+ All Categories
Home > Education > Ceylon Electricity Board

Ceylon Electricity Board

Date post: 08-Jan-2017
Category:
Upload: wickramarathne-gt
View: 140 times
Download: 3 times
Share this document with a friend
98
DEPARTMENT OF MECHANICAL & MANUFACTURING ENGINEERING FACULTY OF ENGINEERING UNIVERSITY OF RUHUNA INDUSTRIAL TRAINING REPORT SUBMITTED IN PARTIAL FULFILMENT OF THE DEGREE OF BACHELOR OF SCIENCE IN ENGINEERING 29 th April 2016 CEYLON ELECTRICITY BOARD (From 04th January 2016 To 24 th April 2016) WICKRAMARATHNE G.T (EG/2012/2111)
Transcript
Page 1: Ceylon Electricity Board

DEPARTMENT OF MECHANICAL & MANUFACTURING ENGINEERING

FACULTY OF ENGINEERING

UNIVERSITY OF RUHUNA

INDUSTRIAL TRAINING REPORT SUBMITTED IN PARTIAL FULFILMENT OF THE DEGREE OF BACHELOR OF SCIENCE IN ENGINEERING

29 th April 2016

CEYLON ELECTRICITY BOARD

(From 04th January 2016 To 24 th April 2016)

WICKRAMARATHNE G.T (EG/2012/2111)

Page 2: Ceylon Electricity Board

Preface

I am a Mechanical & Manufacturing engineering undergraduate at University of Ruhuna.

I trained under Ceylon Electricity Board ( CEB) from 04th January 2016 to 24

th March

2016 under the second industrial training session of my degree program. Electricity

generation and distribution are done by Ceylon Electricity Board.

My working experience and industrial exposure in the above company during the 12

week time period is mentioned in this report. Chapter 1 is dedicated to the

“Introduction of the Ceylon Electricity Board”. And Chapter 2 is described for the

training experience and industrial exposure of myself at there. Chapter 3 has reserved

to discuss the “Management” where it is mentioned about the managements knowledge

that I could gain at CEB. Finally the chapter 4 is separated for the “Summary and

Conclusion”.

I have tried my best to present what I could learn at CEB with graphical explanations.

Page 3: Ceylon Electricity Board

Acknowledgment

As an engineering student I was lucky to have this valuable and rare chance to have my

second industrial training experience at Ceylon Electricity Board where I was able to

gain great work place experience and technical knowledge.

Most especially I’m thankful to Dr. Sumith Baduge, Department head of the

Mechanical & Manufacturing Department.

And also I take this opportunity to express my profound gratitude and deep regard Dr.

J.M.R.S Appuhami who coordinated and guided us in selecting training places and

taking all the arrangements to make it more successful. My sincere gratitude goes to

Engineering Education Center of Ruhuna Engineering Faculty for giving me this

opportunity and also to NAITA for granting us for the training.

I convey my special thanks to Head of the Training Center of CEB and the staff of Train-

ing Center who arranged a better training sessions for us, for supporting and guiding us

during the training period. I would also like to thank all the staff at CEB for their

great support and for the knowledge and experience they shared with us.

I thank all the Engineers and other staff of CEB at the who spent their valuable time to

explain and to teach us about different fields.

My heartiest gratitude goes to my parents, my brothers and friends who helped me a lot

to make my industrial training a success .The blessing, help and guidance given by them

time to time shall carry me a long way in the journey of life on which I am about to

embark.

Thank you.

Wickramarathne G.T.-EG/2012/2111

Faculty of Engineering,

University of Ruhuna,

Galle.

Page 4: Ceylon Electricity Board

1

Contents

1 INTRODUCTION ...................................................................................................... 6

1.1 About the Training Session .................................................................................. 6

1.2 Ceylon Electricity Board (C.E.B.) ....................................................................... 7

1.2.1 Organizational Structure of the CEB ............................................................ 9

1.3 Electricity Generation Sources ........................................................................... 10

1.4 CEB Grid Network............................................................................................. 11

2 TECHNICAL DETAILS .......................................................................................... 13

2.1 Hydroelectric Power .......................................................................................... 13

2.2 Main Components of Hydroelectric Power Plant .............................................. 15

2.2.1 Dam ............................................................................................................. 15

2.2.2 Water Reservoir .......................................................................................... 16

2.2.3 Intake or Control Gates ............................................................................... 16

2.2.4 Penstock ...................................................................................................... 17

2.2.5 Surge Tank .................................................................................................. 19

Power Station ............................................................................................................ 20

2.2.6 Main inlet valve (MIV) ............................................................................... 20

2.2.7 Turbine ........................................................................................................ 21

2.2.8 Generator .................................................................................................... 22

2.2.9 400V Switch Board ..................................................................................... 26

2.2.10 Switch Yard ................................................................................................ 27

2.2.11 Generator Transformer ............................................................................... 27

2.2.12 HVAC system ............................................................................................. 28

2.3 Maintenance Works ........................................................................................... 30

2.3.1 Annual maintenances (28/12/2015- 11/01/2016) – Kukuleganga Power

Station ................................................................................................................... 30

2.3.2 Breakdown Maintenance at Kukuleganga Power Station .......................... 37

2.3.3 Maintenance works at Samanalawewa ....................................................... 38

2.3.4 First Aid Camp at Samanalawewa .............................................................. 39

2.4 Thermal Power: How It Works .......................................................................... 40

2.4.1 Important of Coal Power Plant to Sri Lanka .............................................. 41

2.4.2 Working of a Coal Fired Plants .................................................................. 42

Page 5: Ceylon Electricity Board

2

2.4.3 Introduction to LakVijaya Power Station ................................................... 44

2.5 Main Sections of LakVijaya Power Station ....................................................... 44

2.5.1 Fuel Handling Section ................................................................................ 44

2.5.2 Boiler and Boiler Auxiliaries Section ......................................................... 53

2.5.3 Turbine and Turbine Auxiliaries ................................................................ 67

2.5.4 Generator .................................................................................................... 73

2.5.5 Transformer ................................................................................................ 73

2.5.6 Balance of Plant (BOP) .............................................................................. 74

2.5.7 Maintenance Works .................................................................................... 81

3 MANAGEMENT ..................................................................................................... 83

3.1 Demand Side Management (DSM) .................................................................... 83

3.2 Financial Management ....................................................................................... 84

3.3 Human Resource Management (HRM) ............................................................. 86

3.4 Quality Control Program .................................................................................... 87

3.5 Health and Safety Management ......................................................................... 88

3.6 Energy and Waste Management ........................................................................ 90

4 SUMMARY AND CONCLUSION ......................................................................... 93

4.1 Summary ............................................................................................................ 93

4.2 Conclusion ......................................................................................................... 94

5 References ................................................................................................................. 95

Page 6: Ceylon Electricity Board

3

List of Figures

Figure 1-1 Crest of the Ceylon Electricity Board ............................................................... 7

Figure 1-2 Organizational structure of the CEB ................................................................ 9

Figure 1-3 Electricity generation in Sri Lanka by source ................................................. 10

Figure 2-1 Hydro power works ......................................................................................... 13

Figure 2-2 Samanalawewa location .................................................................................. 14

Figure 2-3 Regulation pond gate of the Kukule Ganga Hydroelectric Power Plant ........ 17

Figure 2-4 Schematic diagram of Samanalawewa Power Station .................................... 18

Figure 2-5 Schematic diagram of Kukuleganga Power Station ........................................ 19

Figure 2-6 MIV with by-pass system ............................................................................... 20

Figure 2-7 MIV with service seal ..................................................................................... 20

Figure 2-8 Turbine of Samanalawewa .............................................................................. 21

Figure 2-10 Bearing arrangement of generator shaft ........................................................ 22

Figure 2-12 Chilled water cooling system ........................................................................ 28

Figure 2-13 Air handling unit arrangement ...................................................................... 29

Figure 2-14 Repairing and maintenance of spiral casing process .................................... 30

Figure 2-15 Paints used for repainting the spiral casing................................................... 31

Figure 2-16 Pressure testing setup .................................................................................... 31

Figure 2-17 Repairing of gate valve ................................................................................. 32

Figure 2-18 Portable oil filter unit .................................................................................... 33

Figure 2-19 Clearance measuring test .............................................................................. 34

Figure 2-20 Replacing the ‘O’ rings of the oil cooler ...................................................... 34

Figure 2-21 Clearance measuring of runner guide veins .................................................. 35

Figure 2-22 Crack detector dye penetrant ........................................................................ 36

Figure 2-23 Closing the manhole of spiral casing ............................................................ 36

Figure 2-24 Tightening a coupling .................................................................................. 37

Figure 2-25 Some equipment in machine shop ................................................................ 38

Figure 2-26 First aid tips................................................................................................... 39

Figure 2-27 Artifical breathing practical section .............................................................. 39

Figure 2-28 How a steam power plant works ................................................................... 40

Page 7: Ceylon Electricity Board

4

Figure 2-29 From coal to electricity ................................................................................. 43

Figure 2-30 Coal unloading system .................................................................................. 46

Figure 2-31 Jetty ............................................................................................................... 46

Figure 2-32 Self propeller barge ....................................................................................... 47

Figure 2-33 Coal unloading process ................................................................................. 47

Figure 2-34 Parts of bridge ship unloader ........................................................................ 48

Figure 2-35 Coal yard ....................................................................................................... 49

Figure 2-36 Bucket wheel stacker-reclaimer .................................................................... 49

Figure 2-37 Coal bunker ................................................................................................... 50

Figure 2-38 Coal feeder .................................................................................................... 51

Figure 2-39 Coal pulverizer .............................................................................................. 52

Figure 2-40 Steam cycle ................................................................................................... 55

Figure 2-41 Steam drum ................................................................................................... 56

Figure 2-42 Main component of the re- heater system ..................................................... 57

Figure 2-43 Boiler main auxiliary systems and steam path arrangement ......................... 57

Figure 2-44 Burner and wind box arrangement inside the furnace .................................. 58

Figure 2-45 Plane view of the fire arrangement and imaginary fire circle ....................... 59

Figure 2-46 Primary air fan .............................................................................................. 60

Figure 2-47 Seal air fan .................................................................................................... 61

Figure 2-48 FD and ID fans .............................................................................................. 62

Figure 2-49 Working principle of ESP ............................................................................. 63

Figure 2-50 Flue­gas desulfurization unit ........................................................................ 64

Figure 2-51 Working principle of aeration basin ............................................................. 66

Figure 2-52 Aeration of sea water to remove Sulphur ..................................................... 66

Figure 2-53 LP, IP and HP turbines.................................................................................. 67

Figure 2-54 Bearing arrangement of the rotor .................................................................. 68

Figure 2-55 Coagulation tanks .......................................................................................... 75

Figure 2-56 Ultra filter ...................................................................................................... 75

Figure 2-57 RO device ...................................................................................................... 76

Figure 2-58 Energy recovery unit operation principle ..................................................... 77

Figure 2-59 Make-up water treatment process flow chart ................................................ 77

Figure 2-60 Hydrogen generating system ......................................................................... 79

Figure 2-61 Hydrogen generating storage system ............................................................ 79

Page 8: Ceylon Electricity Board

5

Figure 2-62 Control room ................................................................................................. 80

Figure 2-63 Repair the pulley system of a gantry crane ................................................... 82

Figure 3-1 Summary statics 2013 ..................................................................................... 85

Figure 3-2 How to avoid accidents ................................................................................... 88

Figure 3-3 Different types of fire extinguishers in power plant ....................................... 89

Figure 3-4 Eye washer ...................................................................................................... 90

Figure 3-5 Waste disposal coding system ........................................................................ 91

Figure 3-6 ESP unit .......................................................................................................... 92

Page 9: Ceylon Electricity Board

6

CHAPTER ONE

1 INTRODUCTION

1.1 About the Training Session

For the second session of industrial training I got the opportunity to train in Ceylon

Electricity Board. The training session was planned to both hydro and thermal power

generation .The training session was expanded for 12 weeks from 04/01/2016 to

24/03/2016.

Before starting the training we were asked to report to Office of Deputy General Manager

(Training), Piliyandala and there we got our training schedule. The provided training

schedule is shown in table 1.1.

