City of New Ulm
Request for Council Action
Meeting: City Council - 01 Dec 2020 Agenda Section: REPORTS FROM OFFICERS, BOARDS AND COMMISSIONS
Resolution: N/A Originating Department: Engineering
Ordinance: N/A Prepared By: Joe Stadheim
Attachments: 1 Presented By: Joe Stadheim
Item: Report from the City Engineer regarding the proposed 2021 Capital Improvement Program.
Proposed Action: Adopt the proposed 2021 Capital Improvement Program and acknowledge receiving the Engineer's Report. Board/Commission Recommendation: The proposed 2021 Capital Improvement Program was reviewed by the Safety Commission at their September 3, 2020 meeting and recommended for approval in terms of the Program meeting the City of New Ulm Complete Streets Policy. Overview: Enclosed please find the Engineer’s Report on the proposed 2021 Capital Improvement Program (CIP) which includes a
listing of projects recommended for inclusion in the 2021 CIP. The improvements outlined in this report are necessary, feasible, cost-effective and align with the City’s Complete Streets Policy and the ADA Transition Plan whenever
practical. They have been grouped to enhance constructability and to encourage competitive bidding from multiple contractors. The program includes recommended improvements that are devoted to reconstruction of deficient roadways and utilities, as well as initial improvements. Beginning in 2008, the City had 29 miles of roadway rated in the failed condition (OCI < 28). In the 13 construction seasons since that time, the City has reconstructed 33.5 miles of roadway or an average of 2.6 miles per year. In an attempt to maintain or better the City’s current roadway condition distribution, to take advantage of the current competitive bidding atmosphere and the low cost to borrow money, I recommend that the City Council continue the roadway reconstruction program as presented within the proposed 2021 CIP. If approved and constructed, this CIP will reconstruct 1.7 miles of roadway, removing them from the failed category. A resident outreach meeting was held virtually on October 14, 2020 for those residents that may affected by the proposed 2021 Utility, Street and Alley Improvement Project. This meeting served as an opportunity for residents to ask questions and provide feedback on the proposed projects. A public open house for the proposed 2021 MSAS Improvement Project (North Highland Ave/Boundary Street/CSAH 13) was conducted on November 18, 2020 at the Community Center as an opportunity for residents within the project neighborhood to ask questions and provide feedback on the proposed project. The meeting was conducted by Brown County Highway Department Staff and the City Engineer. Primary Issues/Alternatives to Consider: This report has several sections including one devoted to Special Benefit Methodology. It is believed that when applied, the methodology developed to calculate the special assessments provides an amount that approximates the market value
increase and therefore is an approximate market analysis. In addition, the land will receive a special benefit from the improvement, the assessment will not exceed the special benefit measured by the increase in market value due to the improvement, and the assessment will be uniform as applied to the same class of property in the assessed area. The City Council could receive this report for further review and refinement or could act to approve the recommended Capital Improvement Program as presented or as modified by the Council. Adoption of the proposed 2021 CIP does not obligate the City to construct the listed improvements, as generally the City Council must conduct a Public Hearing, order the improvements and award a contract prior to the commencement of any work within the CIP. Budgetary/Fiscal Issues: The estimated cost of the improvements listed within the attached Capital Improvement Program is $5,265,773.00 with an estimated total bonding need of $2,438,644.00. Attachments: 2021 CIP Presentation 2021 CIP Report
11/19/2020
1
City of New UlmEngineering Department2021 Capital Improvement Program & City Engineer’s Report
2021 Capital Improvement Program (CIP) Agenda
• Recent Roadway Reconstruction History
• Distribution of Pavement Condition
• Categories & Criteria of Potential Improvements
• Proposed 2021 Improvements & Estimated Costs
• Special Benefit and Methodology
• Estimated Special Assessment Amounts
• Projected Three-year CIP Listing
1
2
11/19/2020
2
Roadway Reconstruction Activity History
• 33.5 Miles of Failed Rodway Pavement Reconstructed Since 2008
• Average 2.6 Miles of Reconstructed Roadways Per Year
Construction
Year
Miles
Reconstructed
Dollar Value
(Millions)
Average Cost
Per Mile
(Thousands)
2008 3.9 2.9 743
2009 4.6 3.6 782
2010 2.8 2.0 714
2011 3.1 2.7 871
2012 2.5 3.9 1,560
2013 2.1 2.5 1,190
2014 2.7 3.0 1,111
2015 2.0 2.8 1,423
2016 1.9 2.0 1,031
2017 1.7 2.0 1,143
2018 1.6 1.9 1,187
2019 2.1 5.7 2,730
2020 2.5 5.7 (Est.) 2,280 (Est.)
Summation 33.5 40.7
Distribution of Pavement Condition
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
MIL
ES
YEAR
PAVEMENT CONDITION HISTORY
Failed Marginal Adequate Total Paved
3
4
11/19/2020
3
Categories & Criteria of Potential Improvements
Pavement Condition
Concrete Curb & Gutter
Watermain Needs
Sanitary Sewer Needs
Storm Sewer Needs
ADA Improvements
• OCI used to identify potential candidates
– 0 to 27.99 Failed
– 28 to 65.99 Marginal
– 66 to 100 Adequate
• Evaluate curb & gutter condition
• Study watermain material & history
• Study sanitary sewer condition & history
• Determine if storm sewer extension or modifications are necessary
• Identify necessary ADA improvements
• Alleys are based on OCI & storm sewer needs
5
6
11/19/2020
4
Proposed 2021 Improvements & Estimated Costs
• 2021 Utility, Street & Alley Improvements – Group I
– Jefferson Street from 7th North Street to 12th North Street• Watermain & sanitary sewer reconstruction, storm sewer extension, complete roadway
reconstruction
• Watermain age: 98-year-old cast iron
• Sanitary Sewer age: 84-year-old vitrified clay
• Average OCI: 31.6
• Estimated Cost: $2,488,290
– Washington Street from 4th North Street to 5th North Street• Watermain & Sanitary Sewer reconstruction, storm sewer modifications, complete roadway
reconstruction, pedestrian bump-outs on 5th North Street
• Watermain age: 122-year-old cast iron
• Sanitary Sewer age: 99-year-old vitrified clay
• Average OCI: 39
• Estimated Cost: $481,180
Proposed 2021 Improvements & Estimated Costs
• 2021 Utility, Street & Alley Improvements – Group I
– State Street from 16th South Street to 17th South Street
• Watermain and sanitary sewer main extensions
• Estimated Cost: $83,908
– Maplewood Drive from Red Bud Road to Ryan Road
• Watermain extension and initial roadway improvements
• Completes the Maplewood Drive segment between Garden Street & North Highland Avenue
• Estimated Cost: $577,808
– 20th North Street from Spring Street to Front Street
• Tree clearing in advance of the 2022 20th North Street construction project
• Estimated Cost: $16,500
7
8
11/19/2020
5
Proposed 2021 Improvements & Estimated Costs
• 2021 Utility, Street & Alley Improvements – Group I
– Alley Block 189 North
• Alley from 7th North Street to 8th North Street between Payne Street & Garden Street
• Alley Reconstruction
• Estimated Cost: $40,040
– Alley Block 191 North
• Alley from 9th North Street to 10th North Street between Payne Street & Garden Street
• Alley Reconstruction
• Estimated Cost: $40,040
– Cottonwood River Outfall O-C-23 Repair
• Repair damaged storm sewer outfall
• Estimated Cost: $29,700
Proposed 2021 Improvements & Estimated Costs
• 2021 Utility, Street & Alley Improvements – Group I
– Concrete Sidewalk & ADA Improvements
• Improvements within the 2021 Surface Reconstruction Project
• Reconstruct 32 non-compliant ramps
• Estimated Cost: $128,000
• 2021 MSAS Improvement Project
– CSAH 13 (North Highland Avenue) from CSAH 29 to North Broadway
• Brown County led project
• Roadway improvements, sidewalk, bituminous recreational trail, street lighting
• Estimated City Cost: $350,000
9
10
11/19/2020
6
Proposed 2021 Improvements & Estimated Costs• 2021 Surface Reconstruction Project by City Forces
– 3rd North Street from Garden Street to Washington Street• Average OCI: 5.5• Estimated Cost: $153,120
– 8th North Street from Franklin Street to Washington Street• Average OCI: 8• Estimated Cost: $37,840
– 18th North Street from Broadway to State Street• Average OCI: 11• Estimated Cost: $39,960
– 20th North Street from HWY 14 to North Broadway• Average OCI: 28• Estimated Cost: $146,520
– Franklin Street from 17th North Street to HWY 14• Average OCI: 24• Estimated Cost: $115,280
Proposed 2021 Improvements & Estimated Costs
• 2021 Mn/DOT Project
– Traffic signal & ADA Improvements at 16th North Street & HWY 14
• Estimated City Cost: $176,101
• 2021 Brown County Project
– CSAH 26 (10th South Street) from Broadway to Flandrau State Park
• Mill & Overlay with ADA improvements
• Contingent on the County receiving State Park Road funds
• No City Cost Participation
• 2021 Airport Improvement Project
– Pavement Reconstruction around T-hangars and parking lot
• Estimated Cost: $351,686
11
12
11/19/2020
7
Proposed 2021 Improvements & Estimated Costs
• SUMMARY
– 2021 Utility Street & Alley Improvements – Group I $3,898,266
– 2021 MSAS Improvement Project $350,000
– 2021 Surface Reconstruction Project $489,720
– 2021 Mn/DOT Project $176,101
– 2021 Brown County Project $0
– 2021 Airport Project $351,686
– Summation 2021 CIP $5,265,773
Proposed 2021 Improvements Bonding Needs
• Estimated Dedicated Funding Sources
– PUC Base & Infrastructure Funding, Street Department, MSAS Funding & Airport Funding
– Estimated Summation: $2,913,458
• Projected Bonding Need
– Estimated CIP Cost: $5,265,773
– Less Estimated Dedicated Funding: ($2,913,458)
– Add 0.5% Contingency: $26,329
– Estimated Bond Issuance Cost: $60,000
– Projected Gross 2021 Bonding Need: $2,438,644
13
14
11/19/2020
8
2021 CIP Project Locations
Special Benefit Methodology
• Initial Improvements
– Per existing Development Agreement or if no Agreement assessed on a front foot basis.
– Utilities assessed per existing Development Agreement. Generally 100% assessed to the benefitting property owners.
