+ All Categories
Home > Engineering > City of orlando db colonial ped overpass technical

City of orlando db colonial ped overpass technical

Date post: 10-Feb-2017
Category:
Upload: brendan-oconnor
View: 2,256 times
Download: 0 times
Share this document with a friend
21
RFP 16-0017 | March 23, 2016 Request for Proposal for Design-Build Services (Technical Proposal) for Colonial Pedestrian Overpass Submitted to City of Orlando RFP16-0017, Orlando Urban Trail Colonial Drive (State Road 50) Pedestrian Overpass - Technical David Billingsley, Chief Procurement Officer Attention: Teddi McCorkle, C.P.M., CPPB, Senior Contract Administrator Procurement and Contract Division 400 South Orange Avenue, 4th Floor Orlando, Florida 32801 Submitted by Gibbs & Register, Inc. 232 S. Dillard Street Winter Garden, FL 34787 Vanasse Hangen Brustlin, Inc. 225 E. Robinson Street, Suite 300 Orlando, FL 32801 In Association with Borrelli + Partners, Inc. Florida Bridge and Transportation, Inc. Geotechnical and Environmental Consultants, Inc. HDR Engineering, Inc. Southeastern Surveying and Mapping Corp.
Transcript
Page 1: City of orlando db colonial ped overpass   technical

RFP 16-0017 | March 23, 2016

Request for Proposal for

Design-Build Services (Technical Proposal) for Colonial Pedestrian OverpassSubmitted to City of Orlando RFP16-0017, Orlando Urban Trail Colonial Drive (State Road 50) Pedestrian Overpass - Technical David Billingsley, Chief Procurement Officer

Attention: Teddi McCorkle, C.P.M., CPPB, Senior Contract Administrator Procurement and Contract Division 400 South Orange Avenue, 4th Floor Orlando, Florida 32801

Submitted by Gibbs & Register, Inc. 232 S. Dillard Street Winter Garden, FL 34787

Vanasse Hangen Brustlin, Inc. 225 E. Robinson Street, Suite 300 Orlando, FL 32801

In Association with Borrelli + Partners, Inc.Florida Bridge and Transportation, Inc.Geotechnical and Environmental Consultants, Inc.HDR Engineering, Inc.Southeastern Surveying and Mapping Corp.

Page 2: City of orlando db colonial ped overpass   technical

March 23, 2016

City of Orlando

GIBBS & REGISTER, INC. 232 South Dillard Street Winter Garden, Florida 34787 Telephone: (407) 654~6133 Facsimile: (407) 654~6134

David Billingsley, CPSM, CPM, Chief Procurement Officer 4th Floor, City Hall 400 South Orange Avenue Orlando, Florida 32801

Re: Design-Build Services for Colonial Pedestrian Overpass (SR50), RFP16-0017 Technical Proposal City Project No. TRE0003 _ G

Dear Mr. Billingsley:

Thank you for shortlisting our team and allowing us to provide our Technical Proposal for the project. We are truly excited about working for the City of Orlando and also about working alongside our teammates once again. Ours is a team that has a history of working together and we have successfully delivered a Design-Build project together in the past.

The G&RNHB Team has gained a thorough understanding of this project through a comprehensive review of site conditions and design concepts. We have reviewed concept plans, visited the project site, and familiarized ourselves with the issues facing this project. We have arrived at a very innovative approach to the project, which we look forward to presenting to you.

Our team believes that successful design-build projects result from thorough planning, exceptional orga­nization, seamless teamwork, and a "do whatever it takes" attitude. The Colonial Pedestrian Overpass Project requires a team with proven design-build experience, technical expertise with this type of project delivery and the commitment to proactively resolve any issues. The G&RfVHB team possesses all of these attributes and more. We are the "can do" team!

We are a team committed to providing the professional and financial resources required to successfully design and build this exciting project for the City of Orlando. In accordance with the RFP, we have enclosed our technical proposal and look forward to a favorable review of our capabilities.

Respectfully submitted,

GIB7J~ By: Theodore Ferguson, DBIA

President TF [email protected]

Page 3: City of orlando db colonial ped overpass   technical

Section 1

Section 1: Project Approach

Project Approach

Page 4: City of orlando db colonial ped overpass   technical

City of Orlando Design Build Services for the Colonial Pedestrian Overpass (SR50) - Technical Proposal Project No. TRE0003_G

Project ApproachAlignmentOur team walked the site and collected additional information regarding the I-4 Ultimate project, more specifically – drainage calculations and pond details for Pond P-15A and P-15B and the I-4 schedule of events within the State Road 50 (SR 50/Colonial Drive) interchange area. Based on review of this data, we have proposed an alternative alignment that will eliminate construction within the actual pond area by spanning the pond with a prefabricated steel box-truss. Piers and foundations will be constructed outside the pond to support the truss, removing the need to puncture the pond lining and boot piles. Please note this alternative alignment remains within the pond parcel as required in the RFP and will not impact the oil-cooled underground electric utility adjacent to the existing Garland Avenue.

The alternative alignment is slightly longer than the original; however, it maintains the general smooth flow characteristics of the original alignment. It also allows the walls along the east side of the pond where the alignment diverges to be reduced in height from 12 feet to 5 feet.

The above proposed modifications in the alignment and use of a prefabricated box-truss structure to span the pond dramatically reduce construction risks, costs, and time. By reviewing the I-4 schedule, we determined the timing of construction activities for the two projects should not interfere with each other.

