Date post: | 19-Jan-2016 |
Category: |
Documents |
Upload: | lizbeth-britten |
View: | 214 times |
Download: | 0 times |
City of Bloomfield Hills
2015
Road Improvement Program
Introductions City Commissioners in Attendance City Staff
Jay Cravens, City ManagerJamie Spivy, DPW Foreman
Hubbell, Roth and Clark, Inc.James Burton, PEMelissa Coatta, PE
Purpose of Meeting Provide an update on the road program Define the scope of the proposed work Review the Construction Schedule, Proposed
Sequencing, & Maintenance of Traffic Plan Answer general questions Opportunity to review work near your home on a
one on one basis
Update Year 9 of the City approved 10 year Road
Improvement Program Vaughn Road and S. Cranbrook Road were
selected for this round of improvements New Water Main Select Drainage Improvements
Disclaimer Plans subject to change due to budgetary
concerns
General Construction IssuesWe aim to minimize:The disruption and inconvenience of constructionIncreased truck traffic
General Construction IssuesWe suggest:Following the proposed detoursAvoid driving through the construction areas (Local Traffic Acceptable)
HRC Field Representative will be available
Underground Installations
Typical Construction
Roadway Grading
Typical Construction
Brick Pavers
Typical Construction
Restoration
Typical Construction
Proposed Schedule Consumers Energy Gas Main Improvements
Not part of City project
Underground (water main, edge drain, storm sewer) Vaughn Road: March 2015 – April 2015 Cranbrook Road: July 2015 – August 2015
Roadwork (to follow underground) Vaughn Road: May 2015 – June 2015 Cranbrook Road: August 2015 – September 2015
Notifications (events, contractors, etc.)
Water Service Schedule Watermain shut down will typically occur for
approximately 4 hours Boiled water advisories may be required Appropriate notification will be distributed
Maintaining Traffic Roads Closed to Thru Traffic
Local traffic only One-way traffic only
Limited Trips = Increase in Contractor Productivity Reduces duration of inconvenience
Areas of Improvement: Vaughn Road
Improvements to Vaughn Road Roadway will be reconstructed
New water main installationCulvert crossing improvementsDrainage improvements
Ditch enclosure pipe and edge drain Catch basin relocation and/or grading
Consistent 22’ road width 1’- 2’ shoulders
Approximately 6,220 feet
Areas of Improvement: S. Cranbrook Road
Improvements to S. Cranbrook Road Roadway will be reconstructed
New water main installationDrainage improvements
Ditch enclosure pipe and edge drain Catch basin relocation and/or grading
Consistent 22’ road width 1’- 2’ shoulders
Approximately 2,900 feet
Previous Project: Epping Looking North
Pre-Construction Completed
Previous Project: Lone Pine
Pre-Construction Completed
Previous Project: Kensington
Pre-Construction Completed
Drainage Improvements Intent is to preserve and protect the road Will be installed in select locations
Looking for input from residents
Drainage Improvements
S. Cranbrook Road - Christ Church of Cranbrook
Vaughn Road - southwest towards Lahser Road
City Right-of-Way Management Utility Installations
Intent of right-of-way is to provide and maintain public infrastructure
Vehicle SafetyRecovery Zone (Clear Zone/Crash Zone)Lateral Offsets
Recommended 4’ to 5’ lateral offset free from obstructions for low volume low speed roads
City Right-of-Way Management Trees within City ROW may be impacted
In-line with utility improvements Overhanging roadway
Aesthetic improvements within City ROW Intent is “Not To Disturb” Will be placed back to the best of the Contractor’s ability
Examples (Brick paver drives, planting beds, stone mailboxes) Will be placed back to meet minimum City requirements
Examples (Guardrails, Concrete drives)
City Right-of-Way Management
City Right-of-Way Management
City Right-of-Way Management
City Right-of-Way Management
City of Bloomfield Hills Road Improvement Program is Interested in Knowing About?Various Concerns Existing Drainage Problems Utilities Irrigation Systems Lighting, Invisible Dog Fences, Landscaping,
etc. Special Events
Road Improvement Program Contacts City website www.bloomfieldhillsmi.net City Hall 248.644.1520
City Manager Jay Cravens Hubbell, Roth and Clark, Inc.
Jamie Burton, P.E. Associate, LEED AP, CFM 248.454.6363 [email protected]
Melissa Coatta, P.E. Project Engineer 248.454.6567 [email protected]