Maple Highlands Trail ConnectionProject Status and Future Connections
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
2/29
Overview
Status of current project
Current alignment
Next steps for current project
Future trail connection
Why an alignment study is important Example of alignment study
Alignment study proposal
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
3/29
Current Project Status
Right-of-Way Acquisition
Communication is in process with property owners
Donation letters have been sent
Appraisals are currently on hold per request of the City
CE Document (Categorical Exclusion Process)
CE document was approved by ODOT earlier this
summer (Environmental is cleared)
Alignment
Alignment is set
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
4/29
Current Phase - Alignment
http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=wOnpLplDDuS_YM&tbnid=DgqdMuapJDlQqM:&ved=0CAUQjRw&url=http://ian.umces.edu/imagelibrary/displayimage-topn-0-6412.html&ei=ZhxLUry_MNah4AOu7IGoBg&bvm=bv.53371865,d.dmg&psig=AFQjCNE1wy2a6D8mMpy8fas0-LfPhCAOnQ&ust=13807405774879167/27/2019 Chardon MapleHighlandsPresentation 10-01-13
5/29
Current Project Status
Trailheads/Nodes
Design/site plan is complete
Design will be incorporated into final construction
documents
Full planting and materials plan will be included
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
6/29
Fifth Avenue Trailhead
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
7/29
Fifth Avenue Trailhead
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
8/29
Fifth Avenue Trailhead
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
9/29
Center Street Trailhead
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
10/29
Center Street Trailhead
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
11/29
Center Street Trailhead
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
12/29
Water Street Trailhead
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
13/29
Water Street Trailhead
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
14/29
Water Street Trailhead
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
15/29
Current Project Next Steps
Wayfinding
Location and design of wayfinding will be determined
Most likely a pre-fabricated wayfinding and kiosk
system will be recommended
Right-of-Way
Completed in the next four months (realistically)
We are not assuming that all property owners will
donate Purchasing takes longer than transferring
ownership of a donated property
Cost Estimate
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
16/29
Maple Highlands Trail - Next Phase
Future Connection
Connects Water
St. (current
phase) to
Existing MapleHighlands Trail
on S.R. 44
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
17/29
Future Alignment Study
Importance of Alignment Study
Assure that you have enough property
You want multiple alignment options before you
apply for outside funding for implementation
Acquiring right-of-way vs. not acquiring right-of-waymakes a major difference in cost and time
Right-of-way acquisition is an eligible expense for
federal funds at an 80/20 match
End goal is to make sure you are asking for theappropriate amount of money and enough money to
cover your eligible costs
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
18/29
Future Alignment Study
CSX property affects next phase
Environmental Design Group is already helping the
City in talking to CSX
Even if federal funds are not used for property
acquisition, we still have to follow ODOTregulations when talking to any property owner if
the trail is going to be built with federal funds
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
19/29
Funding Changes
$300 Million less than combined programs of SAFETEA-LU
http://t4america.org/wp-content/uploads/2012/11/Transportation-Alternatives-flowchart.jpghttp://t4america.org/wp-content/uploads/2012/11/Transportation-Alternatives-flowchart.jpghttp://t4america.org/wp-content/uploads/2012/11/Transportation-Alternatives-flowchart.jpg7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
20/29
Alignment Study - Example
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
21/29
Alignment Study - Example
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
22/29
Alignment Study - Example
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
23/29
Alignment Study - Example
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
24/29
Future Alignment Study - Proposal
Task 1 - Concept Alignment Study
Coordinate with the City of Chardon staff to develop preliminary horizontal
alignment for a 10 separated all-purpose trail along the Maple Highlands Trail
corridor.
A. Review previous studies, maps, and information from Client and other
sources.
B. Site inventory of existing conditions within the corridor.
C. Work with the Client to identify a preferred horizontal trail alignment.
D. Identify trail alignment conflicts that would require changes to roadway orother shared improvements.
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
25/29
Future Alignment Study - Proposal
Task 2 Cost Opinion
We will review conceptual alignment study and make any necessary revisions to
the plans.
A. Prepare preliminary site plan(s) showing preferred alignment.B. Prepare final cost opinion.
C. Prepare a report documenting plans, cost opinions, inventory, and analysis.
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
26/29
Future Alignment Study - Proposal
Task 3 Typical Sections and Conceptual Renderings
We will develop (up to) three typical sections and design two renderings that
highlight two focus areas along the conceptual alignment. We will prepare
color rendered plan enlargements, perspectives, and/or sections depicting the
trail character and context to be used to promote the project to public andfunders.
A. Up to three trail sections will be developed showing typical materials,
construction dimensions and possible buffer solutions.
B. Detailed enlargement renderings will be rendered for two focus areas alongthe conceptual alignment. Renderings will be in full color and show before
and after images.
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
27/29
Future Alignment Study - Proposal
Task 4 NOACA Grant Application
We will prepare the grant application to NOACA to obtain Preliminary
Engineering and Design, and Construction funds for the Maple Highlands Trail
Phase II.
A. Organize and attend one meeting between NOACA, ODOT, and the City of
Chardon to discuss the project prior to submitting the application.
B. Complete theApplication for Proposed Federal-Aid Projects and Programs
as required by NOACA to obtain federal funds for the project.
C. Provide a sealed cost opinion for the preliminary engineering, design andconstruction of the project.
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
28/29
Future Alignment Study - Proposal
Task 1 Conceptual Alignment Study $6,750.00
Task 2 Cost Opinion $2,600.00
Task 2 Presentation Graphics and Conceptual Renderings $1,250.00
Task 4 NOACA Grant Application $2,000.00
TOTAL $12,600.00
7/27/2019 Chardon MapleHighlandsPresentation 10-01-13
29/29
Questions
Michelle Johnson
Senior Planner/Project Manager
513.461.2121 (cell) 330.375.1390 (office)
mailto:[email protected]:[email protected]