1

1-1

Page 5: City of orlando db colonial ped overpass   technical

G&R | Project Approach

StructuresSeveral options for foundation, substructure, and superstructure elements were analyzed based on the constraints and conditions at the proposed site and considerable discussion with the project team, various fabricators, and suppliers. We carefully weighed constructability, schedule, maintainability, safety, and cost during that process. We are confident in our analysis and the recommendations contained within our proposal for the design and construction of the pedestrian and bicycle trail over SR 50 and the CFCR railroad.

A solid foundation is critical to every bridge project. The three main piers supporting the two prefabricated steel truss bridge sections and the architectural pylons will be supported by 18-inch square precast pre-stressed concrete (PPC) piles with a cast-in-place concrete pile cap. These deep foundations are the most appropriate substructure type to withstand the larger-than-typical loads associated with the two 220-foot prefabricated steel truss bridges and all the accompanying architectural elements. Gibbs & Register (G&R) will monitor

all vibrations during pile-driving operations as required by FDOT. Each of the truss sections will span between cast-in-place two-column piers. The two main crossings, one over SR 50 and the CFCR railroad and the other over the pond, will each span 220 feet and will consist of a prefabricated steel box-truss with a cast-in-place concrete deck, two-inch square mesh fencing, and lighting for safety and enhanced aesthetics. Curbing will line the truss spanning the railroad and roadway to prevent any water from falling onto the restricted right-of-way below. All water will be collected at the piers via scuppers and funneled to ground level in a controlled manner through pipes located inside the pier columns.

In order to reduce project costs, the main span pier on the north side of SR 50 will sit within the railroad right-of-way. FDOT and American Railway Engineering and Maintenance-of-Way Association (AREMA) require any bridge pier located less than 25 feet from the centerline of the nearest tracks be protected by a crash wall. The crash wall will stand slightly more than 18 feet from the centerline of and run parallel to the nearest tracks. It will extend 12 feet in each direction beyond the face of the adjoining column. At a minimum, the crash wall will extend 6 feet above the lowest ground elevation and be 2.5 feet thick in compliance with FDOT and AREMA requirements.

The remainder of the elevated approach ramp bridge structure will be supported by spread footing foundations. Each approach ramp bridge span shall consist of either cast-in-place flat slab sections (on the curved portions) or a pair of precast pre-stressed concrete double-tee beams (on the straight portions) spanning between cast-in-place single-column piers. As the deck element is already an integral part of the beams, the use of double-tee beams ensures a low maintenance component which facilitates reduced construction times and the most economical use of available funds.

Use of the double-tee beams and the box-truss structures that are designed and fabricated early in the Design-Build schedule will also reduce construction time. Each truss will arrive in six pieces with the side fencing pre-installed and will be lifted from the delivery trucks and placed on low elevation temporary supports for final assembly. Once assembled, metal pans will be attached while still on the ground. Not only will these assembly methods reduce the

1-2

Page 6: City of orlando db colonial ped overpass   technical

G&R | Project Approach

construction time, they will also greatly reduce the personnel required to attach fencing and metal pans at higher elevations over a busy roadway and minimize coordination with the railroad. This is discussed in further detail in the Construction section that follows.

We chose to support the majority of the remaining approach ramp on the north side of SR 50 on retained earth (RE) walls for several reasons – ease of construction, decreased project schedule, safety, and aesthetics. Not only are the precast walls faster to construct, they can be installed without the use of heavy construction equipment that may prove difficult to maneuver within the limited project right-of-way and easements on the north side of the SteelHouse Apartments, as well as avoid adjacent ditches and other obstructions. To

complete the picture, ADA compliant 54-inch aluminum handrails will secure pedestrians on the approach ramps, providing a durable, low-maintenance, and aesthetically pleasing structure that the City and its patrons can enjoy in the heart of downtown Orlando for many years to come.

StormwaterThe proposed bridge lies within the Lake Concord Basin of the St. Johns River Water Management District (SJRWMD). The bridge and trail will be constructed across and around proposed Pond P-15 from the Proposed I-4 Expansion. A portion of the trail will be constructed on the top of the maintenance berm that separates the two lobes of the pond (Ponds P-15A and P-15B). The top of the maintenance berm in this area is 97.0 feet, and the peak stage in the proposed pond is approximately 96.5 feet for the 25-year 96-hour storm event. Therefore, the proposed construction of the trail will have no impact on the storage capacity of the proposed pond.

According to 62-330.051(10) F.A.C., trail projects are exempt from permitting. In addition, since there are no proposed wetland or surface water impacts, a permit will not be required from the SJRWMD and the Army Corps of Engineers (ACOE).

Schedule/Construction/MOTUpon receipt of the Notice to Proceed (NTP), our team will schedule a kick off meeting with the City and FDOT. During this meeting, our team will present a formal project schedule and determine the lines of communication for the project. Because we already have design survey, we will begin preparing final design plans immediately and develop milestone dates for the 30%, 60%, 90% and final plans. Each phase will be submitted to the City and FDOT for review. VHB will transmit the plans to FDOT via their ERC system upon approval from the City. During the 30% phase, we will schedule stakeholder meetings to gather input on the project. We will also initiate utility coordination efforts since we already are aware of at least two utilities that will be impacted, TECO gas and electric. Our goal is to work with the utility companies to relocate the utilities prior to the start of construction. Geotechnical explorations will be initiated during the 60% design phase. Traffic control plans will be developed and approved as part of the final plans and coordinated with stakeholders. This will be critical so that adequate notice can be given for road and lane closures. Construction activities and sequencing are outlined in detail in the following paragraphs.

