City of Fargo
Mickelson Field Area FloodRisk Management –
Project 5902
Public Information Meeting
November 19, 2012
Overview/Why Are We Here
Discuss Changes Since Last Meeting
Update Project Schedule
Obtain Additional Public Comment
Mickelson Flood Risk Management
Agenda
Past Flood Fight Strategy (i.e. 2009,2010,…)
Assessment of Flood Risk Overview of Project Objectives Recommended Plan
– Changes since July Public Meeting Project Schedule / Financing Questions
Mickelson Flood Risk Management
2009 Spring Flood – Mickelson Area
2009 Spring Flood – Mickelson Area
2010 Spring Flood – Mickelson Area
Existing vs. Preliminary FEMA Floodplain
EXISTING – RS 38.3±
PROPOSED – RS 39.5±
Assessment of Flood Risk
River Stage 25.0ft
River Stage 35.0ft
Assessment of Flood Risk
Oak Street Dike – Action Stage RS 30 –
Inundation 34.6
River Stage 37.0ft
Assessment of Flood Risk
Emergency Dike Closure – Action Stage RS 31 –
Inundation 36.0±
River Stage 38.0ft
Assessment of Flood Risk
River Stage 39.0ft
Assessment of Flood Risk
River Stage 40.0ft
Assessment of Flood Risk
FEMA 100-yr Flood Stage 39.5
River Stage 41.0ft
Assessment of Flood Risk
2009 Spring Flood – RS 40.8
River Stage 42.0ft
Assessment of Flood Risk
River Stage 42.5ft
Assessment of Flood Risk
USACE Recent Evaluation – 1% Flood in Fargo is 42.4?
Reduced Reliance on Temporary Flood Protection
– Clay levees, closures, and etc. Existing Storm Sewer Lift Station
Improvement – Reduce Internal Flooding Potential– Redundant Pumping Capacity
Overview of Project Objectives
Construct Earthen Levee (RS 39.5+4.5’)
Abandon Lift Stations 29, 37, and 38 Construct New Combined Lift Station Storm Sewer Outlet Structure Storm Sewer Improvements Dry Stormwater Pond General Landscaping / Grading Impacts to Existing Park Facility – Fargo
Park District Future Modifications
Recommended Plan
Save Field 2 Relocate Recycle Center Preserving trees in NW Corner of Project
Area
Changes as a Result of July Meeting
Mickelson Flood Risk Management
Mickelson Flood Risk Management
Mickelson Flood Risk Management
Mickelson Flood Risk Management
Recommended Plan– Approximately $4.9 M± (Construction)
Preliminary Funding Plan – FEMA – HMGP Funding – Pending (75%)– Local Cost Share – City (25%)
Project Schedule / Financing
Project Schedule / Financing Schedule
– HMGP Grant Submittal – Recommended Project Design– Public Informational Meeting (7/12)
– Revised Project Design – Public Comments– Final Plans / Specifications / Cost Estimates
– Public Informational Meeting (tonight) Public Comment Period (Until 11/30)
– Right-of-way / Park District Approval (Dec 2012)
– Anticipated Grant Approval (Mar 2013)
– Recommendation to City Commission (Spring 2013?)
– Permitting/Construction Bidding/Award Contract (Spring 2013?)
– Anticipated Construction Begins (TBD – Summer 2013?)
– Anticipated Construction Ends (TBD - Fall 2014?)
Comment Form
Questions / Discussionwww.cityoffargo.com\Engineering
Follow The Project On Twitter
Mickelson Area Flood Risk Management – Project 5949
Mickelson Area Flood Risk Management – Project 5949
Mickelson Area Flood Risk Management – Project 5949
Mickelson Area Flood Risk Management – Project 5949
Mickelson Area Flood Risk Management – Project 5949
Mickelson Area Flood Risk Management – Project 5949
Mickelson Area Flood Risk Management – Project 5949
Mickelson Area Flood Risk Management – Project 5949