110
CHAPTER 6
OPTIMAL SIZING AND LOCATION OF DISTRIBUTED
GENERATORS USING MODIFIED BACTERIAL
FORAGING ALGORITHM UNDER VARIABLE
LOADING CONDITIONS
6.1 INTRODUCTION
Around the world, conventional power systems are facing the
problems of gradual depletion of fossil fuel resources, poor energy efficiency
and environmental pollution. Many private sectors invest huge money to meet
their contingent loads under power cut and also cater peak load demand
locally using conventional diesel generators. These problems have led to a
new trend of power locally at the distribution voltage level using non-
conventional/ renewable energy sources like Natural gas, Biogas, Wind-
power, Solar Energy and Fuel cells, Combined Heat and Power (CHP)
systems, Micro turbines, and Sterling Engines and their integration into the
utility distribution networks. This type of power generation is termed as
distributed generation and the energy sources are termed as distributed energy
distinguish this concept of generation from centralized conventional
generation. The distribution network becomes active with the integration of
D.G. and hence is termed as active distribution network Durga & Nadarajah
(2007).
114
can again be connected to the utility as a separate semi-
autonomous entity.
Stand-a
generation augmentation, thereby improving overall power
quality and reliability. Moreover, a deregulated environment
and open access to the distribution network also provide greater
opportunities for D.G. integration. In some countries, the fuel
diversity offered by DG is considered valuable, while in some
developing countries, the shortage of power is so acute that any
form of generation is encouraged to meet the load demand.
6.4 TYPES OF DG DEVICE
The D.G. device utilized in this paper is I.C Engine. The internal
combustion engine is an engine in which the combustion of a fuel (normally a
fossil fuel) occurs with an oxidizer (usually air) in a combustion chamber. In
an internal combustion engine, the expansion of the high-temperature and
high -pressure gases produced by combustion apply direct force to some
component of the engine. This force is applied typically to pistons, turbine
blades, or a nozzle. This force moves the component over a distance,
transforming chemical energy into useful mechanical energy. The first
functioning internal combustion engine was created by Étienne Lenoir.
ICEs cost less than its peers such as fuel cells and are of the
conventional form of energy. They can be integrated directly into the power
grid as compared to renewable forms like wind, solar that need power
converters for linkage purposes. Table 6.1 list out the various types of DG
device, their operation range and their utility interface.
115
Table 6.1 Various types of DG devices, their operation range andmeans
of implementation
Technology Typical Capability Ranges Utility Interface
Solar Cells A few W to several hundred kW
dc to ac converter
Wind A few hundred W to a few MW
Asynchronous generator
Geothermal A few hundred kW to a few MW
Synchronous generator
Ocean A few hundred kW to a few MW
Four-quadrant synchronous machine
Internal combustion engine
A few hundred kW to tens of MW
Synchronous generator or ac to ac converter
Combined cycle A few tens of MW to hundreds of MW
Synchronous generator
Combustion turbine
A few MW to hundreds of MW
Synchronous generator.
Micro turbines A few tens of kW to a few MW
ac to ac converter
Fuel cells A few tens of kW to a few tens of MW
dc to ac converter
6.5 MODIFIED BACTERIAL FORAGING ALGORITHM FOR
OPF
The following section explains the various steps involved in
implementation of Bacterial Foraging Algorithm (BFA) for the above
formulated problem. BFA is based on the principle of foraging theory and
used to solve numerous engineering problems. The advantages of BFA such
116
as speedy convergence, self-adaptive, computationally intensive etc. make it
superior over other existing intelligent techniques. The basic Bacterial
Foraging Optimization consists of three principal mechanisms; namely
chemotaxis, reproduction and elimination-dispersal. In case of MBFA the
chemotaxis step of normal BFA is altered by introducing variable step size in
each iteration (Hanning et al 2009).
Step 1: Initialization
1) S - Number of bacteria
2) p - Dimension of the search space.
3) sN - Swimming length, the maximum number of steps each
bacteria swims before tumbling
4) cN - Number of iterations to be undertaken in a chemotactic
loop;
5) reN - Maximum number of reproduction to be undertaken;
6) reN - Maximum number of elimination and dispersal;
7) edP - Probability of elimination and dispersal ;
8) )(iC - Unit run length for bacterium
9) Sii ........,,3,2,1, - Random Swim direction
Step 2: Read bus data, line data, active power limits and cost coefficients of
generator including DG
Step 3: Run Newton-Raphson (NR) load flow.
