31
Capital Budgeting Overview 1 Capital Budgeting is the set of valuation techniques for real asset investment decisions. Capital Budgeting Steps estimating expected future cash flows for the proposed real asset investment (Chap 12) estimating the firm’s cost of capital (Chap 10) based on the firm’s optimal capital structure using a decision-making valuation technique which depends on the company’s cost of capital to decide whether to accept or reject the proposed investment (Chap 11)
Transcript
Page 1: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Capital Budgeting Overview1

Capital Budgeting is the set of valuation techniques for real asset investment decisions.

Capital Budgeting Steps estimating expected future cash flows for the

proposed real asset investment (Chap 12) estimating the firm’s cost of capital (Chap 10)

based on the firm’s optimal capital structure using a decision-making valuation technique which

depends on the company’s cost of capital to decide whether to accept or reject the proposed investment (Chap 11)

Page 2: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

CHAPTER 10THE COST OF CAPITAL

Estimating 3M’s Cost of Capital Air Jordan’s Divisional Cost of Capital

2

Page 3: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Chapter 10 Learning Objectives

3

Describe the concepts underlying the firm’s cost of capital (known as weighted average cost of capital) and the purpose for its calculation.

Calculate the after-tax cost of debt, preferred stock and common equity.

Calculate a firm’s weighted average cost of capital.

Adjust the firm’s cost of capital on a by division or by project basis.

Use the cost of capital to evaluate new investment opportunities.

Page 4: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Cost of Capital4

The firm’s cost of raising new funds The weighted average of the cost of

individual types of funding One possible decision rule is to compare

a project’s expected return to the cost of the funds that would be used to finance the purchase of the project

Accept if : project’s expected return > cost of capital

Page 5: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Cost of Capital Terms5

Capital Component = type of financing such as debt, preferred stock, and common equity

rd = cost of new debt, before tax rd(1-T) = after-tax component cost of debt rp = component cost of new preferred stock rs = component cost of retained

earnings(or internal equity, same as rS used in Chapters 8 and 9

Page 6: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

More Cost of Capital Terms6

re= component stock of external equity raised through selling new common stock

WACC = wdrd(1-T) + wprp + wcrs = the weighted average cost ot capital which is the weighted average of the individual component costs of capital

wi = the fraction of capital component i used in the firm’s capital structure

Page 7: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Component Cost of Debt7

Remember, a corporation can deduct their interest expense for tax purposes

Therefore, the component cost of debt is the after-tax interest rate on new debt

rd(1-T) where T is the company’s marginal tax

rate rd can be estimated by finding the YTM

on the company’s existing bonds

Page 8: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Cost of Debt Example8

We want to estimate the cost of debt for 3M which has a marginal tax rate of 35%. We find the following bond quote.

CoName Rate Price Mat. Date3M 5.7 103.43 Mar. 15, 2037 Annual coupon rate = 5.7%, n = 30 years ,

Price = 103.43% of par value, Semiannual coupons

Find YTM

Page 9: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

3M’s Cost of Debt9

Page 10: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Cost of Preferred Stock, rp 10

Cost of new preferred stock rp= Dp / Pp

Dp = annual preferred stock dividend Pp = price per share from sale of preferred

stock Preferred Stock Characteristics

Par Value, Annual Dividend Rate(% of Par) generally: no voting rights; must be paid

dividends before common dividends can be paid

Page 11: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Cost of Preferred Stock Example

11

3M wants to sell new preferred stock. The par value will be $25 a share and 3M decides they will pay an annual dividend yield of 7.5%. 3M’s advisors say the stock will sell for a price of $26 if the dividend yield is 7.5%. What is the cost of this new preferred stock?

Page 12: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Cost of Retained Earnings, rs 12

3 different approaches can be used to estimate the cost of retained earnings, but I hate the Bond Yield Plus Risk Premium Approach. So, ignore it.

The 2 remaining approaches assume that the company’s stock price is in equilibrium.

Page 13: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

The CAPM Approach to the Cost of Retained Earnings

13

The CAPM Approach: is the required rate of return from Chapter 8.

rs = rRF + (rM - rRF)bi

Example: The risk free rate is 4.9%, and the required market return is 13.4%. What would 3M’s CAPM cost of retained earnings be if its beta is 0.85

Page 14: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Discounted Cash Flow Approach for the Cost of Retained Earnings

14

The expected return formula derived from the constant growth stock valuation model.

rs = D1 / P0 + g = D0(1+g)/P0 + g In practice: The tough part is estimating g. Security analysts’ projections of g can be

used. According to the journal, Financial

Management, these projections are a good source for growth rate estimates.

Page 15: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

DCF estimate for the Cost of Retained Earnings for 3M

15

Recent Stock Price = $77.00, Last Dividend = $1.84, expected constant growth rate in

dividends = 7%

Page 16: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

What to do about the different cost of retained earnings estimates?16

CAPM: 12.1% DCF: 9.6% Average the two or choose one or the other?

Choosing DCF estimate makes for an easier cost of new common stock (external equity) estimate.