– Concrete sidewalk & driveways assessed to the adjacent property owners.
– Alley improvements assessed to the adjacent property owners.
• Reconstruction of Existing Improvements
– Reconstructs are assessed at 60% of the cost of a general City street, generally on a per parcel basis.
– Utility reconstruction is generally not specially assessed and paid for PUC Infrastructure Surcharge
– Surface Reconstruction projects assessed at 45% of the reconstruction rate.
– Alley projects are assessed on a front foot basis to the adjacent property owners
15
16
11/19/2020
9
Special Benefit Amounts
• 2021 Utility, Street & Alley Improvements
– Jefferson Street from 7th North Street to 12th North Street
• Assessed on a unit basis – 70 single family parcels at $3,600 rate
• Total assessed amount: $252,000
– Washington Street from 4th North Street to 5th North Street
• Assessed on a unit basis – 11 single family parcels at $3,600 rate
• Total assessed amount: $39,600
– State Street from 16th South Street to 17th South Street
• No assessments assigned. Connection charges will be established and enforced at the time of connection to the watermain and sanitary sewer main.
Special Benefit Amounts
– Maplewood Drive from Red Bud Road to Ryan Road
• Existing Development Agreement assigns the cost the benefitting parcels within Fairhills 6th
Addition and split evenly to the undeveloped property and City park land
• Total assessed amount: $551,429
– 20th North Street from Spring Street to Front Street
• Tree clearing only, no assessments assigned.
– Alley Blocks 189 and 191 North of Center
• Assessed to abutting property on a front foot basis, estimated at $52.00 per front foot.
• Total assessed amount: $40,040
– Cottonwood River Outfall
• No assessments assigned
– Concrete Sidewalk and ADA Improvements
• No assessments assigned
17
18
11/19/2020
10
Special Benefit Amounts
• 2021 MSAS Improvement Project
– North Highland Ave (Boundary Street)• No assessments assigned
• 2021 Surface Reconstruction Project– 3rd North Street from Garden Street to Washington Street
• 30 residential parcels at $1,620 per parcel
• Total assessed amount: $48,600
– 8th North Street from Franklin Street to Washington Street• 7 residential parcels at $1,620 per parcel
• Total assessed amount: $11,340
– 18th North Street from Broadway to State Street• 3 Commercial Properties assigned 2 units each, $3,240 per parcel
• Total assessed amount: $9,720
Special Benefit Amounts
– 20th North Street from HWY 14 to North Broadway• 1 Commercial assigned 3 units and storage building complex assigned 1.4 units
• Total assessed amount: $7,128
– Franklin Street from 17th North Street to 20th North Street• 9 residential parcels, 6 units assigned for North Park, 9 commercial units
• Total assessed amount: $38,880
• 2021 Mn/DOT Project
– No assessments assigned
• 2021 Brown County Project
– No assessments assigned
• 2021 Airport Project– No Assessments assigned
19
20
11/19/2020
11
Special Benefit Amounts Summary
ProjectEstimated Project
CostEstimated Special
Assessments
2021 Utility, Street & Alley Improvements $3,898,266.00 $923,109.00
2021 MSAS Improvement Project $350,000.00 $0.00
2021 Surface Reconstruction Project $489,720.00 $115,668.00
2021 Mn/DOT Project $176,101.00 $0.00
2021 Brown County Project $0.00 $0.00
2021 Airport Project $351,686.00 $0.00
Summation 2021 CIP $5,265,773.00 $1,038,777.00
Proposed 3-Year Project Listing - 2022
• 2022 Utility, Street & Alley Improvements
– German Street from 7th North Street to 12th North Street
– Oakwood Avenue from Boettger Avenue to Milford Street
– Alley Block 190 North
– Alley Block 196 North
– Alley Block 94 North
– Alley Block 174 South
– Sewer Spot Repair at 19th North & State
– Concrete Sidewalk and ADA Improvements
• Total Estimated Cost (2020 Dollars): $3,548,160
21
22
11/19/2020
12
Proposed 3-Year Project Listing - 2022• 2022 MSAS Improvement Project
– 20th North Street from North Broadway to Front Street and Front Street from 19th North Street to 20th North Street• Estimated Cost (2020 Dollars): $1,700,965
• 2022 Surface Reconstruction Project by City Forces– 19th North Street from Broadway to Franklin Street
– Franklin Street from 16th North Street to 17th North Street
– Franklin Street from 12th North Street to 14th North Street
– Payne Street from 16th North Street to North Terminus
– 17th North Street from Franklin Street to Jefferson Street
– 10th South Street from Summit Avenue to Roslyn Road
– Roslyn Road from 10th South Street to South Terminus
– 12th South Street from Valley Street to German Street• Estimated Cost (2020 Dollars): $476,124
• Estimated Total 2022 CIP: $5,725,249
2022 CIP Project Locations
23
24
11/19/2020
13
Proposed 3-Year Project Listing - 2023
• 2023 Utility, Street & Alley Improvements
– Bridge Street from Cottonwood Street to Tower Road
– Alley Block 77 North
– Alley Block 97 South
– Alley Block 96 South
– Alley Block 93 South
– Concrete Sidewalk and ADA Improvements• Total Estimated Cost (2020 Dollars): $3,260,160
• 2023 MSAS Improvement Project
– North Highland Avenue from Oak Street to HWY 14
– North Broadway from 20th North Street to CSAH 13/North Highland Avenue• Estimated Cost (2020 Dollars): $1,182,754
Proposed 3-Year Project Listing - 2023• 2023 Surface Reconstruction Project by City Forces
– German Street from 19th North Street to 20th North Street
– German Street from 12th South Street to 16th South Street
– 10th South Street from Valley Street to Front Street
– 12th South Street from Minnesota Street to German Street
– 8th South Street from Valley Street to Front Street
– 7th South Street from Railroad Tracks to Front Street
– 5th South Street from Valley Street to Front Street
– 6th South street from Broadway to German Street
• Estimated Cost (2020 Dollars): $454,0080
• Estimated Total 2023 CIP: $4,896,994
25
26
11/19/2020
14
2023 CIP Project Locations
Discussion, Comments and QuestionsThank You!
27
28
1
City of New Ulm Office of the City Engineer
100 North Broadway Telephone: (507)-359-8380
New Ulm, MN 56073 Fax: (507)-359-8306 Email: [email protected]
TO: Honorable Mayor and City Council FROM: Joseph E. Stadheim, P.E., City Engineer DATE: November 20, 2020 SUBJECT: ENGINEER’S REPORT ON THE PROPOSED 2021 CAPITAL
IMPROVEMENT PROGRAM (CIP) This report has been prepared as a planning tool and recommends various capital improvement projects as candidates for construction. Additionally, the intention of this report is to further advise the City Council in a preliminary way as to whether the proposed improvement is necessary, cost-effective, and feasible; whether it should best be made as proposed or in connection with some other improvement; to provide a reasonable estimate of the total amount of benefit to be specially assessed; and a description of the methodology used to calculate individual assessments for affected parcels. This report has the following sections and addendums: Section I. Project Description and Summary of Preliminary Estimated Cost Section II. Funding Sources and Projected Bonding Need Section III. Roadway, Utility and Other Reconstruction Categories/Criteria Section IV. City of New Ulm Complete Streets Policy Section V. Necessity, Cost-Effectiveness and Feasibility Section VI. Special Benefit Methodology Section VII. Estimated Special Assessment Amounts
Section VIII. Projected Three-Year (2021, 2022 and 2023) Capital Improvement Listing
Addendum No. 2021 Project Description and Detailed Basis of Estimated Cost The following Projects are recommended as viable candidates for 2021 construction: Section I. Project Description and Summary of Preliminary Estimated Cost.
A. 2021 Utility, Street and Alley Improvements – Group I. This group of work includes
improvements that have been petitioned for and/or ordered in by the City Council, as well as other improvements that should be considered as potential construction candidates. The improvements and associated estimates of cost that I recommend for consideration are as follows:
2
i. Jefferson Street from 7th North Street to 12th North Street. This project consists of the reconstruction of the existing watermain, sanitary sewer main, sewer and water end services and reconstruction of the existing roadway section including excavation and replacement of subgrade, aggregate base, bituminous paving, pavement subdrains, storm sewer extension and inlet structure reconstruction, concrete curb and gutter, pedestrian sidewalk ramps, street lighting and selective replacement of concrete driveway pavement and sidewalk. Estimated Cost: $2,488,290.00
ii. Washington Street from 4th North Street to 5th North Street. This project consists of the reconstruction of the existing watermain, sanitary sewer main, sewer and water end services and reconstruction of the existing roadway section including excavation and replacement of subgrade, aggregate base, bituminous paving, pavement subdrains, storm sewer modification and inlet structure reconstruction, concrete curb and gutter, pedestrian sidewalk ramps, street lighting and selective replacement of concrete driveway pavement and sidewalk. Estimated Cost: $481,180.00
iii. State Street from 16th South Street to 17th South Street. This project consists of the extension of watermain and sanitary sewer main. Estimated Cost: $83,908.00
iv. Maplewood Drive from Red Bud Road to Ryan Road. This project consists of watermain extension, sewer and water end services, grading, aggregate base, bituminous base, concrete curb and gutter, concrete sidewalk, concrete driveway pavement, bituminous surfacing, boulevard trees, boulevard restoration and street lighting.
Estimated Cost: $577,808.00
v. 20th North Street Tree Clearing. This project consists of tree removal in the
anticipated construction limits for the 2022 20th North Street construction project. Estimated Cost: $16,500.00
vi. Alley Block 189 North of Center Street.
Alley from 7th North Street to 8th North Street between Garden Street and Payne Street. This project consists of the reconstruction of the existing alley pavement section including grading, aggregate base, bituminous surfacing,
3
seven inch (7”) concrete alley approach pavement, underdrain, miscellaneous removals and restoration.
Estimated Cost: $40,040.00
vii. Alley Block 191 North of Center Street.
Alley from 9th North Street to 10th North Street between Garden Street and Payne Street. This project consists of the reconstruction of the existing alley pavement section including grading, aggregate base, bituminous surfacing, seven inch (7”) concrete alley approach pavement, underdrain, miscellaneous removals and restoration.
Estimated Cost: $40,040.00
viii. Cottonwood River Outfall O-C-23 Repair. This project consists of repairing a damaged storm sewer outfall and stabilizing the riverbank at the outfall. Estimated Cost: $29,700.00
ix. Concrete Sidewalk and ADA Improvements.