Table 1.1. Training Schedule

Branch/Workplace From To

Samanala Hydro Complex 04/01/2016 12/02/2016

LakVijaya Coal Power Station 15/02/2016 24/03/2016

In the 6 week period of Samanala Hydro Complex, first we had 3 weeks training in Kukule

Ganga Hydro power Station and then 3 weeks in Samanalawewa Hydro Power Station.

Page 10: Ceylon Electricity Board

7

Figure 3-1 Crest of the Ceylon Electricity Board

1.2 Ceylon Electricity Board (C.E.B.)

Vision

“Enrich Life Through Power”

Mission

To develop and maintain an efficient, coordinated and economical system of electricitysupply to the whole of Sri Lanka, while adhering to our core values

* Quality

* Service to the nation

* Efficiency and effectiveness

* Commitment

* Safety

* Professionalism

* Sustainability

Page 11: Ceylon Electricity Board

8

CEB is empowered to

o Generate electrical energy

o Transmit electricity

o Distribute it to reach all categories of consumers and

o Collect the revenue.

CEB is also empowered to

o Acquire assets, including human resources following the approved procedures.

It is the duty of the CEB to make the optimal use of the resources through the

application of pragmatic and time-tested managerial methods.

Statutory Obligation

It shall be the duty of the Board, with effect from the date of the transfer to the Boardof Government Electrical Undertakings under Section 18, to develop & maintain anefficient, coordinated & economical system of electricity supply for the whole of SriLanka.

Section 11, Ceylon Electricity Board Act No.17 of 1969

Page 12: Ceylon Electricity Board

9

1.2.1 Organizational Structure of the CEB

Figure 3-2 Organizational structure of the CEB

Page 13: Ceylon Electricity Board

10

1.3 Electricity Generation Sources

C.E.B. generates typically 74% of the total electricity demand of Sri Lanka. C.E.B.

purchase electricity from P.P.P. (Private Power Purchases) to fulfil the remaining

electricity demand. Electricity generation in Sri Lanka can be categorized into 4 major

categories. They are

Hydro

Thermal-oil

Thermal-coal

NCRE (Non-Conventional Renewable Energy)

Contribution of each category depends on several facts like weather (rain), fuel prize,

condition of plants etc. For an example consider following charts taken from the

‘Statistical Digest of the C.E.B. 2013’.

Figure 3-3 Electricity generation in Sri Lanka by source

By considering above charts it can be seen that rainfall in 2012 is less than 2013. That’s

why Hydro electricity generation in 2012 is less than 2013. As well in 2013 only the phase

1 of LakVijaya coal power plant was operational. That’s why contribution from thermal-

coal power plants is less than the contribution from thermal-oil power plants.

Page 14: Ceylon Electricity Board

11

1.4 CEB Grid Network

Table 1.2 - Existing and Committed Power Plants

Plant Name Units x

Capacity Capacity

(MW) Expected

Annual

Avg.

Energy

(GWh)

Year of

Commissioning

Canyon 2 x 30 60 160 1983 - Unit 1

1989 - Unit 2

Wimalasurendra 2 x 25 50 112 1965

Old Laxapana

3x 9.5+

2x12.5

53.5 286 1950

1958

New Laxapana 2 x 58 116 552 Unit 1 1974

Unit 2 1974

Polpitiya 2 x 37.5 75 453 1969

Laxapana Total 354.5 1563

Upper Kotmale 2 x 75 150 409 Unit 1 - 2012

Unit 2 - 2012

Victoria 3 x 70 210 865 Unit 1 - 1985

Unit 2 - 1984

Unit 3 - 1986

Kotmale 3 x 67 201 498 Unit 1 - 1985

Unit 2&3 –‘88

Randenigala 2 x 61 122 454 1986

Ukuwela 2 x 20 40 154 Unit 1&2 – ‘76

Bowatenna 1 x 40 40 48 1981

Rantambe 2 x 24.5 49 239 1990

Mahaweli Total 812 2667

Samanalawewa 2 x 60 120 344 1992

Kukule 2 x 35 70 300 2003

Small hydro 20.45

Samanala Total 210.45 644

Existing Total 1376.95** 4874

Committed

Broadlands 2x17.5 35 126 2017

Moragolla 2x15.5 31 97.6

2020

Page 15: Ceylon Electricity Board

12

Note: * According to feasibility studies. ** 3MW wind project at Hambantota not included

Multi-Purpose Projects

Uma Oya 2x60 120 231 2017

Gin Ganga 2x10 20 66 -

Thalpitigala 2x7.5 15 52.4 -

Moragahakanda (2x5) +

7.5 +

7.5

25 114.5 Unit 1-2017

Unit 2-2020

Unit 3-2022

Total Hydro 246 687.5*

Puttalam Coal Power

Plant Puttalam CPP

3 x 300

3 x 275

-

2011 & 2014

Puttalam Coal Total 900 825 -

Kelanitissa Power Station

Gas turbine (Old) 4 x 20 4 x 16.3 417 Dec 81, Mar 82,

Apr 82,

Gas turbine (New) 1 x 115 1 x 113 707 Aug 97

Combined Cycle (JBIC) 1 x 165 1 x 161 1290 Aug 2002

Kelanitissa Total 360 339.2 2414

Sapugaskanda Power

Station

Diesel 4 x 20 4 x 17.4 472 May 84, May 84,

Sep 84, Oct 84

Diesel (Ext.) 8 x 10 8 x 8.7 504 4 Units Sept 97

4 Units Oct 99

Sapugaskanda

Total

160 139.2 976

Other Thermal Power

Plants

UthuruJanani 3 x

8.9

3 x 8.67 Jan 2013

Existing Total

Thermal

1446.7 1329.4 3390

Page 16: Ceylon Electricity Board

13

CHAPTER TWO

2 TECHNICAL DETAILS

2.1 Hydroelectric Power

Hydropower is using water to power machinery or make electricity. When flowing water

is captured and turned into electricity, it is called hydroelectric power or hydropower. In

this case a power source-water is used to turn a propeller­ like piece called a turbine, which

then turns a metal shaft in an electric generator, which is the motor that produces

electricity.

Figure 3-4 How hydro power works

The theory is to build a dam on a large river that has a large drop in elevation. The dam

stores lots of water behind it in the reservoir. Near the bottom of the dam wall there is the

water intake. Gravity causes it to fall through the penstock inside the dam. At the end of

the penstock there is a turbine propeller, which is turned by the moving water. The shaft

from the turbine goes up into the generator, which produces the power. Power lines are

connected to the generator that carry electricity to our homes. The water continues past the

propeller through the tailrace into the river past the dam.

Page 17: Ceylon Electricity Board

14

There are three types of hydropower facilities as

Impoundment

The most common type of hydroelectric power plant is an impoundment facility. An

impoundment facility, typically a large hydropower system, uses a dam to store river

water in a reservoir. Water released from the reservoir flows through a turbine, spinning

it, which in turn activates a generator to produce electricity.

Therefore Samanalawewa power station belongs into this category where its dam is located

in the Udawalawe basin. It was built at the confluence of the Walawe River and the Belihul

Oya, a location 400 m above mean sea level.

Figure 3-5 Samanalawewa location

Diversion

A diversion, sometimes called run-of-river, facility channels a portion of a river through

a canal or penstock. It may not require the use of a huge dam. So there won’t be a huge

reservoir to only a small pond is built up. Kukuleganga hydro power station falls under

this category where its catchment area is 312 km2, full spill level is 206.00 msl and

minimum operating level is 204 msl and effective storage is 1.67 million m.

Page 18: Ceylon Electricity Board

15

Pumped storage.

Another type of hydropower called pumped storage works like a battery, storing the

electricity generated by other power sources like solar, wind, and nuclear for later use. It

stores energy by pumping water uphill to a reservoir at higher elevation from a second

reservoir at a lower elevation. When the demand for electricity is low, a pumped storage

facility stores energy by pumping water from a lower reservoir to an upper reservoir.

During periods of high electrical demand, the water is released back to the lower reservoir

and turns a turbine, generating electricity. [1]

2.2 Main Components of Hydroelectric Power Plant

2.2.1 Dam

The dam is the most important component of hydroelectric power plant. The dam is built

on a large river that has abundant quantity of water throughout the year. It should be built

at a location where the height of the river is sufficient to get the maximum possible

potential energy from water. E.g.:

Samanalawewa dam

Length : 460m

Height : 100m

Type : Rock fill clay core type

Spillway gates : 3 (max 1200 m3/s x 3)

Irrigation gate : 10 m3/s (max)

Low Level Outlet : 75 m3/s (max)

Kukuleganga dam-

Length : 110m (at Meepagama)

Height : 16m

Type : Gravity type

Low Level Outlet : 2.5 m3/s (max)

The water so collected in the pond is run through a settling tank or a sand trap, to stop

some of the sediment particles which could damage the turbines from entering into the

waterway.

Page 19: Ceylon Electricity Board

16

2.2.2 Water Reservoir

The water reservoir is the place behind the dam where water is stored. E.g.:

Samanalawewa

Catchment area : 341 𝐾𝑚2

Main feeds : Walawe ganga and Belihul oya

Capacity : 278 MCM

Usable capacity : 218 MCM

Max water level : 455 MSL

Minimum water level : 424 MSL(for power generation)

Leak : 1.8𝑚3/s

Kukuleganga

Catchment area : 312 𝐾𝑚2

Main feeds : Kukule ganga

Capacity : 1.67 MCM

Max water level : 206 MSL

Minimum water level : 204 MSL(for power generation)

2.2.3 Intake or Control Gates

These are the gates built on the inside of the dam and water enters the power generation

unit through these gates. When the control gates are opened the water flows due to gravity

through the penstock and towards the turbines.

Samanalawewa

To get a vortex free or lesser water supply to tunnels intake is built with Bell mouth shape.

To collect logs and trash which flow towards the intake there is a trash rack as well. The

intake to the tunnel is some 5.5km up steam of the dam on the right bank of the walawe

river limb of the reservoir the tunnel intake consist of a screened bell mouth and anti-

vortex structure, a short section of tunnel leading to emergency and control and monitoring

equipment. The bell mouth structure is constructed in front of the tunnel portal with an

invert level of 416.75msl.the trash screens are inclined at an angle of 45 degrees.

Page 20: Ceylon Electricity Board

17

An anti-vortex structure is constructed above bell mouth in take to prevent the formation

of air entering vortices as the level approaches the lowest reservoir level of 424.0 msl. The

bell mouth structure terminates at the 6m long transition to the 4.5m internal diameter

concrete lined intake tunnel which extends horizontally for some 40m to the bottom of the

gate shaft at invert level 417.0 msl. The gate shaft is divided into upstream chambers. A

control gate operates in the downstream chamber. Bothe the control and emergency gates

are equipped with 300mm diameter by-pass valves for controlled tunnel filling and

pressure equalizing.

Figure 3-6 Regulation pond gate of the Kukule Ganga Hydroelectric Power Plant

2.2.4 Penstock

The penstock is the long pipe or the shaft that carries the water flowing from the reservoir

towards the power generation unit, comprised of the turbines and generator. In

Samanalawewa first water carries out by power tunnel till to portal valve house. And then

use the penstock to bring water to power house. We can’t see such portal valve house at

Kukuleganga.

Page 21: Ceylon Electricity Board

18

Samanalawewa

- Power tunnel

Length : 5.35 km

Slope : 1:100

Internal diameter : 4.5 m

- Portal valve house

Type of valve : Butterfly

Hydraulically operated

By pass valve included

- Penstock

Length : 670 m

Diameter : 3.85m at inlet & 2.85m at outlet

Figure 3-7 Schematic Diagram of Samanalawewa Power Station

Page 22: Ceylon Electricity Board

19

Kukuleganga

- Headrace tunnel

Length : 5.7 km

Internal diameter : 6.4 m

Figure 3-8 Schematic Diagram of Kukuleganga Power Station

2.2.5 Surge Tank

This is situated after the concrete made tunnel and is made to bear the sudden pressure

impact when the main inlet valve (MIV) is closed at the power house. Surge chamber is

located at just upstream of portal valve house. The top of 18m diameter surge chamber is

at level 477 msl and 12m above ground level with the floor at 391.0msl. and 6m diameter

shaft leads vertically from and connects to the 4.5m diameter tunnel.

