of 51
7/31/2019 Boiler Erection 2
1/51
Erection of Steam GeneratorsErection of Steam Generators 11
WelcomeWe come toto
Power PlantPower Plant
ErectionErection
Presentation on Erection ofPresentation on Erection of
Steam GeneratorsSteam Generators
7/31/2019 Boiler Erection 2
2/51
Erection of Steam GeneratorsErection of Steam Generators 22
TONNAGE SCHEDULE OF SG
10000
6000
4500
4000
1500
6500
Structures Pressure Parts Rotary Machines & Mills
Ducting Fuel Oil system& piping ESP
7/31/2019 Boiler Erection 2
3/51
Erection of Steam GeneratorsErection of Steam Generators 33
1.0 Sequence of erection1.0 Sequence of erection
Erection of Main and AuxiliaryErection of Main and Auxiliarycolumnscolumns
Erection of MBLs (Main Brace Level)Erection of MBLs (Main Brace Level)
Erection ofErection ofCeiling GirdersCeiling Girders
Boiler Drum LiftingBoiler Drum Lifting
http://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Ceiling%20Girder%20Erection.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Ceiling%20Girder%20Erection.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Ceiling%20Girder%20Erection.shs7/31/2019 Boiler Erection 2
4/51
Erection of Steam GeneratorsErection of Steam Generators 44
Erection of PentErection of Pent House Headers and RoofHouse Headers and Roof
Erection ofErection ofWater Wall tubesWater Wall tubesand Ringand RingHeaderHeader
Erection ofErection ofSuper heater coils,Super heater coils,ReheaterReheatercoilscoils,, Economizer coilsEconomizer coilsand Eco inletand Eco inletheaderheader
Erection ofErection ofBack Pass RoofBack Pass Roof, steam cooled, steam cooledwalls and back pass lower headerswalls and back pass lower headers
http://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Top%20view%20Hdrs.TIFhttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Top%20view%20Hdrs.TIFhttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/WW%20Erection.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/WW%20Erection.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20SH%20&%20RH%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20SH%20&%20RH%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20SH%20&%20RH%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20SH%20&%20RH%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20SH%20&%20RH%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20SH%20&%20RH%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20ECO%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20ECO%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/BP%20Roof%20Erection.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/BP%20Roof%20Erection.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/BP%20Roof%20Erection.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20ECO%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20SH%20&%20RH%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20SH%20&%20RH%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20of%20SH%20&%20RH%20coils.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/WW%20Erection.shshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Top%20view%20Hdrs.TIF7/31/2019 Boiler Erection 2
5/51
Erection of Steam GeneratorsErection of Steam Generators 55
Erection of Eco link, MS Pipe and RHErection of Eco link, MS Pipe and RH
inlet & outlet pipes.inlet & outlet pipes.
Hydro test of BoilerHydro test of Boiler
Installation and Trial of FD fanInstallation and Trial of FD fan
Installation and Trial of SAPHInstallation and Trial of SAPH
Completion of Secondary Air pathCompletion of Secondary Air path
7/31/2019 Boiler Erection 2
6/51
Erection of Steam GeneratorsErection of Steam Generators 66
Completion of Flue Gas path with FlapCompletion of Flue Gas path with Flap
DamperDamper
Installation and Trial of coal millsInstallation and Trial of coal mills
Boiler Light Up with LDO/ HFO/CoalBoiler Light Up with LDO/ HFO/Coal
Alkali Boil Out, Acid CleaningAlkali Boil Out, Acid Cleaning
Steam BlowingSteam Blowing
7/31/2019 Boiler Erection 2
7/51
Erection of Steam GeneratorsErection of Steam Generators 77
Synchronization of unitSynchronization of unit
Trial operationTrial operation
PG TestPG Test
Handing Over to O&M GroupHanding Over to O&M Group
7/31/2019 Boiler Erection 2
8/51
Erection of Steam GeneratorsErection of Steam Generators 88
2.0 Documents Required2.0 Documents Required
Erection DrawingsErection Drawings
Category 1 Drawing: Approved by NTPCCategory 1 Drawing: Approved by NTPC
Category 2 Drawing: Subject to commentsCategory 2 Drawing: Subject to comments
Category 3 Drawing: Not ApprovedCategory 3 Drawing: Not Approved
Category 2 Drawing: Taken for informationCategory 2 Drawing: Taken for information(Only conceptual drawing)(Only conceptual drawing)
ContdContd
7/31/2019 Boiler Erection 2
9/51
Erection of Steam GeneratorsErection of Steam Generators 99
WPSWPS
FQPFQP (Field Quality Plan)(Field Quality Plan)
Welding ScheduleWelding Schedule
Contract DocumentsContract Documents (e.g. LOA, LOI, NOA Scope of(e.g. LOA, LOI, NOA Scope ofwork, General &Special condition of contract etc.)work, General &Special condition of contract etc.)
