Currency: US Dollars
Project No:
Project Title: ANDMA Building in Heart
Location: Herat, Afghanistan
Tender No: 01
Tender Title: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
UNOPS
UNITED NATIONS OFFICE FOR PROJECT SERVICES
BILL OF QUANTITIES
ANDMA Building in Heart
Herat, Afghanistan
1017
2-Story Administration Building and a Guardhouse
NOTICE TO ALL BIDDERS - COMPLETE PROJECT PRICE:
3. Eventual claims for extra works are covered by project general
documentation of contract.
1. All bidders MUST examine the complete project documents. Thesedocuments include the Drawings, BOQ, Schedules and Specifications.
Any discrepancies between these documents are to be brought to the
immediate attention of UNOPS Engineer.
2. Quotation given by the contractor on this BOQ are to cover any and all
additional materials, labor or associated costs to complete the works as
documented on the complete project documents.
7/28/2019 Boq Andma Building
2/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, Afghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total
1. General
1.1 Preliminaries 1.1 Occupied Areas, 1.1 ExistingServices Schedule an d1.1 Items
to be supplied schedules
1 Pre-construction work, mobilisation activitiesincluding paper/ documentation tasks. LS 1.00
2 Post construction works and clean up.LS 1.00
1.2 General Requirements 1.2 Inspection notificationschedule an d1.2 Warranty
schedules
1 Testing and Operation/Maintenance Manuals.LS 1.00
Subtotal General
2. Site
2.0 Deal with Graves 2.1 Identified hazardous materialsan d2.3 Earthwork schedules
1 Deal with human remains found in unmarkedgraves on the site. Excavate, remove remains,
place in a suitable container, and re-bury
remains in a place to be agreed by local
authorities. All work to be carried out in a
manner that does not offend religious and
cultural rules and norms. No. 5.00
2.3 Earthwork 2.1 Identified hazardous materialsan d2.3 Earthwork schedules
1 Excavation (any soil type) for main buildingfoundation and surrounding yard for grading
purposes. This item includes disposal and
temporary support or shoring if needed. Seedrawing and schedule for details. CU.M 1,300.00
2 Excavation (any soil type) for guard roomfoundation. This item includes disposal and
temporary support or shoring if needed. See
drawing and schedule for details. CU.M 25.00
3 Excavation (any soil type) for septic tank. Thisitem includes disposal and temporary support
or shoring if needed. See drawing and
schedule for details. CU.M 110.00
4 Ground improvement under foundations ofmain building. This includes supplying of filling
materials and compacting the layers according
to schedule and drawings. CU.M 15.00
5 Soil backfilling on and around foundation of themain building up to ground level. This includes
supplying of needed materials. See drawings
and schedules for levels/dimensions and
details. CU.M 20.00
Pos.
UNOPS
DETAILS OF COMPONENT
Vertical Structures Unit
7/28/2019 Boq Andma Building
3/15
7/28/2019 Boq Andma Building
4/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, A fghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotaPos.
1 PCC lean concrete (10 Mpa) under thefoundations and any other places shown as
lean concrete for septic tank. CU.M 2.00
2 RCC (20 Mpa) at the foundtions of 2-storymain building. The quantity includes RCC at
foundations and tie beams under the ground. CU.M 18.00
3 RCC (20 Mpa) at the columns of first story ofmain building. CU.M 13.00
4 RCC (20 Mpa) at the columns of second storyof main building. CU.M 11.00
5 RCC (20 Mpa) at the beams of first story of
main building. CU.M 10.00 6 RCC (20 Mpa) at the beams of second story of
main building. CU.M 10.00
7 RCC (20 Mpa) at the slabs of first story of mainbuilding. CU.M 20.00
8 RCC (20 Mpa) at the slabs of second story ofmain building. CU.M 19.00
9 RCC (20 Mpa) at the RCC stair case insidemain building. CU.M 4.00
10 RCC (20 Mpa) at the parapet of main building.CU.M 4.00
11 RCC (20 Mpa) at the entire guard room. Thequantity includes RCC at foundations, floors,
columns, beams, ring beams, lintels, etc. CU.M 6.00
12 RCC (20 Mpa) at entire septic tank and its
manhole. The cost for RCCs here includes wallmounted fixed ladder inside the septic tank as
well. CU.M 15.00
13 PCC (20 Mpa) at the floors, roofs, side walks,ramps, window sills, kerbs, PCC pavements,
flowerpots, septic tank, yard, and any other
places shown as PCC in the drawings for main
building, guard room and the septic tank.