This project consists of ADA pedestrian ramp improvements to compliment the improvements scheduled within the 2021 Surface Reconstruction Project to meet the current ADA requirements as per New Ulm’s adopted ADA Transition Plan. Estimated Cost: $140,800.00
Summation of Estimated Cost 2021 Utility, Street & Alley Improvements – Group I $3,898,266.00
B. 2021 MSAS Improvement Project. This group of work includes improvements on
roadway segments and bridges currently on New Ulm’s Municipal State Aid System (MSAS) except as noted.
i. CSAH 13 (North Highland Avenue) from CSAH 29 to North Broadway. This
project consists of the removal of the existing bituminous pavement, storm sewer modifications, grading, aggregate base, bituminous base, concrete curb and gutter, concrete sidewalk, bituminous recreational trail, concrete driveway pavement, bituminous surfacing, boulevard restoration and street lighting.
Note: This is a Brown County led project with City participation for the concrete sidewalks, recreational trail and street lighting.
4
Estimated City Cost 2021 MSAS Improvement Project $350,000.00
C. 2021 Surface Reconstruction Project by City Forces. This group of work includes
improvements on roadway segments by the City Public Works Department. Improvements include removal of existing bituminous pavement, reshaping the existing gravel base, repave with four inches (4”) of bituminous surfacing (unless noted otherwise) and selective replacement of concrete curb and gutter at the following locations:
i. 3rd North Street from Garden Street to Washington Street (4 Blocks)
Estimated Cost: $153,120.00
ii. 8th North Street from Franklin Street to Washington Street (1 Block)
Estimated Cost: $37,840.00
iii. 18th North Street from Broadway to State Street (1 Block)
Estimated Cost: $36,960.00
iv. 20th North Street from HWY 14 to North Broadway (3 Blocks)
a. Repave with 6” of Bituminous Surfacing
Estimated Cost: $146,520.00
v. Franklin Street from 17th North Street to HWY 14 (3 Blocks)
Estimated Cost: $115,280.00
Summation of Estimated Cost 2021 Surface Reconstruction Project by City Forces $489,720.00
D. 2021 Mn/DOT Project. This group of work includes traffic signal and ADA sidewalk
improvements to the signal system and sidewalk network at the intersection of 16th North Street and US HWY 14. The estimated City contribution will be for half of the traffic signal system only.
Estimated City Cost 2021 Mn/DOT Project $176,101.00
E. 2021 Brown County Project. This group of work includes improvements on roadway segments and bridges currently on Brown County’s County State Aid System (CSAH) that are within the New Ulm Corporate Limits.
5
i. CSAH 26 (10th South Street) from Broadway to Flandrau State Park. This project consists of bituminous mill and overlay and ADA sidewalk improvements. This project is contingent on the County receiving State Park Road funds. The City will not have a cost participation on this project.
Estimated City Cost 2021 Brown County Project $0.00
F. 2021 Airport Project. This group of work includes improvements to the bituminous pavement around the T-Hangars and Terminal Building parking lot area. The estimated project contract cost does not include project engineering, inspection materials testing and administration services which will be paid from the City Airport Budget.
Estimated Contract Cost 2021 Airport Project $351,686.00
SUMMARY OF SECTION I – PRELIMINARY ESTIMATED COST FOR 2021 CIP
A. 2021 Utility, Street & Alley Improvements – Group I $3,898,266.00 B. 2021 MSAS Improvement Project $350,000.00 C. 2021 Surface Reconstruction Project by City Forces $489,720.00 D. 2021 Mn/DOT Project $176,101.00 E. 2021 Brown County Project $0.00 F. 2021 Airport Project $351,686.00
SUMMATION 2021 CIP $5,265,773.00
Section II. Funding Sources and Projected Bonding Need
A. Summation of Estimated Dedicated Funding Sources
PUC Water Department Rate Base Funding $400,000.00 PUC Wastewater Department Rate Base Funding $400,000.00 City Sewer & Water Infrastructure Fund $630,000.00 Street Department Funding (ADA) $100,000.00 Street Department Funding (Surface Reconstruction) $489,720.00 MSAS Funding (CSAH 13/North Highland Ave) $350,000.00 MSAS Funding (Mn/DOT Traffic Signal) $176,101.00 Airport Funding (T-Hangar Pavement) $367,637.00
Summation of Estimated Dedicated Funding $2,913,458.00
B. Projected Bonding Need
Estimated CIP Cost $5,265,773.00
6
Less Estimated Dedicated Funding ($2,913,458.00) Add 0.5% Contingency (materials testing, etc.) $26,329.00 Add Estimated Cost to Issue Bond $60,000.00
PROJECTED GROSS 2021 BONDING NEED $2,438,644.00
Section III. Roadway, Utility and Other Reconstruction Categories/Criteria
A. Paved Roadways
The City utilizes a pavement management system (ICON) to rate all of the paved municipal roadways and alleys within the City. The system includes a computerized inventory or data base of each roadway and alley segment which contains current and historical information relative to the segment. The inventory is updated by physically inspecting (surveying) one-third of the City’s roadways or alleys every year. The survey identifies the type of distress present on all pavement sections and determines the severity and quantity of each distress. When the survey information is entered into the program, the pavement management system assigns each segment an Overall Condition Index (OCI) rating on a scale of 0 to 100 with 0 being the worst and 100 the best. The roadway and alley segments are further categorized according to their OCI as follows:
OCI 0 to 27.99 (Failed) OCI 28 to 65.99 (Marginal) OCI 66 to 100 (Adequate)
Failed segments are considered as candidates for reconstruction. Marginal segments are considered as candidates for either reconstruction or overlay, depending upon several other factors and adequate segments are scheduled to receive normal surface treatment and maintenance, such as crack sealing and seal coating.
7
Recent History of Roadway Reconstruction Activity Construction
Year Miles
Reconstructed Dollar Value
(Millions) Average Cost Per Mile (Thousands)
2008 3.9 2.9 743 2009 4.6 3.6 782 2010 2.8 2.0 714 2011 3.1 2.7 871 2012 2.5 3.9 1,560 2013 2.1 2.5 1,190 2014 2.7 3.0 1,111 2015 2.0 2.8 1,423 2016 1.9 2.0 1,031 2017 1.7 2.0 1,143 2018 1.6 1.9 1,187 2019 2.1 5.7 2,730 2020 2.5 5.7 (Est.) 2,280 (Est.)
Summation 33.5 40.7
Distribution of Pavement Condition Beginning January 1st
Failed (Miles)
Marginal (Miles)
Adequate (Miles)
Total Paved (Miles)
2010 30.70 10.22 40.73 81.65 2011 28.70 9.53 43.52 81.75 2012 26.04 10.22 45.38 81.64 2013 27.53 10.54 43.81 81.88 2014 25.65 10.54 45.98 82.17 2015 20.20 14.56 48.29 83.05 2016 19.41 16.47 47.65 83.53 2017 15.72 18.44 50.07 84.23 2018 14.35 18.19 52.16 84.70 2019 14.53 19.15 51.62 85.30 2020 10.40 25.19 50.03 85.62 2021 10.29 25.28 51.96 87.53
B. Concrete Curb and Gutter
Criteria used to determine when concrete curb and gutter should be reconstructed include the following:
i. Poor overall condition ii. Settled, tipped or uneven segments iii. Roadway grade changes iv. Sanitary Sewer and water end service construction v. Underground utility reconstruction that impacts or undermines the existing
concrete curb and gutter
8
C. Alleys Alleys are considered as candidates for reconstruction when their Overall Condition Index (OCI) falls into the failed category (OCI<28) of the Pavement Management System and/or by the recommendation of the Street Department personnel based on the time, effort and cost needed to maintain the existing bituminous or concrete surface.
D. Watermain
Criteria used to determine when watermain should be reconstructed include the following:
i. Transite pipe ii. Lead water services iii. Cast iron pipe with lead joints iv. Segments of pipe that have a history of breakage and/or have corrosive soil
conditions v. Segments of inadequate domestic or fire flow
E. Sanitary Sewer Main
Criteria used to determine when sanitary sewer main should be reconstructed include the following:
i. Pipe that is undersized to carry existing or future peak flows ii. Pipe that has cracking or other structural deficiencies iii. Pipe that has sags, misaligned joints, deposits or other obstructions iv. Pipe that has severe tree root invasion v. Pipe systems that allow inflow and/or infiltration vi. Aged clay pipe
F. ADA Improvements
In 2018, the City completed an ADA Transition Plan which was adopted by the City Council on June 4, 2019. The development of the Plan included an inventory and evaluation of pedestrian facilities within the public right-of-way. The City of New Ulm will use two methods for upgrading pedestrian facilities to the current ADA standards. The first and most comprehensive of the two methods are the scheduled street and utility improvement projects. The pedestrian facilities impacted by these projects will be upgraded to current ADA accessibility standards whenever feasible. The second method includes standalone sidewalk and ADA accessibility improvement projects. These projects will be incorporated into the CIP on a case by case basis or may be completed by internal City forces as recommended by the City of New Ulm staff and ordered by the City Council.
9
Section IV. City of New Ulm Complete Streets Policy Introduction
Complete streets is a transportation network approach that considers the needs of pedestrians, bicyclists, transit users, motorists, commercial and emergency vehicles, hereby referred to as all users. The goal of complete streets is a transportation system that is accessible, equitable and adapted to serve the needs of individuals regardless of how they choose to travel. Vision and Purpose The City of New Ulm's Complete Streets Policy will assist in the establishment of transportation corridors that are safe, functional, encourage active transportation and aesthetically attractive for all users. This Policy will help guide decision makers in planning, designing and constructing transportation networks to reasonably accommodate all anticipated users. Policy The City of New Ulm will consider the safety and accessibility of users of all abilities and transportation modes through the design, operation and maintenance of the transportation network. This approach will help create a connected network of facilities that accommodates each method of transportation that is consistent with and supportive of the local community. The Policy recognizes that streets are different and the needs of various users will be considered in a balanced and flexible manner. Transportation network improvements may include facilities and amenities that contribute to Complete Streets. This includes but is not limited to street and sidewalk lighting, sidewalk and pedestrian ramp construction and bicycle infrastructure improvements. Early consideration of all transportation modes will be important for this policy to succeed. Those that plan and design roadway improvement projects will give consideration to all users from the beginning of the planning and design process to its conclusion. This will require interested individuals and groups to provide input through the New Ulm Safety Commission at least 6 months in advance of the yearly Capital Improvement Program development process. The project development process will include consideration of the land use and transportation context of the project along with relevant information from the Comprehensive Plan for the City of New Ulm. Gaps and deficiencies in the transportation network for various user groups will be considered and an assessment made of the tradeoffs necessary to balance those needs. Review and input from the City's Safety Commission and other interested individuals or groups will be taken into consideration during the project development process. Factors that may be given high priority include whether:
10
The corridor provides primary access to a significant destination such as parks,
recreation centers, schools, shopping centers, health care facilities, grocery stores or employment centers;
The corridor provides primary access across a natural or manmade barrier such as a river or highway;
The corridor is in an area where a high amount of active transportation and pedestrian traffic can be anticipated;
A road corridor provides important continuity or connectivity links for the existing recreational trail network; or
Nearby routes that provide a similar level of convenience and connectivity already exist.