2.0 Documents Required2.0 Documents Required
http://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Boiler%20Structure%20FQP.pdfhttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Boiler%20Structure%20FQP.pdfhttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Boiler%20Structure%20FQP.pdf7/31/2019 Boiler Erection 2
10/51
Erection of Steam GeneratorsErection of Steam Generators 1010
3.0 T&P Requirement3.0 T&P Requirement
FMC-LS-718 CraneFMC-LS-718 Crane : 1 No.:: 1 No.: 350 MT capacity350 MT capacitywith ringerwith ringer
FMC-LS-248FMC-LS-248 CraneCrane: 1 No.:: 1 No.: 150 MT capacity150 MT capacity KH-700KH-700 CraneCrane: 1 No.:: 1 No.: 150 MT capacity150 MT capacity
KF-500KF-500Crane: 1 No.:Crane: 1 No.: 100 MT capacity100 MT capacity TFC-280TFC-280 Crane: 6 No.:Crane: 6 No.: 75 MT capacity75 MT capacity TFC-75TFC-75 Crane: 1 No.:Crane: 1 No.: 25 MT capacity25 MT capacity WinchesWinches : 15 No. (of capacity: 15 No. (of capacity
2MT,5MT, 10MT, 20MT)2MT,5MT, 10MT, 20MT)
WinchesWinches : 2 No. (of capacity 30MT): 2 No. (of capacity 30MT) Chain Pulley Blocks, Hook chooks & Wire ropeChain Pulley Blocks, Hook chooks & Wire rope
slings as and when required.slings as and when required.
7/31/2019 Boiler Erection 2
11/51
Erection of Steam GeneratorsErection of Steam Generators 1111
4.0 Erection Strategy4.0 Erection Strategy
PreassemblyPreassembly :: The main tool toThe main tool to
reduce the project cycle timereduce the project cycle time
Erection Sequence :Erection Sequence : TheThe
foresightednessforesightedness of the Executerof the Executer
http://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20stratgy.xlshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20stratgy.xlshttp://var/www/apps/conversion/current/tmp/scratch11425/G:/Misc/Presentations/Boiler%20Presentation/Erection%20stratgy.xls7/31/2019 Boiler Erection 2
12/51
Erection of Steam GeneratorsErection of Steam Generators 1212
5.0 System of Nomenclature of5.0 System of Nomenclature of
contractor (e.g. BHEL)contractor (e.g. BHEL)
PG (Product Group)PG (Product Group)
MA (Main Assembly)MA (Main Assembly)
DU No. (Dispatch Unit number)DU No. (Dispatch Unit number)
7/31/2019 Boiler Erection 2
13/51
Erection of Steam GeneratorsErection of Steam Generators 1313
6.0 Project Cycle Time6.0 Project Cycle Time
36 months for Coal firing &36 months for Coal firing &
SynchronizationSynchronization
42 months for Completion of Trial42 months for Completion of Trial
operation & PG Test.operation & PG Test.
