+ All Categories
Home > Documents > Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n...

Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n...

Date post: 31-Mar-2015
Category:
Upload: haden-raleigh
View: 223 times
Download: 1 times
Share this document with a friend
Popular Tags:
50
Chapter 13 Project Management
Transcript
Page 1: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Chapter 13

Project Management

Page 2: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Characteristics of a “project”:

A project is unique (not routine), A project is composed of interrelated

sub-projects/activities, It is associated woth a large

investment.

Page 3: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

What is Project Management

To schedule and control the progress and cost of a project.

Page 4: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

PERT/CPM: Input:

– Activities in a project;– Precedence relationships among tasks;– Expected performance times of tasks.

Output:– The earliest finish time of the project;– The critical path of the project;– The required starting time and finish time of each

task;– Probabilities of finishing project on a certain date;– ...

Page 5: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

PERT/CPM is supposed to answer questions such as: How long does the project take? What are the bottle-neck tasks of the

project? What is the time for a task ready to

start? What is the probability that the project is

finished by some date? How additional resources are allocated

among the tasks?

Page 6: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

PERT Network: • It is a directed network.• Each activity is represented by a node.• An arc from task X to task Y if task Y

follows task X.• A ‘start’ node and a ‘finish’ node are

added to show project start and project finish.

• Every node must have at least one out-going arc except the ‘finish’ node.

Page 7: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example of Foundry Inc., p.523

Activity Immediate Predecessors

A -

B -

C A

D B

E C

F C

G D, E

H F, G

Page 8: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

PERT Network for Foundry Inc. Example

Page 9: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example of a Hospital Project:

Activity Immediate Predecessor(s)

A —

B —

C A

D B

E B

F A

G C

H D

I A

J E, G, H

K F, I, G

Page 10: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

PERT Network for Hospital Project

Page 11: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Performance Time t of an Activity

t is calculated as follows:

where a=optimistic time,b=pessimistic time,m=most likely time.

Note: t is also called the expected performance time of an activity.

ta m b

4

6

Page 12: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Variance of Activity Time t

• If a, m, and b are given for the optimistic, most likely, and pessimistic estimations of activity k, variance k

2 is calculated by the formula

22

6

ab

k

Page 13: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Variance, a Measure of Variation

Variance is a measure of variation of possible values around the expected value.

The larger the variance, the more spread-out the random values.

The square root of variance is called standard deviation.

Page 14: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example, Foundry Inc., p.525

Activity a m b t variance

A 1 2 3

B 2 3 4

C 1 2 3

D 2 4 6

E 1 4 7

F 1 2 9

G 3 4 11

H 1 2 3

Page 15: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Critical Path

• It is the “longest” path in the PERT network from the start to the end.

• It determines the duration of the project.

• It is the bottle-neck of the project.

Page 16: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Time and Timings of an Activity:

• t=estimated performance time;• ES=Earliest starting time;• LS=Latest starting time;• EF=Earliest finish time;• LF=Latest finish time;• s=Slack time of a task.

Page 17: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Uses of Time and Timings

Earliest times (ES and EF) and latest times (LS and LF) show the timings of an activity’s “in/out” of project.

ES and LS of an activity tell the time when the preparations for that activity must be done.

For calculating the critical path.

Page 18: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Computing Earliest Times

Step 1. Mark “start” node: ES=EF=0.

Step 2. Repeatedly do this until finishing all nodes:For a node whose immediate predecessors are all

marked, mark it as below:• ES = Latest EF of its immediate predecessors,• EF = ES + t

• Note: EF=ES at the Finish node.

Page 19: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Computing Latest Times:

Step 1. Mark “Finish” node: LF = LS = EF of “Finish” node.

Step 2. Repeatedly do this until finishing all nodes:For a node whose immediate children’s are all

marked with LF and LS, mark it as below:• LF = Earliest LS of its immediate children,• LS = LF – t

• Note: LS=LF at Start node.

Page 20: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Computing Slack Times

• For each activity:– slack = LS – ES = LF – EF

Page 21: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Foundry Inc. Example

• Calculate ES, EF, LS, LF, and slack for each activity of the Foundry Inc. example on its PERT network, given the data about the project as in the next slide.

Page 22: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example, Foundry Inc.