Page 23: Ceylon Electricity Board

20

Power Station

2.2.6 Main inlet valve (MIV)

Samanalawewa

- Spherical ball valve

- By pass valve included

- Nominal diameter 1.5 m

- Design pressure 44 bar

Figure 3-9 MIV with by-pass system

Kukuleganga

- Spherical ball valve hydraulically operated

- No by pass. MIV is open after pressure balanced by opening service seal.

- Nominal diameter 1.7 m

- Design pressure 24 bar

Figure 3-10 MIV with service seal

By- pass system

Hydraulic

Actuator

Page 24: Ceylon Electricity Board

21

2.2.7 Turbine

When water falls on the blades of the turbine the kinetic and potential energy of water is

converted into the rotational motion of the blades of the turbine. The rotating blades causes

the shaft of the turbine to also rotate. There are many types of turbines such as Kaplan

turbine, Francis turbine, Pelton wheels etc. The type of turbine used in the hydroelectric

power plant depends on the height of the reservoir, quantity of water and the total power

generation capacity.

Samanalawewa

- Vertical shaft Francis type

- Normal speed 500rpm

- counter clockwise rotation

- Turbine setting level 109 MSL

- 20 wicket gates

- Wicket gates operated by hydraulic servo motor

Figure 3-11 Turbine of Samanalawewa

Page 25: Ceylon Electricity Board

22

Kukuleganga

- Vertical shaft Francis type

- Normal speed 500rpm- clockwise rotation view from above

- Turbine effective head 183.17 m

- Turbine setting level 206 MSL

- 20 wicket gates -Wicket gates operated by hydraulic servo motor

Bearing arrangement of generator shaft

Both power plants have same bearing arrangement as follows

Figure 3-12 Bearing arrangement of generator shaft

2.2.8 Generator

It is in the generator where the electricity is produced. The shaft of the water turbine rotates

in the generator, which produces alternating current in the coils of the generator. It is the

rotation of the shaft inside the generator that produces magnetic field which is converted

into electricity by electromagnetic field induction. Hence the rotation of the shaft of the

turbine is crucial for the production of electricity and this is achieved by the kinetic and

potential energy of water. Thus in hydroelectricity power plants potential energy of water

is converted into electricity.

Page 26: Ceylon Electricity Board

23

Samanalawewa

- Vertical shaft

- Salient poles

- 3 phase ,2 units

- Rated power 70.6 MWA

- Rated voltage 10.5 KV

- Output 60 MW

Kukuleganga

- Vertical shaft

- Salient poles-12 poles

- 3 phase

- 2 units

- Rated power 4200KVA

- Rated frequency 50 Hz

- Power factor 0.85

- Output 37 MW

Generator and main systems

- Cooling system

- Compress air system,

- Brake system

- LP and HP oil system

- Fire protection system

- Etc...

Following are some details about those systems of Samanalawewa Power Station that I

could studied.

Page 27: Ceylon Electricity Board

24

Cooling Water System

In the cooling water gallery, there are 5 cooling water pumps. Two for each unit, among

two, one for operation and other one is standby pump while other one for stationary

supplies. Main cooling water pumps are horizontal shaft double suction centrifugal pump

have 35m-10.5 m3/ min, service water supply pump is horizontal shaft single suction

centrifugal pump have 25m- 3.5m3/min.

Cooling water system of generator

The cooling water system comprises three main circuits supplied in parallel:

- Air coolers for generator

- Oil coolers for LP lube oil system for the upper bearing housing

- Cooling coil in the lower guide bearing oil chamber.

Compressed Air System

Two compressed air systems

1. Service compressed air system

Vertical water cooled 2 stage compressor

Ratings of compressor 9 bar – 180 𝑚3/ℎ𝑟

Volume of air tank: 3000l

2. Governor compressed air system

W – Type air cooled 3 stage compressor

Ratings: 67 bar – 477lit /min

Volume of air tank: 2000 l

HP and LP Lube Oil System

• HP oil system - Oil is drowning from the upper bearing housing via a strainer to a single

outlet, electrically driven, high pressure Oil pump. The high pressure oil passes through a

Micronics filter to a distribution manifold in the bearing housing. Each thrust pad is fed

from the manifold by a separate flexible hose. A standby AC motor – driven pump is

provided in case of failure of the main pump.

Page 28: Ceylon Electricity Board

25

• LP oil system - LP oil for the combined thrust and upper guide bearing is circulated

externally in a low pressure flow system comprising oil strainer, main and standby ac

motor driven pumps and shell and tube type oil coolers.

Braking and Jacking System

The generator is equipped with 6 combined brake/jack unit a mounted on the lower bearing

bracket and acting against a brake track mounted on the underside of the rotor. The units

are actuating for braking by compressed air, from the unit brake air compressor. The brakes

are controlled by means of an air valve by ‘on’ and ‘off’ solenoids. A manual operating

facility is also provided locally at the valve by means of key-operated pilot valve for ‘on’

and push button operated pilot valve for ‘off’.

An arrangement of manual valves allows a mobile HP oil pump to be connected to the

system so that the brake units may be used for jacking up the rotor during maintenance

operations. A creep detector is fitted to enable shaft rotation to be detected whilst the

machine is shutdown.

Governor

The governor is of hydroelectric PID type. The main item of the governor system are the

regulator, actuator, speed signal generator (S.S.G), pressure oil supply equipment.

Regulator - The regulator is of the PID type. It consists of various solid state

control circuits which include a speed sensing circuit and proportional integral

derivative circuits and power amplifier circuit. The control signal is provided from

the regulator to the converter equipped in the governor actuator.

Actuator - The actuator is enclosed in the steel cubicle. When the unit speed

changes, the actuator immediately responds to the electrical signal from the

regulator.

S.S.G-The S.S.G consisting of three magnetic pickups and toothed wheel is

insulated on the top of the generator housing. The S.S.G is insulated electrically

from the generator. It provides a frequency signal proportional to the unit speed.

Page 29: Ceylon Electricity Board

26

The pressure oil supply equipment -The governor oil supply system consist of the

oil pressure tanks, sump tank, oil pumps, unloader valves, pilot valves, strainers

etc. oil in the sump tank is drawn up by the oil pump and stored in the oil pressure

tanks. Compressed air is trapped in the space above the oil level of the oil tank.

Pressure oil from the tanks is used for operating the governor, inlet valve,

automatic control devices etc. one oil supply system is provided for water turbine,

while two oil pumps are provided, one being selected for normal operating and the

other for standbys.

Fire Protection System of the Generator

Fire protection of the main transformer is by a high velocity water spray system. On

detection of a fire, the automatic deluge value controlling the fire area is caused to operate.

This release pressurized water at 10.75bar, from the 40 m3 capacity pressure tank, in to the

water distribution pipe work. The distribution pipe work then routes the water to the

transformer bay where it is directed at the transformer by a series of projectors.

A fire is detected by quartzite bulb/pressurized water detection system. The quartzite bulbs

are design to shatter should the temperature exceed 79oC, thereby releasing the pressure in

the detector pipe work. This fall in pressure acts on the deluge valve casing it to trip to the

open position. A small water charging pump and an air compressor are provided for filling

the water pressure tank. The system is controlled from a control kiosk located in the

transformer firefighting bay.

2.2.9 400V Switch Board

The main 400V switchboard consists of four individual switchboards interconnected by

encapsulated resin filled bus ducts. In addition to the 400V switchboard, an auxiliary 400V

switchboard for the diesel generator set is provided. The main 400V switchboard has four

in feeds, namely unit transformer one, unit transformer two, station transformer (fed from

the 33KV network) and the diesel generator supply. Only one in feed supplies the 400V

board at any time. Order of priority being either unit transformer, station transformer or

diesel generator. The diesel generator supplies only the essential service board and one of

the unit boards to enable black start of one generating unit.

Page 30: Ceylon Electricity Board

27

2.2.10 Switch Yard

The 132kV switch yard is the outdoor double bus bar configuration utilizing conventional

open terminal equipment. The switch yard comprises four outgoing feeder circuit, two

incoming or generator circuits and a bus coupler circuit. Three empty bays are provided

which are available for future extension to the switch yard. Each incoming and outgoing

circuit is provided with surge arresters, capacitor voltage transformers, SF6 circuit breaker

and two bus bar selection disconnecting switches. In the case of the generator circuits, the

surge arresters are located at the main transformers, rather than in the switchyard. The

outgoing circuits additionally are equipped with a line trap bolted to the top of the yellow

phase capacitor voltage transformers. The bus coupler circuit couples bus bar 1 to 2 via

two bus bar disconnecting switches and a SF6 circuit breaker. The disconnecting switches

and SF6 circuit breaker. The disconnecting switches are provided with earth connection

Switches to earth one or both of the station bus bar. Current transformers are positioned

on either side of the bus coupler circuit breaker for over current protection and are used in

the station bus bar protection scheme. The 132KV circuit breakers are of the SF6 puffer

type, the operating mechanism being electro-hydraulic. A mechanical interlocking system

is provided for the switchyard equipment utilizing fortress key interlocks.

There are three mode of control of the switchyard equipment as local, remote mimic panel

or remote supervisory control.

2.2.11 Generator Transformer

Each generator is provided with a step up transformer of voltage ratio 138/10.5 KV and

rated at 71MVA. The transformers are of the oil immersed three phase type with

ONAN/ONAF cooling. The HV and LV bushing are oil/air insulated. The H.V. bushing is

of the open terminal type for connection to the overhead 132KV line conductors. The L.V

terminals are connected to the 10.5KV isolated phase bus bar system and are totally

enclosed.

Page 31: Ceylon Electricity Board

28

2.2.12 HVAC system

There are two different air conditioning systems in the plant. One for control room area

and office area and other one are machine hull and loading bay area.

Water chiller, chilled water circulation pump, air handling unit and control panels are

provided in the A/C plant room. Water chiller in the A/C plant room serves the both HVAC

systems. Chilled water is supplied to the AHU-1 in the A/C plant room and cooling that

coil by the circulating cooling water through the heat exchanger. River water from the tail

race is supplied to the system by the cooling water supply pump which is installed in the

cooling water gallery. That system can represent roughly by using the following figure.

Then chilled water is passes through the cooling coil in the air handing unit. Chilled water

flow path and arrangement of the air handling unit is shown in the figure,

Chilled water in Chilled water out

Cooling water inlet

from the tail race

Cooling water outlet

from the tail race

Figure 3-13 Chilled water cooling system

Page 32: Ceylon Electricity Board

29

Figure 3-14 Air handling unit arrangement

As shown in the above figure, air temperature at the return position of the cooling coil in

AHU is transmitted to 3- way motorized valve by dew pint sensor and chilled water flow

volume is controlled by motorized valve to suit the air temperature same as the set point

on the automatic control panel. There is a smoke exhaust air system with a AHU. At the

time of the fire accident, air condition supply system stop and return air fan operates as

smoke exhaust fan automatically. Smoke detector and motorized damper are provided to

serve this mechanism.

By considering necessity of the clean, smell and dirty free air toilet exhaust, kitchen

exhaust, oil store exhaust are not used for return air. Separate ventilation systems are

provided for that area.

Fresh air

Supply air

Return

air

Smoke

detector

Louvers

Page 33: Ceylon Electricity Board

30

2.3 Maintenance Works

2.3.1 Annual maintenances (28/12/2015- 11/01/2016) – Kukuleganga Power

Station

Repairing and maintenance of spiral casing was done.

- Dewatering of spiral case and draft tube liner was done by closing the Main Inlet

valve (MIV) and draft tube flap gate and opening the drainage valve of spiral case.

- Then the maintenances have been started.

- After dewatering visual inspection was done in mud removed and cleaned spiral

casing and the damages of painting for water contact surface were solved by

repainting process.

- Such a repainting process was done on that day. First old paint was removed and

primer was applied and then an anticorrosive paint was applied.

Figure 3-15 Repairing and maintenance of spiral casing process

Page 34: Ceylon Electricity Board

31

Figure 3-16 Paints used for repainting the spiral casing

A Cooler of the generator was pressure tested.

- Tested Pressure : 6 bar (Working Pressure : 5 bar)

- If Leakage is detected, rubber packing was replaced. But fortunately there was no

leakage.

Figure 3-17 Pressure testing setup

Page 35: Ceylon Electricity Board

32

Resistive Temperature Detection Tests for the temperature sensors of main bearing,

lower guide bearing were done.