CU.M 63.00
3.5 Brickwork 3.5 Brickwork constructionschedule
1 Second Class Brick masonry with mortar formain building. This includes all brick walls/
brick masonry in the entire building. CU.M 110.00
2 Second Class Brick masonry with mortar for
guard room. This includes all brick walls/ brickmasonry in the entire building. CU.M 18.00
3.6 Stonework
1 Stone masonry with mortar at the foundationsand/or any places shown in the drawings for
main building. See drawing and schedule for
details. CU.M 50.00
2 Stone masonry with mortar at the foundationsand/or any places shown in the drawings for
guard room. See drawing and schedule for
details. CU.M 13.00
3.10 Concrete Unit Masonry 3.10 Concrete Unit Masonry
1 CMU masonry with mortar. This item coversCMU works on the roof and any other places
shown on the drawings for main building. The
cost includes all needed materials, steel bars,anchors etc and works. CU.M 7.00
Subtotal Structure
7/28/2019 Boq Andma Building
5/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, A fghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotaPos.
4. Enclosure
4.1 Waterproofing 4.1 Waterproofing systemschedule
1 Single layer bitumen membrane (Isogam) atthe floor and walls of toilets/kitchen and at the
ground floors of main building and as well as
guard room. This includes preparation of base
layers shown on the drawings. Refer to
schedule/drawing for details. SQ.M 255.00
4.2 Roofing 4.2 Roofing materials, an d4.2Gutter and Down pipe Schedules
1 Flat roof for the main building. The cost for thisitem includes all roof layers shown such as
rigid foam insulation layer, brick powder layer,
PCC beneath Isogam layer, Isogam layer and
the protective PCC layer on the Isogam. See
drawings for details. The cost also includes
Isogam and flashings needed for the parapet
around the roof. SQ.M 160.00
2 GI corrugated roof for water tank enclosure onthe roof of the building. The cost for this item
includes all roof layers such as GI sheet, steel
profiles for purlins, steel C-shape channels as
the supporting members, mineral wool layer
and the steel mesh supporting the mineral
wool layer, and as well as all needed materials
and accessories required for complete
installation of a functioning roof.
SQ.M 10.00
3 GI flat K-span roof for guard room. The cost forthis item includes all roof layers such as GI
sheet standing seam and mineral wool
insulation layer and all needed materials,
accessories, connections required for complete
installation of a functioning roof. SQ.M 51.00
4 Down pipes, PVC pipe class-B. This includesall accessories such as over flow and stuff-
holder required for complete installation such
as supplying, fixing and others as per drawing
and schedules. Lin M 40.00
4.3 Windows and Window Hardware 4.3 Window, 4.3 WindowHardware, 4.5 Annealed Glasses,
an d4.6 Glassblock work
schedules
1 Wooden frame windows for main building. Thework includes making, transportation,
installation, hardware, glazing, glass-block
work around window, insect screen, 3 coats of
oil-based painting, and other accessories
required for complete installation as per
drawings and schedule. SQ.M 102.00
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
7/28/2019 Boq Andma Building
6/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, A fghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotaPos.