The following section explains the chemotaxis loop, swarming,
reproduction, and elimination and dispersion of a bacterium. Any
117
thi bacteria at the thj chemotactic, thk reproduction and thl
elimination stage is given by ),,( lkji and its corresponding
objective function is ),,,( lkjiJ . The values of ),,( lkji and
),,,( lkjiJ are updated using the following steps.
Step 4: Start Elimination dispersal loop 1ll
Step 5: Reproduction loop 1kk
Step 6: Chemotaxis loop 1jj
A) For each bacterium Si .......,,3,2,1 , compute objective function
),,,( lkjiJ .
a. Let )),,(),,,((),,,(),,,( lkjPlkjJlkjiJlkjiJ iccsw
b. Let ),,,( lkjiJJ swlast , to save this value since we find a
better cost via a run.
c. End of the loop
B) Tumble: Generate a random vector Pi)( with each element
being a random number in the range of [0,1]
C) Move:
Let )(i = )()(
)(ii
iT
)()(),,(),,1( iiClkjlkj ii
This results in a step size )(iC in the direction of the tumble for
the i th bacterium.
118
D) Compute ),,1,( lkjiJ and then let
)),,1(),,,1((),,1,(),,1,( lkjPlkjJlkjiJlkjiJ iccsw
E) Swim
a. Let m = 0 (counter length for swim)
b. While SNm
i. Let 1mm
ii. If lastsw JlkjiJ ),,1,(
then ),,1,( lkjiJJ swlast
)()(),,(),,1( iiClkjlkj ii
and use the above ),,1( lkji to compute
new ),,1,( lkjiJ
iii. Else SNm
F) Go to next bacterium )1(i till all the bacteria undergo
chemotaxis.
G) Update the run length unit using Equation (6.1)
Step 7: Reproduction
a. For the given k and l , for each Si ....,..........,3,2,1 , let 1
1),,,(
cNj
jsw
ihealth lkjiJJ be the health of i th bacterium and sort
healthJ in ascending order
119
b. The bacteria with the highest healthJ values die and those with
minimum values split and the already made copies are now
placed at the same location as their parent.
Step 8: If reNk , go to step 4. In this case, we have not reached the
number of specified reproduction steps, so we start the next
generation in the chemotactic loop.
Step 9: Elimination dispersal: for Si ....,..........,3,2,1 , a random number is
generated and if it is less than or equal to edP , then that bacterium
is dispersed to a new random location else it remains at its original
location. If edNl , then go to step 4; otherwise go to next step
Step 10: Run Newton-Raphson load flow
Step 11: Print OPF Results and end.
The flowchart for the proposed method is shown in Figure 6.1. The
flowchart for finding the optimal location and size of the DG using MBFA
algorithm is shown in Figure 6.2. The parameters selected for the proposed
MBFA algorithm are as follows.
Number of bacteria S : 20
Number of chemotactic steps Nc : 5
Swimming length Ns : 4
of reproduction steps Nre : 4
Number of elimination and dispersal events Ned : 2
Probability of elimination and dispersal Ped : 0.2
120
Depth of attractant : 0.01
Width of attractant : 0.04
Height of repellent : 0.01
Width of repellent : 10.0
6.6 PSEUDO CODE FOR OPTIMAL LOCATION AND SIZE OF
DG USING MBFA
Step 1: DG size and Maximum DG limit should be initialized.
Step 2: Objective Function should be evaluated using MBFA and Optimal
DG location should be updated.
Step 3: The DG size should be increased in all Load buses
Step 4: The condition , is to be checked, if yes go to step 5, else
go back to step 2.
Step 5: The DG size in optimal location is to be increased.
Step 6: Objective Function should be evaluated using MBFA and Optimal
DG location should be updated.
Step 7: The condition , is to be checked, if yes goto step 8 else
goto step 5
Step 8: Optimal DG location and size to be printed.
