+ All Categories
Home > Documents > CH4101_2 Process Hazards Identification

CH4101_2 Process Hazards Identification

Date post: 27-Dec-2015
Category:
Upload: kefeinzel
View: 33 times
Download: 0 times
Share this document with a friend
Description:
Process Hazards Identification
Popular Tags:
45
2. PROCESS HAZARD IDENTIFICATION CH4101 Chemical, Biological & Plant Safety Dr. Foo Swee Cheng
Transcript
Page 1: CH4101_2 Process Hazards Identification

2. PROCESS HAZARD IDENTIFICATION

CH4101 Chemical, Biological & Plant Safety Dr. Foo Swee Cheng

Page 2: CH4101_2 Process Hazards Identification

PROCESS HAZARD ANALYSIS (PHA) Safety in Project Lifecycle

• Business risk(concept/ research/ development): Preliminary Hazard Analysis (PrHA)

Identify the hazards and their likely amount in accidents: Siting & layout

Select high consequences processes for further analysis by HAZOP

• Design improvement(Process/Piping & Instrumentation Diagram; P&ID): HAZOP

Identify problems that prevent efficient OPERATION

Identify the consequences of process deviations for recommending safeguards

Prevent the causes of deviations/ mitigate the consequences of deviations

Select high consequence scenarios for further analysis by LOPA/ FTA/ ETA/ BowTie

• Further design improvement needed? Quantify the risk by QRA

Quantify the risk for improving detailed design: LOPA/ FTA/ ETA/ BowTie

• Project: Final design Construction Commission Operation Decommission

CH4101 FooSC

Page 3: CH4101_2 Process Hazards Identification

Before PI&D

PRELIMINARY HAZARD ANALYSIS Risk Anticipation: Consequence Modelling

Qualitative/ semi-qualitative Risk Consequence Worst Case/ Credible Worst Case

BASIS: Land Use Planning Site selection/ Plant layout

CH4101 FooSC

Page 4: CH4101_2 Process Hazards Identification

PRELIMINARY HAZARD ANALYSIS • Obtain data for PrHA/ plant siting & facilities layout decisions

SDS: Safety Data Sheets

Further testing to provide data not in SDS

• Hazardousness rating: GHS categories

• Consequence rating: Total amount present in an individual unit

• consequence modeling: Define the HAZARD ZONE

Thermal radiation: Pool/ jet fires & BLEVE model

Vapor cloud fires (Flash fires); VCF: Dispersion and fire model

Vapor cloud explosions; VCE: Dispersion and explosion model

Toxic: Dispersion & toxicity model CH4101 FooSC

Page 5: CH4101_2 Process Hazards Identification

JET FIRE ISOPLETHS

CH4101 FooSC

Page 6: CH4101_2 Process Hazards Identification

PLUME DISPERSION ISOPLETHS

CH4101 FooSC

Page 7: CH4101_2 Process Hazards Identification

VAPOR JET DISPERSION ISOPLETHS

CH4101 FooSC

Page 8: CH4101_2 Process Hazards Identification

EXPLOSION ISOPLETHS

CH4101 FooSC

Page 9: CH4101_2 Process Hazards Identification

HAZARD LEVELS

Hazard Level Definition

Low One lost time injury Multiple recordable injuries Emergency response call-out without injury

Medium

Permanent disabilities within localized section of process or building Lost time injuries or hospitalizations outside of local area

High One or more fatalities Injuries or fatalities within community

CH4101 FooSC

Page 10: CH4101_2 Process Hazards Identification

HAZARD ANALYSIS: Acceptance criteria

Risk Acceptance Criteria

Extent of Exposure

Hazard Level

Layers of independent Protection Required

Minor on-site (Use location)

Low (L) Normal Controls

Major On-Site Medium (M)

One layer of independent non-procedural safeguards above normal controls

Major Off-Site High (H)

Two layer of independent non-procedural safeguards above normal controls

CH4101 FooSC

Page 11: CH4101_2 Process Hazards Identification

HAZARD ANALYSIS: Acceptance criteria

M

H

L

M H L

Normal Control

One Independent Non-procedural Control

Two Independent Non-procedural Control

Haz

ard

Leve

l

Extent of Exposure CH4101 FooSC

Page 12: CH4101_2 Process Hazards Identification

After P&ID

Process Hazard Analysis Risk Quantification: Impact Modelling

BASIS: Process Optimization/ Improvement Engineering/ Maintenance/ Emergency Systems

