based on contract amount the Contractor has accomshy

plished 071 progress since the Notice to Proceed

took effed on May lB 1979 The Contractor has

not yet submitted his corrected progress schedule

General - Laboratory equipment submitted Lythe

Contractor is 81 B complete

Roadwork - Roadway and Drainage Excavation has

started between Stas 5 400 and 9 100

with an accomplishment involving 1 968 cu

m Trimming of side s lo~ _s and ditching

in progress between said above stationo

Continue survey work for verification of

vertical control elevations

SUbproj ect No l3-A (Polangui- Lidong)

The accomplishment for the month is 73 making a

total completion to date of 63 B The total slippage

is now 229 compared to last months total of 2340

or a recovery of O 5

Roadwork - On Secondary Road work continue on excashy

vation of portions of road where material

excavated are being utilized to bring embaJkshy

ment to grade Hading spreading and

compacting aggregate subbase in progress

between Stas 2 340 and 2 640 between

Stas 2 900 and 3 900 between Stas

7 320 and 7 400 between Stas 7 440

and 7 800 between Stas 7 880 and 8

560 and between Stas 9 120 and 9 700

and aggregate base course work between

Stas 3 000 and 3 256 7 460 and 7 780

7 900 and 8 500 and 9 140 and 9 600

Feeder Roads - Continue survey work for

staking stationing and alignment Work

continue on hauling spreading and compactshy

ing of aggregate subbas c betwen Stas 0 I

400 and 1 00 at FR-13B Roadway and

Drainage Excavation is complete up to Sta

5 020 at FR-13C

Structures (Bridges) - Concrete placed for backwall and

wingwall at 2nd approach of Pintor Bridge

pile cap at 1 st approach of Pinagdapogan

Bridge and backwall at 2nd approach of

l

Mainaga Bridge Installation of rebar for

backwall at 1 st approach of Pintor Bridge

started and continuing

Structures (Culverts) - Completed placing of concrete

ior exterior sidewalls of RCBC No 1 at

feeder road FR -13 B Preparation of forms

and rebars for bottom B lab of RC Be No 2

at feeder road FR-13C in progress

Surface Courses and Pavement - Secondary Road -

Applied bituminous prime coat and placed

as phalt conc rete between Stas 0 758 and

0820 left lane and between Stas 0855

and 2 220 left and right lanes

Subproject No 13-BLidong-Buhi)

The accomplishment for the month is 43400 making a

total completion to datL of 3206 The total slippage

gt

is now 24 06

Roadwork - On Secondary Road the placing of aggregate

subbas c between Stas 13 200 and 13 500

continue with the same work going on at feeder

road FR-13G b(tw((n Stas 0 800 and Z I

200 Conlinlll11 rVly work

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 6: BICOL SECONDARY FEED,ER ROADS

11 061 m dia 091 m dia 1 07 m dh 1 2L m dia

Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid

FR-7A

o 433 5 pcs (Add1 )

FR-7B

o 280 5 pcs

o 396 10 pel

o 700 5 pcs 5 pcs

FR-7C

2 024 1 pc 1 pc

1 900 9 pcs (Full length)

1 757 9 pcs (Full length)

Structures (Bridges) - Completed driving of 14 regular concrete

piles at Polpog Bridge Started cuttingdriven piles

to cut-off elevation Installation of falsework and

formwork in progress

Surface Courses amp Pavement - On Secondary Road placed 1 13064

sq m of concrete pavement between Stas 5 37850

and 5 446 00 left lane between Stas 5 225 12 and

5 41450 right lane and between Stas 5 53400 and

5 65400 left lane for a total of 1990 14 sq m of

PCC Pavement poured to date

Subproject No 12 (Iriga-Salvacion-Bato)

Based on contract amount the Contractor has accomshy

plished 071 progress since the Notice to Proceed

took effed on May lB 1979 The Contractor has

not yet submitted his corrected progress schedule

General - Laboratory equipment submitted Lythe

Contractor is 81 B complete

Roadwork - Roadway and Drainage Excavation has

started between Stas 5 400 and 9 100

with an accomplishment involving 1 968 cu

m Trimming of side s lo~ _s and ditching

in progress between said above stationo

Continue survey work for verification of

vertical control elevations

SUbproj ect No l3-A (Polangui- Lidong)