1-3

Page 7: City of orlando db colonial ped overpass   technical

G&R | Project Approach

The overpass and first ramp span to the south will be constructed utilizing prefabricated pedestrian bridges. These two spans will be supported on three deep foundations consisting of 18-inch precast pre-stressed concrete piles with a dual column, cast-in-place concrete substructure that is finished per the BA-8 aesthetic agreement. These piles will be driven from crane access that is outside of the CFCR right-of-way as well as SR 50. The approach ramp spans will be constructed from a combination of cast-in-place decking and double-tee beams that will be supported by spread footing foundations at each pier. Construction costs for these spread footings are lower than driven piles, and there are no issues due to vibration or noise impacts normally associated with pile driving. Each precast approach ramp will span 55 feet and shall consist of a pair of precast, pre-stressed concrete double-tee beams spanning between cast-in-place single-column piers. The precast beams will be connected through a closure pour after all sections have been set. As mentioned previously, the deck element is already an integral part of the beams and closure pour, which ensures a low maintenance component, facilitates reduced construction times, and provides the best value for funds expended.

The main crossing over CFCR and the SR 50 right-of-way will span 220 feet and shall consist of a prefabricated box-truss with hot-dipped galvanized mesh on all three exposed sides of the structure. This mesh will be powder-coated to match the truss members for aesthetic tie-in and lighting. Our proposed design has the ramp to the south spanning the entire stormwater pond being constructed for the I-4 Ultimate project. G&R will be utilizing another 220-foot long prefabricated box-truss that will be set with a 4.9% downward slope and contain hot-dipped galvanized mesh on the two exposed vertical sides, powder-coated to match the truss members. Both of these structures will arrive in six separate sections and will be assembled on low elevation temporary supports where the metal deck pans and most of the electrical components will be added prior to lifting into their final position. Our plan will utilize the abandoned alignment for the current configuration of Garland Avenue as our staging and assembly yard. This will allow G&R to have both structures assembled and ready for installation on-site so the restricted hours of work associated with CFCR and SR 50 closures can be fully utilized for placements. Our research revealed that SR 50 has been closed on occasion to support the I-4 construction. We anticipate using the same detour plan previously approved by FDOT and the City of Orlando for the main span lift (Figure 1 (taken from the I-4 Ultimate website)). The timing of this will be coordinated with the City, FDOT, and CFCR.

Due to G&R’s previous experience with placing structures over and within the CFCR right-of-way and their full understanding of the safety and coordination efforts required to complete such time sensitive and high-profile operations; we have developed the following plan for setting the 220-foot span over the rail and SR 50 right-of-way. Final placement will be accomplished utilizing one 600-ton crawler crane. This crane meets the CFCR required safety factor of having a lift capacity capable of picking 150% of our structure’s weight at the same radius and boom angle as the designed pick. This requirement ensures that no failure due to undersized cranes causes damage or disruption to the traveling rail corridor. In addition to the

Figure 1. Detour Plan

1-4

Page 8: City of orlando db colonial ped overpass   technical

G&R | Project Approach

150% pick capacity, CFCR requires an equal lifting capacity back-up crane(s) to be assembled and ready in case of the primary crane’s failure or malfunction. G&R will accomplish this by having two 400-ton hydraulic truck cranes assembled and staged near each of the bridge piers. Please see calcualtions package for graphics for crane and bridge staging. These two cranes have the capacity to dual-pick our entire bridge, and their location will allow them to set the structure in its final location, satisfying the CFCR back-up criteria. Our 600-ton crawler crane will be assembled on the east side of the I-4 stormwater pond in the FDOT right-of-way. This assembly location will allow the crane to “walk” to its pick location which will be a crane-matted area in the center of SR 50, just south of the current driveway apron for the Amerinational Management Services parcel.

Due to the constraints of lane closures on SR 50, as well as having restraints on access to working over the CFCR rail, we propose to transport our prefabricated, pre-assembled box-truss to its pick location on a “heavy haul transport” trailer. This hydraulic lifting trailer will allow us to walk the fully-assembled structure into its picking position without restaging any of our cranes during the outage. Once the pedestrian bridge is in place at the center line of SR 50, our 600-ton crawler crane will pick the entire structure and set it in place over the CFCR rail and SR 50 right-of-way. By utilizing this system, we anticipate being able to set this structure within a seven hour detour/rail available condition. This will provide the least amount of impact for road and rail traffic.

Once the main span crossing the CFCR rail right-of-way has been set, the second prefabricated, pre-assembled structure will be loaded onto the “heavy haul transport” for installation on the following day. We will walk the 600-ton crawler crane to the northeast bridge pier which shares the two 220-foot prefabricated bridges. One of the 400-ton hydraulic cranes will mobilize to the southwest pier near the bridge-assembly area. The “heavy haul transport” will mobilize the second prefabricated bridge at the northwest corner of the I-4

stormwater pond. This span will be placed into final position with a dual-crane pick, using the 600-ton crawler and one 400-ton hydraulic crane. This plan and sequencing allows G&R to best utilize the mobilization expenses for these large cranes and expedites the completion of 440 lineal feet of elevated structure. This design and construction methodology minimizes the amount of work to be performed over the CFCR and SR 50 right-of-way. The prefabricated structures eradicate the need for placing an exposed concrete deck within these highly trafficked areas. In turn, the installation and removal of overhang brackets and installation of SIP decking and railing under detoured conditions are also eliminated. Once our prefabricated structures are set, the remaining items of work (i.e. lighting, deck placement and electrical/CCTV) will be accomplished within the box-truss structure previously enclosed with fencing, reducing the risk of drop hazards onto the active rail line and roadway.

