Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
4 Building Construction Lectures -2nd stage
CHAPTER 2
Soil and Excavations
Soil investigation including two phases: surface investigation and
subsurface investigation
Surface investigation involves making a preliminary judgment about the site’s
suitability for the proposed building. The first part of surface investigation is
a visual assessment of the site. The second part is the land survey provides
physical measurements of the site.
Subsurface investigation deals with conditions below the ground surface to
determine the requirements for the foundations and excavations. Subsurface
conditions have a significant influence on the building design,
construction materials, structural system, construction cost, and schedule.
For example, it is more expensive and time-consuming to excavate in a rocky
stratum or a stratum with a high water table.
Soil classification (Gravels, Sands, Silts, and Clays)
There are a number of characteristics that must be considered in
determining the ability of a soil to support building loads. One important
characteristic is soil classification based on the size of soil particles. The size
of soil particles is measured by passing a dried soil sample through a series of
sieves, each with a standardized opening size (see Figure).
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
5 Building Construction Lectures -2nd stage
Uniqueness of clay (swelling and shrinking) -the expansive
soils
Gravel and sand particles are approximately spherical or ellipsoidal in shape.
This is because gravels and sands are the result of mechanical weathering.
Clay particles are having flat, platelike shapes. Because of their flat particle
shape, the surface-area-to-volume ratio of clays is several hundred or
thousand times greater than the corresponding ratio for gravels and sands.
In the presence of water, the electrostatic forces that developed between
platelike surfaces are repulsive, which increases the space between plates.
Therefore, in the presence of water, clayey soils swell, and as water
decreases (i.e., when they dry), they shrink. Soils that are predominantly
clayey are unstable because they expand and contract, depending on the
amount of water present in them, and are referred to as expansive soils.
Cohesive and noncohesive soils
Fine-grained soil particles adhere to each other in the presence of water and
are, therefore, called cohesive s o i l s . Coarse-grained soils are typically
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
7 Building Construction Lectures -2nd stage
single-grained, lacking cohesiveness, and are referred to as noncohesive soils.
Geotechnical investigations—soil sampling and testing
The objectives of this exploration and sampling are to determine the:
• Engineering properties of the soil at various depths.
• Particle-size distribution of the soil.
• Plasticity index of the soil.
• Nature of the excavation that will suit the soil.
• Depth of the water.
• Compressibility of the soil.
Two methods are generally used for field exploration: (a) the test pit method
and (b) the test boring method.
Bearing capacity of soil
The bearing capacity of a soil is its strength to bear loads imposed on it by
the structure. In other words, the bearing capacity of a soil determines the
maximum load that can be placed on each square foot of the soil before it
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
8 Building Construction Lectures -2nd stage
fails structurally or has an unacceptable amount of settlement.
The bearing capacity of soil generally increases with increasing depth
below ground because the deeper strata of native soil are generally more
densely compacted and have a smaller amount of decomposed plant
matter. Therefore, increasing the depth below ground for the base of the
footing generally reduces the footing area but increases the depth of
excavation, (see Figure).
Presumptive bearing capacity of soil
The allowable bearing capacity of a soil should be obtained from
geotechnical investigations of the site. However, its approximate value,
based on the particle size of the soil at the location (without geotechnical
investigation) is allowed to be used in situations where
• The building is small;
• Adequate information about the soil from adjoining areas is available;
• The site does not contain fill of an unknown origin; and
• The soil is known to be stable (non expansive).
Excavation
Excavation is the first step of construction. It refers to the process of
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
9 Building Construction Lectures -2nd stage
removing soil or rock from its original location. Excavated material
required for backfill or grading fill is stockpiled on the site for
subsequent use. Unneeded material is removed from the site for appropriate
disposal. Excavations are generally classified as Open excavations, Trenches
and Pits.
Open excavations refer to large (and often deep) excavations, such as for a
basement. Trenches generally refer to long, narrow excavations, such as for
footings under a wall or utility pipes. Pits are excavations for the footing of an
individual column, elevator shaft, and so on. The depth of excavation
depends on the type of soil and the type of foundation. Excavation require
various types of power equipment, such as excavators, compactors, and
heavy earth-moving equipment (front-end loaders and backhoes), some of
which are shown in Figure.
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
01 Building Construction Lectures -2nd stage
Supports for open excavations
Excavations in the soil generally require some type of support to prevent
cave-ins while the foundation system or basement walls are constructed. The
simplest excavation support system consists of providing adequate slope in
the excavated (cut) face so that it is able to support itself, (see Figure). This is
feasible only if the site is large enough to accommodate sloped excavations.
