City of Bloomfield Hills 2015 Road Improvement Program
Transcript
Page 1: City of Bloomfield Hills 2015 Road Improvement Program.

City of Bloomfield Hills

2015

Road Improvement Program

Page 2: City of Bloomfield Hills 2015 Road Improvement Program.

Introductions City Commissioners in Attendance City Staff

Jay Cravens, City ManagerJamie Spivy, DPW Foreman

Hubbell, Roth and Clark, Inc.James Burton, PEMelissa Coatta, PE

Page 3: City of Bloomfield Hills 2015 Road Improvement Program.

Purpose of Meeting Provide an update on the road program Define the scope of the proposed work Review the Construction Schedule, Proposed

Sequencing, & Maintenance of Traffic Plan Answer general questions Opportunity to review work near your home on a

one on one basis

Page 4: City of Bloomfield Hills 2015 Road Improvement Program.

Update Year 9 of the City approved 10 year Road

Improvement Program Vaughn Road and S. Cranbrook Road were

selected for this round of improvements New Water Main Select Drainage Improvements

Page 5: City of Bloomfield Hills 2015 Road Improvement Program.

Disclaimer Plans subject to change due to budgetary

concerns

Page 6: City of Bloomfield Hills 2015 Road Improvement Program.

General Construction IssuesWe aim to minimize:The disruption and inconvenience of constructionIncreased truck traffic

Page 7: City of Bloomfield Hills 2015 Road Improvement Program.

General Construction IssuesWe suggest:Following the proposed detoursAvoid driving through the construction areas (Local Traffic Acceptable)

HRC Field Representative will be available

Page 8: City of Bloomfield Hills 2015 Road Improvement Program.

Underground Installations

Typical Construction

Page 9: City of Bloomfield Hills 2015 Road Improvement Program.

Roadway Grading

Typical Construction

Page 10: City of Bloomfield Hills 2015 Road Improvement Program.

Brick Pavers

Typical Construction

Page 11: City of Bloomfield Hills 2015 Road Improvement Program.

Restoration

Typical Construction

Page 12: City of Bloomfield Hills 2015 Road Improvement Program.

Proposed Schedule Consumers Energy Gas Main Improvements

Not part of City project

Underground (water main, edge drain, storm sewer) Vaughn Road: March 2015 – April 2015 Cranbrook Road: July 2015 – August 2015

Roadwork (to follow underground) Vaughn Road: May 2015 – June 2015 Cranbrook Road: August 2015 – September 2015

Notifications (events, contractors, etc.)

Page 13: City of Bloomfield Hills 2015 Road Improvement Program.

Water Service Schedule Watermain shut down will typically occur for

approximately 4 hours Boiled water advisories may be required Appropriate notification will be distributed

Page 14: City of Bloomfield Hills 2015 Road Improvement Program.

Maintaining Traffic Roads Closed to Thru Traffic

Local traffic only One-way traffic only

Limited Trips = Increase in Contractor Productivity Reduces duration of inconvenience

Page 15: City of Bloomfield Hills 2015 Road Improvement Program.

Areas of Improvement: Vaughn Road

Page 16: City of Bloomfield Hills 2015 Road Improvement Program.

Improvements to Vaughn Road Roadway will be reconstructed

New water main installationCulvert crossing improvementsDrainage improvements

Ditch enclosure pipe and edge drain Catch basin relocation and/or grading

Consistent 22’ road width 1’- 2’ shoulders

Approximately 6,220 feet

Page 17: City of Bloomfield Hills 2015 Road Improvement Program.

Areas of Improvement: S. Cranbrook Road

Page 18: City of Bloomfield Hills 2015 Road Improvement Program.

Improvements to S. Cranbrook Road Roadway will be reconstructed

New water main installationDrainage improvements

Ditch enclosure pipe and edge drain Catch basin relocation and/or grading

Consistent 22’ road width 1’- 2’ shoulders

Approximately 2,900 feet

Page 19: City of Bloomfield Hills 2015 Road Improvement Program.

Previous Project: Epping Looking North

Pre-Construction Completed

Page 20: City of Bloomfield Hills 2015 Road Improvement Program.

Previous Project: Lone Pine

Pre-Construction Completed

Page 21: City of Bloomfield Hills 2015 Road Improvement Program.

Previous Project: Kensington

Pre-Construction Completed

Page 22: City of Bloomfield Hills 2015 Road Improvement Program.

Drainage Improvements Intent is to preserve and protect the road Will be installed in select locations

Looking for input from residents

Page 23: City of Bloomfield Hills 2015 Road Improvement Program.

Drainage Improvements

S. Cranbrook Road - Christ Church of Cranbrook

Vaughn Road - southwest towards Lahser Road

Page 24: City of Bloomfield Hills 2015 Road Improvement Program.

City Right-of-Way Management Utility Installations

Intent of right-of-way is to provide and maintain public infrastructure

Vehicle SafetyRecovery Zone (Clear Zone/Crash Zone)Lateral Offsets

Recommended 4’ to 5’ lateral offset free from obstructions for low volume low speed roads

Page 25: City of Bloomfield Hills 2015 Road Improvement Program.

City Right-of-Way Management Trees within City ROW may be impacted

In-line with utility improvements Overhanging roadway

Aesthetic improvements within City ROW Intent is “Not To Disturb” Will be placed back to the best of the Contractor’s ability

Examples (Brick paver drives, planting beds, stone mailboxes) Will be placed back to meet minimum City requirements

Examples (Guardrails, Concrete drives)

Page 26: City of Bloomfield Hills 2015 Road Improvement Program.

City Right-of-Way Management

Page 27: City of Bloomfield Hills 2015 Road Improvement Program.

City Right-of-Way Management

Page 28: City of Bloomfield Hills 2015 Road Improvement Program.

City Right-of-Way Management

Page 29: City of Bloomfield Hills 2015 Road Improvement Program.

City Right-of-Way Management

Page 30: City of Bloomfield Hills 2015 Road Improvement Program.
Page 31: City of Bloomfield Hills 2015 Road Improvement Program.
Page 32: City of Bloomfield Hills 2015 Road Improvement Program.

City of Bloomfield Hills Road Improvement Program is Interested in Knowing About?Various Concerns Existing Drainage Problems Utilities Irrigation Systems Lighting, Invisible Dog Fences, Landscaping,

etc. Special Events

Page 33: City of Bloomfield Hills 2015 Road Improvement Program.

Road Improvement Program Contacts City website www.bloomfieldhillsmi.net City Hall 248.644.1520

City Manager Jay Cravens Hubbell, Roth and Clark, Inc.

Jamie Burton, P.E. Associate, LEED AP, CFM 248.454.6363 [email protected]

Melissa Coatta, P.E. Project Engineer 248.454.6567 [email protected]