The four lighted, decorative spires at the main span will be erected during road-closure and CFCR outage times. These spires are constructed of precast panels attached to a structural steel member internally. This design allows for lighter picks and smaller cranes during their assembly. The smaller crane will be set up on the east side of the northern pier, north of the existing SR 50 for its spire construction. The south spire will have the crane staged in the

1-5

Page 9: City of orlando db colonial ped overpass   technical

G&R | Project Approach

FDOT right-of-way east of the I-4 stormwater pond. This will reduce the time of lane closure and flagging at each pier for crane set-up, thereby reducing overall cost and impact for the public.

In an effort to reduce construction time, the double-tee beams and the box-truss structures are designed and fabricated early in the Design-Build schedule. During the design and fabrication period, G&R will immediately begin clearing and preparing the site for the elevated members. This includes forming and erecting the proposed abutments and piers to receive the beams and then the box-trusses. Upon delivery, the beams for the north approach ramp will be removed from the trucks on west-bound SR 50, utilizing a lane closure for truck staging. Due to the limited access in between CFCR right-of-way and the SteelHouse Apartments, G&R will construct the double-tee beams from north to south utilizing a multi-pick operation that uses a 100-ton hydraulic, rough terrain crane for the first three spans. This will allow us to fly the beams to their final position with minimal impact to the CFCR traffic by relocating the crane during periods of no train movements. The final two spans will be set from a crane staging location at the southwest corner of the SteelHouse Apartments building. The south approach beams will be placed from the abandoned Garland Avenue area to complete the span across the narrow portion of the stormwater pond. All double tee beams will be connected utilizing a closure pour between the structures. All pours will be pumped for quick and safe material delivery, reducing flagging time for the CFCR right-of-way. The two cast-in-place elevated sections of ramp will be completed outside of the CFCR right-of-way, limiting railway flagging to times for pumping of concrete and flying of forming material to the north approach. Both approaches will have ADA compliant, 54-inch aluminum handrails and trail lighting installed once the deck pours are complete.

As discussed in the Structures section, we chose to support the remaining approach ramp on retained earth (RE) walls for several reasons – ease of construction, decreased project schedule, decreased flagging operations at the CFCR right-of-way, safety, and meeting the required aesthetics. Not only are the precast walls faster to construct, they can be installed without the use of large construction equipment or cranes that may prove difficult to maneuver within the limited project right-of-way. Materials for the RE walls will be

shuttled in from the Orange Avenue access, and the walls will be built working our way back to grade and toward Orange Avenue. Once the entire at-grade trail has been constructed, conduit and acorn lighting will be installed to complete the project and provide the City and trail users an enjoyable experience right in the heart of downtown Orlando.

Communications/Video DesignVHB is experienced with the City of Orlando’s Intelligent Transportation System (ITS) including the City’s Traffic CCTV subsystem. VHB ITS Engineer, Erik Spillmann, has over 17 years of experience in ITS and traffic engineering. Erik served as Project Manager for Metropolitan Orlando Computerized Signal System and was involved in the evaluation of controllers, communication systems and traffic management system alternatives for the upgrade of the Regional Computerized Signal System (RCSS) for the City. His work in this project included designing the fiber optic backbone; developing City of Orlando’s Signal System GIS by incorporating regional signal information with geographic information; developing

1-6

Page 10: City of orlando db colonial ped overpass   technical

G&R | Project Approach

intersection design package plans, CCTV incident detection plans and system detector loop plans; inspecting fiber optic cable installation and fiber optic equipment; fiber optic testing; assisting in project management, as well as other tasks.

Erik also served as Engineer of Record (EOR) for the City’s recent Downtown Orlando ITS – Phase II Design-Build project as well as other City ITS projects. With his work in the RCSS, and other City of Orlando projects, Erik has gained added experience in communication systems, gig Ethernet networks, fiber optics, and CCTV design. CCTV placement will be at locations outside the railroad ROW while maximizing the view of SR 50. Consideration will include avoiding maintenance vehicles encroaching on railroad ROW. CCTV’s will be integrated into the City Traffic Ethernet Communication Network and the City’s CCTV Surveillance System. Tree pruning will be required for some of these sites. Our team will coordinate with the City’s urban forester for any tree obstructions that may occur. Tree trimming is anticipated to be minimal for CCTV installations. Maintenance considerations will be of extreme importance.

Our team is familiar with the City’s existing ITS/traffic system. Each of the City’s ITS devices are interconnected to the central hardware/software (HW/SW) via a hybrid WAN communications system. GB Backbone communications links are made from each of 9 hubs located throughout the city. Each hub has a Layer 3 switch connected in a ring topology to the Central Core Layer 3 switch. The Backbone and Core Switches are Juniper GB Model EX3200 full layer 3 router switches. The distribution layer interconnects the ITS devices – including

traffic signal controllers to each of the hubs via a combination of twisted pair copper and SM/MM fiber optic cable. Layer 2 switches of various makes and models are used for this purpose. Our team proposes to integrate the bridge CCTV to the City’s system via a drop run to one of the hub switches located just east of Orange Ave on SR 50.

