+ All Categories
Home > Documents > BUI Final Presentation

BUI Final Presentation

Date post: 02-Jun-2018
Category:
Upload: nhan-trong-do
View: 226 times
Download: 0 times
Share this document with a friend

of 26

Transcript
  • 8/10/2019 BUI Final Presentation

    1/26

  • 8/10/2019 BUI Final Presentation

    2/26

    Outlines

    1. Introduction

    2. Literature Review

    3. Factors affecting BMP Selection

    4. Common BMPs used in Green Buildings

    5. Data & Procedure for Planning Stormwater Design

    6. Case Project Studies

    7. Difficulties & Solutions

    8. Conclusions

    2

  • 8/10/2019 BUI Final Presentation

    3/26

  • 8/10/2019 BUI Final Presentation

    4/26

    Research Process

    1. Review literature

    2. Analyze factors

    affecting BMP selection

    3. Survey studies to define

    common BMPs used in

    green buildings

    4. Find data and equations

    for LEED & Greenroads

    5. Compare LEED &

    Greenroads in

    stormwater design

    6. Establish aprocedure for

    planning in

    stormwater

    design

    7. Use two casestudies to

    examine the

    established

    procedure

    8. Propose difficulties and

    solutions for

    stormwater design

    4

  • 8/10/2019 BUI Final Presentation

    5/26

    2. Literature Review

    2.1 Best Management Practices (BMPs)

    Structural BMPs refer to physical

    structures designed to remove

    pollutants from stormwater runoff,

    reduce downstream erosion,

    provide flood control, and

    promote groundwater recharge.

    They typically require engineering

    design.

    Non-structural BMPs include a

    range of pollution prevention,

    education, management and

    development practices designed to

    limit the conversion of rainfall into

    runoff.

    They normally do not have

    technical or engineering designs

    BMPs

    Structural BMPs Non-structural BMPs

    2. Literature Review

    2.1 Best Management Practices (BMPs)

    1. Dry extended-detention pond2. Wet ponds

    3. Infiltration basins

    4. Infiltration trenchs

    5. Permeable pavements

    6. Bioretention

    7. Sand & organic media filters

    8. Constructed wetlands

    9. Grassed swales10. Vegetated filter strips

    11. Catch basins/Catch basins inserts

    12. Rain barrels and cisterns

    13. Manufactured products for stormwater inlet

    14. Greenroofs

    15. Rain gardens

    16. Dry wells

    17. Alum injection18. Buffer zones

    19. Open space design

    20. Urban forestry

    21. Conservation easements

    22. Infrastructure planning

    23. Narrower residential streets

    24. Curb cuts

    25. Green parking26. Alternative turnarounds

    27. Alternative pavers

    28. BMP inspection & maintenance

    29. Ordinances for post-construction runoff

    30. Zoning

    31. Modular treatment system

    32. Dynamic vortex separators

    BMPs

    Structural BMPs Non-structural BMPs

    16 16

    Stormwater

    Wetlands

    Bioretention

    Greenroof

    Permeable

    Pavement

    Grassed swale

    5

  • 8/10/2019 BUI Final Presentation

    6/26

    2.2 Low Impact Development (LID)

    LID is developed from BMPs. This is a stormwater management strategy

    and emphasizes on design to mimic the natural hydrology for the site

    LID

    Practices

    Designstrategy

    6

  • 8/10/2019 BUI Final Presentation

    7/26

    2.3 Stormwater Design Credits in LEED

    26 pts

    10 pts

    35 pts

    14 pts 15 pts

    6 pts 4 pts

    SS WE EA MR IEQ ID RP

    Allocation of points in 7 categories of LEED

    Objectives1. SS 6.1- Stormwater design: Quantity control

    (1 point)

    2. SS 6.2- Stormwater design: Quality control

    (1 point)

    StormwaterDesign

    7

  • 8/10/2019 BUI Final Presentation

    8/26

  • 8/10/2019 BUI Final Presentation

    9/26

    EW - 2 Runoff flow control

    ROW

    The goal of this credit is to mimic predevelopment hydrological conditions in

    the right of way (ROW) and minimize offsite stormwater control.

    EW - 3 Runoff quality

    The goal of this credit is to improve water quality (80% volume treated with 3

    treatment levels) of stormwater runoff leaving the roadway ROW.

    2.5 Stormwater Design Credits in Greenroads

    9

  • 8/10/2019 BUI Final Presentation

    10/26

    3. Factors affecting BMP selection

    3.1 Sources to define factors

    America Europe Australia

    East Asia

    DID, MAS

    3.1 Factors for BMP selection

    10

    No.