- Equipment Used: Heater, SAE 46 lubricating oil vessel, Thermometer are used

- First the oil bath was heated up and temperature was measured using

thermometer and compare it with the reading displayed by SCARDA system

(calibration was done).

By using a Low Pressure Pump the main bearing (trust bearing) is cooling from draft

water. With parallel to annual maintenance the sealing packing of it that pump was

replaced.

Repaired gate valves of cooling unit of the turbine were re-fixed.

Figure 3-18 Repairing of gate valve

Cyclone separators are in service to supply clean water to turbine shaft seals where the

cooling water further purified and sand and other particles are removed. Sand collector

will be equipped under the cyclone separator, the motor driven drain valve can be

opened automatically by timer or manually by pushing the button to discharge the

sand drain. Such a cyclone separator was dissembled to repair under the annual

maintenance.

Page 36: Ceylon Electricity Board

33

The oil of lower guide bearing, turbine guide bearing and trust bearing was filtered

using the portable oil filter unit.

Figure 3-19 Portable oil filter unit

The clearance larger than recommended value may permit excessive vibration of

turbine. Therefore clearance should be adjusted if necessary. For that the clearance in

between bearing pad and shaft were measured.

o Procedure

I. Guide bearing housing cover was removed.

II. Clearance between shaft and bearing was measured with long feeler gauge.

This clearance will probably not be uniform since the shaft may not have come to rest

in the center of bearing. However the average sum of clearance at diametrically

opposite points is desirable. But for the easiness using pulling bolts clearance at

one point of diametrically opposites were made into zeros.

Page 37: Ceylon Electricity Board

34

Figure 3-20 Clearance measuring test

The ‘O’ rings of the oil cooler of lower guide bearing were replaced.

Procedure

I. The required diameter and length of rubber cord were determined.

II. Drop of Loctite instant (Adhesive) was applied to one end of rubber cord.

III. Two ends of rubber cord was jointed.

IV. Then the rubber ‘O’ ring was placed and coolers were re-fixed.

Figure 3-21 Replacing the ‘O’ rings of the oil cooler

Page 38: Ceylon Electricity Board

35

Oil cooler of governor unit that helps the counter balance which used as mechanical

hydraulic unit to keep the turbine speed stable and regulate the turbine output was

pressure tested at 5 bar and the sealing packing was replaced.

The sealing packings of water supply line system of the governor unit was replaced

and the valves were cleaned.

Clearances of runner guide veins were measured using feeler gauge and electronic

venire caliper.

Figure 3-22 Clearance measuring of runner guide veins

Non Destructive Testing for pole stoppers was done.

o Procedure

- Test part was cleaned and dried before applying penetrant.

- Penetrant was sprayed to cover the test area.

- Time of 20 mins. was allowed before removing surface penetrant.

- Surface penetrant was removed by wiping surface clean with a cloth

moistened with cleaner/ remover.

- Then the developer can was held 20 to 30 cm from the area to be inspected

and thin, even film was sprayed on the part. Followed 10-15 mins of

recommended developing time.

- Final visual inspection was done to identify the cracks. If there are any crack

we can see purple lines clearly in white background. But here we could not

find any cracks

Page 39: Ceylon Electricity Board

36

Figure 3-23 Crack detector dye penetrant

Spiral casing, draft water tube and etc. were inspected before closing the manholes to

re-fill the water.

Rubber sealing were replaced and manholes were closed after ensuring that nothing

and nobody is inside of those.

Figure 3-24 Closing the manhole of spiral casing

The couplings of bearing oil circular pump and bearing oil coolers pumps were re-

fixed and tighten

Page 40: Ceylon Electricity Board

37

Figure 3-25 Tightening a coupling

Cleaned parts of the dust remover (filtering bags) that used to suck out dust inside

generator were re-fixed.

2.3.2 Breakdown Maintenance at Kukuleganga Power Station

A sound from chiller was noted down and the air intake was examined.

o Reason: Then the damper switch of one air intake (There are two air

intakes as standby and operational) wasn’t closed well. So the signal to start

other intake at particular shift change wasn’t taken place.

o Solution: As the reason to malfunctioning damper switch is the dust and

deposition of water particles over long time on that contact surfaces. So a

cleaning is done by spraying a cleaner on it. At that time other intake was

started by switching manual mode in control panel.

Page 41: Ceylon Electricity Board

38

2.3.3 Maintenance works at Samanalawewa

Gate valve of a cooling unit was repaired.

Some gas and arc welding processes were carried out to maintenance works

Different machines of workshop were studied and a chance to operate them was

received. In the workshop of Samanalawewa hydro power station there are

machines for lathe operations, drilling operations, milling, pipe bending, grinding

and etc.

Figure 3-26 Some equipment in machine shop

Water chiller in Air Conditioning plant room services both AC and ventilation

purposes. In our training days at there, one chiller unit had a leakage in its

condenser (water cooled) due to high pressure where we got a chance to reassemble

that unit for repairing. Reason to have a high pressure is due to scaling in copper

tubes of copper tubes of condenser unit as the condenser used in power station not

the best selection for those working conditions. Due to number of tubes for water

cooling is less high pressure is created when units works at fully load. Then

leakages occurred due to that high pressure. Dissembled chiller unit due to water

leakage.

Page 42: Ceylon Electricity Board

39

2.3.4 First Aid Camp at Samanalawewa

During our training period we got a chance to participate for a one day first aid camp

where we could get knowledge of how to handle an immediate accidents, what are the

first aid tips that we must follow in those situations and etc. Some of first aid tips are

follows as extracted from leaflet provided at that day.

Figure 3-27 First aid tips

Figure 3-28 Artifical breathing practical section

Page 43: Ceylon Electricity Board

40

2.4 Thermal Power: How It Works

1. Steam Power Plant

2. Diesel Power Plant THERMAL POWER PLANT:

3. Gas Turbine Power Plant Converts Heat into Electric Energy

4. Nuclear Power Plant

Figure 3-29 How a steam power plant works

As similar in hydro power plant that water flows through the turbine, here steam is sent

through the turbine to generate the electricity which produced by coal fired, diesel fired,

nuclear powered or any energy power operated boiler.

In Sri Lanka we have KPS Gas Turbine, Sapugaskanda-Diesel, Puttalam LakVijaya Coal

Plant and few other steam power plants.

But only one coal power plant in Sri Lanka is Puttalam LakVijaya Coal Plant where I got

an opportunity to get a training of six weeks.

Page 44: Ceylon Electricity Board

41

2.4.1 Important of Coal Power Plant to Sri Lanka

In the present energy has become a more significant factor in the world in power side and

also in an environmental side and also the CEB search the ways to generate electricity

which is cheap and environmental friendly. Hydraulic Power is the cheapest and

environmental friendly method to generate electricity, but hydraulic power cannot fulfill

the nation’s energy consumption

Also with Sri Lanka’s exponential growth the demand for electricity is increasing by about

10% annually. Presently daily electricity requirement of the country stood at 1.9 GW.

Energy supply in Sri Lanka is mainly based on three primary resources, namely,

hydroelectricity, petroleum, and biomass. Hydropower produces 49.4% of electricity and

the wind power produce 0.02% and deficit of 50.58% is fulfilled by fuel.

Generating electricity from oil(diesel, heavy fuel) is cost nearly around 60 rupees per one

unit .So generating electricity from coal is much more than oil because it will cost only 9

rupees per unit. Environmental conditions can be managed by adding suitable methods.

However, Sri Lanka s average consumption is 400 kilo Watt hours per person per annum

and for the country to elevate itself to that of a middle-income level country like Malaysia,

power consumption should be around 2,000 kWh per capita per annum. The North and

Eastern Province too has already progressed in the electrification process and electricity

demand will rice soon.

Electricity costs in Sri Lanka were among the highest in the world with all users paying

high cost for industrial, commercial and domestic uses and driving away the investors.

Main reason for electricity to cost so much is because of our dependence on expensive fuel

oil. The ideal energy source for Sri Lanka should have been a combination of hydro and

coal but high-cost diesel had been promoted due to commercial pressure with diesel being

preferred the energy source of Sri Lanka s Independent Power Plants.

But now at the present moment still we are not taking electricity from private suppliers

also there is a severe drought. All are due to this coal power plant. Otherwise CEB has to

make lot of power cuts and pay lot for private suppliers.

Page 45: Ceylon Electricity Board

42

2.4.2 Working of a Coal Fired Plants

In a coal ­fired steam station water is turned into steam, which in turn drives turbine

generators to produce electricity. Here’s how the process works.

1. Heat is created

Before the coal is burned, it is pulverized to the fineness of talcum powder. It is then mixed

with hot air and blown into the firebox of the boiler. Burning in suspension, the coal/air

mixture provides the most complete combustion and maximum heat possible.

2. Water turns to steam

Highly purified water, pumped through pipes inside the boiler, is turned into steam by the

heat. The steam reaches temperatures of up to 1,000 degrees Fahrenheit and pressures up

to 3,500 pounds per square inch, and is piped to the turbine.

3. Steam turns the turbine

The enormous pressure of the steam pushing against a series of giant turbine blades turns

the turbine shaft. The turbine shaft is connected to the shaft of the generator, where

magnets spin within wire coils to produce electricity.

4. Steam turns back into water

After doing its work in the turbine, the steam is drawn into a condenser, a large chamber

in the basement of the power plant. In this important step, millions of gallons of cool water

from a nearby source (such as a river or lake) are pumped through a network of tubes

running through the condenser. The cool water in the tubes converts the steam back into

water that can be used over and over again in the plant. The cooling water is returned to

its source without any contamination, and the steam water is returned to the boiler to repeat

the cycle.

Page 46: Ceylon Electricity Board

43

Figure 3-30 From coal to electricity

Page 47: Ceylon Electricity Board

44

2.4.3 Introduction to LakVijaya Power Station

As the 1st coal power plant in Sri Lanka LakVijaya Coal Power Plant is doing a great

amount of work to the National energy supply. It is located at Norachcholai village, in

Narakkalliya. As the main advantage of LakVijaya power station is it will not affect by the

environmental conditions like the hydraulic power plants because of that CEB can have

full load capacity throughout the year. It would be a major advantage for the CEB when

energy problem started. As the main weakness of the LakVijaya power plant is supplying

the coal at right time and stores them to a certain period. Because ships cannot come every

month of the year from May to October because of the sea waves because of that coal

storing facilities should be improved. Also there will be SO2 byproduct in flue gas, it is

not good for humans and it should be removed from flue gas.

2.5 Main Sections of LakVijaya Power Station

2.5.1 Fuel Handling Section

Coal handling- Provides coal to the three boilers in the power plant and unloads the coal

from the ships.

Supply ignition and combustion supporting oil-light diesel oil.

There are delivery pumps for diesel and conveyer system with other supporting equipment

for coal.

In LakVijaya Power Plant we use Bituminous coal,

As it has following characteristics compared to Anthracite and Lean coal

Ignition and combustion are relatively easy

Flame is long

Calorific value is relatively high

Weak chocking behavior during combustion

Page 48: Ceylon Electricity Board

45

And also relative to Earth coal Bituminous coal good for long distance conveying and

longtime storage.

Bituminous coal specifications

- Particle Size : < 50 mm

- Moisture Content : < 12 %

- Gross Calorific Value : 5800 - 6300 kCal/kg

- Ash Content : < 15 %

- Bulk Density : 0.8-0.85 t/m3

- Sulphur content : 0.2 –1.2 %

- Volatile matter : > 22 %

- Fixed carbon : > 43 %

Power Plant will burn imported coal of high quality and low Sulphur Bituminous coal from

Australia, South Africa, Indonesia and the United States (but most of the time these coal

imported from Indonesia and South Africa). Imported coal would be unloaded to barges

at mid sea, and coal barges will then be unloaded onto conveyors on near shore trestle jetty

and transferred to the coal storage yard.

- Coal is transported by the ships called “PANAMAX” and capacity of these ships

nearly around 85000GWT.

- Then that coal transported to the jetty by the self-propelled barges (Capacity:

around 1500-2000 tons) and then they unload by the ship unloader.