Systems Communication Equipment – The proposed IP based communications will be designed to seamlessly integrate with the City’s existing communication network. Previously implemented equipment makes and models will be utilized where appropriate.

Our Team will propose CCTV subsystem equipment that has been successful in previous ITS projects for the City’s system. CCTV Installation will include the following FDOT Approved Product List devices:

■ Bosch CCTV Dome Assembly w/J Bracket ■ ITS Express Ethernet GB Switch ■ FO Termination Panels ■ 336 Equipment Cabinet with UPS battery backup ■ Surge Suppression ■ Miscellaneous Cables

Cabinet power will be obtained from the bridge’s power service point. Early in the design-build process, the existing conduits will be checked for blockage and repaired as needed. The conduits will then be tested. Once passed, a pull string will be blown-in for subsequent fiber cable installation.

1-7

Page 11: City of orlando db colonial ped overpass   technical

G&R | Project Approach

Fiber Optic cable and trace wire will be installed that meet the requirements of FDOT Specifications Section 783 and the RFP. The proposed fiber cable will be 12 SM. Fusion splices will be used throughout the project with all splices meeting the latest FDOT standard specifications and design standards. Fiber optic attenuation, splice and termination values will meet or exceed the requirements of the RFP and Section 783. All testing will be documented as required.

A new conduit line will be installed between the proposed ITS cabinet to the City’s existing fiber network at SR 30 and Orange Avenue. Each fiber optic pull box will have the appropriate length of coil neatly placed and labeled. Upon completion (within the project limits), the cable and trace wire will be tested. Test plans will be developed for CCTV field installation and integration into the City’s existing CCTV subsystem.

Railroad (R/R) CoordinationOur Team is aware of the coordination and permitting requirements to construct over railroad tracks. This railroad crossing is owned by Sunrail (Formerly CSX) within the project limits. In order to operate within the railroad right-of-way, a proper agreement and permit must be obtained during the design phase. Our Team has extensive experience with the procurement of Railroad agreements and permits during the design phase. We are well aware of the time factor involved with the procurement of such agreements/permits and provide for this time in the development of our schedules. Additionally, our team is well aware of the required coordination between the Team and the railroad companies during the construction phase of the project. We fully understand and will implement:

■ Close coordination with R/R owners during all construction activities within railroad right-of-way.

■ Any operations that will affect the in-service rail lines will require a flagman/watchman. R/R owners shall be notified at least 72 hours prior to start of construction activities, to schedule this work.

■ We are aware of the railroad regulations and requirements and will be proactive in notifying the owner as per the General Specifications. Various members of our team have extensive experience working closely with CSX personnel and have been trained/certified in railroad safety in order to work around active railroad tracks.

■ Right-of-way fencing will be furnished and installed per the air space agreement.

Aesthetics/Safety/LightingThe gateway pedestrian bridge over SR 50 between Gertrude’s Walk and Dinky Line segments of the Orlando Urban Trail project will consist of gradient approach ramps at the north and south. These will be constructed with mechanically stabilized earth walls that follow the I-4 Ultimate Aesthetics Guidelines in form, material and finish. The approach ramps transition to elevated flying incline ramp structures supported on architecturally detailed and relief,

single column piers, to the crossing elevation of the two 220-foot bridge structures, which spans SR 50 at a 38-degree skew. These bridges will consist of a steel framed box-truss superstructure and an internal pedestrian shelled mesh canopy. Along the bottom chord of the structural truss

1-8

Page 12: City of orlando db colonial ped overpass   technical

G&R | Project Approach

will be a 4-foot blue steel ribbon, which will shield the electrical and drainage system from public view and house the LED illuminated cut out of the marquee sign “Orlando,” at the main span welcoming visitors and residents alike as a threshold and gateway into the downtown of “The City Beautiful.”

Significant architectural elements associated with this design are the individual threshold nodes throughout this portion of the pedestrian bridge that serve as visual benchmarks and way-finding elements associated with the north and south bridge approach ramps, transition points where separate trail ramps merge, and threshold openings of the bridges themselves. These will consist of re-imagined iconic I-4 Ultimate precast concrete pylons with a top illuminated spire that will have the capability to provide themed illumination in conjunction with the overall bridge architectural display lighting package. The lighting design allows the form of the bridge’s architecture and structure to speak for itself, creating a sense of place, while responding to surrounding environmental context and in special social and cultural thematic events, such as holidays, city-based sporting events and other cultural celebrations with programmable colored LED lighting washing the bridge in different theme colored hue. The “ORLANDO” sign that stretches across the base of the bridge and SR 50 is envisioned to be cut out of the horizontal beam and shadowed box with a white interior base color, which is illuminated from the interior by LEDs. Again, during special events and occasions these LED lights can be programmed in multiple ways for thematic events like Orlando Magic and Orlando City Soccer Club game nights, the Fourth of July, Breast Cancer Awareness, etc.