7/31/2019 Boiler Erection 2
14/51
Erection of Steam GeneratorsErection of Steam Generators 1414
SL NO MILESTONE MONTHS (FROMNOA)
REMARKS
1Establishment Of Site Office 6
1.1Mobilization Of Installation Staff At
Site
8
2Commencement of Boiler Erection 11
3Boiler Drum Lifting 15 Approx. Tonnage17%
4 Boiler Hydraulic Test (Drainable) 26 Approx. Tonnage61%
5Readiness of SG C&I for Boiler Lightup
30
6Readiness of ESP 31
7Boiler Light Up & Alkali Boil out 32 Approx. Tonnage81%Acid cleaning completion 33
9Steam Blowing completion. 34
10Safety valve Floating 35
11Steam to TG Set 36
12Coal Firing 36 Approx. Tonnage95%
7/31/2019 Boiler Erection 2
15/51
Erection of Steam GeneratorsErection of Steam Generators 1515
M O N T H L Y E R E C T I O N D E T
0
5 0 0
1 0 0 0
1 5 0 0
2 0 0 0
2 5 0 0
OCT'0
2
NOV'0
2
DEC'0
2
JAN'0
3
FEB'0
3
MAR'O
3
APR'0
3
MAY'0
3
JUN'0
3
JULY'03
AUG'03
SEP'0
3
OCT'0
3
NOV'0
3
DEC'0
3
JAN'0
4
FEB'0
4
MAR'O
4
APR'0
4
MAY'0
4
JUN'0
4
JULY'04
AUG'04
SEP'0
4
OCT'0
4
NOV'0
4
DEC'0
4
JAN'0
5
FEB'0
5
MAR'O
5
APR'0
5
MAY'0
5
JUN'0
5
JULY'05
AUG'05
SEP'0
5
M O N
QTY
(MT)
0
5 0 0 0
1 0 0 0 0
1 5 0 0 0
2 0 0 0 0
2 5 0 0 0
3 0 0 0 0
QTY(MT)
B L R # 3 M O N T H L YB L R # 4 M O N T H L YB L R # 3 C U M M .B L R # 4 C U
7/31/2019 Boiler Erection 2
16/51
Erection of Steam GeneratorsErection of Steam Generators 1616
H P E Q U I V A L E N T J O I N T C O M
0
1 0 0 0
2 0 0 0
3 0 0 0
4 0 0 0
5 0 0 0
6 0 0 0
7 0 0 0
JULY'03
AUG'03
SEP'0
3
OCT'0
3
NOV'0
3
DEC'0
3
JAN'0
4
FEB'0
4
MAR'O
4
APR'0
4
MAY'0
4
JUN'0
4
JULY'04
AUG'04
SEP'0
4
OCT'0
4
NOV'0
4
DEC'0
4
JAN'0
5
FEB'0
5
MAR'O
5
M O N
JOINTS
(NO.)
0
5 0 0 0
1 0 0 0 0
1 5 0 0 0
2 0 0 0 0
2 5 0 0 0
3 0 0 0 0
3 5 0 0 0
JOINTS
(NO.)
U # 3 M O N T H L YU # 4 M O N T H L YU # 3 C U M M U L A T I V EU # 4 C U M M U
7/31/2019 Boiler Erection 2
17/51
Erection of Steam GeneratorsErection of Steam Generators 1717
M O N T H L Y T O N N A G E D
0
1 0 0
2 0 0
3 0 04 0 0
5 0 0
6 0 0
7 0 0
8 0 09 0 0
1 0 0 0
OCT'0
2
NOV'0
2EC
'02
JAN'0
2
FEB'0
2
MAR'O
3
APR'0
3AY
'03
JUN'0
3
JULY'03
AUG'0
3
SEP'0
3
OCT'0
3
NOV'0
3
DEC'0
3
JAN'0
4
FEB'0
4
MAR'O
4
APR'0
4AY
'04
JUN'0
4
JULY'04
AUG'0
4
SEP'0
4
OCT'0
4
NOV'0
4EC
'04
JAN'0
5
FEB'0
5
AR'O5
APR'0
5
MAY'0
5
JUN'0
5
JULY'05
AUG'0
5
SEP'0
5
M O N
0
1 0 0 0
2 0 0 0
3 0 0 0
4 0 0 0
5 0 0 0
6 0 0 0
7 0 0 0
CUMMULAT
IVEMT
E S P # 3 M O N T H L YE S P # 4 M O N T H L YE S P # 3 C U M M .E S P # 4 C
7/31/2019 Boiler Erection 2
18/51
Erection of Steam GeneratorsErection of Steam Generators 1818
7.0 (A) Contract Value for Korba, Stage- III (1X500 MW)7.0 (A) Contract Value for Korba, Stage- III (1X500 MW)
under LOI No. 4669under LOI No. 4669
Description Prices (Rs)
1 0 Ex Works Price for main equipment 8,49,50,00,000
2 0 Ex Works Price for mandatoryspares 36,50,00,000
3 0 Type Test Charge 3,25,00,000
TOTAL 8,89,25,00,000
Total in words: Rupees Eight Billion Eight Hundred Ninety TwoMillion Five Hundred Thousand Only.
