J 19 J ~ ) G 0ztl ~ ) ~ I
BICOL SECONDARY amp FEEDER ROADS PACKAGE III
PROGRESS REPORT July 1979
DceD lti ENGINEERING CORPORATION
---
MINISTRY OF PUBLIC HIGHWAYS BRBDP ROAD COMPONENT
PROJECT MANAGEMENT OFFICE
PROGRESS REPORT July 1979
DCCD ENGINEERING CORPORATION
Prepared by
ANITO R VILLAMIL Resident EnginCcr
Submitted by
TABLE OF CONTENTS
Page
1 GENERAL 1
2 PROGRESS 1
3 MISCELLANEOUS 7
4 ATTACHMENTS
A
B
C
D
PROGRESS CHARTS
CONSULTANTS STAFF
CONTRACTORS STAFF
CONTRACTORS EQUIPMENT ON SITE
MONTHLY PROGRESS REPORT July 31 1979
1 GENERAL
This report covers the adivities for the CONSTRUC-
TION SUPERVISION of the BICOL SECONDARY AND
FEEDER ROADS PROJECT Package III This
Package is composed of Subprojects i~- 8 12 amp 13
The lack of fueladverse weather condition acquili-
tion of Right-Of- Way and delayed payments have
contributed to the slippages in the progres s of
the various proj ects for which the Contractors have
submitted requests for time extension and are now
being checked reviewed and evaluated by the
Consultant
2 PROGRESS
Subproject No 7 (Sto Domingo-Bula-Ombao)
The accomplishment for the month is 681 making
a total completion to date of 48 61 The total
slippage if now 6 09 compared to last months
total of 7 7 or a rcc overy of 1 61
SR-7
Stations 21()()
Z425
31
Roadwork - On Secondary Road hauling spread-
ing and compaction of borrow between
Stas 6 I 000 and 7 I 000 continue to
correct deficiency in shoulder width
Feeder Roads - continue hauling
spreading and c ompactiun of aggregate
subbase of FR-7A between Stas a I
000 and 0 1470 Spreading of aggre-
gate subbase to final grade in progre88
at feeder roads FR-7B and FR-7C
Structur es (Box Culverts) - Conc rete has been
poured for apron wingwalls side-
walls innerwalls cut-off walls and
top slab of RCBC No2
Structures (Drainage) - Continue toasting of
RCPCls Started and continue excava-
tion for end walls of pipes laid at
Secondary and Feeder Roads The
following pipes were laid
0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia
L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc
12 pcs
L-Side Rmiddot Side
12 pcs
11 061 m dia 091 m dia 1 07 m dh 1 2L m dia
Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid
FR-7A
o 433 5 pcs (Add1 )
FR-7B
o 280 5 pcs
o 396 10 pel
o 700 5 pcs 5 pcs
FR-7C
2 024 1 pc 1 pc
1 900 9 pcs (Full length)
1 757 9 pcs (Full length)
Structures (Bridges) - Completed driving of 14 regular concrete
piles at Polpog Bridge Started cuttingdriven piles
to cut-off elevation Installation of falsework and
formwork in progress
Surface Courses amp Pavement - On Secondary Road placed 1 13064
sq m of concrete pavement between Stas 5 37850
and 5 446 00 left lane between Stas 5 225 12 and
5 41450 right lane and between Stas 5 53400 and
5 65400 left lane for a total of 1990 14 sq m of
PCC Pavement poured to date
Subproject No 12 (Iriga-Salvacion-Bato)
Based on contract amount the Contractor has accomshy
plished 071 progress since the Notice to Proceed
took effed on May lB 1979 The Contractor has
not yet submitted his corrected progress schedule
General - Laboratory equipment submitted Lythe
Contractor is 81 B complete
Roadwork - Roadway and Drainage Excavation has
started between Stas 5 400 and 9 100
with an accomplishment involving 1 968 cu
m Trimming of side s lo~ _s and ditching
in progress between said above stationo
Continue survey work for verification of
vertical control elevations
SUbproj ect No l3-A (Polangui- Lidong)
The accomplishment for the month is 73 making a
total completion to date of 63 B The total slippage
is now 229 compared to last months total of 2340
or a recovery of O 5
Roadwork - On Secondary Road work continue on excashy
vation of portions of road where material
excavated are being utilized to bring embaJkshy
ment to grade Hading spreading and
compacting aggregate subbase in progress
between Stas 2 340 and 2 640 between
Stas 2 900 and 3 900 between Stas
7 320 and 7 400 between Stas 7 440
and 7 800 between Stas 7 880 and 8
560 and between Stas 9 120 and 9 700
and aggregate base course work between
Stas 3 000 and 3 256 7 460 and 7 780
7 900 and 8 500 and 9 140 and 9 600
Feeder Roads - Continue survey work for
staking stationing and alignment Work
continue on hauling spreading and compactshy
ing of aggregate subbas c betwen Stas 0 I
400 and 1 00 at FR-13B Roadway and
Drainage Excavation is complete up to Sta
5 020 at FR-13C
Structures (Bridges) - Concrete placed for backwall and
wingwall at 2nd approach of Pintor Bridge
pile cap at 1 st approach of Pinagdapogan
Bridge and backwall at 2nd approach of
l
Mainaga Bridge Installation of rebar for
backwall at 1 st approach of Pintor Bridge
started and continuing
Structures (Culverts) - Completed placing of concrete
ior exterior sidewalls of RCBC No 1 at
feeder road FR -13 B Preparation of forms
and rebars for bottom B lab of RC Be No 2
at feeder road FR-13C in progress
Surface Courses and Pavement - Secondary Road -
Applied bituminous prime coat and placed
as phalt conc rete between Stas 0 758 and
0820 left lane and between Stas 0855
and 2 220 left and right lanes
Subproject No 13-BLidong-Buhi)
The accomplishment for the month is 43400 making a
total completion to datL of 3206 The total slippage
gt
is now 24 06
Roadwork - On Secondary Road the placing of aggregate
subbas c between Stas 13 200 and 13 500
continue with the same work going on at feeder
road FR-13G b(tw((n Stas 0 800 and Z I
200 Conlinlll11 rVly work
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
MINISTRY OF PUBLIC HIGHWAYS BRBDP ROAD COMPONENT
PROJECT MANAGEMENT OFFICE
PROGRESS REPORT July 1979
DCCD ENGINEERING CORPORATION
Prepared by
ANITO R VILLAMIL Resident EnginCcr
Submitted by
TABLE OF CONTENTS
Page
1 GENERAL 1
2 PROGRESS 1
3 MISCELLANEOUS 7
4 ATTACHMENTS
A
B
C
D
PROGRESS CHARTS
CONSULTANTS STAFF
CONTRACTORS STAFF
CONTRACTORS EQUIPMENT ON SITE
MONTHLY PROGRESS REPORT July 31 1979