CH4101 FooSC

Page 13: CH4101_2 Process Hazards Identification

High Tank level BPCS: LE1 LCH LCV1 Low Tank level BPCS: LE2 LCL LCV2 High/ Low Tank Pressure BPCS: Vent Overflow Protection: Prevention: LE1LIH MV Mitigation: Vent Dike

IDENTIFY CONTROL LOOPS: GASOLINE TANK • 5 control loops: 3 active & 2 passive

T101

Vent

LE1

LE2

LCV1

Tank Truck

LCH

MV

LIH

NRV1

LCL

To Process LCV2 NRV2

Control Loop:

Detection (LE1) ↓

Decision (LCH) ↓

Action (LCV1)

LCV1: Command failure

LCV1: Primary failure

CH4101 FooSC

Page 14: CH4101_2 Process Hazards Identification

CONTROL SYSTEM FAILURE LOGIC • Example: LCV1 LCH LE1 • Final ACTION element: LCV1 LCV1 fails system fails

• Failure modes of LCV1 LCV1 Primary failure: LCV1 failed LCV1 has failed and cannot perform function

LCV1 command failure: LCH or LE1 has failed, LCV1 works LCV1 fails to perform function as LCH failed to command LCV1 to perform function LE1 failed to command LCV1 to perform function

CH4101 FooSC

LVC1 Fails OPEN

LCV1 LCH LE1

Primary failure

Command failure

ENV

Corrosion: High

Humidity

Page 15: CH4101_2 Process Hazards Identification

GASOLINE STORAGE TANK: BEFORE HAZOP

T101

Vent

LE1

LE2 LCL

To Process LCV2 NRV2 LCV1

Tank Truck

LCH

MV

LIH

NRV1

CH4101 FooSC

Page 16: CH4101_2 Process Hazards Identification

HAZARD IDENTIFICATION: HAZOP REFERENCES

• HAZOP: Guide to best practice, 2nd ed., IChemE, 2008 • Macdonald D, Practical HAZOPs, trips & alarms, Elsevier, 2004 • A Guide to Hazard and Operability Studies, Chemical Industry

safety & health council of the Chemical Industries Association limited, 1979

• CCPS, Guidelines for hazard evaluation procedures, AIChE, 2008

• Ian Day, Hazop [videorecording] : a team in action CoreMedia Training Solutions, 1991

CH4101 FooSC

Page 17: CH4101_2 Process Hazards Identification

HAZOP METHODOLOGY • Select a study SECTION or NODE from P&ID • Identify OPERATIONAL PARAMETER relevant eg. Flow; pressure; temperature; concentration

• Select meaningful GUIDEWORDS for the parameter eg. High; low; no; less; more; other than

• Combine PARAMETER & GUIDEWORD to form a meaningful DEVIATIONS eg. High pressure; low temperature; high flow

• Identify possible CAUSES of the deviation • Identify the CONSEQUENCES of the deviation • Evaluate & recommend CONTROL MEASURES for the causes &

consequences

CH4101 FooSC

Page 18: CH4101_2 Process Hazards Identification

PROCESS PARAMETERS

CH4101 FooSC

Page 19: CH4101_2 Process Hazards Identification

HAZOP GUIDEWORDS

CH4101 FooSC

Page 20: CH4101_2 Process Hazards Identification

HAZOP DEVIATION

CH4101 FooSC

Page 21: CH4101_2 Process Hazards Identification

HAZOP FLOW CHART

Note Page CH4101 FooSC

Page 22: CH4101_2 Process Hazards Identification

21

Page 23: CH4101_2 Process Hazards Identification

HAZOP TEAM MEMBERSHIP • Based on technical specialties Process Engineering Operations Maintenance/ Reliability Instrumentation

• Based on individual’s experience/ knowledge in these areas Inspection/ Materials Electrical Safety/ Loss Prevention Environmental Packaged Equipment by vendors