7.0 Budget
7/31/2019 Boiler Erection 2
19/51
Erection of Steam GeneratorsErection of Steam Generators 1919
7.0 (B) Contract Value for Korba, Stage- III (1X500 MW)7.0 (B) Contract Value for Korba, Stage- III (1X500 MW)
under LOI No. 4670under LOI No. 4670
Sl No Description Prices (Rs)
1 0 Unloading, receipt, handling, storage, completeinstallation, supervision, pre commissioning,commissioning, completion of facilities, conductingguarantee tests
86,00,00,000
2 0 Local transportation including port clearance & portcharges and inland insurance charges for mainequipment
19,35,00,000
3 0 Local transportation including port clearance & portcharges and inland insurance charges for mandatory
spares
1,40,00,000
TOTAL 1,06,75,00,000
Total in words: Rupees One Billion Sixty Seven Million Five HundredThousand Only.
7/31/2019 Boiler Erection 2
20/51
Erection of Steam GeneratorsErection of Steam Generators 2020
8.0 Scope of Work Under SG8.0 Scope of Work Under SG
PackagePackage
Furnace ,Water Wall Headers, Tubes,Furnace ,Water Wall Headers, Tubes,
RisersRisers
Drum with internals and fittingsDrum with internals and fittings
Super heaters, Re heaters &Super heaters, Re heaters &Economizer with its auxiliariesEconomizer with its auxiliaries
7/31/2019 Boiler Erection 2
21/51
Erection of Steam GeneratorsErection of Steam Generators 2121
Water circulation pumps with drivesWater circulation pumps with drives
and coolersand coolers
Spray type attemperators withSpray type attemperators with
valves and accessoriesvalves and accessories
Complete valves and fittings forComplete valves and fittings for
boiler & aux.boiler & aux.
Soot blowing systemSoot blowing system
7/31/2019 Boiler Erection 2
22/51
Erection of Steam GeneratorsErection of Steam Generators 2222
Thermal insulation for the boiler andThermal insulation for the boiler and
pipingpiping
FD fans with silencers (2 no. per unit)FD fans with silencers (2 no. per unit)
Motors for the aboveMotors for the above
ID fans (2 no. per unit)ID fans (2 no. per unit)
Motors for the aboveMotors for the above
7/31/2019 Boiler Erection 2
23/51
Erection of Steam GeneratorsErection of Steam Generators 2323
Regenerative air pre heaters 4 No. perRegenerative air pre heaters 4 No. per
unit (2 no. PAPH &2 no. SAPH)unit (2 no. PAPH &2 no. SAPH)
Steam coil air pre heaters4 No. per unitSteam coil air pre heaters4 No. per unit
Coal preparation system which includesCoal preparation system which includesraw coal chutes, bunker shut off gates andraw coal chutes, bunker shut off gates and
raw coal feeders.raw coal feeders.
Coal pulverisers with motors (10 no. perCoal pulverisers with motors (10 no. per
unit) Bowl & Roller type XRP1003unit) Bowl & Roller type XRP1003
7/31/2019 Boiler Erection 2
24/51
Erection of Steam GeneratorsErection of Steam Generators 2424
Seal air fans (2 No. per unit)Seal air fans (2 No. per unit)
Coal burnersCoal burners
PF piping and ceramic bendsPF piping and ceramic bends
Complete ductingComplete ducting
DampersDampers
7/31/2019 Boiler Erection 2
25/51
Erection of Steam GeneratorsErection of Steam Generators 2525
Fuel oil systemFuel oil system
Galleries, stairways, walkways,Galleries, stairways, walkways,
roofing, handrails, platforms,roofing, handrails, platforms,
gratings etc.gratings etc.
Electrostatic precipitatorsElectrostatic precipitators
Cranes and hoistsCranes and hoists
7/31/2019 Boiler Erection 2
26/51
Erection of Steam GeneratorsErection of Steam Generators 2626
9.0 Constructional Details Of Boiler9.0 Constructional Details Of Boiler
Design Wt. of each unitDesign Wt. of each unit
(Boiler + ESP):32000 MT Approx.(Boiler + ESP):32000 MT Approx.
