Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009
Transcript
Page 1: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Building for Learning ProjectPhoto Progress Report

Month of May 2010

Project commencement 21st September 2009

Page 2: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Lecture Theatre taking shape with multilevel ceiling and first layers of paint.

Page 3: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Upstairs entry area with ceiling panels ready to add.

Building front without scaffolding

April 2010.

Page 4: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Balcony rendered and stairway constructed.

Page 5: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Toilets, wet areas and kitchen completed.

Page 6: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Downstairs hallway ceiling panels returned

Page 7: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Last of outside Hebal added and service units commissioned and room 9 painted.

Page 8: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Outside rendering completed and prior to renewed streetscape with Wodonga Council.

Page 9: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Final Admin area being plastered and toilet basins and cubicles added.

Page 10: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Council partnership streetscape starts

Page 11: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

Room 8 carpet and ceiling panels returned.

Page 12: Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.

End