1 GENERAL
This report covers the adivities for the CONSTRUC-
TION SUPERVISION of the BICOL SECONDARY AND
FEEDER ROADS PROJECT Package III This
Package is composed of Subprojects i~- 8 12 amp 13
The lack of fueladverse weather condition acquili-
tion of Right-Of- Way and delayed payments have
contributed to the slippages in the progres s of
the various proj ects for which the Contractors have
submitted requests for time extension and are now
being checked reviewed and evaluated by the
Consultant
2 PROGRESS
Subproject No 7 (Sto Domingo-Bula-Ombao)
The accomplishment for the month is 681 making
a total completion to date of 48 61 The total
slippage if now 6 09 compared to last months
total of 7 7 or a rcc overy of 1 61
SR-7
Stations 21()()
Z425
31
Roadwork - On Secondary Road hauling spread-
ing and compaction of borrow between
Stas 6 I 000 and 7 I 000 continue to
correct deficiency in shoulder width
Feeder Roads - continue hauling
spreading and c ompactiun of aggregate
subbase of FR-7A between Stas a I
000 and 0 1470 Spreading of aggre-
gate subbase to final grade in progre88
at feeder roads FR-7B and FR-7C
Structur es (Box Culverts) - Conc rete has been
poured for apron wingwalls side-
walls innerwalls cut-off walls and
top slab of RCBC No2
Structures (Drainage) - Continue toasting of
RCPCls Started and continue excava-
tion for end walls of pipes laid at
Secondary and Feeder Roads The
following pipes were laid
0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia
L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc
12 pcs
L-Side Rmiddot Side
12 pcs
11 061 m dia 091 m dia 1 07 m dh 1 2L m dia
Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid
FR-7A
o 433 5 pcs (Add1 )
FR-7B
o 280 5 pcs
o 396 10 pel
o 700 5 pcs 5 pcs
FR-7C
2 024 1 pc 1 pc
1 900 9 pcs (Full length)
1 757 9 pcs (Full length)
Structures (Bridges) - Completed driving of 14 regular concrete
piles at Polpog Bridge Started cuttingdriven piles
to cut-off elevation Installation of falsework and
formwork in progress
Surface Courses amp Pavement - On Secondary Road placed 1 13064
sq m of concrete pavement between Stas 5 37850
and 5 446 00 left lane between Stas 5 225 12 and
5 41450 right lane and between Stas 5 53400 and
5 65400 left lane for a total of 1990 14 sq m of
PCC Pavement poured to date
Subproject No 12 (Iriga-Salvacion-Bato)
Based on contract amount the Contractor has accomshy
plished 071 progress since the Notice to Proceed
took effed on May lB 1979 The Contractor has
not yet submitted his corrected progress schedule
General - Laboratory equipment submitted Lythe
Contractor is 81 B complete
Roadwork - Roadway and Drainage Excavation has
started between Stas 5 400 and 9 100
with an accomplishment involving 1 968 cu
m Trimming of side s lo~ _s and ditching
in progress between said above stationo
Continue survey work for verification of
vertical control elevations
SUbproj ect No l3-A (Polangui- Lidong)
The accomplishment for the month is 73 making a
total completion to date of 63 B The total slippage
is now 229 compared to last months total of 2340
or a recovery of O 5
Roadwork - On Secondary Road work continue on excashy
vation of portions of road where material
excavated are being utilized to bring embaJkshy
ment to grade Hading spreading and
compacting aggregate subbase in progress
between Stas 2 340 and 2 640 between
Stas 2 900 and 3 900 between Stas
7 320 and 7 400 between Stas 7 440
and 7 800 between Stas 7 880 and 8
560 and between Stas 9 120 and 9 700
and aggregate base course work between
Stas 3 000 and 3 256 7 460 and 7 780
7 900 and 8 500 and 9 140 and 9 600
Feeder Roads - Continue survey work for
staking stationing and alignment Work
continue on hauling spreading and compactshy
ing of aggregate subbas c betwen Stas 0 I
400 and 1 00 at FR-13B Roadway and
Drainage Excavation is complete up to Sta
5 020 at FR-13C
Structures (Bridges) - Concrete placed for backwall and
wingwall at 2nd approach of Pintor Bridge
pile cap at 1 st approach of Pinagdapogan
Bridge and backwall at 2nd approach of
l
Mainaga Bridge Installation of rebar for
backwall at 1 st approach of Pintor Bridge
started and continuing
Structures (Culverts) - Completed placing of concrete
ior exterior sidewalls of RCBC No 1 at
feeder road FR -13 B Preparation of forms
and rebars for bottom B lab of RC Be No 2
at feeder road FR-13C in progress
Surface Courses and Pavement - Secondary Road -
Applied bituminous prime coat and placed
as phalt conc rete between Stas 0 758 and
0820 left lane and between Stas 0855
and 2 220 left and right lanes
Subproject No 13-BLidong-Buhi)
The accomplishment for the month is 43400 making a
total completion to datL of 3206 The total slippage
gt
is now 24 06
Roadwork - On Secondary Road the placing of aggregate
subbas c between Stas 13 200 and 13 500
continue with the same work going on at feeder
road FR-13G b(tw((n Stas 0 800 and Z I
200 Conlinlll11 rVly work
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
TABLE OF CONTENTS
Page
1 GENERAL 1
2 PROGRESS 1
3 MISCELLANEOUS 7
4 ATTACHMENTS
A
B
C
D
PROGRESS CHARTS
CONSULTANTS STAFF
CONTRACTORS STAFF
CONTRACTORS EQUIPMENT ON SITE
MONTHLY PROGRESS REPORT July 31 1979
1 GENERAL
This report covers the adivities for the CONSTRUC-
TION SUPERVISION of the BICOL SECONDARY AND
FEEDER ROADS PROJECT Package III This
Package is composed of Subprojects i~- 8 12 amp 13
The lack of fueladverse weather condition acquili-
tion of Right-Of- Way and delayed payments have
contributed to the slippages in the progres s of
the various proj ects for which the Contractors have
submitted requests for time extension and are now
being checked reviewed and evaluated by the
Consultant
2 PROGRESS
Subproject No 7 (Sto Domingo-Bula-Ombao)
The accomplishment for the month is 681 making
a total completion to date of 48 61 The total
slippage if now 6 09 compared to last months
total of 7 7 or a rcc overy of 1 61