2 Wooden frame windows for guard room. Thework includes making, transportation,
installation, hardware, glazing, glass-block
work around window, insect screen, 3 coats of
oil-based painting, and other accessories
required for complete installation as per
drawings and schedule. SQ.M 6.00
4.4 Doors and Door Hardware 4.4 Joinery doors 4.4 PVC doors,4.4 Steel doors an d4.5
Annealed Glasses schedules
1 Wooden frame doors for main building. Thework includes making, transportation,
installation, hardware, glazing, and other
accessories required for complete installation
as per drawings and schedule. SQ.M 58.00
2 Wooden frame doors for guard room. The
work includes making, transportation,installation, hardware, glazing, and other
accessories required for complete installation
as per drawings and schedule. SQ.M 9.00
3 Steel frame doors (for water tank enclosure onmain building). The work includes making,
transportation, installation, hardware, glazing,
1 coat of anti-rust followed by 2 other coats of
oil-based painting, and other accessories
required for complete installation as per
drawings and schedule. SQ.M 0.80
4 Steel doors [the access way to the roof of mainbuilding] plus steel type fixed ladder at first
floor hall. The work and the cost includes
construction and complete installation of inner
steel door to the ceiling of the first floor, andinstallation of outer steel plate pane at the roof,
and as well as wall mounted steel ladder as
shown. The cost also includes all
hardware/accessories/works/materials needed
to a complete and functioning job. The cost
also includes one coat anti-rust followed by 2
other coats of oil-based painting to all non-
galvanized steel surfaces as per given specs
and full satisfaction of UNOPS engineer.
LS 1.00
4.5 Glazing 4.5 Mirrors schedules
1 Mirrors (40x60cm) at toilets of main buildingand the guard room. This includes complete
installation. No 7.00
4.6 Glass Blockwork 4.6 Glass Block Schedule
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
NOTE: Cost for steel related items in this section
includes supplying materials, accessories,
connections, welding, any works, painting according
to the schedules and specifications for steel member
painting, which is at least on coat of anti-rust
followed by 2 other coats of oil-based painting for all
surfaces.
7/28/2019 Boq Andma Building
7/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, A fghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotaPos.
1 Mortar jointed panels glass blockwork atwindow 'W6'. This includes reinforcement and
all other accessories required for complete
work. See drawing and schedule for details. SQ.M 12.00
Subtotal enclosure
5. Interior
5.4 Suspended Ceiling 5.4 Suspended Ceiling Schedule
1 Lasani wooden board, 6mm, fixed ceiling forsoffits and ceilings of the water tank enclosure
on main building. The cost includes fixings,
accessories, materials, works, oil based
painting etc for a complete job to the full
satisfaction of Engineer. SQ M 10.00
2 Aluminum frame with 60x60 gypsum boardsuspended ceiling for guard room. The cost
includes fixings, accessories, materials, works,
etc for a complete job to the full satisfaction of
Engineer. SQ M 28.00
5.5 Joinery 5.5 Joinery fixtures schedule
1 Wooden frame, MDF finish, wall mountedcabinet at the kitchen for main building. See
drawings for details. The cost includes making,
installation, framing, hardware, finish, 3 coatsoil-based painting and all to the complete job.
LS 1.00
2 Wooden frame, MDF finish, wall mountedcabinet at the kitchen for guard room. See
drawings for details. The cost includes making,
installation, framing, hardware, finish, 3 coats
oil-based painting and all to the complete job.
LS 1.00
3 Wooden frame, MDF finish, floor mountedcupboard at the kitchen for main building. See
drawings for details. The cost includes making,
installation, framing, finish, hardware, stone
table top, splash back, 3 coats oil-based
painting and all to the complete job.
LS 1.00
4 Wooden frame, MDF finish, floor mountedcupboard at the kitchen for guard room. See
drawings for details. The cost includes making,
installation, framing, finish, hardware, stone
table top, splash back, 3 coats oil-based
painting and all to the complete job.
LS 1.00
5.6 Metalwork 5.6 Metal Fixtures Schedule
1 Metallic plaster beads for outer corners at thecorridors only, including edge of walls for main
building and as well as for guard room. This
includes any needed work for complete
installation. See schedules and drawings for
details. Lin M 95.00
7/28/2019 Boq Andma Building
8/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, A fghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotaPos.
