September 6, 2012 Chadron State College Armstrong Gymnasium Campus Event Center Renovation and Addition Nebraska State College Board of Trustees Schema7c / Design Development Presenta7on
Transcript

September 6, 2012

Chadron State College Armstrong Gymnasium Campus Event Center Renovation and Addition

Nebraska  State  College  Board  of  Trustees    Schema7c  /  Design  Development  Presenta7on  

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

Introduction

Location and Site

Design Overview

Project Budget

Questions

AGENDA

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

INTRODUCTION | Project Overview •  Proposed  renova,on/expansion  of  Armstrong  Building  was  noted  

as  a  priority  need  in  the  2001  and  2012  Campus  Master  Plans      

•  Exis,ng  Armstrong  PE  Building:      •  Constructed  in  1964  for  $800,000  •  Approximately  37,000  GSF  •  1,400  arena  seaBng  capacity  

•  Armstrong    PE  Building  is  the  current  home  of:    •  CSC  AthleBc  Department  Offices  •  CSC’s  men’s  and  women’s  basketball,  football  and  volleyball  

programs,  and  sports  strength  room.      

•  Construc,on  assumes  3  Phases  

•  The  new  athle,cs  facility  will  include:    •  11,500  GSF  in  the  natatorium  addi7on  at  the  Nelson  Physical  

Ac7vity  Center.  •  98,300  GSF  in  the  expanded  Armstrong  Building  •  2,100  arena  sea7ng  capacity    

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

Introduction Location and Site Design Overview

Project Budget Questions

LOCATION AND SITE

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

Introduction Location and Site Design Overview

Project Budget Questions

LOCATION AND SITE

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

Introduction Location and Site Design Overview

Project Budget Questions

LOCATION AND SITE

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Design Objectives

•  Contextual.    Provide  a  soluBon  which  is  contextually  responsive  to  the  Chadron  State  Campus,  while  enhancing  the  overall  image  of  the  Armstrong  Gym.  

•  Func,onal.  Provide  a  funcBonally  efficient  layout  for  mulBple  departments  and  flow  of  operaBons.    

•  RespecHul.  Provide  a  soluBon  which  aestheBcally  Bes  the  addiBon  to  the  exisBng  building  through  the  use  of  similar  exterior  finishes  and  some  shared  architectural  language.  

•  Community.  Provide  a  grand  public  entrance  for  the  for  the  facility  and  the  new  event  center.  

•  Compe,,ve.  Provide  a  facility  that  meets  or  exceeds  Chadron  State  College’s  peer  insBtuBons,  thereby  aiding  in  Student-­‐Athlete  retenBon  and  recruiBng.  

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | First Floor Plan

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Second Floor Plan

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Rendering

Aerial View of the New Addition

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Concept Rendering

View of the Proposed Event Center Main Southwest Entrance and Public Plaza

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Concept Rendering

View of the Proposed North Entrance from the Student Center

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Concept Rendering

View of Elliot Field from Inside the Proposed Hall of Fame Room

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Project Phasing •  The  project  assumes  construc,on  in  three  phases.  

 PHASE  1  •  Phase  1.A:  Renovate  exisBng  natatorium  into  a  

new  strength  and  condiBoning  center.  •  Phase  1.B:  Event  Center  with  a  seaBng  capacity  of  

2,100,  locker  rooms,  lobby  and  entrance  spaces,  circulaBon  and  fan  amenity  spaces.  

 PHASE  2  •  Phase  2.A:  Coaches  offices,  meeBng  rooms,  

football  locker  room  and  equipment  room.  •  Phase  2.B:  Renovate  exisBng  locker  rooms,  sports  

medicine  and  support  spaces.  

 PHASE  3  •  New  natatorium    with  a  25  meter  five  lane  pool,  

lockers  rooms,  office  and  mechanical  spaces.  

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Project Phasing – First Floor

View of Elliot Field from Inside the Hall of Fame Room

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Project Phasing – Second Floor

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

DESIGN OVERVIEW | Project Phasing – Natatorium

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

PROJECT BUDGET | Funding Sources

State  Funds      $  6,700,000  

Federal  Funds                No  Federal  Funds  

LB  309  Funds        See  Below    Revenue  Bonds          No  Revenue  Bonds    Private  Dona,ons      $  2,000,000    Cash  and  Other  Sources    $  4,300,000  

 Total                                  $  13,000,000  

No  LB309  funds  have  been  idenBfied  for  this  project.  However,  some  porBons  of  the  renovaBon  may  be  eligible  for  future  LB309  funding.  

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

BUDGET AND FISCAL IMPACT

Es,mate  of  Probable  Construc,on  Cost          June  2012      Site  Construc,on        $1,055,000    Phase  1.A  (Strength  Center  +  MEP)        1,236,045    

Phase  1.B  (New  Event  Center)                                        7,365,580    Phase  2.A  (Football  Locker  &  Offices)        2,826,700    Phase  2.B  (Sports  Med,  Locker  Rm,  Conc.,  Rest  Rms)            516,000    Total                                          $  12,999,325  

Phase  3.A  (Natorium  Addi7on  to  Nelson)        2,650,000      The  GMP  will  not  exceed  the  maximum  available  funds  for  the  project.  

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

PROPOSED PROJECT SCHEDULE

   Phase  1.A    October  2012  Bidding  Phase  

   November  2012  NTP                

Phase  1.B    December  2012  Bidding  Phase      December  2012  NTP        

   Phase  2.A    April  2013  Bidding  Phase  

   May  2013  NTP    Phase  2.B    Sept  2013  Bidding  Phase  

   November  2013  NTP      

     

.  

CSC Armstrong Gym Campus Event Center Renovation and Addition

NSCS Board of Trustees SD / DD Presentation

PROPOSED PROJECT SCHEDULE

 Phase  1.A    October  2012  Bidding  Phase  

   November  2012  NTP                

Phase  1.B    December  2012  Bidding  Phase      December  2012  NTP  

 Phase  1    October  2013  Substan7al  Comple7on    Phase  2.A    April  2013  Bidding  Phase  

   May  2013  NTP    Phase  2.B    Sept  2013  Bidding  Phase  

   November  2013  NTP    Phase  2    August  2014  Substan7al  Comple7on    

           

.  