SR-7
Stations 21()()
Z425
31
Roadwork - On Secondary Road hauling spread-
ing and compaction of borrow between
Stas 6 I 000 and 7 I 000 continue to
correct deficiency in shoulder width
Feeder Roads - continue hauling
spreading and c ompactiun of aggregate
subbase of FR-7A between Stas a I
000 and 0 1470 Spreading of aggre-
gate subbase to final grade in progre88
at feeder roads FR-7B and FR-7C
Structur es (Box Culverts) - Conc rete has been
poured for apron wingwalls side-
walls innerwalls cut-off walls and
top slab of RCBC No2
Structures (Drainage) - Continue toasting of
RCPCls Started and continue excava-
tion for end walls of pipes laid at
Secondary and Feeder Roads The
following pipes were laid
0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia
L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc
12 pcs
L-Side Rmiddot Side
12 pcs
11 061 m dia 091 m dia 1 07 m dh 1 2L m dia
Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid
FR-7A
o 433 5 pcs (Add1 )
FR-7B
o 280 5 pcs
o 396 10 pel
o 700 5 pcs 5 pcs
FR-7C
2 024 1 pc 1 pc
1 900 9 pcs (Full length)
1 757 9 pcs (Full length)
Structures (Bridges) - Completed driving of 14 regular concrete
piles at Polpog Bridge Started cuttingdriven piles
to cut-off elevation Installation of falsework and
formwork in progress
Surface Courses amp Pavement - On Secondary Road placed 1 13064
sq m of concrete pavement between Stas 5 37850
and 5 446 00 left lane between Stas 5 225 12 and
5 41450 right lane and between Stas 5 53400 and
5 65400 left lane for a total of 1990 14 sq m of
PCC Pavement poured to date
Subproject No 12 (Iriga-Salvacion-Bato)
Based on contract amount the Contractor has accomshy
plished 071 progress since the Notice to Proceed
took effed on May lB 1979 The Contractor has
not yet submitted his corrected progress schedule
General - Laboratory equipment submitted Lythe
Contractor is 81 B complete
Roadwork - Roadway and Drainage Excavation has
started between Stas 5 400 and 9 100
with an accomplishment involving 1 968 cu
m Trimming of side s lo~ _s and ditching
in progress between said above stationo
Continue survey work for verification of
vertical control elevations
SUbproj ect No l3-A (Polangui- Lidong)
The accomplishment for the month is 73 making a
total completion to date of 63 B The total slippage
is now 229 compared to last months total of 2340
or a recovery of O 5
Roadwork - On Secondary Road work continue on excashy
vation of portions of road where material
excavated are being utilized to bring embaJkshy
ment to grade Hading spreading and
compacting aggregate subbase in progress
between Stas 2 340 and 2 640 between
Stas 2 900 and 3 900 between Stas
7 320 and 7 400 between Stas 7 440
and 7 800 between Stas 7 880 and 8
560 and between Stas 9 120 and 9 700
and aggregate base course work between
Stas 3 000 and 3 256 7 460 and 7 780
7 900 and 8 500 and 9 140 and 9 600
Feeder Roads - Continue survey work for
staking stationing and alignment Work
continue on hauling spreading and compactshy
ing of aggregate subbas c betwen Stas 0 I
400 and 1 00 at FR-13B Roadway and
Drainage Excavation is complete up to Sta
5 020 at FR-13C
Structures (Bridges) - Concrete placed for backwall and
wingwall at 2nd approach of Pintor Bridge
pile cap at 1 st approach of Pinagdapogan
Bridge and backwall at 2nd approach of
l
Mainaga Bridge Installation of rebar for
backwall at 1 st approach of Pintor Bridge
started and continuing
Structures (Culverts) - Completed placing of concrete
ior exterior sidewalls of RCBC No 1 at
feeder road FR -13 B Preparation of forms
and rebars for bottom B lab of RC Be No 2
at feeder road FR-13C in progress
Surface Courses and Pavement - Secondary Road -
Applied bituminous prime coat and placed
as phalt conc rete between Stas 0 758 and
0820 left lane and between Stas 0855
and 2 220 left and right lanes
Subproject No 13-BLidong-Buhi)
The accomplishment for the month is 43400 making a
total completion to datL of 3206 The total slippage
gt
is now 24 06
Roadwork - On Secondary Road the placing of aggregate
subbas c between Stas 13 200 and 13 500
continue with the same work going on at feeder
road FR-13G b(tw((n Stas 0 800 and Z I
200 Conlinlll11 rVly work
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
MONTHLY PROGRESS REPORT July 31 1979
1 GENERAL
This report covers the adivities for the CONSTRUC-
TION SUPERVISION of the BICOL SECONDARY AND
FEEDER ROADS PROJECT Package III This
Package is composed of Subprojects i~- 8 12 amp 13
The lack of fueladverse weather condition acquili-
tion of Right-Of- Way and delayed payments have
contributed to the slippages in the progres s of
the various proj ects for which the Contractors have
submitted requests for time extension and are now
being checked reviewed and evaluated by the
Consultant
2 PROGRESS
Subproject No 7 (Sto Domingo-Bula-Ombao)
The accomplishment for the month is 681 making
a total completion to date of 48 61 The total
slippage if now 6 09 compared to last months
total of 7 7 or a rcc overy of 1 61
SR-7
Stations 21()()
Z425
31
Roadwork - On Secondary Road hauling spread-
ing and compaction of borrow between
Stas 6 I 000 and 7 I 000 continue to
correct deficiency in shoulder width
Feeder Roads - continue hauling
spreading and c ompactiun of aggregate
subbase of FR-7A between Stas a I
000 and 0 1470 Spreading of aggre-
gate subbase to final grade in progre88
at feeder roads FR-7B and FR-7C
Structur es (Box Culverts) - Conc rete has been
poured for apron wingwalls side-
walls innerwalls cut-off walls and
top slab of RCBC No2
Structures (Drainage) - Continue toasting of
RCPCls Started and continue excava-
tion for end walls of pipes laid at
Secondary and Feeder Roads The
following pipes were laid
0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia
L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc
12 pcs
L-Side Rmiddot Side
12 pcs
11 061 m dia 091 m dia 1 07 m dh 1 2L m dia
Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid
FR-7A
o 433 5 pcs (Add1 )
FR-7B
o 280 5 pcs
o 396 10 pel
o 700 5 pcs 5 pcs
FR-7C
2 024 1 pc 1 pc
1 900 9 pcs (Full length)
1 757 9 pcs (Full length)
Structures (Bridges) - Completed driving of 14 regular concrete
piles at Polpog Bridge Started cuttingdriven piles
to cut-off elevation Installation of falsework and
formwork in progress
Surface Courses amp Pavement - On Secondary Road placed 1 13064
sq m of concrete pavement between Stas 5 37850
and 5 446 00 left lane between Stas 5 225 12 and
5 41450 right lane and between Stas 5 53400 and
5 65400 left lane for a total of 1990 14 sq m of
PCC Pavement poured to date
Subproject No 12 (Iriga-Salvacion-Bato)
Based on contract amount the Contractor has accomshy
plished 071 progress since the Notice to Proceed
took effed on May lB 1979 The Contractor has
not yet submitted his corrected progress schedule
General - Laboratory equipment submitted Lythe
Contractor is 81 B complete
Roadwork - Roadway and Drainage Excavation has
started between Stas 5 400 and 9 100
with an accomplishment involving 1 968 cu
m Trimming of side s lo~ _s and ditching
in progress between said above stationo
Continue survey work for verification of
vertical control elevations
SUbproj ect No l3-A (Polangui- Lidong)
The accomplishment for the month is 73 making a
total completion to date of 63 B The total slippage
is now 229 compared to last months total of 2340
or a recovery of O 5
Roadwork - On Secondary Road work continue on excashy
vation of portions of road where material
excavated are being utilized to bring embaJkshy
ment to grade Hading spreading and
compacting aggregate subbase in progress
between Stas 2 340 and 2 640 between
Stas 2 900 and 3 900 between Stas
7 320 and 7 400 between Stas 7 440
and 7 800 between Stas 7 880 and 8
560 and between Stas 9 120 and 9 700
and aggregate base course work between
Stas 3 000 and 3 256 7 460 and 7 780
7 900 and 8 500 and 9 140 and 9 600
Feeder Roads - Continue survey work for
staking stationing and alignment Work
continue on hauling spreading and compactshy
ing of aggregate subbas c betwen Stas 0 I
400 and 1 00 at FR-13B Roadway and
Drainage Excavation is complete up to Sta
5 020 at FR-13C
Structures (Bridges) - Concrete placed for backwall and
wingwall at 2nd approach of Pintor Bridge
pile cap at 1 st approach of Pinagdapogan
Bridge and backwall at 2nd approach of
l
Mainaga Bridge Installation of rebar for
backwall at 1 st approach of Pintor Bridge
started and continuing
Structures (Culverts) - Completed placing of concrete
ior exterior sidewalls of RCBC No 1 at
feeder road FR -13 B Preparation of forms
and rebars for bottom B lab of RC Be No 2
at feeder road FR-13C in progress
Surface Courses and Pavement - Secondary Road -
Applied bituminous prime coat and placed
as phalt conc rete between Stas 0 758 and
0820 left lane and between Stas 0855
and 2 220 left and right lanes
Subproject No 13-BLidong-Buhi)
The accomplishment for the month is 43400 making a
total completion to datL of 3206 The total slippage
gt
is now 24 06
Roadwork - On Secondary Road the placing of aggregate
subbas c between Stas 13 200 and 13 500
continue with the same work going on at feeder
road FR-13G b(tw((n Stas 0 800 and Z I
200 Conlinlll11 rVly work
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
SR-7
Stations 21()()
Z425
31
Roadwork - On Secondary Road hauling spread-
ing and compaction of borrow between
Stas 6 I 000 and 7 I 000 continue to
correct deficiency in shoulder width
Feeder Roads - continue hauling
spreading and c ompactiun of aggregate
subbase of FR-7A between Stas a I
000 and 0 1470 Spreading of aggre-
gate subbase to final grade in progre88
at feeder roads FR-7B and FR-7C
Structur es (Box Culverts) - Conc rete has been
poured for apron wingwalls side-
walls innerwalls cut-off walls and
top slab of RCBC No2
Structures (Drainage) - Continue toasting of
RCPCls Started and continue excava-
tion for end walls of pipes laid at
Secondary and Feeder Roads The
following pipes were laid
0-61 m dia 091 m dia 1 07 m dia 1 ZZ m dia
L-Sidc R-Sidc L-Sidc R-Sidpound L-Sidc R-Sidc
12 pcs
L-Side Rmiddot Side
12 pcs
11 061 m dia 091 m dia 1 07 m dh 1 2L m dia
Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid
FR-7A
o 433 5 pcs (Add1 )
FR-7B
o 280 5 pcs
o 396 10 pel
o 700 5 pcs 5 pcs
FR-7C
2 024 1 pc 1 pc
1 900 9 pcs (Full length)
1 757 9 pcs (Full length)
Structures (Bridges) - Completed driving of 14 regular concrete
piles at Polpog Bridge Started cuttingdriven piles
to cut-off elevation Installation of falsework and
formwork in progress
Surface Courses amp Pavement - On Secondary Road placed 1 13064
sq m of concrete pavement between Stas 5 37850
and 5 446 00 left lane between Stas 5 225 12 and
5 41450 right lane and between Stas 5 53400 and
5 65400 left lane for a total of 1990 14 sq m of
PCC Pavement poured to date
Subproject No 12 (Iriga-Salvacion-Bato)
Based on contract amount the Contractor has accomshy
plished 071 progress since the Notice to Proceed
took effed on May lB 1979 The Contractor has
not yet submitted his corrected progress schedule
General - Laboratory equipment submitted Lythe
Contractor is 81 B complete
Roadwork - Roadway and Drainage Excavation has
started between Stas 5 400 and 9 100
with an accomplishment involving 1 968 cu
m Trimming of side s lo~ _s and ditching
in progress between said above stationo
Continue survey work for verification of
vertical control elevations
SUbproj ect No l3-A (Polangui- Lidong)
The accomplishment for the month is 73 making a
total completion to date of 63 B The total slippage
is now 229 compared to last months total of 2340
or a recovery of O 5
Roadwork - On Secondary Road work continue on excashy
vation of portions of road where material
excavated are being utilized to bring embaJkshy
ment to grade Hading spreading and
compacting aggregate subbase in progress