The accomplishment for the month is 73 making a

total completion to date of 63 B The total slippage

is now 229 compared to last months total of 2340

or a recovery of O 5

Roadwork - On Secondary Road work continue on excashy

vation of portions of road where material

excavated are being utilized to bring embaJkshy

ment to grade Hading spreading and

compacting aggregate subbase in progress

between Stas 2 340 and 2 640 between

Stas 2 900 and 3 900 between Stas

7 320 and 7 400 between Stas 7 440

and 7 800 between Stas 7 880 and 8

560 and between Stas 9 120 and 9 700

and aggregate base course work between

Stas 3 000 and 3 256 7 460 and 7 780

7 900 and 8 500 and 9 140 and 9 600

Feeder Roads - Continue survey work for

staking stationing and alignment Work

continue on hauling spreading and compactshy

ing of aggregate subbas c betwen Stas 0 I

400 and 1 00 at FR-13B Roadway and

Drainage Excavation is complete up to Sta

5 020 at FR-13C

Structures (Bridges) - Concrete placed for backwall and

wingwall at 2nd approach of Pintor Bridge

pile cap at 1 st approach of Pinagdapogan

Bridge and backwall at 2nd approach of

l

Mainaga Bridge Installation of rebar for

backwall at 1 st approach of Pintor Bridge

started and continuing

Structures (Culverts) - Completed placing of concrete

ior exterior sidewalls of RCBC No 1 at

feeder road FR -13 B Preparation of forms

and rebars for bottom B lab of RC Be No 2

at feeder road FR-13C in progress

Surface Courses and Pavement - Secondary Road -

Applied bituminous prime coat and placed

as phalt conc rete between Stas 0 758 and

0820 left lane and between Stas 0855

and 2 220 left and right lanes

Subproject No 13-BLidong-Buhi)

The accomplishment for the month is 43400 making a

total completion to datL of 3206 The total slippage

gt

is now 24 06

Roadwork - On Secondary Road the placing of aggregate

subbas c between Stas 13 200 and 13 500

continue with the same work going on at feeder

road FR-13G b(tw((n Stas 0 800 and Z I

200 Conlinlll11 rVly work

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 7: BICOL SECONDARY FEED,ER ROADS

Subproject No 12 (Iriga-Salvacion-Bato)

Based on contract amount the Contractor has accomshy

plished 071 progress since the Notice to Proceed

took effed on May lB 1979 The Contractor has

not yet submitted his corrected progress schedule

General - Laboratory equipment submitted Lythe

Contractor is 81 B complete

Roadwork - Roadway and Drainage Excavation has

started between Stas 5 400 and 9 100

with an accomplishment involving 1 968 cu

m Trimming of side s lo~ _s and ditching

in progress between said above stationo

Continue survey work for verification of

vertical control elevations

SUbproj ect No l3-A (Polangui- Lidong)

The accomplishment for the month is 73 making a

total completion to date of 63 B The total slippage

is now 229 compared to last months total of 2340

or a recovery of O 5

Roadwork - On Secondary Road work continue on excashy

vation of portions of road where material

excavated are being utilized to bring embaJkshy

ment to grade Hading spreading and

compacting aggregate subbase in progress

between Stas 2 340 and 2 640 between

Stas 2 900 and 3 900 between Stas

7 320 and 7 400 between Stas 7 440

and 7 800 between Stas 7 880 and 8

560 and between Stas 9 120 and 9 700

and aggregate base course work between

Stas 3 000 and 3 256 7 460 and 7 780

7 900 and 8 500 and 9 140 and 9 600

Feeder Roads - Continue survey work for

staking stationing and alignment Work

continue on hauling spreading and compactshy

ing of aggregate subbas c betwen Stas 0 I

400 and 1 00 at FR-13B Roadway and

Drainage Excavation is complete up to Sta

5 020 at FR-13C

Structures (Bridges) - Concrete placed for backwall and

wingwall at 2nd approach of Pintor Bridge

pile cap at 1 st approach of Pinagdapogan

Bridge and backwall at 2nd approach of

l

Mainaga Bridge Installation of rebar for

backwall at 1 st approach of Pintor Bridge

started and continuing

Structures (Culverts) - Completed placing of concrete

ior exterior sidewalls of RCBC No 1 at

feeder road FR -13 B Preparation of forms

and rebars for bottom B lab of RC Be No 2

at feeder road FR-13C in progress

Surface Courses and Pavement - Secondary Road -

Applied bituminous prime coat and placed

as phalt conc rete between Stas 0 758 and

0820 left lane and between Stas 0855

and 2 220 left and right lanes

Subproject No 13-BLidong-Buhi)