2 Metal handrails, balustrades, infill andmoldings to concrete stairs for main building.
This includes any needed work for complete
installation and also includes painting as per
schedule and specification for metallic surface
painting. See drawing for details. Lin M 8.00
3 Metal guardrails at stair's landing for mainbuilding. This includes any needed work for
complete installation and also includes painting
as per schedule and specification for metallic
surface painting. See drawing for details.
Lin M 2.20 4 Metal handrails, balustrades, infill and
moldings to concrete for ramp. This includes
any needed work for complete installation and
also includes painting as per schedule and
specification for metallic surface painting. See
drawing for details. Lin M 11.00
5 Toilet roll holders for main building and guardroom. This also includes installation. No 7.00
6 Grab rail for handicap toilet. One complete set.This includes supplying and complete
installation. LS 1.00
7 Soap dishes for main building and guard room.This also includes installation. No 7.00
5.8 Fire Extinguishers and Blankets 5.8 Fire Extinguishers Schedule
1 Extinguishers at main building and guard room,wall mounted, powder-type (9kg). No 3.00
Subtotal Interior
6. Finish
6.1 Plastering 6.1 Plastering Schedule
Internal and external surfaces
1 Cement render medium CRM followed bycement render fine CRF on all internal and
external surfaces of walls/ ceilings/ beams/
columns/ reveals/ parapets, porches etc formain building. See schedule for detail. SQ.M 1,940.00
2 Cement render medium CRM followed bycement render fine CRF on all internal and
external surfaces of walls/ ceilings/ beams/
columns/ reveals/ etc for guard room. See
schedule for detail. SQ.M 200.00
6.3 Tiling 6.3 Wall tiling an d6.3 Floor tilingschedules
For main building:
1 Ceramic wall tiles for toilets, kitchen. The costincludes bed preparation, bedding and grout.
SQ.M 90.00
2 Ceramic floor tiles for toilets including bedpreparation, bedding and grout. SQ.M 43.00
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
7/28/2019 Boq Andma Building
9/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, Afghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotaPos.
3 Marble tiles for all rooms and halls where didnot receive ceramic tiles. The cost includes
bedding and grout. SQ.M 202.00
4 Marble skirting for all rooms and halls wheredid not receive ceramic tiles. The cost includes
bedding and grout. Lin M 210.00
5 Granite tiles (30mm) for stairs treads andlandings including bedding and grout. SQ.M 15.00
6 Granite tiles (10mm) for stairs raise includingbedding and grout. SQ.M 4.00
7 Granite skirting for stairs including bedding andgrout. Lin M 14.00
8 Granite tiles for internal window sill at windowW6, including bedding and grout. No 1.00
For guard room:
9 Ceramic wall tiles for toilets, kitchen. The costincludes bed preparation, bedding and grout.
SQ.M 40.00
10 Ceramic floor tiles for toilets including bedpreparation, bedding and grout. SQ.M 14.00
11 Marble skirting for all walls that did not receiveceramic tiles. The cost includes bedding and
grout. Lin M 13.00
6.6 Painting 6.6 Interior/Exterior paintingschedule
Internal surfaces
1 Flat water based: Interior, on all surfaces thatreceive cement plaster for main building. The
cost includes wall putty (gypsum filling) layer
before painting and all needed preparation of
the surfaces for painting. See schedule for
detail on this paint system SQ.M 1,450.00
2 Flat water based: Interior, on all surfaces thatreceive cement plaster for guard room. The
cost includes wall putty (gypsum filling) layer
before painting and all needed preparation of
the surfaces for painting. See schedule for
detail on this paint system SQ.M 105.00
External surfaces
3 Flat water based: Exterior, on all surfaces thatreceive cement plaster for main building. The
cost includes wall putty (gypsum filling) layer
before painting and all needed preparation of
the surfaces for painting. See schedule for
detail on this paint system SQ.M 490.00
4 Flat water based: Exterior, on all surfaces thatreceive cement plaster for guard room. The
cost includes wall putty (gypsum filling) layer
before painting and all needed preparation of
the surfaces for painting. See schedule for
detail on this paint system SQ.M 95.00
Subtotal Finishes
8. Water Services
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
7/28/2019 Boq Andma Building
10/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, Afghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotPos.