The threshold nodes of the trail heads are appropriate locations for special architectural detailing and way-finding elements that provide a sense of place, origin and transition. These areas will incorporate human-scaled architectural pylons similar in design to the iconic I-4 Ultimate precast concrete pylons with similar architectural LED thematic lighting systems. These areas will also be natural places to provide Orlando Urban Trail map signage, heritage signs, and directional signage to aide in user way-finding. They will serve as locations for rest, reprieve and taking in the unique urban sights associated with these vantage points along Orlando Urban Trail.

Our Crime Prevention Through Environmental Design (CPTED) certified design professionals have a proven track record related to providing safe, secure, unobtrusive and economic solutions to our public trails, bridges and park projects. Fear of criminal victimization would threaten the ultimate success for this project – an essential component to the City of Orlando’s desire to being a bicycle, alternative transportation and recreational friendly City. Our design will incorporate strategic elements of surveillance, access control, public territorial

reinforcement and maintenance control to limit conditions that would give rise to unwanted or illegitimate activities associated with criminal behavior. Our proposal incorporates integrated LED lighting systems to illuminate the walkway, as well as provide illumination for facial recognition, a key component to trail CPTED principals. Furthermore, the pedestrian safety screening along the bridge sections will incorporate LED strips along the bridge length to provide additional illumination for both safety and part architectural expression and show.

1-9

Page 13: City of orlando db colonial ped overpass   technical

G&R | Project Approach

Our team’s experience has proven the importance of providing modular, prefabricated and maintenance orientated bridge sub-components, such as guardrails, railing and pedestrian safety fencing. Not only do they prove economical to install, but they are easy to maintain and refurbish providing significant savings in operational maintenance cost. Additionally, our experience has confirmed the substantive value in providing dedicated integrated bridge subsystem service, such as dedicated electrical and lighting control cabinets, in-facilities that are secure and visually isolated from public view, providing for increased ease of inspection, service and repair, as well as enhancing the visual aesthetic and appeal of the finished project. Likewise, integrated or shielded electrical and drainage systems infrastructure, in established right-of-ways, concealed raceways and conduit that are incorporated as part of the overall bridge design provide direct benefits to in-service operations and public perception for this city icon project, where detailing such as this matters.

Public Involvement ProgramPublic Involvement and Stakeholder OutreachWhile the practice of involving the public and other interested groups on a project is nothing new, the level of stakeholder influence and engagement required on complex projects being completed in an urban situation like this has never been higher. Accordingly, effective and timely stakeholder and public involvement are more important than ever to the successful completion of this project.

Advisory Boards and Internal StakeholdersWe will ensure the project goes smoothly within the City and its processes and approvals because we understand the process and the internal stakeholders. This will result in a project with no surprises. The internal City process involves providing the City Project Management team with an up-to-date fact sheet and easily understood schedule that City project management staff can have easily available should a last second call or question come from a Commissioner. We are also there to assist with briefings and other internal meetings with other departments as necessary in order to support the City’s Project Manager. We have team members with established relationships throughout the City. Our schedule will be proactive and ensure that we meet the requirements of the following:

■ City Appearance Review Board (ARB) – We are aware that the ARB Coordinator, Doug Metzger, has been involved in the development of the urban design of the project, and we will work with him to provide what is needed to engage and receive timely approvals of the ARB.

■ Historic Preservation Board (HPB) – Our team has worked with the City’s Historic Preservation Officer, Richard Forbes. Working through the City Project Manager, we will make sure Richard has information early so he can make any determinations that could be necessary.

■ Downtown Development Board (DDB)/Community Redevelopment Agency (CRA) Board– Our team knows the DDB/CRA Staff and Advisory Board members can be deeply engaged in the process and key projects such as this one. We have extensive experience with the staff and the Advisory Board and will ensure they are informed regarding the project design and schedule. The City Project Manager and Kelly Moody with DDB will likely be the most involved in working with these groups, and we have a history of working with both. We also know the importance of working with Bob Fish who leads the Downtown Clean Team to keep him in the loop so the maintenance and upkeep will be smooth.

1-10

Page 14: City of orlando db colonial ped overpass   technical

G&R | Project Approach

■ City Bicycle and Pedestrian Advisory Committee – This City committee will be deeply interested in the direction and progress of this project. We will work to make sure the Project Manager and Ian Sikonia with Transportation Planning can keep this group informed early with clear materials and engaging presentations.

■ Streets & Parks Division Maintenance Staff – Upfront work and coordination with the City’s Streets and Parks Divisions will help guarantee the project has a smooth transition from construction into maintenance. This will be key to minimize long-term costs and maintain the image of The City Beautiful.

Public Involvement and StakeholdersWhile the footprint of the project may not be large, the public involvement and stakeholder interaction that needs to be completed must be planned, thorough and comprehensive. This outreach will keep the project on track. These stakeholders are also enduring the long I-4 Ultimate Construction. We will coordinate the outreach timing as much as possible with the I-4 Ultimate to be sensitive to the stakeholders’ construction fatigue. The approaches to outreach can be public presentations, press releases, group meetings and one-on-one interactions. We have extensive experience with social media, blogs, and interactive tools that the City has used such as mySidewalk (formerly Mindmixer). We have worked with the Public Information Team from the Mayor’s Office and with City staff from the Office of Communications and Neighborhood Relations. We know they are a great resource to help successfully complete this project in a smooth and efficient way for the City. Some, but not necessarily all of the stakeholders that we will need to engage include:

■ Bicycle Community and Bike/Walk Central Florida – The entire bike community will be interested in the project and can be kept informed through reaching out through the City Bike Committee along with local bicycle shops and Bike/Walk Central Florida. Bike/Walk’s newsletter reaches a wide audience and can help get information out early.