No of ceiling girdersNo of ceiling girders : 6: 6
7/31/2019 Boiler Erection 2
27/51
Erection of Steam GeneratorsErection of Steam Generators 2727
Elevation of T.O.S. of main columnsElevation of T.O.S. of main columns
84.945 m84.945 m
Type of Main columns: Star sectionType of Main columns: Star section
Type of aux columns: Box sectionType of aux columns: Box section
No. of HP joints: 27000 approx.No. of HP joints: 27000 approx.
7/31/2019 Boiler Erection 2
28/51
Erection of Steam GeneratorsErection of Steam Generators 2828
No of Coal elevationsNo of Coal elevations : 8 to 10: 8 to 10
No of Oil elevationsNo of Oil elevations : 4 to 5: 4 to 5
No of front & rear WW tubesNo of front & rear WW tubes : 269: 269
No of left & right side WW tubes: 212No of left & right side WW tubes: 212
7/31/2019 Boiler Erection 2
29/51
Erection of Steam GeneratorsErection of Steam Generators 2929
No of blocks in Eco systemNo of blocks in Eco system : 2 to 3: 2 to 3
No of rows of Eco system coils : 184No of rows of Eco system coils : 184
No. of tubes in one coil of EcoNo. of tubes in one coil of Eco : 6: 6
No of blocks in LTSH systemNo of blocks in LTSH system : 2: 2
No of rows of LTSH system coilsNo of rows of LTSH system coils : 124: 124
No. of tubes in one coil of LTSHNo. of tubes in one coil of LTSH : 6: 6
7/31/2019 Boiler Erection 2
30/51
Erection of Steam GeneratorsErection of Steam Generators 3030
No of rows of RH systemNo of rows of RH system : 74: 74
No. of tubes in one coilNo. of tubes in one coil : 12: 12
No of rows of Platen coilsNo of rows of Platen coils : 25: 25
No. of tubes in one coil of Platen : 16No. of tubes in one coil of Platen : 16
7/31/2019 Boiler Erection 2
31/51
Erection of Steam GeneratorsErection of Steam Generators 3131
No of rows of Divisional SH systemNo of rows of Divisional SH system
coilscoils : 6: 6
No. of coils in one row of Div. SHNo. of coils in one row of Div. SH: 8: 8
No of tubes in one coil of Div. SHNo of tubes in one coil of Div. SH
: 9: 9
No of LRSBNo of LRSB : 34: 34
No of Wall blowersNo of Wall blowers : 88: 88
7/31/2019 Boiler Erection 2
32/51
Erection of Steam GeneratorsErection of Steam Generators 3232
FD fanFD fan : 2 No, AXIAL AP1-26/16,: 2 No, AXIAL AP1-26/16,
Blade pitch control, 980 rpm, 1300Blade pitch control, 980 rpm, 1300kw motorkw motor
PA fanPA fan : 2 No, AXIAL AP2-20/12,: 2 No, AXIAL AP2-20/12,
Blade pitch control, 1480 rpm, 2950Blade pitch control, 1480 rpm, 2950kw motor.kw motor.
ID fanID fan :2 No, NDZV 47 SIDOR, Inlet:2 No, NDZV 47 SIDOR, Inlet
damper + VFD control, 580 rpmdamper + VFD control, 580 rpm4050 kw motor4050 kw motor
7/31/2019 Boiler Erection 2
33/51
Erection of Steam GeneratorsErection of Steam Generators 3333
10.0 Constructional Details of ESP10.0 Constructional Details of ESP
ESP efficiency: 99.914 %ESP efficiency: 99.914 %
No of ESP passes: 4 pass per unitNo of ESP passes: 4 pass per unit
No of fields : 8 fields/passNo of fields : 8 fields/pass
7/31/2019 Boiler Erection 2
34/51
Erection of Steam GeneratorsErection of Steam Generators 3434
Total no. of collecting electrodes perTotal no. of collecting electrodes perboilerboiler : 11712: 11712
Nominal length of collecting elNominal length of collecting el ::13 m13 mNominal length of collecting el :750Nominal length of collecting el :750
mmmm Type of emitting el: Spiral withType of emitting el: Spiral with
hookshooksSize of emitting electrode: 2.7 mmSize of emitting electrode: 2.7 mm
dia.dia. Total no of emitting electrodes perTotal no of emitting electrodes per
boilerboiler : 1,03,680: 1,03,680
7/31/2019 Boiler Erection 2
35/51
Erection of Steam GeneratorsErection of Steam Generators 3535
Rappers for collecting electrodesRappers for collecting electrodes
No. of rappers: one drop hammer perNo. of rappers: one drop hammer per
rowrow
Rapper size: 4.9 kgRapper size: 4.9 kg
Frequency of rap: varying from 20 rapsFrequency of rap: varying from 20 raps
per hour at inlet field to 1 rap per hourper hour at inlet field to 1 rap per hour
at the exit field.at the exit field.