A Complete Streets segment may be achieved through a single improvement project or through a series of improvement projects over a period of time.
Section V. Necessity, Cost-Effectiveness and Feasibility The City’s pavement management system ratings and visual inspection clearly
indicate that the recommended roadway reconstruction segments are in need of reconstruction. The ADA Improvements have been scheduled according to the implementation methodology outlined within the City of New Ulm ADA Transition Plan intended to meet the requirements of Title II of the Americans with Disabilities Act (ADA) of 1990.
The underground utility reconstruction is recommended as a systematic method to
replace old, undersized or obsolete watermain and sanitary sewer main piping and materials, as well as pipe segments prone to breakage or infiltration. Storm sewer extensions are recommended when mandated to accommodate additional impervious surface, or when cost effective to eliminate storm water drainage problems and vehicular hazards created by pavement cross-gutters. Storm water quality ponds or other treatment facilities are required to meet NPDES or MPCA Stormwater Regulations and must be maintained to their original dimensional design standard. The balance of the recommended improvements have been petitioned for by adjoining property owners, have been contemplated within inplace Development Agreements, have been requested by Developers, property owners, or City Departmental personnel along with a corresponding budget appropriation. Therefore, I believe that all of the recommended improvements are necessary. In addition, the improvements outlined in this report are feasible and have been grouped to enhance constructability and to encourage competitive bidding from multiple contractors, which ultimately provides for a cost-effective Capital Improvement Program.
Section VI. Special Benefit and Methodology
A. Initial Improvement
11
i. Roadway Improvements. The benefit for initial roadway improvements is normally assessed according to an inplace Development Agreement for the area of development. Without an Agreement, the City’s policy is to assess the benefit of the initial roadway improvements at the cost of a normal City street which is currently estimated to be $200.00 per foot per side, which includes concrete curb and gutter and 10% for administration and engineering services. In the case of very narrow or very wide parcel front footage, a minimum and/or maximum benefit or a unit value of benefit may be assigned.
ii. Utility Improvements. The benefit for the initial utility improvements is normally assessed according to an inplace Development Agreement for the area of development. Generally, 100% of the cost of the improvements is assessed to the benefiting properties. The cost of sewer and water end services are assessed to the benefiting property.
iii. Concrete Sidewalk and Driveway Improvements. It has been customary to
assign the benefit associated with concrete sidewalk and driveway improvements to the adjacent property owners as the contract unit cost of the improvements plus an allowance for administration and engineering multiplied by the area of concrete sidewalk and driveway construction. The concrete driveway pavement normally extends through the sidewalk area.
iv. Alley Improvements. It has been customary to assign the benefit associated
with alley improvements to the abutting property owners regardless of access on a front foot basis as the contract cost of a normal improvement plus an allowance for contract administration and engineering. Special benefit for improvements within a T-alley configuration will be assigned on a case-by-case basis and may be assigned on a unit basis.
B. Reconstruction of Existing Improvements
i. Roadway Reconstruction.
The policy utilized to assign benefit for roadway reconstruction improvements is based on City Council Resolutions No. 88-50 and No. 90-35. Resolution No. 88-50 resolved that the City shall reassess the cost of reconstruction of streets at 60% of the cost of a general City street. Resolution No. 90-35 established a unit assessment policy for each buildable residential parcel. Non-residential properties are either assigned incremental benefit or may be assessed for 60% of the reconstruction cost for general City streets or 60% of the cost of the actual project, whichever is less, on a front foot basis, but will not be specially assessed less than the single family residential rate per parcel. In some cases, the benefit assigned to a larger non-residential parcel may be capped at a maximum amount.
12
I recommend that the City Council continue the policy of assigning the benefit of roadway reconstruction on a unit basis to each single family residential parcel at a rate of $3,600.00 per parcel. The average estimated cost to reconstruct a general City street in 2021 is $320.00 per centerline foot, or $160.00 per foot per side. 60% of $160.00 is $96.00. The residential assessment rate using the normal 50 foot wide frontage is then $96.00 x 50 f.f. = $4,800.00. I believe that the $4,800.00 amount per residential parcel would not be supported by an economic analysis and therefore, I recommend that the $4,800.00 amount be reduced to $3,600.00 per residential parcel. The $3,600.00 per parcel rate should be considered the minimum benefit associated with roadway reconstruction and does not include any benefit associated with curb and gutter reconstruction, driveway, sidewalk and/or other requested improvements. If a residential parcel has frontage on two (2) intersecting streets and both roadways are being reconstructed in the same construction season as part of the same or separate projects, the parcel will typically be specially assessed on both sides, one side at the full reconstruction rate and the other side at 60% of the full reconstruction rate. If a parcel has frontage on two (2) intersecting streets and has been specially assessed in the past ten (10) years for a roadway improvement or a reconstruction project excluding a surface reconstruction project on a front yard basis, a side yard calculation may be applied to the adjoining side at 60% of the current reconstruction assessment rate. Each unit of a twin home or duplex is assessed at 75% of the current reconstruction assessment rate on the front yard side. Multi-unit residential facilities are assigned incremental benefit depending on the number of units.
ii. Underground Utility Reconstruction.
Reconstructed sanitary sewer and watermain are typically not specially assessed as the City infrastructure charge paid by each residential unit on the monthly PUC bill is used to partially fund main reconstructions.
iii. Surface Reconstruction and Overlays by City Forces.
The special benefit and methodology discussed in this paragraph is for surface reconstruction and overlay improvements constructed by the City Street Department. Surface reconstruction generally consists of removing the existing bituminous pavement, reshaping the gravel base and repaving with four inches (4”) of bituminous surfacing. The work may include selective replacement of concrete curb and gutter and minor subgrade correction. The average cost of surface reconstruction per centerline foot is approximately 45% of the cost to reconstruct a general City Street.
13
Therefore, I recommend that the benefit specially assessed for surface reconstruction be 45% of the full reconstruction rate of $3,600.00 which would be $1,620.00 assigned on a residential unit basis while assigning incremental benefit to larger, non-residential parcels. The $1,620.00 per parcel rate should be considered the minimum benefit associated with surface reconstruction and does not include any benefit associated with curb and gutter reconstruction or subgrade correction. The full rate is applied to subdivided or half lots on side streets. Side yard calculations are not applied to corner lots when assessing surface reconstruction projects. Overlays constructed by City forces are not typically assessed.
iv. Alley Reconstruction.
The benefit associated with alley reconstruction will be assigned to the abutting property owners regardless of access on a front foot basis as the contract cost of a normal reconstruction plus an allowance for contract administration and engineering.
v. Sidewalk Reconstruction.
The benefit associated with sidewalk reconstruction will be assigned to the adjacent property owners as the contract unit cost of the improvements plus an allowance for administration and engineering multiplied by the area of concrete sidewalk reconstruction. In some cases, the City Council may order the reconstruction of existing concrete sidewalk as a means to resolve a safety hazard. If the existing sidewalk was previously constructed by the City’s contractor, is less than ten (10) years old, and has a ¾” vertical displacement and/or more than a one inch longitudinal (1”) gap, the cost of the sidewalk reconstruction will not typically be assessed. Sidewalk is generally not reconstructed to resolve a perceived aesthetic or cosmetic defect.
Section VII. Estimated Special Assessment Amounts
A. 2021 Utility, Street and Alley Improvements – Group I Project
i. Jefferson Street from 7th North Street to 12th North Street. The development along this five-block segment of Jefferson Street is residential. The benefit of the roadway reconstruction improvement from 7th North Street to 12th North Street will be specially assessed on a unit basis of $3,600.00 to each residentially zoned parcel abutting the project. If each parcel were assessed according to this methodology, the estimate of the amount to be specially assessed would be 70 single family parcels at $3,600.00 per parcel for a total assessment amount of $252,000.00.
14
ii. Washington Street from 4th North Street to 5th North Street. The development along this one-block segment of Washington Street is residential. The benefit of the roadway reconstruction improvement from 4th North Street to 5th North Street will be specially assessed on a unit basis of $3,600.00 to each residentially zoned parcel abutting the project. If each parcel were assessed according to this methodology, the estimate of the amount to be specially assessed would be 11 single family parcels at $3,600.00 per parcel for a total assessment amount of $39,600.00
iii. State Street from 16th South Street to 17th South Street. No special assessments will be assigned. Connection charges will be established and enforced at the time of connection to the watermain and sanitary sewer main.
iv. Maplewood Drive from Red Bud Road to Ryan Road. The improvements proposed for Maplewood Drive are being undertaken according to the in place Development Agreement for Fairhills Sixth Addition.
In terms of Special Assessments for uncompleted improvements, the Development Agreement stipulates that the cost of the Public Improvements plus an allowance for contract administration and engineering will be assigned as benefit and specially assessed to the 6 platted lots within the subdivision abutting the improvements and evenly assigned to the undeveloped property to the south which includes City park land. The estimate of the total amount specially assessed for the Public Improvements to serve Maplewood Drive is $551,429.00 adjusted according to the final actual project cost plus allowance.
v. 20th North Street Tree Clearing. The improvements recommended for the tree clearing along 20th North Street prior to the scheduled 2022 MSAS Improvement project are to avoid contract time restrictions. No special assessments will be assigned.
vi. Alley Block 189 North of Center Street. The benefit of this residential alley reconstruction will be specially assessed to the abutting property on a front foot basis. The estimated project cost and benefit is $52.00 per front foot per side. The estimate of the total amount to be assessed is $40,040.
vii. Alley Block 191 North of Center Street. The benefit of this residential alley reconstruction will be specially assessed to the abutting property on a front foot basis. The estimated project cost and benefit is $52.00 per front foot per side. The estimate of the total amount to be assessed is $40,040.