CH4101 FooSC

Page 24: CH4101_2 Process Hazards Identification

HAZOP Process Section: Petrol storage tank filling line

Design Intention: Tank T101 to store 6000 m3 of petrol Operation Phase: Tank Filling Petrol: MV, LCV1 OPEN, Pump ON

Guide Word: High Process Parameter: Level

Deviation: HIGH LEVEL Causes: (1) Petrol supply CONTINUE

(2) LCV1fails OPEN: LCV1-->LCH-->LE1

Consequences: (1) Tank overfill HIGH PRESURE RUPTURE (2) Tank T101 OVERFLOW (3) Petrol DISPERSE on ground (4) Vapor cloud FORMATION/ DISPERSION (5) FLASH FIRE/ VC EXPLOSION (6) Pool/tank fire

Safeguards: (1) MV CLOSED: MV-->HULIH-->LE1 (2) VENT: m1

(3) DIKE (Bund): m3 (4) Foam: m4 (5) Sprinke: m6

Actions: (1) High level ALARM: p2; MV-->HULAH-->LE1 (2) Overflow ALARM: m2; MV-->FA (3) FOAM: m4; FOAM-->FA (4) Improve LCV1 reliability: p3

• Develop HAZOP

• Select parameter: LEVEL

• Apply guideword: HIGH

• Deviation: HIGH LEVEL

• Identify

CAUSES

Consequences

(Exiting) Safeguards

• Recommend: Actions (additional safeguards)

CH4101 FooSC

Page 25: CH4101_2 Process Hazards Identification

UPDATED GASOLINE STORAGE TANK: AFTER HAZOP

T101

Vent

LE1

LE2 LCL

To Process LCV2 NRV2 LCV1

Tank Truck

LCH

MV

LIH

NRV1

LAH

CH4101 FooSC

Page 26: CH4101_2 Process Hazards Identification

RELIABILITY SYSTEMS • Reliability system representation A combination of series and parallel network

• Series network: System reliability < unit reliability Any one unit fails system fails ALL units work system works

• Parallel network: System reliability > unit reliability Redundancy system Any one unit works system works ALL units fail system fails

A B C

X

Z

Y

CH4101 FooSC

A B C

OR gate

X Y Z

AND gate

Page 27: CH4101_2 Process Hazards Identification

FAULT TREE OPERATORS • Series: OR gate

The output: at least one of the inputs exists

• Parallel: AND gate

The output: if all the inputs exist

• IF gate or inhibition gate

Output is generated if

Input exists

Condition C verified Limnios N, Fault Trees, ISTE, 2007

C

CH4101 FooSC

Page 28: CH4101_2 Process Hazards Identification

DRAW FAULT TREE FROM HAZOP

Process Section: Petrol storage tank filling line Design Intention: Tank T101 to store 6000 m3 of petrol Operation Phase: Tank Filling Petrol: MV, LCV1 OPEN, Pump ON

Guide Word: High Process Parameter: Level

Deviation: HIGH LEVEL Causes: (1) Petrol supply CONTINUE

(2) LCV1 fails OPEN: LCV1-->LCH-->LE1

Consequences: (1) Tank overfill HIGH PRESURE RUPTURE (2) Tank T101 OVERFLOW (3) Petrol DISPERSE on ground (4) Vapor cloud FORMATION/ DISPERSION (5) FLASH FIRE/ VC EXPLOSION (6) Pool/tank fire

Safeguards: (1) MV closed: MV-->HULIH-->LE1 (2) VENT: m1

(3) DIKE (Bund): m3 (4) Foam: m4 (5) Sprinkler: m6

Actions: (1) High level ALARM: p2; MV-->HULAH-->LE1 (2) Overflow ALARM: m2; MV-->FA (3) FOAM: m4; FOAM-->FA (4) Improve LCV1 reliability: p3