Step 9: Terminate
121
Figure 6.1 Flowchart for OPF using BFA
Initialize: BFA parameters Read power system
Run NR Load Flow
Compute OF for bacterium
Compute new OF
Tumble bacterium for a step size of along a randomly generated tumble vector
Set
Run NR Load Flow
Print OPF Results
=
End
Start
Elimination-Dispersal
Reproduction
X
X
Y
Y
Yes
No
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
122
Figure 6.2 Flowchart for obtaining optimal location and size of DG
using MBFA
Start
Initialize DG size ,
Evaluate Objective function using MBFA and update optimal DG Location
Increase DG Size in all Load buses
Increase DG Size in Optimal Location
Evaluate Objective function using MBFA and update optimal DG Size
Print: Optimal DG location and Size
End
No
No
Yes
Yes
123
6.7 RESULTS AND DISCUSSIONS
To solve the effectiveness of the proposed MBFA algorithm, in
finding the optimal location and rating of DG in IEEE 14 and IEEE 30 bus
system are used. A Matlab program is written and executed in intel core i5
3.2GHz processor system. The Distributed Generation data available in the
literature Durga & Nadarajah (2007) is used in this work. The quadratic cost
coefficients of DG used are given in Table 6.2. The line data, bus data and
generator data of IEEE 30 and IEEE 14 bus test systems are presented in
Appendix 1 and 2 respectively.
Table 6.2 Distributed Generation data
d ($/MW2h) e ($/MWh) f ($/h)
0.002 15 0
6.7.1 Variation of Objective Function (OF) with DG Placement
The problem formulated in chapter 3 is solved using proposed
BFOA algorithm. In this work, IC engine is considered as Distributed
Generator and it is added to the load buses of IEEE14 and IEEE30 bus
system. The rating of DG is varied between 1MW to 40 MW. Figure 6.3
shows the effect of DG placement on cost of power production on IEEE 14
bus system. From the figure, it is clear that the cost decreases when DG is
added at bus number 13. Similarly the optimal placement of DG for IEEE 30
bus system with increased loading of 30MW at bus number 2 is computed and
the results obtained are presented in Figure 6.4. From the figure, it is apparent
that the best cost minimization is obtained at bus number 7.
124
Figure 6.3 Variation of objective function with DG location for IEEE
14 bus system
Figure 6.4 Variation of objective function with DG location for IEEE
30 bus system
0 2 4 6 8 10 12 14
1596
1597
1598
1599
1600
1601
1602
1603
1604
1605
Bus Number
Increasing DG Size
0 5 10 15 20 25 30950
952
954
956
958
960
962
964
966
968
Bus Number
125
6.7.2 Optimal Size of DG
From the above discussion it is found that minimum OF is attained
when DG is placed at bus no 13 and bus number 7 for IEEE 14 and IEEE 30
bus system respectively. However, to identify the optimal rating of DG, for
reduced losses, now DG rating is increased between 1MW to 40MW in the
above identified optimal location. The results obtained for IEEE14 bus system
by connecting DG at bus no 7 is presented in Figure 6.5. Similarly the
variation of objective function with respect to change in DG size at optimal
location for IEEE30 bus system and 30 MW loading at bus number 2 is
shown in Figure 6.6. From the results presented in Figure 6.5 and 6.6, the
optimal values of DG are15 MW and 23 MW respectively.
Figure 6.5 Variation of objective function with DG size for IEEE
14 bus system at optimal location (bus no.13)
0 5 10 15 20 25 30 35 401596
1596.5
1597
1597.5
1598
1598.5
1599
1599.5
DG Size (MW)
126
Figure 6.6 Variation of objective function with DG size for IEEE 30
bus system at optimal location (bus no.7)
To test the effectiveness of the proposed algorithm, different levels
of loading was done at randomly selected PQ buses. The results obtained are
tabulated and presented in Table 6.3. From the table, it is observed that, when
30MW additional loading is done at buses 2, 4, 14, 17 and 10, the
corresponding optimal DG locations are found to be bus no 21, 7, 24, 9 and
22 respectively.
Further, it may be noted that, the rating of DG added to meet the
additional load is always less than that of the load increased; because of the
fact that, in the practical case, DGs are located closer to the demand point so
that it meets the required amount of additional load. However, the addition of
DG to the existing IEEE14 and IEEE30 bus system will contribute to increase
in total generation cost. This increased cost can be met with savings made in
loss reduction. It is also seen from the table that, in most of the cases, bus
number above 20 is found to be the optimal location.
127
Table 6.3 Optimal sizing and location of DG devices under variable
loading conditions
Bus No.