between Stas 2 340 and 2 640 between
Stas 2 900 and 3 900 between Stas
7 320 and 7 400 between Stas 7 440
and 7 800 between Stas 7 880 and 8
560 and between Stas 9 120 and 9 700
and aggregate base course work between
Stas 3 000 and 3 256 7 460 and 7 780
7 900 and 8 500 and 9 140 and 9 600
Feeder Roads - Continue survey work for
staking stationing and alignment Work
continue on hauling spreading and compactshy
ing of aggregate subbas c betwen Stas 0 I
400 and 1 00 at FR-13B Roadway and
Drainage Excavation is complete up to Sta
5 020 at FR-13C
Structures (Bridges) - Concrete placed for backwall and
wingwall at 2nd approach of Pintor Bridge
pile cap at 1 st approach of Pinagdapogan
Bridge and backwall at 2nd approach of
l
Mainaga Bridge Installation of rebar for
backwall at 1 st approach of Pintor Bridge
started and continuing
Structures (Culverts) - Completed placing of concrete
ior exterior sidewalls of RCBC No 1 at
feeder road FR -13 B Preparation of forms
and rebars for bottom B lab of RC Be No 2
at feeder road FR-13C in progress
Surface Courses and Pavement - Secondary Road -
Applied bituminous prime coat and placed
as phalt conc rete between Stas 0 758 and
0820 left lane and between Stas 0855
and 2 220 left and right lanes
Subproject No 13-BLidong-Buhi)
The accomplishment for the month is 43400 making a
total completion to datL of 3206 The total slippage
gt
is now 24 06
Roadwork - On Secondary Road the placing of aggregate
subbas c between Stas 13 200 and 13 500
continue with the same work going on at feeder
road FR-13G b(tw((n Stas 0 800 and Z I
200 Conlinlll11 rVly work
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
11 061 m dia 091 m dia 1 07 m dh 1 2L m dia
Stations L-Side R-Side L-Side R-Side L-Side R-Sicie L-Side R-Sid
FR-7A
o 433 5 pcs (Add1 )
FR-7B
o 280 5 pcs
o 396 10 pel
o 700 5 pcs 5 pcs
FR-7C
2 024 1 pc 1 pc
1 900 9 pcs (Full length)
1 757 9 pcs (Full length)
Structures (Bridges) - Completed driving of 14 regular concrete
piles at Polpog Bridge Started cuttingdriven piles
to cut-off elevation Installation of falsework and
formwork in progress
Surface Courses amp Pavement - On Secondary Road placed 1 13064
sq m of concrete pavement between Stas 5 37850
and 5 446 00 left lane between Stas 5 225 12 and
5 41450 right lane and between Stas 5 53400 and
5 65400 left lane for a total of 1990 14 sq m of
PCC Pavement poured to date
Subproject No 12 (Iriga-Salvacion-Bato)
Based on contract amount the Contractor has accomshy
plished 071 progress since the Notice to Proceed
took effed on May lB 1979 The Contractor has
not yet submitted his corrected progress schedule
General - Laboratory equipment submitted Lythe
Contractor is 81 B complete
Roadwork - Roadway and Drainage Excavation has
started between Stas 5 400 and 9 100
with an accomplishment involving 1 968 cu
m Trimming of side s lo~ _s and ditching
in progress between said above stationo
Continue survey work for verification of
vertical control elevations
SUbproj ect No l3-A (Polangui- Lidong)
The accomplishment for the month is 73 making a
total completion to date of 63 B The total slippage
is now 229 compared to last months total of 2340
or a recovery of O 5
Roadwork - On Secondary Road work continue on excashy
vation of portions of road where material
excavated are being utilized to bring embaJkshy
ment to grade Hading spreading and
compacting aggregate subbase in progress
between Stas 2 340 and 2 640 between
Stas 2 900 and 3 900 between Stas
7 320 and 7 400 between Stas 7 440
and 7 800 between Stas 7 880 and 8
560 and between Stas 9 120 and 9 700
and aggregate base course work between
Stas 3 000 and 3 256 7 460 and 7 780
7 900 and 8 500 and 9 140 and 9 600
Feeder Roads - Continue survey work for
staking stationing and alignment Work
continue on hauling spreading and compactshy
ing of aggregate subbas c betwen Stas 0 I
400 and 1 00 at FR-13B Roadway and
Drainage Excavation is complete up to Sta
5 020 at FR-13C
Structures (Bridges) - Concrete placed for backwall and
wingwall at 2nd approach of Pintor Bridge
pile cap at 1 st approach of Pinagdapogan
Bridge and backwall at 2nd approach of
l
Mainaga Bridge Installation of rebar for
backwall at 1 st approach of Pintor Bridge
started and continuing
Structures (Culverts) - Completed placing of concrete
ior exterior sidewalls of RCBC No 1 at
feeder road FR -13 B Preparation of forms
and rebars for bottom B lab of RC Be No 2
at feeder road FR-13C in progress
Surface Courses and Pavement - Secondary Road -
Applied bituminous prime coat and placed
as phalt conc rete between Stas 0 758 and
0820 left lane and between Stas 0855
and 2 220 left and right lanes
Subproject No 13-BLidong-Buhi)
The accomplishment for the month is 43400 making a
total completion to datL of 3206 The total slippage
gt
is now 24 06
Roadwork - On Secondary Road the placing of aggregate
subbas c between Stas 13 200 and 13 500
continue with the same work going on at feeder
road FR-13G b(tw((n Stas 0 800 and Z I
200 Conlinlll11 rVly work
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
Subproject No 12 (Iriga-Salvacion-Bato)
Based on contract amount the Contractor has accomshy
plished 071 progress since the Notice to Proceed
took effed on May lB 1979 The Contractor has
not yet submitted his corrected progress schedule
General - Laboratory equipment submitted Lythe
Contractor is 81 B complete
Roadwork - Roadway and Drainage Excavation has
started between Stas 5 400 and 9 100
with an accomplishment involving 1 968 cu
m Trimming of side s lo~ _s and ditching
in progress between said above stationo
Continue survey work for verification of
vertical control elevations
SUbproj ect No l3-A (Polangui- Lidong)
The accomplishment for the month is 73 making a
total completion to date of 63 B The total slippage
is now 229 compared to last months total of 2340
or a recovery of O 5
Roadwork - On Secondary Road work continue on excashy