8.1 Water Services 8.1 Water services samples, 8.1Water system piping, 8.1 Sanitary
fixtures, 8.1 Water heater
schedules an d8.1 Water
Services Testing schedules
NOTE: The cost for all pipes exposed to
weather includes glass wool thermal insulation
cover. The cost given for all GI and PVC pipes
with diameter less than 60mm includes all
required fittings, accessories and work for
complete system installation. To be mentioned
that the following section cover watersanitation needs for main building, septic tank
and the guard room.
Water supply piping
1 GI water supply pipe D=32mm, includingfittings and installation. Lin M 80.00
2 GI water supply pipe D=25mm, includingfittings and installation. Lin M 110.00
3 GI water supply pipe D=20mm, includingfittings and installation. Lin M 100.00
4 GI water supply pipe D=15mm, includingfittings and installation. Lin M 148.00
5 Water supply bronze Valve D=32mm, includingfittings and installation. No 2.00
6 Water supply bronze Valve D=25mm, includingfittings and installation. No 3.00
7 Water supply bronze Valve D=20mm, includingfittings and installation. No 4.00
8 Damp proof Insulation rubber tape for all GIPiping. Lin M 200.00
9 Water supply inspection manhole less than1200mm deep. This includes excavation and
any needed work to make the manhole as per
drawings and schedule. No 1.00
Sanitation Piping
10 PVC pipe D=125mm, including supply andinstallation. This also includes supply and
installation of PVC pipe from GI sheet
downpipes to the open channel collector at the
side walks. Lin M 40.00 11 PVC pipe D=100mm, including supply and
installation. This also includes supply and
installation of PVC pipe from GI sheet
downpipes to the open channel collector at the
side walks. Lin M 95.00
12 PVC pipe D=50mm, including fittings andinstallation. Lin M 110.00
13 Ventilation PVC pipes D=100mm (from toiletsto roof). This also includes supplying and
installation of PVC screen at the pipe inlets
inside the toilets. See drawing and schedule
for details. Lin M 10.00
14 Ventilation PVC pipes D=50mm (from toilets toroof). This also includes supplying and
installation of PVC screen at the pipe inletsinside the toilets. See drawing and schedule
for details. Lin M 35.00
7/28/2019 Boq Andma Building
11/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, Afghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotPos.
15 PVC Elbow D=50x50,45, including supply andinstallation. No 2.00
16 PVC Elbow D=50x50,90, including supply andinstallation. No 8.00
17 PVC Elbow D=100x100,45, including supplyand installation. No 1.00
18 PVC Elbow D=100x100,135, including supplyand installation. No 4.00
19 PVC Tee D=100x50x100,45, including supplyand installation. No 4.00
20 PVC Tee D=50x100x50,45, including supply
and installation. No 7.00 21 PVC Tee D=50x50,45, including supply and
installation. No 5.00
22 PVC Tee D=100x100, 45, including supply andinstallation. No 2.00
23 Sewer Manhole. This includes excavation andany needed work to make the manhole
according to the drawings and schedules. No 7.00
Sanitary and other fixtures
24 Western toilet, including supply, installationand accessories. No 7.00
25 Ceramic sink at toilets and labs, includingmixer and all accessories, supplying and
installation. No 7.00
26 Shower, including supply, installation andaccessories. No 1.00
27 Floor trap D=50mm, including supply andinstallation. No 7.00
28 kitchen steel sink, Including supply andinstallation. No 2.00
29 Ventilation cap D=100mm, including supplyand installation. No 1.00
30 Ventilation cap D=50mm, including supply andinstallation. No 3.00
31 Service Sink, including supply and installation.No 2.00
32 Electrical water boiler with capacity of 50 Liter,including supply and installation. No 3.00
33 Electrical water boiler with capacity of 30 Liter,including supply and installation. No 2.00
34 PVC Reservoir capacity of 2000 Liter, includingsupply and installation. No 1.00
35 Grease Trap less than 1200mm deep. Thisincludes excavation and any needed work to
make the manhole according to the drawings
and schedules. No 2.00
Tube well:
Borehole
Drilling well (8") diameter in soil, any type.