Activity a m b t variance

A 1 2 3 2 0.111B 2 3 4 3 0.111C 1 2 3 2 0.111D 2 4 6 4 0.444E 1 4 7 4 1F 1 2 9 3 1.777G 3 4 11 5 1.777H 1 2 3 2 0.111

Page 23: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

H 2

ES=

LS=

EF=

LF=

A 2

ES=

LS=

EF=

LF=

B 3

ES=

LS=

EF=

LF=

F 3

ES=

LS=

EF=

LF=

G 5

ES=

LS=

EF=

LF=

ES=EF=

LS=LF=

ES=EF=

LS=LF=

Start Finish

slack= slack=

slack= slack=

slack=

Network for Foundry Inc.

D 4

ES=

LS=

EF=

LF=

slack=

C 2

ES=

LS=

EF=

LF=

slack=

E 4

ES=

LS=

EF=

LF=

slack=

Page 24: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example of Hospital Project:

Calculate ES, EF, LF, LS and slack of each activity in this project on its PERT network, given the data about the project as in the next slide.

Page 25: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example: A Hospital Project

Activity Immediate Predecessor(s)

Performance time t (weeks)

A — 12

B — 9

C A 10

D B 10

E B 24

F A 10

G C 35

H D 40

I A 15

J E, G, H 4

K F, I, G 6

Page 26: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

J 4

ES=

LS=

EF=

LF=

A 12

ES=

LS=

EF=

LF=

B 9

ES=

LS=

EF=

LF=

G 35

ES=

LS=

EF=

LF=

H 40

ES=

LS=

EF=

LF=

ES=EF=

LS=LF=

ES=EF=

LS=LF=

Start Finish

slack=

slack=

slack=

slack=

slack=

A Hospital Project

E 24

ES=

LS=

EF=

LF=

slack=

F 10

ES=

LS=

EF=

LF=

slack=

D 10

ES=

LS=

EF=

LF=

slack=

I 15

ES=

LS=

EF=

LF=

slack=

C 10

ES=

LS=

EF=

LF=

slack=

K 6

ES=

LS=

EF=

LF=

slack=

Page 27: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Slack and the Critical Path

• The slack of any activity on the critical path is zero.

• If an activity’s slack time is zero, then it is must be on the critical path.

Page 28: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Critical Path, Examples

• What is the critical path in the Foundry Inc. example?

• What is the critical path in the Hospital project example?

Page 29: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Calculate the Critical Path:

Step 1. Mark earliest times (ES, EF) on all nodes, forward;

Step 2. Mark latest times (LF, LS) on all nodes, backward;

Step 3. Calculate slack of each activity;

Step 4. Identify the critical path that contain the activities with zero slack.

Page 30: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

D 3

ES=

LS=

EF=

LF=

A 2

ES=

LS=

EF=

LF=

B 7

ES=

LS=

EF=

LF=

C 4

ES=

LS=

EF=

LF=

E 2

ES=

LS=

EF=

LF=

ES=EF=

LS=LF=ES=EF=

LS=LF=

StartFinish

slack= slack=

slack=

slack=

slack=

Calculate the critical path

Page 31: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example: Draw diagram and find critical path

Activity Predecessor t

A - 5

B - 3

C - 6

D B 4

E A 8

F C 12

G A,D 7

H E,G 6

I G 5

Page 32: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example: Draw diagram and find critical path

Activity Predecessor t

A - 3

B - 4

C A 6

D B 5

E A,B 8

F C 2

G D,E,F 4

H E,F 5

Page 33: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Solved Problem 13-1&2, p.547-548

Calculate the Critical Path

Activity a m b Immediate predecessor

A 1 2 3 -

B 2 3 4 -

C 4 5 6 A

D 8 9 10 B

E 2 5 8 C, D

F 4 5 6 B

G 1 2 3 E

Page 34: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Steps for Solving 13-1&2

1. Calculate activity performance time t for each activity;

2. Draw the PERT network;

3. Calculate ES, EF, LS, LF and slack of each activity on PERT network;

4. Identify the critical path.

Page 35: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Probabilities in PERT

• Since the performance time t of an activity is from estimations, its actual performance time may deviate from t;

• And the actual project completion time may vary, therefore.