vation of portions of road where material
excavated are being utilized to bring embaJkshy
ment to grade Hading spreading and
compacting aggregate subbase in progress
between Stas 2 340 and 2 640 between
Stas 2 900 and 3 900 between Stas
7 320 and 7 400 between Stas 7 440
and 7 800 between Stas 7 880 and 8
560 and between Stas 9 120 and 9 700
and aggregate base course work between
Stas 3 000 and 3 256 7 460 and 7 780
7 900 and 8 500 and 9 140 and 9 600
Feeder Roads - Continue survey work for
staking stationing and alignment Work
continue on hauling spreading and compactshy
ing of aggregate subbas c betwen Stas 0 I
400 and 1 00 at FR-13B Roadway and
Drainage Excavation is complete up to Sta
5 020 at FR-13C
Structures (Bridges) - Concrete placed for backwall and
wingwall at 2nd approach of Pintor Bridge
pile cap at 1 st approach of Pinagdapogan
Bridge and backwall at 2nd approach of
l
Mainaga Bridge Installation of rebar for
backwall at 1 st approach of Pintor Bridge
started and continuing
Structures (Culverts) - Completed placing of concrete
ior exterior sidewalls of RCBC No 1 at
feeder road FR -13 B Preparation of forms
and rebars for bottom B lab of RC Be No 2
at feeder road FR-13C in progress
Surface Courses and Pavement - Secondary Road -
Applied bituminous prime coat and placed
as phalt conc rete between Stas 0 758 and
0820 left lane and between Stas 0855
and 2 220 left and right lanes
Subproject No 13-BLidong-Buhi)
The accomplishment for the month is 43400 making a
total completion to datL of 3206 The total slippage
gt
is now 24 06
Roadwork - On Secondary Road the placing of aggregate
subbas c between Stas 13 200 and 13 500
continue with the same work going on at feeder
road FR-13G b(tw((n Stas 0 800 and Z I
200 Conlinlll11 rVly work
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
excavated are being utilized to bring embaJkshy
ment to grade Hading spreading and
compacting aggregate subbase in progress
between Stas 2 340 and 2 640 between
Stas 2 900 and 3 900 between Stas
7 320 and 7 400 between Stas 7 440
and 7 800 between Stas 7 880 and 8
560 and between Stas 9 120 and 9 700
and aggregate base course work between
Stas 3 000 and 3 256 7 460 and 7 780
7 900 and 8 500 and 9 140 and 9 600
Feeder Roads - Continue survey work for
staking stationing and alignment Work
continue on hauling spreading and compactshy
ing of aggregate subbas c betwen Stas 0 I
400 and 1 00 at FR-13B Roadway and
Drainage Excavation is complete up to Sta
5 020 at FR-13C
Structures (Bridges) - Concrete placed for backwall and
wingwall at 2nd approach of Pintor Bridge
pile cap at 1 st approach of Pinagdapogan
Bridge and backwall at 2nd approach of
l
Mainaga Bridge Installation of rebar for
backwall at 1 st approach of Pintor Bridge
started and continuing
Structures (Culverts) - Completed placing of concrete
ior exterior sidewalls of RCBC No 1 at
feeder road FR -13 B Preparation of forms
and rebars for bottom B lab of RC Be No 2
at feeder road FR-13C in progress
Surface Courses and Pavement - Secondary Road -
Applied bituminous prime coat and placed
as phalt conc rete between Stas 0 758 and
0820 left lane and between Stas 0855
and 2 220 left and right lanes
Subproject No 13-BLidong-Buhi)
The accomplishment for the month is 43400 making a
total completion to datL of 3206 The total slippage
gt
is now 24 06
Roadwork - On Secondary Road the placing of aggregate
subbas c between Stas 13 200 and 13 500
continue with the same work going on at feeder
road FR-13G b(tw((n Stas 0 800 and Z I
200 Conlinlll11 rVly work
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
l
Mainaga Bridge Installation of rebar for
backwall at 1 st approach of Pintor Bridge
started and continuing
Structures (Culverts) - Completed placing of concrete
ior exterior sidewalls of RCBC No 1 at
feeder road FR -13 B Preparation of forms
and rebars for bottom B lab of RC Be No 2
at feeder road FR-13C in progress
Surface Courses and Pavement - Secondary Road -
Applied bituminous prime coat and placed
as phalt conc rete between Stas 0 758 and
0820 left lane and between Stas 0855
and 2 220 left and right lanes
Subproject No 13-BLidong-Buhi)
The accomplishment for the month is 43400 making a
total completion to datL of 3206 The total slippage
gt
is now 24 06
Roadwork - On Secondary Road the placing of aggregate
subbas c between Stas 13 200 and 13 500
continue with the same work going on at feeder
road FR-13G b(tw((n Stas 0 800 and Z I
200 Conlinlll11 rVly work
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
11
S~ructures (Bridges) - Placed concrete for girders
at Araga Bridge Erection of formworks
and installation of rebars for top slap for
the same bridge going on
Structures (Box Culverts) - Continue excavation for
foundations of RCBCls Nos 4 5 and 6
Structures (Drainage) - Continue fabrication of Repels
Excavation for pipes continue and the
following pipes laid
SR-13B 061 m dia 091 m dia
Stations L-Side R-Side L-Side R-Side
14 300 6 pcs
14 750 4 pcs 4 pcs
18 260 7 pcs 7 pcs
FR-13G
0 085 6 pcs S pcs
o 520 5 pcs 5 pcs
1 280 5 pcs 6 pcs
MISCELLANEOUS
Subproject No B The Composite Management Group has
awarded the project to Capitol Industrial Construction
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
~
Group and a contract will be prepared by the Projec
Management Office at Naga City
Subproject No 12 The Project Manager of the
Cunsultants called a llleeting with the Contractor on
July 12 1979 at the DCCD Engineering Corporation
Makati Offic e and the Contractor was warned that
unless satisfactory progress is shown Jefore 25
of the cuntract time (xpires the Consultants will
recommend to the Government implementation of
Article 808 Df toe Standard Specifications for Highshy
ways and Bridges Further a meeting was also held
betwlen the P1oj cct Managlr of the Consultants and
the Contr~ctors at the jobsite in Camarines Sur on