15
viii. Cottonwood River Outfall O-C-23 Repair. The improvements recommended for repairing a damaged storm sewer outfall and stabilizing the riverbank at the outfall where it discharges into the Cottonwood River.
No special assessments will be assigned.
ix. Concrete Sidewalk and ADA Improvements. No special assessments will
be assigned. Subtotal 2021 Utility, Street and Alley Improvements – Group I Estimated Special Assessments $923,109.00
B. 2021 MSAS Improvement Project
i. CSAH 13 (North Highland Avenue) from CSAH 29 to North Broadway.
Note: This is a Brown County led construction project with City participation for sidewalk, recreational trail and street lighting construction. No special assessments will be assigned.
Subtotal 2021 MSAS Improvement Project Estimated Special Assessments $0.00
C. 2021 Surface Reconstruction Project by City Forces. The benefit of the Surface Reconstruction by City Forces will be specially assessed at the rate of $1,620.00 per residential parcel to the adjacent property while assigning incremental benefit to larger non-residential parcels estimated as follows:
i. 3rd North Street from Garden Street to Washington Street (4 Blocks) 30 Residential Parcels x $1,620.00 per parcel = $48,600.00
ii. 8th North Street from Franklin Street to Washington Street (1 Block) 7 Residential Parcels x $1,620.00 per parcel = $11,340.00
iii. 18th North Street from Broadway to State Street (1 Block) 6 Units x $1,620.00 per unit = $9,720.00 Note: Units are assigned as follows: 2 Units – JP Plumbing & Heating Parcel 2 Units – Rooms and Rest Furniture Parcel 2 Units – Robert Seifert CPA Parcel 6 Units Total
16
iv. 20th North Street from HWY 14 to North Broadway (3 Blocks)
4.4 Units x $1,620.00 per unit = $7,128.00 Note: Units are assigned as follows: 3 Units – UCU Inc. Complex
7 Units assigned at 20% for the Storage Solutions of New Ulm Association for a total of 1.4 Units 4.4 Units Total
v. Franklin Street from 17th North Street to 20th North Street (3 Blocks)
24 Units x $1,620.00 per unit = $38,880.00 Note: Units are assigned as follows: 17th North Street to 19th North Street 9 Units – 9 Residential Parcels 6 Units – North Park 19th North Street to HWY 14 3 Units – 3 Commercial Parcels 2 Units – Bode Collision Parcel 2 Units – Little Rascals Parcel 2 Units – Brown County License Bureau Parcel
24 Units Total Subtotal 2021 Surface Reconstruction Project Estimated Special Assessments $115,668.00
D. 2021 Mn/DOT Project. Traffic signal replacement and ADA improvements at the intersection of 16th North Street and HWY 14 (Broadway).
No special assessments will be assigned. Subtotal 2021 Mn/DOT Project Estimated Special Assessments $0.00
E. 2021 Brown County Project. CSAH 26 (10th South Street) from Broadway to
Flandrau State Park mill and overlay and ADA sidewalk improvements.
No special assessments will be assigned. Subtotal 2021 Brown County Project Estimated Special Assessments $0.00
17
F. 2021 Airport Improvement Project. Pavement reconstruction at T-Hangars and Terminal parking lot.
No special assessments will be assigned. Subtotal 2021 Airport Improvement Project Estimated Special Assessments $0.00
SUMMARY OF SECTION VII – ESTIMATED SPECIAL ASSESSMENT AMOUNTS
Project Estimated
Project Cost Estimated Special
Assessments
2021 Utility, Street & Alley Improvements $3,898,266.00 $923,109.00
2021 MSAS Improvement Project $350,000.00 $0.00
2021 Surface Reconstruction Project $489,720.00 $115,668.00
2021 Mn/DOT Project $176,101.00 $0.00
2021 Brown County Project $0.00 $0.00
2021 Airport Project $351,686.00 $0.00
Summation 2021 CIP $5,265,773.00 $1,038,777.00
18
Section VIII. Projected Three-Year Capital Improvement Plan Listing YEAR 2021 - 2021 Utility, Street and Alley Improvement – Group I Project
Jefferson Street from 7th North Street to 12th North Street o Watermain, sanitary sewer main, roadway reconstruction, storm sewer
extension and ADA improvements Washington Street from 4th North Street to 5th North Street
o Watermain construction, sanitary sewer and roadway reconstruction and ADA improvements
State Street from 16th South Street to 17th South Street o Watermain and sanitary sewer main extensions
Maplewood Drive from Red Bud Road to Ryan Road o Construct watermain, sewer and water end services, roadway and sidewalk
improvements 20th North Street Tree Clearing Alley Block 189 North of Center Street
o 7th North Street to 8th North Street between Garden Street & Payne Street – Alley reconstruction
Alley Block 191 North of Center Street o 9th North Street to 10th North Street between Garden Street & Payne Street –
Alley reconstruction Cottonwood River Outfall O-C-23 Repair Concrete Sidewalk & ADA Improvements
o To fulfill the 2021 Surface Reconstruction Project ADA requirements Estimated Cost: $3,898,266.00
2021 MSAS Improvement Project (led by Brown County) North Highland Avenue (CSAH 13) from CSAH 29 to North Broadway
o Roadway improvements, storm sewer modifications, sidewalk & trail construction
Estimated Cost (City Portion): $350,000.00 2021 Surface Reconstruction Project (City Forces)
3rd North Street from Garden Street to Washington Street (4 Blocks) 8th North Street from Franklin Street to Washington Street (1 Block) 18th North Street from Broadway to State Street (1 Block) 20th North Street from US HWY 14 to North Broadway (3 Blocks) Franklin Street from 17th North Street to US HWY 14 (3 Blocks) Estimated Cost: $489,720.00
2021 Mn/DOT Project US Highway 14 at 16th North Street Traffic Signal & ADA Improvements Estimated Cost (City Portion): $176,101.00
2021 Brown County Project 10th South Street (CSAH 26) from Broadway to Flandrau Park
o Mill & Overlay with ADA Improvements Estimated Cost (City Portion): $0.00
2021 Airport Project Pavement Reconstruction at T-Hangars and Terminal Parking Lot
Estimated Cost: $351,686.00 Estimated Total Cost 2021 CIP: $5,265,773.00
19
YEAR 2022 2022 Utility, Street and Alley Improvement – Group I Project
German Street from 7th North Street to 12th North Street o Watermain, sanitary sewer main, roadway reconstruction, storm sewer
extension and ADA improvements Oakwood Avenue from Boettger Avenue to Milford Street
o Roadway reconstruction, select concrete curb and gutter and driveway apron reconstruction
Alley Block 190 North of Center Street o 8th North Street to 9th North Street between Garden Street & Payne Street
– Alley Reconstruction Alley Block 196 North of Center Street
o 14th North Street to 15th North Street between Garden Street & Payne Street – Alley Reconstruction
Alley Block 94 North of Center Street o 11th North Street to 12th North Street between Broadway & State Street –
Alley Reconstruction Alley Block 174 South of Center Street
o 7th South Street to 8th South Street between Payne Street & Jefferson Street – Alley Reconstruction
Sanitary Sewer Spot Repair o Repair separated pipe at 19th North and State Street
Concrete Sidewalk & ADA Improvements o To fulfill the 2022 Surface Reconstruction Project ADA requirements
Estimated Cost (2020 Dollars): $3,548,160.00 2022 MSAS Improvement Project
20th North Street from North Broadway to Front Street and Front Street from 19th North Street to 20th North Street
o Roadway improvements, storm water modifications/treatment, sidewalk and trail construction
Estimated Cost (2020 Dollars): $1,700,965.00 2022 Surface Reconstruction Project (City Forces)
19th North Street from Broadway to Franklin Street (2.5 Blocks) Franklin Street from 16th North Street to 17th North Street (1 Block) Franklin Street from 12th North Street to 14th North Street (2 Blocks) Payne Street from 16th North Street to North Terminus (2 Blocks) 17th North Street from Franklin Street to Jefferson Street (1 Block) 10th South Street from Summit Avenue to Roslyn Road (1 Block) Roslyn Road from 10th South Street to South Terminus (1 Block) 12th South Street from Valley Street to German Street (2 Blocks)
12.5 Blocks Total Estimated Cost (2020 Dollars): $476,124.00
Estimated Total Cost 2022 CIP: $5,725,249.00
20
YEAR 2023 2023 Utility, Street and Alley Improvement – Group I Project
Bridge Street from Cottonwood Street to Tower Road o Watermain, sanitary sewer main, roadway reconstruction, storm sewer
extension and ADA improvements Alley Block 77 North of Center Street
o 11th North Street to 12th North Street between Broadway & Minnesota Street – Alley Reconstruction
Alley Block 97 South of Center Street o 8th South Street to 9th South Street between Broadway & State Street –
Alley Reconstruction Alley Block 96 South of Center Street
o 9th South Street to 10th South Street between Broadway & State Street – Alley Reconstruction
Alley Block 93 South of Center Street o 12th South Street to 13th South Street between Broadway & State Street –
Alley Reconstruction Concrete Sidewalk & ADA Improvements
o To fulfill the 2023 Surface Reconstruction Project ADA requirements Estimated Cost (2020 Dollars): $3,260,160.00
2023 MSAS Improvement Project
North Highland Avenue from Oak Street to HWY 14 o Mill & Overlay and ADA improvements
North Broadway from 20th North Street to CSAH 13 o Mill & Overlay and ADA improvements
Estimated Cost (2020 Dollars): $1,182,754.00 2023 Surface Reconstruction Project (City Forces)