Excavation in coarse-grained soils requires a shallower slope than excavation
in fine-grained soils (see Figure). Self-supporting sloped excavations cannot
be provided where the site area is restricted or adjoining structures are
present. In these cases, the excavation must consist of vertical cuts. In
cohesive soils, shallow vertical cuts (generally 5 ft. or less in depth) may be
possible without any support system. Deeper vertical cuts must be provided
with a support system. Some of the commonly used methods of supporting
deep vertical cuts in the soil are
1. Sheet piles
2. Cantilevered soldier piles
3. Anchored soldier piles
4. Contiguous bored concrete piles
5. Secant piles
6. Soil nailing
7. Bentonite slurry walls
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
00 Building Construction Lectures -2nd stage
Excavation support using sheet piles
For depths of up to about 15 ft., vertical sheets of steel, referred to as sheet
piles, can be driven into the ground before commencing excavations.
Sheet piles consist of individual steel sections that interlock with each other
on both sides. The interlocks form a continuous barrier to retain the
earth. Sheet piles are available in many cross-sectional profiles. The most
commonly used profile is a Z-section, (see Figure). The sections are driven
into the ground one by one using either hydraulic hammers or vibrators,
Figure (see Figure). For deeper excavations (generally greater than 15 ft.),
sheet piles are braced with horizontal or inclined braces or anchored with
tiebacks, (see Figure). Sheet piles are removed after they are no longer
required or can be left in place if needed.
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
01 Building Construction Lectures -2nd stage
Excavation support using cantilevered soldier piles
One of the disadvantages of sheet piles is the noise and vibration created in
driving them, particularly in stiff soils where the vibratory method is
ineffective and hydraulic hammers must be employed. An alternative to
sheet pile excavation support is the soldier pile system. In this support
system, H-shaped steel columns (called soldier piles or H-piles) are placed in
the ground. The piles are placed in predrilled circular holes approximately
6 to 8 ft. on center. After the piles are placed, the holes are filled with
lean concrete (see Figure). Excavation of the ground abutting the piles is
commenced after the concrete around the piles has gained sufficient
strength.
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
02 Building Construction Lectures -2nd stage
Excavation support using anchored soldier piles
The use of a cantilevered soldier pile system is uneconomical beyond a
depth of approximately 15 ft. because of the increase in pile cross section. For
deeper excavations, an anchored soldier pile system is employed, which is
similar to the cantilevered pile system except that the piles are tied back
(anchored) into the ground. The commonly used vertical support members
for this system consist of two steel channels with a space between them. The
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
03 Building Construction Lectures -2nd stage
channels are connected together with steel plates welded at intervals in this
space, (see Figure).
Drilling for tieback anchors is done through the space between the twin C-
sections of piles, (see Figure). After a tieback hole has been drilled, steel
bars or high-strength steel tendons are placed in the hole, and the hole is
grouted, (see Figure).
Excavation support using contiguous bored concrete piles
In situations where the (deep) excavation is close to an adjacent building or the
property line, tiebacks cannot be used. In this situation, closely spaced
reinforced concrete piles, called contiguous bored piles (CBPs), are often used, (see
Figure). Each pile is made by screwing an auger into the ground. The auger has
a hollow stem in the middle of a continuous spiral drill.
Once the drill has reached the required depth below the ground, high-
slump concrete is pumped down the hollow stem of the auger to the
bottom of the bore. Once the pumping starts, the auger is progressively
withdrawn. Immediately after the entire bore has been concreted, a
reinforcement cage is lowered in the concrete-filled bore.
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
04 Building Construction Lectures -2nd stage
Excavation support using secant piles
A major shortcoming of CBPs is the gaps between piles and the consequent
lack of water resistance of the excavation support. This problem is
overcome by the use of the modified version of CBPs called secant piles.
Secant piles essentially consist of two sets of interlocking contiguous piles.
The first set, called the primary piles, is bored and concreted in the same way
as the CBPs. The center-to- center distance between the primary piles is
slightly smaller than twice their diameter.
After the primary piles are constructed, the secondary piles are bored at mid-
distance between the primary piles, which also bores through part of the
primary piles, (see Figure). The secondary piles are concreted and reinforced
in the same way as the CBPs.
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
05 Building Construction Lectures -2nd stage
Excavation support using soil nailing
Soil nailing is a means of strengthening the soil with closely spaced, inclined
steel bars that increase the cohesiveness of the soil and prevent the soil from
shearing along an inclined plane. The inclined bars are almost
perpendicular to the possible shearing plane. In other words, the steel bars
connect imaginary inclined layers of the earth into a thick block that
behaves as a gravity-retaining wall when excavated, (see Figure).