Actual well depth will depend the site water
level. Lin M 80.00
36 Gravel river type 8-12mm in size.LS 2.00
37 PCC and clay seal to borehole.
LS 2.00
7/28/2019 Boq Andma Building
12/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, A fghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotaPos.
38 (6") diameter PVC pipe 7-10mm in thickness.The actual pipe length will be adjusted
according to the actual well depth in the site.
Lin M 50.00
39 (6") diameter PVC filter 7-10mm thickness.See schedule for slot sizes and other specs.
The actual pipe length will be adjusted
according to the actual well depth in the site.
Lin M 8.00
40 Insulation of casing and filter.LS 2.00
41 Gravel pack around casing, filters up to 10mfrom surface of ground. LS 2.00
42 Clay and cement pack from 10m to surfacelevel. LS 2.00
43 Water wash and Compression test of well.LS 2.00
44 Preparation of hydro geological section, yieldof well, water level, in report LS 2.00
45 Chemical and bacteriological analysis tests ofwater samples. No 2.00
46 Draw down test for wellLS 2.00
47 Manhole on top of the well More than1200mm deep. This includes excavation and
any needed work to make the manhole
according to the drawings and schedules. No 1.00
48 Installation of Italian 'Pedrollo' brand orequivalent submersible D=40mm water pumpwith 40 L\min discharge capacity capable of
153m total head, power capacity=4kw,three
phase. This item includes complete and
functioning pump installation and reinstating of
the place to the satisfaction of UNOPS
engineer if required. This also includes all
mechanical works needed for successful
installation. For electrical accessories required
for the pump installation refer to section 9.
Electrical Services down this document.
No 1.00
Subtotal Water Services
9. Electrical Services
9.1 Electrical Services 9.1 Electrical systems, 9.1Electrical supply mains, 9.1
Electrical switchboard design, 9.1
Main 380VAC Distribution
System, 9.1 Panel Construction,
9.1 Power accessories, 9.1
Lighting control and fittings, 9.1
Fire Detection Equipment
Schedule Schedules an dthe
Attachments
Note: for all items below the cost includes
complete/installations with all needed
accessories and works. To be mentioned that
the following section cover water sanitationneeds for main building and the guard room.
7/28/2019 Boq Andma Building
13/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, Afghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotPos.
Power Distribution Main and Sub Boards
1 30KA ISC /0.5Sec, 380Y/220 Volt. 3 Phase, 4Wire , 50Hz, having grounding bus and surge
arrestors with all accessories. Out door NEMA
enclosure type, Main Power Distribution Panel
Board (MDP) . No. 1.00
2 30KA ISC /0.5Sec, 380Y/220 Volt. 3 Phase, 4Wire , 50Hz, having grounding bus and surge
arrestors with all accessories. In door NEMA
enclosure type, Main Power Distribution Panel
Board (DP1) . No. 1.00 3 30KA ISC /0.5Sec, 380Y/220 Volt. 3 Phase, 4
Wire , 50Hz, having grounding bus and surge
arrestors with all accessories. In door NEMA
enclosure type, Main Power Distribution Panel
Board (DP2) . No. 1.00
4 30KA ISC /0.5Sec, 380Y/220 Volt. 3 Phase, 4Wire , 50Hz, having grounding bus and surge
arrestors with all accessories. Out door NEMA
enclosure type, Main Power Distribution Panel
Board (DP3) . No. 1.00
5 Main circuit breaker, MCCB, 3x80Amps.No. 1.00
6 Main circuit breaker, MCCB, 3x63Amps.No. 3.00
7 Main circuit breaker, MCCB, 3x40Amps.No. 1.00
8 Main circuit breaker, MCCB, 3x20Amps.No. 2.00
9 Circuit breaker, MCB, 1x32Amps.No. 3.00
10 Circuit breaker, MCB, 1x20Amps.No. 33.00
11 Circuit breaker, MCB, 1x16Amps.No. 6.00
Distribution cabling and wiring
12 1(4Cx16mm) PVC/PVC Insulated Cable, in50mm PVC electrical conduit.
