Blue Ribbon Update March 15, 2016
Building for the Future 2016-2019
2016 Schedule
Mary Castle Elementary Renovation $7,000,000
McKenzie Center for Innovation & Technology
$4,000,000
District Wide Upgrades $1,000,
000
Roof Replacements
$1,000,000
Lawrence Central High School (Exterior Facilities) $8,000,000
Lawrence North High School (Exterior Facilities) $8,000,000
Technology Upgrades
$1,000,000
Total
$30,000,000
2017 Schedule
Indian Creek Elementary Renovation $3,500,000
Skiles Test Elementary Renovation $3,500,000
Belzer Middle School Site/Athletic Fields $3,000,000
Harrison Hill Elementary Renovation $4,200,000
Roof Replacement $1,500,000
Technology Upgrades $3,000,000
District Wide Interior Upgrades $1,300,000
TOTAL $20,000,000
2018 Schedule Lawrence North High School Renovation $4,500,000
Lawrence Central High School Renovation $4,500,000
Oaklandon Elementary Renovation $3,500,000
Forest Glen Elementary Renovation $1,100,000
Fall Creek Valley Middle School Renovation $5,500,000
Roof Replacements $1,500,000
Brook Park Elementary Renovation $2,000,000
LECC HVAC Upgrades and site work $2,200,000
Amy Beverland Renovation $1,700,000
Technology Upgrades $3,000,000
District Wide Upgrades $500,000
Total
$30,000,000
2019 Schedule
Winding Ridge Elementary Upgrades $1,500,000
Sunnyside Elementary Upgrades $1,500,000
Amy Beverland ELC Upgrades $500,000
Brook Park ELC Upgrades $500,000
Mary Castle ELC Upgrades $500,000
Winding Ridge ELC Upgrades $500,000
Technology Upgrades
$3,000,000
Roof Replacement $1,500,000
District Wide Upgrades $500,000
Total
$10,000,000
Grand Total
$90,000,000
Mary Castle Schematic Plan
Admin
Mary Castle Elementary Scope:
• Move administration office to
front of building to create a
secure entry.
• Renovate existing classrooms
and pods with new technology,
marker walls, finishes, storage
and individual student cubbies.
• Renovate existing space to add
four new classrooms.
• Relocate and provide new
student restrooms.
• Increase size of existing
cafeteria for additional seating.
• Renovate existing Media Center
• Overall Interior Finish Upgrade
• Upgrade existing mechanical
system.
Classrooms
Cla
ssro
om
s Classrooms
RR
RR
Classrooms
Cafe
Media
Classrooms
RR
RR
Mary Castle Schematic & Scope
• Improve site circulation by
reconfiguring and separating bus
and parent drop off.
Parent &
Visitor
Parent &
Visitor BUS
McKenzie Scope
• Relocate as part of the new addition
Bernie’s Place Restaurant to front of
culinary area with new separate,
handicapped accessible public
entrance.
• Renovate existing space for new
appropriately sized culinary
classrooms and labs with new
technology and finishes.
• Building addition to include additional
square footage for Cosmetology
program and new public entrance
shared with Bernie’s Place Restaurant.
• Provide new public restrooms at
restaurant entry.
• Renovation of existing space for new
Cosmetology I & II and Barbering
classrooms and labs to include new
technology and finishes.
• Overall building renovation to include
renovation of building HVAC
controls.
Public
Cosmetology
Culinary
RR
McKenzie Schematic
Bu
ildin
g A
dd
itio
n
• Relocate as part of the new
addition Bernie’s Place
Restaurant to front of culinary
area with new separate,
handicapped accessible public
entrance.
• Building addition to include
additional square footage for
Cosmetology program and
new public entrance shared
with Bernie’s Place
Restaurant.
Bernie’s Place Restaurant
Salon Entrance
Lawrence
North
Schematic
• New home side bleachers with press
box and renovation of visitors
bleachers for handicapped
accessibility
• New fencing and access for band
onto field
• Additional site lighting for safety
and security
• Support other activities
T
Mu
lti-
Pu
rpo
se
Bleachers
T
T
• Reorganization of existing stadium for
clearer home and visitor entry with new
ticket entry points and circulation
• New End Zone Multi-Purpose Building
to include locker room space,
team/hospitality room, training room,
coaches & official space, storage and
support spaces
• New Restroom Concession Buildings
on home side
•Lawrence North High School Stadium •Lawrence North High School Grandstand
•Lawrence North High School End Zone Building
Lawrence Central Schematic
• Reorganization of existing
stadium for clearer home and
visitor entry with new ticket
entry points and circulation.
• New End Zone Building to
include locker room space,
team/hospitality room, training
room, coaches & official space,
storage and support spaces.
• New home side bleachers with
press box and renovation of
visitors bleachers for
handicapped accessibility.
• New Restroom Concession
Buildings on home and visitor
sides.
• New fencing and access for
band onto field
• Additional site lighting for
safety and security.
• Support other outdoor activities
Multi-Purpose
T T
T B
leac
her
s
•https://youtu.be/Pdt3ZaQzMPw •https://youtu.be/uHQGFzcs4ws