July 18 1979 wherein problCms of management
finances and equipment were clarified with the Contractor
promising immediatC resolution of the defirlencies cited
and exerting lxtra effort to lnak( up f(lr the slow activity
which is causing delayed progress
Subproject No 13-A The Consultants has written the
Contractor inviting attention to tillt slippagcs and in a
lllllIing wilh I Ill Proitd Mmlglr of till Consultants the
Contractor was told to take th~ necessary action and exert
lxtra lffort to mak lip 1lIe1 a11 tllglUwr lradklt till
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
J
slippages
Subprojed No 13-B The Contractor was called to
a meeting at the jobsite on July 25 1979 wherein
the Cunsulta1ls stressed their concern about th
delayed progrCss causing increasing slippage The
Contractor was wa rned that unles s immediate mc~shy
sures were taken to stop further slippage und to put
more effort tu make up for the existing slippage the
Consultants will rccommCnd rescission of their
CONTRACT This warning was put in writing addressed
to the CONTRACTOR in a letter dated July 26 1979
The Contractor admitted some financial difficulties
which he claims has now cas ed and will exert extra
lttention and effort to increase his accomplishment
Two meetings one on June 14 1979 and the latest on
July 17 1979 betwcCn all the Contractors of the onshy
going projects and lhe Consultants were called by the
Project Manager uf the Consultants to emphasize the
growing conClrn for the Contractors slow progress
and disCUSStd uplratiuns prubltllls that might bl adding
to delays in prugress Causes uf delays in progress
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
lQ
esb 72779
have been submitted for evaluation and the Contractors
also promised to accelerate their operation with the
ea sing situ ation
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
CONTRACTOR WILLIAM U~ - CON TRACTOR BtCOl SECONDARY BIDDING DATE JANUARY 91978 PAC IC A OFfiCIAL STARTING DATE JULY 15 1978 CONTRA ORloNAL COMPLETION DATE JANUARY 5 1960 POLANGU 1-L IDONI-I
APPROVED REVISED COMPLETION DATE PROGRE8 t-- ----- ----
PROBABLE COMPLETION DATE JANUARY 5 1980 ----- __- ---
~IIJ LampJ IampJ I- 1-1-
s~ UIIJ 1978 i T E M ~a3 ILIJ
~IampJQ ~Q o I- laquo o I- 00 zgt -2 a~ 8 (LO
J J A S 0 N 0 J I ()
GENERAL 65 1 tT_ 7~ E ~ 82
I 15 556 08 56 516 Iamp ~ra l 16 5~
I- --r-1 amp I~ 119 2 115 3~
II EARTHWORK 465 94 456 9 2~ 2fi 314 -
44-3r~ II 21 14 III BASE COURSE 79
---
SURFACE COURSES 15
IV AND PAVEMENT 1
220r2 40
3 7 -V STRUCTURES 195 5()8 99 ~ 112 2 ~ 7
VI INCIDENTAL CONSTRUCTION 06 00 00
TOTAL looj I ------
~ PROGRESS
) Scheduled cmiddota l~ ~ V ~ _4 ACTUAL 638 -
J -
L V ------ -1- 5 SCHEDULEC 867
~ [Report ~ COMPLETION ~ Illonth Flat ~
previoul
Th riod
LEGEND --- ORIGINAL SCHEDULED PROGRESS ----------- ACTUAL PROGRESS
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
- middotAt - a
In AND FEEDER ROADS MONTHLy PROGReJs REPQ(r Its ~ JULY 31 19
~KAGE III - PREPARED IV JUANITO R VILLAMIL RE
ACT NO I NET CONTRAcT BID AMOUNT 14 t 435584000middot IG-BUHI (SUB-PROJECT 13A) -APPROVED REVISED CONTRACT AMOUNT
ESS CHA RT CURRENT ESTIMmEO FINAL COST
1amp1 1amp1
197 9~ 198 0 ~ ~ a
S 0 N D J F M A M J J A 8 M A M J J A F 0_-uv-~--
--
ltoo e 14 a ~ 9 b 913 ~ ~ lJ
~~ 5~ 5 rs ~ IS 516 5~ 516 Y 90-i
~ -
91 100 419 sl5 ~ 91
~13 f 6~ 69 8 ~r14 middot80-
214 ~3 S[I 1100
- I-
I 2 lo 3[1 414
13 4 2- 71 70-
9 13 lioo _
1 0[8 lio 1j8
60-
719 fig 91s 100 ~~ e E~
i 213 215 3 f -34 415 418 51
50-I
I
IS ~12 100 1 I
r n
40- - r-l --
11
30-
f I
middot~O-
- - -- bull f- 10-- - _-
-~
-
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
CONTRACTOR V P EUSEBIO CONSTRUCTION INC BICOL SECONDARY BIDDING DATE NOVEMBER II 1977 PACK A
I
OFFICIAL STARTING DATE SEPTEMBER 181978 ~ ORIlINAL COMPLETION DATE MARCH 10 1980 STO DOMINGO - BU~A - d
i APPROVED REVISED COMPLETION DATE PROG RESt PROBABLE COMPLETION DATE MARCH 10 1980
I
I- -I -I i
~-I
I T E M 21amp1 01amp1 19 7 8 ~~3 1-1amp1 J ~~~ ~ z -~
I
8 ~o 0 J J A S 0 N 0 J F
II ~7 sk 85 bull I GENERAL 525 8723 458
lIS
P I~ 9 14
EARTHWORK 5317 6901 3669 14 116 312
III SURFACE COURSES 2575 699
AND PAVEMENT 180
b 0 5 IV STRUCTURES 1583 3500 5 54
I a
TOTAL 1000
PROGRESS j
Scheduled
)~
gt-Actual
ACTUAL I
4861 I
I I ~
~5 ~
~
SCHEDULED 547C f IReport CXWLETION ~ Ilion Fag
~
vIoue ~
nl periN
f LEGEND -- ORIGINAL SCHEDUlED PROGRESS
----~------ ACTUAL p~SS
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
AtfaChmnt A-I
~ AM) FEEDER ROADS MONTHLY PROGRESS REPORT AS Of JULY 311979
~~E III PREPARED BY JUAN ITO R VILLAMIL RE
UCT NO I 7 ) NET CONTRACT BID AMOUNT ~ 11887 77~ 20 OMBAO (SUB-PROJECT
5S CHART APPROVED REVISED CONTRACT AMOUNT 1148867390
CURRENT ESTIMATED FINAL COST
III 19 B 0
197 9 ~ t I 2 I
0 N 0 J F M A M J J A 8 F M A M J J A S 100-t4 17 ~8 ~ 89 9 10 9 91g 913 914 9~ 96 9 tzA ~ _9 ~IOO
10 J rr E 17 EI7 815 SIS EI7 ~~
90-7 19 8 9 14 917 JbO
H ~~ 34 ~II lt4~ 6 ~ 14 IlL -ltI
418 5~ 612 613 613 [I 80-
p 114 2 19 4 l 41 lt4 ~ 5 17 ill sis 1100 ~
[2 2 2 l 70-
15 113 2 t5 313 41 4~ 5[7 014 2 7t9 et6 9~ ~ ~J ~fOO I ~A
Ie 13 13 13 17 i9 5L 60-
lI ~o-
V I
l-L
I
40-
v
[ ~o-
---- -I I I
If 20--
I
V
~ 10-
0-
~
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
CONTRACTOR JPY CONSTRUCTON BICOl SECONDAR~ BIDDING DATE JANUARY 9 1978 PACK OFFICIAL STARTING DATE JULY 15 1978 CONT~
ORIGINAL COMPLETION DATE JANUARY 5 1980 POlANGUI- LIDON6-
APPROVED REVISED COMPLETION DATE PROGRE~
PROBABLE COMPLETION DATE JANUARY 5 1980
~ ~ ~~
~~ u I T E M ~~~ J 19 7 8 ~Dt J ~Q ~cI
t~ o~ zgt Dto 8 Q u J J A S 0 N l) J
4 ~2 ~ 8 614 81s fJ 19 I GENERAL 1126696 075
f7ij r~ 26 8
0 001 4 18 17
EARTHWORK 3636 68 19 2479 8 J4 19 19 31 145
III BASE COURSE 892 000 000
IV SURFACE COURSE~ 2138 000 000 AND PAVEMENT
0 OI~ 1 4 V STRUCTURES 3217 2027 f 52
096 2 06 ~
VI INCIDENTAL CONSTRUCTION 005 000 000
TOTAL 1000
PROGRESS
Scheduled [Adaa l~
~ ACTUAL 320euro
1
- ~ --- ~ I~ -e 5