Normal Loading
New Loading
Optimal DG size
Optimal DG
Location
Total loss
Total Cost
Total Load
MW MW MW Bus No. MW $/Hr MW 30 MW loading
02 21.7 51.7 22.00 21 7.964 951.1 313.4
04 07.6 37.6 23.87 07 8.272 953.2 313.4
14 06.2 36.2 23.98 24 9.615 956.9 313.4
17 09.0 39.0 28.16 09 8.94 955.8 313.4
10 05.8 35.8 26.00 22 8.879 955.0 313.4
20 MW loading
15 08.2 28.2 18.18 19 8.575 919.7 303.4
15 MW loading
18 03.2 18.2 12.54 10 9.119 903.8 298.4
10 MW loading
20 02.2 12.2 8.188 27 8.755 885.3 293.4
23 03.2 13.2 7.733 06 9.021 886.0 293.4
6.7.3 OPF without DG in IEEE 14 Bus System
The real power generations in IEEE 14 bus system under normal
loading conditions without including DG is given in Table 6.4. The total
generation cost including the cost of DG for a IEEE 14 bus system is found to
be 1423$/Hr using the proposed MBFA algorithm. This generation cost is
compared with other optimization techniques namely BFA, GA and PSO in
Table 6.5. The cost convergence curve for OPF Using MBFA in IEEE-14 Bus
System is shown in Figure 6.7. From the figure it is clear that the approximate
convergence takes near 52nd iteration.
128
Table 6.4 Real power generation in IEEE 14 bus system using MBFA
Optimization Technique
G1 G2 G3 G4 G5 Total Cost
MW MW MW MW MW $/Hr
56.5942 51.1667 28.6715 39.0819 86.7263 1423
Table 6.5 Total Cost Comparison for IEEE 14 bus system
Total Generation Cost ($/Hr)
MBFA BFA GA PSO 1423 1440.4 1613.4 1507.3
Figure 6.7 Cost Convergence Curve for OPF Using MBFA for IEEE
14 Bus System
0 50 100 150 200 250 300 350 400 450 5001420
1425
1430
1435
1440
1445
1450MBFA graph
ITERATIONS
129
6.7.4 OPF with DG in IEEE 14 Bus System
In the problem of finding the optimal location and rating of DG in
IEEE 14 bus system, a DG with 80.4695 MW at bus no.4 is found to be the
optimal rating and location respectively and is presented in Table 6.6. It is
also noted that the inclusion of DG leads to a remarkable decrease in total real
power loss. Figure 6.8 is used to show the variation in power loss with DG
location. Bus no.4 is found to be the optimal location with minimum loss. The
variation of real power loss with change of DG rating is shown in Figure 6.9.
From the figure 80.4695MW is found to be the optimal DG rating. The
voltage profile in IEEE 14 bus system with and without DG is shown in
Figure 6.10.
Table 6.6 Optimal sizing and location of DG for IEEE 14 bus system
Loss without DG
(MW)
Loss with DG
(MW)
Optimal location of
DG
Total cost including DG
($/Hr)
Optimal rating of DG (MW)
3.2951 1.613 4 2218.8 80.4695
Figure 6.8 Optimal location of DG in IEEE 14 bus system
0
0.5
1
1.5
2
2.5
3
3.5
1 2 3 4 5 6 7 8 9 10 11 12 13 14Bus no
130
Figure 6.9 Power Loss variations with DG size in IEEE 14 bus system under normal loading condition
Figure 6.10 Voltage profile with and without DG in IEEE14 bus system
0 50 100 150 200 250 300 3500
2
4
6
8
10
12
14
16
18Loss variation at DG located bus
DG size
0 2 4 6 8 10 12 141.01
1.02
1.03
1.04
1.05
1.06
1.07
1.08
1.09
1.1
1.11VOLTAGE PROFILE
BUS NO.
131
6.7.5 OPF without DG in IEEE 30 Bus System
The total generation cost including the cost of DG for a IEEE 30
bus system using the proposed MBFA technique is found to be 798.22$/Hr.
This generation cost is compared with other optimization techniques namely
BFA, GA and PSO in Table 6.7. The cost convergence curve for OPF Using
MBFA in IEEE 30 Bus System is shown in Figure 6.7. From the figure it is
evident that the objective function converges at 35th iteration.