- Coal purchasing and handling up to jetty is done by “Lanka Coal Company”

- Coal consumption for one Boiler : 114 t/hr

- Coal storage capacity 738,720 t

Page 49: Ceylon Electricity Board

46

Figure 3-31 Coal unloading system

Figure 3-32 Jetty

Page 50: Ceylon Electricity Board

47

Figure 3-33 Self propeller barge

Ship Unloader

Bridge type grab ship unloader is one of the main unloading devices of project loading and

unloading feedstock coal in Puttalam 300MW coal power station dock, this is the type with

4-winding-drums hauling car. When working, after grab bucket grabs bulkcargo from

cabin, grab car runs towards shore, unload the bulkcargo to the inboard hopper of front

gantry, cart drives the whole machine to run along the dock track to realize shifting taking

materials.

Figure 3-34 Coal unloading process

Page 51: Ceylon Electricity Board

48

Bridge type grab ship is mainly composed by security supporting facilities, including steel

structure; rising, opening and closing, car running gear (the three melds, we call them 4-

winding-drums gear for short); amplitude gear; cart running gear; material conveying

system; dustproof and environmental system; mobile operator’s cab; electrical system;

inspecting facilities and wheel clamping device, anchoring, hitch lines, safty hook, limit

device,etc.

Figure 3-35 Parts of bridge ship unloader

Page 52: Ceylon Electricity Board

49

Coal Yard

Figure 3-36 Coal yard

The total storage capacity of coal yard is approximately 738,720 t, which can meet up with

the coal consumption of 900MW units for 90 days or three months. There is a wind

resistance wall with height of 15m located near sea side along the coal yard. Anti-penetrate

film is provided on the coal yard ground to prevent coal water from penetrating or

contaminating the ground water. Also the coal yard consists of dry coal shed. That means

of concrete supports with a steel roof enclosed and for phase I dry coal shed has

length/width/height of 50m/100m/30m, and the capacity is 19,152 t, which can meet up

with the coal consumption of 300MW units for 7 days.

Bucket Wheel Stacker-Reclaimer

There are two bucket wheel stacker-reclaimers in the power plant and its arrangement

makes coal stacking to coal yard and supplying coal to coal bunkers simultaneously.

- stacking capacity : 1500t/h

- reclaiming capacity : 600t/h

Figure 3-37 Bucket wheel stacker-reclaimer

Page 53: Ceylon Electricity Board

50

Belt Conveyer

This conveyer system is use for the transport coal from jetty to coal yard and coal yard to

coal bunkers. The design capacity of conveyor and their associated equipment will be

calculated on the basis of 24 hours continuous operation. These conveyers are different

from each other.

Coal Bunkers

After coal is transport through the belt conveyers to feed to the boiler they are temporally

stored in the coal bunkers. There are five coal bunkers for the one boiler.

Fuel Supply System to Boilers

By the fuel system supplies the necessary fuel to the furnace. For the startup of the boiler

diesel is used and after reaching the balanced condition coal is used in the furnace. This

diesel line is always in operational which means that diesel oil pumps always operating

when plant is at operational and circulating the diesel. Coal feeding system consists of

coal feeder, coal pulverizer and coal burners.

Figure 3-38 Coal bunker

Page 54: Ceylon Electricity Board

51

Coal feeder

There are five coal feeders in one phase and it is able to supply coal continuously and

evenly. During whole process of operation, the feeder performs accurate weighing of the

feeding and indicates the instantaneous value and accumulative amount of coal supply,

and automatically adjust coal supply quantity according to the instruction of boiler

combustion control system to meet the requirement of boiler load.

Figure 3-39 Coal feeder

Coal pulverizer

The type of mill is MPS HP or ZGM and bowl type middle speed mill. When burning the

rainy season coal or range of coal, all pulverizer have to be used. The total output of

operating pulverizes except the standby one is greater than 110% of consumption of coal

at BMCR condition. Pulverizes is capable of re-starting, following an emergency trip.

There are five coal pulverizer in one phase and four is operational and one is standby. Its

main function is to pulverize the coal from coal feeder. It consists of transmission device,

grinding roller, spring load device, bowl device, side body, separator body, blades device,

Venture Outlet and porous outlet devices, coal pulverizer outlet valve device.

Page 55: Ceylon Electricity Board

52

Figure 3-40 Coal pulverizer

Page 56: Ceylon Electricity Board

53

2.5.2 Boiler and Boiler Auxiliaries Section

In this part mainly consist of boiler and to support the functions of the boiler and there are

many boiler auxiliary systems such as,

Furnace

Air system

Ash handling system (both fly ash and bottom ash)

Fuel system

Electrostatic Precipitator (ESP)

Flue Gas Desulphurization system (FGD)

Boiler

The boiler is all steel-frame suspension structured, bituminous coal- fired drum boiler with

sub-critical parameters, natural circulation single furnace, primary intermediate reheat,

balanced draft, corner firing four corner arrangement sway burner ,tangent burning, and

dry ash extraction. The boiler mainly consists of steam drum, water wall, divisional panels,

re-heaters, super heaters, economizer, soot blowers and air pre heaters. The wall type

radiation re-heater and big patch divisional panels are arranged (hanged) in the upper

furnace to increase the radiation characteristics of the re-heater and the super-heater. There

are all together 92 soot blowers which include 60 wall soot blowers and 32 extension soot

blowers which use for the cleaning of the ash deposit on the water wall.

Table 2.1: Boiler specifications

Boiler design parameters BMCR condition THA condition

Super heated steam flow 1025t/h 912t/h

Super heated outlet pressure 17.3Mpa 17.2Mpa

Supper heated steam outlet temperature 5410C 5410C

Reheated steam flow 851.3t/h 762.8t/h

Reheated steam inlet pressure 3.993Mpa 3.574Mpa

Reheated steam outlet pressure 3.793Mpa 3.395Mpa

Reheated steam inlet temperature 338.50C 326.90C

Reheated steam outlet temperature 5410C 5410C

Feed water temperature 282.20C 274.60C

BMCR : Boiler Maximum Continuous Ratings THA : Thermal Heat Acceptance

Page 57: Ceylon Electricity Board

54

Page 58: Ceylon Electricity Board

55

Figure 3-41 Steam cycle

Page 59: Ceylon Electricity Board

56

Main Components of the Boiler System

Economizer

The function of the economizer is to heat the boiler feed water, thereby recovering heat

from the flue gas leaving the boiler. Its arrangement has been designed to be completely

drainable. The water flow preferably is upwards. The economizer has been divided into

banks the height of which is not more than 3.2m and the distance between the banks is not

less than 0.8m.

Super heater system

The super heater consists of six main components; final stage super-heater, rear plate

super-heater, isolating platen, vertical low-temperature super-heater, horizontal low-

temperature super-heater, rear pass wall enclosure and ceiling super-heater. The super-

heaters are equipped with two-stage de-super-heater sprays. Total flow of spray water is

less than 10 percent of MCR flow of boiler.

Steam drum -

Drum diameter Φ1778mm, wall thickness 178mm, body length18000mm, total length

20184mm, gross weight 189 tons. There is cyclone separators inside the drum to separate

the water in steam and also it consist of safety valves for the safety of the drum. The feed

water for the boiler is directly entered to the drum through the economizer and then the

water and steam separated in drum and water is delivered to the water walls through the

down comers.

Figure 3-42 Steam drum

Page 60: Ceylon Electricity Board

57

Re-heater system

The re-heater consists of three main components; final re-heater, re-heater front platen,

wall radiant re-heater. Burner tilting is adopted to control steam temperature of re-heater

and total flow of emergency de-superheating spray water for re-heater is less than 5 percent

of MCR flow. Change of excess air also can control RH steam temperature as assistant

method at lower load.

Figure 3-43 Main component of the re- heater system

Figure 3-44 Boiler main auxiliary systems and steam path arrangement

Boiler

Furnace

Economizer

HPH1

HPH2

HPH3

Supper heater

LP Turbine

Condenser

Hot well

HP Turbine

IP Turbine Re-heater

LPH1

LPH2

LPH

3 LPH

4 Gland steam condenser

Deaerator

Deaerator tank

Page 61: Ceylon Electricity Board

58

Furnace

Furnace consists of four oil burners at four corners which can be tilted up and down and

the all burners are tangential firing and also consist of five coal burners in five layers at

four corners. Also there are secondary air delivery windows.

In the furnace it uses the tangential firing method to fire coal and the oil. In furnace ignition

oil are used for warming up boiler during start up, coal nozzle ignition and the stabilizing

combustion under low load. Extractable high energy igniter and simple mechanical

atomization nozzle is adopted in oil gun

Two imaginary cycles are adopted in the furnace. Main burning system imaginary cycle is

must be tangential firing with counter clockwise. OFA is designed to be anti-tangential.

So it can form reverse momentum to balance the main rotary momentary and reduce the

furnace outlet gas deviation. Furthermore combusting with higher ratio of OFA reduce the

NOx formation.

Figure 3-45 Burner and wind box arrangement inside the furnace

Page 62: Ceylon Electricity Board

59

Figure 3-46 Plane view of the fire arrangement and imaginary fire circle

Table 2.2: Furnace Specifications

Primary air ratio 22.20%

secondary air ratio 73%

Primary air temperature 3360

secondary air temperature 344.40

primary air velocity 27m/s

Secondary air velocity 47m/s

tangential circle diameter 800m

Air System

In the air system is consists of primary air system, secondary air system, seal air system

and flue gas system. By the secondary air system it supplies necessary air for the furnace.

The seal air system is used to supply the seal air for the coal mills and coal feeder.

Page 63: Ceylon Electricity Board

60

Primary Air system

The function of this system is providing air to pulverizer for transport coal to furnace. The

primary air is supplied by two constant speeds, electric motor-driven, centrifugal, primary

Air (PA) fans. Fans are suitable for all weather outdoor operation. There are two primary

air fans and after the primary air fans part of air goes to the APH (air pre-heater) and other

part goes to wind box. Then heated air outlet of the primary air will be combined into a

common duct at wind box which the air distributed to each pulverizer. The air flow rate

will be controlled to maintain the proper velocity in the pulverizer and in the conveying

pipes.

Figure 3-47 Primary air fan

Secondary Air system

The function of the secondary air system is to provide large amount of hot air for the

optimum combustion process in the furnace. Two forced draft (FD) fans having constant

speed, electric motor - driven, axial flow supply secondary air to the furnace. Fan inlets

are provided with silencers. Variable dynamic blade pitch is used to control (hydraulically

controlled) the flow through the fans. Secondary Air is heated by Air Pre-Heater (APH).

From the APH, the secondary air is distributed into the boiler wind boxes.

Page 64: Ceylon Electricity Board

61

Seal Air system

Seal air is supplied to the following equipment pulverizers, coal Feeders, pulverizer

primary air inlet dampers, and pulverized coal shut off gate other dampers and accessories.

The source of the seal air is air from the PA fan. Two constant speed and electric motor-

driven, seal air blowers is used to obtain the required seal air pressure. While one fan is in

operation, the other one is stand-by. The capacity of each seal air blower will be 1.2 times

of the total seal air.

Figure 3-48 Seal air fan

Flue Gas system

In the flue gas system, gas flue flow coming from burning goes through heat exchangers

then is vented to the outside air continuously and instantly in order to maintain boiler

running. To take out the flue gas from the furnace there are two induced draft (ID) fans.

When the flue gas came out from the boiler their heat energy is recovered by the Air Pre

Heater (APH) and by this heat it heated the secondary air. This APH works as the gas to

gas heat exchanger.

Page 65: Ceylon Electricity Board

62

FD fan and ID fan

Forced Draft Fans supplies the air necessary for fuel combustion and must be sized to

handle the stoichiometric air, plus the excess air needed for proper burning of the specific

coal for which they are designed. It provides air to make up for air heater leakage and for

some sealing air requirements. Forced draft fans supply the total airflow except when an

atmospheric-suction primary –air fan is used. It operates in the cleanest environment

associated with a boiler and is generally the most efficient fans in the power plant. The

main purposes of the ID fans are to take out the flue gas which in inside the furnace. The

flow rate of the flue gas is control by adjusting the stator blades angle of the ID fans.

Always flow rate from ID fan higher than FD fan to maintain negative pressure inside the

furnace.

Electrostatic Precipitator (ESP)

ESP is a highly-efficient, energy-saving equipment for flue gas cleaning, having merits of

high collection efficiency, large gas volume to be treated, long life span and low cost of

maintenance. At present, as the requirements for environmental protection are becoming

more and more stringent, ESP is used more widely.