The accomplishment for the month is 43400 making a

total completion to datL of 3206 The total slippage

gt

is now 24 06

Roadwork - On Secondary Road the placing of aggregate

subbas c between Stas 13 200 and 13 500

continue with the same work going on at feeder

road FR-13G b(tw((n Stas 0 800 and Z I

200 Conlinlll11 rVly work

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 8: BICOL SECONDARY FEED,ER ROADS

excavated are being utilized to bring embaJkshy

ment to grade Hading spreading and

compacting aggregate subbase in progress

between Stas 2 340 and 2 640 between

Stas 2 900 and 3 900 between Stas

7 320 and 7 400 between Stas 7 440

and 7 800 between Stas 7 880 and 8

560 and between Stas 9 120 and 9 700

and aggregate base course work between

Stas 3 000 and 3 256 7 460 and 7 780

7 900 and 8 500 and 9 140 and 9 600

Feeder Roads - Continue survey work for

staking stationing and alignment Work

continue on hauling spreading and compactshy

ing of aggregate subbas c betwen Stas 0 I

400 and 1 00 at FR-13B Roadway and

Drainage Excavation is complete up to Sta

5 020 at FR-13C

Structures (Bridges) - Concrete placed for backwall and

wingwall at 2nd approach of Pintor Bridge

pile cap at 1 st approach of Pinagdapogan

Bridge and backwall at 2nd approach of

l

Mainaga Bridge Installation of rebar for

backwall at 1 st approach of Pintor Bridge

started and continuing

Structures (Culverts) - Completed placing of concrete

ior exterior sidewalls of RCBC No 1 at

feeder road FR -13 B Preparation of forms

and rebars for bottom B lab of RC Be No 2

at feeder road FR-13C in progress

Surface Courses and Pavement - Secondary Road -

Applied bituminous prime coat and placed

as phalt conc rete between Stas 0 758 and

0820 left lane and between Stas 0855

and 2 220 left and right lanes

Subproject No 13-BLidong-Buhi)

The accomplishment for the month is 43400 making a

total completion to datL of 3206 The total slippage

gt

is now 24 06

Roadwork - On Secondary Road the placing of aggregate

subbas c between Stas 13 200 and 13 500

continue with the same work going on at feeder

road FR-13G b(tw((n Stas 0 800 and Z I

200 Conlinlll11 rVly work

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 9: BICOL SECONDARY FEED,ER ROADS

l

Mainaga Bridge Installation of rebar for

backwall at 1 st approach of Pintor Bridge

started and continuing

Structures (Culverts) - Completed placing of concrete

ior exterior sidewalls of RCBC No 1 at

feeder road FR -13 B Preparation of forms

and rebars for bottom B lab of RC Be No 2

at feeder road FR-13C in progress

Surface Courses and Pavement - Secondary Road -

Applied bituminous prime coat and placed

as phalt conc rete between Stas 0 758 and

0820 left lane and between Stas 0855

and 2 220 left and right lanes

Subproject No 13-BLidong-Buhi)

The accomplishment for the month is 43400 making a

total completion to datL of 3206 The total slippage

gt

is now 24 06

Roadwork - On Secondary Road the placing of aggregate

subbas c between Stas 13 200 and 13 500

continue with the same work going on at feeder

road FR-13G b(tw((n Stas 0 800 and Z I

200 Conlinlll11 rVly work

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 10: BICOL SECONDARY FEED,ER ROADS

11

S~ructures (Bridges) - Placed concrete for girders

at Araga Bridge Erection of formworks

and installation of rebars for top slap for

the same bridge going on

Structures (Box Culverts) - Continue excavation for

foundations of RCBCls Nos 4 5 and 6

Structures (Drainage) - Continue fabrication of Repels

Excavation for pipes continue and the

following pipes laid

SR-13B 061 m dia 091 m dia

Stations L-Side R-Side L-Side R-Side

14 300 6 pcs

14 750 4 pcs 4 pcs

18 260 7 pcs 7 pcs

FR-13G

0 085 6 pcs S pcs

o 520 5 pcs 5 pcs

1 280 5 pcs 6 pcs

MISCELLANEOUS

Subproject No B The Composite Management Group has

awarded the project to Capitol Industrial Construction

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 11: BICOL SECONDARY FEED,ER ROADS