■ Downtown Condo Association – This group operates similarly to a homeowner’s association in Downtown Orlando. We will keep the overall group informed along with the individual associations nearest the project such as the China Glass Warehouse owners.

■ China Glass Loft Condominium Owners and/or Residents – The China Glass project was one of the early historic renovation residential projects completed in the City. We will work with these residents and owners as the construction will be just on the other side of the rail line from their residences. Many will understand the benefits and purpose of the overall project, but we will need to keep them informed and engaged in order to keep things moving smoothly.

■ Camden Orange Court Apartments – Residents, Property Owner’s and Property Management – The Camden Orange Project dedicated and constructed a tract intended to be Gertrude’s Walk. Many residents and the owner will be interested and engaged in a project that is occurring immediately adjacent but not tying into or using the original section. The upfront meetings will help make sure things go smoothly.

■ SteelHouse Residents, Property Owner and Property Management – The SteelHouse Project has been tied to the project from the beginning with the initial trail bridge easement dedication that occurred at the time the property received abandonment of right-of-way in the area. Even with this upfront knowledge, we will still need to remind and work with these three different constituencies related to the property. We know each has a different perspective, but keeping all of them on the same page with this project, the I-4 related work (including changes to SR 50) and the additional quiet zone rail crossing work will be key. Coordinating construction activities along the north property line will also be important as we work with individual residents.

1-11

Page 15: City of orlando db colonial ped overpass   technical

G&R | Project Approach

■ 790 North Orange Owners and Tenants – Engaging the property owner and the tenants immediately north of the SteelHouse will be important as the project will connect back into North Orange in this area. This property also has construction fatigue from all the recent projects that have been under construction.

Coordination with I-4 Ultimate/Project ScheduleAs previously indicated above, we have begun coordination with the I-4 project management team, working through Loreen Bobo as instructed. This coordination effort will continue throughout the project phase to ensure the projects will not impact each other. Our schedule of events was developed based on the I-4 construction activities as provided in the schedule dated February 16, 2016. The Garland Avenue Ramp C over State Road 50 should be ready for traffic by April 2017, thereby freeing up the pond area and existing Garland Avenue

for construction of the bridge scheduled to begin in June 2017. The remaining construction activities outside the pond area will occur independent of the I-4 construction.

Coordination with FDOT LAPG&R/VHB are thoroughly familiar with the FDOT LAP program, both design requirements and construction reporting. In addition, we understand this project will be completed in compliance with FDOT specifications as if it were a FDOT project. Our experience with FDOT LAP includes the recent Design-Build project, Semoran Boulevard Streetscape improvements for the City of Orlando as well as two ongoing trail/pedestrian bridge LAP projects for the City of Titusville and Volusia County, both within District 5.

UtilitiesOnce we receive the NTP for this project, we will initiate utility coordination efforts for the known impacts, namely the TECO gas line and the five utility poles adjacent to the SteelHouse Apartments. We anticipate advancing the utility work prior to commencing construction so that once construction begins, the utility impacts will have already been resolved.

We will also work closely with utility companies to identify facilities within the area of the directional bore that will be required for the communication conduit associated with the video camera and electrical leads.

GeotechnicalThe subsurface conditions along this trail alignment are predominantly loose to medium dense fine sands to fine sands with silt in the top 30 to 40 feet. A very loose silty to clayey fine sand layer was then encountered from 40 to 60 feet. This very loose layer was underlain by medium dense clayey fine sand and firm to very stiff clay to a depth of 95 feet. At approximately 95 feet, a very dense silty fine sand to stiff to hard clay bearing layer was encountered. Seasonal high groundwater tables are estimated to be greater than 7 feet below ground surface and are not anticipated to adversely impact trail design and construction. Substructure environmental classification is anticipated to be moderately aggressive for concrete and steel substructure design.

1-12

Page 16: City of orlando db colonial ped overpass   technical

G&R | Project Approach

For the main spans of the pedestrian bridge, 18-inch PPC piles driven into the bearing layer to about 100 feet will achieve Nominal Bearing Resistances (NBR) of 225 tons each. Pile minimum tip elevations will be provided to ensure the pile tips are below the very loose soil layer encountered in the borings. Of particular concern for the selection of foundations is the TCE contamination plume near this location. The contaminant plume is present above the clayey sand layer at a depth of about 45 feet. GEC aided FDOT District 5 in a detailed pilot study to determine the effect of driving deep piles through this plume. The results of the pilot study indicated that driven piles did not cause a breach in the confining layer below the plume and allow the TCE contamination to migrate downward. Therefore, driven PPC piles are suitable for constructability at this site.

Additional concerns with PPC piles are noise and vibration in the downtown urban setting with existing structures nearby. Based on the soils at this site, we have estimated structures located more than 150 feet from pile driving operations will not incur any structural damage due to pile driving vibrations. As a precaution, pre-construction surveys and vibration monitoring will be conducted during pile driving operations.

For pedestrian ramp segments approaching the main spans, the existing soils are suitable for supporting shallow foundations with allowable bearing capacities up to 4,000-5,000 psf. GEC and VHB have analyzed the various approach ramp footing loads and determined settlements to be within the acceptable range.