  • 8/10/2019 BUI Final Presentation

    11/26

    4. Common BMPs usedin Green Buildings

    1. USEPA 2. LEEDprojects

    1. USEPA

    BMPs Used (%)

    1. Grassed swales 62

    2. Bioretention (including rain garden) 52

    3. Permeable pavement 47

    4. Rain barrels and cisterns 45

    5. Curb cuts 38

    6. Greenroofs 17

    - 32BMPs (including structural and non-structural BMPs) were proposed in 2003.

    - 6common BMPs used according to a report of ASLA in 2011.

    479case

    studies

    from

    43states

    6

    11

  • 8/10/2019 BUI Final Presentation

    12/26

    2. LEED projects

    LEED version

    Projectv2.0 v2.1 v2.2 v3 Total

    Available 289 1,202 3,038 0 4,529

    With case study only 65 47 15 0 127

    Number of reviewed LEED projects

    11 projects are removed due to missing information. 116

    %

    30 %

    41 %

    51 %

    96 %

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    Certified Silver Gold Platinum

    Percentage of projects earning

    SS 6.1 & SS 6.2

    12

  • 8/10/2019 BUI Final Presentation

    13/26

    Common BMPs used in Green Buildings

    1

    2

    2

    3

    514

    14

    16

    19

    2034

    38

    42

    42

    76

    15. Infiltration trench

    14. Restored Riparian buffer

    13. Catch basin

    12. Infiltration basin

    11. Open space design

    10. Constructed Wetland

    9. Sand/Vegetated filter

    8. Wet Pond

    7. Extended Detention pond

    6. Curb cuts

    5. Greenroof

    4. Rain Barrel & Cistern

    3. Bioretention/Rain garden

    2. Bio/Grassed Swales

    1. Permeable Pavement

    BMPs LEED Projects

    10

    13

  • 8/10/2019 BUI Final Presentation

    14/26

    5.1 Equations and Data needs for LEED

    1. Runoff coefficients for different surface types and for the site.

    [C] = (Ci Ai) Ai

    2. Runoff volume is often calculated by the NRCS method (1986).

    Runoff volume[] = 0.2

    + 0.8

    The value of Sis related to the soil and surface characteristics of the drainage

    area by the following equation:

    =1000

    10

    CNis the curve number, unitless. It has a range from 30 to 100. The low number

    indicates the area has low runoff potential while large number means high

    runoff potential.

    5. Data & Procedure for Planning Stormwater Design

    14

    3. Peak flow rate for the site.Peak Flow Rate[Q]= C I A

    Website provides rainfall data: www.cwb.gov.tw (Taiwan)

    www.nws.noaa.gov (U.S.)

    http://www.nws.noaa.gov/http://www.cwb.gov.tw/http://www.nws.noaa.gov/http://www.nws.noaa.gov/http://www.cwb.gov.tw/
  • 8/10/2019 BUI Final Presentation

    15/26

    5.1 Equations and Data needs for LEED

    Climate zone Annual Precipitation (in) Estimated 90% of annual rainfall (in)

    Humid >40 1 over total site

    Semiarid 20-40 0.75 over total site

    Arid

  • 8/10/2019 BUI Final Presentation

    16/26

    5.2 Comparisons between LEED & Greenroads

    SimilaritiesDifferences

    Requirements, Equations and Data needs

    LEED requirements and equations are simpler than Greenroads in both credits

    (stormwater quantity and quality). Especially in stormwater quality credit, Greenroadsis more complicated with three treatment levels (basic, enhanced & oil)

    Advantages

    LEED has a large database with many certified projects because it was developed for a

    longer time, there are more examples to follow to obtain LEED certification.

    Greenroads needs time to accumulate certified projects to form a stronger database.

    16

  • 8/10/2019 BUI Final Presentation

    17/26

    5.3 Establish Procedure

    1. Collect

    data

    2. Select

    suitableBMPs

    3. Develop

    SWMconcept plan

    4. Evaluate

    performance

    ImplementSWM plan

    Execution

    Planning

    Procedure for planning stormwater design

    Modify concept

    planNO

    YES

    17

  • 8/10/2019 BUI Final Presentation

    18/26

    Step 1 Collect data

    5. Data & Procedure for Planning Stormwater Design

    o Guidelines of stormwater management from governments or regulations,

    such as manuals of BMPs.

    o Location, climate zone of the project, such as being located in the humid,

    arid or semiarid place.

    o Square area including total area and imperviousness area, total segment

    length and total width of cross section.

    o Surface type on site, runoff coefficients for surface types.

    o Drainage area characteristics and the curve number.

    o Precipitation/weather data, including rainfall depth, storm duration in 1-

    year, 2-year 24-hour, rainfall per 24 hours, and 90% of annual rainfall.