However, if you wanted to be conservative, go with the higher estimate. Aggressive, go with lower estimate

Let’s average the two estimates and go with 10.9% for our rs estimate.

Page 17: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Adjusting for flotation costs of new security issues.

17

Include flotation costs for funds raised for a project as an additional initial cost of the project. OR adjust the component cost of capital.

For example, for selling new common & preferred stock.

ke = D1 / P0(1 - F) + g; kp = D/P0(1 - F) where F = flotation(underwriting) cost % P0(1 - F) is the net price per share the company

actually receives from selling new stock

Page 18: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

3M’s estimated cost of newly issued common equity , re

18

Let’s go back to our original DCF estimates: P0: $77, D0: $1.84, g = 7% Assume new stock can be sold at the current

market price and 3M will incur a 20% floatation cost per share.

re = [$1.84(1.07)/$77(1-0.20)] + 7% = 10.2% DCF rs = 9.6%. Difference = 0.6% So, if we want to use our average CAPM/DCF

estimate for rs, then the re estimate would be 10.9% +0.6% = 11.5%

Page 19: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Weighted Average Cost of Capital, WACC

19

WACC = wdrd(1-T) + wp rp + wc rs

wi = the fraction of capital component i used in the firm’s capital structure

What is 3M’s WACC if their market value target capital structure is 15% debt, 5% preferred stock, and 80% common equity financing through retained earnings?

Page 20: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

3M’s Weighted Average Cost of Capital, WACC

20

Recall our previous estimates for 3M. rd(1-T) = 3.6% , rp = 7.2% , rs = 10.9% wd = 15% or 0.15, wp = 5% or 0.05, wc =

80% or 0.8

Page 21: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

When to use new common stock (external equity) financing: retained earnings breakpoint

21

3M’s projected net income = $3.4 billion, dividend payout ratio = 41%, 80% common equity financing.

Retained earnings = NI(1-dividend payout)

Retained Earnings Breakpoint = RE/wc

Page 22: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

3M’s Weighted Average Cost of Capital, WACC with re

22

Recall our previous estimates for 3M rd(1-T) = 3.6% , rp = 7.2% , re = 11.5% wd = 15% or 0.15, wps = 5% or 0.05, wc

= 80% or 0.8

Page 23: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

What factors influence a company’s composite WACC?

23

Market conditions. The firm’s capital structure and

dividend policy. The firm’s investment policy. Firms

with riskier projects generally have a higher WACC.

Page 24: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Some Problems in estimating Cost of Capital

24

Small firms without dividends: DCF approach is out.

Firms that aren’t publicly traded: no beta data, CAPM approach is difficult.

What about depreciation? Large source of funds. Cost of depreciation funds = WACC with RE.

WACC is just for average risk projects.

Page 25: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Adjusting for project risk25

The WACC is for average risk projects. A company should adjust their WACC

upward for more risky projects and downward for less risky projects = project’s Risk-Adjusted Cost of Capital.

A company can also make this adjustment on a divisional basis as well.

Page 26: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Using the CAPM for Risk-adjusted Cost of Capital

26

Can use this model to estimate a project cost of capital, rpr

rpr = rRF + (rM - rRF)bpr

where bP is the project’s beta Note: investing in projects that have

more or less beta (or market) risk than average will change the firm’s overall beta and required return.

Page 27: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Risk and the Cost of Capital27

Rate of Return(%)

WACC

Rejection Region

Acceptance Region

Risk

L

B

A

H12.0

8.0

10.010.5

9.5

0 RiskL RiskA RiskH

Page 28: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Jordan Air Inc.: a Divisional Cost of Capital Example

28

Jordan Air is a sporting goods apparel company which has recently divested itself from the sports franchise ownership business.

Jordan Air is starting a golf equipment division to go along with its sports apparel division.

The company uses only debt and common equity financing and thinks they should use different cost of capital for each division.

Page 29: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Jordan Air Inc.: a Divisional Cost of Capital Example

29

The company has a 40% tax rate and uses the CAPM method for estimating the cost of common equity.

Apparel Division: 35% debt and 65% equity financing. Before-tax cost of debt is 8%. Beta = 1.2.

Golf Division: 40% debt and 60% equity financing. Before-tax cost of debt 8.5%. Estimated beta = to Callaway Golf’s beta of 1.6.

Page 30: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Jordan Air’s Apparel Division’s Cost of Capital Calculation

30

The company has a 40% tax rate and uses the CAPM method for estimating the cost of equity with rRF = 5%, RPm = 8%.

Apparel Division: 35% debt and 65% equity financing. Before-tax cost of debt is 8%. Beta = 1.2.

Page 31: Capital Budgeting Overview 1  Capital Budgeting is the set of valuation techniques for real asset investment decisions.  Capital Budgeting Steps  estimating.

Jordan Air’s Golf Division’s Cost of Capital Calculation

31

The company has a 40% tax rate and uses the CAPM method for estimating the cost of equity with rRF = 5%, RPm = 8%.

Golf Division: 40% debt and 60% equity financing. Before-tax cost of debt 8.5%. Estimated beta = to Callaway Golf’s beta of 1.6.