• Obtain HAZOP record

• Select TOP EVENT: T101 Overflow

• Identify BPCS: LCV1LCHLE1

• Identify Protection: MVHULILE1

• Identify Mitigation: None

• Draw Fault Tree

CH4101 FooSC

Page 29: CH4101_2 Process Hazards Identification

T101 OVERFILL: FAULT TREE BEFORE IMPROVEMENT

Minimal Cut Sets: T = [LCV1+LCH+LE1][MV+HU+LI+LE1] = LE1 + (LCV1 + LCH)(MV + HU + LI) = LE1 + (LCV1)(MV) + (LCH)(MV) + (LCV1)(HU) + (LCH)(HU) + (LCV1)(LIH) + (LCH)(LIH) = LE1 + (LCH + LCV1)(MV) + (LCH + LCV1)(HU) + (LCH + LCV1)(LIH)

Primary failures

T101 OVERFLOW

T101 LEVEL HIGH

LVC1 Fails OPEN

LCV1 LCH LE1

MV LIH LE1

MV CLOSED

HU

Command failures

CH4101 FooSC

Page 30: CH4101_2 Process Hazards Identification

T101 OVERFILL: EVENT TREE BEFORE IMPROVEMENT Starting: Tank Level High

CH4101 FooSC

No Overflow

Overflow

LE1 LCH LCV1 LIH HU MV

Y

Y

Y

Y Y

Y

Y Y

Y

N

N N

N N

N N

N N

No Overflow

No Overflow

Overflow

Overflow Overflow

Overflow

Overflow Overflow

High Tank Level

Page 31: CH4101_2 Process Hazards Identification

DEVELOP FAULT TREE BY LOGICAL DEDUCTION PROCESS • Top Event: T101 OVERFLOW • Determine the sequence: T101 filling fails to STOP at pre-set level • FILLING: Petrol to T101 ON MV & LCV1 OPEN T101 Level RISING

T101 OVERFLOW (T101 level RISING) MV fails OPEN LCV1 fails OPEN T101 LEVEL reaches pre-set level

• Logic Diagram:

CH4101 FooSC

T101 OVERFLOW

T101 level HIGH

HU MV LE1 LIH

MV Fails OPEN

T101 Filling

LVC1 Fails OPEN

LCV1 LCH LE1

Petrol to T101 ON

MV & LCV1 OPENS

LCV1 fails OPEN

MV fails OPEN

T101 OVERFLOW

&

FILLING TANK T101

BPCS

Protection System

Top Event

Page 32: CH4101_2 Process Hazards Identification

CONSEQUENCE OUTCOMES • Depends on plant engineering design/ plant layout/ fire protection

systems/ incident management system; Example: • Consequence Mitigation Hazardousness control measures: e.g. dike/bund; overflow

detection; spill removal/ vapor suppression system Ignition control: Electrical hazardous area zoning & equipment

classification Emergency preparedness & Response

• Prevent Escalation (to adjacent facilities) Thermal isolation: Distancing/ fire proofing/ sprinklers/ water

curtains Material Transfer

CH4101 FooSC

Page 33: CH4101_2 Process Hazards Identification

Tank 912 overfilled

Stage 1: Vapor cloud close to source or within dike/ bund of source

Water curtains

Northgate Building

STAGES OF CONSEQUENCE DEVELOPMENT

CH4101 FooSC

Page 34: CH4101_2 Process Hazards Identification

Tank 912 overfilled

Stage 1: Vapor cloud within dike/ bund of source Stage 2: Vapor cloud covers large part of site (e.g. Phillips 66 explosion/fire: Oct 23, 1989 Pasadena, Texas, USA.)

Water curtains

STAGES OF CONSEQUENCE DEVELOPMENT

CH4101 FooSC

Page 35: CH4101_2 Process Hazards Identification

Tank 912 overfilled

Stage 1: Vapor cloud within dike/ bund of source Stage 2: Vapor cloud covers large part of site Stage 3: Vapor cloud travels offsite site (e.g. Buncefield fuel depot fire, Dec 11, 2005)

Water curtains

STAGES OF CONSEQUENCE DEVELOPMENT

CH4101 FooSC

Page 36: CH4101_2 Process Hazards Identification

Northgate Building fire

FIRE AFTER IGNITION

CH4101 FooSC

Page 37: CH4101_2 Process Hazards Identification

Tank 912 overfilled

Northgate Building

AFTER FIRE

CH4101 FooSC

Page 38: CH4101_2 Process Hazards Identification

Northgate Building

Fuji Building

VCE DAMAGE

CH4101 FooSC

Page 39: CH4101_2 Process Hazards Identification

TANK OVERFILL MITIGATION: EVENT TREE BEFORE HAZOP Starting: Tank Overflow

• Immediate: Flammable vapor with dike/bund • Early: Flammable vapor within site • Delay: Flammable vapor extended off-site • Tank filling stopped after detection/ ignition