Due to the presence of the very loose silty to clayey fine sand from 40 to 60 feet deep, the width and length of the shallow foundations will be designed so the stress influence from the heavily loaded shallow foundations does not extend down into the very loose layer thereby causing excessive settlements. The footings provided will provide adequate bearing capacity with settlements within the tolerable range of less than one-inch.

The potentiometric elevation of the Floridian Aquifer is documented to be approximately +50 feet NGVD. Ground surface elevations are approximately +95 feet NGVD; therefore, artesian conditions are not expected. Additionally, sinkhole potential is not considered to be a high risk in this area. Shallow foundation-supported structures are very typical in this area and the ramp approach structure loads are relatively low so that shallow footings will provide considerable construction cost savings as compared to driven pile foundations for this structure type.

Contamination ApproachThis section of the proposed Orlando Urban Trail is in the vicinity of several documented areas of contamination impact. The contamination sites are as follows:

1. Railroad line - The SunRail railroad corridor is located immediately adjacent to the proposed alignment. Historical rail spurs are likely to have been located within the alignments. Historical rail lines have several common chemical constituents of concerns as follows:

■ Arsenic: The most commonly used arsenic-containing products were herbicides, pesticides, insecticides, and wood-treating agents such as chromated copper arsenate.

■ Creosote: Creosote is used to coat railroad ties.

1-13

Page 17: City of orlando db colonial ped overpass   technical

G&R | Project Approach

■ Polynuclear aromatic hydrocarbons: Polynuclear aromatic hydrocarbons are a coal tar and creosote by-product. Coal tar is more commonly associated with rail yards.

■ Other inorganic constituents used in herbicides.

Due to its residual nature, arsenic is the most commonly occurring chemical constituent related to railroad beds because of liberal applications of herbicides used to keep the railroad free of vegetation. The creosote and polynuclear aromatic hydrocarbons are commonly found associated with railroad ties and rail yards.

2. Former Orlando Steam Laundry – This facility was historically located on the north side of Concord Street, east of the SunRail line. A solvent contamination plume is documented extending towards the northwest from the facility, crossing the rail line between Concord Street and SR 50. The plume is located at shallow and intermediate depths (roughly 10 feet to 50 feet below ground surface). This contamination plume extends approximately 25 to 30 feet west of the rail line.

3. Orlando Sentinel Plume B – This contamination plume extends beneath West Colonial Drive and the SunRail railroad intersection on a northwest/southeast axis. The contaminant levels range from 2.5 micrograms per liter (ug/l) to 1,300 ug/l in the vicinity of the intersection. The contamination was detected in monitoring wells ranging from approximately 38 to 47 feet below the ground surface.

4. Orlando Sentinel Plume A – This contamination plume extends beneath the West Colonial Drive and North Orange Avenue intersection, continuing on to I-4, on a northwest/southeast axis. The contaminant levels range from not detectable to 140 ug/l in the vicinity of the proposed alignment. The contamination was detected in monitoring wells ranging from approximately 40 to 45 feet below the ground surface.

5. Union 76 Station – This facility is also called the SteelHouse Brownfield Site and is located on the north side of West Colonial Drive, east of the SunRail rail line. This facility has petroleum groundwater impacts, at depths of less than 20 feet below the ground surface that are located in the proximity of the East Colonial Drive and North Orange Avenue intersection.

These contamination sites appear to have very limited potential to impact the proposed Orlando Urban Trail based on the following:

■ The trail construction will be limited to surficial impacts and is not expected to extend more than 2 to 3 feet in depth.

■ The groundwater is located approximately 10 feet below the ground surface in the area of the trail; therefore no construction dewatering activities are proposed.

■ Deep driven PPC concrete piles are proposed to be used to support a pedestrian bridge that will span the West Colonial Drive and SunRail track intersection. GEC performed a February 22, 2008 Pile Foundation Study Report for the I-4 project. The report found that driven piles are not likely to create preferential pathways for the contaminants in the surficial aquifer to migrate into deeper aquifers.

GEC will review all contamination information available to guide the design and construction of the trail and structure foundations. Plan notes will be developed to inform the contractor of the contamination horizontal and vertical limits so that it can be avoided during design and construction and to provide guidance to the contractor in the event contamination is inadvertently encountered during construction.

1-14

Page 18: City of orlando db colonial ped overpass   technical

G&R | Project Approach

Overall, we are consciously sensitive to the fact that the pedestrian bridge over the SR 50 project will serve not only as a practical connector linking communities and the downtown business district and surrounding neighborhoods, but will stand as a very visual and tangible symbol of the City’s values and dedication to providing, safe, economic and livable environments on a civic scale furthering the goals of “The City Beautiful.” We look forward to providing a complete turn-key Design-Build project that will exceed this City’s expectations.

1-15

Page 19: City of orlando db colonial ped overpass   technical

Section 2: Plans and Technical Special Provisions

Plans and Technical Special ProvisionsSection 2

Page 20: City of orlando db colonial ped overpass   technical

City of Orlando Design Build Services for the Colonial Pedestrian Overpass (SR50) - Technical Proposal Project No. TRE0003_G

Plans and Technical Special ProvisionsPlans and Technical Special Provisions have been submitted under separate cover.

2

2-1

Page 21: City of orlando db colonial ped overpass   technical

www.gibbsandregister.com


Recommended