Table 6.7 Total Cost Comparison for IEEE 30 bus system
Total generation cost ($/Hr) MBFA BFA GA PSO
798.2 800.2052 803.5495 801.26
Figure 6.11 Cost Convergence Curve for OPF Using MBFA in IEEE 30
Bus System
0 10 20 30 40 50 60 70 80 90 100798
799
800
801
802
803
804
805
806
807
808
ITERATIONS
132
6.7.6 OPF with DG in IEEE 30 Bus System
In the problem of finding the optimal location and rating of DG in
IEEE 30 bus system, a DG with 128.823 MW at bus no.6 is found to be the
optimal rating and location respectively and is presented in Table 6.8. It is
also noted that the inclusion of DG leads to a remarkable decrease in total real
power loss of 5MW. Figure 6.12 is used to show the variation in power loss
with DG location. Bus no.6 is found to be the optimal location with minimum
loss. The variation of real power loss with change of DG rating is shown in
Figure 6.13. From the figure 128.8223MW is found to be the optimal DG
rating. The voltage profile in IEEE 30 bus system with and without DG is
shown in Figure 6.14.
Table 6.8 optimal sizing and location of DG for IEEE 30 bus system
Loss without
DG (MW)
Loss with DG
(MW)
Optimal location of DG
Total cost including DG
($/Hr)
Optimal rating of DG
(MW) 7.4016 2.437 6 2694.9 128.8223
Figure 6.12 Optimal location of DG in IEEE 30 bus system
0
1
2
3
4
5
6
7
8
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29Bus no
133
Figure 6.13 Variation of losses w.r.t DG size for IEEE-30 Bus System
Figure 6.14 Voltage profile with and without DG in IEEE 30 bus system
0 50 100 150 200 250 300 3502
4
6
8
10
12
14
16Loss variation at DG located bus
DG size
134
6.7.7 OPF including DG under Variable Loading Condition
The proposed MBFA method for solving OPF including DG is
further analyzed under variable condition. An increased loading of 50MW,
40MW and 30MW is done on all buses except slack and PV buses and the
optimal location and rating of DG for this variable loading is obtained. The
corresponding total real power loss is also monitored. Table 6.9, Table 6.10
and Table 6.11 presents the optimal rating of DG, optimal location of DG and
total real power loss under 50MW, 40MW and 30MW respectively.
The total real power loss variation under each iteration in a IEEE
30 bus system for and increased loading of 50MW, 40MW and 30MW are
shown in Figure 6.15, Figure 6.16 and Figure 6.17 respectively. The voltage
profile in IEEE 30 bus system with and without DG for an increased loading
of 50MW, 40 MW and 30MW are shown in Figure 6.18, Figure 6.19 and
Figure 6.20 respectively.
Figure 6.21 shows the variation of total real power loss with change
in DG rating for 50MW increased loading in optimal DG location i.e bus
no.14. The optimal rating obtained is 78.96MW and the corresponding loss is
6.15MW. Similarly for 40 MW and 30MW increased loading, the optimal
rating is found to be 69.50MW with 6.34MW loss and 82.69MW with
5.42MW loss respectively and is shown in Figure 6.22 and Figure 6.23.
135
Table 6.9 Optimal rating and location of DG and Corresponding Losses
in IEEE-30 Bus system for 50MW increased loading
Bus No.
Load Optimal DG Power Loss Before After Size Location
(MW) (MW) (MW) (Bus No.) (MW)
3 2.4 52.4 140.71 9 4.12
4 7.6 57.6 167.844 4 3.88
6 0 50 127.96 6 3.88
7 22.8 72.8 137.01 7 3.60
9 0 50 158.64 9 3.18
10 5.8 55.8 162.75 9 3.1817
12 11.2 61.2 116.12 6 4.54
14 6.2 56.2 78.96 14 6.51
15 8.2 58.2 109.65 15 5.55
16 3.5 53.5 122.84 6 5.06
17 9 59 166.29 9 4.70
18 3.2 53.2 89.07 18 5.144
19 9.5 59.5 93.45 19 5.52
20 2.2 52.2 98.37 20 5.84
21 17.5 67.5 118.81 21 4.61
22 0 50 166.06 9 4.61
23 3.2 53.2 93.08 23 6.15
24 8.7 58.7 100.21 24 5.93
27 0 50 176.55 6 4.90
28 0 50 124.37 6 4.63
136
Table 6.10 Optimal rating and location of DG and Corresponding
Losses in IEEE-30 Bus system for 40MW increased loading
Bus No.