Y N

T101 OVERFLOW

Early detection

Immediate Ignition

Early Ignition

Y

N Y

N Y

N

Delay detection

Delay Ignition

Y

N

Stop filling/ start firefighting

Stop filling, suppress ignition, transfer extra fuel in tank

Stop filling/ start fire firefighting

Stop filling/ start firefighting

Y

N

Small Pool/Tank Fire

Small spill control

Large onsite fire/explosion

Large spill control

On-/Off-site fire/explosion

Impossible/ insignificant event

Large On-/Off-site fire/explosion

Stop filling/ start firefighting

CH4101 FooSC

Page 40: CH4101_2 Process Hazards Identification

BOWTIE: CAUSE-CONSEQUENCE DIAGRAM Combining Fault & Event Trees (Before HAZOP)

Y N

T101 OVERFLOW

Early detection

Immediate Ignition

Early Ignition

Y

N Y

N Y

N

Delay detection

Delay Ignition

Y

N

Stop filling/ start firefighting

Stop filling, suppress ignition, transfer extra ful in tank

Stop filling/ start fire firefighting

Stop filling/ start firefighting

Y

N

Small Pool/Tank Fire

Small spill control

Large onsite fire/explosion

Large spill control

On-/Off-site fire/explosion

Impossible/ insignificant event

Large On-/Off-site fire/explosion

Stop filling/ start firefighting T101 LEVEL HIGH

LVC1 Fails OPEN

LCV1 LCH LE1

MV LE1 LIH HU

MV CLOSED

CH4101 FooSC

Page 41: CH4101_2 Process Hazards Identification

GASOLINE STORAGE TANK After Adding recommendations in HAZOP

T101

Vent

LE1

LE2 LCL

To Process LCV2 NRV2 LCV1

Tank Truck

LCH

MV

LIH

NRV1

LAH LE3

CH4101 FooSC

Page 42: CH4101_2 Process Hazards Identification

TANK OVERFILL: BOWTIE (After HAZOP)

Y

N

Stop filling, transfer extra fuel in tank Transfer spilled fuel in dike

Y N

T101

O

VERF

LOW

Early detection

Immediate Ignition

Early Ignition

Y

N Y

N Y

N

Delay detection

Delay Ignition

Y

N

Stop filling/ start firefighting

Stop filling, suppress ignition, transfer extra fuel in tank

Stop filling/ start fire firefighting

Stop filling/ start firefighting

Y

N

Small Pool/One Tank Fire

Small spill control

Large onsite fire/explosion

Large spill control

On-/Off-site fire/explosion

Impossible/ insignificant event

Large On-/Off-site fire/explosion

Stop filling/ start firefighting

Immediate detection

CH4101 FooSC

Page 43: CH4101_2 Process Hazards Identification

LEARNING OBJECYIVES

• After the lecture, students should able to

1) Conduct HAZOP studies

2) Construct fault trees, event trees & BowTie diagrams

3) Recommend additional safeguards

4) Decide the adequacy of safeguards

CH4101 FooSC

Page 44: CH4101_2 Process Hazards Identification

REFERENCES HAZOP, Fault Tree & System Reliability

• Kletz T. Hazop & Hazan: Identifying & assessing process industry hazards. IChemE, 1999

• Limnios N, Fault Trees, ISTE, 2007 [online]

• Hoyland A, System reliability theory: models & statistical methods, John Wiley, 1994 [online]

• Modarres M, What every engineer should know about reliability & risk analysis, Marcel dekker, 1993

• Nolan DP. Safety & security review for the process industries: application of HAZOP, PHA, what-if & SVA reviews. Elsevier Science, 2011 [online]

• Day I, Hazop [videorecording]: a team in actionCoreMedia, 1991 CH4101 FooSC

Page 45: CH4101_2 Process Hazards Identification

END

CH4101 FooSC


Recommended