~

Group and a contract will be prepared by the Projec

Management Office at Naga City

Subproject No 12 The Project Manager of the

Cunsultants called a llleeting with the Contractor on

July 12 1979 at the DCCD Engineering Corporation

Makati Offic e and the Contractor was warned that

unless satisfactory progress is shown Jefore 25

of the cuntract time (xpires the Consultants will

recommend to the Government implementation of

Article 808 Df toe Standard Specifications for Highshy

ways and Bridges Further a meeting was also held

betwlen the P1oj cct Managlr of the Consultants and

the Contr~ctors at the jobsite in Camarines Sur on

July 18 1979 wherein problCms of management

finances and equipment were clarified with the Contractor

promising immediatC resolution of the defirlencies cited

and exerting lxtra effort to lnak( up f(lr the slow activity

which is causing delayed progress

Subproject No 13-A The Consultants has written the

Contractor inviting attention to tillt slippagcs and in a

lllllIing wilh I Ill Proitd Mmlglr of till Consultants the

Contractor was told to take th~ necessary action and exert

lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 12: BICOL SECONDARY FEED,ER ROADS

J

slippages

Subprojed No 13-B The Contractor was called to

a meeting at the jobsite on July 25 1979 wherein

the Cunsulta1ls stressed their concern about th

delayed progrCss causing increasing slippage The

Contractor was wa rned that unles s immediate mc~shy

sures were taken to stop further slippage und to put

more effort tu make up for the existing slippage the

Consultants will rccommCnd rescission of their

CONTRACT This warning was put in writing addressed

to the CONTRACTOR in a letter dated July 26 1979

The Contractor admitted some financial difficulties

which he claims has now cas ed and will exert extra

lttention and effort to increase his accomplishment

Two meetings one on June 14 1979 and the latest on

July 17 1979 betwcCn all the Contractors of the onshy

going projects and lhe Consultants were called by the

Project Manager uf the Consultants to emphasize the

growing conClrn for the Contractors slow progress

and disCUSStd uplratiuns prubltllls that might bl adding

to delays in prugress Causes uf delays in progress

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 13: BICOL SECONDARY FEED,ER ROADS

lQ

esb 72779

have been submitted for evaluation and the Contractors

also promised to accelerate their operation with the

ea sing situ ation

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 14: BICOL SECONDARY FEED,ER ROADS

CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I

APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----

PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---

~IIJ LampJ IampJ I- 1-1-

s~ UIIJ 1978 i T E M ~a3 ILIJ

~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO

J J A S 0 N 0 J I ()

GENERAL 65 1 tT_ 7~ E ~ 82

I 15 556 08 56 516 Iamp ~ra l 16 5~

I- --r-1 amp I~ 119 2 115 3~

II EARTHWORK 465 94 456 9 2~ 2fi 314 -

44-3r~ II 21 14 III BASE COURSE 79

---

SURFACE COURSES 15

IV AND PAVEMENT 1

220r2 40

3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7

VI INCIDENTAL CONSTRUCTION 06 00 00

TOTAL looj I ------

~ PROGRESS

) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -

J -

L V ------ -1- 5 SCHEDULEC 867

~ [Report ~ COMPLETION ~ Illonth Flat ~

previoul

Th riod

LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 15: BICOL SECONDARY FEED,ER ROADS

- middotAt - a

In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19

~KAGE III - PREPARED IV JUANITO R VILLAMIL RE

ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT

ESS CHA RT CURRENT ESTIMmEO FINAL COST

1amp1 1amp1

197 9~ 198 0 ~ ~ a

S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--

--

ltoo e 14 a ~ 9 b 913 ~ ~ lJ

~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i

~ -

91 100 419 sl5 ~ 91

~13 f 6~ 69 8 ~r14 middot80-

214 ~3 S[I 1100

- I-

I 2 lo 3[1 414

13 4 2- 71 70-

9 13 lioo _

1 0[8 lio 1j8

60-

719 fig 91s 100 ~~ e E~

i 213 215 3 f -34 415 418 51

50-I

I

IS ~12 100 1 I

r n

40- - r-l --

11

30-

f I

middot~O-

- - -- bull f- 10-- - _-

-~

-

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 16: BICOL SECONDARY FEED,ER ROADS

CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A

I

OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d

i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980

I

I- -I -I i

~-I

I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~

I

8 ~o 0 J J A S 0 N 0 J F

II ~7 sk 85 bull I GENERAL 525 8723 458

lIS

P I~ 9 14

EARTHWORK 5317 6901 3669 14 116 312

III SURFACE COURSES 2575 699

AND PAVEMENT 180

b 0 5 IV STRUCTURES 1583 3500 5 54

I a

TOTAL 1000

PROGRESS j

Scheduled

)~

gt-Actual

ACTUAL I

4861 I

I I ~

~5 ~

~

SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag

~

vIoue ~

nl periN

f LEGEND -- ORIGINAL SCHEDUlED PROGRESS

----~------ ACTUAL p~SS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 17: BICOL SECONDARY FEED,ER ROADS

AtfaChmnt A-I

~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979

~~E III PREPARED BY JUAN ITO R VILLAMIL RE

UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT

5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390

CURRENT ESTIMATED FINAL COST

III 19 B 0

197 9 ~ t I 2 I

0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO

10 J rr E 17 EI7 815 SIS EI7 ~~

90-7 19 8 9 14 917 JbO

H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI

418 5~ 612 613 613 [I 80-

p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~

[2 2 2 l 70-

15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A

Ie 13 13 13 17 i9 5L 60-

lI ~o-

V I

l-L

I

40-

v

[ ~o-

---- -I I I

If 20--

I

V

~ 10-

0-

~

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 18: BICOL SECONDARY FEED,ER ROADS

CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~

ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-

APPROVED REVISED COMPLETION DATE PROGRE~

PROBABLE COMPLETION DATE JANUARY 5 1980

~ ~ ~~

~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI

t~ o~ zgt Dto 8 Q u J J A S 0 N l) J

4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075

f7ij r~ 26 8

0 001 4 18 17

EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145

III BASE COURSE 892 000 000

IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT

0 OI~ 1 4 V STRUCTURES 3217 2027 f 52

096 2 06 ~

VI INCIDENTAL CONSTRUCTION 005 000 000

TOTAL 1000

PROGRESS

Scheduled [Adaa l~

~ ACTUAL 320euro

1

- ~ --- ~ I~ -e 5

SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~

Previous Thl period

LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 19: BICOL SECONDARY FEED,ER ROADS

I bull bull Att _ bull A-I

~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979

~AGE III PREPARED BY JUAN ITO R VILLAMIL RE

trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO

IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT

ESS CH ART CURRENT ESTIMATED FINAL COST

~

197 9_~ 198 0 ILl

~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A

90 96 A ~ 100-

e ~ 72 74 77 80 82 815 87 93 7 I]

26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-

17 26 35 53 71 80 85 -lI

31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~

80-

I

V 70-P 15 31 46 62 77 100

I rl

60-4 7 25 42 58 11 83 etr 910 96 100

L r 5 1183 1358 I~ 85 I~ 51 1746fC 27

- 50- 10 40 100

11

40- 1

-I 30-

V

r--_ ---_ 20-

1- 1 I ~

10-

I 0-

~

-

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 20: BICOL SECONDARY FEED,ER ROADS

Attachment B

DCCD ENGINEERING CORPORATION

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

CONSULTANTS STAFF As of July 31 1979

CONSULTANT TECHNICAL STAFF

Key Staff

1 2 3

Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr

Support Staff

1 2 3 4 5 6 7

Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen

1 1 4

3 6 1 3 8 3 2

ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL

1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2

T o T 1 L bull bull bull bull bull

6

26

19

51 vv

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 21: BICOL SECONDARY FEED,ER ROADS

Attachment C

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

10

Suberoj cd No 7 (St~ Dominao-Bula-Ombao)

CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC

As of July 31 1979

Supervising Project Manager

Project ManagLr 1

Engin eers 3

SurveyorsAides 6

Super intendents For em en 5

AdministrativeAccounting 9

Skilled Laborerb 66

Unskilled Laborers 77

Timekeeper 3

Security Guards 5

T o T A L

176

176 vvv

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 22: BICOL SECONDARY FEED,ER ROADS

