CATCHMENT 2: GREEN INFRASTRUCTURE CONCEPTUAL PLAN Sydney Hubbert GREEN INFRASTRUCTURE CONFERENCE: Building Resilience in Proctor Creek Communities 21 April 2016
Transcript
Page 1: Catchment 2 Green Infrastructure Conceptual Plan

CATCHMENT 2: GREEN INFRASTRUCTURE

CONCEPTUAL PLANSydney Hubbert

GREEN INFRASTRUCTURE CONFERENCE:Building Resilience in Proctor Creek Communities

21 April 2016

Page 2: Catchment 2 Green Infrastructure Conceptual Plan

Problem Solution

Page 3: Catchment 2 Green Infrastructure Conceptual Plan

PurposeManage storm water run-off

•Total Acreage = 40.5

•25-year Rain Event = 6.2 million gallons

•100-year Rain Event = 7.5 million gallons

Page 4: Catchment 2 Green Infrastructure Conceptual Plan

Focus Area

Page 5: Catchment 2 Green Infrastructure Conceptual Plan

Conceptual Plan

Cisterns

Ephemeral Stream

Floodplain/ Rain Garden

Legend

Cisterns #

Friendship 1

North Metro GNETS 2

Morris Brown College 3

Beckwith 4

MLK, Jr. 5

President's House 6

Bird Cage 7

Page 6: Catchment 2 Green Infrastructure Conceptual Plan
Page 7: Catchment 2 Green Infrastructure Conceptual Plan

New Friendship Baptist ChurchNew Friendship Baptist Church Cistern

Impervious Surfaces sq ft25-year rain

event in

Gallons

John Lewis Gym 20,000 70,257

Friendship Center Apartments 14,000 49,180

Future Friendship Baptist

Church 72,325 254,069

TOTAL 106,325 373,506

Total Area, sq

ft

100-year rain event

in Gallons

165,270 705,935

Page 8: Catchment 2 Green Infrastructure Conceptual Plan

North Metro GNETS

Total Area,sq

ft

100-year rain event

in Gallons

175,365 749,055

North Metro GNETS Cistern

Impervious Surfaces sq ft25-year rain

event in Gallons

North Metro GNETS 45,928 161,339

Parking Lot at School 22,260 78,197

TOTAL 68,188 239,536

Page 9: Catchment 2 Green Infrastructure Conceptual Plan

Morris Brown CollegeMorris Brown Cistern

Impervious

Surfacessq ft

25-year rain

event in

Gallons

Fountain Hall 10,166 35,712

Griffin Hightower 27,706 97,328

Administration 11,931 41,912

Ogelthorpe Hall 4,800 16,862

Parking Lots 6,500 22,834

TOTAL 61,103 214,647

Total Area 100-year rain event

in Gallons

171,200 731,265

Page 10: Catchment 2 Green Infrastructure Conceptual Plan

Interdenominational Theological Center (ITC) - A Quad Cistern

25-year

rain event

Total impervious sq ft 83,080

Total acres

Total Gallons 291,850

70 x 70 x 8 ft

King Meadow100-year

rain event

Total sq ft 221,760

acre 4

total gals 696,914

Minus Quad Cistern 405,065

Page 11: Catchment 2 Green Infrastructure Conceptual Plan

Interdenominational Theological Center (ITC) - B

MLK Cistern25-year

rain event

Total Sq Ft. 111,423

Total Gallons 391415

Gallons/ cubic foot 52328.2

8ft deep 6541.03

80 x 82 x 8 ft

Rain

Garden

100-year

rain event

Total Gallons 561,000

250 x 50 x 6ft deep

Page 12: Catchment 2 Green Infrastructure Conceptual Plan

Clark Atlanta University (CAU) President’s Lot

CAU President's House Cistern

Impervious Surfaces sq ft

25-year rain

event in

Gallons

CAU President's House 3,300 11,592

Knowles Building 6188 21,738

Knowles Parking Lot 20165 70,837

Homes off Beckwith 14,850 51,236

Beckwith Dorm and parking lot 80,920 284,262

TOTAL 125,423 439,665

Total Area

100-year rain

event in

Gallons

111,132 474,690

Page 13: Catchment 2 Green Infrastructure Conceptual Plan

Bird CageBird Cage Cistern

Impervious Surfaces sq ft

25-year

rain event

in Gallons

Homes - Beckwith/ Vine/

Walnut/ Parsons 25,800 663,094

Home - Beckwith/ Vine/ Elm 21,738 26,431

TOTAL 47,538 689,525

Total

Area

100-year rain

event in

Gallons

178,640 763,044

Page 14: Catchment 2 Green Infrastructure Conceptual Plan

ResultsCisterns

Friendship 373,506

North Metro GNETS 239,536

Morris Brown 214,647

ITC Quad 291,850

MLK 391,415

CAU 439,665

Bird Cage 689,525

TOTAL 2,640,144

Greenways

GNETS 749,055

King Meadow 405,065

MLK Rain Garden 561,000

TOTAL 1,715,120

Page 15: Catchment 2 Green Infrastructure Conceptual Plan

Learning Experiences �Quantify storm water runoff from buildings

�Learn about how our campus significantly contributes to flooding and associated health problems in the lower elevation residential neighborhoods such as Vine City and English Avenue

�Engineering principles and concepts

�Insight to the world of community design and urban planning

�Program Management Duties

Page 16: Catchment 2 Green Infrastructure Conceptual Plan

Acknowledgments • ECO-Action, Director – Dr. Yomi Noibi

• Metro Atlanta Urban Watershed Institute (MAUWI) - Bill Eisenhauer

• Faculty from ITC, CAU, and other privately owned properties included in this area


Recommended