CADANGAN KERJA-KERJA TEBATAN BANJIR DAN MENAIKTARAF SISTEM SALIRAN BANDAR S10, DAERAH TIMUR LAUT, PULAU PINANG. “YOUR UNDERGROUND SOLUTION” SRI TANJONG BINA SDN. BHD. (441270-A) BY TEMPORARY LANES CLOSURE AT LEBUH LINTANG PRESENTATION TITLE:
Transcript
Page 1: CADANGAN KERJA-KERJA TEBATAN BANJIR DAN MENAIKTARAF SISTEM … · cadangan kerja-kerja tebatan banjir dan menaiktaraf sistem saliran bandar s10, daerah timur laut, pulau pinang. “yourunderground

CADANGAN KERJA-KERJA TEBATAN BANJIR

DAN

MENAIKTARAF SISTEM SALIRAN BANDAR S10,

DAERAH TIMUR LAUT, PULAU PINANG.

“YOUR UNDERGROUND SOLUTION”

SRI TANJONG BINA SDN. BHD.(441270-A)

BY

TEMPORARY LANES CLOSURE AT LEBUH LINTANG

PRESENTATION TITLE:

Page 2: CADANGAN KERJA-KERJA TEBATAN BANJIR DAN MENAIKTARAF SISTEM … · cadangan kerja-kerja tebatan banjir dan menaiktaraf sistem saliran bandar s10, daerah timur laut, pulau pinang. “yourunderground

PRESENTED BY

YOUR UNDERGROUND SOLUTIONSRI TANJONG BINA SDN. BHD.

(441270-A)

PROJECT PLAN

Page 3: CADANGAN KERJA-KERJA TEBATAN BANJIR DAN MENAIKTARAF SISTEM … · cadangan kerja-kerja tebatan banjir dan menaiktaraf sistem saliran bandar s10, daerah timur laut, pulau pinang. “yourunderground

PRESENTED BY

YOUR UNDERGROUND SOLUTIONSRI TANJONG BINA SDN. BHD.

(441270-A)

OVERALL VIEW OF WORK AT LEBUH LINTANG

4.5m 3.3m4.7m 3.86m 3.61m

CROSSING JALAN LEBUH LINTANG- Twin Box Culvert 3600mm(Width) x 1800mm(Height)

- Excavation Works divided by 3 stages

- Total Duration 3 stages: 105 days

Stage 1Stage 2Stage 3

Several lanes at

Lebuh Lintang

will be closed

temporarily in 3

stages to give

way to the

construction of

twin box culvert

with the overall

width of 7.2 meter.

The work will

start from

20.7.2018 and

expected to

complete by

2.11.2018.

Lebuh Lintang

Jalan Dr. Lim

Chwee Leong

Jalan Dr. Lim

Chwee Leong

Page 4: CADANGAN KERJA-KERJA TEBATAN BANJIR DAN MENAIKTARAF SISTEM … · cadangan kerja-kerja tebatan banjir dan menaiktaraf sistem saliran bandar s10, daerah timur laut, pulau pinang. “yourunderground

PRESENTED BY

YOUR UNDERGROUND SOLUTIONSRI TANJONG BINA SDN. BHD.

(441270-A)

STAGE 1 LANES CLOSURE

During Stage 1

Lane Closure, two

lanes on the right

will be close for

estimated

duration of 35

days starting from

20.7.2018 until

24.8.2018

Stage 1 Lane Closure

Jalan Dr. Lim

Chwee LeongJalan Dr. Lim

Chwee Leong

Lebuh Lintang

Page 5: CADANGAN KERJA-KERJA TEBATAN BANJIR DAN MENAIKTARAF SISTEM … · cadangan kerja-kerja tebatan banjir dan menaiktaraf sistem saliran bandar s10, daerah timur laut, pulau pinang. “yourunderground

PRESENTED BY

YOUR UNDERGROUND SOLUTIONSRI TANJONG BINA SDN. BHD.

(441270-A)

TRAFFIC MANAGEMENT PLAN ( STAGE 2)

Stage 2 Lanes Closure

Jalan Dr. Lim

Chwee Leong Jalan Dr. Lim

Chwee Leong

Lebuh Lintang

During Stage 2

Lane Closure, two

lanes in the

middle will be

close for

estimated

duration of 35

days starting from

25.8.2018 until

28.9.2018.

Page 6: CADANGAN KERJA-KERJA TEBATAN BANJIR DAN MENAIKTARAF SISTEM … · cadangan kerja-kerja tebatan banjir dan menaiktaraf sistem saliran bandar s10, daerah timur laut, pulau pinang. “yourunderground

PRESENTED BY

YOUR UNDERGROUND SOLUTIONSRI TANJONG BINA SDN. BHD.

(441270-A)

TRAFFIC MANAGEMENT PLAN ( STAGE 3)

Stage 3 Lanes Closure

During Stage 3

Lane Closure, two

lanes on the left

will be close for

estimated

duration of 35

days starting from

29.9.2018 until

2.11.2018.

Jalan Dr. Lim

Chwee Leong

Jalan Dr. Lim

Chwee Leong

Lebuh Lintang


Recommended