Attachment C - 1

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

Subproject No 12 (Iriga-Salvacion-Bato)

CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

Project Manager 1

Resident Manager 1

SuperintendentForeman

AdministrativeAccounting 9

Skilled Laborers 7

Unskilled Laborers 8

T o T A L

28

28 vv

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 23: BICOL SECONDARY FEED,ER ROADS

Attachment C - 2

BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

9

Subproj ect No 13 -A (Polangui- LidongJ

CONTRACTORS STAFF WILLIAM UY-CONTRACTOR

As of July 31 1979

Project Manager 1

Engineers 2

SuperintendentsForemen 5

Surveyors Aides 13

AdministrativeAccounting 11

Skilled Laborers 48

Unskilled Laborers 74

Timekeeper 2

Security Gua rds 10

T o T A L

166

166 vvv

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 24: BICOL SECONDARY FEED,ER ROADS

Attachment C - 3

BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III

1

2

3

4

5

6

7

8

Subproject No 13-B (Lidong-Buhi)

CONTRACTORS STAFF JPY CONSTRUCTION

As of July 31 1979

Engineers 1

SurveyorsAides 3

SuperintendentsForemen 5

AdministrativeAccounting 2

Skilled Laborers 28

Unskilled Laborers 56

Timekeeper 3

Security Guards 2

T o T A L

100

100 vvv

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 25: BICOL SECONDARY FEED,ER ROADS

Attachment D

CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC

As of July 31 1979

NO OF EQUIPMENT DESCRIJTION UNITS

1 Bulldozers DB 1 D6 1 DBSA 1

2 Dump Trucks Isuzu 2

3 Payloader Komatsu 1

4 Roadgrader Mitsubishi 1

5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1

6 Vibratory Roller 1

7 Transit Mixers 4

8 Concrete Mixers 2-baggers 1

9 Crawler Crane 1

10 Concrete Vibrator 2

11 Water Truck 1

12 Welding Machine 1

13 Steam Hammer Kobe 32 1

14 Water Pump 3 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull

TOTAL

3

2

1

1

2

1

4

1

1

2

1

1

1

1

22 vv

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 26: BICOL SECONDARY FEED,ER ROADS

Attachment D - 1

CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS

l Bulldozers DfE 3 1

D7 1 1

D8 1 1 (idle)

TD25 1

2 Dump Trucks Isuzu 12 3

3 Haulers Tournapulls 2 2

Euclid 1 1

4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1

5 Roadgraders Komatsu 1 Mitsubishi 1

6 Steel Roller Buffalo Tandem 1 Tandem 1

7 Pneumatic Wobble Watanabe 1 Sakai 1

lRental

8 As phalt Paver 1

9 Vibratory Roller Dynapae 1

10 Water Pump 2 Kohler 3 WiscoDsin 4 1

Sub-total

TOTAL

9

15

6

4

Z

2

3

1

1

4

47

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 27: BICOL SECONDARY FEED,ER ROADS

CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot

Attachment D - 2

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bulldozers DSOA l(idle) 1 2

2 Dump Trucks Isuzu 7 7

3 Payloader Komatsu 1 1 Z

4 Roadgrader Mitsubishi 1 1

5 Pneumatic Roller Watanabe Z Z

6 Steel Roller Tandem Z Z

7 Sheepfoot Roller with Tractor l(idle) 1

S Water Truck Isuzu Rheo 1 1

9 Backhoe Poclain 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv

Under Repair

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 28: BICOL SECONDARY FEED,ER ROADS

(William Uy- Contractor) page 2 - Equipment on Site

Carried Forward bullbull bull bull bull bull bull bull 47

11 Concrete Mixer

12 Concrete Vibrator

13 Cranes

14 Water Truck

15 Asphalt Paver

One-bagger Transit Mixer

Lorrain13 PampH

Isuzu wi sprinkle

3 1

2

1 1

1

1

4

2

2

1

1

TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv

~cUnder Repair

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v

Page 29: BICOL SECONDARY FEED,ER ROADS

Attachment D - 3

CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC

As of July 31 1979

NO OF EQUIPMENT DESCRIPTION UNITS TOTAL

1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2

2 Roadgrader Galion 1 1

3 Steel RoUer Galion 1 1

TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v


Recommended