Note: (conduit is only from hand hole to the
DP1) Lin M 65.00
13 1(4Cx10mm + 1x10mm ) PVC/PVC InsulatedCable, in 50mm PVC electrical conduit.
Lin M 6.00
14 1(4Cx6mm ) PVC/PVC Insulated Cable. Lin M 25.00
15 2(1C x 4mm) + 4mm GND wires pulled inPVC conduit, assorted colors as per phase
requirement RST/UVW, white color is for
neutral and green color for grounding, the duct
should not be filled more than 50%. Lin M 560.00
16 2(1C x 2.5mm) + 2.5mm GND wires pulled inPVC conduit, assorted colors as per phase
requirement RST/UVW, white color is for
neutral and green color for grounding, the duct
should not be filled more than 50%. Lin M 260.00
Fittings/Fixtures
17 10Amp Single Pole/Double Pole light switch.No 30.00
18 4x18W recessed mounted fluorescent lightfixture. Water proof and normal No 4.00
19 2x36W surface mounted fluorescent lightfixture No 25.00
7/28/2019 Boq Andma Building
14/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, A fghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost TotaPos.
20 1x36W surface mounted fluorescent lightfixture. No 22.00
21 1x32W ceiling mounted circular fluorescentlight fixture, Water Proof No 9.00
22 1x18W ceiling mounted circular fluorescentlight fixture, Water Proof No 4.00
23 1x18W wall mounted mirror light fixture, WaterProof No 2.00
24 1x20W wall mounted rechargeable emergencylight fixture. No 3.00
25 1x20W surface mounted rechargeable exit
light fixture. No 3.00 26 13Amp Duplex power receptacle.
No 55.00
27 16 Amp water proof power receptacle.No 10.00
28 20 Amp water proof power receptacle.Note: according to the drawings for AC & oven.
No 6.00
29 20 Amp non fuse disconnect switch.No 3.00
AC/Split Units and Exhaust fans
30 18000 BTU AC/ Split outdoor, indoor andremote control units with all accessories,220 V,
50HZ Samsung or equalingNo 1.00
31 12000 BTU AC/ Split outdoor, indoor andremote control units with all accessories,220 V,
50HZ Samsung or equalingNo 2.00
32 9000 BTU AC/ Split outdoor, indoor andremote control units with all accessories,220 V,
50HZ Samsung or equalingNo 7.00
33 50W ,220V, 50Hz exhaust fans .No 4.00
Electrical Grounding.
34 Grounding system according to the groundingdrawing with electrodes, ground ring and
grounding cables. Sets 2.00
Labeling
35 Proper and correct all circuits numbering, cablecircuit drawings, cable and switchboard
labeling to the full satisfaction of UNOPS
engineer. LS 1.00
Subtotal Electrical Services
7/28/2019 Boq Andma Building
15/15
Currency: US Dollars
Project No: 1017
Project Title: ANDMA Building in Heart
Location: Herat, Afghanistan
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Work Type
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Signature
Total for Interior
Total for General
Total for Site
UNOPS
SUMMARY ESTIMATE
Vertical Structures Unit
Total for Structure
Total for Enclosure
Total for Finish
Total for Water Supply Services
Agreed on behalf of Contractor UNOPS
Zero
Total for 2-Story Administration Building and a Guardhouse
Total for Electrical Services
Estimate Value for whole tender in words:
Signature
Address and
Mobile Number
Name Name
Position Position