When passing through the high voltage electrostatic fields, dust particles in the gas will be

charged by colliding with positive ions, negative ions and electrons or in the ion dispersion

movement. The particles with electrons and ions will then move, under the influence of

Figure 3-49 FD and ID fans

Page 66: Ceylon Electricity Board

63

the electric force, toward and later accumulate on the electrodes of opposite polarity. By

means of rapping, the layer of dust particles on the electrodes will be dislodged into the

bottom hoppers. Practice shows that the higher the strength of electrostatic field, the more

effective an ESP will be, and that it is preferable to have an ESP operating with negative

corona.

Figure 3-50 Working principle of ESP

Then passing through the high voltage electrostatic fields, dust particles in the gas will be

charged by colliding with positive ions, negative ions and electrons or in the ion dispersion

movement. The particles with electrons and ions will then move, under the influence of

the electric force, toward and later accumulate on the electrodes of opposite polarity. By

means of rapping, the layer of dust particles on the electrodes will be dislodged into the

bottom hoppers. Practice shows that the higher the strength of electrostatic field, the more

effective an ESP will be, and that it is preferable to have an ESP operating with negative

corona.

Page 67: Ceylon Electricity Board

64

Flue Gas Desulphurization system (FGD)

Flue-gas desulfurization (FGD) is a set of technologies used to remove sulfur dioxide

(SO2) from exhaust flue gases of fossil-fuel power plants, and from the emissions of other

sulfur oxide emitting processes.

Most FGD systems employ two stages: one for fly ash removal and the other for SO2

removal. Attempts have been made to remove both the fly ash and SO2 in one scrubbing

vessel. However, these systems experienced severe maintenance problems and low

removal efficiency. In wet scrubbing systems, the flue gas normally passes first through a

fly ash removal device, either an electrostatic precipitator or a wet scrubber, and then into

the SO2-absorber. However, in dry injection or spray drying operations, the SO2 is first

reacted with the sorbent, and then the flue gas passes through a particulate control device.

Another important design consideration associated with wet FGD systems is that the flue

gas exiting the absorber is saturated with water and still contains some SO2. These gases

are highly corrosive to any downstream equipment such as fans, ducts, and stacks. Two

methods that can minimize corrosion are:

o Reheating the gases to above their dew point, or

o Choosing construction materials and design conditions that allow equipment to

withstand the corrosive conditions.

Both alternatives are expensive, and engineers designing the system determine which

method to use on a site-by-site basis.

Figure 3-51 Flue­gas desulfurization unit

Page 68: Ceylon Electricity Board

65

The FGD system includes a booster fan (Axial flow fan with adjustable guide vanes), a

GGH (gas-gas heater), a FGD inlet damper, a FGD outlet damper, three absorber pumps,

three aeration fans and other auxiliary devices. SWFGD Process is operating using the

seawater as the only absorbent. The seawater absorbs and neutralizes SO2 and any other

acidic mass in the flue gas.

At the first flue gas enters bottom of the FGD and it gives it heat through the GGH to

treated flue gas. Then sea water pumps to top of the FGD and by plastic packing layer sea

water is uniformly distributed throughout the absorber. Then the SO2 in the flue gas is

absorbed by the sea water and the same time those treated flue gas heated through the

GGH by the incoming flue gas to the FGD. In the absorber following chemical processors

are take place.

SO2 (gas) SO2 (dissolved in the sea)

SO2 (dissolved in the sea) + H2O SO32- + 2H+

After absorbing the SO2 by sea water those sea water is send the aeration basin. In the

aeration basin, following chemical processors are take place in the aeration basin.

SO32- + 1/2 O2 (gas) SO4

2-

CO32- + H+ HCO3

-

HCO3- + H+ CO2 (gas+ dissolved in the sea) + H2O

Page 69: Ceylon Electricity Board

66

Figure 3-52 Working principle of aeration basin

Figure 3-53 Aeration of sea water to remove Sulphur

Page 70: Ceylon Electricity Board

67

2.5.3 Turbine and Turbine Auxiliaries

The turbine body is comprised of rotating and static parts. Rotating parts include cascades,

impellers, main shaft, coupling and fasteners. Static parts are comprised of cylinder nozzle

box, diaphragm sleeve, gland seal, bearings, bearing seats, anchorage system, base and

related fasteners.

Turbine is sub-critical, primary intermediate reheat, single-shaft, double cylinder, double

exhaust, reaction, and condensing steam turbine. This turbine has three pressure stages as

high pressure, Intermidiate pressure and low pressure.high, intermediate pressure

cylinders are integrated into one, and through-flow parts are reversely arranged. For the

high-pressure cylinder, the steam enters it from the lower part, and flows through high-

pressure automatic main steam valve, governing valve, into the positive governing stage,

and then turns the steam flow back by 180° to the 12th reaction stage reversely. For the IP

cylinder, the steam enters it from the lower part, and flows through the IP combined control

valve into the positive 9th reaction stage. For the LP cylinder that is symmetrically

arranged, the steam enters it from the middle, and flows reversely via 7 reaction stages,

respectively. High, intermediate pressure cylinders are double-layer cylinders, and the LP

cylinder is a three-layer cylinder.

Figure 3-54 LP, IP and HP turbines

LP Turbine

Page 71: Ceylon Electricity Board

68

Rotor

HP rotor is combined rotor type, with governing stage at the middle and HP and IP part at

front and back which is integrally forging cast by heat-resistant alloy steel. There are

cooling steam holes at the roots of governing stages after which steam is extracted to cool

the first stage of IP stages, and this method can prolong the service life of rotor. An

extension bearing is connected with the front end of HP and IP rotor, thrust disc, main oil

pump and emergency ram are installed on it. HP and IP flow is arranged conversely, and

axial thrust is balanced by 3 balancing pistons to keep a small positive thrust.

Bearings

The whole turbo-generator unit has a total of six journal bearings that are respectively

fixed on the base seat. The radial bearings of HP & IP rotors are compressible, and the LP

rotor is equipped with 2 tilting-pad bearings and spherical cushion circular journal bearing.

The thrust bearing is a tilting, double adjusting block, located on the short shaft of the

turbine inside the front bearing housing

Figure 3-55 Bearing arrangement of the rotor

Turbine auxiliaries

In this part mainly consist of turbine and to support the functions for the turbine and there

are many turbine auxiliary systems such as,

Boiler feed water pump

Regenerative system

Lubrication system

Circulating water system

EH oil system Generator

Barings

Page 72: Ceylon Electricity Board

69

Boiler Feed Water Pump

Boiler feed water pump is consist of two main parts. They are boiler feed water pump and

boiler feed booster pump. At first feed water came in to the boiler feed booster pump. The

function of the boost pump is to raise the inlet water pressure of the feed-water pump in

order to prevent vaporization in the feed-water pump. Three 50% capacity, horizontal type,

single stage, double suction, centrifugal type boosts pumps are provided. Along the flow

direction, the inlet water pipes of boost pumps are equipped consecutively with a motor

operated gate valve, a pressure release valve and a coarse strainer. The pressure release

valve protects the boost pump and its inlet pipe from possible over pressure, in addition,

the pump warm-up water during reverse warm-up of the pump can also go through the

stand-by boost pump into the inlet pipe. Under those two conditions, an over pressure may

be induced in the stand-by boost pump and its inlet piping, if the inlet isolating valve of

the stand-by boost pump is closed. After the booster pump feed water enters to the boiler

feed water pump. Three 50% capacity, horizontal type, multistage double casing, barrel

type centrifugal motor operated regulating feed-water pumps are provided in the system.

Each feed-water pump is installed with its boost pump as an assembly, and sharing one

motor. A fine strainer is provided in the inlet pipe of BFP, its function is the same as that

of the coarse strainer, but it will not be removed after a certain period of operation. When

the fine strainer is closed by contaminants and high differential pressure is induced, the

pump will be shut-down to clean it out. A main feed water flow nozzle is provided on main

feed water pipe downstream of the highest pressure heater to measure feed water flow to

boiler. The main boiler feed pumps have an inter stage bleed point to furnish re-heater de-

super heater water at the appropriate pressure level. Water to the main steam de-super

heaters is furnished from main feed water line upstream of the No.3 HP heater. The

controls for the re heater and super heater at temperature sprays are part of the coordinated

control system (CCS) to control the steam temperatures by modulating the spray control

valves.

Regenerative System

In the power plant there are eight regenerative stages and this regenerative system uses for

the increase the efficiency of the power plant. It consists of steam extraction, HP and LP

heaters and deaerator.

Page 73: Ceylon Electricity Board

70

Steam Extraction

The turbine has eight (8) pressure stages of non-regulating extraction steam. The No.1,2&3

extraction steam stages supply steam to three (3) HP heaters respectively to heat the feed

water which will flow into boiler. The No.4 extraction steam stage supply steam to

auxiliary steam header and deaerator. The No.5, 6, 7 & 8 extraction steam stages supply

steam to four (4) LP heaters respectively to heat condensate water which will flow into

deaerator.

HP and LP heaters

Feeding water system adopted in this 300MW unit adopts single series, horizontal and big

bypass arrangement. It consists of three HP heaters and uses the No.1, 2 and 3 extraction

steams as the heating medium.

This 300MW unit has four LP heaters, which are arranged in series connection. The type

is horizontal, double flow surface type. There are four LP heaters in one 300MW unit and

it uses the No. 5,6,7 & 8 extraction steam to heat the feed water.

Deaerator

In order to remove corrosive gases entrained in boiler feed water an open feed water heater

called a deaerator is incorporated into the power cycle. The deaerator is designed to heat

the incoming feed water to the saturation point in order to reduce the solubility of any

entrained gases. These are mainly oxygen, carbon dioxide and ammonia that become very

corrosive at elevated temperatures. The water is sprayed in a fine mist into the area that

contains the steam drawn from the high pressure heater drain and extraction steam from

the cold reheat section. This divides the water droplets increasing the overall surface area

therefore increasing the overall heat transfer. The water is then passed over a set of trays

that separates the water into thin sheets from which the gas can easily escape. The gases

are then vented out of the deaerator to the atmosphere.

Page 74: Ceylon Electricity Board

71

Lubrication System

The function of lube oil system is to supply lube oil to the bearings of the unit, the pressure

oil to the governing and emergency system, to the generator bearing and to the turning

gear and jacking device. This system adopts traditional turbine rotor to drive main oil

pump-oil ejector system directly, the main oil pump supplies the pressure oil to governing

and emergency system and also supplies the power oil to the oil ejector. The lubrication

system adopts horizontal type cylindrical oil tank. The AC lube oil pump, DC emergency

oil pump, HP START-UP oil pump, oil level indicator, oil level switch and oil tank electric

heater are installed on the cover plate of oil tank. The oil ejector is installed on internal

piping of oil tank. The oil tank is arranged above 0m floor. One HP oil jacking device is

set in T-G bearings, that the oil jacking pump is plunger pump and supplies oil to every

bearing through diverter and single-way throttle valve. When the speed increases

to1200r/min during startup, cut off jacking device; and during shutdown period, when the

speed decreases to 1200r/min, start oil-jacking device.

Circulating water system

The main function of circulating water is taking away the surplus heat of exhaust

discharged from turbine to condenser, and making it condensate to water. The main

equipment of this system includes a movable grilling filter in the CW pump house front

pit, two rotating filters at the inlet of CW pump, two CW pumps, one set of cooling water

device for CW pump motor, two debris filters, two sets of ball cleaning device for

condenser and its auxiliary pipelines.

Condenser

The function of the condenser is to make the exhaust steam form the turbine condensed

and turn in to the water and to ensure the exhaust outlet of turbine to build the necessary

auxiliary equipment with certain vacuum. Condenser consists of connection neck, shell,

water room and connection pipes of exhaust steam. The final two stages assembled LP

heaters (#7, #8 LP heaters) and condensers adopt single square shell. Its advantage is that:

it is made by welding steel plates, its process is simple, its weight is low and it may make

full use of space under turbine. It is single shell, bisection, double flow surface type.

Page 75: Ceylon Electricity Board

72

Exhausted steam of both turbine and feeding water pump enters into condenser. The water

room of the condenser is divided into two separate cooling water pipes, which have their

own cooling water inlets and outlets. When condenser is dirty, turbine does not need to

stop, it can be cleaned under condition of decreasing a certain load.