7/31/2019 Boiler Erection 2
36/51
Erection of Steam GeneratorsErection of Steam Generators 3636
Rappers for emitting electrodesRappers for emitting electrodes
No. of rappersNo. of rappers : Approx. one drop: Approx. one drophammer for two rows of electrodes.hammer for two rows of electrodes.
Rapper sizeRapper size : 3.0 kgs: 3.0 kgs
Frequency of rapping: 10 raps per hourFrequency of rapping: 10 raps per hour No. of hoppers per unit: 32No. of hoppers per unit: 32
7/31/2019 Boiler Erection 2
37/51
Erection of Steam GeneratorsErection of Steam Generators 3737
11.0 Insulation Details11.0 Insulation Details
Mineral Wool
Pourable RefractoryCastable Refractory
7/31/2019 Boiler Erection 2
38/51
Erection of Steam GeneratorsErection of Steam Generators 3838
12.0 Stress Relieving of Ceiling12.0 Stress Relieving of Ceiling
GirdersGirders HeatingHeating up to 620 degree:up to 620 degree:
Web- @ 65 deg/hrWeb- @ 65 deg/hrFlangeFlange - @75 deg/hr- @75 deg/hr
Soaking:Soaking: At 620 degrees for a timeAt 620 degrees for a timeperiod ofperiod of
WebWeb - 96 Min.- 96 Min.
FlangeFlange - 135 Min- 135 Min
Cooling:Cooling: @ 65 deg/hr for both flange &@ 65 deg/hr for both flange &web up to 300 degrees and then left forweb up to 300 degrees and then left fornatural cooling.natural cooling.
7/31/2019 Boiler Erection 2
39/51
Erection of Steam GeneratorsErection of Steam Generators 3939
13.0 Boiler Mountings13.0 Boiler Mountings
Location No Set Pr.(Kg/cm2)
SafetyValves
Drum 2 207.0,209.0
4 211.1,211.1,213.2,213.2
SHoutlet
SV 2 188.5,188.5
ERV 5 185.5,185.5,186.6,186.6,186.6RH Inlet 4 52.4,52.4,54.0,54.0
Outlet(1) 4 49.4,49.4,50.9,50.9
Outlet(2) 4 48.4,48.4,48.9,48.9
Soot Blower 1 40
Waterlevelindicator
Drum DWLG 2
EWLI 4 -----------------------
7/31/2019 Boiler Erection 2
40/51
Erection of Steam GeneratorsErection of Steam Generators 4040
14.0 Materials used in Pressure Parts14.0 Materials used in Pressure Parts
Material Area of Application
SA 335 P91 (MS line)
SA 213 T91 (Re heater stage-II, SH Platen & Divisional)
SA 213 TP 347H (Platen& Div. SH, RH, SC spacers)
SA 213 T22 (Platen& Div. SH, RH tubes)
SA 213 T11 (Radiant Roof, LTSH )
SA210Gr C (WW panels, UCT, LCT,WW hanger tubes, WW screen tubes, WW bottomHdr nipples, BP SC wall tubes, BP hanger tubes)
SA106Gr C (Suction manifold & Disch. Line of CC pump, WW O/L Hdrs, Saturation
tubes
SA335 P 12 (DESH link LTSH to Div. I/L header & Div. O/L header to platen )
SA515Gr70 (DC pipes, Lower ring Hdrs)
SA387Gr12CL2 (Collector plate, Crown plate)
7/31/2019 Boiler Erection 2
41/51
Erection of Steam GeneratorsErection of Steam Generators 4141
15.0 Major steps taken to reduce15.0 Major steps taken to reduce
cycle timecycle timePre assembly:Pre assembly:
If we reduce the no of lifts, the cycle time of anyIf we reduce the no of lifts, the cycle time of anyactivity reduces itself. Therefore, two auxiliaryactivity reduces itself. Therefore, two auxiliary
columns of boiler are welded at ground and thencolumns of boiler are welded at ground and thenthey were erected in single lift. For examplethey were erected in single lift. For example
Aux column + Aux ColumnAux column + Aux Column
MBLMBL Bracing + Gusset PlateBracing + Gusset Plate
7/31/2019 Boiler Erection 2
42/51
Erection of Steam GeneratorsErection of Steam Generators 4242
During mill erection, union head andDuring mill erection, union head and
journal may be preassembled in yard,journal may be preassembled in yard,
transported to site and then erected. Thistransported to site and then erected. This
has reduced the number of lifts from 60has reduced the number of lifts from 60
to 30.to 30.