German Street from 19th North Street to 20th North Street 1 Block German Street from 12th South Street to 16th South Street 4 Blocks 10th South Street from Valley Street to Front Street 1 Block 12th South Street from Minnesota Street to German Street 1 Block 8th South Street from Valley Street to Front Street 1 Block 7th South Street from Railroad Tracks to Front Street 1 Block 5th South Street from Valley Street to Front Street 1 Block 6th South Street from Broadway to German Street 2 Blocks
12 Blocks Total Estimated Cost (2020 Dollars): $454,080.00
Estimated Total Cost 2023 CIP: $4,896,994.00
21
ADDENDUM NO. 2021 Project Description and Basis of Preliminary Estimated Cost:
A. 2021 Utility, Street and Alley Improvements – Group I Project. This group of work includes improvements that have been petitioned for and/or ordered in by the City Council, as well as other improvements that should be considered as potential construction candidates. The improvements and associated estimates of cost that I recommend for consideration are as follows:
i. Jefferson Street from 7th North Street to 12th North Street. Reconstruction of the existing water main, sanitary sewer main, sewer and water end services, and reconstruction of the existing roadway section including excavation and replacement of subgrade, aggregate base, bituminous paving, pavement subdrains, storm sewer extension and inlet structure reconstruction, concrete curb and gutter, pedestrian sidewalk ramps, street lighting and selective replacement of concrete driveway pavement and sidewalk. Existing Infrastructure:
Segment Termini Watermain Sanitary Sewer Storm Sewer 7th to 8th North 6” Cast Iron (1923) 8” Clay (1937) Inlets at 8th North 8th to 9th North 6” Cast Iron (1923) 8” Clay (1937) None
9th to 10th North 6” Cast Iron (1923) 8” Clay (1937) Inlets at 10th North 10th to 11th North 6” Cast Iron (1923) 10” Clay (1937) None 11th to 12th North 6” Cast Iron (1923) 10” Clay (1937) Inlets at 12th North
Existing Segment Conditions:
Segment ID
Segment Termini OCI Inspection
Year Year Paved
Segment Length (LF)
122 7th to 8th North 39 2019 1940 430 LF 123 8th to 9th North 53 2019 1940 430 LF 124 9th to 10th North 22 2019 1947 430 LF 125 10th to 11th North 19 2019 1947 430 LF 126 11th to 12th North 25 2019 1947 430 LF
5 Blocks Total 2,150 LF
Roadway Plan & Profile: Plan File 4004-7 (7th North to 9th North) Plan File 4701A-7 (9th North to 11th North) Plan File 4701-7 (11th North to 12th North) Estimated Project Element Length: 2,150 LF Watermain Reconstruction (5 Blocks) 7th North to 12th North 2,150 LF Sanitary Sewer Reconstruction (5 Blocks) 7th North to 12th North 2,150 LF Roadway Reconstruction (5 Blocks) 7th North to 12th North
22
1,290 LF Storm Sewer Extension (3 Blocks) 7th North to 8th North and 9th North to 11th North Recommended Improvements and Estimated Cost: a. Watermain Reconstruction
2,150 LF 8” PVC x $105/LF = $225,750.00 b. Replace Existing Water End Services
82 Each x $2,100/Each = $172,200.00 Total Watermain & Water End Services = $397,950.00
c. Sanitary Sewer Main Reconstruction 2,150 LF 8” SDR 26 PVC x $105/LF = $225,750.00
d. Replace Existing Sewer End Services 82 Each x $1,200/Each = $98,400.00 Total Sanitary Main & End Services = $324,150.00
e. Roadway Reconstruction 2,150 LF x $560/LF = $1,204,000.00
f. Storm Sewer Extension 1,290 LF Storm Sewer Pipe x $120/LF = $154,800.00
g. Pedestrian Ramps 20 Each x $4,000/Each = $80,000.00
h. Street Lighting Conduit System 2,150 LF x 2 sides x $10/LF = $43,000.00 Estimated Contract Cost = $2,203,900.00 Engineering Service Fee (10%) = $220,390.00 PUC Street Lighting Charges 20 Decorative Standards x $3,200/Each = $64,000.00 Total Estimated Cost = $2,488,290.00
ii. Washington Street from 4th North Street to 5th North Street. Reconstruction of the existing watermain, sanitary sewer main, sewer and water end services and reconstruction of the existing roadway section including excavation and replacement of subgrade, aggregate base, bituminous paving, pavement subdrains, storm sewer modification and inlet structure reconstruction, concrete curb and gutter, pedestrian sidewalk ramps, street lighting and selective replacement of concrete driveway pavement and sidewalk. Existing Infrastructure:
Segment Termini Watermain Sanitary Sewer Storm Sewer 4th to 5th North 6” Cast Iron (1899) 10” Clay (1922) Inlets at 5th North
23
Existing Segment Conditions:
Segment ID
Segment Termini OCI Inspection
Year Year Paved
Segment Length (LF)
87 4th to 5th North 39 2019 1934 430 LF 1 Block Total 430 LF
Roadway Plan & Profile: Plan File 3403-9 Estimated Project Element Length: 430 LF Watermain Reconstruction 430 LF Sanitary Sewer Reconstruction 430 LF Roadway Reconstruction
Recommended Improvements and Estimated Cost: a. Watermain Reconstruction
430 LF 8” PVC x $105/LF = $45,150.00 b. Replace Existing Water End Services
17 Each x $2,100/Each = $35,700.00 Total Watermain & Water End Services = $80,850.00
c. Sanitary Sewer Main Reconstruction 430 LF 8” SDR 26 PVC x $105/LF = $45,150.00
d. Replace Existing Sewer End Services 17 Each x $1,200/Each = $20,400.00 Total Sanitary Main & End Services = $65,550.00
e. Roadway Reconstruction 430 LF x $560/LF = $240,800.00
f. Pedestrian Ramps 6 Each x $5,000/Each = $30,000.00
g. Street Lighting Conduit System 430 LF x 2 sides x $10/LF = $8,600.00 Estimated Contract Cost = $425,800.00 Engineering Service Fee (10%) = $42,580.00 PUC Street Lighting Charges 4 Decorative Standards x $3,200/Each = $12,800.00 Total Estimated Cost = $481,180.00
iii. State Street from 16th South Street to 17th South Street. Watermain and
sanitary sewer main extensions.
Recommended Improvements and Estimated Cost: a. Watermain Construction
430 LF 6” PVC x $60/LF = $26,000.00 b. Sanitary Sewer Main Reconstruction
24
430 LF 8” SDR 26 PVC x $51/LF = $22,000.00 c. Site Clearing and Restoration
1 LS x $28,280/LS = $28,280.00 Estimated Contract Cost = $76,280.00 Engineering Service Fee (10%) = $7,628.00 Total Estimated Cost = $83,908.00
iv. Maplewood Drive from Red Bud Road to Ryan Road. Watermain extension,
sewer and water end services and roadway improvements including concrete curb and gutter, concrete sidewalk, boulevard trees and street lighting. Existing Infrastructure:
Segment Termini Watermain Sanitary Sewer Storm Sewer Red Bud to Ryan None 8” PVC (2006) 42” RCP (2007)
Roadway Plan & Profile: Plan File B-6-0602 (Utilities) Plan File B-6-0603 (Roadway Profile)
Recommended Improvements and Estimated Cost: a. Watermain Construction
740 LF 6” PVC x $105/LF = $77,700.00 b. Construct Water End Services
9 Each x $2,100/Each = $18,900.00 Total Watermain & Water End Services = $96,600.00
c. Construct Sewer End Services 9 Each x $1,800/Each = $16,200.00
d. Roadway Construction 740 LF x $400/LF = $296,000.00
e. Concrete Sidewalk 7,584 SF x $6/SF = $45,504.00
f. Concrete Driveway Pavement 36 SY x 9 Each x $85/SY = $27,540.00
g. Boulevard Trees 20 Each x $750/Each = $15,000.00
h. Street Lighting Conduit System 740 LF x 2 sides x $10/LF = $14,800.00 Estimated Contract Cost = $511,644.00 Engineering Service Fee (10%) = $51,164.00 PUC Street Lighting Charges 6 High Level Standards x $2,500/Each = $15,000.00
25
Total Estimated Cost = $577,808.00
v. 20th North Street Tree Clearing. Tree removal in the anticipated construction limits for the 2022 20th North Street construction project.
Recommended Improvements and Estimated Cost: a. Tree Clearing
1 LS x $15,000/LS = $15,000.00 Estimated Contract Cost = $15,000.00 Engineering Service Fee (10%) = $1,500.00 Total Estimated Cost = $16,500.00
vi. Alley Block 189 North of Center Street. Alley from 7th North Street to 8th North Street between Garden Street and Payne Street. Reconstruction of the existing alley pavement section (14’ wide) including grading, aggregate base (12”), bituminous surfacing (3”), seven inch (7”) concrete alley approach pavement, underdrain, miscellaneous removals and restoration.
Recommended Improvements and Estimated Cost: a. Alley Reconstruction
700 Front Foot x $52/Front Foot = $36,400.00 Estimated Contract Cost = $36,400.00 Engineering Service Fee (10%) = $3,640.00 Total Estimated Cost = $40,040.00
vii. Alley Block 191 North of Center Street.
Alley from 9th North Street to 10th North Street between Garden Street and Payne Street. Reconstruction of the existing alley pavement section (14’ wide) including grading, aggregate base (12”), bituminous surfacing (3”), seven inch (7”) concrete alley approach pavement, underdrain, miscellaneous removals and restoration.
Recommended Improvements and Estimated Cost: a. Alley Reconstruction
700 Front Foot x $52/Front Foot = $36,400.00 Estimated Contract Cost = $36,400.00
26
Engineering Service Fee (10%) = $3,640.00 Total Estimated Cost = $40,040.00
viii. Cottonwood River Outfall O-C-23 Repair. Repair a damaged storm sewer outfall and stabilizing the riverbank at the outfall.
Recommended Improvements and Estimated Cost: a. Outfall Repair
1 LS x $27,000/LS = $27,000.00 Estimated Contract Cost = $27,000.00 Engineering Service Fee (10%) = $2,700.00 Total Estimated Cost = $29,700.00
ix. Concrete Sidewalk and ADA Improvements. ADA pedestrian ramp
improvements to compliment the improvements scheduled within the 2021 Surface Reconstruction Project to meet the current ADA requirements as per New Ulm’s adopted ADA Transition Plan.