EH oil system

EH oil system supplies high pressure oil to turbine governing system, it is pumped from

fire-resistant oil tank by HP oil pump, it passes pressure oil filter and enters into HP

accumulator through single direction valve. EH oil then is sent to actuators and emergency

governing system by HP oil head pipe. EH oil system consists of oil tank, oil pump, control

block, oil filter, overflow valve, accumulator, oil cooler, EH terminal box and so on. There

are 12 steam valves in DEH system for one unit of the power plant, 2 HP combined steam

valves, among which there are 2 HP main steam valves, 6 HP governing valves; two IP

combined steam valves, among which there are 2 reheated main steam valves, 2 reheated

governing valves. The 4 combined steam valves are located at left and right sides of the

unit respectively. HP main steam valves (TV) are double valve butterfly style, operated

horizontally, arranged at two sides of HP and IP cylinder. There is one small valve for

startup inside the main valve; all valves are single seat non-balance butterfly valves. Open

startup valve to extreme position of its travel, if it opens further, main valve will open.

When main valve is fully open, it is self-sealing structure and there is permanent filter

screen and temporary filter screen at steam inlet. When it closes, startup butterfly valve in

main valve is able to align automatically. Main steam valve is a control type, which is able

to control steam valve at any middle position and to regulate inlet steam proportionally to

meet requirement.

Six (6) HP governing steam valves are installed in the unit, which are allocated at left and

right side of HP & IP cylinder, and assembled together with main steam valves in an

integrated forged piece, composing a steam incoming group. For each steam incoming

group, 1 main steam valve and3 HP steam governing valves are installed. HP steam

governing valve is to control steam flow coming into HP steam cylinder.

Page 76: Ceylon Electricity Board

73

2.5.4 Generator

The generator is three phases non salient pole synchronous generator. The neutral of

generator is grounded through dry transformer with secondary neutral. The generator

include stator, rotor, end shield and the bearing , hydrogen cooler, oil seal, sole plate, brush

holder, collector cover etc. The generator is completely enclosed. The main cooling

material is hydrogen gas circulated by fans. The excitation system of the generator is static

excitation system.

Table 2.3: Generator specification

Aperent power 353MVA

Active power 300MW

Maximum continuous power 332MW

Rated power factor 0.85(lag)

Rated stator voltage 20000V

Rated stator current 10190A

Excitation voltage 365V

Excitation Current 2642A

Efficiency 98.90%

Frequency 50Hz

Rotate speed 3000rpm

Number of phase 3

Stator winding connection type YY

Number of terminals of stator 6

2.5.5 Transformer

Generator Transformer

The transformer will be 3 phase, 50Hz, forced-oil force-air cooled (FOA), oil immersed,

outdoor type with copper windings and low losses. Transformer is supplied with radiators.

The Generator transformer's high voltage terminals are protected by three zinc oxide

lightning arresters at 220KV terminal cable to the switchgear.

Page 77: Ceylon Electricity Board

74

Startup /Standby Transformer (SST)

One Start/ Standby transformer (SST) is set for phase one. The SST is a three wingding

transformer with two equally rated secondary windings. It’s an outdoor type transformer

with on-load tap changer .The high voltage terminal of SST is connected to the 220kV GIS

switchgear through the cable, the low voltage terminal of SST is connected to the 6kV

spare incoming switchboard through the non-segregated phase metal enclosed bus. The

SST provide power to two separate 6kV buses during startup and normal shutdown of the

plant and during plant operation upon loss of the normal auxiliary electrical supply.

Unit Auxiliary Transformer (UAT)

The UAT transformer the generator voltage down to 6.3kV and provides power to two

separate 6kV buses during normal operation. The UAT is a three winding transformer with

two equally rated secondary windings. It’s an outdoor type transformer with no-load tap

changer.

2.5.6 Balance of Plant (BOP)

Balance of the plant section consists of sea water desalination system, boiler makeup water

system, condenser polishing plant, waste water treatment system, auxiliary boiler and

hydrogen generation system. These systems are used as the support system to the other

systems in the plant.

Sea Water Desalination System

Sea water desalination system uses to produce raw water from the sea water. It supply

desalted water for domestic, boiler make-up water system, firefighting, industrial water

and etc. The capacity of seawater desalted system will be 100 m3/h. Sea water will be

clarified and filtered, then will be transferred to sea water desalted system. There are four

treatment stages in the process,

Page 78: Ceylon Electricity Board

75

I. Coagulation

In this process they add two chemicals to the sea water coming from the row water pumps

which is called Poly Aluminum Chloride (PAC) and Polyacrylamide (PAM). Then this

water send to coagulation tanks and in the tank mud partials are settled in the bottom of

the tank.

Figure 3-56 Coagulation tanks

II. Filtration

After the coagulation process the water sent to the gravity filtration process. In this process

Water flows through the filter medium contained in an open tank or vessel under the

influence of gravity and then filtered water sent to the clear water basin.

III. Ultra filtration

Water in the clear water basin is then pump in to the ultra-filters (UF filters) to further

filtration process. This is a process of filtration with a semi permeable membrane with

pressure relatively lower than RO. Then the filtered water pump to the UF tanks

Figure 3-57 Ultra filter

Page 79: Ceylon Electricity Board

76

IV. Reverse osmosis (RO)

After the UF tanks water enters to the RO process. In here it removes many types of large

molecules and ions from solutions by applying pressure to the water. RO unit consists of

cartridge filter, energy recovery unit, high pressure pump, circulation pump and RO

membrane.

Figure 3-58 RO device

Energy Recovery unit (ERI)

By this unit Waste energy recycled at up to 98% efficiency. It consists of a rotor and

surrounding of that rotor has a sleeve and two end covers. At first high pressure reject

concentrate from RO enter one side of the ERI and low pressure sea water enters other

side of the ERI and fills the rotor where it exposed to the high pressure reject concentrate.

Then the hydraulic pressure is been directly transfer in to the reject to seawater. This sea

water goes back in to the system and joined to the stream from HP pump and concentrate

exits to drain. This pressure transferring process continuous and rotor only using fluid for

rotating and because of high rotating speed (1200 r.p.m) mixing between concentrate and

sea water is low.

Page 80: Ceylon Electricity Board

77

Figure 3-59 Energy recovery unit operation principle

After the RO device desalted water is send to the service and fire water, for make-up water

treatment system and for portable water inside the plant domestic work.

Make-up Water Treatment System

This system main functions are supply high purity boiler make-up water (De-mineralized

water) for boiler, supply high purity water to systems in power plant operation (chemical

lab, sample analysis, closed cycle cooling water system) and supply necessary high purity

water for the cleaning and flushing of boiler and turbine system and for lay-up and filling

of the system before start-up.

The capacity of second stage RO will be 2×36m3/h, the capacity of demineralizer will be

2×60 m3/h. The system will be RO, first-stage demineralization and mixed bed, and the

flow path will be as follows,

Figure 3-60 Make-up water treatment process flow chart

Desalted water De-carbonator Intermediate

water tank Safety filter

Second stage RO

Cation exchanger

Anion exchanger

Mixed bed

De-mineralized water storage

tank Main building

Page 81: Ceylon Electricity Board

78

Chlorination Plant

By this plant it provides the chlorine need to dosing to the sea water inlet in the sea. In

here it makes chlorine as sodium hypo chlorate (NaOCl). With seawater as raw material,

6.0KVAC is transformed and rectified to DC through transformer rectifier and applied to

the cathode and anode of seawater electrolytic cell. The seawater get electrolytic reaction

and generate active chlorine, which is put into once-through water cooling system and

seawater pretreatment system with sodium hypochlorite dosing pump to resolve issues

such as the adhesion and breeding of marine organisms and thallophytic in cooling water

pipes and copper condenser tubes, which reduce flow area and influence of water-delivery

capacity, lower cooling efficiency of the condenser, forcing the generating unit to operate

in low load and influence of power generation.

Anode reaction: 2Cl - Cl2+2e

Cathode reaction: 2H2O+2e 2OH-+H2

Chemical reaction between electrodes:

Cl2+2OH- ClO-+Cl-+H2O

ClO-+H2O HClO + OH-

HClO H++ ClO-

Overall reaction:

NaCl+H2O NaClO+H2

Hydrogen Generating System

The cooling method of our plant 1 × 300MW generator unit is water - hydrogen – hydrogen

cooling; hydrogen station provides central hydrogen supply. System include electrolyzer,

oxygen separation scrubber, hydrogen separation scrubber, hydrogen coolers, hydrogen

drying devices, hydrogen storage tank and the rectifier cabinet, desalted water cooling

devices. The hydrogen system is under complete automatic control, the system can

perform automatic open, shut down, automatic alarm and command operation. In the

normal operation, the computer screen can show process, real-time parameters, curves,

store data automatically and print various sheets. Total capacity of hydrogen storage is

Page 82: Ceylon Electricity Board

79

designed in accordance with normal consumption of hydrogen-cooled generator, and the

accumulated hydrogen storage is equivalent to total capacity of startup charging hydrogen

of largest hydrogen-cooled generator within seven days or so.

Figure 3-61 Hydrogen generating system

Figure 3-62 Hydrogen generating storage system

Page 83: Ceylon Electricity Board

80

Control Room (DCS) Operation

A distributed control system (DCS) refers to a control system usually of a manufacturing

system, process or any kind of dynamic system, in which the controller elements are not

central in location but are distributed throughout the system with each component sub-

system controlled by one or more controllers.

DCS (Distributed Control System) is a computerized control system used to control the

production line in the industry. The entire system of controllers is connected by networks

for communication and monitoring. DCS is a very broad term used in a variety of

industries, to monitor and control distributed equipment.

In LakVijaya Coal Power Plant we examine all the activities happened in power plant

from control room and if there is any deviation in process it will give notification.

Figure 3-63 Control room

Page 84: Ceylon Electricity Board

81

Gas-Insulated Substation (GIS)

Compact, multi-component assembly.

Enclosed in a ground metallic housing.

Sulphur Hexafluoride (SF6) gas: the primary insulating medium.

(SF6) gas- superior dielectric properties used at moderate pressure for phase to phase and

phase to ground insulation.

Preferred for voltage ratings of 72.5 kV, 145 kV, 300 kV and 420 kV and above.

Various equipment like Circuit Breakers, Bus-Bars, Isolators, Load Break Switches,

Current Transformers, Voltage Transformers, Earthing Switches, etc. housed in metal

enclosed modules filled with SF6 gas.

In Kukuleganga and Samanalawewa they have used not GIS but switchyards.

2.5.7 Maintenance Works

As electricity is a form of energy it can be neither created nor destroyed. And also the

Alternative Current (AC) can’t be stored. Thus, there should be real time the electricity

production with demand at that time.

This balancing act is done by taking the Frequency of your Power supply (50 Hz in Sri

Lanka) as a guide. When we supply exactly the demand the frequency of supply will be

stable (usually at the rated 50Hz). If our supply is less than your demand, the frequency

will fall below 50Hz and if we supply more, the same will increase above 50Hz.

However, during certain emergencies, our power plants can get tripped (disconnected or

automatically switched off). When a large power station gets tripped in this manner, this

supply­ demand balancing act gets disturbed. As result, the frequency of the power supply

starts to drop. The Engineers who are Operating the Power System has to act quickly and

resupply the shortage. However, this takes some time. Until the supply­demand balance is

restored, the frequency starts to fall below 50Hz

It is not healthy for power plants to operate below a certain frequency. For example most

of the present Grid Connected Power Plants in our system cannot operate below 47Hz.

Thus, if the low frequency situation is allowed to persist, after a certain time, the remaining

power plants too start to get switched off thus aggravating the power shortage further. This

could escalate in to a total cascaded failure.

Page 85: Ceylon Electricity Board

82

Such island blackout caused during our training period. We got the chance to see how the

engineers manage such instance. And replacing of diaphragm of generators where done.

Before starting of units all the units where checked. Especially we also got chance to

engage which inspection of pulverizer units, coal feeders and etc.

During my training at coal handling section pulley system of a gantry crane was repaired.

And also a coal handling belt system was repaired.