Coal pipes may be welded at groundCoal pipes may be welded at groundwhere ever it was possible.where ever it was possible.
7/31/2019 Boiler Erection 2
43/51
Erection of Steam GeneratorsErection of Steam Generators 4343
Foresightedness:Foresightedness:
If MBL members are not available inIf MBL members are not available insequence then ?sequence then ?
Planning for Space for movement ofPlanning for Space for movement of
crane for erecting ceiling girderscrane for erecting ceiling girdersMiddle columns &Middle columns &
Rear equipmentsRear equipments
7/31/2019 Boiler Erection 2
44/51
Erection of Steam GeneratorsErection of Steam Generators 4444
Planning for loose soilsPlanning for loose soils
CAT HAED structures developed atCAT HAED structures developed atground.ground.
Drum dragging saddles (2 no.)Drum dragging saddles (2 no.)fabricationfabrication
To use the psychological slack timeTo use the psychological slack time
After Drum Lifting: Erection of SilencersAfter Drum Lifting: Erection of Silencers& BP Roof P/A etc& BP Roof P/A etc
After Hydro TestAfter Hydro Test
7/31/2019 Boiler Erection 2
45/51
Erection of Steam GeneratorsErection of Steam Generators 4545
use of sliding pulley arrangement touse of sliding pulley arrangement to
erect the Economizer coils and LTSHerect the Economizer coils and LTSH
coils, which reduces the change overcoils, which reduces the change overtime from one coil to another.time from one coil to another.
Use of same resource for maximumUse of same resource for maximumtime e gtime e g
ScaffoldingsScaffoldings
Sky climbersSky climberscranescranes
7/31/2019 Boiler Erection 2
46/51
Erection of Steam GeneratorsErection of Steam Generators 4646
Supply of electricity supply fromSupply of electricity supply from
two sourcestwo sources
Installation of welding equipmentsInstallation of welding equipments
at different locationsat different locations
Arrangement for alternateArrangement for alternate
resources in critical areas likeresources in critical areas like
welding of P91 Materialwelding of P91 Material
7/31/2019 Boiler Erection 2
47/51
Erection of Steam GeneratorsErection of Steam Generators 4747
17.0 QUALITY ASSURANCE17.0 QUALITY ASSURANCE
* A- class check :* A- class check : criticalcritical
* B- class check:* B- class check: majormajor
* C- class check:* C- class check: minorminor
7/31/2019 Boiler Erection 2
48/51
Erection of Steam GeneratorsErection of Steam Generators 4848
How to ensure qualityHow to ensure quality ??
Use of good quality manpower andUse of good quality manpower and
material like argon gas, weldingmaterial like argon gas, welding
consumables etcconsumables etc
Deployment of qualified, experiencedDeployment of qualified, experienced
and sincere supervisorsand sincere supervisors
Higher frequency of inspectionHigher frequency of inspection
O S18 0 DEVIATIONS AND THEIR
7/31/2019 Boiler Erection 2
49/51
Erection of Steam GeneratorsErection of Steam Generators 4949
18.0 DEVIATIONS AND THEIR18.0 DEVIATIONS AND THEIR
DISPOSITIONING STRATEGIES:DISPOSITIONING STRATEGIES:
MDRMDR
SARSAR
NCRNCR
7/31/2019 Boiler Erection 2
50/51
Erection of Steam GeneratorsErection of Steam Generators 5050
19.0 SAFETY ASSURANCE19.0 SAFETY ASSURANCE
PEP talkPEP talk
DemonstrationsDemonstrations
Use of PPEsUse of PPEs
RewardReward
Warning & PenaltyWarning & Penalty
7/31/2019 Boiler Erection 2
51/51
ThankThank
YouYou