Date post: | 29-Mar-2015 |
Category: |
Documents |
Upload: | lesley-criddle |
View: | 220 times |
Download: | 2 times |
Capacity Addition Planningin the Power Sector
Shantanu Dixitwww.prayaspune.org
Prayas2
Interaction plan
Capacity addition plans – e.g Konkan region Climate friendly, economic options for meeting
energy services needs India’s current capacity addition plans Key shortcomings and implications for climate
~7,600 MW of new generation planned in Shahapur Taluka, Dist. Raigadh
~6,600 MW of new generation planned in Ratnagiri district
~19,000 MW of new generation planned in the Konkan strip of Maharashtra
~4000 MW of existing generation in Konkan
Raigadh : 9,558 km² Ratnagiri : 8,208 km²Sindhudurg : 5207 km²
Prayas4
Interaction plan
Capacity addition plans – e.g Konkan region Climate friendly, economic options for
meeting energy services needs India’s current capacity addition plans Key shortcomings and implications for climate
Prayas5
Integrated Resource Planning: Case studies from India
DEFENDUS (Karnataka 1990)– Development Focused End Use oriented Scenario
Amulya Kumar N. Reddy et.al.
Least Cost Plan (Maharashtra 1994)– Prayas Energy Group
Prayas6
Typical Energy Saving Potential (based on Karnataka IRP by Reddy et. Al.)
End use efficiency savings– Industry modernisation–efficient drives etc: 15-25%– CFL for lighting : 14-58%– Solar Water heaters: 28%– LPG instead of electric stoves: 18%– Frictionless foot-valves and HDPE piping for
agirculture pumps: 30%
Prayas7
Conclusions of Integrated Plan for Maharashtra (Prayas 1993)
0
5,000
10,000
15,000
20,000
0% 20% 40% 60% 80% 100%PLFn (at Bus-bar)
Rs/
KW
(B
us-b
ar)
/Yr
Ind.Co-gen
Gasifier
Small hydro
Suger Co-gen
CFL
Loadshift
CL-light
T&D impro.
SWH
IPS
Refri.
HT/LT industry
Prayas8
Typical Benefits of IRP
Typically: efficiency can meet 25-40% and renewable generation can meet 20-25% of incremental needs at lower economic costs.
Maharashtra IRP – while meeting same level of energy services– Financial saving - ~ 33%– Reduction in incremental fossil fuel consumption - ~
55%
Prayas9
Interaction plan
Capacity addition plans – e.g Konkan region Climate friendly, economic options for meeting
energy services needs India’s current capacity addition plans Key shortcomings and implications for climate
Prayas10
Capacity Addition: 11th Plan targets
Projection to add ~ 600 GW in next 25 years 11th Plan (2007-12) - 68869 MW
48010 Coal & Lignite, 15585 Hydro, 3160 Nuclear, 2114 Gas
53% Central, 33% State, 14 Private + 13,500 MW Renewable, Captive … Transmission & Distribution to carry this power
Prayas11
Drivers
Growing economy– GDP growth from ~ 5 - 6% to 8 - 9%
Continuing shortages– Peak shortage - ~ 12% and energy shortage ~ 8%– Only 40-50% of targets met in 8,9,10th plans
Need for greater reliability– Target of 5% spinning reserves
Need to electrify all houses– 44% houses do not have electricity
About 12000 MW of capacity addition
Prayas12
Approach towards meeting energy needs
“We do not enjoy the luxury of an either-or choice: India needs energy from all known and likely sources.” – Prime Minister of India (Speech at Tarapur Automic Station 31st August 2007, - http://www.rediff.com/news/2007/aug/31guest.htm)
Ambitious projections for 10 years– 100,000 MW Thermal– 50,000 MW Hydro – 11,000 MW Nuclear
Expanding fuel supply and sources
Prayas13
Policy changes to meet capacity addition needs
De-licensing of generation projects Merchant plants Captive power plants Ultra mega power plants
Encourage capacity addition through all means
Prayas14
Ultra Mega Power Projects
4000 MW super critical coal thermal plants (5 – 7 plants expected)
Federal government lead – Fiscal incentives, conducting competitive bidding, helped
evolve power purchase agreement and payment security mechanism
Encouraging results for first two projects– Half a dozen bids for each project– Highly competitive tariff
US cents 2.7 / kWh for pithead project and US cents 5 / kWh for imported coal based project (levalised tariff)
– Both projects won by private sector
Prayas15
Ultra Mega Power Projects
Key Features of UMPP Competitive Bidding Process– Transparent process
Well laid out procedures and timetable Anonymous comparison of all bids to be made public All contracts signed with winning bidder (including PPA) will be
public
– No uncertainty and little scope for post bid negotiations All required inputs and clearances to be provided by special
purpose vehicle (govt. owned shell company) Project contract formats finalized before bidding Simple criteria for selection of winner
Prayas16
Interaction plan
Capacity addition plans – e.g Konkan region Climate friendly, economic options for meeting
energy services needs India’s current capacity addition plans Key shortcomings and implications for
climate
Prayas17
Capacity addition planning – Oblivious of key challenges
Significant over projection
Even though capacity addition is 40 – 50% less, shortages have reduced or increased very moderately
Cap. Add. (MW) Peak Shortage (%)5 year planProjected Actual Projected Actual
8 30540 16420 21% 18%9 40250 19015 12% 13%10 41110 19010 12% 14%
Prayas18
Capacity addition planning – Oblivious of key challenges
Economic implications 11th five yr. plan
– Projected investment need – US $ 255 Billion Fixed cost of US cents 15 / unit of incremental
sales!
(v/s current total tariff of around – US cents 8 / unit)
Prayas19
Social and Environmental issues -1
Electricity Policy– Environment
Appropriate advance action through EIA and Environment Action Program Streamline procedures including setting up of Land Bank and Forest Bank Coal washeries, full compliance with environmental norms
– Demand Side Management, Energy Conservation Hydro Policy
– Proper implementation of National Policy on Rehabilitation and Resettlement to ensure that the concerns of project-affected families are addressed adequately.
– Adequate safeguards for environmental protection with suitable mechanism for monitoring of implementation of Environmental Action Plan and R&R Schemes
Prayas20
Environment issues -2
Plans have little details on environment & social impacts – Emphasis on ‘speeding up’ clearance of environmental ‘obstacles’– No analysis on: How much land required? How many people
displaced? Livelihood impact?– No focus on enhancing the effectiveness through democratisation
(participatory R&R mention in Transmission Chapter of11th Plan)
Prayas21
Salient observations
Over projection of demand and poor implementation performance
Shortage psychosis and exaggerated capacity addition plans
Integrated resource planning is avoided Climate friendly options, even though
economical, are ignored
Prayas22
Lesson
To address climate change issues, improvement in national level planning process is critical.
The vicious circle
Prayas24
India’s Capacity Addition Plans
Year Peak Demand GW
Inst.Cap GW
Remarks
2007 104 132 14% peak shortage; Coal (54%),Hydro (26),Gas (11), Nuclear(3), Renewable (6)
2012 158 220
2022 323 425
2032 592 778 ~Coal (50%),Hydro (29),Gas (6), Nuclear(12), Renewable (5)
Source: Integrated Energy Policy, 8% GDP Growth Scenario