The process of soil nailing consists of the following steps:
1) The soil is first excavated 5 to 7 ft. deep, depending on the ability
of the cut face to remain vertical without supports.
2) Holes are drilled along the cut face at 3 to 4 ft. on centers so that
one hole covers approximately 10 to 15 ft2 of the cut face, Figure
11.26(a).
3) Threaded steel bars (approximately 1 in. in diameter) are inserted
in the holes. The length of the bars is a function of the soil type but
is approximately half the final depth of excavation. The bars
protrude a few inches out of the holes.
4) The holes are grouted with concrete.
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
07 Building Construction Lectures -2nd stage
5) WWR is placed over the wall and tied to the protruding bars.
6) A layer of shotcrete is applied to the mesh.
7) Plates and washers are inserted in the protruding bars and locked in
position with a nut.
8) A second layer of shotcrete may be used if the soil-nailed wall is
the finished wall, or a cast-in-place concrete wall may be
constructed against it.
9) These steps are repeated with the next depth of cut.
Excavation support using bentonite slurry as trench support
Another excavation support system, commonly used in situations where the
underground water table is relatively high, is a reinforced concrete wall.
Construction of such walls is done by excavating 10-ft- to 15-ft-long
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
08 Building Construction Lectures -2nd stage
discontinuous trench sections down to bedrock, called primary panels. The
width of the trench sections is the required thickness of the concrete wall.
So that the soil does not collapse, the trench is continuously kept filled with
bentonite slurry as the excavation proceeds. (Bentonite slurry is a mixture
of water and bentonite clay, which pressurizes the walls of the trench
sufficiently to prevent their collapse during excavation.)
Special excavation equipment is used to extract soil through the slurry-filled
trench. After the excavation for the entire primary panel is complete, a
reinforcement cage is lowered into the trench. Concrete is then placed in the
trench panel using two or more tremie pipes, typically one at each end of the
panel. Concrete is placed from the bottom up, and the discharge end of the
tremie is always buried in concrete. A tremie pipe is generally an 8-in. - to
10-in.-diameter steel pipe with a hopper at the top, (see Figure).
As concreting proceeds, the slurry is pumped out from the top of the trench and
stored for later use. After the primary panels have been constructed,
excavation for secondary panels (between the primary panels) is undertaken
in the same way as for the primary panels. To provide shear key and water
resistance between primary and secondary panels, a steel pipe is embedded at
the end of each primary panel prior to its concreting. These pipes are removed
after the concrete in the primary panels has gained sufficient strength.
The tremie pipe method of concrete placement requires great care and
expertise, particularly the initial placement of concrete, which is generally
a richer mix. The concrete must also be placed slowly so that it does not get
too diluted by the slurry.
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
09 Building Construction Lectures -2nd stage
Keeping excavations dry
It is important to keep excavations free from groundwater. Groundwater
control in an excavation consists of two parts: (a) preventing surface water
from entering the excavation through runoff and (b) draining (dewatering)
the soil around the excavations so that the groundwater level falls below the
elevation of proposed excavation. Two commonly used methods of
dewatering the ground are sump pumps and well points
Dewatering through sumps
Sump dewatering consists of constructing pits (called sumps) within the
enclosure of the excavation. The bottom of sumps must be located below
the final elevation of the excavation. As the groundwater from
surrounding soil percolates into the sump, it is lifted by automatic pumps
and discharged away from the building site, (see Figure). The number of
required sumps is a function of the excavation area.
Dewatering through well points
Sump dewatering works well in cohesive soils, where the percolation rate is
Dr. Abdulkhaliq Abdulyimah Jaafer
Misan University - College of Engineering Civil Engineering Department
11 Building Construction Lectures -2nd stage
slow and where the water table is not much higher than the final elevation
of the base of the excavation. A more effective dewatering method uses
forced suction to extract groundwater. This is done by sinking a number
of vertical pipes with a screened end at the bottom (called well points)
around the perimeter of the excavation. The well points reach below the floor
of the excavation and are connected to large-diameter horizontal header
pipes at the surface.
The header pipe is connected to a vacuum-assisted centrifugal pump that
sucks water from the ground for discharge to an appropriate point. For a
very deep excavation, two rings of well points may be required.
Whereas the sump method of dewatering does not greatly affect the existing
water table, dewatering by well points can lower the water table
considerably. The effect of this on the adjoining buildings must be
considered because it can cause consolidation and settling of the
foundations of existing buildings on some types of soils.
Dewatering of excavations can be fairly complicated and generally requires
an expert dewatering subcontractor for large and complicated operations.