Figure 3-64 Repair the pulley system of a gantry crane

Page 86: Ceylon Electricity Board

83

CHAPTER THREE

3 MANAGEMENT

To a successful engineer it is very important to have not only the technical knowledge but

also the management skills when we are dealing with the industry. In the industry we have

to work with several kinds of fields such as

Demand Side Management

Financial Management

Human Resource Management

Quality Management

Safety Management

Environment and Waste Management

Etc.

3.1 Demand Side Management (DSM)

Demand Side Management covers “systematic utility and government activities designed

to change the amount and/or timing of the customer’s use of electricity” for the collective

benefit of the society, the utility and its customers. [2]

It is a combination of

Corporate objectives

- Improving power quality and reliability

- Minimizing pilferage,

- reducing system losses,

- improving the distribution network,

- upgrading sub­stations,

- high collection efficiency ,

- improving customer service

- etc.

Page 87: Ceylon Electricity Board

84

Load Shape objectives

- Primarily DSM is considered as a cost-effective alternative to supply-side

options, it generally address one of the following specific load shape objectives

Peak Clipping: The reduction of utility load primarily during periods of

peak demand

Valley-Filling : The improvement of system load factor by building

load in off-peak periods

Load Shifting: The reduction of utility loads during periods of peak

demand, while at the same time building load in off-peak periods. Load

shifting typically does not substantially alter total electricity sales.

Conservation : The reduction of utility loads, more or less equally ,

during all or most hours of the day

Load Building : The increase of utility loads, more or less equally ,

during all or most hours of the day

Flexible Utility Load Shape : Refers to programs that set up utility

options to alter customer energy consumption on an as needed basis, as

in interruptible / curtailable agreements

No-load Shape objectives

3.2 Financial Management

Due to the authority of CEB in Sri Lankan power supply, it gets chance to earn more and

more income. But there are many key factors cause for deterioration of the liquidity of the

CEB such as, political disturbances, escalation of fuel prices and the cost of purchased

power, low generation from hydro’s due to less rains- climate effects, frequently occurring

unexpected break downs, more maintenance costs for old transmission system and etc.So

good financial management is necessary for CEB and the availability of working them

independently is important to achieve goals of company.

Page 88: Ceylon Electricity Board

85

Figure 3-1 Summary statics 2013

Page 89: Ceylon Electricity Board

86

3.3 Human Resource Management (HRM)

In order to achieve the goals, the quality of Human Resources of an organization plays a

vital role. CEB staff totaling about 15000 employees have proven that they can deliver

output under any circumstances with their efforts to provide reliable and quality electricity

to all the customers. The Training Branch, Personnel Branch, and Human Resources

Officers deployed in the Regions and Divisions have played a vital role towards the well-

being of the organization.

HRM organizes training programs of professional development to all employees

in maintaining and enhancing competence of all the engineering and the technical

staff and soft skills of employees.

The human resources goal must be to get the mind set of all the Regions and

Divisions staff that all of them are a part of a single team to deliver one CEB to the

nation, to innovate and consistently think of faster and better ways to provide their

services to the customer.

CEB provides high salary and remuneration benefit to the team well above local industry

standards. Other than that, to create an environment which motivates employees towards

achieving goals of the Board, CEB has developed several schemes for the benefit of the

employees. These included

Payment of Bonus

Payment of Incentive against Un-availed Sick and Vacation Leave

Payment of various special monetary advances.

Long Service Awards

CEB Provident Fund

Employees’ Trust Fund

CEB Pension (subject to the CEB Pension Rules)

CEB Medical Assistance Scheme

CEB Loan Scheme

Retirement Gratuity

Other fringe benefits.

Page 90: Ceylon Electricity Board

87

Welfare Unit Welfare Unit - for looking after the staff welfare of its employees.

CEB circuit bungalows

Welfare shop

Maintain Montessori schools at all Power Stations

School transport services to the children of CEB families in addition to the

weekend long distance transport facilities to employees.

Sports and recreation facilities

3.4 Quality Control Program

The quality control program clearly defines the responsibility and duties of the quality

control. Checklists that describe the activities, the applicable specifications, standards and

requirements, the initiator, the interval of the examination etc. shall be included to such

program.

Contractor submits to employer for each test/control comprehensive report including all

main details on

Control/testing date, place, and conditions, responsible

Control / testing equipment

Control / testing results

Comments

There are several quality control systems to carry out in the plant operations as following,

Coal quality testing

Demine water testing

Boiler drum water testing

Waste water testing

Lubrication oil testing

To do those testing there is one chemical lab in the LakVijaya Power Station. And

Samanalawewa Power Station does only the lubrication oil testing. That test was done

from external lab.

Page 91: Ceylon Electricity Board

88

3.5 Health and Safety Management

CEB is highly concern “Safety First” concept as the risk at there is very high as they deal

with electricity which can be caused to many damages to lives and death. So safety

equipment such as overall, helmet and boots are mainly provided to all the employees of

power stations for improvement of the safety.

Safety in a Power Station

Planning ahead to control risks

- Ensuring that systems of work are safe and that equipment is properly

maintained.

- Employees are given health and safety information, training and appropriate

supervision.

Figure 3-2 How to avoid accidents

Station evacuation

Whatever the nature of the crisis, people must be able to get out of a hydropower

station safely. So in stations there are at least two independent ways to exit.

Page 92: Ceylon Electricity Board

89

Flood protection

Hydropower stations can and do flood. Failure of drainage pumps will lead to a

slow increase in the water level and eventual flooding of the station. So there is

alarms systems to detect the water levels automatically close the gates and valves.

Fire and smoke control

To detect fires as early as possible, prevent them from spreading, alert all

personnel, and provide safe and well-lit means of evacuation as soon as possible

fire control is important.

Different fire extinguishers used in power plants based on the type of fire as follows

Table 3.1- Fire Extinguisher Types

Fuel (caused for the fire) Extinguisher

Class A Organic solids

Ex. Papers ,woods

Pressurized Water

Class B Combustible liquid/oils

Ex. Oils, Petroleum

Foams, Water

Class C Combustible Gases

Ex. LP gas,CH4

Carbonated Water

Class D Electrical based fire Dry Chemical dust

Figure 3-3 Different types of fire extinguishers in power plant

Page 93: Ceylon Electricity Board

90

Smoke control and ventilation system also very important in hydro power stations.

Boiler hazards control devices like pressure regulators, water level detectors and

etc.

Chemical hazard-

Power plants workers are routinely exposed to dangerous chemicals such as

corrosives (acids and bases), oxidizers and solvents. So there are equipment

consists of emergency showers, face washes and eyewashes.

Figure 3-4 Eye washer

3.6 Energy and Waste Management

Environmental Policy Statement:

“Ceylon Electricity Board will manage all its business activities in a manner, which cares

for the natural and manmade environment and contribute to sustainable development. By

means of openness in dealing with environmental issues, we intend to create confidence in

our activities on the part of the public, customers, authorities, employees, and owners. We

will actively pursue a policy of incorporating and integrating environmental

considerations into our activities.”- [ceb.lk]

Page 94: Ceylon Electricity Board

91

In order to integrate Environmental Considerations into its’ activities, CEB has set up an

Environment Unit which is responsible for monitor and assist in the implementation of the

Environmental Policy of CEB.

In my training period I was lucky to work in Samanalawewa Hydro Power Station which

was the first government entity to be certified with ISO 14001:2004 for its’ Environmental

Management System.

All the activities and processes in power station, dam, reservoir, tunnel intake, surge

chamber, portal valve house and CEB village (with staff quarters) are covered by the

Environmental Management System to assure the optimizing usage of resource and the

prevention of pollution. E.g.:

Environmental emergencies identification process.

- The process to prevent or mitigate associated adverse environmental impacts

by identifying and managing the potential emergencies of power station and

making instructions to handle them.

Environmental monitoring and measurement process

- Solid waste disposal system. Ex: To maintain a cleaner environment there is a

standard waste disposal system in the according to 5S method. The buckets that

collect the waste are colored as the type of waste is allowed for them.

Figure 3-5 Waste disposal coding system

- Dam monitoring system including leakage measuring, piezo-metric pressure,

water quality tests and sound and lighting level measurements.

Page 95: Ceylon Electricity Board

92

Energy conservation process

- Consumption of electricity reduces year by year with in the project with

different programs like replacing of incandescent lamps by Compact

Florescent Lamps.

In Puttalam LakVijaya Power Plant also highly concerned about the environment safe

guard as the pollution that can be occurred from a thermal coal power plant is higher than

hydro power plant. E.g.:

Minimizing of particular matter- Electro Static Precipitator unit is installed to

precipitated 98% of fly ash generated. Then the collected fly ash is sold for cement

manufacturing where disposal of collected fly ash problem solved automatically.

Figure 3-6 ESP unit

Control of Oxides of Sulfur and Nitrogen

After Electro Static Precipitator flue gas is sent to the Flue Gas Desulphurization

plant to remove the Oxides of Sulphur (SOx) and the boiler is designed with

advanced low NOx burner, in order to control the NOx emissions.

Dispersion of Flue Gas

After FGD flue gas will be dispersed into the atmosphere through a 150m tall

stack (chimney) during operation.

Page 96: Ceylon Electricity Board

93

CHAPTER FOUR

4 SUMMARY AND CONCLUSION

4.1 Summary

In my second undergraduate Industrial Training period I was placed in Samanalawewa

Hydro Complex for 6 weeks and Lakvijaya Power Station for 6 weeks. As a request of us

they divide our Samanalawewa 6 weeks into 2 sections as 3 weeks in Kukuleganga and 3

weeks in Samanalawewa. Due to that we got a rare chance of Annual maintain ace, First

aid camp and etc. And we could clearly understand the difference of modern and past

technologies of power plants designing and controlling where Samanalawewa is very old

compare to Kukuleganga project. And technology differences of Japanese and Chinese

(LakVijaya).

Finally we could get wide knowledge and experience in both hydro and thermal power

generation and management and HRM techniques used at those power stations.

And also during my training I have to travel to different parts of country through many

areas where I could get lot of experiences of multi-cultural societies.

Page 97: Ceylon Electricity Board

94

4.2 Conclusion

Industrial training period is the most valuable time period for an Engineering

undergraduate to deal with the field works. I was fortune enough to have my training

session of three months in a places like Kukuleganga, Samanalawewa and LakVijaya

power station. LakVijaya plant is the only coal power station in Sri Lanka. These 12 weeks

of Industrial Training has been very important and very helpful to developer engineering

skills and it broadens our knowledge about engineering world. It provides us to elevate our

engineering career in both theoretical and practical aspects of engineering.

While I was in power station there were so many things to learn. The DGMs, Chief

Engineers & Engineers of Operation, Maintenance sections gave me maximum

opportunities to have a good training section.

The Engineers and all the technical staff have given an excellent guidance and they were

always willing to share their practical knowledge with us. They always invited us to join

with them when they were doing some technical work so that we can take working

experience. The organization culture or the working environment was very pleasant and

encouraging to work. They maintained a necessary and sufficient formal relationship and

a good informal relationship with the trainees.

Since that was a government organization we could get little of hand on experiences. But

due to Annual maintenance of Kukuleganga Power Station we could get huge experience

than any of trainee of any other organization. If EEC (Engineering Education Center)

university of Ruhuna can discuss all necessary arrangement of trainees and training

schedules with organizations about maintenance periods, it will be good for

undergraduates so that students may try to get the maximum while training. As a whole, I

must say that CEB provides a useful training for engineering undergraduates to make them

knowledgeable and energetic engineers to country.

Page 98: Ceylon Electricity Board

95

5 References

[1] "How Hydropower Works," 24 April 2016. [Online]. Available:

http://energy.gov/eere/water/how-hydropower-works.

[2] "http://www.ceb.lk/," [Online]. [Accessed 2016 April 2016].

[3] CEB, Maintainance and Operational Manuals- Kukuleganga, Samanalawewa and

LakVijaya Power Statios.

[4] "Kukuleganga- wikipedia," [Online]. Available:

https://en.wikipedia.org/wiki/Kukule_Ganga_Dam#Power_station. [Accessed 15

April 2016].

[5] "Wikipedia, the free encyclopedia," [Online]. Available:

https://en.wikipedia.org/wiki/Samanala_Dam. [Accessed 16 April 2016].

[6] CEB, "Annual Report," CEB, 2013.


Recommended