September 6, 2012
Chadron State College Armstrong Gymnasium Campus Event Center Renovation and Addition
Nebraska State College Board of Trustees Schema7c / Design Development Presenta7on
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
Introduction
Location and Site
Design Overview
Project Budget
Questions
AGENDA
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
INTRODUCTION | Project Overview • Proposed renova,on/expansion of Armstrong Building was noted
as a priority need in the 2001 and 2012 Campus Master Plans
• Exis,ng Armstrong PE Building: • Constructed in 1964 for $800,000 • Approximately 37,000 GSF • 1,400 arena seaBng capacity
• Armstrong PE Building is the current home of: • CSC AthleBc Department Offices • CSC’s men’s and women’s basketball, football and volleyball
programs, and sports strength room.
• Construc,on assumes 3 Phases
• The new athle,cs facility will include: • 11,500 GSF in the natatorium addi7on at the Nelson Physical
Ac7vity Center. • 98,300 GSF in the expanded Armstrong Building • 2,100 arena sea7ng capacity
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
Introduction Location and Site Design Overview
Project Budget Questions
LOCATION AND SITE
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
Introduction Location and Site Design Overview
Project Budget Questions
LOCATION AND SITE
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
Introduction Location and Site Design Overview
Project Budget Questions
LOCATION AND SITE
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Design Objectives
• Contextual. Provide a soluBon which is contextually responsive to the Chadron State Campus, while enhancing the overall image of the Armstrong Gym.
• Func,onal. Provide a funcBonally efficient layout for mulBple departments and flow of operaBons.
• RespecHul. Provide a soluBon which aestheBcally Bes the addiBon to the exisBng building through the use of similar exterior finishes and some shared architectural language.
• Community. Provide a grand public entrance for the for the facility and the new event center.
• Compe,,ve. Provide a facility that meets or exceeds Chadron State College’s peer insBtuBons, thereby aiding in Student-‐Athlete retenBon and recruiBng.
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | First Floor Plan
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Second Floor Plan
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Rendering
Aerial View of the New Addition
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Concept Rendering
View of the Proposed Event Center Main Southwest Entrance and Public Plaza
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Concept Rendering
View of the Proposed North Entrance from the Student Center
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Concept Rendering
View of Elliot Field from Inside the Proposed Hall of Fame Room
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Project Phasing • The project assumes construc,on in three phases.
PHASE 1 • Phase 1.A: Renovate exisBng natatorium into a
new strength and condiBoning center. • Phase 1.B: Event Center with a seaBng capacity of
2,100, locker rooms, lobby and entrance spaces, circulaBon and fan amenity spaces.
PHASE 2 • Phase 2.A: Coaches offices, meeBng rooms,
football locker room and equipment room. • Phase 2.B: Renovate exisBng locker rooms, sports
medicine and support spaces.
PHASE 3 • New natatorium with a 25 meter five lane pool,
lockers rooms, office and mechanical spaces.
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Project Phasing – First Floor
View of Elliot Field from Inside the Hall of Fame Room
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Project Phasing – Second Floor
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
DESIGN OVERVIEW | Project Phasing – Natatorium
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
PROJECT BUDGET | Funding Sources
State Funds $ 6,700,000
Federal Funds No Federal Funds
LB 309 Funds See Below Revenue Bonds No Revenue Bonds Private Dona,ons $ 2,000,000 Cash and Other Sources $ 4,300,000
Total $ 13,000,000
No LB309 funds have been idenBfied for this project. However, some porBons of the renovaBon may be eligible for future LB309 funding.
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
BUDGET AND FISCAL IMPACT
Es,mate of Probable Construc,on Cost June 2012 Site Construc,on $1,055,000 Phase 1.A (Strength Center + MEP) 1,236,045
Phase 1.B (New Event Center) 7,365,580 Phase 2.A (Football Locker & Offices) 2,826,700 Phase 2.B (Sports Med, Locker Rm, Conc., Rest Rms) 516,000 Total $ 12,999,325
Phase 3.A (Natorium Addi7on to Nelson) 2,650,000 The GMP will not exceed the maximum available funds for the project.
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
PROPOSED PROJECT SCHEDULE
Phase 1.A October 2012 Bidding Phase
November 2012 NTP
Phase 1.B December 2012 Bidding Phase December 2012 NTP
Phase 2.A April 2013 Bidding Phase
May 2013 NTP Phase 2.B Sept 2013 Bidding Phase
November 2013 NTP
.
CSC Armstrong Gym Campus Event Center Renovation and Addition
NSCS Board of Trustees SD / DD Presentation
PROPOSED PROJECT SCHEDULE
Phase 1.A October 2012 Bidding Phase
November 2012 NTP
Phase 1.B December 2012 Bidding Phase December 2012 NTP
Phase 1 October 2013 Substan7al Comple7on Phase 2.A April 2013 Bidding Phase
May 2013 NTP Phase 2.B Sept 2013 Bidding Phase
November 2013 NTP Phase 2 August 2014 Substan7al Comple7on
.