SCHEDULED 5612 -~ Report ~ COMPLETION Month Flag --- ~
Previous Thl period
LEGEND - - - ORIGINAL SCHEDULED PROGRiSS ---------- ACTUAL PROGRESS
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
I bull bull Att _ bull A-I
~y AND FEEDER ROADS MONTHLY PROGRESS REPORT AS OF JULY 31 1979
~AGE III PREPARED BY JUAN ITO R VILLAMIL RE
trRACT NO2 _--NET Q)NfRACT-BID AiJOUNT ~ 10647071 SO
IB-BUHI (SUB-PROJECT 138) -I APPROVED REVISED CONTRACT Aplaquo)UNT
ESS CH ART CURRENT ESTIMATED FINAL COST
~
197 9_~ 198 0 ILl
~ ~ I ~ F M A M J J A S 0 N 0 J F M A M J J A
90 96 A ~ 100-
e ~ 72 74 77 80 82 815 87 93 7 I]
26 ~3I 16 38 16 38 16 38 16 6385 66 raG 44 612 96 9 5 IPo 90-
17 26 35 53 71 80 85 -lI
31 145 39 14 48 9548 95 48 95 5848 68 19 II 10 12 25 37 50 62 75 87 I~
80-
I
V 70-P 15 31 46 62 77 100
I rl
60-4 7 25 42 58 11 83 etr 910 96 100
L r 5 1183 1358 I~ 85 I~ 51 1746fC 27
- 50- 10 40 100
11
40- 1
-I 30-
V
r--_ ---_ 20-
1- 1 I ~
10-
I 0-
~
-
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
Attachment B
DCCD ENGINEERING CORPORATION
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
CONSULTANTS STAFF As of July 31 1979
CONSULTANT TECHNICAL STAFF
Key Staff
1 2 3
Prujlct Managlr Resident Engineer Deputy Rcsidlnt EngineCr
Support Staff
1 2 3 4 5 6 7
Ass t C j v il En gin l l1 S In s p(cto r s La borato r y Eng in llr Survey Chids Survey M (111 blrS Sr La b Technicians Draftsmen
1 1 4
3 6 1 3 8 3 2
ADMINISTRATIVE ST AFF AND SUPPORT PERSONNEL
1 Administrativ( Offic er 1 2 A dminis t ra li v( Ass is tan t 1 3 Ex (cutiv l Secretary 1 4 Accountant 1 5 SlC rdary 1 6 ClerkTypis ts 5 7 Utility ManJanitor Z 8 Drivers 5 9 Security Guards 2
T o T 1 L bull bull bull bull bull
6
26
19
51 vv
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
Attachment C
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
10
Suberoj cd No 7 (St~ Dominao-Bula-Ombao)
CONTRACTORS STAFF V P EUSEBIO CONSTRUCTION INC
As of July 31 1979
Supervising Project Manager
Project ManagLr 1
Engin eers 3
SurveyorsAides 6
Super intendents For em en 5
AdministrativeAccounting 9
Skilled Laborerb 66
Unskilled Laborers 77
Timekeeper 3
Security Guards 5
T o T A L
176
176 vvv
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
Attachment C - 1
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
Subproject No 12 (Iriga-Salvacion-Bato)
CONTRACTORS STAFF PHILCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
Project Manager 1
Resident Manager 1
SuperintendentForeman
AdministrativeAccounting 9
Skilled Laborers 7
Unskilled Laborers 8
T o T A L
28
28 vv
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
Attachment C - 2
BICOL RIVER BASIN SECONDARY amp FEEDER ROADS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
9
Subproj ect No 13 -A (Polangui- LidongJ
CONTRACTORS STAFF WILLIAM UY-CONTRACTOR
As of July 31 1979
Project Manager 1
Engineers 2
SuperintendentsForemen 5
Surveyors Aides 13
AdministrativeAccounting 11
Skilled Laborers 48
Unskilled Laborers 74
Timekeeper 2
Security Gua rds 10
T o T A L
166
166 vvv
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
Attachment C - 3
BICOL RIVER BASIN SECONDARY amp FEEDER RCA DS PROJECT PACKAGE III
1
2
3
4
5
6
7
8
Subproject No 13-B (Lidong-Buhi)
CONTRACTORS STAFF JPY CONSTRUCTION
As of July 31 1979
Engineers 1
SurveyorsAides 3
SuperintendentsForemen 5
AdministrativeAccounting 2
Skilled Laborers 28
Unskilled Laborers 56
Timekeeper 3
Security Guards 2
T o T A L
100
100 vvv
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
Attachment D
CONTRACTORS EQUIPMENT ON SITE V p EUSEBIO CONSTRUCTION INC
As of July 31 1979
NO OF EQUIPMENT DESCRIJTION UNITS
1 Bulldozers DB 1 D6 1 DBSA 1
2 Dump Trucks Isuzu 2
3 Payloader Komatsu 1
4 Roadgrader Mitsubishi 1
5 Roller Steel Tandem 1 Roller Pneumatic Sakai 1
6 Vibratory Roller 1
7 Transit Mixers 4
8 Concrete Mixers 2-baggers 1
9 Crawler Crane 1
10 Concrete Vibrator 2
11 Water Truck 1
12 Welding Machine 1
13 Steam Hammer Kobe 32 1
14 Water Pump 3 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbullbullbull
TOTAL
3
2
1
1
2
1
4
1
1
2
1
1
1
1
22 vv
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
Attachment D - 1
CONTRACTORS EQUIPMENT ON SITE WILLIAM UY-CONTRACTOR
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS
l Bulldozers DfE 3 1
D7 1 1
D8 1 1 (idle)
TD25 1
2 Dump Trucks Isuzu 12 3
3 Haulers Tournapulls 2 2
Euclid 1 1
4 Payloaders TCM 2 Allis Chalmers 1 Kimeo 1
5 Roadgraders Komatsu 1 Mitsubishi 1
6 Steel Roller Buffalo Tandem 1 Tandem 1
7 Pneumatic Wobble Watanabe 1 Sakai 1
lRental
8 As phalt Paver 1
9 Vibratory Roller Dynapae 1
10 Water Pump 2 Kohler 3 WiscoDsin 4 1
Sub-total
TOTAL
9
15
6
4
Z
2
3
1
1
4
47
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
CONTRACTORS EQUIPMENT ON SITE JPY CONSTRUCTION As of Juy 31 1979middot
Attachment D - 2
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bulldozers DSOA l(idle) 1 2
2 Dump Trucks Isuzu 7 7
3 Payloader Komatsu 1 1 Z
4 Roadgrader Mitsubishi 1 1
5 Pneumatic Roller Watanabe Z Z
6 Steel Roller Tandem Z Z
7 Sheepfoot Roller with Tractor l(idle) 1
S Water Truck Isuzu Rheo 1 1
9 Backhoe Poclain 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bull bullbull 19 vv
Under Repair
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
(William Uy- Contractor) page 2 - Equipment on Site
Carried Forward bullbull bull bull bull bull bull bull 47
11 Concrete Mixer
12 Concrete Vibrator
13 Cranes
14 Water Truck
15 Asphalt Paver
One-bagger Transit Mixer
Lorrain13 PampH
Isuzu wi sprinkle
3 1
2
1 1
1
1
4
2
2
1
1
TOT A L NUMBER OF EQUIPMENT ON SIT E bull bullbull 57 vv
~cUnder Repair
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v
Attachment D - 3
CONTRACTORS EQUIPMENT ON SITE PH1LCON BUILDERS amp DEVELOPERS INC
As of July 31 1979
NO OF EQUIPMENT DESCRIPTION UNITS TOTAL
1 Bdldozers Komatsu D8 1 Caterpillar D7 1 (idle) 2
2 Roadgrader Galion 1 1
3 Steel RoUer Galion 1 1
TOTAL NUMBER OF EQUIPMENT ON SITE bullbull 4 v