    5. Data & Procedure for Planning Stormwater Design

    Step 2 Select suitable BMPs

    5. Data & Procedure for Planning Stormwater Design

    Site suitabilityparameter

    Cost &

    community concern

    BMP selection process

    List of commonBMPs

    Phase 1 Phase 2Input

    List of the best

    BMPs for a project

    Output

    BMP selection process

    Site Suitability Cost & Community concern

    1. Land use

    2. Space required

    3. Size of drainage are4. Drained soil and Steep slope

    5. Quantity control

    6. Water quality

    7. High % impervious area

    1. Construction cost

    2. Maintenance cost

    3. Community acceptance4. Conservation habitat

    5. Safety concern

    18

  • 8/10/2019 BUI Final Presentation

    19/26

    Step 3 Develop SWM concept plan

    Items should be included in a concept plan

    o Land use planning, by indicating positions of building, landscape area, road.

    o All the suitable BMPs attained and their location.

    o Directions of runoff flow from each practice and linkage to sewer system.

    Step 4 Evaluate performance of selected BMPs

    This step uses equations and dataproposed to assess whether a project is

    able to earn credits in the LEED or not.

    o

    If the project can meet credit requirements, it will move to implement theSWM plan.

    o If not, the project team has to define what the problems are, what is not

    reasonable in design and which parameters should be considered by going

    back to step 3 to modify the concept design.

    19

  • 8/10/2019 BUI Final Presentation

    20/26

  • 8/10/2019 BUI Final Presentation

    21/26

    1. Bioretention

    2. Grassed swales

    3. Permeable

    pavement4. Curb cuts

    Selected BMPS

    Baseline case

    Design case

    Quantity volume reduction of the renovation office

    Quality control in the renovation office

    TSS = 60 + 85(60 x 85)/100 = 94% removal (> 80%)

    WQVH= (0.083 ft) A = 0.083 ft 3.5 acres = 0.29arce-ft

    21

  • 8/10/2019 BUI Final Presentation

    22/26

    Case 2 Fisher Pavilion at Seattle Center, WA, U.S.

    This building was rebuilt in November 2002, and got certified by LEED

    v2/v2.1 with 29 points in total, but did not achieve stormwater credits of

    LEED. It provides 52% of pervious area.

    The site includes an exhibition hall, upper plaza, lower plaza, and civic green.

    Project location

    Section

    S= 2.6 acres

    22

  • 8/10/2019 BUI Final Presentation

    23/26

    1. Grassed swales

    2. Bioretention

    3. Permeable

    pavement

    Selected BMPS

    Baseline case

    Design case

    SWM concept plan

    Quantity volume and peak flow rate reduction of Fisher Pavilion

    Quality control in Fisher Pavilion

    TSS = 60 + 85(60 x 85)/100 = 94% removal (> 80%)

    WQVS= (0.063 ft) x 2.6 acres = 0.16acre-ft

    23

  • 8/10/2019 BUI Final Presentation

    24/26

    7. Difficulties & Solutions

    7.1 Difficulties encountered in implementation7.2 Solutions

    1. Solutions to low data availability

    The government should take the lead role to launch the

    research about stormwater management in many locations.

    This work will help define and collect data which relate to

    weather, rainfall event, conditions and characteristics.

    2. Solutions to lack of knowledge in design

    Education is the best solution to improve awareness of

    project participants in stormwater management. Land use

    planning, technical capacities of BMPs or LID design, etc.

    should be educated.

    24

  • 8/10/2019 BUI Final Presentation

    25/26

    8. Conclusions

    8.1 Achievements

    1. The research defines twelve factors affecting BMP selection and ten BMPs

    commonly usedin green buildings based on guidelines and LEEDs projects.

    2. This research presents how to achieve effective stormwater design throughthe use of figures, tables, equations, data, and regulations which contain

    necessary information and stormwater design parameters for the site.

    3. The established procedure helps designers have a better understanding of

    how to design a good SWM plan.

    4. Two main difficultiesin low data availability and lack of knowledge in

    design with proposed solution will help the procedure better in the future.

    8.2 Limitations

    1. Non-structural BMPs are not mentioned deeply in the research because

    they are related to principles and require sufficient understanding from

    communities and designers before implementation.

    2. Limited data availability, so only some projects in the U.S. are discussed

    3. Limited knowledge, only existing equations and regulations from LEED

    and Greenroads are explained, but the background knowledge of these

    equations and regulations is not discussed.

    25

  • 8/10/2019 BUI Final Presentation

    26/26

    Thank you for your attention !


Recommended