Cedarvale-Forest Hill CLC January 29, 2020
Agenda
• Cedarvale Station
• Forest Hill Station
Cedarvale Construction Updates
Cedarvale Station Look Ahead
ACTIVITY AREA APPROX. DATE/DURATION
Deep Excavation & Extended Hours – Hauling
Under Eglinton Ave W Underway through till March 2020
6:00 a.m. – 11:00 p.m.
Tieback Installation Throughout all areas Underway through till March 2020
Major Concrete Pours In select areas Underway throughout 2020 into
2021
Geotechnical Monitoring Eastbound curb lane of Eglinton Ave
between Winnett Ave and Allen Rd N January 2020 – September 2020 Every Tuesday between 11:00 a.m. – 2:00 p.m.
Eglinton West Station SOE and
Underpinning Works Eglinton West Station Underway throughout 2020
Temporary Traffic Deck Removal
and Permanent Utility Installation Eglinton Avenue West March 29, 2020 till early 2021
Traffic Configuration – Current Phase
Stage 6A – Crane Installation
Until approximately late March 2020
Construction Progress Photos
Wall Demolition- East Ventilation Shaft
Bulk Excavation – East of the TTC Box
Forest Hill Construction Updates
8
Forest Hill Station Construction Look-ahead
Activity Location Approx. Date and Duration
Hilltop-Bathurst Laneway Closure Closure of Hilltop-Bathurst laneway behind Secondary Entrance; closed to vehicles only
Closed September 2019 for approx. six (6) months
Extended Hours for Deep Excavation North Station Box
Monday – Saturday, 6:00 a.m. – 4:00 a.m. Note: extended hours are expected to resume Monday, February 10, 2020
Manhole Construction
• SW corner of Bathurst St and Eglinton Ave inside work zone
• West side of Secondary Entrance on Eglinton Ave, inside of the work zone
Underway into winter 2020
Sidewalk and Laneway Closure for Concrete Pour
Closure of the Hilltop-Bathurst laneway behind the Secondary Entrance and closure of the pedestrian route around the Secondary Entrance
Wednesday, January 29, 2020 for approx. six (6) hours. • February 03, 2020 • February 13, 2020 • March 10, 2020
9
Current Construction Configuration
Until January 2020
10
Upcoming Traffic Configuration
Beginning February 2020
11
Concrete Pour Traffic Configuration
January 29, 2020 from 8:00 a.m. for approx. six (6) hours
12
Construction Progress Photos
Waterproofing – North Roof Slab
Formwork installation – Secondary Entrance