Scheduled areas of Surface Reconstruction: a. 3rd North Street from Garden Street to Washington Street
Non-compliant ramps: Payne Street 8 Ramps Jefferson Street 8 Ramps Franklin Street 8 Ramps
b. 8th North Street from Franklin Street to Washington Street No non-compliant ramps within project limits
c. 18th North from Broadway to State Street No non-compliant ramps within project limits
d. 20th North Street from HWY 14 to North Broadway No non-compliant ramps within project limits
e. Franklin Street from 17th North Street to HWY 14 Non-compliant ramps: 19th North Street 8 Ramps Summation of Non-Compliant Pedestrian Ramps = 32 Ramps
Recommended Improvements and Estimated Cost:
a. Pedestrian Ramp Reconstruction 32 Ramps x $4,000/Ramp = $128,000.00
27
Estimated Contract Cost = $128,000.00 Engineering Service Fee (10%) = $12,800.00 Total Estimated Cost = $140,800.00
Summation of Estimated Cost 2021 Utility, Street and Alley Improvement – Group I Project $3,898,266.00
B. 2021 MSAS Improvement Project. This group of work includes improvements on roadway segments and bridges currently on New Ulm’s Municipal State Aid System (MSAS) except as noted.
i. CSAH 13 (North Highland Avenue) from CSAH 29 to North Broadway. Removal of the existing bituminous pavement, storm sewer modifications, grading, aggregate base, bituminous base, concrete curb and gutter, concrete sidewalk, bituminous recreational trail, concrete driveway pavement, bituminous surfacing, boulevard restoration and street lighting.
Note: This is a Brown County led project with City participation for the concrete sidewalks, recreational trail and street lighting. Roadway Plan Set: Plan File 0501-47 (Boundary Street Utilities & Paving) Estimated Project Length: 4,600 LF Roadway Improvements (Proposed Alignment) Existing Segment Conditions: Segment
ID Segment Termini OCI
Inspection Year
Year Paved Segment
Length (LF) 1730 CSAH 29 to Lake 34 2019 2005 1,900 LF 644 Lake to 23rd N 33 2019 2005 263 LF
1729 23rd N to
Stoneridge - - Unpaved 971 LF
1728 Stoneridge to
Hoffman - - Unpaved 481 LF
- Hoffman to N
Broadway - - Unopened 985 LF
4,600 LF
Recommended Improvement and Estimated Cost: The Brown County Engineer’s Estimate for the City participation for concrete sidewalks, recreational trail and street lighting is:
Estimated City Project Cost: $350,000.00
28
Estimated Cost 2021 MSAS Improvement Project $350,000.00
C. 2021 Surface Reconstruction Project by City Forces. Removal of existing bituminous pavement, reshaping the existing gravel base, repave with four inches (4”) of bituminous surfacing (unless noted otherwise) and selective replacement of concrete curb and gutter at the following locations:
i. 3rd North Street from Garden Street to Washington Street (4 Blocks)
Existing Segment Conditions:
Segment ID
Segment Termini OCI Inspection
Year Year
Paved
Segment Width (LF)
Segment Length
(LF)
Pavement Area (SF)
357 Garden to Payne 3 2019 36 LF 450 LF 16,200 SF
356 Payne to Jefferson
8 2019 36 LF 430 LF 15,480 SF
355 Jefferson to
Franklin 3 2019 36 LF 430 LF 15,480 SF
354 Franklin to
Washington 8 2019 36 LF 430 LF 15,480 SF
Average OCI: 5.5 1,740 LF 62,640 SF
Estimated Cost: Convert to SY: (1SY/9SF) x 62,640 SF = 6,960 SY 6,960 SY x $22/SY = $153,120.00
ii. 8th North Street from Franklin Street to Washington Street (1 Block) Existing Segment Conditions:
Segment ID
Segment Termini OCI Inspection
Year Year
Paved
Segment Width (LF)
Segment Length
(LF)
Pavement Area (SF)
394 Franklin to
Washington 8 2019 36 LF 430 LF 15,480 SF
Estimated Cost: Convert to SY: (1SY/9SF) x 15,480 SF = 1,720 SY 1,720 SY x $22/SY = $37,840.00
iii. 18th North Street from Broadway to State Street (1 Block) Existing Segment Conditions:
29
Segment ID
Segment Termini OCI Inspection
Year Year
Paved
Segment Width (LF)
Segment Length
(LF)
Pavement Area (SF)
471 Broadway to
State 11 2019 1984 36 LF 420 LF 15,120 SF
Estimated Cost: Convert to SY: (1SY/9SF) x 15,120 SF = 1,680 SY 1,680 SY x $22/SY = $36,960.00
iv. 20th North Street from HWY 14 to North Broadway (3 Blocks) Existing Segment Conditions:
Segment ID
Segment Termini OCI Inspection
Year Year
Paved
Segment Width (LF)
Segment Length
(LF)
Pavement Area (SF)
483 HWY 14 to North
Broadway 28 2019 1986 40 LF 1,000 LF 40,000 SF
Estimated Cost: Convert to SY: (1SY/9SF) x 40,000 SF = 4,444 SY 4,444 SY x $33/SY (6” Pavement) = $146,520.00
v. Franklin Street from 17th North Street to HWY 14 (3 Blocks) Existing Segment Conditions:
Segment ID
Segment Termini OCI Inspection
Year Year
Paved
Segment Width (LF)
Segment Length
(LF)
Pavement Area (SF)
113 17th N to 18th N 25 2019 1984 36 LF 430 LF 15,480 SF 1165 18th N to 19th N 25 2019 1970 36 LF 430 LF 15,480 SF 845 19th N to HWY 14 23 2019 1970 36 LF 450 LF 16,200 SF
Average OCI: 24 1,310 LF 47,160 SF
Estimated Cost: Convert to SY: (1SY/9SF) x 47,160 SF = 5,240 SY 5,240 SY x $22/SY = $115,280.00 Summation of Estimated Cost 2021 Surface Reconstruction Project by City Forces $489,720.00
D. 2021 Mn/DOT Project. Traffic signal and ADA sidewalk improvements at the intersection of 16th North Street and US HWY 14. The estimated City contribution will be for half of the traffic signal system only.
30
Estimated City Cost 2021 Mn/DOT Project $176,101.00
E. 2021 Brown County Project. Improvements on roadway segments and bridges currently on Brown County’s County State Aid System (CSAH) that are within the New Ulm Corporate Limits.
i. CSAH 26 (10th South Street) from Broadway to Flandrau State Park. This project consists of bituminous mill and overlay and ADA sidewalk improvements. This project is contingent on the County receiving State Park Road funds. The City will not have a cost participation on this project. Roadway Plan Set: Plan File 7301-29 (Broadway to Summit) Plan File 8166-31 (10th South to Flandrau Park Entrance) Estimated Project Length: 4,826 LF Roadway Mill & Overlay Existing Segment Conditions: Segment
ID Segment Termini OCI
Inspection Year
Year Paved Segment
Length (LF)
570 Broadway to
State 61 2019 1973 450 LF
571 State to
Washington 57 2019 1973 430 LF
572 Washington to
Franklin 67 2019 1973 430 LF
573 Franklin to Jefferson
46 2019 1973 430 LF
574 Jefferson to
Payne 42 2019 1973 430 LF
575 Payne to Summit 65 2019 1973 1310 LF
804 10th South to Southridge
78 2019 1981 229 LF
805 Southridge to
Lambrecht 52 2019 1981 329 LF
806 Lambrecht to
Lincoln 57 2019 1981 456 LF
807 Lincoln to State
Park 57 2019 1981 332 LF
4,826 LF
Estimated City Cost 2021 Brown County Project $0.00
31
F. 2021 Airport Improvement Project. Pavement reconstruction at the T-Hangars and Terminal Building parking lot area. The estimated project contract cost does not include project engineering, inspection materials testing and administration services which will be paid form the City Airport Budget.
Estimated Contract Cost 2021 Airport Improvement Project $351,686.00
SUMMARY OF ADDENDUM 2021 – PRELIMINARY ESTIMATED COST FOR 2021 CIP
A. 2021 Utility, Street & Alley Improvements – Group I $3,898,266.00 B. 2021 MSAS Improvement Project $350,000.00 C. 2021 Surface Reconstruction Project by City Forces $489,720.00 D. 2021 Mn/DOT Project $176,101.00 E. 2021 Brown County Project $0.00 F. 2021 Airport Project $351,686.00
SUMMATION 2021 CIP $5,265,773.00
Map #1 Pavement ConditionsCity of New UlmCurrent: 11/17/2020
³
LegendState Highway
Local City StreetsOCI
0-27.99 Failed28-65.99 Marginal66 - 100 Adequate
Municipal State AidOCI
0-27.99 Failed28-65.99 Marginal66 - 100 Adequate
County State AidOCI
0-27.99 Failed28-65.99 Marginal66 - 100 Adequate
Andrew GappaEng. Dept.11/16/2020
Recommended 2021 Capital Improvement PlanCity of New Ulm, MinnesotaDRAWN: 7-16-2020
Map #2Recommended 2021 Capital Improvement Plan
2021 SURFACE RECONSTRUCTION - OVERLAY PROJECTS - ADA IMPROVEMENTS2021 MSAS PROJECT - LED BY BROWN COUNTY2021 UTILITY, STREET AND ALLEY IMPROVEMENTS
2021 AIRPORT PAVEMENT PROJECT AT T-HANGERS2021 BROWN COUNTY MILL & OVERLAY WITH ADA IMPROVEMENTS
PARK
MINNESOTA RIVER
MINNESOTA RIVER
Cotton
wood R
iver
Cottonwood River
MINNESOTA RIVER
2021 Mn/DOT TRAFFIC SIGNAL & ADA IMPROVEMENTS
Z:\Engineering\Joe Stadheim\CIP Maps\2021 Utility, Street and Alley Improvements.dwg
Recommended 2022 Capital Improvement PlanCity of New Ulm, MinnesotaDRAWN: 7-16-2020
Map #3Recommended 2022 Capital Improvement Plan
2022 SURFACE RECONSTRUCTION - OVERLAY PROJECTS - ADA IMPROVEMENTS
2022 MSAS PROJECT 2022 UTILITY, STREET AND ALLEY IMPROVEMENTS
PARK
MINNESOTA RIVER
MINNESOTA RIVER
Cotton
wood R
iver
Cottonwood River
MINNESOTA RIVER
Z:\Engineering\Joe Stadheim\CIP Maps\2022 Utility, Street and Alley Improvements.dwg
Recommended 2023 Capital Improvement PlanCity of New Ulm, MinnesotaDRAWN: 7-16-2020
Map #4Recommended 2023 Capital Improvement Plan
2023 SURFACE RECONSTRUCTION - OVERLAY PROJECTS - ADA IMPROVEMENTS
2023 MSAS PROJECT - OVERLAY & ADA IMPROVEMNTS2023 UTILITY, STREET AND ALLEY IMPROVEMENTS
PARK
MINNESOTA RIVER
MINNESOTA RIVER
Cotton
wood R
iver
Cottonwood River
MINNESOTA RIVER
Monument St.
