Build something great™ > Community Consultative Committee meeting BORAL QUARRIES TEVEN 15 November 2017 Teven Quarry offices, Teven
Transcript
Page 1: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Build something great™

> Community Consultative

Committee meeting

BORAL

QUARRIES

TEVEN 15 November 2017

Teven Quarry offices, Teven

Page 2: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Agenda ˃ Welcome, administration and ‘safety moment’

˃ Quarry operations update

˃ Environmental management and performance

˃ Planning consent modification – one year on…

˃ Community participation and general business

Page 3: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Welcome, administration and ‘safety moment’

˃ Welcome and re-introductions

˃ Previous meetings – 2017 Whole of Community Meeting ˃ 8 June 2017

˃ Presentations and meeting notes from previous meetings are available from the quarry’s website

– www.boral.com.au/tevenquarry

˃ Any matters arising?

˃ Apologies for this meeting

˃ Safety moment

Page 4: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

> Quarry operations update

BORAL

TEVEN QUARRY

Build something great™

Page 5: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

˃ Pacific Highway upgrades ˃ Woolgoolga to Ballina

˃ Construction of the new Harwood Bridge

˃ Construction of Ferngrove

residential estate

˃ Local projects ˃ Internal supply to Boral Concrete plants

˃ Internal supply to Boral Asphalt plants

˃ Local civil construction companies

˃ Local supply to landscaping yards

˃ Local supply to Ballina Shire Council

Current and future projects

Page 6: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Zero/One/Ten Award

Page 7: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

IQA Innovation

Awards 2017

Page 8: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis
Page 9: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

> Environmental management and

performance

BORAL

TEVEN QUARRY

Build something great™

Page 10: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis
Page 11: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis
Page 12: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Averaging

Period g/m2/montha

Deposited Dustb Annual 4.00

a – Maximum total deposited dust level

b – Dust is assessed as insoluble solids as defined by

AS3580.10.1-1991 (AM-19) (At the nearest existing or

likely future off-site sensitive receptor)

Source: Table 7.1 (Page 28) of the Approved Methods

for the Modelling and Assessment of Air Pollutants in

NSW – DEC 2005

Average Dust Deposition (Insoluble Solids)

Site 1 0.30 g/m2

Site 2 0.53 g/m2

Site 3 1.80 g/m2

Site 4 0.39 g/m2

As of February 2015 the Environmental Analysis

Laboratory (EAL) at Southern Cross University has

been collecting and analysing the Deposited Dust

sample bottles at the Boral Teven Quarry

Environmental monitoring

Page 13: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Annual Average Dust Deposition (Insoluble Solids) 0.30 g / m2 / month

Environmental monitoring

Page 14: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Annual Average Dust Deposition (Insoluble Solids) 0.53 g / m2 / month

Environmental monitoring

Page 15: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Annual Average Dust Deposition (Insoluble Solids) 1.80 g / m2 / month

Environmental monitoring

Page 16: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Annual Average Dust Deposition (Insoluble Solids) 0.39 g / m2 / month

Environmental monitoring

Page 17: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Environmental monitoring

Page 18: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Water quality limits for Boral Teven Quarry from EPA Licence No 2261

* On the 14/6/17 - 235mm of rainfall was recorded in previous 5 consecutive days. As per condition L1.3 of EPL2216, discharge of runoff exceeding the quality limits in L2.4 to waters from the premises is permitted when the discharge occurs solely as a result of rainfall at the premises exceeding a total of

63.2 millimetres over any consecutive five day period.

Page 19: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Boral Teven Quarry Blast

Limits

• Only 1 blast per day

• Only blast between 9am to

4pm Monday to Friday

• Vibration limits

•5mm/s 95%

•10mm/s 100%

• Overpressure Limits

• 115dB 95%

• 120dB 100%

Date Time Overpressure [dB] Peak Vibration [mm/s]

Tuesday, 8 September 2015 11:48:58 109.9 2.0

Tuesday, 22 September 2015 13:20:50 114.4 1.5

Thursday, 1 October 2015 13:03:07 106.0 2.1

Friday, 16 October 2015 13:32:00 107.0 2.1

Friday, 23 October 2015 13:15:24 110.6 0.8

Thursday, 24 March 2016 11:05:00 104.9 1.1

Tuesday, 3 May 2016 15:03:00 107.5 2.5

Wednesday, 29 June 2016 12:20:00 102.8 0.7

Friday, 9 September 2016 12:03:00 108.8 2.4

Friday, 7 October 2016 12:25:00 <110 <0.51

Monday, 30 January 2017 15:14:00 114.4 0.2

Monday, 13 March 2017 14:45:00 112.8 2.8

Monday, 10 April 2017 12:52:00 101.9 2.8

Friday, 28 July 2017 13:08:00 111.8 1.8

Tuesday, 29 August 2017 12:19:00 No Trigger No Trigger

Monday, 11 September 2017 12:13:00 108.4 2.3

Tuesday, 19 September 2017 15:00:00 101.0 0.6

Page 20: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

> Planning consent modification –

one year on…

BORAL

TEVEN QUARRY

Build something great™

Page 21: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Consent modification – one year on… ˃ Almost 12 months has passed since Council approved the consent modification.

˃ Operating hours for processing have been firmly implemented:

˃ Monday to Friday – 7am to 6pm

˃ Saturday - None

˃ Mobile crushing has been conducted for 31 working days.

˃ Of the additional commitments made by Boral upon approval: ˃ Improved surface water management - dams and drains built earlier this year are working well

˃ Compliance noise monitoring undertaken during June showed no exceedance.

˃ Mobile plant noise mitigation strategy is to be undertaken if exceedance detected.

˃ Resident feedback – how have you found things

during the past year? Any need for change?

Page 22: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Build something great™

> Community participation and

general business

BORAL

TEVEN QUARRY

Page 23: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Community participation

˃ The Boral Teven Quarry has this year supported or been involved with: ˃ Boral’s corporate environmental partners, Conservation Volunteers Australia, spent three days

working at the Southern Cross School, Ballina.

˃ Ballina Lions Club’s World Festival of Magic Children’s Christmas Party.

˃ Immune Deficiencies Foundation Australia.

˃ Donation to the Ballina Junior Touch Football Association.

˃ Donations of material to local schools.

˃ TinCAN partnership – Christmas party transport.

Page 24: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

General business and contacts ˃ Items of general business

˃ Next meeting of the Community Consultative Committee ˃ Next meeting will be arranged for the first half of 2018.

˃ Boral Teven Quarry contacts:

˃ Scott Gillieatt Quarry Manager

6687 8360 / [email protected]

˃ Paul Jackson Stakeholder Relations Manager

4677 2946 (Mon/Tue/Fri) / 0401 894 097 (Wed/Thu) / [email protected]

˃ www.boral.com.au/tevenquarry

˃ [email protected]

Page 25: BORAL QUARRIES TEVEN · Average Dust Deposition (Insoluble Solids) Site 1 20.30 g/m Site 2 0.53 g/m2 Site 3 1.80 g/m2 Site 4 0.39 g/m2 As of February 2015 the Environmental Analysis

Build something great™

> Thank you for your attendance

BORAL

TEVEN QUARRY


Recommended