Page 36: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Probabilistic Information for Management

The expected project finish time and the variance of project finish time;

Probability the project is finished by a certain date.

Page 37: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Project Completion Time and its Variance

• The expected project completion time T:

T = earliest completion time of the project.

• The variance of T, T2 :

T2 = (variances of activities on the critical path)

Page 38: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example, Foundry Inc.Activity a m b t variance

A 1 2 3 2 0.111B 2 3 4 3 0.111C 1 2 3 2 0.111D 2 4 6 4 0.444E 1 4 7 4 1F 1 2 9 3 1.777G 3 4 11 5 1.777H 1 2 3 2 0.111

Critical path: A-C-E-G-H

Project completion time, T = Variance of T, T2 =

Page 39: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Solved Problem 13-1&2, p.547-548Project completion time and varianceActivity a m b t variance

A 1 2 3 2 0.111

B 2 3 4 3 0.111

C 4 5 6 5 0.111

D 8 9 10 9 0.111

E 2 5 8 5 1

F 4 5 6 5 0.111

G 1 2 3 2 0.111

Critical path: B-D-E-GProject completion time, T = Variance of T, T

2 =

Page 40: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Probability Analysis

• To find probability of completing project within a particular time x:1. Find the critical path, expected project

completion time T and its variance T2 .

3. Find probability from a normal distribution table (as on page 698).

2.2

T

TxZCalculate

Page 41: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

The Idea of the Approach

• The table on p.698 gives the probability P(z<=Z) where z is a random variable with standard normal distribution, i.e. zN(0,1); Z is a specific value.

• P(project finishes within x days)

)(2

ZzPTx

zP

T

Page 42: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Notes (1)

• P(project is finished within x days)

= P(z<=Z)• P(project is not finished within x days)

= 1P(project finishes within x days)

= 1P(z<=Z)

Page 43: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Notes (2)

• If x<T, then Z is a negative number. • But the table on p.698 is only for positive Z

values.• For example, Z= 1.5, per to the symmetry

feature of the normal curve,

P(z<=1.5) = P(z>=1.5) = 1P(z<=1.5)

Page 44: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example of Foundry Inc. p.530-531

• Project completion time T=15 weeks.• Variance of project time, T

2=3.111.

• We want to find the probability that project is finished within 16 weeks. Here, x=16, and

• So, P(project is finished within 16 weeks)

= P(z<=Z) = P(z<=0.57) = 0.71566.

57.076.1

1

111.3

15162

T

TxZ

Page 45: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Examples of probability analysis

• If a project’s expected completing time is T=246 days with its variance T

2=25, then what is the probability that the project– is actually completed within 246 days?– is actually completed within 240 days?– is actually completed within 256 days?– is not completed by the 256th day?

Page 46: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

A Comprehensive Example Given the data of a project as in the next

slide, answer the following questions:– What is PERT network like for this project?– What is the critical path?– Activity E will be subcontracted out. What is

earliest time it can be started? What is time it must start so that it will not delay the project?

– What is probability that the project can be finished within 10 weeks?

– What is the probability that the project is not yet finished after 12 weeks?

Page 47: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Data of One-more-example:

Activity Predecessor a m b

A - 1 2 3

B - 5.5 7 8.5

C A 3.5 4 4.5

D A 2 3 4

E B,D 0 2 4

Page 48: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Example (cont.)

Activity Predecessor t v

A - 2 0.111

B - 7 0.250

C A 4 0.028

D A 3 0.111

E B,D 2 0.444

Page 49: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

D 3

ES=

LS=

EF=

LF=

A 2

ES=

LS=

EF=

LF=

B 7

ES=

LS=

EF=

LF=

C 4

ES=

LS=

EF=

LF=

E 2

ES=

LS=

EF=

LF=

ES=EF=

LS=LF=ES=EF=

LS=LF=

StartFinish

slack= slack=

slack=

slack=

slack=

Calculate the critical path

Page 50: Chapter 13 Project Management. Characteristics of a project: n A project is unique (not routine), n A project is composed of interrelated sub-projects/activities,

Solving on QM

Critical path, ES, LS, EF, LF, and slack can be calculated by QM for Windows. We need to enter activities’ times and immediate predecessors.

But QM does not provide the network.


Recommended