D.M.&E. Railroad
18th
S. S
t.
20th
N. S
t.
19th
N. S
t.
20th
N. S
t.
19th
N. S
t.
18th
N. S
t.
17th
N. S
t.
Water St.
Industrial St.
21st
N. S
t.
22nd
N. S
t.
Bere
ns B
lvd.
Somsen St.
Libe
rty S
t.
Rot
hmei
er C
t.
Mack Ln.Village Ln.
Lake
Ave
.
Doris Dr.
Bou
lder
Dr.
Hoffman Rd.
Broadway
23rd
N. S
t.
Sunrise Dr.
Garden St. Southridge Rd.
Butternut St.
Cot
tonw
ood
St.
Woodhaven Cir.
Summit Ave.
Crestwood Ln.
Linc
oln
Ln.
Lam
brec
ht L
n.
Circ
uit D
r.
Kennedy Dr.
Roslyn Rd.Whi
tney
Ln.
Jonathon Dr.
Woo
dlan
d D
r.
21st
St.
Indian Point Dr.
Oak
St.
Raymond Dr.
11th
N. S
t.
10th
N. S
t.
9th
N. S
t.
N. H
ighland Ave.
Cemetery Ave.
Kar
l Dr.
Ashland Rd.
Willow Rd.
Ced
ar D
r.
Birc
hwoo
d D
r.
2nd
S. S
t.
Cam
elsb
ack
Rd.
Hollywood Ave.
Hazelwood Ave.
Hill
top
St.
Elm
woo
d A
ve.
Che
rry
St.
Hei
nenh
ill S
t.
Sun
set A
ve.
Park Ln.
Cortland Cir.
McIntosh Dr.
Jona
thon
Dr.
20th
S. S
t.
18th
S. S
t.
Meyer Dr.
Lookout Ln.
Wes
tridg
e R
d.
Milford St.
Oak
woo
d A
ve.
Boe
ttger
Rd.
Golf Dr.
16th
S. S
t.
Ridge
view D
r.
Terrace Dr.
D
a
c
o
t
a
h
D
r
i
v
e
B
e
n
z
C
i
r
c
l
eS
e
t
t
l
e
r
T
r
a
i
l
CS
AH
27
Lee
Ave
.
3rd
N. S
t.
2nd
N. S
t.
10th
S. S
t.
Elm
St.
Cen
ter
St.
Cla
y C
ir.
Bianchi Dr.
Fla
ndra
u Ln
.
Summit Ave.
Monument St.
South Highland Ave.
Bac
ker
St.
Pfa
ende
r Dr.
Waraju Ave.
Haeberle Ave.
Bein
horn
St.
Map
le S
t. R
.O.W
.
D S
tree
t
CSAH 29
CSAH 13
Center S
treet (CS
AH
13)
CS
AH
26
Washington St.
Franklin St.
U.S
. Hw
y 14
Spring St.
19th
S. S
t.
Wes
tridg
e R
d.
Turner Rd.
North Highland Ave.
U.S
. Hw
y 14
Airp
ort R
d.
Wes
tridg
e R
d.
Vacated Valley Heights Drive
Hen
le D
r.
Map
lew
ood
Dr.
7th
N. S
t.
Wes
tridg
e R
d.
Palmer Avenue
U.S
. Hw
y 14
Water St.Water St.
Front St.
Spring St.
Front St. Front St.
Spring St.
Front St.
Valley St.
Spring St.
Front St.
Valley St.
Spring St.
Front St.
14th
N. S
t.
15th
N. S
t.
13th
N. S
t.
12th
N. S
t.
11th
N. S
t.
10th
N. S
t.
9th
N. S
t.
6th
N. S
t.
5th
N. S
t.
1st N
. St.
14th
N. S
t.
16th
N. S
t.
15th
N. S
t.
13th
N. S
t.
12th
N. S
t.
11th
N. S
t.
10th
N. S
t.
9th
N. S
t.
8th
N. S
t.
7th
N. S
t.
6th
N. S
t.
5th
N. S
t.
4th
N. S
t.
3rd
N. S
t.
2nd
N. S
t.
1st N
. St.
14th
N. S
t.
16th
N. S
t.
15th
N. S
t.
13th
N. S
t.
17th
N. S
t.
12th
N. S
t.
11th
N. S
t.
10th
N. S
t.
9th
N. S
t.
8th
N. S
t.
7th
N. S
t.
6th
N. S
t.
5th
N. S
t.
4th
N. S
t.
3rd
N. S
t.
2nd
N. S
t.
1st N
. St.
19th
S. S
t.
17th
S. S
t.
Cen
ter
St.
1st S
. St.
3rd
S. S
t.
4th
S. S
t.
5th
S. S
t.
6th
S. S
t.
7th
S. S
t.
8th
S. S
t.
9th
S. S
t.
10th
S. S
t.
11th
S. S
t.
12th
S. S
t.
13th
S. S
t.
14th
S. S
t.
15th
S. S
t.
2nd
S. S
t.
16th
S. S
t.
17th
S. S
t.
Cen
ter
St.
1st S
. St.
3rd
S. S
t.
4th
S. S
t.
5th
S. S
t.
6th
S. S
t.
7th
S. S
t.
8th
S. S
t.
9th
S. S
t.
10th
S. S
t.
11th
S. S
t.
12th
S. S
t.
15th
S. S
t.
2nd
S. S
t.
Minnesota St.
Front St.
Valley St.
German St.
Broadway
Spring St.
Front St. Front St.
Valley St.
Front St.
Valley St.
Front St.
Valley St.
Front St.
Valley St.
Front St.
Valley St.
Front St.
Valley St.
Payne St.Payne St.Payne St.Payne St.
Franklin St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Franklin St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Franklin St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Franklin St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Franklin St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Payne St.
Franklin St.
Garden St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Franklin St.
Garden St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Payne St.
Franklin St.
Garden St.
German St.
Minnesota St.
Broadway
State St.
Jefferson St.
Payne St.
Franklin St.
Garden St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Payne St.
Franklin St.
Garden St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Payne St.
Franklin St.
Garden St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Payne St.
Oak
St.
North Highland Ave
.
North Highland Ave.
6th
N. S
t.
Cen
ter
St.
Cot
tonw
ood
St.
Cre
stvi
ew D
r.
Summit Ave. Summit Ave.
Linc
oln
Ln.
Southridge Rd.
Friton St.
Vacated Spring St.
Vac
ated
2nd
N. S
t.
Hay
Str
eet
Meadow Street
Henderson State Road
Vacated Water Street
8th
N. S
t.
Riverside A
ve.
Wiesen Tahl Avenue
Henderson State Road
A S
tree
t
B S
tree
t
Vac
ated
Cou
rtla
nd S
tree
t
C S
tree
t
Hillside Avenue
Loretto St.
7th
N. S
t.
8th
N. S
t.
Bishop Lucker Ln.
Monument St.
West St.
Linden St.
5th
N. S
t.
2nd
S. S
t.
K.C. Rd.
North Highland Ave.
T.H. Hwy 15 & 68
Hauenstein Dr.U.S
. Hw
y 14
Map
lew
ood
Dr.
Broadway
Boundary St.
Franklin St.
Garden St.
German St.
Minnesota St.
Broadway
State St.
Washington St.
Jefferson St.
Payne St.
Boettger Rd.
Minnesota St.
Franklin St.
Front St.
Valley St.
German St.
State St.
Broadway
Payne St.
Washington St.
Brid
ge S
t.
Oak
woo
d Av
e.
3rd
S. S
t.
4th
S. S
t.16th
N. S
t.
20th
S. S
t.
19th
S. S
t.
18th
S. S
t.
8th
N. S
t.
7th
N. S
t.
4th
N. S
t.
3rd
N. S
t.
2nd
N. S
t.
17th
S. S
t.
Cen
ter
St.
1st S
. St.
3rd
S. S
t.
4th
S. S
t.
5th
S. S
t.
6th
S. S
t.
7th
S. S
t.
8th
S. S
t.
9th
S. S
t.
10th
S. S
t.
11th
S. S
t.
12th
S. S
t.
13th
S. S
t.
14th
S. S
t.
15th
S. S
t.
2nd
S. S
t.
16th
S. S
t.
7th
N. S
t.
Jacobs Street
Hun
ters
St.
Hickory St.
Upp
er W
alla
chei
Low
er W
alla
chei
Southridge Rd.
Circ
uit D
r.
Ros
lyn
Rd.
Sto
nerid
ge R
d.
Ryan Rd.
Alison Ave.
Birc
hwoo
d D
r.
19th
N. S
t.
18th
N. S
t.
17th
N. S
t.
16th
N. S
t.
15th
N. S
t.
14th
N. S
t.
13th
N. S
t.
12th
N. S
t.
11th
N. S
t.
10th
N. S
t.
9th
N. S
t.
8th
N. S
t.
7th
N. S
t.
6th
N. S
t.
5th
N. S
t.
4th
N. S
t.
3rd
N. S
t.
2nd
N. S
t.
1st N
. St.
Min
neco
n D
r.
Boundary St.
Par
k S
t.
Riv
er S
t.
Water St.
Spring St.
Bridge St.
Cot
tonw
ood
St.
Tow
er R
d.
Hauen
stein
Dr.
Sch
ell's
Rd.
Cre
stvi
ew D
r.
18th
S. S
t.
17th
S. S
t.
Crestview Dr.
16th
S. S
t.
17th
S. S
t.
Cen
ter
St.
1st S
. St.
3rd
S. S
t.
4th
S. S
t.
5th
S. S
t.
6th
S. S
t.
7th
S. S
t.
Vac
ated
8th
S. S
t.
9th
S. S
t.
10th
S. S
t.
11th
S. S
t.
12th
S. S
t.
13th
S. S
t.
14th
S. S
t.
15th
S. S
t.
Location of M.R. Paving & Excavating, INC.
Spring St.
Oak
St.
Lind Rd.
Cotto
nwoo
d St
.
12th
N. S
t.
8th
S. S
t.
Red Bud Rd.
Birc
hwoo
d D
r.
Map
lew
ood
Dr.
Pfaender Dr.
Stat
e R
oad
Z:\Engineering\Joe Stadheim\CIP Maps\2023 Utility, Street and Alley Improvements.dwg