Load Optimal DG Power Loss Before After Size Location
(MW) (MW) (MW) (Bus No.) (MW)
3 2.4 42.4 135.30 9 3.88
4 7.6 47.6 164.88 4 4.07
6 0 40 148.36 9 4.36
7 22.8 62.8 129.38 7 3.54
9 0 40 152.07 9 3.71
10 5.8 45.8 155.53 9 3.33
12 11.2 51.2 96.16 6 3.43
14 6.2 46.2 154.43 4 6.49
15 8.2 48.2 99.39 15 5.19
16 3.5 43.5 147.22 9 5.37
17 9 49 153.49 9 4.08
18 3.2 43.2 81.48 18 5.43
19 9.5 49.5 83.98 19 5.94
20 2.2 42.2 90.54 20 5.28
21 17.5 57.5 152.05 9 4..38
22 0 40 151.33 9 3.96
23 3.2 43.2 79.32 23 5.57
24 8.7 48.7 87.63 24 5.12
27 0 40 143.03 6 4.34
28 0 40 109.60 6 4.52
137
Table 6.11 Optimal rating and location of DG and Corresponding
Losses in IEEE-30 Bus system for 30MW increased loading
Bus No.
Load Optimal DG Power Loss Before After Size Location
(MW) (MW) (MW) (Bus No.) (MW)
3 2.4 32.4 129.56 9 3.62
4 7.6 37.6 138.78 9 4.23
6 0 30 137.41 9 3.55
7 22.8 52.8 117.74 7 3.54
9 0 30 137.39 9 3.65
10 5.8 35.8 151.81 9 3.51
12 11.2 31.2 91.06 6 3.61
14 6.2 36.2 82.69 6 5.42
15 8.2 38.2 139.43 9 5.35
16 3.5 33.5 132.25 9 4.23
17 9 39 141.31 9 3.64
18 3.2 33.2 139.07 18 5.15
19 9.5 39.5 144.45 9 5.55
20 2.2 32.2 139.87 20 4.95
21 17.5 47.5 142.01 9 3.67
22 0 30 141.16 9 3.85
23 3.2 33.2 69.24 23 5.63
24 8.7 38.7 87.63 24 5.12
27 0 30 143.03 6 4.34
28 0 30 109.60 6 4.52
138
Figure 6.15 Loss variation in DG installed bus under 50 MW loading
Figure 6.16 Loss variation in DG installed bus under 40 MW loading
0 10 20 30 40 50 60 70 80 90 1005
6
7
8
9
10
11
12
13
14Loss variation at DG located bus
ITERATIONS
139
Figure 6.17 Loss variation in DG installed bus under 30 MW loading
Figure 6.18 Voltage profile with and without DG for 50 MW increased
loading
0 5 10 15 20 25 300.95
1
1.05
1.1VOLTAGE PROFILE
BUS NO.
140
Figure 6.19 Voltage profile with and without DG for 40 MW increased
loading
Figure 6.20 Voltage profile with and without DG for 30 MW increased
loading
0 5 10 15 20 25 300.98
1
1.02
1.04
1.06
1.08
1.1
1.12VOLTAGE PROFILE
BUS NO.
0 5 10 15 20 25 300.98
1
1.02
1.04
1.06
1.08
1.1VOLTAGE PROFILE
BUS NO.
141
Figure 6.21 Loss variations with DG size in IEEE 30 bus system under
50 MW increased loading
Figure 6.22 Loss variations with DG size in IEEE 30 bus system under
40 MW increased loading
0 50 100 150 200 250 300 3500
10
20
30
40
50
60
70Loss variation at DG located bus
DG SIZE
0 50 100 150 200 250 300 3500
10
20
30
40
50
60
70Loss variation at DG located bus
DG SIZE
142
Figure 6.23 Loss variations with DG size in IEEE 30 bus system under 30 MW increased loading
6.8 CONCLUSION
In this work, Modified Bacterial Foraging Optimization Algorithm
is proposed to find the optimal location and sizing of DG for IEEE14 and
IEEE30 bus system. Minimization of total cost, in addition to optimal location
and sizing of DG, is framed as objective function and solved using the
proposed method. Further, the proposed method is tested under varying load
conditions and the results are presented. From the results, it is apparent that,
appropriate size and location of DG sources are highly crucial, and important
to maximize the benefits. The proposed algorithm is found to be effective in
finding the optimal DG size and location and the suitable DG sizes are 15MW
and 23MW for IEEE14 with increased loading of 30MW in bus number 4 and
IEEE30 bus system with increased loading in bus number 2 respectively.
Finally, the results obtained in this study, demonstrated that DG is a viable
economic alternative relative to upgrading substations and feeder facilities, if
the incremental cost of serving additional load is considered.
0 50 100 150 200 250 300 3504
5
6
7
8
9
10
11
12Loss variation at DG located bus
DG SIZE